Professional Documents
Culture Documents
8 Subsea Well Control 1 PDF
8 Subsea Well Control 1 PDF
PVD Training
October 25, 2012
Authored by: Pham Van Thien
PVD Training
Section 8. Subsea Well Control
Floating drilling operations from semi submersibles and drill ships present special problems in well control.
Complications occur due to weather conditions, water depth, geology, and the design and operation of the
Subsea BOP stack and control system.
Two of the most serious operational scenarios are controlling a kick when only a shallow casing string has
been set and when drilling a long open-hole section before setting a protective casing string. Blowouts
have occurred in shallow wells when gas quickly arrived at surface with little warning.
Connectors with the lower pressure rating are designated CL while those rated at the BOP stack working
pressure are designated CH. Additional factors to be considered in selection of the proper connector
should include ease and reliability of engagement/disengagement, angular misalignments and mechanical
strength.
Engagement or disengagement of connector with the mating hub should be an operation that can be
repeatedly accomplished with ease, even for those conditions where some degree of misalignment exists.
Mechanical strength of the connector should be sufficient to safely resist loads that might reasonably be
anticipated during operations. This would include tension and compression loads during installation, and
tension and bending forces during both normal operations and possible emergency situations.
During normal drilling operations, the pressure head created by the mud column inside the riser keeps the
valve's internal sleeve closed. When riser pressure drops, ocean pressure pushes the sleeve up, initiating
a sequence which fully opens the valve to allow sea water to enter the riser, equalizing the pressure and
preventing riser collapse. The riser fill-up valve is activated by the pressure sensory sleeve when the
pressure inside the riser is from 250 - 350 psi below the ambient ocean pressure.
When activate, the valve fully opens to rapidly fill the riser. When pressure is equalized, the pressure
sensor returns to its normal position and the internal sleeve closes. Although the unit is totally self-
contained and independent of any control lines, the valve can also be manually operated through control
lines to the surface.
It would be useful to have a riser fill - up valve while drilling in areas with a high risk of lost circulation, or if
shallow gas were to evacuate mud from the riser.
occupying the pore space within the matrix, above the zone of interest. These two factors combine to
produce what is known as the overburden pressure. Assuming the average density of a thick sedimentary
sequence to be the equivalent of 19.2 ppg then the overburden gradient is given by:
0.052 x 19.2 = 1.0 psi/ft
Since the degree of compaction of sediments is known to vary with depth the gradient is not constant.
Fig 8.1.2
Onshore, since the sediments tend to be more compacted, the overburden gradient can be taken as being
close to 1.0 psi/ft. Offshore, however the overburden gradients at shallow depths will be much less than
1.0 psi/ft due to the effect of the depth of seawater and large thicknesses of unconsolidated sediment. This
makes surface casing seats in offshore wells much more vulnerable to break down and is the reason why
shallow gas kicks should never be shut-in as shown in Figure 8.1.3.
Fig 8.1.3
outlet. All right angle bends should be made with targeted tees or target type angle valves. The piping
between the upper valve and the choke/kill connectors or stab subs should be as straight as possible.
Slight changes of direction in this piping should be made with bends in the pipe itself, not using ells or
other weld fittings.
Gas Removal
In order to displace a gas kick completely from the wellbore several circulations of the well might be
needed. During this time some of the gas may have become trapped under closed rams in the BOP stack
as shown in Fig 8.1.4 (A). This has the potential to cause a serious problem if the gas is not removed in a
controlled manner.
If the rams were opened without removing the trapped gas, the gas would be released into the riser. As the
gas migrated, it would expand rapidly and cause the riser to unload mud onto the rig floor.
The most thorough method of gas removal is to leave the well shut on the lower rams whilst displacing the
choke and kill lines to water. By closing the kill line valves, pressure can be bled off up the choke line and
―U-tubed‖ up the choke line by opening the pipe rams. This sequence is shown below in Figures 8.1.4 (B)
thru (E).
The surface diverter should be closed during the operations so that any residual gas from the riser can be
safely dealt with. Once the riser has been displaced to kill weight mud the lower rams can be opened and
the well flow-checked. Calculate any new riser margin or trip margin that might have to be added to the
mud weight.
1. Isolate the well from the BOP stack by closing the lower pipe rams.
DEPTH - 1000 ft
Choke Line Length = 1000'
Volume of Gas Trapped = 3 bbls
Kill Mud = 15 ppg
15 ppg x 0.052 x 1000‘ = 780 psi
Atmospheric Pressure = 14.7 psi
Riser Margin
Standard operating procedures (and in many areas, government regulation) have required a mud weight in
excess of formation pressure in the event of emergency disconnect so that the mud weight remaining in
the hole will balance formation pressure.
The additional mud weight designed to compensate for the loss of hydrostatic pressure of the mud column
from the wellhead back to the rig when the BOP is closed and the riser disconnected is known as the riser
margin.
The riser margin can be calculated as follows:
Reduction in BHP (psi) =
[Riser Length (ft) x Mud Gradient (psi/ft)] – [Water Depth (ft) x Sea Water Gradient (psi/ft)]
In deepwater drilling, where the difference between formation and fracture pressures are very small, the
well cannot handle any extra pressure without losses occurring.
For this reason, enhanced well monitoring and training in well control and reconnecting methods becomes
essential.
Shallow Gas
Shallow gas is a frequent hazard in offshore drilling for bottom supported rigs and floating drilling vessels.
Worldwide studies of blowouts indicate that shallow gas is the most serious cause of kicks leading to
blowouts, and that these blowouts have caused more rigs to be severely damaged or entirely lost, than any
other well control problem. Attempts to divert shallow gas flows fail, on average, 50% of the time, and
result in loss of equipment and/or lives. Therefore, it is crucial to be prepared for encountering shallow gas
unexpectedly.
The data collected should be verified and interpreted by experienced personnel. The report, too, should be
generated by professionals experienced in preparing such reports. Ideally the Hazard Survey Report is
available before the well plan is prepared, allowing shallow gas contingencies to be written into the drilling
program. The report might impact rig selection as well.
Generally the report may be considered valid for 18 months, less if the drilling location is in an active
geologic area, or in a geo-technical area such as at the mouth of a river. Also, many drilling contractors
require hazard surveys to be conducted within 6 months of spud to detect recent debris.
If the hazard survey indicates the existence of shallow gas at the intended drilling location, a decision must
be made to either avoid it by moving to an alternate, shallow gas-free location within the hazard survey
area, or prepare to divert if necessary.
Drilling Riserless
The conductor hole (26‖) should be drilled without a hydraulic connector and associated riser. There are
several reasons why drilling riserless is preferable, including:
• When a riser is in use, the mud and cuttings contained in the riser put an increased hydrostatic
pressure on the exposed formations. This hydrostatic pressure could cause broaching or lost
circulation.
• If a shallow gas zone is entered with a riser installed, the riser serves as a conduit to bring the
potentially explosive and/or lethal gas to the rig floor.
• The hydrostatic pressure of the sea water is always exerted on a flowing formation.
One disadvantage of drilling riserless is that it is difficult to detect a gas flow. A subsea video camera,
either the rig‘s camera or one carried by an ROV, must be used.
Frequently, when drilling riserless, the only indication that a well is flowing is bubbles breaking the surface
of the sea.
The key point is to react as soon as a flow is noted.
While every floating rig has specific procedures for drilling in a shallow gas prone area, a contingency plan
ought to be developed and reviewed with the drilling contractor prior to rig mobilization. The following
guidelines should be considered in developing both the contingency plan and the drilling plan:
1. Serious attention should be given to drilling a pilot hole to conductor (20”) setting depth. This
pilot hole is drilled before setting structural casing (30”).
Pilot hole advantages include:
• Less expense is incurred if an uncontrolled shallow gas flow takes place and the pilot hole is lost.
• A dynamic kill may be possible in holes 8-1/2‖ or smaller. The back pressure on the flowing formation
due to the friction of drilling fluids being pushed up the hole may be great enough to kill the well, or at
least to slow gas flow substantially.
2. Pilot hole disadvantages include:
• Records show that many shallow gas flow occurrences have been initiated by swabbing. By design,
pilot holes have a restricted annulus, which increases swabbing tendencies. The swabbing potential is
worse in areas where BHA balling is a problem.
• The pilot hole annulus volume is smaller, permitting mud displacement by smaller kick volumes and at
a faster rate.
• Control drill to avoid overloading the annulus with cuttings. This is a concern if a pilot hole is drilled,
because of the relatively small annular clearance.
Note: Consider recommending drilling pilot hole to the depth of 1 st casing string intended to permit
conventional well control (which might be, but usually isn‟t, the 20”). Otherwise, you lose much of the
benefit of a pilot hole. Since most subsea BOP‟s go on the 20” wellhead, the above practice often results in
possibly encountering relatively shallow gas with a BOP and riser in place – thereby missing the benefits of
riserless drilling.
Only 1 of every 2 surface diverts are successful. Statistically, half of all attempts to divert a shallow gas
flow at the surface will fail.
Considering this information, it is obvious that a much better way to divert a gas flow is to do so at the
seabed (mud line). Seabed diverting provides more advantages than surface diverting, as follows:
• Keeps hazardous flow remote from rig.
• Diffuses the flow and diminishes its effect.
• Throughout a diverting event, the hydrostatic head of the sea water is exerted against a flowing
formation to help reduce the flow.
• If blind/shear rams are installed in the seabed diverter system, it's possible to quickly shear the drill
string, disconnect, and move the rig off location.
Note: When a seabed diverter is installed, a surface diverter is also installed to provide a means of
diverting any gas which may get into the riser due to the late detection of a kick or a leaking seabed
sealing element.
(Refer to Section 7.3 for surface diverting procedures)
Note: Avoid bringing gas flow to the rig through the riser / diverter system. Shut-in on surface hole kicks.
While circulating out a shallow gas influx, a high degree of readiness to react to additional complications
should be maintained. Some considerations regarding kill operations include:
• Mooring lines/winches:
a. Pre-establish the move–off direction. This will be based on wind and current direction. The
appropriate mooring winches to be released (slackened) should also be determined.
b. Pretension the anchor lines to allow the rig to be moved off location. If moving off location becomes
necessary, this would be accomplished by releasing the anchor tension on the leeward anchors and
winding in the lines on the windward anchors.
c. Keep winches on brakes, not dogged off.
d. Man each winch continuously with experienced personnel while drilling is underway.
