ONLINE

PERMIT TO OPERATE
(PTO) APPLICATION

Engr. Melchy C. Enriquez


PCAPI 4A Vice President

TLC: The Learning Curve Series


ON-LINE PERMITTING
Permitting for Air Quality Management
Permit to Operate (PTO)-Air Pollution Control Facility

Requirements of RA 8749
(The Phil. Clean Air Act)

TLC: The Learning Curve Series


ON-LINE PERMITTING
LEARNING OBJECTIVES

At the end of this session, the participants


shall be able to:

➢ Learn the permits and permitting


requirements of RA 8749 or the Clean Air
Act
➢ Identify the requirements in securing
Permit to Operate (PTO)
➢ Learn to access and use the OPMS for
PTO application online

TLC: The Learning Curve Series


ON-LINE PERMITTING
OUTLINE OF THE PRESENTATION

1. Introduction
2. Illustrative Demonstration of Online
PTO Application
3. Compliance to PTO Conditions
4. Reminders and Tips

TLC: The Learning Curve Series


ON-LINE PERMITTING
INTRODUCTION

Objective of RA 8749: The Phil. Clean Air Act of 1999

Achieve and to meet the national


maintain clean air quality guidelines
air for criteria pollutants

While minimizing the possible associated


impacts on Philippine economy

TLC: The Learning Curve Series


ON-LINE PERMITTING
INTRODUCTION

The Clean Air Act sets the


standard limits for Air Quality

➢ Point Source (smokestack) Emission


standards for industries CO
➢ Ambient Air Quality Standards to NOx
protect public health and welfare
SO2

TLC: The Learning Curve Series


ON-LINE PERMITTING
NESSAP

1. National Emission Standard for Source Specific Air Pollutants (1/3)

TLC: The Learning Curve Series


ON-LINE PERMITTING
NESSAP

1. National Emission Standard for Source Specific Air Pollutants (2/3)

TLC: The Learning Curve Series


ON-LINE PERMITTING
NESSAP

1. National Emission Standard for Source Specific Air Pollutants (3/3)

TLC: The Learning Curve Series


ON-LINE PERMITTING
NAAQS

2. National Ambient Air Quality Standards for Source Specific Air Pollutants

TLC: The Learning Curve Series


ON-LINE PERMITTING
PERMITTING REQUIREMENTS FOR
INDUSTRIES

➢Permit to Operate (PTO)


shall be secured for any
source emitting regulated air
pollutants.
➢ Facilities w/ more than one
source may group the
sources under a single
permit application.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PERMITTING REQUIREMENTS FOR PTO

PROCESS FLOW
PERMIT TO OPERATE –AIR POLLUTION SOURCE AND CONTROL INSTALLATION
Air Quality Section
Applicant Evaluate submitted application and
Start Submit online application for requirements within 20 days
PTO with corresponding including inspection/sampling and
requirements endorses to Pollution Control
Division (PCD)

PCD
Conduct final evaluation and
recommends approval to the EMB
Regional Director

Work on the supporting


documents prior to PTO EMB Regional Director
Online Application End Review and approval of the PTO

TLC: The Learning Curve Series


ON-LINE PERMITTING
SUPPORTING DOCUMENTS FOR
NEW APPLICANT
✓ Copy of Certificate of Accreditation of PCO or
appointment/ designation as such by the Managing Head
✓ Receive page of submitted test plan /test report with
accreditation certificate*
✓ Copy of recent Permit to Operate*
✓ Proof of compliance to permit conditions*
✓ Self Monitoring Reports (if applicable)*
✓ ECC/CNC copy
✓ Hazardous Waste Registration Certificate
✓ Brochure /Picture
✓ Other requirements (e.g. Dispersion Model)
✓ Ambient Air Test (if required)
TLC: The Learning Curve Series
ON-LINE PERMITTING
TYPES OF PTO

