Document No : GF-GGTU-M-VD-13008
Revision : 0
Page : 1 of 7
STORAGE PROCEDURE
FOR 15T OH CRANE (ITEM NO: 54-CR-24700)
GF-GGTU-M-VD-13008
JKH 2015-05-15
REVISION HISTORY
TABLE OF CONTENT
1.0 Packing 3
1.0 Packing:
- Loose parts shall be packed in suitable wooden crates / boxes as may be convenient for
Handling. (e.g.: Power line system, Main switch, Rising cable)
- Runway rail shall be bundled with steel strap at adequate interval of the length. Standard Rail
Length is 6m.
- The crane shall be dispatched in fully assembled condition or partially dismantled condition as
required based on transport constraint.
If the equipment is not installed immediately upon receipt, it must be stored properly to prevent
corrosion and deterioration.
3.0 Storage instruction for Packed goods (Power line system & accessories):
Packed goods can normally be kept in a closed warehouse for up to four years provided that
temperature is no lower than -20°C or higher than +60°C and humidity level do not exceed 70%.
If, for any reason, humidity levels were to exceed +60% or storage were to continue for a longer
period it would be necessary to carry out some extra preliminary operations before setting the
machine to work (see Page-4). No other packages must be placed on top of the crates.
The following preservation instructions describe actions which when followed ensure that the
Protection of the product against external influences and effects must be ensured, Storage in a dry,
REQUIREMENT GROUP:
# ACTIONS A B C D
06 Close open threaded holes with suitable screw (coated with lubricant) X X
Fill cavities of control, hoist, travel motors and other aggregates with
08 X X
sufficient desiccant
The preservation measures must be checked periodically and added to or corrected as necessary.
SOURCES:
The following actions are to be carried out before setting the equipment to operation which have
STRUCTURES:
a) Remove protection from threaded holes, e.g. end carriages to crane beams fixings, if
necessary by taping.
b) Remove protection, lubricant, paint or any corrosion from bright matching surfaces,
c) Repair any damage to crane beam flanges (single girder cranes) or trolley rail top (double girder
d) Using correct paint, touch up parts that have been affected by handling & improper/longer storage.
MECHANISM:
a) Check there are no leaks of lubricant from the reducers and replaced any damaged seals.
c) Check all the elements which hold the mechanisms to the structures are tight
d) Remove any traces of corrosion from rotating or sliding pins such as limit switches, control
pins, saddles for activating micro-switches, control chains for various components.
e) Check any carrion of the wires which make up the rope. Clean the metal ropes, the pulley
grooves and the lifting drums. Lubricate with specified type of lubricant.
ELECTRICAL PARTS:
b) Motors: remove all condensation from the inside sucking air through the open terminal box or
after having taken off the end cover. Dry blasts or air.
c) Disk brakes: open the brake cover and remove all disks. Dry using air, check the condition
and efficiency of the springs. Put the disks back after having carefully cleaned the braking
d) Limit switches: limit switches much be checked carefully to establish their good running order
both from the mechanical and electrical point of view. Particularly lubricate the moving joints
and pins.
e) Control switchgear: all casing, remove condensation, dry the contacts, of the remote controls
switches. Check the condition of any electronic cards. Spray all components with suitable
cleaner/degreaser. Apply Vaseline to the closing sections and to threaded covers of all the
f) Carry out insulation test at 2000V after having insulated any bridge rectifiers/electronic cards
g) Check all electric lines and loops slide easily and if necessary, lubricate cable trolley wheels
i) Thorough check should be carried out on the push-button pendant: remove condensation,
check that the contacts are working properly, and that the terminals are well-secured.
For explosion-proof version check the pins turn perfectly and the small control pistons slide