• Use an ROV or rig camera to watch for gas bubbles at the wellhead or from the seabed in the vicinity
of the wellhead.
• Have an anchor handling boat sailing around the rig until the surface hole section is drilled. The boat
should not be tied up to the rig, or on anchor.
• Post and rehearse, rig crew assignments and duties.
• Consider evacuating non-essential personnel.
If the well broaches while circulating out an influx, and the rig is not endangered by an erupting gas plume,
then it may be possible to displace the open hole section with high density mud. Rapidly displacing the
open hole section with a high density fluid may kill the well, or at least prevent continued broaching, and
cratering. Therefore, a reserve pit of high density mud should be ready to pump.
Case histories of many shallow gas kicks indicate that swabbing is a major cause of these incidents.
Therefore, if a pilot hole is drilled, remember that the reduced annular space may exacerbate swabbing
tendencies, particularly in areas prone to BHA balling.
Diverter Equipment
The diverter that is part of the riser equipment on floaters has a different function than a similar component
found on a bottom supported rig. The main function of the diverter on a floating rig is to handle gas that
may inadvertently enter the riser during a well control operation. This could occur if gas migrates into the
riser before a kick is recognized and preventers are closed, if preventers leak, or when gas is being
circulated out from between two closed preventers after the well is killed (clearing stack–gas). See Sub-
section 8.1.7.
By far the most common surface diverter found on floating rigs is the ABB-Vetco Gray (formerly Regan)
KFDS. Vetco Gray has improved on the KFDS with the KFDS-1000 CSO, illustrated in Regan KFDS-1000
Surface Diverter illustration. This new design uses a spherical sealing element rather than the insert type
used in earlier generation Regan diverters.
The ―CSO" (Complete Shut Off) designation denotes the capability of this diverter to close and seal on
open hole without pipe. Other than the spherical sealing element, the operation of this diverter is identical
to that of the insert type KFDS.
Fig 8.1.12
Fig 8.1.13
value for choke line friction after changing mud weights, use Equation 8.1 to closely approximate the new
value for choke line friction:
Equation 8.1 Adjusting Choke Line Friction for New Mud Weights
Shut-in Procedures
General
When a kick is detected, the well should be closed-in on the uppermost annular preventer. After shut-in,
drillstring reciprocation through the annular preventer is not recommended as significant wear may occur
on the sealing element, especially if a tool joint is reciprocated through the element. To avoid this, the
drillstring should be hung-off on a pipe ram as soon as possible. Additionally, a trapped gas bubble will be
left in the BOP stack between the annular preventer and the choke line outlet used to circulate the well.
This trapped bubble may be hazardous to handle at the surface, depending on its size and pressure. To
minimize the risk of annular wear and the size of the trapped bubble, the following is recommended:
a. The well should be shut-in on the annular preventer in the LMRP and operations begun immediately
to hang off the drillpipe on the pipe rams. Pipe reciprocation should be sacrificed in order to minimize
the size of the trapped bubble and annular element wear. It is acceptable (but not recommended) to
hang off on VBRs only if a tool joint will rest on ram blocks, not on the fingers.
b. When circulating out the influx, returns should be taken through the choke or kill line outlet directly
beneath the closed pipe rams. Once the influx is circulated from the wellbore, remove the trapped gas
from the BOP stack. Fill the riser with kill weight mud. The diverter controls and overboard line should
be manned before the well is opened. When circulation begins up the riser, any residual gas bubble
will then be diverted overboard through the diverter lines as necessary.
c. In the event of trapping significant quantities of gas in the BOP stack for any of the following reasons:
i) Not hanging off the drill pipe on the pipe rams.
ii) Not closing the well in until gas reaches the BOP stack.
iii) Pipe rams leaking with the annular closed.
iv) Not being able to utilize a choke or kill line outlet directly beneath the hang-off rams.
Special procedures must be used to control the expansion of the trapped bubble when the well is opened
up. This topic is discussed in detail later in this section.
NOTE: The quantity of gas trapped in the BOP stack which will become significant at the surface is
dependent upon water depth and mud weight. Two barrels of trapped gas in 150' of water with 10 ppg mud
will expand to just over 10 barrels at the surface. The same two barrels in 1000' of water with 15 ppg mud
will expand to over 100 barrels
The three advantages of hanging-off versus reciprocating through the annular preventer are:
a. Minimizes wear on the annular
b. Minimizes the amount of trapped gas in the stack after the kick has been circulated out.
c. Facilitates a quick disconnect if the need should arise.
2) Close the pipe rams below the choke and kill outlets and circulate the "old mud" above the closed
pipe rams and displace the choke line; or
3) Use the slowest pump rate possible and hold the drillpipe pressure constant until the choke line is
displaced.
3. Increase casing pressure to 900 psi by adjusting the choke. The drillpipe pressure should increase to
590 psi.
4. Reduce the pump rate to 20 spm while holding the casing pressure constant at 900 psi. Drillpipe
pressure should decrease to 325 psi.
5. Increase casing pressure to 950 psi by adjusting the choke. The drillpipe pressure should increase to
375 psi.
6. Stop the pumps while holding the casing pressure constant at 950 psi. The drillpipe pressure should
be 0 psi after the pump is stopped since kill weight mud is at the bit.
When kill weight mud is circulated back to the surface, choke line friction will increase due to higher density
fluid being circulated through the choke. In some situations, the increase in choke line friction can be
significant and may become critical, e.g. deep water with a long choke line, a large increase in kill mud
density, or the kill weight mud density is close to the shoe test. In these situations, it may become
necessary to open the choke, or perhaps open a second choke, in order to reduce the drillpipe pressure to
its proper value. If the drillpipe pressure is still too high, the only alternative would be to slow down the
pump. The amount of choke line friction increase can be predicted using Equation 8.1, by subtracting off
the value of choke line friction for the "old" mud weight.
The procedure once used was to slow the pumps down after pumping 65% of the annulus volume.
However, this resulted in several complications as follows:
1. After 65% of the annulus volume has been pumped, a gas bubble is rapidly expanding and the mud
ahead of the bubble is flowing at a rate faster than that being pumped. Therefore, when the pumps
are slowed down and the proper amount of choke line friction is put back into the system, the amount
of choke line friction is incorrect due to the higher flow rate through the choke line. Thus, after slowing
the pumps down, there will be more choke line friction in the system than necessary, which could
result in formation breakdown and lost circulation.
2. Adjusting the choke line friction and slowing down the pumps causes the bubble pressure to change
significantly. Because gas is very sensitive to changes in pressure, it acts like a shock absorber
downhole and may require a long period of time to stabilize. Until the bubble pressure and volume
stabilize, changes in drillpipe pressure will make it difficult to keep bottomhole pressure constant. This
in turn may result in either lowering bottomhole pressure to a point where a second kick is taken, or
raising bottomhole pressure to a point that formation breakdown could occur.
Thus, the recommended procedure is to choose a circulating rate that allows controlling the kick when it
arrives at the choke line and maintain that rate for the entire circulation.
A second complication of gas in the choke line is that PcMax at the surface will be higher than that
calculated using the charts. The charts are designed to calculate PcMax at the wellhead, which is at the
mudline for a subsea stack. Thus, to calculate the PcMax at the surface, which is the pressure imposed on
the choke manifold and surface equipment, PcMax must be corrected using Equation 8.3:
Equation 8.3 PcMax at the Surface
PcMaxCorr = PcMaxCalculated + [(Old Mud Wt,ppg)*(0.052) - SG Gas][RKB - ML,ft]
Example:
A kick is going to be circulated out PcMax is calculated to be 3,000 psi (using the charts), old mud weight
is 14.5 ppg, and RKB to Mud LIne is 1,000 feet. Assume a gas gradient of 0.1 psi/ft. The corrected PcMax
would be:
PcMaxCorr = 3000 psi + [(14.5)(0.052) - 0.1]*[1000 ft) = 3000 + 654 = 3654 psi
7. Pick up drillpipe above the BOP stack. Check for flow and close the blind shear rams. Close the
wedge locks if ram is a Cameron ram.
8. Displace the riser with sea water and adjust riser tensioning. Dump the subsea accumulator bottles, if
applicable. Deballast part or all of the air buoyancy tanks on the riser, if applicable.
9. Pull the remainder of the drillpipe out of the riser. Disconnect the LMRP and pull the riser.
Emergency Disconnect
Situations that might require an emergency disconnect include: the loss of well control, a sudden change in
weather, or waiting too long to do a "non-emergency" disconnect. In these situations, the following
procedure is recommended:
1. Pick up and space out to hang off on the designated hang-off ram.
2. Close hang-off ram with 1,500 psi closing pressure. Close wedge locks if ram is a Cameron ram.
3. Close lower pipe rams for a backup.
4. Adjust compensator to support string weight above rams, plus overpull of 10,000 lbs (time
permitting).
5. Shear drillpipe with full operating pressure (3,000 psi). Some BOP manufacturers have had trouble
with new drillpipe. On some new drillpipe, the tapered section next to the tool joint has been
lengthened. If some of this type of drillpipe is in the string, the BOPE manufacturer should be
contacted to determine shearing capability.
6. Check the riser tensioning then disconnect the LMRP and pull the riser if possible. If unable to pull
the riser, move the vessel off location while dragging the riser. Stay clear of shallower water and away
from the BOP stack.
Note:
Studies conducted by Operator Companies and ram manufacturers indicate that complete shear of some
grades of drillpipe will not be obtained using 1,500 psi closing pressure. Five inch grade G drillpipe may
require up to 3,000 psi closing pressure for a complete shear. Also, note that high strength drillpipe that
has been sheared can explode, long after shearing. A sheared stub should be handled carefully and
removed from the rig as soon as possible.
5. Open the middle pipe rams and monitor the well for flow.
6. Pull the hang-off tool (or overshot, if pipe was sheared) out of the hole.
7. Trip to bottom, circulate and condition mud as required.
Note: If S-135 drillpipe has been sheared, "shattered" pieces of the drillpipe will be on top of the shear
rams. Pick up these pieces with a magnet prior to opening the shear rams
Introduction
BOP Equipment and Control Systems Overview
Much of the BOP equipment found on floating drilling rigs duplicates that which is used for surface
locations. With only slight modifications, surface-style‖ annular preventers, pipe rams, and hydraulic
valves are incorporated onto a four posted subsea BOP guide frame. Like surface operations, pressurized
hydraulic fluid operates this equipment. Both a choke and kill line are available for well control, with bottom
hole pressure being regulated via an adjustable choke and manifold assembly. Differences include a pilot
operated control system, the number and types of preventers (complete with - remote locking
mechanisms), the need for hydraulic connectors and motion compensation, and even the physical location
of the stack. The purpose of positioning the BOPs on the seafloor is to allow for vessel motion and to
facilitate a swift departure procedure after disconnect of the hydraulic connector without pulling the well
over. Also, with the stack on bottom, the marine riser doesn‖ t have to contend with high wellbore
pressures. Therefore, a significant reduction in the riser pipe burst strength is realized.
In this section, the subsea BOP equipment and control systems will be divided into the following five major
components (as shown in Figure 8.1.1):
1. BOP Stack
2. LMRP (Lower Marine Riser Package)
3. Marine Riser and Diverter Assembly
4. Choke Manifold
5. Control System
Note: The remaining BOP equipment, which is identical for both environments, is reviewed in Sections 7
& 8.
BOP Stack
As depicted in Figure 8.1.2, the BOP Stack consists of a hydraulic wellhead connector, ram type
preventers, choke and kill line valves, and pod receiving blocks/lower female receptacles. An annular
preventer may or may not be included on the BOP Proper. Notice the absence of drilling spools between
preventers, a design intended to minimize the overall height, thereby increasing the assembly‖s stiffness
and reducing the bending moment transferred to the wellhead.
Typically the subsea stack has consisted of 4 rams and possibly an annular (alternately the annular is on
the LMRP). However, today‖s new generation rigs and the increasingly difficult drilling conditions have
changed the thinking on a ―typical‖ BOP configuration. Many new generation rigs are now equipped with 6
ram stacks with either single or double annulars both on the stack and on the LMRP. A detailed well
program should help the planning engineers to determine the BOP configuration required for specific
operations. Additionally, extensive thought must be given to the configuration of rams within the ram
bodies (i.e., where to put the shears, VBRs. Etc and why).
Fig 8.2.1
8.2.1 Diverter
When a diverter system is to be used in connection with a subsea installation, there must be a short string
of casing or drive pipe installed below the mud line. A marine riser is attached to this casing or drive pipe.
The diverter system is then connected to the top of the marine riser above the telescopic joint (slip joint)
and secured to the rig substructure.
The diverter system vent lines are usually large diameter (12‖ or larger) and are designed to divert wellbore
fluids away from the rig floor with minimum back pressure on the wellbore. They are usually directed to the
opposite extremities of the vessel. The live vent line would be determined by wind direction to carry
wellbore fluids away from the rig. Any valves in the diverter vent lines must be full-opening and either
automatic or selectively controlled or sequenced, so that flow from the well bore cannot be closed in.
The diverter and valves should be actuated when installed and at appropriate times during operations to
determine the system will function properly.
The outer barrel (lower member), connected to the riser pipe and remaining fixed with respect to the
seabed, is attached to the riser tensioning system and also provides connections for the choke and kill
lines. A pneumatically or hydraulically actuated resilient packing element contained in the upper portion of
the outer barrel provides a seal around the outside diameter of the inner barrel.
The inner barrel (upper member), which reciprocates within the outer barrel, is connected to and moves
with the drilling vessel and has an internal diameter compatible with other components of the marine riser
system. The top portion of the inner barrel has either a drilling fluid return line or diverter system attached,
and is connected to the underneath side of the rig substructure.
The telescopic joint (slip joint), either in the extended or contracted position, should be capable of
supporting anticipated dynamic loads while running or pulling the BOP stack and should have sufficient
strength to safely resist stresses that might reasonably be anticipated during operations. Stroke length of
the inner barrel should provide a margin of safety over and above the maximum established operating
limits of heave for the vessel due to wave and tidal action.
Selection of a telescopic joint (slip joint) should include consideration of such factors as size and stroke
length, mechanical strength, packing element life, ease of packing replacement with the telescopic joint
(slip joint) in service, and efficiency in attachment of accessories (i.e. tensioner cables, choke and kill lines,
diverter system, etc.).
Flex – Joint
A flexible-ball joint is used in the marine riser system to minimise bending moments, stress concentrations
and problems of misalignment engagement. The angular freedom of a flexible joint is normally 10 degrees
from vertical. A flexible joint is always installed at the bottom of the riser either immediately above the
remotely operated connector normally used for connecting/disconnecting the riser from the blowout
preventer stack (BOP stack), or above the annular preventer when the annular preventer is placed above
the remotely operated connector.
For those vessels having a diverter system, a second flexible joint is sometimes installed between the
telescopic joint (slip joint) and the diverter to obtain required flexibility, or some type of gimbal arrangement
may also be used. For deep water operations or unusually severe sea conditions, another flexible joint may
be installed immediately below the slip joint.
Mechanical strength requirements for flexible joints are similar to those for the remotely operated
connector. They should be capable of safely withstanding loads that might reasonably be encountered
during operations, both normal and emergency. In addition, the angular freedom of up to approximately 10
degrees should be accomplished with minimum resistance while the joint is under full anticipated load.
Hydraulic ―pressure balancing‖ is recommended for ball-type flexible joints to counteract unbalanced forces
of tensile load, drilling fluid density and sea water density. This pressure balancing also provides
lubrication for flexible joints.
Technical investigations and experience have shown the importance of close monitoring of the flexible joint
angle to keep it at a minimum. One method of accomplishing this is by the use of an angle-azimuth (slope)
indicator. The flexible joint angle, vessel offset and applied (riser) tension are indications of stress levels in
the riser section. For continuous drilling operations, the flexible joint should be maintained as straight as
possible, normally at an angle of less than 3 degrees: greater angles cause undue wear or damage to the
drill string, riser, BOPs, wellhead or casing.
For riser survival (to prevent overstressing) the maximum angle will vary from about 5 degrees to
something less than 10 degrees, depending upon parameters such as water depth, vessel offset, applied
tension and environmental conditions. Drill pipe survival must also be considered if the pipe is in use
during those critical times of riser survival conditions.
The following limits are recommended for the lower ball joint angle:
Ball Joint Angle Range Comments
00 – 10 The ―goal‖ during operations is to maintain the ball joint angle within
these limits if at all possible.
At 50 and increasing Drill pipe hung-off. Preparations started for riser disconnect.
Utilizing the lower ball joint angle ranges indicated above, the following operational limits are recommended:
A flexible kill system to pump into the hole through the annulus or drillstring.
Instrumentation to control the well killing operation.
Subsea BOP stacks are similar in component arrangement to surface installations, with the following
differences:
a. Choke and kill lines are normally connected to ram preventer body outlets.
b. Spools may be used to space preventers for shearing tubulars, hanging off drill pipe, or stripping
operations.
c. Choke and kill lines are manifolded for dual purpose usage.
d. Blind/shear rams are normally used in place of blind rams.
e. Ram preventers are usually equipped with an integral or remotely operated locking system
f. More accumulator volume is required and some of the accumulator bottles may be mounted on the
BOP stack.
Figure 8.2.4
In the 1980‘s, Cameron experienced seal difficulties with the 2 7/8‖ x 5‖ and the 3 ½‖ x 5‖ VBR‘s for type U
18 ¾‖ preventers. This lead to the development of a Flex Packer, which consists of multiple metal inserts
bonded into the elastomer. As the rams are closed and energisezed, the appropriate set of inserts is forced
against the pipe. (The top plate of the packer fits the largest pipe diameter). This design incorporated metal
pins through the plates which provides a system for positive retention, even if the bonding fails as shown in
Figure 8.2.5
Fig 8.2.5
Typically, there is not enough distance between the #3 (upper pipe) ram and #4 (blind/ shear) ram to fit a
tool joint. Since the capability to shear pipe is lost, this may not be a prudent hangoff location. Placing the
hang-off ram in the #2 position (middle pipe ram) allows for shearing operations and the #1 (bottom pipe)
ram to act as a back-up.
Choke and kill valve outlet placement becomes a function of the procedures planned and an assessment
of what contingencies are to be given priority. Consideration is given to where valve failures can be
tolerated and how placement affects a corresponding back-up plan, what the likelihood is of a disconnect
during a well control procedure, and whether it is possible to re-establish onto a well after returning from a
disconnect. Most of these scenarios can be handled by having one outlet below and one outlet above the
hang-off ram. If a third outlet is present, it should be below the hang-off ram as well. (If fortunate to have a
forth outlet, position it above the hang-off ram).
A consequence of certain outlet placements is a lack of consistent BOP pressure testing on every outlet.
For example, a weekly pressure test of blind shear rams requires backing off a test plug, which can be
undesirable. (If test pressure leaks by the - backed off‖tool, it can go to the formation, since the subsea
wellhead has no casing valve that can be opened. Also, any damage to the test tool while running, setting,
or retrieval may dictate a fishing job). If the blind/shear rams are only pressure tested before drilling out
casing strings, any valves on outlets directly under these rams will experience the same infrequent
intervals (and only tested to casing pressure). Ensure this is thoroughly addressed in the Application to
Drill.
Besides the safety / environmental implications of BOP equipment failure, there can be huge costs
associated with such failures. Operators must actively participate with the Contractor on all aspects of BOP
inspections, testing, maintenance, and repair. Probably the single most important aspect that the Operator
can influence (positively as well as negatively) is in the planned maintenance programs (PMP). Operators
and their rig site representatives must play a pro-active role in these programs not only during the actual
operations but also during the well / project planning stages. All too often the well work program takes no
account of the requirements for planned maintenance and critical items are deferred in preference to the
―job at hand‖.
It is recommended that Operators review planned maintenance programs to ensure all critical items are
included and that the programs are followed. An excellent way to ensure the programs are followed is to
compare PMPs to purchase orders. For example, if the PMP calls for the replacement of particular seals
on a six monthly basis there should be a record of purchase orders for those items every six months. This
can prove to be a valuable way to ensure that the programs are being followed.
Introduction
Every component in a blowout preventer assembly is operated hydraulically by moving a piston up and
down or back and forth. Thus the function of a BOP control system is to direct hydraulic fluid to the
appropriate side of the operating piston and to provide the means for fluid on the other side of the piston to
be expelled.
On land, jack-up or platform drilling operations the control of the BOP is easily achieved in a conventional
manner by coupling each BOP function directly to a source of hydraulic power situated at a safe location
away from the wellhead. Operation of a particular BOP function is then accomplished by directing hydraulic
power from the control unit back and forth along two large bore lines to the appropriate operating piston.
This system uses the minimum number of controlling valves to direct the hydraulic fluid to the required
function. It also enables the returning fluid to be returned to the control unit for further use.
For subsea drilling operations, it is necessary to control larger, more complex BOP assemblies which are
remotely located on the sea-bed. In this instance, direct control cannot be applied since the resulting
control lines connecting the BOPs to the surface would be prohibitively large to handle. Reaction times
would also be unacceptable due to the longer distances to the BOP functions and the consequent pressure
drop.
In order to overcome these problems indirect operating systems have been developed. There are two
types - hydraulic and multiplex electro-hydraulic of which the indirect hydraulic system is by far the most
common.
No attempt is made to recover the hydraulic power fluid once it has been used to operate a function since
this would increase the number of lines required in the umbilical. Instead the fluid is vented subsea from
the control pod.
Overview
Fluid used to operate the functions on the BOP stack is delivered from the hydraulic power unit on
command from the central hydraulic control manifold. This contains the valves which direct pilot pressure
to the pilot valves in the subsea control pods and which are operated either manually or by solenoid
actuated air operators.
In this way the manifold can be controlled remotely via the actuators from the master electric panel (usually
located on the rig floor) or from an electric mini-panel (located in a safe area). The system may include
several remote mini-panels if desired. An electric power pack with battery back-up provides an
independent supply to the panels via the central control manifold.
The pilot fluid is sent to the subsea control pods through individual, small diameter hoses bundled around
the larger diameter hose which delivers the power fluid. In order to provide complete redundancy for the
subsea portion of the control system there are two independent hydraulic hose bundles and two
independent control pods.
The hydraulic hose bundles (or umbilicals) are stored on two hose reels, each of which is equipped with a
special manual control manifold so that certain stack functions can be operated whilst the stack is being
run. Hydraulic jumper hose bundles connect the central hydraulic control manifold to the two hose reels.
Each umbilical is run over a special sheave and terminates in its control pod.
For repair purposes each pod along with its umbilical can be retrieved and run independently of the BOP
stack. In order to do this, the pod and umbilical is run on a wireline which is usually motion compensated.
In some designs of control system, the umbilical is run attached to the riser in order to give it more support
and reduce fatigue at hose connections. The pod is still attached to a wireline for retrieval purposes. This
design has the advantage of not having to handle the umbilicals whenever the pod is pulled but has the
disadvantage of requiring more subsea remote hydraulic connections. Guidance of the pod is provided by
the guidewires and guideframe as shown in Figure 8.3.1.
Figure 8.3.2 is a block diagram of the hydraulic flow system for a stack function. The hydraulic fluid is
prepared and stored under pressure in the accumulators. Some accumulators (usually two) are dedicated
to storing fluid for use in the pilot line network and the remaining accumulators contain the fluid that is used
Figure 8.3.1
The power fluid is routed to the subsea control pod selected by the pod selector valve which is located in
the central hydraulic control manifold. The line to the non-selected pod is vented. When power fluid
reaches the pod, it is combined with fluid stored at the same pressure in subsea accumulators, located on
the BOP stack. The pressure of the combined fluid is then reduced, to that required to operate the stack
function, by a subsea regulator situated in the control pod. Adjustment of this regulator is performed from
PVD Training | 8.3 Subsea BOP Control Systems 49
PVD Training
Section 8. Subsea Well Control
the surface via dedicated pilot and read-back lines in the hose bundle.
Pilot fluid is always directed to both pods at the same time. When the pilot fluid for a particular function
reaches each pod, it lifts the spindle of its associated SPM (sub plate mounted) pilot valve. In the pod to
which the power fluid has been sent this will allow the fluid to pass through the SPM valve and be routed to
the stack function via a shuttle valve.
Operating Sequence
A summary of this operating sequence is shown in Fig 8.3.3 following. A more detailed description of the
sequence of events that occur when a function is operated will now be given with reference to the flow
diagram in Figs 8.3.4 (A) (B) and (C). Each piece of equipment on the BOP stack has a corresponding pilot
control valve on the central hydraulic control manifold which actuates the appropriate SPM valve. The
control valve is a four-way, three position valve and can be functioned manually or by an air operator.
Close Function
In Fig 8.3.4 (A) one of the BOP rams is being closed using the drillers master control panel. Pushing the
―close‖ button on this panel actuates the solenoid valves on the hydraulic manifold thus allowing air
pressure to move the pilot control valve to the ―close‖ position. The solenoid valve on the right in the
diagram vents the other side of the air cylinder.
With the pilot control valve in the ―close‖ position, pilot fluid at 3000 psi is sent down the umbilical to the
RAMS CLOSE SPM valve in the subsea control pods. The pressure lifts the spindle in this valve so that it
seals against: the upper seat, thus blocking the vent.
At the same time power fluid at its regulated pressure is allowed past the bottom of the spindle and into the
valve block in the male and female sections of the control pod. From the bottom of the female section, the
power fluid then travels through the shuttle valve to the ―close‖ side of the BOP ram cylinder. Simultaneous
reciprocal action in th RAMS OPEN SPM valve vents the hydraulic fluid from the ―open‖ side of the BOP
ram.
Block Function
The block function is used to vent a pilot control valve. By doing this individually on each valve a leak in the
control system or the preventers can be located and isolated. By centering and venting all the valves when
the accumulator unit is first being pressurized unintentional and inadvertent operation of the various other
positions and functions can be eliminated.
Referring to Figure 8.3.4 (B), when the ―block‖ button is pressed, both the solenoid valves are actuated in
such a way as to apply pressure to both sides of the air operator. This causes the pilot control valve to be
centered which then allows both the pilot ―open‖ and ―close‖ lines to be vented. The springs in both the
SPM valves then push the spindles down so that they seal against the bottom seats and block the flow of
any power fluid through the valves. At the same time this also vents both sides of the BOP ram operating
cylinders.
Open Function
This sequence is the parallel opposite of the CLOSE function. As shown in Figure 8.3.4 (C), when the
―open‖ button is pressed, the solenoid valves on the hydraulic control manifold are actuated and allow air
pressure to move the operator on the pilot control valve to the ―open‖ position. The solenoid valve on the
left in the diagram vents the ―close‖ side of the operating piston.
The pilot fluid can then flow down to the subsea control pod where it lifts the spindle in the RAMS OPEN
SPM valve thus blocking the vent and allowing power fluid to flow through the valve. From the pod the
power fluid travels through the ―open‖ shuttle valve to the ―open‖ sides of the BOP ram operating cylinders.
Simultaneous reciprocal action in the RAMS CLOSE SPM valve allows the fluid from the ―close‖ side of the
operating cylinders to be vented.
allows the control fluid to charge the stack mounted accumulator bottles. Shuttle valves allow the bottles to
be charged from either pod.
Mixing System
The hydraulic power unit supplies hydraulic fluid to the entire control system. It requires fresh water,
soluble oil, glycol (for freeze protection), compressed air and electrical power for operation. Two small
reservoirs contain the soluble oil and glycol which are automatically blended with fresh water to make up
the hydraulic fluid which is then stored in a large reservoir known as the mixed fluid tank. Since the control
system is an open one in that the used hydraulic power fluid is vented into the sea, the type of soluble oil
used must be completely biodegradable. Additives to prevent bacteria growth and to inhibit corrosion are
also frequently included in the mix water.
The soluble oil reservoir has a capacity of at least 110 gal whilst the mix fluid tank should be capable of
holding sufficient fluid to charge the system accumulators from their pre-charge condition to their maximum
operating pressure. All the tanks are fitted with sight glasses and a low-level alarm system which activates
a warning light and horn on the control panels.
The proper mixing fluid ratio is maintained by air operated hydraulic pumps, a water pressure regulator, a
double acting motor valve and a water flow rate indicator. A reservoir float switch is used to control
operation of the mixing system in order to maintain the correct level of fluid and to ensure a continued
supply for the control system.
Water/additive concentrations can be adjusted by setting the mixing pump to run at the appropriate rate. A
minimum rig water supply pressure of 25 psi is typically required for the correct operation of the mixing
system and to provide a fluid supply at least equal to the rate at which mix fluid is drawn from the tank by
the high pressure pumps.
Accumulator Requirements
Volumetric Capacity
As a minimum requirement, closing units for subsea installations should be equipped with accumulator
bottles with sufficient volumetric capacity to provide the usable fluid volume (with the pumps inoperative) to
close and open the ram preventers and one annular preventer.
Usable fluid volume is defined as the volume of fluid recoverable from an accumulator between the
accumulator operating pressure and 200psi above the pre-charge pressure. The additional pre-charge
pressure required to offset the hydrostatic head of the seawater column and the effects of subsea
temperature should be considered when sizing subsea mounted accumulator bottles,
Response Time
The closing system should be capable of closing each ram preventer within 45 seconds. Closing time
Subsea Accumulators
The nitrogen precharge pressure must be increased in the subsea accumulator bottles in order to account
for the hydrostatic pressure of the hydraulic fluid in the power fluid supply hose, when calculating the
amount of usable fluid volume. As an added safety factor the sea water gradient is used for this purpose,
i.e. .445 psi/ft.
If operating in 1500 ft of water, the hydrostatic pressure would be:
1500 ft x .445 psi/ft = 667.5 or 668 psi (rounded off).
Thus the nitrogen precharge would need to be increased by 668 psi.
i.e. 1000 psi + 668 psi = 1668 psi.
Therefore:
P1 = nitrogen precharge pressure of 1668 psi (1000 psi + 668 psi)
P2 = minimum operating pressure of 1868 psi (1200 psi + 668 psi)
P3 = maximum operating pressure of 3668 psi (3000 psi + 668 psi)
V1 = bladder internal volume at precharge pressure (11 gal - 1 gal)
V2 = bladder internal volume at minimum operating pressure, P2 (in gals)
V3 = bladder internal volume at maximum operating pressure, P3 (in gals)
Therefore:- 1668 psi x 10 gals = 1868 psi x V2 and 1668 psi x 10 gals = 3668 psi x V3
Giving: V2 = 1668 psi x 10 gals = 8.93 gals and V3 = 1668 psi x 10 gals = 4.55 gals
1868 psi 3668 psi
The usable volume of hydraulic fluid per subsea bottle in 1500 ft of water would be the difference between
these two volumes.
V2 – V3 = 8.93 gals - 4.55 gals = 4.38 gals.
Application of the above calculation now makes it possible to determine the total number of accumulator
bottles required both on the surface and subsea, given the following opening and closing volumes of
hydraulic fluid for a typical 18.75 inch subsea BOP stack.
Annular preventer 44 gals to close 44 gals to open
Ram preventer 17.1 gals to close 15.6 gals to open
Failsafe valves 0.6 gals to close 0.6 gals to open
Assuming that company policy is to have sufficient subsea accumulator capacity to close:
1 annular
1 ram preventer
4 failsafe valves
Then the usable volume required will be 44 gal + 17.1 gal + (4 x 0.6 gal) = 63.5 gals and since each bottle
can deliver 4.38 gals then:
Regulator Control
Since the power fluid arrives at the subsea control pod at 3000 psi and the BOP functions have a
maximum normal operating pressure of 1500 psi, regulators are needed in the pods - one is provided for
the annular preventers and one for the ram preventers. Figure 8.3.11 shows how the subsea regulator is
controlled from the surface. A 1/2" air operated pilot regulator in the control manifold transmits pilot
pressure to the subsea regulator in order to adjust its setting.
The air operator can be manipulated either manually using an air regulator on the control manifold or
remotely from another control panel. When operated from a remote panel a solenoid valve is used to
increase the air pressure by allowing rig air to flow into a 1 gallon receiver connected to the air pilot line.
The receiver acts as a surge protector for the pilot regulator. Decreasing the air pressure is achieved by
using a solenoid valve to vent the line to atmosphere.
Pressure Readback
In order to ensure that the subsea regulator has set the desired operating pressure the manifold
incorporates a readback system. The output of each subsea regulator is connected through a 1/8" hose in
the umbilical back to a pressure gauge in the control manifold. Pressure transducers transmit the readback
pressures to remote panels. A shuttle valve also in the manifold unit connects the lines from both
umbilicals and isolates the active and inactive pods.
All the electrical components are housed in separate explosion proof housings on the control manifold unit.
One housing contains the solenoid valves and another contains the transducers and pressure switches.
The pressure switches are typically set to be activated ‗on‘ when pressure in the pilot line to the ram or
PVD Training | 8.3 Subsea BOP Control Systems 65
PVD Training
Section 8. Subsea Well Control
failsafe SPM reaches 1000 psi and to switch ‗off‘, when the pressure falls to below 700 psi.
Control Panels
These panels permit the operation of the manifold unit from remote locations. Usually two remote panels
are used - a master one on the drill floor, and a mini-panel in a relatively safe location such as a rig office.
Other mini-panels can be integrated into the system if desired.
The drillers‖ master panel is normally explosion proofed or air-purged since it is located in a hazardous
area. It contains a set of graphically arranged push-button/indicating lights for operation and status
indication of each stack function. The regulator pressures are controlled by increase/decrease push-
buttons and there are gauges for monitoring pilot and readback values. A digital readout of the flow meter
located on the control manifold is also provided.
Many types of drillers panel also include controls for the operation of the rig diverter system which is
controlled in a similar way to a surface BOP system. The mini-panel is usually not required to be explosion
proof. It operates in the same way as the master panel but does not include the pressure gauges. Both
panels include lamp test facilities to check for burnt out lamps. They also contain alarms for low hydraulic
fluid level, low accumulator pressure, low rig air pressure and an alarm to indicate that the emergency
battery pack is in use.
The remote panels contain all the necessary electrical switches to operate the solenoid valves on the
hydraulic control manifold which in turn control the air operators of the pilot control valves. Lights on the
panels (red, amber, green) indicate the position of the 3-way valve (open, block, close) and there is a
memory system so that when a function is in block with the amber light on, the actual position of the
function (the red or green light) will also be displayed.
Figure 8.3.12 (A) (B) & (C) shows in more detail the operation of a BOP function from a remote panel.
Although the lights on the panels show the position of the BOP functions, the control buttons are not active
until a ―push and hold‖button is depressed in order to allow the supply of electrical power to the panel.
The sequence of events that occur is as follows:
Close
1. The ―press and hold‖ button is held in to activate the panel.
2. The ―close‖ button is pressed.
3. Current flows to the ‗close‘ solenoid valve which lifts to supply air to the 3- position air operator.
4. The air operated piston moves the pilot control valve to the ―close‖ position and pilot pressure is sent to the
subsea control pod.
5. Successful pressurization of the pilot line to the control pod actuates a pressure switch on the control manifold.
6. Current flows through an electronic card which illuminates the lamp of the ―close‖ button indicating that the
function is now closed.
7. The ―press and hold‖ button is released; the ―close‖ lamp remains illuminated.
Open
1. The ―press and hold‖ button is held in to activate the panel.
2. The ―open‖ button is pressed.
3. Current flows to the ‗open‘ solenoid valve which lifts to supply air to the 3- position air operator.
4. The air operated piston moves the pilot control valve to the ―open‖ position and pilot pressure is sent to the
subsea control pod.
5. Successful pressurization of the pilot line to the control pod actuates a pressure switch on the control manifold.
6. Current flows through an electronic card which illuminates the lamp of the ―open‖ button indicating that the
function is now closed.
7. The ―press and hold‖ button is released; the ―open‖ lamp remains illuminated.
Block
1. The ―press and hold‖ button is held in to activate the panel.
2. The ―block‖ button is pressed.
3. Current flows to both the ‗close‘ and ‗open‘ solenoid valve which lifts to supply air to both sides of the 3- position
air operator piston.
4. The air operated piston moves to a central position which places the pilot control valve in the middle ―block‖
position so that no pilot pressure is sent down either the ―close‖ or ―open‖ pilot line.
5. Since no pilot line is pressurized, neither pressure switch is activated.
6. The electronic card senses that no pressure switch has been operated and illuminates the ―block‖ lamp.
7. The ―press and hold‖ button is released; the ―block‖ lamp remains illuminated.
The ‘block’ position can be used to assist with the location of a hydraulic leak in the system by
systematically isolating the various BOP stack functions. It is also used to depressurize the pilot lines when
attaching junction boxes to the umbilical hose reels.
Note: The illumination of a push button lamp only indicates that a pilot pressure signal has been generated
and not that a function has been successfully operated subsea.
Hose Reels
The hose bundle as shown in Figure 8.3.13 is mounted on heavy duty reels for storage and handling and
are connected to the hydraulic control manifold by jumper hoses. The reels are driven by reversible air
motors and include a disc brake system to stop the reel in forward or reverse rotation.
Once the BOP has been landed and latched on to the wellhead, the control points on the side of the reel
are shut down and isolated to prevent interference with the full control system. The regulators on the reel
which control the manifold and annular pressures must also be isolated in case they dump pressure when
the jumper hose RBQ plate is attached as shown in Figure 8.3.14.
When the subsea control pod is run or retrieved, the junction box for the jumper hose is disconnected from
the hose reel. However in order to keep selected functions ―live‖ during running or retrieval operations, five
or six control stations are mounted on the side of the reel. These live functions include at least the riser
and stack connectors, two pipe rams and the pod latch. Figure 8.3.13 is a schematic of the hydraulic
system through which the power fluid flows to the controlled functions during reel rotation.
With the supply pressure isolated the 3-position, 4-way valves are used to vent any pressure that may
remain trapped in a pilot line holding an SPM valve open. This is necessary, as the reel is fitted with a
different type of valve to the control manifold manipulator valves. These valves look similar but do not vent
when placed in the ―block‖ position, see Figure 8.3.12(C).
Fig 8.3.13
Fig 8.2.14
The packer seals on the retrievable valve block are pressure balanced in a breakaway condition so that
there is no tendency for it to be blown out of the pocket if the pod has to be released under pressure.
Besides the latching system, packer seals and piping, the principal components of the retrievable valve
blocks are the SPM pilot valves and regulators.
The valve is a poppet type in which a sliding piston seals at the top and bottom of its travel on nylon seats.
In the normally closed position a spring attached to the top of the piston shaft keeps the piston on the
bottom seat and prevents the power fluid from passing through the valve to the exit port. Power fluid
pressure, which is permanently present, also assists in keeping the valve closed by acting on a small
piston area on the spindle. In this position fluid from the valve‖s associated operating piston is vented
through the sliding piston at ambient conditions.
When pilot pressure is applied to the valve the sliding piston moves up and seals against the upper seat
which blocks the vent ports and allows regulated power fluid to flow through the bottom section of the valve
to function the BOP. Note that the pilot fluid therefore operates in a closed system whilst the hydraulic
power or control fluid is an ―open‖circuit with all used fluid being vented to the sea.
As illustrated previously in Figures 8.3.12 (A), (B) & (C), two SPM pilot valves are required to operate a
BOP function.
Shown below is an illustration of a single SPM Valve.
Regulators
Each subsea control pod contains two regulators - one to regulate pressure for the ram preventers and one
to regulate the pressure for operating the annular preventers. Some control systems incorporate a third
regulator so that the operating pressure of each annular preventer can be individually manipulated.
Typical regulators are 1 l/2" hydraulically operated, stainless steel, regulating and reducing valves. As
shown in Figure 8.2.11 the output line of each regulator is tapped and the pressure roused back to a
surface gauge through the umbilical. This readback pressure is used to confirm that the subsea regulator is
supplying the power fluid at the pressure set by the pilot surface regulator.
Redundancy/Shuttle Valves
The two subsea control pods are functionally identical. When a pilot control valve (rams close for example)
is operated on the hydraulic control manifold a pilot signal is sent down both umbilicals so that the
associated SPM valve in each pod ―fires‖. If the pod selector valve is set on yellow then power fluid is sent
only to this pod and it is only through the SPM valve in this pod that the fluid will reach the ram operating
piston. The pod selection has no effect on the pilot system.
