Professional Documents
Culture Documents
Settings Recommendations R6
Settings Recommendations R6
Settings Recommendations R6
Recommendations
GE Multilin UR
series relays
May 2006
GE Multilin Setting Recommendations: UR series
CONTENTS
A. INTRODUCTION
B. DISTANCE PROTECTION
B.1. OVERVIEW
B.2. DISTANCE ZONES SETINGS RECOMMENDATIONS
B.3. POWER SWING BLOCKING SETINGS RECOMMENADTIONS
B.4. LINE PICKUP SETINGS RECOMMENDATIONS
B.5. DISTANCE PROTECTION IN UNGROUNDED OR PETERSEN COIL
GROUNDED SYSTEMS
C. PHASE-COMPARISON PROTECTION
C.1. OVERVIEW
C.2. GENERAL PHASE-COMPARISON SETINGS RECOMMENADTIONS
C.3. TAPPED LINE APPLICATIONS
C.4. SENSITIVITY AND SECURITY ADDITONAL MEANS
D. ZERO-SEQUENCE OVERCURRENT PROTECTION
D.1. DIRECTIONAL ELEMENTS SETTINGS RECOMMENADTIONS
D.2. OVERCURRENT ELEMENTS SETTINGS RECOMMENADTIONS
E. PHASE OVERCURRENT PROTECTION
E.1. PHASE DIRECTIONAL OC SETTINGS RECOMMENADTIONS
E.2. PHASE OVERCURRENT SETINGS RECOMMENADTIONS
F. SINGLE-POLE TRIPPING APPLICATIONS RECOMMENADTIONS
F.1. OPEN POLE
F.2. TRIP OUTPUT
G. AUTORECLOSURE AND SYNCHROCHECK
G.1.BREAKERS FUNCTION
G.2.AUTORECLOSURE
G.3.SYNCHROCHECK
G.4.COORDINATION BETWEEN SYNCHROCHECK AND
AUTORECLOSURE
H. BREAKER FAILURE
Ilia Voloh
05/05/2006 Page 2 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I. TRANSFORMER DIFFERENTIAL
I.1. OVERVIEW
I.2. CTs AND SOURCES CONFIGURATION
I.3. TRANSFORMER GENERAL SETTING AND WINDING
I.4. TRANSFORMER DIFFERENTIAL
I.5. TRANSFORMER RESTRICTED GROUND FAULT
I.6. REACTOR PROTECTION
J. BUSBAR DIFFERENTIAL
J.1. OVERVIEW
J.2. DIFFERENTIAL SETTINGS
J.3. B90 BREAKER FAILURE
Ilia Voloh
05/05/2006 Page 3 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
A. INTRODUCTION
UR series relays feature common platform hardware and firmware functionality, same
PC program is used to interface all UR relays. In the design of UR relays, the term
“element” is used to describe a feature that is based around a comparator. Elements are
arranged into two classes, GROUPED and CONTROL. Each element classed as a
GROUPED element is provided with six alternate sets of settings, in setting groups
numbered 1 through 6. The setting group that is active at a given time defines the
performance of a GROUPED element. The performance of a CONTROL element is
independent of the selected active setting group. Some settings for current and voltage
elements are specified in per-unit (pu) calculated quantities. UR relays Sources concept
allows for processing 2 or more CTs inputs individually plus summing up currents
internally which increase security for some applications.
Important observation is that all UR platform elements are exactly identical with
respect to settings and functionality. This means that IOC, distance or undervoltage
elements are exactly the same on D60, G60 or L60 relays. Therefore, all
recommendations below are applicable to the same elements throughout all UR series
relays.
In spite of D60 is designed primarily for EHV applications with mostly single-pole
tripping, it can be applied on any voltage level as either primary or backup protection.
For example, following distance setting recommendations are fully applicable to
applications of D60, D30, L60, L90 or G60, as these relays are using same protection
distance algorithms. The difference is number of zones and specific single-pole tripping
elements, which are found in D60 and L60 only .
Another example is transformer (T60/T35) or bus differential (B30/B90). Same
differential functions with same menus and same algorithms are used in above-mentioned
relays; therefore recommendations are fully applicable to all of these relays.
Because of this “universality” of UR series relays, following recommendations are
structured by functionality rather than by the relay type.
Ilia Voloh
05/05/2006 Page 4 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
B. DISTANCE PROTECTION
B.1. OVERVIEW
This document outlines recommendations for settings when GE Multilin UR series relays
are used protecting any voltage level lines or transformer-line blocks. UR series distance
related functions include the following:
A.1. 5-zones Phase and Ground distance elements, with all zones settings
individually configured per zone. Zones can be shaped MHO, QUAD,
directional or non-directional.
A.2. Power Swing Blocking/Out-of-Step Tripping-to prevent distance elements
misoperation during swing conditions.
A.3. Load Enchroachment-to prevent operation of phase distance during heavy load
conditions.
A.4. VT Fuse Fail detector-to prevent distance elements misoperation during VT
secondary circuits problems.
A.5. Line pickup-to provide protection when line is energized onto the fault and
distance elements don’t have memory voltage established to operate on their
own.
A.6. Single-pole tripping package, which includes Phase Selector, Open Pole and
Trip Output elements-to provide correct operation.
The phase and ground mho distance function uses a dynamic 100% memory-polarized
mho characteristic with additional reactance, directional, and overcurrent supervising
characteristics. The phase quadrilateral distance function is comprised of a reactance
characteristic, right and left blinders, and 100% memory-polarized directional and current
supervising characteristics. When set to “Non-directional”, the mho function becomes an
offset mho with the reverse reach controlled independently from the forward reach, and
all the directional characteristics removed. When set to “Non-directional”, the
quadrilateral function applies a reactance line in the reverse direction instead of the
directional comparators. Refer to D60 Chapter 8 for additional information and theory
behind UR distance functionality. Each zone is configured individually through its own
setting menu. All of the settings can be independently modified for each of the zones
except 3 common settings: a) Source; b) memory duration; c) force self-polarization.
Note: when UR distance function is applied, local utility practice, standards and
settings recommendations have to be considered first as guidance for settings
calculations. This document gives some supplementary advises on specific for UR
settings.
Ilia Voloh
05/05/2006 Page 5 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
On the other hand, the MEMORY DURATION cannot be too long as the power
system may experience power swing conditions rotating the voltage and current phasors
slowly while the memory voltage is static, as frozen at the beginning of the fault.
Keeping the memory in effect for too long may eventually lead to incorrect operation of
the distance functions.
B.2.4. REACH
Accuracy of UR distance elements reach is guaranteed within 5% for any current.
Additional sources of inaccuracy are CT and VT errors, primary system parameters errors
resulting in settings errors etc. Such errors in this document are assumed to be not more
than 5%. However, based on the local utility practice, additional security factors can be
applied.
Ilia Voloh
05/05/2006 Page 6 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Z2 has to reliably cover remaining 10-15% of the line, which Z1 doesn’t cover and
provide backup protection for Z1 of the adjacent line close-by faults. Generally,
Z2 reach for Phase and Ground Distance is generally set to:
1.25 • Z1L ≤ Z 2 ≤ Z1ADJ • 0.5 + Z1L (B-3)
of the protected line (Z1L) and adjacent lines (Z1ADJ) positive sequence
impedances.
However, possible “infeed” or “outfeed” have to be considered. Picture B-1
below denotes that, when setting up Z2 for protection 1, problem arises when line
BC is shorter than line BD. Setting Z2 of protection #1 to cover 50% of the line
BC impedance will cover much smaller portion of the line BD. From other hand,
Z2 underreaching is possible due to fault contribution from line BC.
B
C
A IBC
3 4
Z AB
1 2 n ZBD D
IAB F1
5 6
I AB+IBC
Figure B-1: Distance reach with infeed at remote bus
Ilia Voloh
05/05/2006 Page 7 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
IC
C
Figure B-2: Distance reach with a tapped transformer
Apparent impedance seen by protection #1 during fault F2 at the remote bus
would be:
I
Z APPAR = n • Z AB + (1 + C ) • (1 − n ) • Z AB (B-5)
IA
B.2.4.2. Z3 REACH
If a remote backup philosophy is followed, then the reach of both phase and ground
elements must be set to account for any infeed at the remote bus, plus the impedance of
the longest line which terminates on this remote bus. The time delay must coordinate
Ilia Voloh
05/05/2006 Page 8 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
with other time-delayed protections on any remote line. Circuit loading limitations
created by a long zone reach may be overcome by using lens or quadrilateral
characteristics and/or a load encroachment, supervising characteristic. Consideration
should also be given to a situation where the load impedance may enter into the relay
characteristic for a time longer than the chosen time delay, which could occur transiently
during a system power swing. For this reason the Power Swing Blocking function should
be used.
Generally, Z3 should backup adjacent line protection if adjacent line protection or
breaker fails to clear the fault and should coordinate with Z2 of the adjacent line;
Z 3 ≤ Z1L + 0.9 • K I • Z ADJ
2 (B-8)
Additionally, per NERC requirement, the zone 3, if used, should not operate at or below
150 percent of the emergency ampere rating of a line, assuming a 0.85 per unit voltage
and a line phase angle of 30 degrees;
0.85• VL
Z min
LOAD = (B-9)
3 •1.5• I max
L
where VL is the line nominal voltage and I max
L is the line maximum current.
If a MHO characteristic is used, then minimum safe Z3 reach is determined as;
min Z min
LOAD
Z3 = (B-10)
cos(RCA L1 − 30°)
If this is not satisfied, then Load Encroachment has to be used or lenticular characteristics
as described below.
Ilia Voloh
05/05/2006 Page 9 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
This setting specifies the ratio and angle between the zero-sequence and positive-
sequence impedance required for zero-sequence compensation of the ground distance
elements. Settings have to be calculated at the reach point, individually per zone.
Z0L ⎛ Z0L ⎞
Z0 / Z1 _ MAG = and Z0 / Z1 _ ANG = arg⎜ ⎟ (B-11)
Z1L ⎜ Z1L ⎟
⎝ ⎠
For example, if Z1L = 10Ω • e j85° and Z0L = 27Ω • e j75° then:
27Ω • e j75° ⎛ 27Ω • e j75° ⎞
Z0 / Z1 _ MAG = = 2.7 , Z0 / Z1 _ ANG = arg⎜ ⎟ = −10°
10Ω • e j85° ⎜ j85° ⎟
⎝ 10Ω • e ⎠
Ilia Voloh
05/05/2006 Page 10 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
A B C A B C
1b 1b
1c 1c
2b 2b
2c 2c
3b
D60-1 D60-2 3b
3c 3c
4b 4b
4c 4c
L1 L2
Figure B-3: CT connections for parallel line zero-sequence mutual coupling compensation
Eventually setting have to be calculated as follows;
Z0M ⎛ Z0M ⎞
Z0M / Z1 _ MAG = and Z0M / Z1 _ ANG = arg⎜ ⎟ (B-12)
Z1L ⎜ Z1L ⎟
⎝ ⎠
Figure B-4: Sources assignment for parallel line zero-sequence mutual coupling
compensation
Ilia Voloh
05/05/2006 Page 11 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
better), and the zero-sequence polarizing should be selected. Otherwise, the negative-
sequence is a better polarizing signal.
IF
IF
Ilia Voloh
05/05/2006 Page 12 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 13 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
the quadrilateral characteristic and should be set giving consideration to the maximum
load current and required resistive coverage. Following conditions apply:
Integrity of the QUAD characteristics;
R RGT _ BLD ≤ 4.5 • Z R (B-17)
Desired resistive fault coverage;
R RGT _ BLD ≥ 1.25 • [R F + Z L • cos(ϕ L )] (B-18)
where RF and ZL are secondary fault arc resistance and line impedance
respectively
Immunity during heavy load conditions per equation B-15 above-set above
value per this formula.
Ilia Voloh
05/05/2006 Page 14 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
VT = 13.8kV/120V VT = 315kV/120V
CT = 8000:5 CT = 300:5
0.688Ω∠85°
2.57Ω∠88.4°
For relay applied at the point H, transformer impedance and group have to be taken
into account. As both CT and VT are located at the opposite of reach point transformer
side, then settings have to be set as:
XFMR VOL CONNECTION = “Dy11”
XFMR CUR CONNECTION = “Dy11”
Consequently, at point H (13.8kV side) secondary line impedance and transformer
impedance will be as follows:
Transformer primary impedance at 13.8kV side is;
Z Tpri _ H
=
E% VnH
• =
( )2
10 (13.8)2
• = 0.127 • e j90°Ω (B-20)
100 MVA 100 150
Total secondary impedance to the reach point at relay point H will be;
2 2
CTR ⎡ VnH ⎤ CTR 1600 ⎡13.8 ⎤
Zsec_ H
= Z pri
• •⎢ ⎥ + ZTpri _ H • = 30.11 • e j85°• •⎢ +
R L VTR ⎢⎣ VnX ⎥⎦ VTR 115 ⎣ 315 ⎥⎦
1600
+ 0.127 • e j90° • = 2.569 • e j88.4°Ω (B-21)
115
Ilia Voloh
05/05/2006 Page 15 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
The negative value means that an underreaching zone cannot be used as the circuit
between the potential source of the relay and an external fault for which the relay
must not pick-up, is overcompensated, i.e. capacitive.
Use adaptive reach control feature, the DIST VOLT LEVEL setting shall be set
accordingly per zone.
