IN COMMISSIONING AREA
Document No. :70150-2505-JEL-TR-MS-051
Contract No.: 70150-2505
Comments:
WORK METHOD STATEMENT
FOR WORKING IN COMMISSIONING AREA
Page 1 of 6
CONTENTS
1.0 PURPOSE 2
2.0 SCOPE 2
3.0 DEFENITIONS 2
4.0 REFERENCES 4
5.0 RESPONSIBLITIES 4
9.0 ATTACHMENTS 6
WORK METHOD STATEMENT
FOR WORKING IN COMMISSIONING AREA
Page 2 of 6
1. PURPOSE:
The purpose of this method of statement is to make sure that working in commissioning area
which is done safely as per applicable standards. This document describes the methods and
details, procedure and work sequence for.
3. DEFINITIONS
OWNER (CLIENT):
CONTRACTOR:
PROJECT:
SUBCONTRACTOR).
Calibration Comparison of a measurement and test equipment with a reference standard
or with another one provided with better tolerance in order to detect or to measure possible
inaccuracies and to document or eliminate them.
Control Forms Record that establishes the control and checkpoints to be done by the
PARTNER team (Construction Supervision, Quality and/or Pre-commissioning/
Commissioning team), Subcontractors and the OWNER if required. The proper execution
of the Work is proved by the Control Form signed by the parts involved in the process
and mentioned in the Form.
Document This term shall be used to identify any document produced by the
SUBCONTRACTOR in relation to the Subcontract, such as: drawings, specifications,
standards, schemes, inspection and test plans/procedures, test results, reports, etc.
Handover Control System (HCS): It is the software developed by PARTNER used to
monitor the Pre-commissioning, Commissioning activities and the Punch Lists to assure
the correct transference of Operating Subsystems/Systems. This software will be also
used to control some of the activities developed prior the transference of Subsystems,
activities such as the Test Packages and its related Control Forms.
Hold Point (H) Observe all of the production/activities or tests. Advanced written
notification shall be provided to the PARTNER. Fabrication or activity shall not proceed
until hold point inspection has been approved by PARTNER Authorized Inspector.
Inspection Is an activity such as measuring, examining, testing or gauging one or more
characteristics of an entity and comparing the results with specified requirements in order
to establish whether conformity is achieved for each characteristic.
Inspection Waiver Written confirmation if the PARTNER elects not to visit the
SUBCONTRACTOR to perform an inspection activity.
ITP Inspection and Test Plan/Procedure prepared in accordance with the corresponding
and applicable contractual, engineering and vendors requirements. The ITP shall provide
references to applicable procedures, documentation, quality records and inspection
attendance to be performed, in chronological order, from initial inspection, throughout
final inspections and mechanical completion. Non-Conformance Report (NCR)
OWNER, CONTRACTOR, PARTNER or SUBCONTRACTOR
document that highlights any non-conformance discovered during the execution of the
subcontract.
Non-Conformance The non-fulfilment of specified requirements.
WORK METHOD STATEMENT
FOR WORKING IN COMMISSIONING AREA
Page 3 of 6
Witness Point An inspection activity that requires the PARTNER, CONTRACTOR and
OWNER inspector to be notified by the SUBCONTRACTOR of a specific time and
place for the activity to be witnessed. The activity will commence with or without the
presence of the inspector.
Work Means all the works and services and other obligations to be
carried out by SUBCONTRACTOR under the Subcontract.
WORK Site Means all location at which SUBCONTRACTOR performs any portion of
the WORK. Any other terms related to quality and not listed above shall conform to
section 3 “Term and Definition” of ISO 9000:2015 “Quality Management System –
Fundamentals and vocabulary.
4. REFERENCES:
5. RESPONSIBILITES:
Project Manager: Dealing with the Client/Authorities and site supervisor to follow up
progress reports and project time schedule and quality of all the site activities and to
watch and follow all the site activities along with site supervisor dealing with the site
foreman and other subcontractors at site
Safety Officer: Follow up site activities as to be progressed in safely. Report to Site
Supervisor & Project Manager.
Site Supervisor: Follow up all the site activities which shall be carried out according to
approved drawings and quality of used materials and prepare a daily report against to
project manager. Dealing with the suppliers.
QA/QC engineer shall be responsible for ensuring that execution of works are
complying with approved method statement specification approved and ensure ITP are
submitted.
QA/QC Engineers must ensure before starting any inspection, control, trials, tests etc.
that QC protocol are on field as well as all needed tools and devices (duly calibrated a
calibration certificate copy must be with the tools /devices at field).
QA/QC Engineers must ensure that all QC protocols have been filled and signed
(involved parts) on field just after finishing inspections, control, test, trials, etc.
QA/QC must ensure that method statement is at site where the works are going on.
WORK METHOD STATEMENT
FOR WORKING IN COMMISSIONING AREA
Page 5 of 6
6. PROCEDURE:
In order to ensure that all hydro static testing water pipe works to take s place in a safer manner
the following shall be considered.
Spot safety meeting will be done by competent engineer to the working group
Fitting, thread and connections will be checking up for broken on unthreaded parts.
To make sure everyone in testing area knows that the pressure test will be done and
proper tags to be displayed.
Ensure that all pipes are fastened properly
Warning signs will display in both English and local language.
Valves operation to be understood by operator before pressure test starts.
Restrict the access for common people to the testing area, use communication system for
announcements etc.
Only authorised persons are allowed to check the pipes during the pressure in progress
After test is complete the pressure should be released slowly and open all valves one the
pressure is zero, to ensure that there is no pressure trapped anywhere in the system.
All the testing workers must have pressure test training.
Pressurizing hose should be tied off in case of a break
All trenches should have a proper access.
During the test, any section can be subject on impact forces.
9. ATTACHMENTS: