Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

WORK METHOD STATEMENT FOR

CONCRETE REPAIR WORKS

SIGNATURE NAME DATE


Comments:
METHOD STATEMENT FOR
CONCRETE REPAIR WORKS
Page 1 of 5

CONTENTS

SL. NO DESCRIPTION PAGE NO.

1.0 PURPOSE 2

2.0 SCOPE OF WORK 2

3.0 DEFENITION 2

4.0 REFERENCES 2

5.0 RESPONSIBILITY 3

6.0 SAFETY 2

7.0 TOOLS AND EQUIPMENTS 3

5.0 METHOD OF EXECUTION 2

6.0 INSPECTION 3

7.0 ATTACHMENTS 3
METHOD STATEMENT FOR
CONCRETE REPAIR WORKS
Page 2 of 5

1. PURPOSE:
THE METHOD OF statements describes the procedure to be followed during concrete
repair of substructure and superstructures for the

2. SCOPE OF WORK:
This shall covers all the repair works that will come across during execution of job
related to concrete such as honey combs, blow holes, tie-rod holes, cracks, voids and
other surface defects and larger repairs.

3. DEFINITIONS
CONTRACTOR:
PROJECT:
SUBCONTRACTOR :
Calibration Comparison of a measurement and test equipment with a reference standard
or with another one provided with better tolerance in order to detect or to measure possible
inaccuracies and to document or eliminate them.
Control Forms Record that establishes the control and checkpoints to be done by the
PARTNER team (Construction Supervision, Quality and/or Pre-commissioning/
Commissioning team), Subcontractors and the OWNER if required. The proper execution
of the Work is proved by the Control Form signed by the parts involved in the process
and mentioned in the Form.
Document This term shall be used to identify any document produced by the
SUBCONTRACTOR in relation to the Subcontract, such as: drawings, specifications,
standards, schemes, inspection and test plans/procedures, test results, reports, etc.
Handover Control System (HCS): It is the software developed by PARTNER used to
monitor the Pre-commissioning, Commissioning activities and the Punch Lists to assure
the correct transference of Operating Subsystems/Systems. This software will be also
used to control some of the activities developed prior the transference of Subsystems,
activities such as the Test Packages and its related Control Forms.
Hold Point (H) Observe all of the production/activities or tests. Advanced written
notification shall be provided to the PARTNER. Fabrication or activity shall not proceed
until hold point inspection has been approved by PARTNER Authorized Inspector.
Inspection Is an activity such as measuring, examining, testing or gauging one or more
characteristics of an entity and comparing the results with specified requirements in order
to establish whether conformity is achieved for each characteristic.
Inspection Waiver Written confirmation if the PARTNER elects not to visit the
SUBCONTRACTOR to perform an inspection activity.
ITP Inspection and Test Plan/Procedure prepared in accordance with the corresponding
and applicable contractual, engineering and vendors requirements. The ITP shall provide
references to applicable procedures,, documentation, quality records and inspection
attendance to be performed, in chronological order, from initial inspection, throughout
final inspections and mechanical completion. Non Conformance Report (NCR)
OWNER, CONTRACTOR, PARTNER or SUBCONTRACTOR
METHOD STATEMENT FOR
CONCRETE REPAIR WORKS
Page 3 of 5

document that highlights any non-conformance discovered during the execution of the
subcontract.
Non Conformance The non-fulfilment of specified requirements.
Non-Destructive Testing (NDT) Non-destructive tests or non-destructive essays.
QA Quality Assurance: Part of quality management focused on providing
confidence that quality requirements will be fulfilled.
Quality Assessment Generally replaces the term 'Quality Audit'. A systematic and
independent examination to determine whether quality activities and related results
comply with planned arrangements and whether these arrangements are implemented
effectively and are suitable to achieve objectives.
QC Quality Control: Part of quality management focused on fulfilling quality requirements.
QMS Means Quality Management System. Part of the organization’s management
system, procedures, process and resources, that focuses on achievement of results, in
relation to the quality objectives, to satisfy the needs, expectations and requirements
of PARTNER and of any other interested parties, as appropriate.
Quality Manual Is a document setting out the SUBCONTRACTOR´s quality
policies, systems, procedures and practices and including a listing of procedures.
Quality Plan Is the SUBCONTRACTOR document specifying which procedures
and associated resources shall be applied by whom and when during the execution
of the Subcontract.
Quality Record Book or Final Quality Dossier A compilation of documents which
provide a record of Quality checks performed by the SUBCONTRACTOR under the
scope of the Subcontract.
Quality Surveillance Is the continual monitoring and verification of the status of
an entity and analysis of records to ensure that specified requirements are being
met.
RFI Request for Inspection: Document that is issued by the SUBCONTRACTOR to
PARTNER and PARTNER in turn to the OWNER for notification and subsequent
confirmation of inspections and tests requiring in accordance with the ITP approved by
PARTNER, CONTRACTOR and OWNER. Shall "Shall" expresses a provision that is
binding between two or more parties.
Should " Should" expresses a recommendation among other possibilities
SQP Site Quality Plan: Narrative detail of how the Subcontractor address the
individual elements of ISO 9001:2015 which are applicable for the execution of the
specific contractual scope of work.
Subcontract Means any tier of contract for the performance of any portion of the
Work entered into by a Subcontractor.
Subcontractor Procedures Technical and specific Construction Procedures in
accordance with the requirements of their Subcontract, which are developed by the
SUBCONTRACTOR for PARTNER approval. ITPs are included in the scope of
Subcontractor Procedures.
Test Packages Package of documents required to carry out an inspection or a test. It
shall contain at least: Cover, Index, Engineering Documents and Control Forms.
Third Party Inspection (TPI) Third Party Inspection: any organization, authority,
person or persons, to which Subcontractor has subcontracted the execution of inspection
and or laboratory testing, related activities.
METHOD STATEMENT FOR
CONCRETE REPAIR WORKS
Page 4 of 5