Setting is entered in per unit of the phase VT bank configured under the
DISTANCE SOURCE. Effectively, this setting facilitates dynamic current-based
reach reduction. In non-directional applications (DIST DIR SETTING set to “Non-
directional”), this setting applies only to the forward reach of the non-directional
zone. This setting is a sum of the overvoltage protection levels for all the series
capacitors located between the relay potential source and the far-end busbar, or
location for which the zone must not overreach. The setting is entered in pu of the
phase VT nominal voltage, Line-to-Ground (RMS, not peak value). If a minimum
fault current level (phase current) is causing a voltage drop across a given capacitor
that prompts its air gap to flash over or its MOV to carry practically all the current,
then the series capacitor shall be excluded from the calculations (the capacitor is
immediately by-passed by its overvoltage protection system and does not cause any
overreach problems). For example, for Sending end of the 500kV system shown on
the diagram above, assuming that voltage protective level for 2 capacitors of 3Ω
and 4Ω (line VT used) are V3Ω =122kV and V4Ω=163kV RMS bus, setting should
calculated as;
V + V4Ω 122 + 163
VPU = 3Ω = = 0.99pu (B-22)
VnLG 500 3
Refer to D60 manual for more information on the theory and operation on series
compensated lines.
The both phase and ground distance elements are supervised by the magnitude of the
line-to-line current for phase distance (fault loop current used for the distance
calculations) or 3I0 current for ground distance. For convenience, phase distance is
accommodated by the pickup (i.e., before being used, the entered value of the threshold
setting is multiplied by √3. If the minimum fault current level is sufficient, the current
Ilia Voloh
05/05/2006 Page 16 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
supervision pickup should be set above maximum full load current preventing
maloperation under VT fuse fail conditions. It has to be noted that phase distance zone 1
is mostly affected by VT fuse fail conditions as time delayed phase distance zones are
blocked in time, while ground distance is supervised by 3I0 which normally is small and
caused by unbalance in phase currents. From another hand it has to be sensitive enough
for the end of the zone faults under minimum system conditions taking into account
current distribution for all system configurations.
0.8 • I min
F
ISUPV ≤ (pu) (B-23)
CTR
where I min
F is the minimum phase-to-phase fault for phase distance and 3I0 current for
ground for the end of the zone fault.
When fault current doesn’t allow setting phase distance above maximum load current,
to eliminate racing between VTFF and phase distance Z1, supervision by 50DD is
recommended accordingly GE Multilin application note. In any case setting current
supervision too low for both phase and ground distance (below 0.2pu) is not
recommended.
The Power Swing Detect element provides both power swing blocking and out-of-step
tripping functions. The element measures the positive-sequence apparent impedance and
traces its locus with respect to either two or three user-selectable operating characteristic
boundaries. Upon detecting appropriate timing relations, the blocking and/or tripping
indication is given through FlexLogic™ operands. The element incorporates an adaptive
disturbance detector. This function does not trigger on power swings, but is capable of
detecting faster disturbances – faults in particular – that may occur during power swings.
Operation of this dedicated disturbance detector is signaled via the POWER SWING
50DD operand.
The Power Swing Detect element asserts two outputs intended for blocking selected
protection elements on power swings: POWER SWING BLOCK is a traditional signal
that is safely asserted for the entire duration of the power swing, and POWER SWING
UN/BLOCK is established in the same way, but resets when an extra disturbance is
detected during the power swing. The POWER SWING UN/BLOCK operand may be
used for blocking selected protection elements if the intent is to respond to faults during
power swing conditions. Different protection elements respond differently to power
swings. If tripping is required for faults during power swing conditions, some elements
may be blocked permanently (using the POWER SWING BLOCK operand), and others
may be blocked and dynamically unblocked upon fault detection (using the POWER
SWING UN/BLOCK operand).
Refer to D60 manual for more information on the theory and operation Power Swing
Blocking and Out-of-Step tripping.
Ilia Voloh
05/05/2006 Page 17 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 18 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 19 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Zb Z1, Z0 Zf
~ ~
1
2
3
4
0 R
Ilia Voloh
05/05/2006 Page 20 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Zf * CTR 0 *120
ZSf = = = 6Ω secondary ohms
VTR 1400
As MHO Zone 3 is being blocked by Power Swing Blocking in this example, the Inner
Limit Angle is established by coordination with Zone 3. Goal is to find where swing
locus intersects Zone 3 (point 2), take a safety margin of 25% (point 3) and establish
angle then.
Ilia Voloh
05/05/2006 Page 21 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
6. Average rotor velocity during stable power swing is 2 slip cycles per second (real
number has to be confirmed with system studies) δ=2cyc/sec
Refer to D60 manual for other Power Swing Blocking settings recommendations, related
mostly to Out-of-Step tripping.
The LINE PICKUP element (SWITCH ONTO A FAULT) is typically applied to trip the
line when energizing onto a fault. When a line was de-energized the distance elements
are blocked for a short period of time in order to avoid racing conditions between the
voltage and currents building up from zero to their steady state values. Normally the
LINE PICKUP protects the line during the switch on conditions. Another applications of
this element on the D60 include a HYBRID POTT pilot-aided scheme and positive-
sequence undervoltage function. The element responds to the positive-sequence voltage
in order to detect un over/under voltage condition and to phase currents in order to detect
line end open and excessive current conditions.
The elements interfaces with Zone 2 (zone 2 can operate the LINE PICKUP) as well as
with the TRIP OUTPUT scheme. The trip command from the LINE PICKUP is
automatically accepted as a request for a three-pole trip action.
The element asserts a number of output FlexLogic operands that can be used freely as per
UR convention. Some of them are “pre-wired” to the HYBRID POTT and TRIP
OUTPUT elements.
The line pickup feature uses a combination of undercurrent and undervoltage to identify a
line that has been de-energized (line end open). Three instantaneous overcurrent elements
are used to identify a previously de-energized line that has been closed onto a fault,
which could be due to maintenance grounds that have not been removed. Faults other
than close-in faults can be identified satisfactorily by the distance elements, which
initially will be self or faulted phase polarized and then become memory polarized when
a satisfactory memory signal is available.
Ilia Voloh
05/05/2006 Page 22 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
where I min
F is the minimum SLG fault current for fault on the line when line is energized
from any line terminal.
It’s generally desirable to set pickup above maximum load current. If this is not possible,
then coordination delay described below has to be employed.
Ilia Voloh
05/05/2006 Page 23 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
IB0Σ
I0Σ C0Σ
o
I0Σ I0Σ
90
~ 3I0Σ
(faulted line) (rest of the network,
unfaulted lines)
21 IC0Σ
VA
V0
C0L I0L
V0 VCF VBF
VC VB
a) b) c)
When a phase-to-ground fault does occur, the unfaulted phase-to-ground voltages are
increased essentially by 3 throughout the whole ungrounded system, thus increasing the
probability of the insulators breakdown in the same or geographically different location
belonging to the same ungrounded system. This may trigger cross-country fault, when
one phase-to-ground fault exists on the protected line, while another phase-to-ground
fault occurs in other phase of the adjacent or remote line belonging to the same system.
When such cross-country fault occurs, it’s possible to trip one line only, leaving the
system with one phase-to-ground fault until fault is cleared.
bg
3Ib0
~
~
21 AG
3IA0
Ilia Voloh
05/05/2006 Page 24 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
downstream the relay measuring point but one fault is on the protected line while
another fault is on the outgoing from opposite bus feeder), there is no zero-sequence
current flowing through the relay location, therefore ground distance will not have
chance to operate. However, 2nd fault should be cleared by the protection of the
adjacent line. In the case if sources are present at both ends of the line, during forward
cross-country fault, situation is similar to the radial line ground distance
measurement; there is no zero-sequence current flowing through the relay location
and correct distance measurement is possible to the nearer fault.
If, however, one phase-to-ground fault exists in the forward direction, while another
fault in the different phase exists in the reverse direction, then there is a zero-
sequence current flowing through the relay location. However, magnitude and angle
of the zero-sequence current are dictated by how far are two fault locations from each
other relative to relay measuring point and phases involved. This current can/cannot
be used to compensate ground distance. Figure B-12 below illustrates the complexity
for the correct measurement of the distance to fault for the ground distance. If fault
behind the relay measuring point is assumed in phase A while the fault in the forward
2
direction is assumed in the phase B, then there is a shift by a , a and 1 between
positive-, negative- and zero-sequence networks respectively, where a denotes a
phase shift of 120°. If forward fault occurs in phase C instead of phase B, then the
A A B
(1-m) Z 1S m Z 1S n Z 1L (1-n) Z 1L Z 1S 2
1:a
I1R
E1 E2
A A B
(1-m) Z 2S m Z 2S n Z 2L (1-n) Z 2L Z 2S
1:a
I2R
A A B
(1-m) Z 0S m Z 0S n Z 0L (1-n) Z 0L Z 0S
1:1
I0R
Figure B-12. Sequence networks connections during cross-country fault on the line with
sources at both ends
Ilia Voloh
05/05/2006 Page 25 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
2
shift will be a, a and 1 respectively.
Particularly, depending on the cross-country fault locations and system impedances at
both (or just one in case of radial line) line terminals, there might be 3 different
conditions with regards to zero-sequence current and ground distance elements:
1. No zero-sequence current at all if both fault locations are in the relay’s
forward direction.
2. Zero-sequence current with correct direction, which might be used for
ground distance in case of radial lines as shown in the Figure B-10 above.
3. Zero-sequence current with undermined direction, depending on the both
sources impedances and fault locations in case of cross-country fault on the
transit lines between two sources when one fault in in the forward direction
while another fault in the reverse direction.
Taking into mentioned above, directional elements based on sequence components
cannot be used to achieve required functionality. The proper determination of the
fault location can be achieved with phase directional element only and a proper logic.
When protecting ungrounded/resonant/grounded system, system protection can be
organized in a way that fault in phase B is never sensed and tripped therefore, due to
CTs might not be installed in phase B in all locations (installed in phases A and C
only). In such case throughout the whole system there should be adopted a rule of
how protection operates during cross-country faults.
For example following protection rules can to be adopted for the particular system
and following relay functionality can be achieved:
1. AC or ACG or ABC: trip issued
2. AG-bg: trip issued
3. CG-bg: trip issued
4. AG-cg: trip issued
5. BG-cg or BG-ag: no trip issued
6. CG-ag: no trip issued (fault ag is expected to be cleared by the adjacent line
protection)
Note: upper case letters denotes fault on the protected line, while lower case denotes
fault in the other location of the ungrounded/resonant grounded system as shown in
the Figure B-11 above.
To achieve such functionality, following protection elements are used:
1. Phase and Ground Zone 1 and zone 2 set in the forward direction output
operands of specific loops.
2. Phase and Ground Zone 3 set as overreaching non-directional zone
supervising any distance trips.
3. Phase IOC1 specific phases pickup operands are directionalized with Phase
Directional OC and used to supervise distance trips for certain combinations
of fault phases involved.
For example, protecting a 33kV line with Z1=10Ω∠75° and Z0=30Ω∠65°,
CT=300/5A and VT=33000/110V, following setting can be adopted;
Phase Distance Zone 1: Direction forward, reach at 80%, MHO shape,
Ground Distance Zone 1: Direction forward, reach at 80%, QUAD shape,
Z0/Z1 MAG=3, Right blinder set at 3 times reach, Left blinder at 1.5 times.
Ilia Voloh
05/05/2006 Page 26 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 27 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
GND DIST Z1 OP 1
OR
OR
GND DIST Z2 OP
3
PHASE IOC1 PKP A AND ANY AG (VO2)
AND
2
PH DIR1 BLK A
GND DIST Z1 OP 4
OR
OR
GND DIST Z2 OP
PH DIST Z1 OP 9
OR
OR
PH DIST Z2 OP
PHASE IOC2 OP
Ilia Voloh
05/05/2006 Page 28 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 29 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
VT1
1PH
BF1 BF2
SRC1 SRC3
PHASE
COMPARISON
L60 SRC1 SRC3
Σ
SRC3 SRC4
Synchro- DISTANCEand
check 1 OVERCURRENT
SRC4 SRC4
3PH
VT3
PROTECTED
LINE
Figure C-1: Sources configuration for breaker-and-a-half configuration
breaker accordingly. Similarly, these two currents are processed individually in Phase
Comparison element. Sum of 2 currents is calculated on the source “Sum CT” which is
used for overcurrent, distance and other protection elements. This source also has 3-phase
voltage VT bank, needed for distance protection as well.
Ilia Voloh
05/05/2006 Page 30 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
~ 5c ~ 6c
~ 6c ~ 5c
~ 5b ~ 5b
CH1
CH1
L60 - 1 PLC PLC L60 - 2
~ 6b ~ 6b
~ 5a ~ 6a
~ 6a ~ 5a
Tx Positive Ch 1
~ 5c
~ 5b
~ 5a
COMM S INTERFACE INPUTS/ OUTPUTS
Rx Positive Ch 1
~ 6c
~ 6b
~ 6a
~ 7c
~ 7b
~ 7a
~ 8c
~ 8b
~ 8a
~ 5c ~ 6c
~ 6c ~ 5c
~ 5b ~ 5b
CH1
CH1
For dual phase comparison 3-frequency PLC is needed: middle frequency, which is guard
frequency is used to monitor the channel, high frequency shift is used to key on the
positive half of the sinewave and low frequency shift is used to key on the negative half.
