Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

BSc (Hons) QS/FM

 ...is a legally binding agreement (usually)


between two parties.
 Usually a written (& sometimes not)
 All agreements are not contracts
 Test
◦ Offer and acceptance
◦ Intention to create legal relationship
 All contracts are agreements

Suranga Jayasena
1 2

 It is about what is agreed by the parties.


 Rather than what they are, we may also look
Contract defines how they are defined.
◦ Rights and  Contract defines
◦ Obligations ◦ What is to be designed
 of parties under the agreement. ◦ What is to be built and
◦ How much to be paid
 Client’s right: to get the project done.  How these are defined maybe used to classify
 Contractor’s right: to get paid the contracts

3 4

 Simplest maybe to look at design and build  Looks at how reward (payment) is paid to the
responsibilities, i.e. classification by contractor by the client.
responsibility. ◦ >> What is agreed at the time of contract.

◦ A design contract
◦ A building/construction contract  Broadly, either
◦ A design and build contract ◦ Price Based, or
 This classification may not be deep enough ◦ Cost Based
for our purposes

5 6

by Suranga Jayasena 1
BSc (Hons) QS/FM

 Broadly Two  Contract Sum (for the total contract) is agreed


at signing of the contract.
◦ Lump Sum Contracts  Appropriate for most of contracts.
 Client has the maximum price certainty
◦ Measurement Contracts before contractor starts performing.

7 8

 Agree for a mechanism to arrive at final sum  Most effective when works are substantially
based on actual quantities of work done. designed but final details not yet completed.
 Price certainty only at the end of  Client can shorten overall programme at the
performance. expense of price certainty.
 Higher price risk compared to lump sum.  Fair Price ...?
 Some, are “re-measurement” contracts.

9 10

 Agreed for mechanism for final price  Known as Cost Reimbursement Contracts
 Price = Costs + Agreed Allowance  Used When not appropriate to measure even
 Costs approximate quantities: scope not clear, risk
◦ Actual costs (prime cost) incurred by the contractor unreasonable to price, etc.
in performing the contract >> labour, plant, ◦ Risk >>> Profit Margin
material, fuel, etc.  Examples: emergency building repair after
 Allowance fire, Civil Engineering work under water.
◦ A fee: which needs to be agreed.

11 12

by Suranga Jayasena 2
BSc (Hons) QS/FM

 Provide for great flexibility for change  Cost + Percentage Fee


◦ Programme, scope, quantity of works, etc.
 Price risk to contractor is low; to client high  Cost + Fixed Fee
 Weakness in lack of incentive for contractor
minimize his “prime cost”  Cost + Fluctuating Fee
 Few variants depending on the way the fee is
applied.
 Target Cost Reimbursement Contract

13 14

 Drawings and Specification


 Performance Specification  Simplest type
 Schedule of Rates  Complete drawings and full specifications
 Schedule of Prices  Comprises of large amount of tender
 Bills of Firm Quantities information
 Bills of Approximate Quantities  Most pricing risk to the contractor
 Tendency to overprice due to above
 Known to be used with lump sum price (and
no BoQ)

15 16

 Each bidder quantifies for pricing >>  Price based on employers brief and user
wasteful requirements (documented as a performance
 Difficult to evaluate bid prices spec)
 Design needs to be fully completed for  Within the parameters laid down, contractor
signing of the contract chooses methods, materials and the design
 Variations might become problematic to value (often)
 Flexibility to the contractor
 Defined performance to be achieved

17 18

by Suranga Jayasena 3
BSc (Hons) QS/FM

 Lump sum price


 Natural to offer least expensive materials and  Similar to BoQ but no quantities
construction methods  Principles of SMM used
 Difficulty is to draft the Performance Spec  Bidders insert their rates
perfectly  Neither contract sum nor final price
 Suits projects of any size. predictable
 Difficult to price in absence of quantities
 Used when not possible to predetermine the
extent of proposed work

19 20

 Similar to Schedule of Rates, but tender


includes rates (from current market)  Both Quantities and Unit Rates form part of
 Bidders offer discounts (+/-) for work contract
sections  Design to be virtually completed
 Facilitate bid evaluation  Clear picture of commitment of both parties
 Usage of standard allows familiarity >>  Detail breakdown of bid/tender sum >>
better pricing better bid evaluation
 Unit rates >> basis for pricing variations

21 22

 Bid can be compared on bid sum alone  Used when not possible to measure work
 Widely used, suits projects of any size accurately
 Price certainty comparatively less than
 Lot of time on design and bill preparation previous
 Risk of quantity errors in BQ is with bidder  Entire work re-measured on completion
◦ Bidder to rate strategically  Only Unit Rates form part of contract
◦ May cause problems in variations pricing  Quantities ...?

23 24

by Suranga Jayasena 4
BSc (Hons) QS/FM

 Less pressure to fully complete the design  Decision on type of contract, conditions of
contract and contract documentation
 Signing of contract before finalizing the
design  Selection of the contractor
 Lesser overall time  Establishment of contract price (or how the
price will be arrived at)
 No risk to bidder on quantity errors in the bill
(what if for large deviations)
 Extra expense (time/money) on bill of firm
quantities avoided >> but, what about
remeasuring

25 26

Thank You

27

by Suranga Jayasena 5

You might also like