This document summarizes the results of an inspection of steam turbine K-210-130-8 during an overhaul in February-March 2020. The inspection found some minor issues like corrosion, scratches and damage from foreign objects. Recommendations were made to repair damaged areas, clean parts, adjust clearances and center components. The turbine was determined to be in generally good condition with these recommendations implemented.
This document summarizes the results of an inspection of steam turbine K-210-130-8 during an overhaul in February-March 2020. The inspection found some minor issues like corrosion, scratches and damage from foreign objects. Recommendations were made to repair damaged areas, clean parts, adjust clearances and center components. The turbine was determined to be in generally good condition with these recommendations implemented.
This document summarizes the results of an inspection of steam turbine K-210-130-8 during an overhaul in February-March 2020. The inspection found some minor issues like corrosion, scratches and damage from foreign objects. Recommendations were made to repair damaged areas, clean parts, adjust clearances and center components. The turbine was determined to be in generally good condition with these recommendations implemented.
This Protocol testifies that the inspection of Steam Turbine was conducted during implementation of Overhauling works in February-March, 2020.
In result of inspection the
The technical condition of the Steam Turbine, recommendations for repair and following was determined: operation.
Inspection results: 1. High-pressure cylinder.
Visual inspection of the HPC casing metal did not reveal any defects. The casing metal was cleaned and its condition was checked according to the scope of the overhauling works. The preparation and condition checking of the joint studs metal were completed. Washouts were fixed by welding and scraped, assembly tightness is ensured. The HPC horizontal connection clearances were measured at loose cover laying (in the steam inlet zone the horizontal connection clearance is up to 0.45 mm at the outside and 0.40 mm at the inside). Magnetic Particle Test and ultrasonic inspection of welded joints, heat-affected zones and HPC radial transitions were performed. No defects detected. Cleaning and ultrasonic inspection of the HPC studs have been carried out, no defects have been revealed. Disassembly, cleaning and assemble of the key system completed with taking measurements of clearances at HPC keys. No defects were revealed. Visual inspection of the guide wheels blades did not reveal any defects. It is recommended to approve for further operation. HPC front and rear end seals carriers, last stage carrier. Cleaning of scale and corrosive sediments at carriers, seals and installation ribs have been performed. The front end seals carriers have been repaired at areas having washouts on horizontal connections. Sealing segments replaced. It is recommended to ensure prescribed clearances at segments of the HPC end seals after performing the centering of these HPC flow part elements. HPC diaphragms carriers Nos. 1, 2, 3. Cleaning of scale and corrosive sediments at carriers have been performed. Washouts at horizontal connections fixed by welding and scraped. Shroud seal at Diaphragms No.1 canopy replaced. It is recommended to ensure prescribed clearance at shroud seal after performing the centering of HPC flow part. • HPC stages Nos. 2…12 diaphragms. Visual inspection of guiding blades of stages Nos. 2…12 diaphragms did not reveal any damage. Cleaning of scale and corrosive sediments at blades and diaphragms bodies have been performed. Diaphragms shroud sealings replaced. Segments of diaphragm seals have been dismantled, grooves have been cleaned, new diaphragm seals have been prepared for installation. It is recommended to perform centering of the HPC flow part elements and to ensure prescribed clearances at diaphragm seals and shroud seals segments. During the Steam Turbine start and warm-up it is required to monitor the HPR thermal expansion and not to exceed the warm-up speeds for HPR and HPC.