Ilia Voloh
05/05/2006 Page 31 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Tx Positive Ch 1
~ 5c
Common (+) Ch 1
~ 5b
Tx Negative Ch 1
COMM S INTERFACE INPUTS/ OUTPUTS ~ 5a
Rx Positive Ch 1
~ 6c
Common (-) Ch 1
~ 6b
Rx Negative Ch 1
~ 6a
~ 7c
~ 7b
~ 7a
~ 8c
~ 8b
~ 8a
~ 5c ~ 6c
PLC PLC
~ 6c ~ 5c
~ 5b ~ 5b
CH1
CH1
L60 - 1 L60 - 2
~ 6b ~ 6b
~ 5a ~ 6a
PLC PLC
~ 6a ~ 5a
PLC
PLC
~ 5b
~ 6b
~ 5a
~ 6a
~ 5c
~ 6c
CH1
L60 - 3
Ilia Voloh
05/05/2006 Page 32 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 33 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
phase comparison will operate for SLG faults only-another protection like distance is
required to be engaged for phase-to-phase faults. This setting has to be the same at all
line terminals. I 2 − K • I 1 mode allows Phase comparison to detect any type of the fault.
This setting must be set identically at all terminals of the line, or the scheme will be
dramatically impacted, to the extent of entirely diminishing security and/or dependability.
The same caution applies to the scheme type, operating current, and K settings
Ilia Voloh
05/05/2006 Page 34 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
terminal lines, using phase distance, unvervoltage, sequence componenets IOCs and
disturbance detectors reacting to the change in the sequence components currents can
chieve improvement in sensitivity. FDL starts keying when fault occurs on the protected
line or in the vicinity. It’s critical to ensure that FDL has enough sensitivity for all types
of the fault. If this is not possible, then additional keying starters have to be assigned in
parallel with built-in FDL using 87PC FDL AUX setting as is shown below. Generally,
keying is not desirable under normal load conditions; therefore it’s recommended to
calculate FDL setting as follows:
FDL = 1.1 • K • I1L (C-1)
where I1L is maximum line load current.
It must be noted that in some cases there might not be enough sensitivity for internal SLG
faults. In such cases, by reducing K factor FDL could be set much more sensitive,
operating mainly on the negative-sequence current. Minimum FDL setting in such case
should not be less than 0.04 pu to provide immunity to load unbalance and CT errors.
Ilia Voloh
05/05/2006 Page 35 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
If charging current compensation is used, then 2-nd term in the equations above can be
neglected.
Setting chosen per formulas above insure security against misoperations on external
faults. It’s necessary to check that with FDH setting determined, the mixing current
I 2 − K • I 1 output at all terminals for any internal fault will be sufficient to operate FDH
with 50% margin.
First step it should be determined that for the minimum 3-phase fault anywhere on the
line the network I 2 − K • I 1 is at least 1.5 times FDH pickup;
I13θ MIN • K ≥ 1.5 • FDH (C-4)
Whether or not SLG or LLG at the same location will also result in a the mixing current
I 2 − K • I 1 output of at least 1.5 times FDH pickup will depend upon the K setting,
maximum load current and the Z0 / Z1 ratio. Fault circuit studies are required to determine
either there will be enough negative sequence current for FDH for different types of the
fault. Simplified approach to determine this, using tables and curves is presented below in
the section C-4.
Ilia Voloh
05/05/2006 Page 36 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Tx duration=9.38ms Rx duration=10.63ms
Ilia Voloh
05/05/2006 Page 37 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
IRF
V2F
RCA
ILF
-IRF I2C
Ilia Voloh
05/05/2006 Page 38 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 39 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Figure C-11: Using FlexElements to measure THD during XFMR energization inrush
Ilia Voloh
05/05/2006 Page 40 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
On the transfromer HV side 2nd harmonic prevails which is used to detect transfer inrush
for transformer differential inhibit. However, on the line terminal CT, due to line
capacitance and inductance, shunt reactors harmonics spectrum is different with other
harmonics besides 2nd one
Therefore it’s beneficial to use THD for the line projection. L60 measures Total
Harmonic Distortion (THD) in all 3 phase currents plus neutral current, which are
available for protection purposes though FlexElement (Universal Comparator). Output of
the Flexelement can be used to block sensitive Neutral IOC or Phase Comparison on
transformer energization.
Typical pickup setting for THD is 10-25%. THD measurements are available per sources,
therefore, on the breaker-and-a-half applications source which sums both CT current has
to be used for that.
Ilia Voloh
05/05/2006 Page 41 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
components of the element and should assure correct starting by FDL detector and
arming action by FDH detector to allow coincidence detector operate correctly. Therefore
some precautions are needed when choosing setting for FDL and FDH or assigning
auxiliary element to compliment those detectors.
Even if direct coordination between FDL and FDH at opposite ends of the line is not
needed, it should be checked that FDH at one end and FDL at the opposite ends of the
line have enough security margin. This is especially critical when Blocking scheme is
used. It’s not advisable to set pickup setting of FDH at one end of the line the same, close
or lower than FDL at other end of the line. FDL at remote terminal should always be
more sensitive and reach farther to external faults behind remote bus. Diagram below
illustrates that. For protection #1 it’s critical to ensure that for any type of the fault F1
beyond terminal B, where FDH of protection #1 still operates, FDL at terminal B is
sensitive enough and has at least 20% margin for operation. It has to be noted that fault
current even for through fault might be quite different due to line capacitance, reactors on
the line etc. Situation worsens when there is a tapped load off protected line which can
infeed/outfeed fault current. Same checks are needed to coordinate protection #2 FDH
with protection #1 FDL for fault F2.
A B
FDL
FDH
Figure C-13: Coordination between FDH and FDL at opposite ends of the line
To secure FDH and FDL setting at opposite ends of the line during external fault, for 2-
terminal line, the relationship between the FDH setting at one end of the line to FDL
setting at the other end of the line is as follows;
FDH A ≥ I1C + 4 • FDLB (C-6)
3
For 3-terminal line, the formula is as follows;
FDH A ≥ I1C + 8 • FDLB(C) (C-7)
3
where FDLB(C) is a maximum of FDL settings at 2 other terminals
The maximum negative sequence charging current will flow when maximum negative
sequence voltage appears on the line. The maximum negative-sequence voltage will
appear on the line when a phase-to-phase fault occurs at or near one of the terminals. This
voltage will be only half of the system normal phase-to-neutral positive sequence voltage
at this terminal. It will appear at the point of the fault and will diminish along the line
back towards the zero potential bus. If it is assumed that system negative sequence
impedance is large compared with line impedance, then the voltage will not diminish
very much along the line. On the other hand, if the system impedance is small, then the
voltage diminishes to zero. A reasonable compromise is to assume that the voltage
Ilia Voloh
05/05/2006 Page 42 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
diminishes to about half of its maximum value at the other terminal. This results in the
average from both terminals negative sequence voltage of
⎡V V ⎤
V2 = ⎢ N + N ⎥ / 2 = 3 • VN = 0.375 • VN of the normal system phase-to-neutral voltage
⎣ 2 4 ⎦ 8
of the line. Therefore in calculations of FDL/FDH in equations above, factor of
3/8=0.375 is applied.
If charging current compensation is applied, then term I1C in the equations above can be
neglected.
Note: If system studies prove that there is sufficient margin between FDH setting and
minimum fault current, it’s recommended raising FDH and FDL setting to prevent
unnecessary 87PC starts during remote external fault. FDL setting has to be calculated
back from adopted FDH setting maintaining margin per formulas C-2 (C-3) or at least
50%.
Although both FDL and FDH are mostly responding to the negative-sequence current,
which is present in all but 3-phase faults, pickup setting of both fault detectors is related
to maximum load and minimum 3-phase fault. In general, fault studies must determine
the magnitude and relative phase angle of the I 2 − K • I1 quantity for all types of the fault
on all combinations pf phases for all reasonable system conditions and including the
effect of power flow. Relay calculates symmetrical component current based of phase A
reference. As during AG fault I1 and I2 are approximately 180º apart (neglecting load and
charge current) and producing smallest I 2 − K • I1 quantity therefore, this fault type has to
be considered first to determine FDL and FDH sensitivity. Then 3-phase fault needs
attention further. Simplified approach of selecting settings is outlined below.
Ilia Voloh
05/05/2006 Page 43 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 44 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Also, checking either magnitude of the negative sequence current for particular
application is enough or not for FDH, can be done using curves below
Ilia Voloh
05/05/2006 Page 45 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Z0/Z1<1 (B)
Z0/Z1>1 (A)
These curves provide the means of determining the negative sequence current for a fault
at given location on the protected line in terms of the positive sequence fault current for a
3-phase fault at the same location and he ratio of Z0 / Z1. Where Z0 / Z1 ratio is less than
1.0, the double-phase-to-ground (ØØG) fault yields the lower negative sequence current
and curve B should be used. Where, Where Z0 / Z1 ratio is greater than 1.0, phase-to-
ground fault (ØG) are limiting and curve A should be used.
Ilia Voloh
05/05/2006 Page 46 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 47 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Example B. Assume an application on the 2-terminal line, where maximum load current
is 0.8pu, minimum 3-phase fault current is 2.0pu and normal positive sequence charge
I13θ MIN
current is 0.1pu. System Z0 / Z1 is varying from 4.0 to 5.0. If ratio is less than
I1L
Ilia Voloh
05/05/2006 Page 48 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
C D
A B
E F
In setting the relays in Figure D-1 and checking for a breaekr failure at Station 2 for
protection on line A-B, the following should be checked: for all ground faults on the lines
C-D and E-F, relay A should have at least have at least 1.3 times PU for either the pilot
trip or the ground TOC element. However, sequential clearing is allowed. This should
take into account current distribution at station 2 and all considered contingencies.
Considered contingencies depend on the system configuration, voltage level, security and
dependability of protection applied on lines C-D and E-F. Typically these contingencies
are: transmission line(s) out of service, generating unit(s) out of service, pilot protection
on adjacent line out of service etc
Typically, coordination of O/C relays is a rigorous and sometimes difficult task. This
requires system data to carry out short circuit studies, maximum and minimum fault
current expected to flow through protective devices, type of protection schemes at the
adjacent system elements, normal and maximum load current at system components, CT
data including excitation curves, motors starting current and time, etc.
Coordination must ensure such settings that device will not operate in the backup
areas until the primary protection assigned to that area have the opportunity to clear the
fault. The primary objective of coordination studies is to set the protection to operate as
fast as possible for faults in the primary zone and delay sufficiently for faults in the
Ilia Voloh
05/05/2006 Page 49 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
backup zones. As such, referring to the figure D-1 above, protection on the line A-B
should be from one hand be sensitive enough to operate for all faults on the line A-B,
from another hand should not operate prior than protection on the lines C-D and E-F for
faults on these lines. There are few methods of achieving proper relay coordination:
• Discrimination by time, when appropriate time delay is chosen for each relay on
the adjacent lines,
• Discrimination by current, when appropriate pickup setting is chosen based on the
fact that fault current value increases for faults closer to the source,
• Discrimination by both current and time, using inverse time characteristics,
• Discrimination by direction, when O/C element is allowed to operate for fault in
the chosen direction only.
Ilia Voloh
05/05/2006 Page 50 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
respectively. If set to use the calculated 3I_0, the element applies a “positive-sequence
restraint” for better performance: a small user-programmable portion of the positive–
sequence current magnitude is subtracted from the zero-sequence current magnitude
when forming the operating quantity.
-3V_0 line
REV LA FWD LA
line line
VAG
(reference)
LA LA
3I_0 line
ECA
ECA line
-ECA line
-3I_0 line LA
VCG LA
VBG
REV LA FWD LA
line line
3V_0 line
Ilia Voloh
05/05/2006 Page 51 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
(5 Amp CT)
A
C
F 1b
F 2b
F 3b
F 4b
F 1a
F 1c
F 2a
F 2c
F 3a
F 3c
F 4a
F 4c
F 5a
F 5c
F 6a
F 6c
F 7a
F 7c
IA1
IB1
IC1
IG1
VC
VC
IA5
IB5
IC5
IG5
VB
VB
VA
VA
IB
IG
IA
IC
UR relay
Ilia Voloh
05/05/2006 Page 52 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 53 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Table D-2. Polarizing and operating quantities for “measured IG” mode
Ilia Voloh
05/05/2006 Page 54 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
the restraint completely. It may be set higher if large system unbalances or poor CT
performance are expected.
S_pol
V0
V0 -V0 Zoff x I0
Relay
a) I0
S_pol S_op = Z x I0
V0 Zoff x I0
Relay
-V0 V0
b)
I0
Figure D-5. Offset impedance during internal (a) fault and external (b) fault
For regular application, this setting is recommended:
Z0 L Z0 L
< Z OFFSET < (D-2)
5 2
where Z0 L is line zero-sequence impedance
1. The offset impedance must be higher the net capacitive impedance between the
potential source of the relay and the local equivalent system (ensures correct operation on
forward faults). If the net impedance between the potential source and the local
equivalent system is inductive, then there is no need for an offset. Otherwise, the offset
impedance shall be at least the net capacitive reactance.
Ilia Voloh
05/05/2006 Page 55 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
2. The offset must not be higher than the net inductive reactance between the potential
source and the remote equivalent system (ensures correct operation on reverse faults). For
simplicity and extra security, the far-end busbar may be used rather than the remote
equivalent system.
voltage
SENDING RECEIVING
protection reactance
BUS BUS
level
0.5 pu 0.6 pu 0.5 pu 0.7 pu
-2 Ω -4 Ω -3 Ω -5 Ω
INFINITE
INFINITE
3Ω 10 Ω 7Ω
BUS
BUS
F2 A B B A F1
Protected Line
Figure D-6. Offset impedance on series compensated lines
As the ground directional functions are meant to provide maximum fault resistance
coverage, it is justified to assume that the fault current is very low and none of the series
capacitors is guaranteed to get by-passed.
For example for the system shown above for the Left Terminal:
Bus side VTs (A):
Impedance from the VTs backward to the equivalent system;
REV = −2 + 3 = +1Ω , inductive, no need for the offset, minimum offset
Z0 Σ
Z0 MAX = 5Ω
Z0 MAX + Z0 MIN 5 + 0
Recommended setting Z0 OFFSET = = = 2.5Ω (D-3)
2 2
Line side VTs (B):
Impedance from the VTs backward to the equivalent system;
REV = −2 + 3 − 4 = −3Ω , capacitive, offset is needed, minimum offset
Z0 Σ
adopted Z0 MAX = 9Ω
Z0 MAX + Z0 MIN 9 + 3
Recommended setting Z0 OFFSET = = = 6Ω
2 2
For neutral directional, line and system zero-sequence impedances assumed for
calculations, for negative-sequence directional rules are the same, but negative-sequence
impedances shall be used instead.
Ilia Voloh
05/05/2006 Page 56 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 57 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 58 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
these goals. It helps the setting calculations if the system impedances are reasonably well
known.
1 2 3 4 5
min
IF1 D
max
F
IF
max
IFR
where K is safety factor varying from 1.1 to 1.3 depending on utility practice
max is maximum
and/or the degree of conservatism of protection engineer, If G
ground fault current, which can be either LG or LLG depending on system
impedances.
Ilia Voloh
05/05/2006 Page 59 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
2. If value calculated above per formula D-4 is greater than maximum fault current
on the bus A behind ( I OP > I max
FR ), then directional control is not needed.
Otherwise neutral directional should be used to directionalize IOC.
3. Sensitivity and protection coverage should be checked by the ratio of the
minimum line fault current to element operate setting I min
F1 / I OP , which should
be greater than 1.5 for close-in faults. Coverage of 30-50% of the line is
considered adequate, as the rest of the line is protected by the time overcurrent
elements (TOC).
4. If 2-nd step neutral IOC is applied as a backup for the relay #4, then it has to be
time coordinated with the instantaneous 1-st step neutral IOC of the relay #4. For
the close-in fault F2 to the relay #4, 2-nd step IOC at the relay #2 should be
sensitive enough to detect this fault and have a time delay of typically 0.25-0.5s.
Ilia Voloh
05/05/2006 Page 60 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
the element is blocked, the time accumulator will reset according to the reset
characteristic. For example, if the element reset characteristic is set to “Instantaneous”
and the element is blocked, the time accumulator will be cleared immediately.
I min
F3
I OP = (D-4)
1 .3
On the other hand, setting cannot be too sensitive as unbalance in phase currents may
be as high as 10-15%.
Regulations in some utilities has placed an upper limit of 600 amperes primary for the
ground TOC pickup to protect against low level tree faults
Ilia Voloh
05/05/2006 Page 61 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Table below indicated curves available on the UR series relays. Curves can be
initialized and plotted either using URPC program or using formulas stated in UR
manuals. If specific curve is not found in the UR curves library, up to four curves can be
programmed using FlexCurves A to D and then used with TOC elements.
1 2 3 4 5
X~
X~ #2
X~ 25~
#4
1000 ^
1499
2000 ^
2499 2500
A
It’s required to coordinate at the highest level of fault current, unless one can find an
excuse to coordinate at a lower level. Why? Consider the system in Figure D-8
coordination of TOC elements of relays #4 and #2. Assume the five fault points 1...5 on
the line B-C have fault levels of 1000, 1499, 2000, 2499, and 2500 respectively. Relays
#2 at A location must operate slower than the relays #2 at B location. Figure D-10 shows
the two curves for relays #2 and #4. Since fault current levels can range from 0 to
thousands of amps, and times can range from 0 to hundreds of seconds, the curves are
always plotted on a log-log scale. Move to the left and the times increase. The more to
the left, the more dramatic the increase, even though it appears the separations decrease
(remember this is log-log scale). Referring to the figure D-10, the separation of the two
curves at assumed 5 fault points 1...5 are 25~, 26~, 30~, 40~, and 60~, respectively.
Ilia Voloh
05/05/2006 Page 62 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
#2 with inst at #4
#2 without inst at #4
#2
25~
25~
25~
#4
^
1499 ^
2500 A
Ilia Voloh
05/05/2006 Page 63 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Operating time can be verified using URPC software. In order to do that, one should
select System Setup\FlexCurves\FlexCurve A menu as it’s shown in the figure D-12
below.
Ilia Voloh
05/05/2006 Page 64 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
In practice, such calculations should be carried out for all considered contingencies
such as minimum or maximum operating system conditions, lines I or out of service, AR
cycle etc, placing faults on all feeders outgoing from the station B. Using relay
coordination software, such task becomes much easier, when user can plot curves of
many relays simultaneously, visualizing coordination margin between relays.
Ilia Voloh
05/05/2006 Page 65 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 66 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
TS
TP U 0
OU
-90o
VA G(Faulted) IA
ECA
set @ 30 o
VBC
VBC
VCG VBG o
+ 90
The main component of the phase directional element is the phase angle comparator with
two inputs: the operating signal (phase current) and the polarizing signal (the line voltage,
shifted in the leading direction by the characteristic angle, ECA). The following table
shows the operating and polarizing signals used for phase directional control:
Ilia Voloh
05/05/2006 Page 67 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
• If, prior to reverse fault, power flow was “forward” with element output logic at
“0”, it would take some for the element to assert logic “1” (Block). Therefore, if
element is used to block Phase IOC, there should be delay of 10-20ms added to
IOC to prevent racing between IOC and Phase Directional OC.
Ilia Voloh
05/05/2006 Page 68 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I PKP = K • If 3max
Θ (E-2)
where K is safety factor varying from 1.3 to 1.5 depending on utility practice
and/or the degree of conservatism of protection engineer, If3max
Θ is a maximum 3-
phase fault on the remote bus current.
Ilia Voloh
05/05/2006 Page 69 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I PKP = K • Vn (E-4)
X1S + X 'd'
where K is a safety factor with typical values K=1.6-2.0, X1S is the system
positive-sequence impedance and X 'd' is the motor subtransient reactance.
Typically motor starting current is 6-8 times nominal current.
Sensitivity during phase-to-phase then is checked as;
S = 0.866• Vn (E-5)
X1S • I PKP
Value of S greater than 2-3 is considered satisfactory.
Ilia Voloh
05/05/2006 Page 70 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 71 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
a) Line protection –usually, Phase TOC is not used for tripping on the
transmission lines (sometimes overload signal), however it’s widely used on
the distribution lines. It should be chosen as maximum of short-time
maximum load current and magnetizing inrush of the transformers supplied by
this line:
I PKP = max ⎡(1.5 • I max max ⎤
Load ), (1.5 • I Insrush ) ⎥⎦ (E-6)
⎢⎣
where 1.5 is safety factor, allowing for 150% overload or margin during
insrush
Then sensitivity is checked during phase-to-phase fault at the end of the protected
line when line is energized from this terminal only:
min
If LL
S= (E-7)
I PKP
If S<3, it’s recommended to decrease setting to provide necessary sensitivity
and use undervoltage, supervising Phase TOC. Set the undervoltage relays at
0.9pu, but make sure that for a three phase fault at the end of the line, the
calculated voltage is no higher than 0.8pu, giving a 0.1pu margin.
b) Motor protection – TOC is used to protect from failure to accelerate to rated
speed in the normal starting interval, motor stalled condition, low-magnitude
phase fault current and overload. Generally, Thermal Model function,
following motor thermal curves provides best protections against overload.
When Phase TOC is applied together with Thermal Model function, then they
have to be coordinated by plotting motor starting curves, motor thermal limit
curves and Phase TOC inverse time characteristics. Choosing appropriate
TOC inverse-time characteristics curve, coordination is achieved. Typically,
TOC pickup is chosen as one-half of the locked-rotor current or less.
c) Generator protection- Phase TOC provides backup protection and usually is
employed as voltage-restraint function. The voltage-restraint function changes
TOC pickup to decrease with decreasing voltage (see description below). If
TOC is employed as a voltage-restraint function, then pickup is chosen as
150% of the FLA (full load amperes) of the generator.
I PKP = 1.5 • FLA (E-8)
d) Transformer protection- requirement for overload overcurrent protection are
specified in IEEE Std C37.91-2000 IEEE Guide for Protective Relay
Applications to Power Transformers. This is sometimes complicated task as
setting depends on the transformer thermal damage curve and frequency of the
through faults. Usually pickup is set to 250% of the rated current, however
this could allow that transformer to be damaged without the protective relay
operating.
Ilia Voloh
05/05/2006 Page 72 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
V (pu)
Ilia Voloh
05/05/2006 Page 73 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 74 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 75 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
connected with the fourth reactor with Xreact_n reactance connected between reactor-
bank neutral and the ground) it’s calculated as follows;
Ilia Voloh
05/05/2006 Page 76 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
This element works in association with other D60/L60 elements that must be
programmed and in-service for successful operation. The necessary elements are:
Breaker Control, Open Pole Detector, and Phase Selector. The recloser must also be in
the “Reset” state before a single pole trip can be issued. Outputs from this element are
also directly connected as initiate signals to the breaker failure
Ilia Voloh
05/05/2006 Page 77 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 78 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Typically this operand should combine reverse zone indications (such as Zone 4 pickup)
with a half-cycle pickup delay, and 2-cycle dropout delay. This setting should be used
only in single-pole tripping applications, when evolving faults are of importance, and
slightly delayed operation on evolving faults could be traded for enhanced accuracy of
single-pole tripping.
Phase Selector
The D60 uses phase relations between current symmetrical components for phase
selection. First, the algorithm validates if there is enough zero-, positive-, and negative-
sequence currents for reliable analysis. The comparison is adaptive; that is, the
magnitudes of the three symmetrical components used mutually as restraints confirm if a
given component is large enough to be used for phase selection. Once the current
magnitudes are validated, the algorithm analyzes phase relations between the negative
and positive-sequence currents and negative and zero-sequence currents (when
applicable) as illustrated below.
Due to dual comparisons, the algorithm is very secure. For increased accuracy and to
facilitate operation in weak systems, the pre-fault components are removed from the
analyzed currents. The algorithm is very fast and ensures proper phase selection before
any of the correctly set protection elements operates.
Under unusual circumstances such as weak-infeed conditions with the zero-sequence
current dominating during any ground fault, or during cross-country faults, the current-
Ilia Voloh
05/05/2006 Page 79 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
based phase selector may not recognize any of the known fault pattern. If this is the case,
voltages are used for phase selection. The voltage algorithm is the same as the current-
based algorithm, e.g. phase angles between the zero-, negative-, and positive-sequence
voltages are used. The pre-fault values are subtracted prior to any calculations.
The pre-fault quantities are captured and the calculations start when the Disturbance
Detector (50DD) operates. When the trip command is issued by the trip output logic
(TRIP 1-POLE or TRIP 3-POLE) and during open pole conditions (OPEN POLE OP),
the phase selector resets all its output operands and ignores any subsequent operations of
the Disturbance Detector.
FLEXLOGIC OPERANDS
TRIP 1-POLE
TRIP 3-POLE OR RESET
OPEN POLE OP
DELAY
0 DELAY FLEXLOGIC OPERANDS
4 cycles PHASE SELECT AG
FLEXLOGIC OPERAND AND 0 START
500 ms PHASE SELECT BG
SRCn 50DD OP
PHASE SELECT CG
PHASE SELECT AB
PHASE SELECTOR
FLEXLOGIC OPERAND
PHASE SELECT BC
SRCn VT FUSE FAIL OP
PHASE SELECT CA
PHASE SELECT ABG
SETTING
PHASE SELECT BCG
DISTANCE SOURCE: PHASE SELECT CAG
PHASE SELECT 3P
I_0
PHASE SELECT SLG
I_1
PHASE SELECT MULTI-P
I_2
PHASE SELECT VOID
V_0
V_1
V_2
Output operands of the Phase Selector are important indications for post-fault analysis.
It’s recommended to assign at least PHASE SELECT A (B, C), PHASE SELECT
MULTI-P and PHASE SELECT VOID operands into oscillography digital channel to be
captured during fault.
As it was mentioned above, Trip Output is interaction with many other elements in
order to perform tripping action correctly. These elements include; autoreclosure, breaker
control, phase selector, pilot schemes, open pole detector etc. This is especially critical
for single-pole tripping applications. Therefore, it’s of importance to configure these
elements correctly.
