DAILY ACTIVITIES REPORT Poroject
DAILY ACTIVITIES REPORT Poroject
V AREA OF CONCERN
1 Area Vertical shaft Pile Cap membutuhkan tambahan equipment Jack Hammer 2 unit
2 Area Galian ACSC percepatan Rekondusi Mobil Duck untuk Shocrete and servis kompresor
3 Area Vertical shaft Pile Cap membutuhkan penambahan manpower
MERANGIN HYDROELECTRIC POWER PLANT 350 MW PROJECT
CONSTRUCTION DAILY ACTIVITIES REPORT
el 553
el 558
`
MERANGIN HYDROELECTRIC POWER PLANT 350 MW PROJECT
CONSTRUCTION DAILY ACTIVITIES REPORT
`
MERANGIN HYDROELECTRIC POWER PLANT 350 MW PROJECT
CONSTRUCTION DAILY ACTIVITIES REPORT