Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 202

STANDAR HARGA SATUAN DASAR UPAH

HARGA SATUAN DASAR


(TIDAK TERMASUK
NO MATERIAL SATUAN KODE
PROFIT & OVERHEAD)
(Rp)

A. UPAH
1 Pekerja Org/hari L. 01 105,000.00
2 Tukang Gali / Batu / Tembok / Kayu /Besi / Cat / Pipa / Cor / Semen / Listrik / Pancang Org/hari L. 02 125,000.00
3 Kepala Tukang Org/hari L. 03 145,000.00
4 Mandor Org/hari L. 04 155,000.00
5 Ahli alat berat (mekanik) Org/hari L. 07 125,000.00
6 Operator Alat Berat Org/hari L. 08 170,000.00
7 Pembantu Operator Org/hari L. 09 100,000.00
8 Supir Truk Org/hari L. 10 115,000.00
9 Kenek truk Org/hari L. 11 80,000.00

STANDAR HARGA SATUAN DASAR BAHAN

HARGA SATUAN DASAR


(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

B. BAHAN PENGISI
1 Batu Kong M³ 300,000.00
2 Batu Sap Pinang M³ 320,000.00
3 Batu pecah 15-20 cm M³ 335,000.00
4 Batu pecah 10-15 cm M³ 350,000.00
5 Batu pecah 3-5 cm M³ 405,000.00
6 Batu pecah 2-3 cm M³ 435,000.00
7 Batu pecah 1-2 cm M³ 475,000.00
8 Batu pecah 0,5-1 cm M³ 500,000.00
9 Stone Dust M³ 350,000.00
10 Aspal Kg 13,790.00
11 Aspal Emulsi (Teak Coat) Kg 14,175.00
12 Aspal Emulsi (Prime Coat) Kg 14,175.00
13 Aspal Sealent Kg 36,000.00
14 Pasir Kasar M³ 125,000.00
15 Pasir Halus M³ 125,000.00
16 Semen PC Zak 75,000.00
17 Semen PC Kg 1,500.00
18 Tanah Ex. Peniraman M³ 190,000.00
19 Tanah Pilihan (Paladis) M³ 284,000.00
20 Paving Block Bh 3,750.00
21 Paving Stone Persegi Panjang (21 x 10,5 x 8) Bh 2,650.00
22 Paving Stone Persegi Panjang (21 x 10,5 x 10) Bh 3,750.00
23 Paving Stone Segi 5 (21 x 30 x 6) Bh 4,200.00
24 Paving Stone Diamond (Segi 6, 18 x 10.5 x 7 ) Bh 3,250.00
25 Batu Bata 5 x 11 x 22cm Bh 2,000.00
26 Bataco 15 x 30 x 7 cm Bh 1,800.00
27 Bataco 20 x 40 x 9 cm ( press ) Bh 2,500.00
28 Bataco 20 x 40 x 7 cm ( press ) Bh 2,300.00
29 Bata Ringan 20 x 60 x 10 Bh 18,000.00
30 Kerawang ( roster ) 18 x 18 cm Bh 20,000.00
31 Kerawang press ( roster ) 30 x 30 cm Bh 60,500.00
32 Keramik 20 x 20 cm Polished ex Roman Kotak 86,500.00
33 Keramik 20 x 20 cm Unpolished ex Roman Kotak 98,000.00
34 Keramik 30 x 30 cm Polished ex Roman Kotak 100,000.00
35 Keramik 30 x 30 cm Unpolished ex Roman Kotak 100,000.00
36 Keramik 40 x 40 cm Polished ex Roman Kotak 110,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