Ilia Voloh
05/05/2006 Page 80 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Phase Selector
AR RIP
Volts Reset
and Output Fault Locator
Amps
Block Specific Protection Elements
Volts
and
Trip Output Amps
Protection
Setting
Elements
1-Pole
Trip 1-Pole
Inputs Setting Request Trip
Open
Pilot- Pole
Aided
Schemes Detector
Trip
A or B or C
Setting Setting
Setting Permission
S B
e Inputs k
Reset t r
Breaker t
Control i 1
n Outputs &
3-Pole 3-Pole g 2
Trip Trip
Request
Line Pickup Setting
CLOSE 1
CLOSE 2
CLOSE 1
CLOSE 2
Multi - Phase
Operator
Void Force 3-Pole
3-Pole Operation
Setting Operation Setting
AR Force 3-P
Initiate
Reclose Request Trip
Initiate
AR Initiate 3-Pole
Recloser
Multi-Phase
Ilia Voloh
05/05/2006 Page 81 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 82 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
• BREAKER 1(2) FUNCTION: Set to "Enable" to allow the operation of any breaker
control feature.
• BREAKER1(2) PUSH BUTTON CONTROL: Set to "Enable" to allow faceplate
push button User 2 and User 3 operations.
• BREAKER 1(2) NAME: Assign a user-defined name (up to 6 characters) to the
breaker. This name will be used in flash messages related to Breaker 1.
• BREAKER 1(2) MODE: Selects "3-pole" mode, where all breaker poles are operated
simultaneously, or "1-pole" mode where all breaker poles are operated independently.
• BREAKER 1(2) OPEN: Selects an operand that creates a programmable signal to
operate an output relay to open Breaker No. 1(2).
• BREAKER 1(2) CLOSE: Selects an operand that creates a programmable signal to
operate an output relay to close Breaker No. 1(2).
• BREAKER 1(2) ΦA/3-POLE: Selects an operand, usually a contact input connected
to a breaker auxiliary position tracking mechanism. This input can be either a 52/a or
52/b contact, or a combination the 52/a and 52/b contacts, that must be programmed to
create a logic 0 when the breaker is open. If BREAKER 1 MODE is selected as "3-
Pole", this setting selects a single input as the operand used to track the breaker open
or closed position. If the mode is selected as "1-Pole", the input mentioned above is
used to track phase A and settings BREAKER 1 ΦB and BREAKER 1 ΦC select
operands to track phases B and C, respectively.
• BREAKER 1(2) FB: If the mode is selected as 3-pole, this setting has no function. If
the mode is selected as 1-pole, this input is used to track phase B as above for phase A.
• BREAKER 1(2) FC: If the mode is selected as 3-pole, this setting has no function. If
the mode is selected as 1-pole, this input is used to track phase C as above for phase A.
• BREAKER 1(2) EXT ALARM: Selects an operand, usually an external contact
input, connected to a breaker alarm reporting contact.
• BREAKER 1(2) ALARM DELAY: Sets the delay interval during which a
disagreement of status among the three pole position tracking operands will not
declare a pole disagreement, to allow for non-simultaneous operation of the poles. If
single-pole tripping and reclosing is used, the breaker may trip unsymmetrically for
faults. In this case, the minimum alarm delay setting must exceed the maximum time
required for fault clearing and reclosing by a suitable margin.
• MANUAL CLOSE RECAL1 TIME: Sets the interval required to maintain setting
changes in effect after an operator has initiated a manual close command to operate a
circuit breaker.
• BREAKER 1(2) OUT OF SV: Selects an operand indicating that Breaker 1(2) is out-
of-service.
G.2. AUTORECLOSURE
The autoreclose scheme is intended for use on transmission lines or distribution with
circuit breakers operated in both the single pole and three pole modes, in one or two
breaker arrangements. The autoreclose scheme provides four programs with different
operating cycles, depending on the fault type. Each of the four programs can be set to
trigger up to two reclosing attempts. The second attempt always performs three pole
reclosing and has an independent dead time delay.
Ilia Voloh
05/05/2006 Page 83 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
When used in two breaker applications, the reclosing sequence is selectable. The
reclose signal can be sent to one selected breaker only, to both breakers simultaneously or
to both breakers in sequence (one breaker first and then, after a delay to check that the
reclose was successful, to the second breaker). When reclosing in sequence, the first
breaker should reclose with either the 1-Pole or 3-Pole dead time according to the fault
type and reclose mode; the second breaker should follow the successful reclosure of the
first breaker. When reclosing simultaneously, for the first shot both breakers should
reclose with either the 1-Pole or 3-Pole dead time, according to the fault type and the
reclose mode.
The signal used to initiate the autoreclose scheme is the trip output from protection.
This signal can be single pole tripping for single phase faults and three phase tripping for
multi-phase faults. The autoreclose scheme has five operating states.
• Enabled- Scheme is permitted to operate
• Disabled- Scheme is not permitted to operate
• Reset- Scheme is permitted to operate and shot count is reset to 0
• Reclose In Progress- Scheme has been initiated but the reclose cycle is not
finished (successful or not)
• Lockout- Scheme is not permitted to operate until reset received
Ilia Voloh
05/05/2006 Page 84 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
resulting in power surges and large mechanical shaft torques that can cause severe
damage.
With synchronous machines, reclosing must be delayed until machines are removed
from the circuit; then reclosing can restore voltage and pickup static load. This can be
accomplished by frequency relays and undervoltage relays or “live bus”-“dead line”
function of synchronism check function.
For induction motors, reclosing should not take place until their residual voltage has
decreased to 33% of rated value.
Transmission lines: Lines used to transfer power between stations require high speed
reclosing on both terminals to restore service. High-speed can be applied when there are
parallel ties in the network to provide an exchange of power and holding stations in
synchronism. This requires high-speed simultaneous tripping at both line terminals as is
limited therefore to lines protected by unit protection such as line current differential, line
phase comparison and pilot protection. Reclosing on transmission lines usually calls for
the following:
1. Single-pole tripping is preferable as statistically 80-90% of the faults are SLG
and opening faulted phase only allows for power exchange over two
remaining phases, thus keeping sources in synchronism.
2. Reclose one end instantaneously and other end after checking that bus
voltage and line voltage are synchronous. Synchronous sources are usually
considered when voltages across open breaker are of sufficient magnitude,
frequency is within prescribed limit and angle of those two voltages is within
typically 20-50°
3. Without unit protection, reclose with time delay; a) live bus-dead line, b) live
line-live bus with synchronism check, c) live line-dead bus.
G.2.1. AR MODE
This setting selects the Autoreclose operating mode, which functions in conjunction with
signals received at the initiation inputs as described previously.
1ST SHOT 2ND SHOT 3RD SHOT 4TH SHOT
AR MODE Single Multi Single Multi Multi Multi Single Multi
phase phase phase phase phase phase phase phase
fault fault fault fault fault fault fault fault
1&3 POLE 1 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE
or LO or LO or LO or LO or LO or LO
1 POLE 1 POLE LO 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE
or LO or LO or LO or LO or LO or LO
3 POLE-A 3 POLE LO 3 POLE LO 3 POLE LO 3 POLE LO
or LO or LO or LO
3 POLE-B 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE 3 POLE
or LO or LO or LO or LO or LO or LO
Ilia Voloh
05/05/2006 Page 85 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
time delay initiated. If two or more shots are enabled, the second, third, and fourth
shots are always three-pole and start the AR 3-P DEAD TIME 2(4) timers.
• “1 Pole”: This mode is selected when AR should be allowed to reclose single-pole
during SLG faults only, when one pole of the breaker(s) opens only. In this mode, the
autorecloser starts the AR 1-P DEAD TIME for the first shot if the fault is single
phase. If the fault is multi-phase or a three-pole trip on the breaker occurred during
the single-pole initiation, the scheme goes to lockout without reclosing. If two or
more shots are enabled, the second, third, and fourth shots are always three-pole and
start the AR 3-P DEAD TIME 2(4) timers.
• “3 Pole-A”: This mode is selected for 3-pole tripping applications, when AR should
be allowed to reclose for SLG single phase faults only, although the trip is three pole.
The autorecloser uses the AR 3-P DEAD TIME 1 for the first shot if the fault is
single phase. If the fault is multi phase the scheme will go to Lockout without
reclosing. If two or more shots are enabled, the second, third, and fourth shots are
always three-phase and start the AR 3-P DEAD TIME 2(4) timers.
• “3 Pole-B”: This mode is selected for 3-pole tripping applications for any type of
fault and starts the AR 3-P DEAD TIME 1 for the first shot. If the initiating signal is
AR 3P TD INIT the scheme starts AR 3-P DEAD TIME 2 for the first shot. If two or
more shots are enabled, the second, third, and fourth shots are always three-phase and
start the AR 3-P DEAD TIME 2(4) timers.
Ilia Voloh
05/05/2006 Page 86 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
line (for the central breaker in a breaker and a half arrangement), or a sum of conditions
combined in FlexLogic™.
G.2.7. AR 1P INIT
This setting selects a FlexLogic™ operand that is intended to initiate high-speed single-
pole autoreclosure via timer AR 1P DEAD TIME. If Trip Output is used, then single-pole
AR initiation happens automatically- no need to assign anything with this setting. Usually
high-speed reclosure is initiated when line is tripped from both ends by instantaneous
protection and is reclosed simultaneously from both ends. Mostly, line current differential
line phase comparison and pilot schemes are recommended to be initiating high-speed
reclosure. The intent is to try to have both terminal breakers tripped and reclosed at the
same instant, reducing the effect on the power system
G.2.8. AR 3P INIT
This setting selects a FlexLogic™ operand that is intended to initiate three-pole
autoreclosure via first timer AR 3P DEAD TIME 1, which can be used for a high-speed
three-pole autoreclosure. If Trip Output is used, then three-pole AR initiation happens
automatically- no need to assign anything with this setting. Consideration for high-speed
reclosure indicated above for 1P initiation, is applicable to 3P high-speed initiation as
well.
G.2.9. AR 3P TD INIT
This setting selects a FlexLogic™ operand intended to initiate three-pole autoreclosure
via second timer AR 3P DEAD TIME 2, which can be used for a time-delay
autoreclosure. Typically, time delayed protection or non-unit protection is assigned to
cause time delayed reclosure on the transmission lines.
Ilia Voloh
05/05/2006 Page 87 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Breakers scheme indicating breaker(s) status. Setting is provided in case when Breakers
scheme is not used.
G.2.17. AR RESET
This setting selects the operand that forces the autoreclose scheme from any state to
Reset. Typically this is a manual reset from lockout, local or remote. It has to be
remembered that AR is automatically reset from either Breaker Manual close command
derived from Breakers element or 10 seconds after breaker was closed if previously it
was locked out. This setting is mostly used, if before breaker close operation, AR has to
be brought into “Enabled” state.
Ilia Voloh
05/05/2006 Page 88 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
G.2.20. AR BLOCK
This setting selects the operand that blocks the Autoreclose scheme (it can be a sum of
conditions such as: time delayed tripping, breaker failure, bus differential protection,
etc.). If the block signal is present before autoreclose scheme initiation, the scheme is
taken out of service with AR DISABLED FlexLogic™ operand being set. If the block
signal occurs when the scheme is in the RIP state the scheme will be sent to Lockout.
G.2.21. AR PAUSE
The pause input offers the ability to freeze the autoreclose cycle until the pause signal
disappears. This may be done when a trip occurs and simultaneously or previously, some
conditions are detected such as out-of step or loss of guard frequency, or a remote
transfer trip signal is received. When the ‘pause’ signal disappears the autoreclose cycle
is resumed. This feature can also be used when a transformer is tapped from the protected
line and a reclose is not desirable until it is disconnected from the line. In this situation,
the reclose scheme is ‘paused’ until the transformer is disconnected.
G.2.23. AR TRANSFER 1 TO 2
This setting establishes how the scheme performs when the breaker closing sequence is
1-2 and Breaker 1 is blocked. When set to “Yes” the closing command will be transferred
directly to Breaker 2 without waiting for the transfer time. When set to “No” the closing
command will be blocked by the AR BKR1 BLK signal and the incomplete sequence
timer will send the scheme to Lockout.
Ilia Voloh
05/05/2006 Page 89 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
G.2.24. AR TRANSFER 2 TO 1
This setting establishes how the scheme performs when the breaker closing sequence is
2-1 and Breaker 2 is blocked. When set to “Yes” the closing command will be transferred
directly to Breaker 1 without waiting the transfer time. When set to “No”, the closing
command will be blocked by the AR BKR2 BLK signal and the incomplete sequence
timer will send the scheme to Lockout.
Ilia Voloh
05/05/2006 Page 90 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
G.3. SYNCHROCHECK
The synchronism check function is intended for supervising the paralleling of two
parts of a system, which are to be joined by the closure of a circuit breaker. The
synchrocheck elements are typically used at locations where the two parts of the system
are interconnected through at least one other point in the system. Two synchrocheck
elements are available.
Ilia Voloh
05/05/2006 Page 91 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Result of this formula implies that if the admissible angle difference between two
sources voltage is 30° and sources slip frequency is 0.1 Hz, then reclosing should take
place within 1.67 seconds.
Syncrocheck can operate if either three-phase or single-phase voltage from both sides
of the breaker is supplied to the relay. As a minimum requirement for synchrocheck to be
set and to be functional, is to assign this either three-phase or single-phase voltage from 2
different VTs to two different sources in the UR System Setup\Sources menu. If one or
both sources are de-energized, the synchrocheck programming can allow for closing of
the circuit breaker using undervoltage control to by-pass the synchrocheck measurements
(Dead Source function).
The selected sources for synchrocheck inputs V1 and V2 (which must not be the same
source) may include both a three-phase and an auxiliary voltage. The relay will
automatically select the specific voltages to be used by the synchrocheck element in
accordance with the following table.
Ilia Voloh
05/05/2006 Page 92 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 93 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 94 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Usually it’s predetermined by the user, which terminal closes first and which follows.
Terminal closing first needs to check dead line-live bus condition (dead line charging),
while the other needs to check synchronism to eventually restore the power transit.
Example: If it’s necessary to charge the line from station A after 5 seconds breaker
was tripped for “dead line-live bus” condition, while station B would reclose 2 seconds
after line was charged with synchronism check or in 15 seconds if line is still dead in case
station A failed to charge the line.
A B
Relay at A:
Assuming that Trip Output scheme and Breakers scheme are used: AR in initiated
automatically from Trip Output:
1. Synchrocheck 1 is selected as Live V1 (bus)-Dead V2 (line) as shown in the
Figure G-3 above.
2. AR dead time timer #1 is set to 5 seconds
3. In the Flexlogic AR CLOSE BRK1 is AND-ed with SYNCH1 DEAD S OP,
assigned with a Virtual Output closing the breaker.
Relay at B:
Assuming that Trip Output scheme and Breakers scheme are also used: AR in
initiated automatically from Trip Output. This relay has to wait until either voltage
appears on the line to reclose in 2 seconds with synch or if voltage doesn’t appear, then
reclose in 15 seconds.
1. Synchrocheck 1 is selected as Live V1 (bus)-Dead V2 (line) as shown in the
Figure G-3 above to reclose in 15 seconds for the 2-nd condition.
2. As AR is initiated automatically from Trip Output it has to be paused until
Ilia Voloh
05/05/2006 Page 95 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 96 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
H. BREAKER FAILURE
Protection systems are coordinated so that the circuit breaker(s) nearest the fault are
opened to interrupt, or clear, the fault with minimum impact to the remainder of the
power system. This critical operation requires that the circuit breaker interrupt, or clear,
fault current.
B C
A 3 4
1 2 5 6
Load Load
7 8
Load
Figure H-1. Local and remote breaker fault clearing
While infrequent, circuit breakers occasionally fail to trip, or fail to clear a fault.
Depending on the power system network topology other circuit breakers must then be
called upon to trip and isolate the sources contributing to the fault. Referring to Figure H-
1, assume a fault exists between breaker 3 and breaker 4. Protective relays associated
with breaker 3 and breaker 4, designed to detect faults on the line between these breakers,
operate and command breaker 3 and breaker 4 to trip. In this example, breaker 3 fails to
interrupt the fault current. Therefore, all sources that continue to supply fault current
through breaker 3 must be interrupted. Assuming sources at stations A and C, locally,
breakers 2, 5, and 7 must be opened, or remotely, breakers 1, 6, and 8 must be opened.
To implement remote breaker failure backup protection for breaker 3, the protective
relays at breakers 1, 6, and 8 must have overreaching elements that sense faults anywhere
on the line between breaker 3 and breaker 4, and operate after a time delay, typically
about 0.5 seconds. This time delay is required to allow time for the local line protection
on breaker 3 to operate, and for the breaker to successfully clear the fault, recognizing
that the local protective relay scheme on breaker 3 may include time delayed tripping to
coordinate with other protective relays. Remote backup protection does not have the
benefit of knowing exactly when the breaker is commanded to open. Therefore, the
remote backup protection must include sufficient time delay to accommodate all possible
tripping delays.
The advantage of remote breaker failure protection is that it is completely
independent of protective relays, control systems, and battery supplies at the station with
the failed breaker.
Remote backup, however, has several disadvantages: a) all tapped loads between
breakers, 1-2, 5-6, and 7-8 are dropped causing widespread customer outages; b) the
lengthy backup clearing time will cause excessive system voltage dip duration, additional
damage to faulted equipment, possible damage to unfaulted equipment, and may lead to
system instability; c) due to possible infeed effects from the other lines, it may be
difficult to set the relay at 1 to detect faults on the entire length of the adjacent lines; d)
the settings required at 1 to provide sufficient reach to detect faults out to the remote ends
of the adjacent lines may be so sensitive that the line is susceptible to tripping under
Ilia Voloh
05/05/2006 Page 97 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
heavy load during extreme disturbances, which could initiate or exacerbate a wide-area
cascading outage.
An alternative to remote backup is local breaker failure protection, which receives a
signal directly from the line protection relays at the same station as the impaired breaker,
indicating when the trip command is sent to the breaker. Local breaker failure protection
eliminates the disadvantages of remote backup protection. Using the example in Figure
H-1 again, when the protective relay on breaker 3 senses a fault on line 3-4 and issues a
trip to breaker 3, local breaker failure protection starts a timer. If the timer times out, and
the fault is not cleared by breaker 3, then the local breaker failure scheme sends trip
signals to adjacent breakers 2, 5, and 7. The local breaker failure scheme has several
benefits over the remote backup scheme. If there are sources at buses A and C, tapped
loads between breakers 1-2, 5-6, and 7-8 can still be served. The total clearing time for
the fault is reduced substantially compared to the remote backup method. The timer
setting for the local breaker failure scheme is composed of breaker interrupting time plus
some margin. Margins have been used from less than 1 cycle to 3 cycles as dictated by
the critical fault clearing time. Protective relay time is not included in this time delay.
This timer setting is typically less than 12 cycles, compared to 30 cycles for remote
backup. This time difference could mean the difference between a stable and unstable
system for some critical faults and may substantially reduce the extent of damage at the
fault. The primary disadvantage of local breaker failure protection is that it may suffer
from common-mode failure. Station battery failure, for example, that may be the original
cause of the breaker failure condition, may also disable the local breaker failure
protection. Likewise, local protective relay malfunction may cause a failure to trip the
breaker, and also fail to initiate the local breaker failure timer. The cost of separate
breaker failure relays, while once a major consideration, has been significantly reduced as
the breaker failure function has been integrated into each UR protective relay.
There are many things that may cause the failure of a circuit breaker to interrupt fault
current. If a defective trip coil or trip circuit is the cause for the failure, slow clearing of
the fault will not cause further damage to the breaker. However, some common causes for
the failure to interrupt are that the breaker mechanism travel is incomplete or the
mechanism is slow; components needed for the interruption: (resistors or capacitors), are
faulty; or the dielectric material in the interrupter is out of specification (low pressure,
low temperature) or contaminated. If these are the causes for the failure to interrupt, the
breaker needs protection to prevent further damage. By the time the remote backup
protection has operated, the arcing inside the interrupter will likely cause a phase-to-
ground fault internal to the breaker. These internal faults may lead to explosions and
fires. As a result of the slow clearing of the original fault, what could have been a minor
breaker repair project, if the faulty breaker had been isolated in a timely manner, now
may require the replacement of the breaker and possibly other equipment in close
proximity to the faulty breaker.
Basic breaker failure protection provides a means to trip adjacent current sources if a
fault is detected by protective relays and the associated breaker(s) fail to interrupt the
fault.
Ilia Voloh
05/05/2006 Page 98 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
0 Rampdown
P ROTECTION OPERATION B REAKER INTERRUPTINGTI ME
(ASS UMED 1.5 cyc les) (A SSUMED 3 cy cles)
MARGIN BACKUP B REAKEROPERATING TIME
(As sumed 2 Cycl es) (A ssume d 3 Cyc les)
FAULT
OCCURS cycles
0 1 2 3 4 5 6 7 8 9 10 11
Ilia Voloh
05/05/2006 Page 99 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 100 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I PH min
PKP = K • If1Θ for 1-pole tripping BF (H-1)
Ilia Voloh
05/05/2006 Page 101 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I PH min
PKP = K • If 2Θ for 3-pole tripping BF (H-2)
Ilia Voloh
05/05/2006 Page 102 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
breaker failure scheme equipment. In microprocessor relays this time is not significant. In
UR relays, which use a Fourier transform, the calculated current magnitude will ramp-
down to zero somewhat later after the current is interrupted, and this lag should be
included in the overall margin duration, as it occurs after current interruption. The
Breaker Failure Main Path Sequence diagram below shows a margin of two cycles; this
interval is considered the minimum appropriate for most applications. Note that in bulk
oil circuit breakers, the interrupting time for currents less than 25% of the interrupting
rating can be significantly longer than the normal interrupting time.
T 2 = BRK op _ time + 50BFRST + TS (H-5)
836769A2.CDR
Ilia Voloh
05/05/2006 Page 103 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 104 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
resistor is inserted (approximately 90% of the resistor current). This setting is valid only
for 3-pole breaker failure schemes.
Note: It is desirable to set the breaker failure timer so that the total fault clearing time is
less than:
• transient stability time,
• the time to damage major equipment such as conductors and transformers,
• the time that major customers’ processes may be affected.
Ilia Voloh
05/05/2006 Page 105 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Stability constraints typically require breaker failure timer settings in the ten to thirty
cycle range, but in rare cases may require settings as low as four cycles. Equipment
damage typically occurs for clearing times greater than thirty cycles. Clearing times that
impact major customer processes may be longer than thirty cycles. If the required
clearing times are less than thirty cycles, it is highly unlikely that faster breaker failure
clearing will prevent the process shutdown.
Ilia Voloh
05/05/2006 Page 106 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I. TRANSFORMER DIFFERENTIAL
I.1. OVERVIEW
The T60 and T35 Transformer Management Relays are microprocessor-based relays for
protection of small, medium, and large three-phase power transformers. The T60 relay
can be configured with maximum of four three-phase current inputs and four ground
current inputs (banks), and can satisfy applications with transformer windings connected
between two breakers, such as in a ring bus or in breaker-and-a-half configurations. The
T35 Transformer Management Relay is available with two to six banks of three-phase
inputs: either CTs, or CTs and VTs for applications of up to six breakers/CTs associated
to transformer windings The T60 and T35 relays perform magnitude and phase shift
compensation internally, eliminating requirements for external CT connections and
auxiliary CTs.
The Percent Differential element is the main protection function, which is identical in
both T60 and T35 relays. Instantaneous Differential protection, Volts-per-Hertz (T60
only), Restricted Ground Fault (T60 only), and many current, voltage, and frequency-
based protection elements are also incorporated.
The T60 and T35 include sixteen fully programmable universal comparators–
(FlexElements™), that provide additional flexibility allowing the user to customize their
own protection functions using any signal measured or calculated by the relay.
Ilia Voloh
05/05/2006 Page 107 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
rating of the CT should not be less than the full forced cooled rating of the transformer,
as CTs typically have a rating factor of 150%, and few operators allow transformer
emergency loading above 140% of the forced cooled rating
Sources are a mechanism that allows creation of named entities that may sum currents
from different CT banks, and associate the currents along with their voltage inputs.
Source settings specify which DSP (CT/VT) module currents and voltages are processed
for later use. For example, specifying Phase CT input as “F5” means that 3-phase current
measured by DSP module installed in the slot “F”, terminals starting from “5” are
processed on this particular source. Protection elements use sources to specify which AC
inputs they use. The base current and the primary rating of a source is the highest CT
primary rating of the CTs summed by that source. Any currents summed by a source are
rescaled to this base before summing. Overcurrent relay settings are in per unit on the
base of the source it measures. The differential elements use this primary rating to
determine its base current.
For transformer applications, it is advantageous to have a separate source for each CT
bank, rather than using sources to sum the currents that add to the winding current. This
provides with extra security during through fault with some CT saturated due to
differential element can obtain a restraint signal from any other configured supplying
adequate current . For example, for 2-breakers applications (breaker-and-a-half or ring
connection), it’s beneficial to assign separate source for each breaker CT instead of
summing up 2 breakers CT in one source.
Figure I-2 depicts sources assignments 138/69/13.2 kV transformer all three windings
CTs to different sources.
Ilia Voloh
05/05/2006 Page 108 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Margin is then calculated as ratio between winding CT primary current and winding
nominal current per equation I-1 above:
CT
I PRI
MWx = (I-2)
I N( W )
Ilia Voloh
05/05/2006 Page 109 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
LOAD LOSS AT RATED LOAD: This setting should be taken from the transformer
nameplate. If not available from the nameplate, the setting value can be computed as,
PR = I 2N ( W ) * R W where I 2N ( W )
is the winding rated current and R W is the three-phase
series resistance. The setting is used as an input for the calculation of the hottest-spot
winding temperature.
RATED WINDING TEMP RISE: This setting defines the winding temperature rise
over 30°C ambient temperature. The setting is automatically selected for the transformer
type as shown in the table in T60 manual.
NO LOAD LOSS: This setting is obtained from the transformer data and is used to
calculate the aging acceleration factor.
5
TYPE OF COOLING: The setting defines the type of transformer cooling and is used to
calculate the aging acceleration factor. The values and their description for this setting are
as follows:
“OA”: oil-air
“FA”: forced air
“Non-directed FOA/FOW”: non-directed forced-oil-air/forced-oil-water
“Directed FOA/FOW”: directed forced-oil-air/forced-oil-water
“Sealed Self Cooled”, “Vented Self Cooled”, “Forced Cooled”: as named
TOP OIL RISE OVER AMBIENT: This setting should be available from the
transformer nameplate data.