Temporary PTO Regular PTO


• Issued for commissioning, • Issued after complying with all
sampling and inspection the requirements and
purposes which are valid for 3 conditions of the IRR of the
months. Clean Air Act such as Ambient
• If required test results are not and Emission Standards (DAO
submitted temporary permit 2004-26)
may be issued to allow
compliance testing to be
Conduct Stack Testing
conducted
before applying for PTO
online so that Regular PTO
will be issued by EMB.
TLC: The Learning Curve Series
ON-LINE PERMITTING
DAO 2016-28 NEW FEES AND CHARGES
FOR PTO APPLICATION
Permit Capacity Amount of Fee
Environmental User’s Fees/Emission Permits
1. Air Pollution / Filing Fee P 600.00
2. Permit to Operate for the following:
Steam Boilers and Oil heaters rated HP-up to 1-100HP P 280.00
100 200 HP P 380.00
300HP P 560.00
400HP P 750.00
500HP P 950.00
Over 500 P 1,130.00
Electric Furnaces and Ovens 125 P 280.00
Per kilowatt- up to 75 175 P 380.00
225 P 560.00
325 P 750.00
Over 325 P 940.00
P 1,130.00

TLC: The Learning Curve Series


ON-LINE PERMITTING
ILLUSTRATIVE DEMO
OF ONLINE PTO APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Go to the emb.gov.ph
Scroll the page down TLC: The Learning Curve Series
ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“FOR ACTION” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“MY APPLICATION” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
“MY APPLICATION” TAB How does it look like?
Another PCO’s
xxxxxxxxx

account

xxxxxxx Permit to Operate


xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“FOR ACTION” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“PERMIT TO OPERATE” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“PERMIT TO OPERATE” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

RENEWAL OF PTO

PTO-R4A-21-01363

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“PERMIT TO OPERATE” TAB How does it look like?

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

STEP 1: GENERAL INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 1: GENERAL INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 1: GENERAL INFORMATION

Attach a pdf copy of


existing PTO

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
Search from the google map

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 2: AIR POLLUTION SOURCES CONTROL DEVICE AND PROCESSS

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 2: AIR POLLUTION SOURCE CONTROL DEVICE AND PROCESS

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
AIR POLLUTION CONTROL DEVICES

Select the control device


from the dropdown

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 3: STACK TESTING INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 3: STACK TESTING INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

DENR EMB ACCREDITED STACK SAMPLERS

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 3: STACK TESTING INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 3: STACK TESTING INFORMATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
US EPA Test Methods;
40 CFR 60, Appendix A

Perf. Spec Parameter Method


3 O2 & CO2 3,3A
- H2 O 4
2 SO2 6, 6C
2 NOx 7,7A,7B,7E
2&3 NOx & CO2 7C,7D
4 CO 10,10A,10B
7 H2 S 11
5 TRS 16,16A
6 Flow Rate 1-4

3
5
TLC: The Learning Curve Series
ON-LINE PERMITTING
PTO ONLINE APPLICATION

Method 6

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 4: POLLUTION DETAILS

TLC: The Learning Curve Series


ON-LINE PERMITTING
Average
PTO ONLINE APPLICATION concentration
from Stack
Sampling
Test Report

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 4: POLLUTION DETAILS

TLC: The Learning Curve Series


ON-LINE PERMITTING
Average
PTO ONLINE APPLICATION concentration
from Stack
Sampling
Test Report

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 4: POLLUTION DETAILS

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 4: POLLUTION DETAILS

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

IF YOU WANT TO DELETE DATA

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 5: DOWNLOAD APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
DOWNLOADED
PTO APPLICATION FORM
DOWNLOADED
PTO APPLICATION FORM

Print 4 copies of PTO


application form and
have them
NOTARIZED.
PTO ONLINE APPLICATION
STEP 5: DOWNLOAD APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
STEP 6: UPLOAD REQUIREMENTS

Maximum filesize is 20 MB

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

xxxxx

xxxxxxxx
xxxxxxxx xxxxxxxx
xxxxx xxxxxxxx

xxxxxxxx
xxxxxxxx
xxxxxxxx
xxxxxxxx

xxxxxxxx

xxxxxxxx
xxxxxxxx

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

xxxxxxx

xxxxxxx
xxxxxxx
xxxxxxx

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Provide the information to all


requirements with *

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
Once all attachments were uploaded, press “Finalize Application”

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Once all attachments were uploaded, press “Finalize Application”

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Once the online application is completely


submitted, EMB will send a notification via email

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

ONCE SUBMITTED ONLINE EMB WILL SEND AN EMAIL NOTIFICATION

EMB OPMS Start Application – Permit to Operate

Hi Ronel Reyes.
You submitted an application for a Permit to Operate. A screening officer will not check your application. You can check the status of your
application by logging into the system.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

May

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
EMB WILL REVIEW THE APPLICATION
After EMB’s review, a notification will be sent to your email

Hi Ronel Reyes.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

You will be directed to this page…

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

You will be directed to this page…

Permit to Please submit the


Operate latest Stack Sampling
Report.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Comply with the additional requirements and update your application.