37 Keramik 40 x 40 cm Unpolished ex Roman Kotak 110,000.00


38 Keramik 30 x 60 cm Polished (setaraf Indogress) Kotak 250,000.00
39 Keramik 30 x 60 cm Unpolished (setaraf Indogress) Kotak 250,000.00
40 Keramik 40 x 40 cm Polished (setaraf Indogress) Kotak 155,000.00
41 Keramik 40 x 40 cm Unpolished (setaraf Indogress) Kotak 155,000.00
42 Keramik 60 x 60 cm Polished (setaraf Indogress) Kotak 320,000.00
43 Keramik 60 x 60 cm Unpolished (setaraf Indogress) Kotak 323,000.00
44 Keramik 60 x 60 cm Granit 160,000.00
45 Keramik dinding 20 x 20 cm ex Roman Kotak 98,750.00
46 Keramik dinding 20 x 25 cm ex Roman Kotak 102,000.00
47 Marmer M² 1,400,000.00
48 Wood Flooring M² 420,000.00
49 List Keramik WC. 8 x 20 cm Bh 11,600.00
50 Plint Kayu uk. 2 x 10 cm Bh 61,000.00
51 Floor Hardener Kg 16,600.00
52 Beton Ready Mix B 0 M³ 1,072,500.00
53 Beton Ready Mix 125 M³ 1,108,250.00
54 Beton Ready Mix 175 M³ 1,194,050.00
55 Beton Ready Mix 225 M³ 1,329,800.00
56 Beton Ready Mix 250 M³ 1,372,800.00
57 Beton Ready Mix 300 M³ 1,430,000.00
58 Beton Ready Mix 350 M³ 1,530,100.00
59 Beton Ready Mix 400 M³ 1,601,600.00
60 Beton Ready Mix 450 M³ 1,673,100.00
61 Additive Ready Mix Liter 38,300.00
62 Karung Goni Curing Beton ( 0.7m² ) Lembar 11,300.00
63 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 20 x 20, 4 D 16, ø 6 K 300 - 6m Btg 1,440,000.00
64 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 20 x 20, 8 D 13, ø 6 K 350 - 6m Btg 1,620,000.00
65 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 25 x 25, 4 D 16, ø 6 K 300 - 6m Btg 1,740,000.00
66 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 25 x 25, 8 D 13, ø 6 K 350 -6 m Btg 1,800,000.00
67 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 30 x 30, 4 D 16, ø 6 K 450 - 6m Btg 2,460,000.00
68 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 20 x 20, 8 D 13, ø 6 K 350 - 8m Btg 2,240,000.00
69 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 25 x 25, 8 D 16, ø 6 K 350 - 9m Btg 3,825,000.00
70 Tiang Pancang (Mini Pile / Ready Mix) uk. Δ 28 x 28 x 28, K 350 - 6m Btg 1,122,000.00
71 Tiang Pancang (Mini Pile / Ready Mix) uk. Δ 32 x 32 x 32, K 450 - 6m Btg 1,158,300.00
72 Sheetpile 0,6 x 0,15 x 4 meter K.350 (Besi Ulir D 13 Polos D 6) Btg 1,400,000.00
73 Sheetpile 0,6 x 0,15 x 5 meter K.350 (Besi Ulir D 13 Polos D 6) Btg 1,750,000.00
74 Sheetpile 0,6 x 0,15 x 6 meter K.350 (Besi Ulir D 13 Polos D 6) Btg 2,100,000.00
75 Sewa Pompa Ready Mix (Min. 100 M³) M³ 33,000.00
76 Bahan Plastik Cor Beton M² 1,500.00
77 Kansteen / kerb beton 20x30x60 bh 65,000.00
78 Kansteen / kerb beton 16x28x45 bh 55,000.00

C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ 11,805,000.00
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ 11,700,000.00
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ 8,950,000.00
4 Ky. Belian tdk ketam Uk. 8/16 - 4 M M³ 8,750,000.00
5 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ 9,567,900.00
6 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ 10,000,000.00
7 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ 13,020,900.00
8 Ky. Belian tdk ketam Uk. 18/18 - 4 M M³ 10,416,700.00
9 Ky. Belian tdk ketam Uk. 5/10 - 4 M M³ 11,500,000.00
10 Ky. Belian ketam Uk. 6/6 - 4 M M³ 12,800,000.00
11 Ky. Belian ketam Uk. 7/7 - 4 M M³ 12,500,000.00
12 Ky. Belian ketam Uk. 8/8 - 4 M M³ 11,015,700.00
13 Ky. Belian ketam Uk. 5/10 - 4 M M³ 11,000,000.00
14 Ky. Belian ketam Uk. 4/8 - 4 M M³ 11,718,750.00
15 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam ) M³ 7,421,875.00
16 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam ) M³ 7,500,000.00
17 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam ) M³ 7,800,000.00
18 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam ) M³ 7,840,000.00
19 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam ) M³ 9,050,000.00
20 Kusen Ky Belian uk. 5/10 Meter 120,000.00
21 Kusen Ky Kelas I Bangkirai uk. 5/10 Meter 80,000.00
22 Kusen Ky Kelas II uk. 5/10 Meter 65,000.00
23 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam ) M³ 4,440,000.00
24 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam ) M³ 4,716,717.69
25 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M³ 5,070,000.00
26 Ky. klas II Mabang uk. 5/7 - 4 M ( tdk ketam ) M³ 4,755,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

27 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam ) M³ 3,355,000.00


28 Ky. klas II Mabang uk. 6/10 - 4 M ( tdk ketam ) M³ 3,576,000.00
29 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M³ 4,224,000.00
30 Ky. klas II Mabang uk. 4/8 - 4 M ( tdk ketam ) M³ 5,468,750.00
31 Ky. klas II Mabang uk. 8/15 - 4 M ( tdk ketam ) M³ 4,589,000.00
32 Ky. klas II Mabang uk. 8/12 - 4 M ( tdk ketam ) M³ 4,634,000.00
33 Ky. klas II Mabang uk. 8/8 - 4 M ( ketam ) M³ 4,531,000.00
34 Ky. klas II Mabang uk. 7/7 - 4 M ( ketam ) M³ 5,600,000.00
35 Ky klas III uk. 3/5 - 4 M ( tdk ketam) M³ 2,500,000.00
36 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M³ 2,083,000.00
37 Papan belian ketam (4m) M³ 14,814,000.00
38 Papan belian tdk ketam (4m) M³ 13,880,000.00
39 Papan kayu klas II (mabang) tdk ketam M³ 7,060,000.00
40 Papan kayu klas II (mabang) ketam M³ 8,300,000.00
41 Papan kayu klas I tdk ketam M³ 10,819,800.00
42 Papan kayu klas I ketam M³ 11,188,300.00
43 Papan mal klas III M³ 2,558,000.00
44 Renglat kayu klas I uk 1/8 cm Btg 18,000.00
45 Kayu profil 10cm Btg 35,000.00
46 Kayu cerucuk /dolken ø 6 - 8 - Pj. 3,8 M Btg 9,000.00
47 Kayu cerucuk /dolken ø 8 - 10 - Pj. 3,8 M Btg 12,000.00
48 Kayu cerucuk /dolken ø 10 - 12 - Pj. 6 M Btg 85,000.00
49 Kayu cerucuk /dolken ø 12 - 15 - Pj. 11 M Btg 150,000.00
50 Alas laci Btg 11,000.00
51 Wood Plank M' 77,500.00
52 Bambu Pj. 10 m Btg 12,000.00