Ilia Voloh
05/05/2006 Page 110 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 111 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
WINDING x SOURCE: Defines CT connection for each winding per source, configured
under Sources menu as shown on the Figure I-2 above
WINDING x RATED MVA: Defines MVA per each winding source, used to calculate
winding nominal current for magnitude compensation. T60/T35 calculate magnitude
compensation factor for each winding as follows:
( Wx ) ( Wx )
C I PRI •VN
MWx = (I-3)
( Wref ) ( Wref )
I PRI •VN
For example, for transformer shown on Figures I-2 to I-4, magnitude compensation
factors for each winding are calculated as follows:
C = 2000•13.2 = 1.00
For 13.2 kV as a reference winding, chosen automatically, M13.2 2000•13.2
C = 600•138 = 3.136
For 138 kV winding, it’s M138
2000•13.2
C = 1200• 69 = 3.136
For 69 kV winding, it’s M 69
2000•13.2
The maximum allowed magnitude compensation factor (and hence the maximum allowed
CT ratio mismatch) is 32.
WINDING x ANGLE WRT WINDING 1: Selects the angle of the phase shift for all
windings with respect to (WRT) to winding #1. The angle for the first winding from the
transformer setup must be 0° and the angles for the following windings must be entered
as negative (lagging) angle with respect to (WRT) the Winding 1. This is also closely
related to system phase rotation ABC or ACB.
For example,
• Y/d-1 per IEC nomenclature ABC rotation results in setting of 30° in T60/T35
relays.
Ilia Voloh
05/05/2006 Page 112 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
•Y/d-1 per IEC nomenclature ACB rotation results in setting of 330° in T60/T35
relays.
• Y/d-11 per IEC nomenclature ABC rotation results in setting of 330° in T60/T35
relays
• Y/d-11 per IEC nomenclature ACB rotation results in setting of 30° in T60/T35
relays
• D/y-1 per IEC nomenclature ABC rotation results in setting of 30° in T60/T35
relays
Refer to T60/T35 manual for more details on phase and magnitude compensation.
Ilia Voloh
05/05/2006 Page 113 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
that might be seen under normal load operating conditions. Two factors may create
differential current during the normal transformer operation: errors due to CT
inaccuracies and current variation due to on-load tap changer operation. A setting of 0.1
to 0.3 is generally recommended (the factory default is 0.1 pu). More precisely setting
can be calculated as follows:
• Error due to CT inaccuracy: assume CT class with 5% guaranteed accuracy is
used. Worst case is when CTs on different Tx windings generate errors in
opposite direction, one CT generates +5% error while another –5% error.
± 5% • I N ( W ) • M C
(W )
I ERR = (pu) (I-4)
(W ) CT
I PRI
Ilia Voloh
05/05/2006 Page 114 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
DIFPKP
SLOPE1 = ( ) • 100% + K S % (I-6)
RESTR
where K S % is safety margin withrecommended values of 5 to 10%
For example above, assuming restraint value maximum of 2 windings currents, which is
1.14pu plus +5% of safety margin, yields following:
0.15 pu
SLOPE1 = ( ) • 100% + 5% = 18%
1.14 pu
Ilia Voloh
05/05/2006 Page 115 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
where I sec is maximum external fault secondary current, I relay is current supplied by
the saturated CT to the relay, I magnetizing is a magnetizing current of the saturated CT,
Vmagnetizing is a magnetizing voltage at secondary fault current.
1000
100
sample CT
Vmag (V)
10
1
0.01 0.1 1 10 100
Imag (A)
The magnetizing current of the saturated CT will appear to the differential element
protecting the transformer. Therefore slope has to high enough to cope with this spurious
differential current.
I magnetizing
SLOPE 2 = ( ) • 100% + K S % (I-11)
I relay
where K S % is the safety margin with recommended values of 15% to 25%. Safety factor
accounts for additional spilled differential current due to DC offset in the current,
remanence effect, and errors in calculations.
For example, if sample CT with magnetizing characteristics shown on the Figure I-7
with CT ratio 600/5 and burden 2.1Ω is exposed to maximum 3-phase fault current of
14kA, following calculations are to be carried out;
max
IF
1. Secondary fault current is equal to: I sec = = 14000 = 116.67 A
N CT 120
2. Voltage at CT terminals is equal to: Vmagnetizing = I sec • R B = 116.67 • 2.1 = 245V
3. Using sample CT curve per Figure I-7, magnetizing current can be obtained equal
to I magnetizing = 45 A .
4. Now current supplied by CT to the relay can be calculated per formula I-9 as:
I relay = I sec 2 − I 2 magnetizing = 116.67 2 − 45 2 = 107.6 A
5. Slope 2 is then determined per formula I-11 as:
Ilia Voloh
05/05/2006 Page 116 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
I magnetizing
SLOPE 2 = ( ) • 100% + 10% = ( 45 ) • 100% + 20% = 61.8%
I relay 107.6
Note that minimum available setting for Slope 2 is 50%.
After Pickup, Break 1, Break 2, Slope 1 and Slope 2 are calculated, sensitivity of
protection has to be checked for the minimum fault conditions;
⎡ I min • M C + …+ I min • M C ⎤
⎢⎣ F ( W 1 ) ( W1 ) F ( Wn ) ( Wn ) ⎥⎦
K= (I-12)
max ⎡ I min • M C , I min •M C ,I min • M C ⎤ • S1( 2 )
⎢⎣ F ( W 1 ) (W1 ) F( W 2 ) ( W 2 ) F ( Wn ) ( Wn ) ⎥⎦
To determine sensitivity margin factor K, values of minimum fault current from all sides
has to be obtained from the fault studies. Maximum fault current from any side matched
by compensating factor M will become restraint current. Using value of that current,
Slope, used during minimum fault current conditions can be determined (slope 1 or 2
value). Slope 1 or 2 value during minimum fault current conditions is then used in
formula I-12.
Value of factor K should not be less than 2.
INRUSH INHIBIT FUNCTION: This setting provides a choice for 2nd harmonic
differential protection blocking during magnetizing inrush conditions. Two choices are
available: “Adapt. 2nd”, and “Trad. 2nd” – traditional 2nd harmonic blocking. The
adaptive 2nd harmonic inhibit responds to both magnitudes and phase angles
relationships between the 2nd harmonic and the fundamental frequency components. The
traditional 2nd harmonic restraint responds to the ratio of magnitudes of the 2nd
harmonic and fundamental frequency components. If low second harmonic ratios
duringmagnetizing inrush conditions are not expected, the relay should be set to
traditional way of restraining.
Ilia Voloh
05/05/2006 Page 117 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
INRUSH INHIBIT LEVEL: This setting specifies the level of 2nd harmonic component
in the transformer magnetizing inrush current above which the percent differential
element will be inhibited from operating. The value of the INRUSH INHIBIT MODE
setting must be taken into account when programming this value. The INRUSH
INHIBIT LEVEL is typically set to 20%.
Four Restricted Ground Fault elements are available. Restricted Ground Fault (RGF)
protection provides sensitive ground fault detection for low-magnitude fault currents,
primarily faults close to the neutral point of a Wye-connected winding. An internal
Ilia Voloh
05/05/2006 Page 118 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
ground fault on an impedance grounded Wye winding will produce a fault current
dependent on the ground impedance value and the fault position on the winding with
respect to the neutral point.
The resultant primary current will be negligible for faults on the lower 30% of the
winding since the fault voltage is not the system voltage, but rather the result of the
transformation ratio between the primary windings and the percentage of shorted turns on
the secondary. Therefore, the resultant differential currents may be below the slope
threshold of the main differential element and the fault could go undetected. Application
of the RGF protection extends the coverage towards the neutral point.
If CT(1200:1)
r
3I0
CTg (600:1)
Ig
T60
Ig
The differential current is produced as an unbalance current between the ground current
of the neutral CT (IG) and the neutral current derived from the phase CTs (IN = IA + IB
+ IC):
I gd = I G + I N = I G + I A + I B + I C
The relay automatically matches the CT ratios between the phase and ground CTs by re-
scaling the ground CT to the phase CT level.
The restraining signal ensures stability of protection during CT saturation conditions and
is produced as a maximum value between three components related to zero, negative, and
positive-sequence currents of the three phase CTs as follows:
Ilia Voloh
05/05/2006 Page 119 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
For example, for 11kV winding of the 10MV transformer with CT 600/5 and
grounding resistor of 6.3Ω, this result in the following;
RGFPKP = 0.05 • 11000 = 0.08 pu
3 • 6.3• 600
RGFSLOPE = 8.0 • 0.08• 600 • 100% − 20% = 53%
524.9
2. Security check during external 1-phase faults with or without CT saturation
when fault current is greater at least than 1.5pu. Function should produce
enough restraint not to operate during such external fault condition;
1θ
ext = 3 • I1 max − RGF
ID (I-16)
CT PKP
I PRI
Then security factor is calculated to check either element has enough restraint:
ext •100%
ID
SF = ≥ 1.3 (I-18)
ext • RGF
IR 0 SLOPE
Ilia Voloh
05/05/2006 Page 120 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 121 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
C
UR relay
F 1a
F 1b
F 2a
F 2b
F 3a
F SLOT X 8CT CURRENT INPUTS
F3b
F 4a REACTORS
T35/T60 RELAY
F 4b
F5a
F 5b
F 6a
F 6b
F 7a
F7b
F 8a
F 8b
Ilia Voloh
05/05/2006 Page 122 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
secondary arc current in a faulted and disconnected phase conductor during single-phase
fault interruption.
Oil-immersed reactors may also be connected to the substation bus, and as with line-
connected reactors, are generally solidly grounded and may be either switched or
permanently connected to the bus. Relaying protection for bus connected reactors and
for four-reactor configured banks is basically the same as that used for line-
connected, solidly grounded, oil-immersed reactors
Assume that 33MVA reactor in each phase in connected to 230kV line. T36/T60
transformer differential element is used for reactor percent differential protection. Both
winding are configured as Wye connection with grounding “Not within zone”.
DIFFERENTIAL PICKUP
The minimum PKP setting defines the minimum differential current, which may occur
during normal operating conditions mainly due to CT errors. For example, if we have
installed C class accuracy CT (up to 10% error) on each winding of the transformer, the
minimum per-unit differential current can be defined as;
Ilia Voloh
05/05/2006 Page 123 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
±10% • S N • 3
I (ERR
W) = (pu) (J-19)
CT •V
I PRI N
where S N is the reactor nominalcapacity in each phase
V N is system nominal line voltage
CT is CT primary rated current
I PRI
For CT’s 300/1A differential pickup can be calculated as
1.1• S N • 3 0.9 • S N • 3
DIFPKP = - + 0.05 = 0.91 - 0.75 + 0.05 = 0.21 (pu) (J-20)
CT •V
I PRI CT •V
I PRI
N N
where 0.05 is security margin
DIFFERENTIAL SLOPE 1
Slope 1 can be calculate the same as for transformer protection with formula J-6 above
using pickup and restraint equal to 1.1•IN calculated with formula J-20 above;
DIFPKP 0.21
SLOPE1 = (
RESTR
) • 100% + K S % =
0.91
• 100% + 5% = 28% (J-21)
DIFFERENTIAL SLOPE 2
The Slope 2 setting ensures stability during heavy through fault conditions, where CT
saturation results in high differential current. Calculation of this settings is similar to
Transformer Differential outlined by formulas J-9 and J-11 above.
Ilia Voloh
05/05/2006 Page 124 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 125 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 126 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
J. BUSBAR PROTECTION
J.1. OVERVIEW
The substation bus and switchgear are the parts of the power system used to direct the
flow of power to various feeders and to isolate apparatus and circuits from the power
system. These parts include the bus bars, circuit breakers, fuses, disconnection
devices, current transformers (CTs), voltage transformers (VTs), and the structure on
or in which they are mounted. To isolate bus faults, all power source circuits
connected to the bus are opened electrically by circuit breakers responding to relay
action. In view of the system downtime resulting from a bus fault, the equipment
should be designed to be as nearly fault proof as practicable. Regardless of the steps
taken to avoid bus faults, such faults occasionally occur. High-speed protective
relaying should be used to minimize fault duration. Shorter faults limit damage and
mitigate the effects on other parts of the power system. Providing proper bus
protection requires a well-designed system.
The number of circuits that are connected to a bus varies widely. When there are
more than six to eight circuits involved, buses are often split to a by a circuit breaker
(bus tie), or a bus arrangement in service is used that minimizes the number of
circuits that must be opened for a bus fault. There are many bus arrangements in
service dictated by the application, economics and flexibility of operation: major
types are illustrated on the figures below.
ZONE 1
1 2 3 ---- n-1 n
Single-bus scheme with single breaker per circuit with bus differential relaying is
mostly applied for distribution and lower transmission voltage levels buses. It doesn’t
have operating flexibility and during fault on the bus scheme trips all circuit breakers.
ZONE 2
ZONE 1
Ilia Voloh
05/05/2006 Page 127 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Two section bus with a single breaker per circuit with a bus tie breaker is used on lower
transmission voltages-this scheme has limited operating flexibility as well.
ZONE 1
ZONE 2
ZONE 2
Figure J-4. Double-bus single breaker scheme with a transfer bus and bus tie
Double-bus single breaker scheme with a transfer bus and bus tie is another very
popular arrangement for transmission voltage level. It allows very high operating
flexibility for breaker maintenance by transferring circuit load to a transfer bus. This
arrangement has an advantage of permitting maintenance of either bus or any breaker. In
this arrangement care has to be taken in operating disconnect switches in te proper
sequence to prevent scheme operation under load.
Ilia Voloh
05/05/2006 Page 128 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
ZON E 1
ZON E 2
Breaker-and-a-half bus scheme provides the facilities of the double main bus at a
reduction in equipment cist by using three breakers for each two circuits. However,
more complicated engineering s involved as middle breaker in each tie must be
responsive for troubles on either of its associated circuits in the correct sequence.