Type Test :Test or series of tests directed towards approval of a design conducted to
determine that is capable of meeting the requirements of the product specifications
Will "Will" expresses a declaration of purpose or intent by one party.
Witness Point An inspection activity that requires the PARTNER, CONTRACTOR and
OWNER inspector to be notified by the SUBCONTRACTOR of a specific time and
place for the activity to be witnessed. The activity will commence with or without the
presence of the inspector.
Work Means all the works and services and other obligations to be
carried out by SUBCONTRACTOR under the Subcontract.
WORK Site Means all location at which SUBCONTRACTOR performs any portion of
the WORK. Any other terms related to quality and not listed above shall conform to
section 3 “Term and Definition” of ISO 9000:2015 “Quality Management System –
Fundamentals and vocabulary

4. REFERENCE STANDARD:
 ACI 224 – Control of cracking in concrete
 ACI 546 – Guide to concrete repair
 ACI 117-10 -Specification for tolerances for concrete construction and material
 ACI 301-16 – specification for structural material

4.1 OTHER REFERENCES:

5. RESPONSIBILITES:

 Project Manager: Dealing with the Client/Authorities and site supervisor to follow up
progress reports and project time schedule and quality of all the site activities and to
watch and follow all the site activities along with site supervisor dealing with the site
foreman and other subcontractors at site
 Safety Officer: Follow up site activities as to be progressed in safely. Report to Site
Supervisor & Project Manager.
 Site Supervisor: Follow up all the site activities which shall be carried out according to
approved drawings and quality of used materials and prepare a daily report against to
project manager. Dealing with the suppliers.
 QA/QC engineer shall be responsible for ensuring that execution of works are
complying with approved method statement specification approved and ensure ITPs are
submitted .
 QA/QC Engineers must ensure before starting any inspection,control,trials ,tests etc that
QC protocol are on field as well as all needed tools and devices (duly calibrated a
calibration certificate copy must be with the tools /devices at field ).
 QA/QC Engineers must ensure that all QC protocols have been filled and signed
(involved parts) on field just after finishing inspections, control, test, trials, etc.
 QA/QC must ensure that method statement is at site where the works are going on.
METHOD STATEMENT FOR
CONCRETE REPAIR WORKS
Page 5 of 5

6. SAFETY:
 All activities shall be in accordance with approved TR safety procedures.
 Personal protective equipment shall be worn by all personal involved in the preparation
activities in this document.

7. METHOD OF EXECUTION:
5.1 Damaged areas shall be identified and clearly marked.
5.2 Holes left for form works supports shall be thoroughly cleaned out to remove all
loose material and the sides be roughened to ensure a satisfactory bond with the repair
mortar.
5.3 Pinholes bubbles, surface discoloration and minor defects shall be rubbed down with
sacking immediately after the form work is removed.
5.4 Cut back using mechanical cutter or grinding machine around the edge of the repair
mortar with a depth of 10mm to avoid feather-edging.
5.5 break out or remove loose concrete by chisel and hammer exposing rear face of any
steel uncovered.
5.6 steel bars must be cleaned to bright condition (special attention to rear faces) by steel
brushing.
5.7 forms shall be prepared strong, properly braced and oiled. If necessary, hole in the
form shall be provided as relief holes during pouring.
5.8 Remove all loose debris and dust by air compressor.
5.9 Thoroughly soak with clean water and remove any excess.
5.10 Fosroc Renderoc FC shall be used as the repair mortar with a depth of repair less
than 3mm.
5.11 Fosroc Renderoc HS Extra shall be used as the repair mortar with a thickness of
repair more than 3mm.
5.12 mixing and application of the mortar shall be as per manufacturer instruction
provided in the product data sheet.
5.13 Cutting shall be done as soon as the sheen of water disappears and the mortar has
begun to stiffen. The surface shall be continuously wet with water and covered with
burlap and plastic sheet.

8.0 INSPECTION:
6.1 work execution inspection shall be monitored witnessed and recorded.
6.2 Request for Inspection shall be issued to inspect any completed works for final
acceptance.

9.0 ATTACHEMNTS:

You might also like