D. BAHAN CAT
1 Amplas Lbr 4,000.00
2 Minyak cat Kg 36,000.00
3 Cat kilat setara Dulux Kg 70,000.00
4 Cat kilat setara Avian Kg 70,000.00
5 Plamur Kg 31,500.00
6 Cat Dasar Alkali Kg 140,000.00
7 Cat Akhir Interior setara Dulux Kg 104,000.00
8 Cat Akhir Eksterior (weather shield) setara Dulux Kg 115,000.00
9 Cat Dasar setara Mowilex Kg 70,000.00
10 Cat Akhir Interior setara Mowilex Kg 100,000.00
11 Cat Akhir Eksterior (weather shield) setara Mowilex Kg 120,000.00
12 Cat Dasar setara Vinilex Kg 27,000.00
13 Cat Akhir Interior setara Vinilex Kg 28,000.00
14 Cat seng (Zinc Chromate) Kg 44,000.00
15 Plitur Kg 64,000.00
16 Thiner Ltr 25,000.00
17 Melamic Ltr 67,000.00
18 Vernis Ltr 45,000.00
19 Meni Kg 52,000.00
20 Oker / Semen Warna Kg 14,000.00
21 Lem Kayu Kg 20,000.00
22 Sealent Kg 107,700.00
23 Soda Api Kg 25,000.00
24 Sabun / cream pembersih kotoran Kg 15,700.00
25 Teak Oil Ltr 60,000.00
26 Ter / Residu Ltr 58,400.00
27 Kuas 4" Bh 25,000.00
28 Cat Marka (non Thermoplas) Kg 65,000.00
29 Cat Marka (Thermoplastic) Kg 95,000.00
30 Cat Kansteen (ex. Matex) Kg 53,750.00
31 Cat Trotoar (ex. Tenokote) Kg 41,250.00
32 Glass Bead Kg 30,000.00
33 Weatherbond Emulsion ( cat kerb ) Kg 39,000.00
34 Cat Water Proofing Kg 78,500.00

E. BAHAN BESI DAN ALUMINIUM


1 Besi Tulangan Beton U 24 Kg 13,500.00
2 Besi Tulangan Beton U 32 Kg 13,500.00
3 Besi wire mesh ø 5 Kg 14,500.00
4 Besi wire mesh ø 6 Kg 14,500.00
5 Besi wire mesh ø 8 Kg 14,500.00
6 Kawat baja/bendrat Kg 25,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

7 Baut dia 4/8 " pj = 20 cm Btg 5,000.00


8 Besi Penahan bh 16,000.00
9 Beugel plat L. 3 cm bh 15,000.00
10 Plat 1,2 x 2,4 x 12 Bh 310,000.00
11 Besi Profil Kg 17,000.00
12 Kawat Las Btg 5,300.00
13 Kawat Las Kg 28,500.00
14 Kawat harmonika M² 45,000.00
15 Kawat kasa M² 16,000.00
16 Pipa galvanis dia 3/4" Btg 190,000.00
17 Pipa galvanis dia 1/2" Btg 230,000.00
18 Pipa galvanis dia 1" Btg 325,000.00
19 Pipa galvanis dia 1 1/4" Btg 410,000.00
20 Pipa galvanis dia 1 1/2" Btg 465,000.00
21 Pipa galvanis dia 2" Btg 610,000.00
22 Pipa galvanis dia 2,5" Btg 785,000.00
23 Pipa galvanis dia 3" Btg 1,015,000.00
24 Pipa galvanis dia 4" Btg 1,465,000.00
25 Pipa galvanis dia 5" Btg 2,000,000.00
26 Pipa galvanis dia 6,5" Btg 2,395,000.00
27 Folding gate M² 715,000.00
28 Rangka Aluminium 1 1/2" x 3" Meter 85,000.00
29 Rangka Aluminium 1 3/4" x 4" Meter 95,000.00
30 Pintu Aluminium std IKP, lengkap 4" Unit 1,500,000.00
31 Kusen Aluminium 3" Putih Meter 120,000.00
32 Kusen Aluminium 3" Hitam Meter 85,000.00
33 Kusen Aluminium 3" Silver Meter 75,000.00
34 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang s/d 16 m) M² 235,200.00
35 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang 17 m s/d 30 m) M² 272,500.00
36 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang s/d 16m) M² 250,000.00
37 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang 17 m s/d 30 m) M² 304,100.00
38 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang s/d 16 m) M² 175,000.00
39 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang 17 m s/d 30 m) M² 225,400.00
40 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang s/d 16m) M² 193,900.00
41 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang 17 m s/d 30 m) M² 257,000.00
42 Reng Rangka Baja Ringan (Polos) uk. 0.40 - 0.45 Pjg 6 m btg 52,500.00
43 Rangka baja truss (0,75-6m) btg 94,000.00
44 Rangka baja truss (0,65-6m) btg 85,000.00
45 Dinabolt bh 6,500.00
46 L. Braket bh 6,000.00
47 Baut truss bh 550.00
48 Baut reng bh 500.00
49 Baut atap 5 cm bh 500.00
50 Alumunium Komposit + Rangka Besi M² 908,700.00
51 Alumunium Komposit Interior (1,22 x 2,44 m) Lbr 560,000.00
52 Alumunium Komposit Exterior (1,22 x 2,44 m) Lbr 815,000.00
53 Rangka Plafond Metal Furing + Pemasangan M² 130,000.00
54 Besi stainles 1" btg 145,000.00
55 Besi tempa btg 69,600.00
56 Kawat Simpai Kg 25,000.00
57 Waring Gulung 325,000.00