Once the yellow pod SPM valve ―fires‖, the power fluid passes through it to a shuttle valve, the shuttle
piston of which moves across and seals against the blue pod inlet. The fluid then passes through the
shuttle valve to move the ram to the close position. Fluid from the opposite side of the operating piston is
forced out through the ―ram open‖ shuttle valve and vented through the ―ram open‖ SPM valve and into the
sea.
Note that if the blue pod was now selected to open the rams; then the power fluid would flow to the ram
through the ―open‖ SPM on the blue pod but the fluid from the ―close‖ side of the piston would be vented
through the yellow pod SPM since the ―close‖ shuttle piston would still be sealing the blue pod inlet port.
The shuttle valve (s) should be located as near as possible to their relevant ports on the BOP stack since
the system is redundant only down as far as the shuttle valves. Figure 8.3.18 shows a NL Shaffer shuttle
valve.
Flowmeters
Flowmeters are generally mounted in the surface accumulator the bottles remain on line. Isolation of
bottles should only be done when a very close determination of the actual fluid supplied to a function must
PVD Training | 8.3 Subsea BOP Control Systems 76
PVD Training
Section 8. Subsea Well Control
be known (e.g., in the event of a problem while testing the BOP stack).
features are: a remotely controlled adjustable choke and adjustable choke systems (manual) to permit
control through either the choke or kill line, double valves upstream of each choke, an accurate pressure
gauge, and tie-ins to both drilling fluid and cement unit pump systems.
Fig 8.3.21 Example Choke and Kill Manifold for 5K, 10K, and 15K Rated Working Pressure Service Subsea
BOP Installations
Installation Guidelines
Recommended practices for planning and installation of choke manifolds for subseainstallations include:
a. The assembly connections, full-opening valves, fittings, piping, etc., subject to well or
pump pressure should be flanged, clamped, or welded and have a rated working
pressure at least equal to the rated working pressure of the blowout preventers.
Maintenance
Preventative maintenance of the choke assembly and controls should be performed regularly checking
particularly for wear and plugged or damaged lines. Frequency of maintenance will depend on usage.
Spare Parts
An adequate supply of spare parts is important for components subject to wear or damage or whose failure
seriously reduces the effectiveness of the manifold. Standardization of components is recommended to
minimize the inventory required. Although the inventory will vary from rig to rig, a generalized
recommended spare parts list includes:
Installation Description
Choke and kill lines for subsea installations are installed opposite one another on the exterior of the marine
riser and are of three types: integral, track or funnel.
Fig 8.3.22 Example Riser Mounted Kill and Choke Lines for Subsea BOP Installations
The integral type has the lines permanently installed on each marine riser joint, with pin and box
connectors stabbed and made up simultaneously with the riser connector. The track type has two guide
rails permanently installed on the marine riser which offers guidance to ―skates‖ attached to choke and kill
lines; Choke and kill lines are run after the riser has been installed. The third type has funnels attached to
the marine riser, which also permit choke and kill lines to be run after the riser is installed. Choke and kill
lines are normally 3 inches in nominal diameter or larger.
Installation Guidelines
Some of the more important considerations concerning subsea choke and kill lines are:
A. Connector pressure sealing elements should be inspected, changed as required, and tested
before being placed into service. Period pressure testing is recommended during installation.
Pressure ratings of all lines and sealing components should equal or exceed the rated working
pressure of the ram preventers.
B. Selection of choke and kill line connectors must take into consideration the ease of
connect/disconnect operations and the dependability of sealing elements for those emergency
situations where it is necessary to unlatch the riser from the BOP stack and then
latch/reconnect again prior to resuming normal operations.
C. Each choke and kill line should have two full opening valves adjacent to the preventers. These
valves are hydraulically operated and at least one on each line should be ―failsafe‖ in the
closed position. Periodic pumping through the valves is necessary since they are normally
closed and may become plugged if not occasionally flushed.
D. Locations of the choke and kill lines openings on the BOP stack depends on the particular
configuration of the BOP stack and the operator‖ s preferred flexibility for well control
operations. Sharp turns in the piping arrangement should be targeted where practical.
E. Flexible connections required for choke and kill lines both at the top and bottom of the marine
riser, should have a pressure rating equalling or exceeding the rated working pressure of the
ram preventers
Fig 8.3.23 Example types of flex connection on Tp of marine riser for choke/kill
F. Selection of the top connection should include consideration of criteria such as relative
movement between vessel and riser, the environment, type and temperature of fluids handled,
pressure integrity, service life, ease of connect/disconnect operations and replacement costs.
G. Bottom flexible connections (circumventing the flexible (ball) joint) have the same requirements
as the top connection but are even more critical due to their relative inaccessibility and the
environmental conditions under which they must operate. For deeper water operations,
particular considerations should be given to internal–external pressure integrity and reliability.
Fig 8.3.24 Example Types of Flex Connectors at Bottom of Marine Riser for C/K Lines
on the wire lines is directly proportional to the pressure of stored air. In general, as the vessel heaves
upward, fluid is forced out of the hydraulic cylinders thereby compressing air. As the vessel heaves
downward, pressure of the compressed air will cause the hydraulic cylinders to stroke in the opposite
direction.
Selection of tensioner should be based on load rating, stroke length, speed of response, service life,
maintenance costs, and ease of servicing. Maximum load rating of individual tensioners depends on the
manufacturer, typically ranging from 45,000 to 80,000 pounds and allowing maximum vertical vessel
motion of 30 to 50 feet. Design of the wireline system that supports the riser must take into consideration
the angle between the wireline and the axis of the telescopic joint and its influence on stresses.
The number of tensioners required for a specific operation will depend on such factors as riser pipe size
and length, drilling fluid density, weight of suspended pipe inside the riser, ocean current, vessel offset,
wave height and period, and vessel motion. Computer programs are available for riser analysis, including
tensioning requirements. Consideration should also be given to operating difficulties that might occur
should one of the tensioners experience wireline failure.
Periodic examination of riser tensioning system units should be made while in service, since the system
can cycle approximately 6000 times per day. Particular care should be taken to establish a wireline and
replacement program based on ton cycle life for the particular rig installation. Users should consult the
equipment manufacturer for general maintenance procedures and specifications recommendations.
Buoyancy
For deeper waters, it may be impractical from an operating viewpoint to install sufficient units capable of
providing adequate tensioning. In these cases, some types of riser buoyancy may be the solution (flotation
jackets, buoyancy tanks, etc.). Buoyancy reduces the top tensioning requirements but loses some of its
effectiveness as a result of the increased riser diameter exposing a greater cross sectional area to wave
forces and ocean currents. Selection of the optimum method and/or material for obtaining buoyancy
requires careful consideration of a number of factors, including water absorption, pressure integrity,
maintenance requirements, abuse resistance, and manufacturer‖s quality control. Several of these factors
are time and water-depth dependent. As water depth increases, these factors become more critical. A part
of any analysis for an optimum system should include consideration of the consequences of buoyancy
failure during operations.
destructive) of the connector and critical weld areas to reduce failures. Refer to API RP 2K: Recommended
Practice for Care and Use of Marine Riser Drilling Systems for specific information.
Annular Preventers
At least one annular preventer will be located on the LMRP. Other than the size, its design is the same as
that used on surface locations. One prudent addition often found is a ―surge bottle‖, which is a pre-charged
accumulator style bottle tied into the close chamber of the annular. The bottle acts as a buffer for tool joints
that are stripped through, allowing the pressured closing fluid to be momentarily stored rather than
dumped. This is required because the pressure regulator on the subsea pod cannot respond quickly
enough to the fluctuations caused by the passing tool joint. The surge bottle should be pre-charged to 500
to 700 psi plus hydrostatic adjustment (approx .445 psi/ft).
Ball Joints
A ball joint consists of a ball and socket assembly, similar to a human hip joint. The hydrostatic head of
fluids inside the marine riser impart a downward force against the inside of the ball, while the overpull of
the riser tensioners create an upward force on the socket. Both forces act upon the interface of ball to
socket. As such, a pressure balance system is required on a ball joint to reduce the bearing forces that
result from high tension loads across the face. Therefore, a hydraulic line must be run. In very deep water
or where high mud weights are used, the pressure required to compensate the ball joint may limit the
capacity of the seals.
For those vessels having a diverter system, a second flexible joint is sometimes installed between the
telescopic joint and the diverter to obtain required flexibility, or some type of gimbal arrangement may also
be used. For deep-water operations or unusually severe sea conditions, another flexible joint may be
installed immediately below the telescopic joint.
Mechanical strength requirements for flexible joints are similar to those for the remotely operated
connector. They should be capable of safely withstanding loads that might reasonable be encountered
during operations, both normal and emergency. In addition, the angular freedom of up to approximately 10
degrees should be accomplished with minimum resistance while the joint is under full anticipated load.
Hydraulic ―pressure balancing‖ is recommended for ball-type flexible joints to counteract unbalanced forces
of tensile load, drilling fluid density and seawater density. This pressure balancing also provides lubrication
for flexible joints.
Technical investigations and experience have shown the importance of close monitoring of the flexible joint
angle during operations to keep it at a minimum. One method of accomplishing this is by the use of an
angle–azimuth indicator. The flexible joint angle, vessel offset and applied (riser) tension are indications of
stress levels in the riser section.
For continuous drilling operations, the flexible joint should be maintained as straight as possible, normally
at an angle of less than 3 degrees: greater angles cause undue wear or damage to the drill string, riser,
BOPs wellhead or casing. For riser survival (i.e. to prevent overstressing) the maximum angle will vary
from about 5 degrees to something less than 10 degrees, depending on parameters such as water depth,
vessel offset, applied tension and environmental conditions. Drill pipe survival must also be considered if
the pipe is in use during those critical times of riser survival conditions.
considered a ―last option‖ when pressure integrity can not be achieved with metal-to-metal seals.
A high angle release model is also available (see Section 8.3.28) termed the HAR-H4. Its purpose is for
LMRP connection to the BOP Proper where higher angles of inclination (between the BOPs and riser
column) are conceivable, especially deepwater prospects. A much shorter swallow design permits
disconnects at up to 15 degree offsets. (However, realize that the rig may not be capable of disconnecting
above 8 degrees because of pod interference or moonpool binding). This high angle connector only
―swallows‖ about 13 inches of the locking mandrel, whereas the standard H-4 ―swallows‖ about 27 inches.
