PERHITUNGAN PEKERJAAN STRUKTUR

PROYEK : PEMBANGUNAN KCU BCA BUKIT DARMO, SURABAYA


Lantai : 3

No Item Pekerjaan Sat Uraian Perhitungan

1 PEKERJAAN PEMBESIAN
Selimut beton = 0.05 m
1.1 Type K3 16 bh Tinggi / Panjang Overlap Hook Jmlh Besi Berat Jmlh Kolom Volume Besi Volume Beton Volume B
Dimensi ( 0.8 x 0.8 ) (m1) (m) (m) (btg) (kg/m1) (bh) (kg) (m3)
- Tulangan Utama = 24 D 19 kg 4.20 + 0.68 + - x 24.00 x 2.23 x 16.00 = 4,170.53 43.01
- Sengkang
SK A (Tul. Sengkang)
Ujung = D 13 - 100 kg 2.80 + - + 0.16 x 11.50 x 1.04 x 16.00 = 566.69
Tengah = D 13 - 150 kg 2.80 + - + 0.16 x 15.00 x 1.04 x 16.00 = 739.15
Ujung = D 13 - 100 kg 2.80 + - + 0.16 x 11.50 x 1.04 x 16.00 = 566.69
SK B (Tul. Ekstra)
Ujung = D 13 - 100 kg 2.80 + - + 0.62 x 11.50 x 1.04 x 16.00 = 656.40
Ujung = D 13 - 100 kg 2.80 + - + 0.62 x 11.50 x 1.04 x 16.00 = 656.40

1.2 Type K4 12 bh Tinggi / Panjang Overlap Hook Jmlh Besi Berat Jmlh Kolom Volume Besi Volume Beton Volume B
Dimensi ( 0.9 x 0.9 ) (m1) (m) (m) (btg) (kg/m1) (bh) (kg) (m3)
- Tulangan Utama = 28 D 19 kg 4.20 + 0.68 + - x 28.00 x 2.23 x 12.00 = 3,649.21 40.82
- Sengkang
SK A (Tul. Sengkang)
Ujung = D 13 - 150 kg 3.20 + - + 0.16 x 8.00 x 1.04 x 12.00 = 335.67
Tengah = D 10 - 150 kg 3.20 + - + 0.12 x 15.00 x 0.62 x 12.00 = 368.42
Ujung = D 13 - 150 kg 3.20 + - + 0.16 x 8.00 x 1.04 x 12.00 = 335.67
SK B (Tul. Ekstra)
Ujung = D 13 - 150 kg 4.80 + - + 0.94 x 8.00 x 1.04 x 12.00 = 573.72
Tengah = D 10 - 150 kg 4.80 + - + 0.72 x 15.00 x 0.62 x 12.00 = 612.55
Ujung = D 13 - 150 kg 4.80 + - + 0.94 x 8.00 x 1.04 x 12.00 = 573.72

1.3 Type K2 3 bh Tinggi / Panjang Overlap Hook Jmlh Besi Berat Jmlh Kolom Volume Besi Volume Beton Volume B
Dimensi ( 1.4 x 0.4 ) (m1) (m) (m) (btg) (kg/m1) (bh) (kg) (m3)
- Tulangan Utama = 32 D 16 kg 4.20 + 0.57 + - x 3.00 x 1.58 x 3.00 = 67.75 7.06
- Sengkang
SK A (Tul. Sengkang)
Ujung = D 13 - 100 kg 3.20 + - + 0.16 x 11.50 x 1.04 x 3.00 = 120.63
Tengah = D 10 - 150 kg 3.20 + - + 0.12 x 15.00 x 0.62 x 3.00 = 92.11
Ujung = D 13 - 150 kg 3.20 + - + 0.16 x 8.00 x 1.04 x 3.00 = 83.92
SK B (Tul. Ekstra)
Ujung = D 13 - 100 kg 1.80 + - + 0.94 x 11.50 x 1.04 x 3.00 = 98.35
Ujung = D 13 - 100 kg 1.80 + - + 0.94 x 11.50 x 1.04 x 3.00 = 98.35
Total = 14,365.93 90.89

REKAP BERDASARKAN DIAMETER BESI :


D 10 = 1,073.08 Kg
D 13 = 5,405.36 Kg
D 16 = 67.75 Kg
D 19 = 7,819.75 Kg
+
Total = 14,365.93 Kg
No Item Pekerjaan Sat Uraian Perhitungan

-
Uraian Perhitungan Volume Reff. Dwg.

14,365.93

Volume Bekisting
(m2)
215.04

Volume Bekisting
(m2)
181.44

Volume Bekisting
(m2)
45.36

441.84
Uraian Perhitungan Volume Reff. Dwg.
REKAP BERDASARKAN DIAMETER BESI :
D 10 = 1,073.08 Kg
D 13 = 5,405.36 Kg
D 16 = 67.75 Kg
D 19 = 7,819.75 Kg
+
Total = 14,365.93 Kg