F. BAHAN PENGGANTUNG
1 Pintu PVC untuk WC Bh 266,000.00
2 Kait angin Bh 14,400.00
3 Handle Jendela Bh 15,400.00
4 Handle Pintu Bh 170,000.00
5 Engsel jendela Bh 18,800.00
6 Engsel pintu Bh 29,000.00
7 Slot pintu Bh 18,900.00
8 Slot jendela Bh 8,800.00
9 Kunci tanam 2 slag (setaraf Belluci) Bh 180,000.00
10 Kunci tanam 1 slag Besar Bh 230,000.00
11 Kunci tanam 1 slag Kecil Bh 150,000.00
12 Kunci silinder Bh 78,800.00
13 Door Closer Bh 250,000.00
14 Door Stoper Bh 88,750.00
15 Paku Seng Kg 35,000.00
16 Paku campuran 1" - 5 " Kg 23,000.00
17 Paku beton Kg 40,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

18 Paku triplek Kg 25,000.00


19 Paku GRC Kg 25,000.00
20 Paku Zincalum Kg 10,700.00
21 Paku Onduline Bh 1,300.00
22 Sekrup Onduline Bh 1,500.00
23 Sekrup Gibsum Kg 60,000.00
24 Sekrup Fixer Bh 2,500.00
25 Sekrup Steel Sheet uk. 5 x 15 mm Bh 300.00
26 Sekrup Steel Sheet uk. 5 x 25 mm Bh 300.00
27 Sekrup Steel Sheet uk. 5 x 35 mm Bh 400.00
28 Sekrup Steel Sheet uk. 5 x 45 mm Bh 500.00
29 Sekrup Steel Sheet uk. 5 x 50 mm Bh 500.00
30 Sekrup Steel Sheet uk. 5 x 55 mm Bh 600.00
31 Sekrup Steel Sheet uk. 5 x 65 mm Bh 700.00
32 Sekrup Ulir Kayu Bh 700.00
33 Paku asbes Bh 600.00
34 Sekrup Zincalume Bh 500.00
35 Pintu Tempered Polos 12 mm - uk. 87 x 213,5 cm Unit 5,500,000.00
36 Pintu Alumunium + Engsel Tanam - uk. 90 x 215 cm Unit 775,000.00
37 Pintu Alumunium + Engsel Kupu-kupu - uk. 90 x 215 cm Unit 700,000.00
38 Jendela Casement - uk. 60 x 120 cm (Lengkap - Tanpa Kaca) Unit 800,000.00