Note: All H-4 greasing operations should be performed with the connector removed from the test stump.
Otherwise, a hydraulic grease lock may develop
Both styles of Cameron connectors normally use an AX ring gasket to mate with the wellhead. Model 70 —
The clamp segment is engaged by a series of hydraulic pistons (see Figure 8.3.29). A common plumbing
arrangement has all 9 pistons dedicated to lock: six pistons to primary unlock, and three pistons to
secondary unlock. Unlike Vetco‘s ―fluid band‖, all pistons are individually hosed. Each piston is designed
to provide an unlocking force that is 80% greater than the locking force. One other feature is that the ring
gasket can be hydraulically locked in place while running or retrieving the BOP stack. Manual override is
standard.
Fig 8.2.29
The difference in this connector is that the clamp segment is engaged by an annular preventer
type of piston (see Figure 8.3.30). No hydraulic pistons are necessary, therefore no hoses. This
actuator piston design provides substantially higher clamping pre-loads than the hydraulic pistons.
HCH4. This model is based on the standard HC connector but is modified toconnect onto a Vetco
H4 wellhead profile
DWHC. This model was designed specifically for deep water applications. This connector is
designed to mate with the Cameron DW wellhead profile or the standard Cameron wellhead hub.
Segment and hub geometry and a large actuating piston area create a greater clamping force for
the higher load requirements of deep water drilling.
Fig 8.2.30
Hydrates
Severe problems have occurred due to gas percolation causing hydrates to form inside the wellhead
connector. Hydrates that form within the internal pockets (that are open to the sea) can prevent the
connector from being unlatched. As all connectors internal mechanisms have internal pockets that are
open to the sea, this is a problem that must be considered for every connector type.
The means of hydrate prevention has been to employ a method of ―diverting‖ the gas away from these
components. The primary method is to install a ―hydrate seal‖ between the base of the connector and the
wellhead housing. Additionally, some contractors and/or operators have modified the wellhead connectors
with a flushing port. This port allows access to the void areas by use of an ROV stab. The ROV can then
pump methanol to dissolve a hydrate plug. Another (secondary) method of diversion is to use diverting
plates on the subsea guidebase to deflect any percolating gas away from the entire wellhead connector
area.
Dril-Quip DX connector
Has a "hydrate diversion seal" at the base of the connector as standard design. A flushing port is not
standard in the design. However, the connector could be modified to allow such a function by utilizing one
of the excess ports that are available for indicator rods.
Vetco Connectors
Employ a bolt-on type"hydrate excluder seal". Machine modifications to the connector and the test stump
are required to facilitate installation of this seal. There has been some problems with the original design of
the seal and changes have been made. A full description of the modifications required can be found in
Appendix 4 ABB Vetco Gray Engineering Bulletin H-990750. H-4 Wellhead Connector Excluder Ring for
Hydrate or Shallow Flow Silt Contamination Cameron connectors employ a bolt-on type diverting seal at
the base of the connector. Bolt on seals can be used on all of the Cameron designs without modification
but the seal is not standard with the connector. Inclusion of a flushing port would require the connector to
be modified.
Guide Structure
The guide structure, a four-post tubular structure attached to the BOP assembly, is the primary guidance
means for guiding the complete BOP stack for primary alignment onto the permanent guide base
The upper section of the guide structure acts as primary guidance for the lower marine riser package. The
guide structure also acts as the structural mounting for the various components of the remote control
system and the choke/kill connectors or stab subs. The guide structure should have sufficient strength to
protect the BOP stack from damage during handling operations.
Tilt-Azimuth Indicator
Tilt-azimuth devices are attached to the flexible (ball) joint and/or marine riser to indicate the amount and
direction of deflection. With this information, proper corrective measures can be taken to minimise the
deflection.
Underwater Television
An underwater television system for visual inspection of the wellhead, BOP stack, marine riser, and other
allied components generally consists of a television camera and high intensity lights attached to a
telescoping guide frame. This guide frame normally attaches around two of the guide lines. The assembly
can be lowered by special umbilical cable which supports the package plus furnishes all electrical circuits
for the TV camera and lights. Surface equipment includes a powered reel for the umbilical cable and a TV
monitor with allied electronic equipment and camera remote control.
“Failsafe Valves”
―Failsafe‖ valves are required by the regulatory authorities in the UK and Norway, but not in other operating
areas of the world.
An operating scenario to consider is an emergency disconnect sequence or difficulties with the multiplex
BOP control system.
Prudent operating procedures suggest that the outer valve be closed first in the event full closure is not
achieved or erosion occurs preventing a seal. The outer gate will then act as a choke and increase the
likelihood that the inner valve will successfully close and obtain a seal.
All choke and kill valves on a subsea stack are hydraulically actuated gate valves, containing the same
seats, gates, stems, etc. as their surface counterparts. They vary from a surface stack ―HCR‖ valve in that
they contain a spring to assist gate closure (under most operating conditions). Hydraulic pressure applied
to the open port forces the valve stem down, compressing the spring. When this pressure is removed, the
spring assists in closing the gate. The term ―failsafe‖ valves is more recognizable, but recent tests with
mud and simulated deep water production conditions have shown the spring does not always close the
valve, especially where a plug in the opening port may occur. Manufacturers now stress the term ―spring
assist‖. Two subcategories exist for spring assist valves, ―line pressure closure‖ and ―system closure‖. Both
styles permit bi-directional sealing.
System closure valves have a hydraulic control fluid supply plumbed to both open and close ports.
However, if a hydraulic pressure failure occurs, the actuator spring should ensure the valve closes. Some
actuators (Cameron DF see Figure 8.3.33) have an exposed tailrod that the hydrostatic pressure can acts
on, enhancing in the hydrostatic pressure already acting on the close side hydraulic fluid. This serves to
PVD Training | 8.3 Subsea BOP Control Systems 97
PVD Training
Section 8. Subsea Well Control
counteract the hydrostatic forces imparted by the column of fluid acting on the open side hydraulic fluid,
which try to open the valve. Shaffer‘s ―HB Short Chest‖ is another example of a system closure valve.
Subsea valves can also have a pressure assist bottle tied into the closing chamber (accumulator style
bottles, pre-charged for water depth). When the valve opens, fluid from the closing chamber charges the
bottle, storing it to assist with the next closure.
It is required to always have two valves on each choke/kill outlet, providing redundancy. The actuators
require only 1500 psi to operate, but are rated to 3000 psi, should the higher operating pressure be
required. When possible, the valves should be mounted directly to the ram preventer outlets, eliminating
spools (and possible additional leak paths).
System Maintenance
Grease insert sealing failures on choke and kill line valves have occurred on a number of semi-
submersibles, or both old and new valves. It is recommended all ―high pressure‖ grease inserts be
replaced with certified ―high pressure‖ plugs prior to stump testing. However, it is critical that the valves are
greased. After each well these grease inserts should be reinstalled and each valve greased with OEM
recommended lubricant. These lubricants greatly enhance valve gate and seat life. A 3‖ valve will hold
approximately 4 lbs of grease.
Most subsea BOPs have eight failsafe valves. Typically one valve or one set (two valves) should be
disassembled, inspected and serviced after an average well (assuming 12-20 weeks for a well). API
recommends one spare valve of each size and type be kept onboard (RP53 9.4) so a swap out is usually
more efficient between wells, with the service performed while the stack is on bottom.
build up on BOP components, particularly valve gates and seats. Proper maintenance (greasing) programs
of the valves must be adhered to.
However, on wells that will drill through large sections of sub-sea, this standard procedure may not be
sufficient. It should be considered that all valves should undergo a complete service prior to use on a well
which will utilize a salt saturated mud system and drill large sections of sub-salt. Additionally, extra
diligence for the choke manifold valves maintenance is warranted.
Hydrate Considerations
Hydrates have formed and caused severe problems while killing gas influx kicks. In a well control situation,
the kick fluid leaves the formation at a high temperature, with an extended shut-in period of time it can cool
to seabed temperature. With high enough hydrostatic pressure at the mudline, hydrates could form in the
BOP and choke / kill lines.
Hydrates are created by the reaction of natural gas with water and occur under certain pressure and
temperature conditions. They form substances that consist of ± 10% hydrocarbon and ± 90% water that
range in texture from a "jelly-like" mush to a solid "ice-like" substance. Although the solids are similar in
appearance and shape to the physical properties of ice, they incorporate light hydrocarbons, carbon
dioxide, hydrogen sulphide, nitrogen and some other small compounds. Each hydrocarbon (guest)
molecule is surrounded by a number of water (host) molecules that create a cage. There are roughly 17
water molecules for each gas molecule, so water is the predominant component of these solids.
The danger of hydrates comes from several basic physical properties, the plugging nature of the hydrate
phase itself and its tendency to adhere to metal surfaces. And the large gas content of the hydrate phase
which, upon melting, can release up to 170 scf of gas per cubic foot of hydrates. Furthermore, hydrate
formation can cause the breakdown of a mud system by fresh water extraction from the mud to form the
hydrate structure.
Hydrates formation in drilling fluids is a relatively new experience offshore.
Temperature, pressure and gas composition determines the conditions for hydrate formation. Solidification
of the hydrate occurs as the temperature decreases and/or pressure increases with the proper amount of
gas and water present. In a drilling situation hydrates can format temperatures well above freezing
temperature of water due to the pressure exerted by the hydrostatic head. That statement should not be
construed to mean that hydrates are only a concern in deep water. Hydrates are a serious concern any
time that cold temperatures meet high pressure. The common condition in all hydrate formation
experienced offshore has been extended shut-in periods. The well control operations should start as soon
as possible after recording the shutin pressure parameters.
The significant effects of the hydrate formation in drilling operations are:
Plugging of choke and kill lines
Formation of a plug at or below the BOP, preventing monitoring of pressures below the BOP.
Formation of a plug around drillstring in riser, BOP or casing
Formation of a plug in ram cavity of a closed BOP- preventing it from fully opening.
In order to prevent hydrate formation during a kick situation, mineral oil base fluid can be spotted across
the BOP and in the choke / kill lines. In the event of a gas kick when a water based mud system is being
used, be prepared to spot a glycol / salt pill in the BOP, choke / kill lines.
