Professional Documents
Culture Documents
WRD720S-2022 - Task 01 - EE Rev1
WRD720S-2022 - Task 01 - EE Rev1
WRD720S-2022 - Task 01 - EE Rev1
1.
A project requires loan finance of N$ 5000 now and N$ 3000 in 3 years’ time.
• Option 1:
Loan repayment: Over 5 years In five (5) equal annual instalments, if the interest rate is 5%
p.a.
• Option 2:
Capitalization of the loan present value (equal to the loan repayment calculated for
Option 1), as a single payment in 5 years’ time with interest being 7% p.a.
[28]
2.
A lump-sum deposit of $7000 is made now into an investment account that pays 5% pa. interest.
2.1 Draw a cash flow diagram indicating the investment and withdrawals
2.2 Determine the final account balance using calculation by hand aided with interest factors.
[10]
3.
An energy utility company requires that for each of their power generators annual investments be
placed into a capital reserve fund to ensure funds being available for unexpected major
refurbishment of equipment.
For this purpose, N$ 5000 was deposited annually for a period of 15 years which made N$ 100000
available now for refurbishments.
1
What rate of return did this practice provide to the company?
(Solve both by hand calculation and MS Excel Spreadsheet financial function application.)
[14]
4.
The cost of a pump set for a sewer pump station is expected to amount to N$ 80000 and to have a
life of 5 years. Maintenance costs are estimated to be 2% of the initial cost and the latter will
increase linearly at 10% annually.
4.1 Draw a cash-flow timeline for each system option, indicating all cost components.
(a) total present cost of the pump set over its life of 5 years?
(b) from the total present cost in 4.2(a), determine the EUAC over the life of the pump set.
[12]
5.
The supply from a treatment plant is required to meet growth in water demand for a particular
region. The existing facility has reached the end of its economic operational life and design
Three (3) different locations for constructing the new facility has been identified and related cost
and benefit data are given below.
5.2 Rank the economically feasible construction locations for the new facility
from least to most beneficial, based on economics alone using an
incremental EUAC benefit-cost analysis. (4)
Do all calculations in N$ millions (in accordance with the monetary data given).
[10]
2
6.
A choice must be made between two operational systems for a new sewerage pump station.
System 1:
Initial installation cost = N$ 1.8 Million.
Retrofit of installation every 15 years = N$ 1.2 Million
Estimated energy costs per year = N$ 50000.
Estimated operation & maintenance cost per year = N$ 36000.
Estimated salvage value at end of life = N$ 20000.
System 2:
Initial installation cost = N$ 2.0 Million.
Refurbishment every 15 years = N$ 450000.
Estimated energy costs per year = N$ 25000.
Estimated annual O & M cost = N$ 32000.
Estimated salvage value at end of life = N$ 35000.
6.1 Draw a cash-flow timeline for each system option, indicating all cost components.
6.2 Do a comparative economic analysis of the system options assuming a rate of return of
10% p.a. and select the best system based on economics alone.
Do calculations by hand aided by interest factors using a EUACF approach . [26]