G. BAHAN ATAP
1 Sirap belian Lbr 5,300.00
2 Asbes Lbr 57,200.00
3 Eternit M² 68,400.00
4 Genteng Metal Type Permata 0.30 Lbr 63,000.00
5 Genteng Metal Type Prima 0.30 Lbr 66,600.00
6 Genteng Metal Type Royal 0.30 Lbr 66,600.00
7 Genteng Metal Type Classic 0.30 Lbr 66,600.00
8 Genteng Metal Type Permata 0.25 Lbr 51,800.00
9 Genteng Metal Type Classic 0.25 Lbr 51,800.00
10 Genteng Metal Type Royal 0.25 Lbr 51,800.00
11 Atap Genteng Onduline Transparan 2 x 0,95 m Lbr 275,000.00
12 Atap Genteng Onduline Warna 2 x 0,95 m (merah,hijau,coklat & hitam) Lbr 173,000.00
13 Atap Genteng Onduline Warna 2 x 0,95 m (Biru /Premium) Lbr 200,000.00
14 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (merah,hijau,coklat & hitam) Lbr 59,000.00
15 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (teracota 3D & florentino) Lbr 54,000.00
16 Perabung Onduline Warna 90 x 50 cm (merah, coklat, hijau & hitam) Lbr 100,000.00
17 Perabung Onduline Warna 90 x 50 cm (biru/premium) Lbr 110,000.00
18 Perabung Onduline Warna 90 x 50 cm (florentino) Lbr 110,000.00
19 Siku Onduline Warna 110 x 40 cm (merah,coklat,hijau & hitam) Lbr 93,000.00
20 Apron Piece Onduvilla 102 x 14 cm Lbr 89,500.00
21 Verge Piece Onduline/Onduvilla 104 x 10,5 cm tinggi 11,4 cm Lbr 89,500.00
22 Onduband M 57,000.00
23 Atap Seng Metal Soka Abadi Lbr 92,000.00
24 Atap Seng Metal Soka Jempol Lbr 67,000.00
25 Atap Seng Metal Soka Tiara Lbr 68,000.00
26 Genteng Metal Stone ( Type Classic 0.35 ) Lbr 80,000.00
27 Genteng Metal Stone ( Type Prima 0.35 ) Lbr 80,000.00
28 Atap Metal Supersheet 0.35 (polos) M² 81,300.00
29 Atap Metal Supersheet 0.35 (colour) M² 111,900.00
30 Atap Metal Supersheet 0.25 (polos) M² 47,000.00
31 Atap Metal Supersheet 0.25 (colour) M² 70,000.00
32 Atap Trim Deck 0.3 (polos) M² 100,000.00
33 Atap Trim Deck 0.35 (color) M² 112,300.00
34 Atap polycarbonat M² 78,300.00
35 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh 46,000.00
36 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm) Bh 75,000.00
37 Nok bubungan genteng metal kotak 0.35 M' 50,000.00
38 Nok bubungan genteng metal stone kotak 0.35 M' 96,900.00
39 Nok bubungan Trim Deck (polos) M' 109,500.00
40 Nok bubungan Trim Deck (color) M' 123,100.00
41 Seng Gelombang Bjls 30 Lbr 72,000.00
42 Seng Gelombang Bjls 20 Lbr 55,000.00
43 Seng Plat Bjls 20 Lbr 65,000.00
44 Seng Plat Bjls 30 Lbr 80,000.00
45 Seng Plat Bjls 30 (lebar 45 cm) M' 42,500.00
46 Plat Datar Color 0.35 Lbr 55,000.00
47 Zincalume Gelombang Persegi 0.40 (polos) M² 75,900.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

48 Zincalume Gelombang Persegi 0.35 (polos) M² 73,000.00


49 Zincalume Gelombang Persegi 0.30 (polos) M² 70,000.00
50 Zincalume Gelombang Persegi 0.40(color) M² 83,800.00
51 Zincalume Gelombang Persegi 0.35 (color) M² 80,000.00
52 Zincalume Gelombang Persegi 0.30 (color) M² 55,000.00
53 Zincalume Plat 0.2 Lbr 50,000.00
54 Aluminium Foil M² 55,000.00
55 Papan Belian utk Atap uk. 1/15 pj. 50 cm Lbr 15,200.00
56 Atap Steel Sheet 0.30 lurus (silver) M 55,000.00
57 Atap Steel Sheet 0.35 lurus (silver) M 60,000.00
58 Atap Steel Sheet 0.4 lurus (silver) M 65,000.00
59 Atap Steel Sheet 0.25 lurus (biru, merah, hijau tua) M 50,000.00
60 Atap Steel Sheet 0.30 lurus (biru, merah, coklat, hijau tua, biru tua) M 57,000.00
61 Atap Steel Sheet 0.35 lurus (coklat, biru, merah, hijau muda) M 67,000.00
62 Atap Steel Sheet 0.40 lurus (biru) M 72,000.00
63 Atap Steel Sheet 0.45 lurus (biru, merah, hijau muda) M 77,000.00
64 Atap Steel Sheet 0.30 lengkung (silver) M 60,500.00
65 Atap Steel Sheet 0.35 lengkung (silver) M 66,000.00
66 Atap Steel Sheet 0.4 lengkung (silver) M 71,500.00
67 Atap Steel Sheet 0.30 lengkung (biru, merah, coklat, hijau tua, biru tua) M 62,700.00
68 Atap Steel Sheet 0.35 lengkung (coklat, biru, merah, hijau muda) M 73,700.00
69 Atap Steel Sheet 0.40 lengkung (biru) M 79,200.00
70 Atap Steel Sheet 0.45 lengkung (biru, merah, hijau muda) M 84,700.00
71 Nok/Prabung Steel Sheet 0.30 lebar 333 mm (silver) M 22,000.00
72 Nok/Prabung Steel Sheet 0.35 lebar 333 mm (silver) M 24,000.00
73 Nok/Prabung Steel Sheet 0.40 lebar 333 mm (silver) M 26,000.00
74 Nok/Prabung Steel Sheet 0.25 lebar 333 mm (biru, merah, hijau tua) M 20,000.00
75 Nok/Prabung Steel Sheet 0.30 lebar 333 mm (biru, merah, coklat, hijau tua, biru tua) M 22,800.00
76 Nok/Prabung Steel Sheet 0.35 lebar 333 mm (coklat, biru, merah, hijau muda) M 26,800.00
77 Nok/Prabung Steel Sheet 0.40 lebar 333 mm (biru) M 28,800.00
78 Nok/Prabung Steel Sheet 0.45 lebar 333 mm (biru, merah, hijau muda) M 30,800.00
79 Nok/Prabung Steel Sheet 0.30 lebar 500 mm (silver) M 33,000.00
80 Nok/Prabung Steel Sheet 0.35 lebar 500 mm (silver) M 36,000.00
81 Nok/Prabung Steel Sheet 0.40 lebar 500 mm (silver) M 39,000.00
82 Nok/Prabung Steel Sheet 0.25 lebar 500 mm (biru, merah, hijau tua) M 30,000.00
83 Nok/Prabung Steel Sheet 0.30 lebar 500 mm (biru, merah, coklat, hijau tua, biru tua) M 34,200.00
84 Nok/Prabung Steel Sheet 0.35 lebar 500 mm (coklat, biru, merah, hijau muda) M 40,200.00
85 Nok/Prabung Steel Sheet 0.40 lebar 500 mm (biru) M 43,200.00
86 Nok/Prabung Steel Sheet 0.45 lebar 500 mm (biru, merah, hijau muda) M 46,200.00