Select Submit requested information as an action taken

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

May

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

AFTER SUBMISSION OF ADDTITIONAL SUPPORTING DOCUMENTS


Another notification will be sent to your email
You will be advised to pay for the PTO Fee

Hi Ronel Reyes.

An application has been returned to you by one of our staff. You may view and take action on this application at
the EMB OPMS website.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

AFTER SUBMISSION OF ADDTITIONAL SUPPORTING DOCUMENTS


Another notification will be sent to your email
You will be advised to pay for the PTO Fee

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
You will be directed to this page…

Permit to
Operate

TLC: The Learning Curve Series


ON-LINE PERMITTING
Print the Order of
SAMPLE OF ORDER OF PAYMENT Payment

PTO 21-xxxx PTO 21-xxxx

PTO PTO

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
PTO
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxx xxxxxx

600.00
9,500
Permit to Operate
10.100.00
PAYMENT OPTIONS

1. Payment at EMB RO Cashier


2. Online payment via landbank.com

TLC: The Learning Curve Series


ON-LINE PERMITTING
PAYMENT OPTIONS
Payment at the EMB Regional Office

Go to the EMB RO Cashier and


pay for the PTO Application Fee

TLC: The Learning Curve Series


ON-LINE PERMITTING
PAYMENT OPTIONS

1. Payment at EMB RO Cashier


2. Online payment via landbank.com

TLC: The Learning Curve Series


ON-LINE PERMITTING
PAYMENT OPTIONS
Online Payment of the PTO Application Fee

Pay online via Landbank.com

TLC: The Learning Curve Series


ON-LINE PERMITTING
PAYMENT OPTIONS
Online Payment of the PTO Application Fee

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION
You will be directed to this page…

Permit to
Operate

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Once paid, update the payment information section

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

Once paid, update the payment information section

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

May

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

AFTER SUBMISSION OF PAYMENT INFORMATION

A final notification will be sent to your email


You will be advised to you application for PTO was APPROVED
EMB OPMS Application for Permit to Operate - Approved

Hi Ronel Reyes.
Your application for Permit to Operate with number 112345 was approved. Please visit the following link to view your certificate.

TLC: The Learning Curve Series


ON-LINE PERMITTING
PTO ONLINE APPLICATION

“FOR ACTION” TAB


xxxxxxxxx

xxxxxxx Permit to Operate


xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx
xxxxxxx

TLC: The Learning Curve Series


ON-LINE PERMITTING
Compliance to
PTO Conditions

TLC: The Learning Curve Series


ON-LINE PERMITTING
SAMPLE OF ISSUED PTO
xxxxxxxxxxxxx
Date of Issuance of PTO XXXXXX

XXXXXXXXXXXXXXX xxxxxxxxxxxxx
Company Name and Address xxxxxxxxxxx

Description of Pollution Source xxxxxxxxxxxxx

Installation

Permit Conditions of a Mfg. Plant

Validity of Permit & Expiration

Signatures
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 1:
That the permittee shall install a Continuous Emissions Monitoring System (CEMS)
in compliance with RA 98749;

Ways to Comply
• DAO 2007-22 provides the guidelines for the requirements of the CEMS
• Criteria/Specifications for the CEMS when required for each applicable pollutant emitted by a
given source:

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 2:
That the CEMS’ Relative Accuracy Test Audit (RATA) shall be conducted
annually. RATA Report shall be submitted to this office prior to
renewal;

Ways to Comply
DAO 2007-22 Section 6 item 6:
• RATA must be performed annually by industries in the presence of
EMB personnel.
• A thirty (30) day notice should be presented to EMB prior to the
conduct of RATA.
• RATA is conducted to determine CEMS compliance to the RA.

