Professional Documents
Culture Documents
PM Gray Chapter 7 PERT Appendix Ex 7.1 - 7.2
PM Gray Chapter 7 PERT Appendix Ex 7.1 - 7.2
Given the project information below, what is the probability of completing the National
Holiday Toy project in 93 time units?
Act. Description Prede Optm. Most Pess. Act time Variance Critical
ID cessor (a) Likely (m) (b) te [(b - a)/ 6]2
1 Design package None 6 12 24 13 9 x
2 Design product 1 16 19 28 20 4 x
3 Build package 1 4 7 10 7 1
4 Secure patent 2 21 30 39 30 9 x
5 Build product 2 17 29 47 30 25 x
6 Paint 3, 4, 5 4 7 10 7 1 x
7 Test market 6 13 16 19 16 1 x
TS TE 93 86 7 7
1.00 P = .841
t
2 9 4 9 25 1 1 49 7
E
4
2
5 6 7
1
3
1– 2 – 4 – 6 – 7 13+20+30+7+16 = 86
1– 2 -5 -6- 7 13 + 20+ 30+7 +16 = 86
1- 3- 6 - 7 13+7+7+16 = 43
4. What is the probability of completing the project by day 112? Within 116 days?
Note:
It is interesting to see the Monte Carlo results of the Consolidation Project when it is
simulated 200 times using a triangular distribution to represent the activity distributions.
The average simulated project duration for each path (e.g.,118.7) demonstrates the impact of
merge bias from the manual computed method that yielded a duration of 114 time units. The
fact that two paths, other than the critical path, have probabilities of .200 and .270
respectively, suggests there is at least a good chance one could become critical. if they have
a serious delay. The simulated results allow more for objective assessment of scheduling
risk.
Appendix Case
International Capital, Inc.—Part A
Time in Workdays
Activity Optimistic Most likely Pessimistic te Variance
A 4 7 10 7 1
B 2 4 8 4 1
C 2 5 8 5 1
D 16 19 28 20 4
E 6 9 24 11 9
F 1 7 13 7 4
G 4 10 28 12 16
H 2 5 14 6 4
I 5 8 17 9 4
J 2 5 8 5 1
K 17 29 45 30 22
It is possible to compress the project to reach about a 95% chance of hitting the average.
This would require compression down to 61 days from the current plan of 73 days. See
below.
Z = (TS – TE) / Sq. root of sum of variance along Critical Path (s)
Getting to the average of 70 days and upping the chance of making it would require
compressing the project. Compressing to 61 days will improve the chance of meeting the
95% confidence level (but probably increase the risk and lower the real chance of 95
percent).
OR