H. BAHAN KACA
1 Kaca Polos, t = 3 mm M² 150,000.00
2 Kaca Polos, t = 5 mm M² 200,000.00
3 Kaca Polos, t = 8 mm M² 398,000.00
4 Kaca Polos, t = 12 mm M² 640,000.00
5 Kaca Rayben, t = 3 mm M² 200,000.00
6 Kaca Rayben, t = 5 mm M² 200,000.00
7 Kaca Rayben, t = 8 mm M² 550,000.00
8 Kaca Rayben, t = 12 mm M² 900,000.00
9 Kaca Cermin t = 3 mm M² 275,000.00
10 Kaca Cermin t = 5 mm M² 418,000.00
11 Kaca Repsol, t = 5 mm M² 550,000.00
12 Sealent Kg 35,000.00
13 Nako + Bingkai (80 x 15) x 10 daun polos Bh 400,000.00
14 Nako + Bingkai (80 x 15) x 10 daun rayben Bh 469,000.00
15 Kaca Es, t = 3 mm M² 275,000.00
16 Kaca Es, t = 5 mm M² 267,500.00
17 Kaca Raindown, t = 5 mm M² 550,000.00

I. BAHAN TRIPLEK
1 Triplek t = 3 mm Lbr 70,000.00
5 Teakwood t = 3 mm Lbr 140,000.00
6 Formika t = 0,03 mm Lbr 115,000.00
7 Multiplex t = 6 mm Lbr 111,000.00
8 Multiplex t = 9 mm Lbr 220,000.00
9 Multiplex t = 10 mm Lbr 278,000.00
10 Multiplek t = 12 mm Lbr 282,000.00
11 Plywood 4' x 8' x 4mm Lbr 120,000.00
12 Panel GRC 120 x 240 x 40 Lbr 79,700.00
13 GypsumBoard t = 9 mm Lbr 74,600.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

14 Super Plank 10 x 240 x 9 cm Lbr 65,000.00


15 Super Plank 20 x 240 x 9 cm Lbr 70,000.00
16 Super Plank 30 x 240 x 9 cm Lbr 110,000.00

J. BAHAN SANITASI
1 Wastafel setara Toto Bh 1,000,000.00
2 Kloset duduk monoblok Bh 2,962,700.00
3 Kloset duduk putih (setaraf TOTO) Bh 2,246,800.00
4 Kloset duduk warna (setaraf TOTO) Bh 2,500,000.00
5 Kloset jongkok (setaraf TOTO) Bh 330,000.00
6 Kloset jongkok (setaraf INA) Bh 200,000.00
7 Urinoir setaraf Toto Unit 2,000,000.00
8 Bak air fibreglass uk. 55x55x60 cm Bh 300,000.00
9 Shower Spray setara Toto Unit 350,000.00
10 Sliding rail setara Toto Unit 500,000.00
11 Floordrain stainless steel setara Toto Bh 400,000.00
12 Floordrain PVC Bh 35,000.00
13 Tempat Sabun Setara Toto Bh 120,000.00
14 Kran zink setara Toto Bh 307,000.00
15 Kitchenzink stainless steel 1 lubang Unit 650,000.00
16 Kran dinding setara Toto Bh 150,000.00
17 Kran air uk 1/2" Bh 32,500.00
18 Pipa PVC dia 1/2" AW ex Wavin Btg 23,400.00
19 Pipa PVC dia 3/4" AW ex Wavin Btg 32,500.00
20 Pipa PVC dia 1" AW ex Wavin Btg 44,400.00
21 Pipa PVC dia 2" AW ex Wavin Btg 100,000.00
22 Pipa PVC dia 3" AW ex Wavin Btg 203,500.00
23 Pipa PVC dia 4" AW ex Wavin Btg 335,500.00
24 Pipa PVC dia 8" AW ex Wavin Btg 1,306,800.00
25 Pipa PVC dia 3/4" D ex Wavin Btg 23,500.00
26 Pipa PVC dia 1" D ex Wavin Btg 30,000.00
27 Pipa PVC dia 2" D ex Wavin Btg 61,000.00
28 Pipa PVC dia 3" D ex Wavin Btg 111,000.00
29 Pipa PVC dia 4" D ex Wavin Btg 173,300.00
30 Stop kran dia 1/2" ex onda Bh 43,000.00
31 Stop kran dia 3/4" ex onda Bh 51,200.00
32 Stop kran dia 1" ex onda Bh 115,000.00
33 Tangki air 1000 liter Bh 2,500,000.00
34 Tangki air 500 liter Bh 1,500,000.00
35 Pelampung otomatis Bh 75,000.00
36 Roof Drain Metal Bh 75,000.00
37 Mesin Jet Pump kap.250 watt Unit 1,440,000.00
38 Mesin Pompa tekan kap. 150 watt Unit 550,000.00

