Professional Documents
Culture Documents
02 Contracts
02 Contracts
Suranga Jayasena
1 2
3 4
Simplest maybe to look at design and build Looks at how reward (payment) is paid to the
responsibilities, i.e. classification by contractor by the client.
responsibility. ◦ >> What is agreed at the time of contract.
◦ A design contract
◦ A building/construction contract Broadly, either
◦ A design and build contract ◦ Price Based, or
This classification may not be deep enough ◦ Cost Based
for our purposes
5 6
by Suranga Jayasena 1
BSc (Hons) QS/FM
7 8
Agree for a mechanism to arrive at final sum Most effective when works are substantially
based on actual quantities of work done. designed but final details not yet completed.
Price certainty only at the end of Client can shorten overall programme at the
performance. expense of price certainty.
Higher price risk compared to lump sum. Fair Price ...?
Some, are “re-measurement” contracts.
9 10
Agreed for mechanism for final price Known as Cost Reimbursement Contracts
Price = Costs + Agreed Allowance Used When not appropriate to measure even
Costs approximate quantities: scope not clear, risk
◦ Actual costs (prime cost) incurred by the contractor unreasonable to price, etc.
in performing the contract >> labour, plant, ◦ Risk >>> Profit Margin
material, fuel, etc. Examples: emergency building repair after
Allowance fire, Civil Engineering work under water.
◦ A fee: which needs to be agreed.
11 12
by Suranga Jayasena 2
BSc (Hons) QS/FM
13 14
15 16
Each bidder quantifies for pricing >> Price based on employers brief and user
wasteful requirements (documented as a performance
Difficult to evaluate bid prices spec)
Design needs to be fully completed for Within the parameters laid down, contractor
signing of the contract chooses methods, materials and the design
Variations might become problematic to value (often)
Flexibility to the contractor
Defined performance to be achieved
17 18
by Suranga Jayasena 3
BSc (Hons) QS/FM
19 20
21 22
Bid can be compared on bid sum alone Used when not possible to measure work
Widely used, suits projects of any size accurately
Price certainty comparatively less than
Lot of time on design and bill preparation previous
Risk of quantity errors in BQ is with bidder Entire work re-measured on completion
◦ Bidder to rate strategically Only Unit Rates form part of contract
◦ May cause problems in variations pricing Quantities ...?
23 24
by Suranga Jayasena 4
BSc (Hons) QS/FM
Less pressure to fully complete the design Decision on type of contract, conditions of
contract and contract documentation
Signing of contract before finalizing the
design Selection of the contractor
Lesser overall time Establishment of contract price (or how the
price will be arrived at)
No risk to bidder on quantity errors in the bill
(what if for large deviations)
Extra expense (time/money) on bill of firm
quantities avoided >> but, what about
remeasuring
25 26
Thank You
27
by Suranga Jayasena 5