2. HP Rotor (See Appendix 1).
• During visual inspection of the HPR working blades, jams were found on the at governing stage (5 places) resulting of the hits by foreign objects. It is recommended to perform cutting of the damaged areas and to fulfill non-destructive inspection tests. • Inspection of the HPR axial channel has been carried out, no defects have been revealed. • Working blades of 9,10,11,12 stages have traces of stand-idle corrosion. It is recommended to clean the corrosive areas. • Visual inspection of the HPR journal revealed the ring grooves up to 0.02 mm deep and grooves in the area of oil-protective rings. It is recommended to grind and polish the HPR journal, places of oil- protective rings installation. To clean the Turbine oil system, to adjust the prescribed clearances at the oil-protective rings of Bearing No.1. • Assembly of HPR-IPR half-couplings to be carried out ensuring the elongation of the connecting bolts on the HPR-IPR half-coupling (0.15-0.17 mm) and the pendulum check of the HPR front end (up to 0.10-0.15mm). 3. Intermediate Pressure Cylinder. • Visual inspection of the IPC casing metal did not reveal any defects. The casing metal was cleaned and its condition was checked according to the scope of the overhauling works. Magnetic Particle Test and ultrasonic inspection of welded joints, heat-affected zones and IPC radial transitions were performed. No defects were found. • Cleaning and ultrasonic inspection of the IPC studs have been carried out, no defects have been revealed. • Disassembly, cleaning and assemble of the IPC key system completed with taking measurements of clearances at IPC keys. No defects were revealed. • Visual inspection of the guide wheels blades did not reveal any defects. It is recommended to approve for further operation. • IPC front and rear end seals carriers, IPC last stage carrier. Cleaning of scale and corrosive sediments at carriers, sealings grooves and installation ribs have been performed. While performing centering of the flow part, warping of Diaphragms Nos. 1, 2 and of the front end sealing last stage carrier, opening of the horizontal connection at the left and right side of the rotor up to 4 mm have been detected. It is recommended to perform scraping of horizontal connection before the final closing. To replace segments of end seals with ensuring of prescribed clearances at segments of the IPC end seals after performing of these IPC flow part elements centering. • IPC diaphragms carriers. Cleaning of scale and corrosive sediments at carriers, sealings grooves and installation ribs have been performed. The front end seals carriers have been repaired at areas having washouts on horizontal connections. • Diaphragms of IPC Stages Nos. 14, 15, 16, 17, 18, 19, 20, 21, 22, 23. Visual inspection of guiding blades of stages Nos. 14…23 diaphragms did not reveal any damage. Cleaning of scale and corrosive sediments at blades and diaphragms bodies have been performed. Segments of diaphragm seals have been dismantled, grooves have been cleaned, new diaphragm seals sets have been prepared for installation. Diaphragms sealings segments are being replaced. It is recommended to perform centering of the IPC flow part elements and to ensure prescribed clearances at diaphragm seals and shroud seals segments.
4. Intermediate Pressure Rotor (See Appendix 2).
• During visual inspection of the IPR Stages Nos. 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23 working blades, no defects or damages were found. At IPR Stages Nos. 18, 19, 20, 21, 22, 23 working blades cleaning of stand-idle corrosion areas was performed, after cleaning no defects were found. • Visual inspection of the Bearings Nos.2,3 journals revealed the ring grooves up to 0.05 mm deep. Grooves up to 0.50 mm deep found in the areas of installation of oil-protective rings. It is recommended to grind and polish the IPR journals and places of oil-protective rings installation. To clean the Turbine oil system, to adjust the prescribed clearances at the oil-protective rings of Bearings Nos.2,3. To perform HPR-IPR centering at half-couplings reaching the prescribed values, to adjust HPR-IPR misalignment reaching the prescribed values. • Visual inspection examination of the IPR thrust rib revealed ring grooves up to 0.05 mm deep on both sides of the rib. It is recommended to grind and polish of both sides of the IPR thrust rib. • Tearings were detected in the fit bolts holes at IPR half-coupling from HPR side. Holes for fit bolts installation to be polished up to acceptable surface roughness level. Fit bolts should be made of the allowed size (clearance 0.02 mm). • Tearings were detected in the fit bolts holes at IPR half-coupling from LPR side. Holes for fit bolts installation to be polished up to acceptable surface roughness level. Fit bolts should be made of the allowed size (clearance 0.02 mm).
5. Low Pressure Cylinder (see Appendix 3).
• Visual inspection of the LPC casing metal did not reveal any defects. Cleaning of LPC horizontal connection and places for flow part elements installation was performed. No defects were found. • Cleaning and visual inspection of LPC fastening has been carried out. No defects were found. • Inspection of IPC-LPC receiver pipes has been carried out. It is recommended to replace/repair damaged fasteners and replace gaskets. • LPC atmospheric dump valves have been inspected. It is recommended to perform repacking of atmospheric valves with replacement of gaskets, to replace/repair damaged fasteners. • Visual inspection of end sealings carriers and LPC last stage carriers has been performed. The leakage of horizontal connections, steaming through seals during the turbine operation have been revealed. Radial clearances at the sealings nibs exceed the prescribed values (up to 1.5 mm). It is recommended to repair horizontal connections of the LPC end sealings carriers, to replace the sealings segments and to ensure prescribed clearances for the end sealings. • LPC Stages Nos. 24, 25, 26, 27, 28 & 29 Diaphragms. Cleaning of corrosive at diaphragm blades and bodies. At the lower half of the Diaphragm No.29 the guide key (right side) and the top of the oblique surface of the Diaphragm casing (left side) are broken off. Segments of diaphragm seals have been dismantled, grooves have been cleaned, new diaphragm seals sets have been prepared for installation. It is recommended to replace the guide key of the Diaphragm No.29, to ensure prescribed clearances at diaphragm seals segments.