Deep water and/or cold water locations, which will explore for gas should take into consideration the
prediction and prevention of hydrates during the planning phase.
Choke Manifold
A floating vessel‖s choke manifold is often more elaborate than it‖s surface counterpart (as depicted in
Figure 8.3.34). Often times, two hydraulic chokes with at least one manual type choke are present.
Depending on the choke placements, various flow path combinations can be available, should either a
washout or plug occur during well control operations. Both the choke and kill lines terminate at this
manifold, where fluids can be circulated through either one (The mud pumps can be routed into the
manifold, and most rigs have provisions to tie in the cement unit as well). Also, depending on kill line outlet
placement on the BOP, pressure at the BOPs can be monitored via the kill line during well control
operations, reducing the need for ―choke line friction determinations. The remaining manifold
components, including gate valves, pressure gauges and choke actuators, are the same as those found on
- surface operations
Note: Grease insert sealing failures on choke manifold valves have occurred. It has been recommended
all „high pressure‟ grease inserts be replaced with certified „high pressure‟ plugs prior to testing and system
maintenance.
This allows 3,000 psi pilot fluid, located at the pod, to flow into the function – controlling SPM valve almost
instantaneously.
The SPM valve moves off seat immediately and the overall operating time is reduced by half or more.
All other features of the standard hydraulic control apply. A schematic of the quick response system is
shown in Figure 8.3.35.
Fig 8.3.35
A MUX processor is mounted above each pod/solenoid rack in a one atmosphere bottle. A multiplex
control bundle size is generally 1 to 1-1/2" OD. (The electronic signal and solenoid valve arrangement is
analogous to a pre-pressured control line and extra pilot operated valve in a quick-response system.) EH
and MUX pods are larger than hydraulic pods and are typically not remotely retrievable.
Solenoids
Solenoid valves are used to send SPMs hydraulic signals. See Figure 8.3.36. With two additional equip-
ment packages, these control systems are obviously much more complex. The advan-tage of each is a
lower response time (i.e., the function signal is delivered to the pod much faster). Rams will respond in 6-8
seconds, bag-type annulars in 12-18 seconds. MUX has an additional advantage over a straight EH
system with the control cable options. Since only one pair of signal wires is required, extra features such
as riser angle indicator read-back or coaxial cables for stack mounted TV can be added without a
significant bundle OD increase. Additional stack functions may be added easily since all signals travel via
one pair of wires.
1. On a floating rig with an indirect hydraulic control system manifold regulators are used in the Subsea
control pods to regulate power fluid.
Which of the following hydraulic BOP functions are operated using this regulated power fluid?
(Select SIX answers)
a) Annular BOPs.
b) Ram BOPs.
c) Riser Connector.
d) Wellhead Connector.
e) Wedge Locks.
f) Fail safe valves.
g) Mini collet connectors.
h) Diverter.
4 points
2. What is the maximum allowed response time for a subsea annular preventer according to API RP 53?
a) 30 seconds.
b) 45 seconds.
c) 1 minute.
d) 2 minutes.
e) Less than 15 minutes.
2 points
3. Which of the following statements describe the functions performed by the pilot control lines in the pod
control hose?
(Select FOUR answers)
a) Pilot lines allow regulation of the subsea regulators inside the control pods.
b) Pilot lines can be activated by the four way manipulator valves on the hydraulic closing unit.
c) Pilot lines operate SPM valves which allow hydraulic fluid to flow to the relevant BOP function.
d) Pilot lines are activated by manifold pressure.
e) Pilot lines are operated by annular pressure.
f) Pilot lines are operated by pilot pressure which is supplied by the accumulators.
4 points
4. Which of the following statements best describe a manipulator valve?
a) A manipulator valve is a 3 position 4 way valve that when activated allows regulated power fluid to be directed
to the relevant SPM valves in the control pods.
b) A manipulator valve is a 3 position 4 way valve that when activated directs unregulated power fluid to the
active pod on the subsea stack.
c) A manipulator valve is a 3 position 4 way valve that when activated directs regulated pilot pressure to the
relevant SPM valves in the active control pod.
d) A manipulator valve is a 3 position 4 way valve that when activated allows pilot pressure to be directed to the
relevant SPM valves in the control pods.
2 points
5. When a ram BOP is activated to the close position from the remote and/or central hydraulic control unit
on a floating rig, certain functions occur. Identify the correct functions from the list below.
(Select TWO answers)
a) An SPM valve fires in the active pod only.
b) SPM valves fire in both the active and redundant pods.
c) The ram open SPM valve or valves will be vented.
d) The ram closed SPM valve or valves will be vented.
4 points
6. Figure SS7- 001 below illustrates a Sub Plate Mounted valve (SPM) used in the In-direct hydraulic control
system in a Subsea BOP system.
Identify whether the valve is in the open or closed position.
a) The SPM valve is in the open position, allowing hydraulic fluid to flow to the BOP function.
b) The SPM valve is in the closed position allowing power fluid from the BOP function to be vented.
18. Which of the following locking systems requires separate hydraulic control lines?
a) Wedge Lock.
b) Ultra Lock.
c) Pos Lock.
d) MPL.
1 point
19. On a ram type preventer, on a surface stack, in which position will the 4-way valve be put to assist with
the removal of the bonnet after backing off the bonnet bolts?
a) Open.
b) Close.
c) Neutral (Block).
d) Any position, it does not matter.
1 point
20. Which of the following are disadvantages when using a float valve?
(Select THREE answers)
a) If reverse circulation is required.
b) For obtaining drill pipe shut in pressure reading.
c) To prevent flow back while tripping.
d) Minimising surge pressure.
4 points
21. Which piece of equipment on a floating rig is considered to be the weakest point when diverting a
shallow gas kick?
a) The seals between marine riser joints.
b) The ball joint on the lower marine riser package.
c) The ball joint on the diverter housing.
d) The slip joint packers.
e) The insert packer (annular packing element).
2 points
22. An accumulator cylinder at surface has a pre-charge pressure of 1000 psi.
The pressure gradient for sea water is 0.445 psi/ft.
What will be the correct pre-charge pressure if the cylinder is used subsea in 1000 feet of water?
a) 555 psi
b) 445 psi
c) 1445 psi
3 points
23. Figure SS7-005 illustrates the main components of the Lower Marine Riser Package (LMRP) used for
subsea drilling operations.
Place the corresponding number in box next to the correct locking device.
a) Connector.
b) Annular Preventer.
c) Flex Joint.
d) Control Pod.
1 point of each correct answer
25. Figure SS7-007 illustrates a Hydril GL annular BOP. Which of the following statements are correct when
this preventer is used in a Subsea operation?
(Select TWO answers)
a) The secondary chamber allows balancing the opening force of the piston created by drilling fluid hydrostatic
pressure in the marine riser.
b) Lowest required hydraulic closing pressure when closing chamber and secondary chamber are connected.
c) Lowest required hydraulic closing pressure when opening chamber and secondary are connected.
3 points
26. Which one of the following statements about the “Memory Function” on a Subsea BOP Driller‟s panel is
true?
a) Memory Function indicates the previous position of the stack function before the ―Block position‖ was
selected.
b) Memory Function indicates a malfunction by giving a permanent light on the alarm panel after an alarm has
been acknowledged and the audible alarm has stopped.
c) Memory Function reminds the Driller to add anti-freeze fluid when the temperature drops below a set level.
d) Memory Function reminds the Driller to engage wedge locks before hanging off the drill string on the ram
BOPs.
3 points
27. On a subsea BOP installation, what is the advantage of using a kill line gauge to monitor changes in
pressure during a well kill operation?
a) The kill gauge is always more accurate.
b) The effect of choke line friction is reduced to a quarter when monitoring of the kill line gauge during the kill
operation.
c) Maintaining a constant pressure on the kill line gauge when starting or stopping the pump compensates for
the effect of choke line friction.
d) The effect of choke line friction is reduced to a half when monitoring on the kill line gauge during the kill
operation.
2 points
28. Figure SS7-008 illustrates part of the hydraulic “principle of redundancy” utilised to control functions on
the subsea BOP stack.
Which statement about the Shuttle valves on a subsea BOP stack is correct?
a) The Shuttle valves require 3000 psi to operate.
b) The Shuttle valves are directly controlled by pilot fluid.
c) The Shuttle valves are 3 position/4 way valves.
d) The Shuttle valves isolate the control fluid system between the active and the redundant pods.
e) The Shuttle valves isolate the hydraulic pilot system from the hydraulic control system.
3 points
29. When is the accumulator bank isolation valve closed on a hydraulic BOP control unit according to API
RP 16E?
a) During drilling ahead.
b) During the testing of the BOP‘s.
c) During any testing of accumulator unit, transportation and servicing.
d) When filling the reservoir with soluble oil.
3 points
1. B, C, D, E, F, G e) 2, Piston
2. C f) 6, Tail Rod
3. A, B, C, F 14. E
4. D 15. 2, 4, 5, 6, 1, and then 7
5. B, C 16. B
6. A 17. a) 1, Quick Release Top
7. B b) 8, Piston
8. A c) 7, Pusher Plate
9. B d) 9, Hydraulic Closing Port
10. a) True e) 5, Ring Groove
b) True 18. A
c) True 19. B
11. a) 2, Hydril 20. A, B, D
b) 3, Shaffer 21. D
c) 1, Cameron 22. C
d) 3, Shaffer 23. a) 7, Connector
12. a) 6, Control Pod b) 5, Annular Preventor
b) 7, Telescoping Joint c) 1, Flex Joint
c) 3, Annular Preventer d) 6, Control Pod
d) 4, Hose Reel 24. a) 9, Drill Pipe
e) 5, Choke and Kill lines b) 7, Standard (Outer) Packer
f) 8, Wellhead Connector c) 5, Diverter Packer Closing Port
g) 2, Hydraulic Unit d) 4, Flow Line Seals
h) 9, LMRP connector e) 8, Insert Packer Lockdown Dogs
i) 1, Drillers remote panels 25. A, B
13. a) 3, Locking Wedge 26. A
b) 4, Locking Port 27. C
c) 5, Extension Tail Rod 28. D
d) 1, Unlocking Port 29. C