K. BAHAN MINYAK (TANPA KEUNTUNGAN)


1 Minyak solar industri Ltr 8,100.00
2 Bensin industri Ltr 7,400.00
3 Minyak pelumas/Oli Ltr 28,800.00
4 Minyak tanah Ltr 9,600.00
5 Gas Elpiji Refill 12 kg Kg 28,800.00
6 Sewa Molen Set 170,000.00
7 Sewa Alat Perakitan Set 70,000.00
8 Sewa Peralatan Las Set 70,000.00
9 Alat-alat bantu Set 66,400.00

L. BATU ALAM
1 Batu Andesit Ukuran 10 x 20 cm M² 170,000.00
2 Batu Andesit Ukuran 15 x 30 cm M² 200,000.00
3 Batu Andesit Ukuran 20 x 40 cm M² 230,000.00
4 Batu Andesit Ukuran 30 x 60 cm M² 260,000.00
5 Batu Candi Ukuran 10 x 20 cm M² 170,000.00
6 Batu Candi Ukuran 15 x 30 cm M² 200,000.00
7 Batu Candi Ukuran 20 x 40 cm M² 220,000.00
8 Batu Pacitoroso Ukuran 10 x 20 cm M² 190,000.00
9 Batu Pacitoroso Ukuran 15 x 30 cm M² 220,000.00
10 Batu Pacitoroso Ukuran 20 x 40 cm M² 250,000.00
11 Batu Bali Green Ukuran 10 x 20 cm M² 180,000.00
12 Batu Bali Green Ukuran 15 x 30 cm M² 200,000.00
13 Batu Bali Green Ukuran 20 x 40 cm M² 220,000.00
14 Batu Prasasti Peresmian (batu hitam) ukuran 40 x 60 buah 2,400,000.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

15 Batu Prasasti Peresmian (batu hitam) ukuran 60 x 80 buah 4,800,000.00


16 Batu Koral (batu taman) kg 14,000.00
17 Batu Granit Ukuran Lebar 60 cm M² 1,300,000.00

M. BAHAN ALAT-ALAT LISTRIK


1 Traffo HPL 400 Watt Buah 298,500.00
2 Traffo HPL 250 Watt Buah 228,000.00
3 Traffo HPL 125 Watt Buah 155,350.00
4 Traffo SON T 1000 Watt Buah 1,687,000.00
5 Traffo SON T 400 Watt Buah 462,000.00
6 Traffo SON T 250 Watt Buah 311,930.00
7 Traffo SON T 150 Watt Buah 179,000.00
8 Traffo SON T 125 Watt Buah 180,000.00
9 Traffo SON T 70 Watt Buah 120,000.00
10 Traffo Neon 40 Watt Buah 40,000.00
11 Traffo Neon 20 Watt Buah 40,000.00
12 HPL 250 Watt Buah 170,500.00
13 HPL 125 Watt Buah 117,750.00
19 Bola Lampu HPIT 400 Watt Buah 240,000.00
31 Lampu Sorot 300 Watt (LENGKAP) Buah 250,000.00
50 Bola Lampu Sorot 300 Watt Buah 32,000.00
51 Hologen 500 Watt Buah 35,500.00
52 Hologen 1.000 Watt Buah 51,250.00
90 Box MCB 1 Group Buah 3,500.00
91 Box Time Swich ( Lengkap pipa optic 1,5 +Klem + Kunci ) Set 2,695,650.00
92 Box KWH Meter Uk. L 35 cm x T 50 cm x LS 25 cm Buah 781,700.00
94 Fitting Duduk Buah 13,300.00
95 Fitting Atom Buah 3,500.00
96 Fitting Gantung E 27 Buah 11,000.00
97 Fitting Duduk E 27 Buah 41,000.00
98 Full Breket Buah 17,500.00
100 Icnitor SN 58 Buah 51,500.00
101 Inector Buah 73,500.00
102 Ignator Buah 35,000.00
103 Kap Hijau E 27 Buah 12,000.00
104 Kap Hijau E 40 Buah 16,000.00
105 Kop Skring Buah 7,000.00
106 k. Skum 10-8 Buah 1,000.00
107 MCB 1.A Buah 35,000.00
108 MCB 2.A Buah 31,600.00
109 MCB 25 A Buah 33,000.00
110 MCB 63 A Buah 62,000.00
111 MCB 40 A Buah 29,000.00
112 MCB 50 A Buah 62,000.00
113 MCB 10 A Buah 37,500.00
114 MCB 16 A Buah 44,800.00
115 MCB 6 A Buah 33,000.00
116 MCB 32 A Buah 33,000.00
117 MCB Box Buah 2,500.00
118 Multi Tester Buah 110,000.00
119 Macon Mec gmg-50 aC Buah 484,500.00
120 Magnetic Contactor 100 A Buah 672,000.00
121 NH Fuse 80 A Buah 495,000.00
122 Ornamen Pijar Buah 89,000.00
125 Solar Seal / Photo Seal Buah 50,000.00
126 Rangka Ring 32 Watt Buah 45,000.00
127 Rel MCB Buah 15,000.00
135 Solder Pistol Buah 45,000.00
136 Solar Seal / Photo Seal Buah 56,000.00
138 Steker T Buah 20,000.00
139 Sadel No. 6 Bungkus 6,500.00
140 Sadel No. 8 Bungkus 7,000.00
141 Sadel No. 9 Bungkus 7,350.00
142 Sadel No. 10 Bungkus 8,000.00
143 Sadel No. 12 Bungkus 9,500.00
144 Sadel No. 14 Bungkus 12,600.00
145 Sadel No. 19 Bungkus 18,100.00
146 Sadel No. 22 Bungkus 19,100.00
147 Stater Buah 5,500.00
150 Tang Kombinasi Buah 35,000.00
151 Time Swicht Theben Buah 334,250.00
152 Taping Conector 1 baut Buah 16,266.00
153 Taping Conector 2 baut Buah 24,233.00
154 Tespen Buah 17,500.00
155 Amatur Lampu Son T 250 Watt (lengkap) Set 3,856,500.00
HARGA SATUAN DASAR
(TIDAK TERMASUK
NO MATERIAL SATUAN
PROFIT & OVERHEAD)
(Rp)