6. Low Pressure Rotor (see Appendix 3).
• During visual inspection of the Stages Nos. 24, 25, 26, 27, 28 working blades no defects or damages were found. Blades cleaning of plaque and stand-idle corrosion was performed. To perform IPR-LPR centering at half-couplings reaching the prescribed values, to adjust IPR-LPR pairing misalignment reaching the prescribed values. • During visual inspection of the Stages No. 29 damages of leading edges of blades nos. 6, 13, 29, 33, 34, 36, 40, 43, 48, 49, 52, 55, 56, 59, 61, 65, 67, 69, 71, 72, 81 & 87 were found, also some stellite plates are missing, there are damages in the shape of ragged jams from 3 mm to 60 mm long, from 1 mm to 10 mm deep. The leading edges of the blades No. 61 and No. 65 are deformed at areas of 10- 15 mm long. It is recommended to replace the working blades of LPR Stage No. 29. • Tearings were detected in the fit bolts holes at LPR half-coupling from IPR side. Holes for fit bolts installation to be polished up to acceptable surface roughness level. Fit bolts should be made of the allowed size (clearance 0.02 mm). • Tearings were detected in the fit bolts holes at LPR half-coupling from Generator Rotor side. Holes for fit bolts installation to be polished up to acceptable surface roughness level. Fit bolts should be made of the allowed size (clearance 0.02 mm). • LPR Bearings Nos.4,5 journals. Visual inspection of LPR Bearings Nos. 4,5 journals revealed the ring grooves up to 0.02 mm deep. Grooves up to 0.50 mm deep found in the areas of installation of oil- protective rings. It is recommended to grind and polish the ДPR journals and places of oil-protective rings installation. To clean the Turbine oil system, to adjust the prescribed clearances at the oil-protective rings of Bearings Nos.4,5. To perform IPR-LPR, LPR-GR centering at half- couplings reaching the prescribed values, to adjust IPR-LPR, LPR- GR pairings misalignment reaching the prescribed values • No defects were found during visual inspection of the shaft-turning gear wheel.
7. Steam turbine slide bearings.
• Front bearing. Visual inspection revealed that the rotor saddle of the bearing bushing bottom half is smooth, of normal dimensions. Separation of babbit filling from the bushing body has not been revealed. At the bushing upper half there are no traces of the shaft contact, edges of the oil channel are straight, no chippings were found. The condition of the bushing installation pads and their seats is satisfactory. • Bearing No.2. Thickness of babbit filling at bearing area is 5.00 mm. Scraping of the bushing bearing area has been performed to restore the rotor saddle. Quality of babbit filling contact was inspected by kerosene sample testing. Defective sections of the bearing bushing babbit filling (2 areas – 20*10 mm and 20*20 mm) were cut out to determine the quality of the remaining filling contact. Local babbit refilling, scraping and contact check were performed. Checking of contact and scraping of the bushing spherical surface against the bearing housing (contact on paint at least 75%), as well as for installation pads and their seats (at least 70%). Inspection of support pads performed. Inspection of the working and installation pads of the thrust bearing No.2 has been carried out, have been replaced with new ones. The rotor oil run has been restored to prescribed values. • Bearing No.3. Visual inspection revealed no defects of the babbit filling, rotor saddle is smooth, of normal dimensions, separation of babbit filling from the bushing body has not been revealed. Visual inspection of the bushing upper half showed no defects of the babbit filling, no traces of the shaft contact, edges of the oil channel are straight without chippings. The condition of the bushing installation pads and their seats is satisfactory. Quality of babbit filling contact was inspected by kerosene sample testing. The bushing babbit filling boring to be scraped as per gage or to be processed with machine with the removal of a minimum layer of metal. Checking and repair of thrust pads and their seats performed (contact on paint at least 70%). • Bearing No.4. Visual inspection revealed that at the lower half of bushing babbit boring the rotor saddle is slightly increased (sector- 40°). Scraping and lower half babbit filling surface positioning as per gage was performed. Separation of babbit filling from the bushing body has not been revealed. Visual inspection of bushing upper half revealed no defects of the babbit filling, no traces of the shaft contact, edges of the oil channel are straight without chippings. The condition of the bushing installation pads and their seats is satisfactory. Quality of babbit filling contact was inspected by kerosene sample testing. The bushing babbit filling boring to be scraped as per gage or to be processed with machine