L1 L2
TB1
B1 B2
TB1
L3 L4
Figure J-6. Ring bus scheme
Ilia Voloh
05/05/2006 Page 129 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
An important advantage of the ring bus is that it requires the use of only one circuit
breaker per circuit into or out of the bus as illustrated in Figure J-6 above. Another
advantage is that each outgoing circuit has, in effect, two sources of supply. Scheme used
on higher transmission voltage levels.
There are different protection methods and techniques for bus relaying:
1. Interlocking schems
2. The differential circuit using simple overcurrent relay (unrestrained
differential)
3. High Impedance (voltage operated) differential relaying
4. Liner couplers
5. Low impedance percentage restrained (biased) differential relaying
Both UR series B30 and B90 relays are employing indicated per (5) above low
impedance percentage restrained differential principle. This low-impedance approach
does not require dedicated CTs, can tolerate substantial CT saturation and provides for
high-speed tripping. B30 and B90 relays perform CT ratio compensation eliminating the
need for matching CTs. Microprocessor-based relays allow for advanced algorithms
supplementing the percent differential protection function thus making the application of
the relay simpler but very secure. Advantages are following;
a) Protection of re-configurable busbars becomes easier as the dynamic bus
replica (bus image) can be accomplished without switching current secondary
circuits.
b) Integrated Breaker Fail (BF) function can provide optimal tripping strategy
depending on the actual configuration of a busbar.
c) Security is enhanced in 2 different ways: first the differential protection
function uses a double-slope double- breakpoint characteristic, secondly the
operating region of the characteristic is divided into two areas Region 1 (low
differential current) and Region 2 (high differential current with possible CT
saturation).
|ID|
differential
OPERATE
Region 2 HIGH
SLOPE
Region 1
BLOCK
LOW
SLOPE IR
PICKUP
HIGH BPNT
LOW BPNT
restraining
Ilia Voloh
05/05/2006 Page 130 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
⎛ Ip ⎞ BLOCK
imag ⎜ ⎟
⎜ ID − I p ⎟
⎝ ⎠
OPERATE
BLOCK
⎛ Ip ⎞
ID - Ip real ⎜ ⎟
⎜ ID − I p ⎟
⎝ ⎠
Ip
BLOCK OPERATE
BLOCK
Ilia Voloh
05/05/2006 Page 131 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
DIF1
AND
DIR
OR
TRIP
OR
SAT
AND
DIF2
The B30/B90 relay operates in the 2-out-of-2 mode in the first region of the
differential characteristic. Both differential and directional principles must confirm an
internal fault in order for the biased differential element to operate.
The relay operates in the dynamic 1-out-of-2 / 2-out-of-2 mode in the second region
of the differential characteristic. If the saturation detector does not detect CT
saturation, the differential protection principle alone is capable of operating the biased
differential element. If CT saturation is detected, both differential and directional
principles must confirm an internal fault in order for the biased differential element to
operate.
Because of diverse operating modes in the first and second regions of the differential
characteristic, the user gains double control over the dependability and security
issues. The first level includes slopes and breakpoints of the characteristic with regard
to the amount of the bias. The second level includes control over the split between the
first and second regions of the characteristic.
C-3 C-5
NORTH BUS
B-7
CT-6
CT-8
B-6
S-2 S-4 S-6
SOUTH BUS
To provide the bus differential zoning as shown in the figures, eight currents need to be
measured. Consequently, the protection can be accomplished either by one B90 or by two
B30s protecting separately North and South buses.
The basic CT data is presented in the table above. Below fault data and sample system
time constants are shown.
C-3 6.00 5
C-4 5.00 30
C-5 3.00 40
The magnetizing characteristics of the three different types of CTs used in this example
are shown in the following figure below.
3
10
1200:5
1000:5
600:5
2
10
Magnetizing Voltage, V
1
10
0
10
-2 -1 0 1 2 3
10 10 10 10 10 10
Magnetizing Current, A
CT-2, CT3 and CT-4 might be included or excluded in the North bus differential zone,
which is reflected by the status of the corresponding isolator S-1, S-3 and S-5.
In spite of in the example is shown just one contact input connected to the isolator
auxiliary contact, for greater security it’s recommended to use 2 breaker auxiliary
contact, one NO while another NC. Using Flexlogic, status of the breaker can be
determined more precisely and securely.
In the Figure above, there are 2 “healthy” position indications: OK (ON) and OK (OFF).
If discrepancy appears between NC and NO breaker auxiliary contacts, then last healthy
position “memorized” with a latch and conditioned with new “wrong” isolator position
will be used. Also alarm is set immediately, allowing operating personnel take preventive
measures.
The trip signal should be routed directly to the B-1, B-5 and B-7 breakers while it
should be supervised by the status of S-1, S-3 and S-5 for the B-2, B-3 and B-4
breakers, respectively.
Ilia Voloh
05/05/2006 Page 136 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
for each feeder is required. Maximum of these load currents is taken to calculate Low
Slope setting:
DIFPKP
SLOPElow = (
I min load
) • 100% + K S % (J-1)
where K S % is safety margin with recommended values of 5 to 10%
For example above, assuming pickup of 0.1pu and maximum of all feeders minimum
load currents equal to 0.7pu plus +5% of safety margin, yields following:
0.1 pu
SLOPElow = ( ) • 100% + 5% = 19%
0.7 pu
Table J-3. Limits of Linear Operations of the CTs for the sample system
Ilia Voloh
05/05/2006 Page 137 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Assuming 0.003 Ω/m lead resistance and approximating the B30/B90 input resistance
for the 5A input CTs as 0.2 VA / (5 A)2 or 0.008 Ω, the limits of the linear operation
of the CTs have been calculated and presented in the Limits of Linear Operations of
the CTs table above.
As an external fault may happen on any of the connected circuits, threatening
saturation of any of the CTs, the minimum value of the linear operation limit should be
taken as the HIGH BPNT setting. The limit of linear operation that neglects both the residual
magnetism and the effect of the DC component should be the base for setting the higher
breakpoint of the biased differential characteristic.
The B30/B90 requires the breakpoints to be entered as ‘pu’ values. The relay uses the
largest primary current of the CTs bounding the bus differential zone as a base for the pu
settings. North bus has the largest primary current of the CTs of 1200 A (CT-7 and CT-
8), thus upon configuration of the relays, 1200 A is automatically selected as base for the
pu quantities. With a given I base = 1200 A current, the limits of linear operation have been
recalculated to pu values as follows:
I max(sec ondary )
I max( pu ) =
I base
• CTratio (J-4)
The DC component in the primary current may saturate a given CT even with the AC
current below the suggested value of the higher breakpoint. The relay copes with this
threat by using the Saturation Detector and applying a 2-out-of-2 operating principle
upon detecting saturation.
The residual magnetism (remanence) left in the core of a CT can limit the linear
operation of the CT significantly. It is justified to assume that the residual flux could be
as high as 80% of the saturation level leaving only 20% to accommodate the flux
component created by the primary current. This phenomenon may be reflected by
reducing the saturation voltage in the calculations by the factor of 100% / 20%, or 5.
This, in turn, is equivalent to reducing the limit of linear operation by the factor of 5,
hence the last column in the Limits of Linear Operations of the CTs table.
For example, if the residual flux left in the core of the CT-1 is as high as 80% of its
saturation level, the CT will saturate at 17.92 A secondary, or 3.58 times its rated
current, or at 1.79 pu of the bus differential zone. The reduced limit of linear
operation should be used as the lower breakpoint of the biased differential
characteristic (the LOW BPNT setting). In this way the interval spanning from the lower
to higher breakpoints covers the indistinct area of possible saturation due to the
random factor of residual magnetism. The LOW BPNT setting should be set at 1.79 pu for
the North bus zone as this the minimum value among all feeders.
A combination of very high residual magnetism and a DC component with a long
time constant may saturate a given CT even with the AC current below the suggested
value of the lower breakpoint. The relay copes with this threat by using a 2-out-of-2
operating mode for low differential currents
Ilia Voloh
05/05/2006 Page 138 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
accommodate the spurious differential current resulting from saturation of the CTs
during heavy external faults. This requirement may be considerably relaxed in favor
of sensitivity and speed of operation as the relay detects CT saturation and upon
detection applies the directional principle to prevent maloperation. When adjusting
this setting, it must be kept in mind that the restraining signal is created as the
maximum of all the input currents.
To set the higher slope and threshold of the high set (unbiased) differential operation,
external faults must be analyzed. Consider an external fault for the North bus relay. It
is justified to assume bus configurations that give maximum stress to the maximum
number of CTs. For this purpose we will assume the tie breaker, B-7 closed; all the
circuitry capable of supplying the fault current to be in service; moreover, they are
connected to the South bus in order to analyze the CT-7 and CT-8 carrying the fault
current
By comparing the secondary currents (column 3 in the table below) with the limits of
linear operation for the CTs (column 4 in the Limits of Linear Operations of the CTs
table earlier), it is concluded that CT-1 will saturate during this fault, producing a
spurious differential signal for the North bus zone differential protection. All other
CTs will not saturate due to the AC components. The amount of the spurious
differential current (magnetizing current of CT-1) can be calculated using the burden,
magnetizing characteristic and primary current of the noted CT by solving the
following equations:
I relay = I s2 - I magnetizin
2
g (J-5)
where K S % is the safety margin with recommended values of 15% to 25%. Safety factor
accounts for additional spilled differential current due to DC offset in the current,
remanence effect, and errors in calculations.
Consequently, the slope of the characteristic should be calculated as
29.73
112.8
) • 100% + 20% = 46% and the pick up of the high set differential elements should
not be lower than 29.73 A, or 2.97 pu. Minimum allowable high slope setting is 50%.
The CTs identified as operating in the linear mode as far as the AC components are
considered may, however, saturate due to the DC components. Saturation will not occur
V > I × R × (1 + ω × T )
if sat s s dc
, where ω is radian system frequency (2πf).
If the above condition is violated, saturation will occur but not before:
( Vsat ⁄ I s R s ) – 1⎞
Ts at = – T dc × ln ⎛⎝ 1 – ---------------------------------------
-⎠
ωT dc (J-8)
Ilia Voloh
05/05/2006 Page 139 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Columns 6 and 7 of the table below summarize the DC saturation threat for the fault on
C-1. CT-4, CT-6, CT-7, and CT-8 may saturate due to the DC components and may
generate spurious differential signal for both the North bus relays depending on the bus
configuration. The saturation will not occur before 4.7 ms and will be detected by the
Saturation Detector.
The transient saturation of the CTs due to the DC component may be neglected when
setting the slopes of the characteristic as the saturation will be detected and the relay will
use the current directional principle. It must however, be taken into account when setting
the high set (unbiased) differential element
Table J-4. External Fault Calculations on the C-1 feeder on the sample bus
Same calculation should be performed for each feeder and worst case has to be
adopted to choose the setting.
Ilia Voloh
05/05/2006 Page 140 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
supplied by CT-1 will be used as the restraint signal. CT-1 is guaranteed to saturate if
the current exceeds 89.55 A secondary, or 17.9 times its rated current, or 8.96 pu of
the bus differential zone per Table J-3 above. Consequently, considering CT-1, the
value of 8.96 pu should be used as the higher breakpoint of the characteristic.
Considering CTs that could be connected (depending on the positions of the switches)
to the North bus, the HIGH BPNT for the North bus zone should be selected as the
minimum of (8.96, 9.13, 31.17, 22.88, 24.57, 31.17), or 8.96 pu.
Ilia Voloh
05/05/2006 Page 141 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Received as DIRECT
INPUTs 1 through 9
breaker auxiliary switches
(if used for BF) IED 4
sent as bits no.13, 14 and 15
IED 3
phase C current, wired to F7
BKR FAIL SUPV OP
BKR FAIL HISET OP
BF CT = F7 BKR FAIL LOSET OP
The Protection IEDs 1, 2, and 3 (B90 FUNCTION set to "Protection") send the Breaker
Fail current supervision flags over the Direct I/O communications. Assume bits 13, 14,
and 15 are used for this purpose as follows:
For IED 1:
DIRECT OUTPUT DEVICE ID: "1" (this is an originating device)
Ilia Voloh
05/05/2006 Page 142 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
Ilia Voloh
05/05/2006 Page 143 of 144 Settings recommenations R6
GE Multilin Setting Recommendations: UR series
The received flags are now to be configured for in the Breaker Failure 3 logic as follows:
BF 3 AMP SUPV OP A: "Direct Input 1 On" BF 3 AMP HISET OP A: "Direct Input 2
On" BF 3 AMP LOSET OP A: "Direct Input 3 On"
As the overcurrent supervising flags must be sent via Direct I/Os to the B90 IEDs that
perform the BF functionality, an extra delay is introduced. Consequently, the following is
recommended for coordinating the BF time margin:
Total BF Reset Time 0.7 of a power cycle 0.2 of a power cycle Direct I/O bridge count
For example, in the four-IED application example shown earlier, IED 2 is two "bridges"
away from IED 4; therefore, the Total BF Reset Time= 0.7 + 2 x 0.2 = 1.1 of a power
system cycle. Note that a message delivery time of 0.2 of a cycle per "bridge" applies
when the DIRECT I/O DATA RATE is set to 128 kbps.
Ilia Voloh
05/05/2006 Page 144 of 144 Settings recommenations R6