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 3:
Operating conditions under this permit shall be based on the average operating
conditions during the previous CEMS results in compliance with the emission
standards for specific pollutants.

Ways to Comply
• Maintain condition of the Air Pollution Devices as when the testing of the
CEMS was conducted
• There should be no changes on the mode of operation of the fuel burning
equipment

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 4:
That the permittee shall install closed circuit television (CCTV) camera
installed at the stacks. The CCTV shall be a web-based and capable of
real-time viewing and readily accessible by the DENR-EMB.

Ways to Comply
• The plant provides a web-based CCTV camera that is accessible to
the DENR EMB IVA personnel via internet.
• DAO 2017-14 requires large industries with emission of greater
than 750Tonnes/yr to re-program the CCTV and CEMS data to the
EMB online information database.

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 5:
This permit is subject to revocation if found violating the Ambient
and Source Emission Standards and other provisions of the Clean Air
Act and its IRR.

How to comply

• Conduct of monitoring of plant emissions and ambient air quality


monitoring
• Results of emission monitoring shall conform to the Ambient and
Source Emission Standards of the Phil. Clean Air Act

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 6:
That any authorized DENR-EMB personnel shall be allowed unconditional
access to conduct an on- the-spot inspection and monitoring w/o prior notice
to the proponent .

How to Comply

• Allow all DENR EMB personnel to conduct an on-the-spot inspection and


monitoring at the plant at all times

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE
CONDITIONS OF THE PTO
Permit Condition No. 7:
That non-compliance of any of the conditions set forth herein shall be sufficient
cause for the suspension or cancellation of this permit and /or payment of fine in
an amount not to exceed ten thousand pesos (PhP 10,000.00) for every condition
violated;

How to Comply

• Always review the conditions of the permit and ensure 100% compliance
• Post the PTO in conspicuous place and near the equipment

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE CONDITIONS OF
THE PTO
Permit Condition No. 8:
Deadline of Submission of SMR
8. That a Self-Monitoring Report (SMR) on the operation and maintenance of
the aforesaid installations shall be made quarterly and submitted based on
the following schedule.
Province 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
Cavite Mar. 23-30 Jun. 23-20 Sept. 23-30 Dec. 23-30
Laguna Apr. 8-15 Jul. 8-15 Oct. 8-15 Jan. 8-15
Batangas Apr. 1-7 Jul. 1-7 Oct. 1-7 Jan. 1-7
Rizal Mar. 7-14 Jun. 7-14 Sep. 7-14 Dec. 7-14
Quezon Mar 15-22 Jun. 15-22 Sep. 15-22 Dec.15-22

TLC: The Learning Curve Series


ON-LINE PERMITTING
COMPLIANCE TO THE CONDITIONS
OF THE PTO Prepare a Matrix of
Compliance Status

TLC: The Learning Curve Series


ON-LINE PERMITTING
REMINDERS AND TIPS

• Unannounced Inspection / Visit by EMB Personnel

• Unannounced Air Emission Testing by EMB Personnel

• PCO to follow-up status of online application

• Payment of fees once the PTO is evaluated

• Other supporting documents might be required by


EMB

TLC: The Learning Curve Series


ON-LINE PERMITTING
REMINDERS AND TIPS

TLC: The Learning Curve Series


ON-LINE PERMITTING
EFFECTIVITY OF PTO

✓Temporary Permit to Operate is valid for 3 months

✓Regular Permit to Operate is valid for a maximum of five (5)


years from the date of issuance

TLC: The Learning Curve Series


ON-LINE PERMITTING
GROUNDS FOR REVOCATION

Grounds for Suspension of Revocation of Permit


✓ Non compliance with or gross violation of any provisions of the
CAA IRR or permit condition.
✓ Deliberate or negligent submission of false information in the
application for permit that lead to the issuance of permit
✓ Deliberate or negligent submission of false monitoring data or
report required in the PTO
✓ Refusal to allow lawful inspection conducted by EMB authorized
personnel
✓ Other grounds provided by law.

TLC: The Learning Curve Series


ON-LINE PERMITTING
Thank you!