with the removal of a minimum layer of metal. Checking and repair of thrust pads and their seats performed (contact on paint at least 70%). • Bearing No.5. Visual inspection revealed that at the lower half of bushing babbit boring the rotor saddle is slightly increased. Scraping and lower half babbit filling surface positioning as per gage was performed. Separation of babbit filling from the bushing body has not been revealed. Visual inspection of bushing upper half revealed no defects of the babbit filling, no traces of the shaft contact, edges of the oil channel are straight without chippings. The condition of the bushing installation pads and their seats is satisfactory. Quality of babbit filling contact was inspected by kerosene sample testing. The bushing babbit filling boring to be scraped as per gage or to be processed with machine with the removal of a minimum layer of metal. Checking and repair of thrust pads and their seats performed (contact on paint at least 70%). • Oil-protective rings of Bearings Nos.1-5. The clearances at oil shields ribs Nos.1-7 of bearings housings are increased up to 0.5mm as a result of wearing. It is recommended to replace the defective ones, to bring clearances at oil-protective rings of Bearings Nos.1-5 to prescribed values, to inspect the fastening, to scrape the connections.
8. Steam distribution units.
• Stop valves (HPC automatic shutter valves). The working surfaces of the valves and the seats have been cleaned. Steam boxes of valves are cleaned for metal inspection according to works scope, defects have not been identified. Disassembly and repair completed with replacement of worn and damaged parts. The valves are fitted to the seats (contact 100%). The steam strainers are cleaned. Measurements of lift and clearances completed according to regulations. • HPC automatic shutter valves servomotors. The oil chambers cleaned of sludge and coking oil. Piston drive stem of right Stop Valve repaired – replacement of the upper thread part. Internal spring of servodrive, two piston rings, shock absorbers spring washers of both valves have been replaced. Measurements of lift and clearances completed according to regulations. • HPC Governing valves. The working surfaces of the valves and the seats have been cleaned. Steam boxes of valves are cleaned, metal inspection completed as per works scope. The valves are fitted to the seats (contact 100%). The steam strainers are cleaned. Measurements of lift and clearances completed according to regulations. • HPC Governing valves Nos.1-4 carriers. The working surfaces of the carriers and valve frames have been cleaned of scale. Repair completed. • HPC Cam distribution device, valves racks and rods. The jammed pin was dismantled with replacement of the pin and needle bearings. The geometry of the rack work surfaces has been restored by welding followed by a paint fit. The gear wheel pitch is eliminated by key welding and following fitting. Cam shafts with valve cams replaced with new ones. • Safety valves (IPC automatic shutter valves). The working surfaces of the valves and the seats have been cleaned. Steam boxes of valves are cleaned, metal inspection completed as per works scope. The valves are fitted to the seats (contact 100%). The steam strainers are cleaned. Measurements of lift and clearances completed according to regulations. • IPC Governing valves Nos.1-4. The working surfaces of the valves and the seats have been cleaned of scale and sediments. Steam boxes of valves are cleaned, metal inspection completed as per works scope. Inspection of cover flanges working connections and replacement of worn fasteners completed. The valves are fitted to the seats (contact 100%). The steam strainers are cleaned. Measurements of lift and clearances completed according to regulations. • IPC Governing valves Nos.1-4 carriers. The working surfaces of the carriers and valve frames have been cleaned of scale. Repair completed. • IPC Cam distribution device, valves racks and rods. The jammed pin was dismantled with replacement of the pin and needle bearings. The geometry of the rack work surfaces has been restored by welding followed by a paint fit. The gear wheel pitch is eliminated by key welding and following fitting. Defective bearings replaced. Cam shafts with valve cams replaced with new ones. • Servomotor (main) of HPC, IPC Governing valves. Standard repair, cleaning completed. Casing and flanges gaskets replaced. Slide valve HPR Inspection.
Bearing No.1 Journal.
HPR Governing stage Oil-protection rings installation position from Bearing No.2 side Stand-idle corrosion of working blades of HPR Stages Nos. 9,10,11,12 Intermediate Pressure Rotor.
Bearing No.2 Journal surface.
Bearing No.3 Journal surface. Thrust rib from Governing side. Thrust rib from Generator side. Low Pressure Rotor.