156 Amatur Lampu Son T 150 Watt (lengkap) Set 3,304,300.00


162 Wide Klem Buah 5,800.00
163 Pole Breacket Buah 21,600.00
164 Kapasitor Buah 181,200.00
REKAPITULASI
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
BIDANG CIPTA KARYA
KOTA PONTIANAK
TAHUN ANGGARAN 2019

KODE HARGA
ANALISA URAIAN (Rp.)

A.2.2.1 Harga Satuan Pekerjaan Persiapan


A.2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter 603,911.00
A.2.2.1.3 (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter 209,314.38
A.2.2.1.4 Pengukuran dan pemasangan 1m Bouwplank 115,748.65
A.2.2.1.5 (K3) Pembuatan 1m2 kantor sementara lantai plasteran 2,159,124.06
A.2.2.1.9 (K3) Pembersihan 1 m2 lapangan atau perataan 12,075.00
A.2.2.1.12 Pembuatan 1 m2 jalan sementara 218,126.25
A.2.2.1.13 Pembongkaran 1 m3 beton bertulang 1,652,124.50
A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata 826,062.25

A.2.3.1 Harga Satuan Pekerjaan Tanah


A.3.2.1.1 Penggalian 1m3 tanah biasa sedalam 1m 95,018.75
A.3.2.1.2 Penggalian 1m3 tanah biasa sedalam 2 m 116,696.25
A.3.2.1.3 Menggali 1m3 tanah biasa sedalam 3 m 138,730.25
A.3.2.1.4 Menggali 1m3 tanah keras sedalam 1 m 126,454.00
A.3.2.1.5 Menggali 1m3 tanah cadas sedalam 1 m 126,454.00
A.3.2.1.6 Menggali 1m3 tanah lumpur sedalam 1 m 152,921.25
A.3.2.1.8 Menggali 1m3 tanah lumpur sedalam 1 m 41,630.00
A.3.2.1.9 Pengurugan kembali 1 m3 galian tanah 241,787.50
A.3.2.1.10 (K3) Pemadatan tanah 1 m3 tanah (per 20 cm) 69,287.50
A.3.2.1.11 Pengurugan 1 m3 dengan pasir urug 241,787.50
A.2.3.1.11.a Pengurugan 1 m3 dengan Tanah Pilihan 461,207.50
A.3.2.1.11b Pengurugan 1 m3 dengan Tanah Ex. Peniraman 331,487.50

A.3.2.1 Harga Satuan Pekerjaan Pondasi


A.3.2.1.1 Pemasangan 1m3 pondasi batu belah campuran 1SP : 3PP 1,215,981.25
A.3.2.1.2 Pemasangan 1m3 pondasi batu belah campuran 1SP : 4PP 1,153,737.50
A.3.2.1.9 (K3) Pemasangan 1m3 pondasi batu kosong (anstamping) 708,802.50
A.3.2.1.10 Pemasangan 1m3 pondasi siklop, 60% beton campuran 1 SP : 2PB : 3 Kr dan 40% batu belah 3,413,458.75
A.3.2.1.11 Pemasangan 1m3 pondasi sumuran, diameter 100 cm 1,255,621.75

A.4.1.1 Harga Satuan Pekerjaan Beton


A.4.1.1.1 Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87 1,177,760.18
A.4.1.1.1.a Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87 (menggunakan molen) 1,170,256.43
A.4.1.1.2 Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78 1,228,835.54
A.4.1.1.2.a Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78 (menggunakan molen) 1,221,331.79
A.4.1.1.3 Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72 1,267,556.01
A.4.1.1.3.a Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72 (menggunakan molen) 1,260,052.26
A.4.1.1.4 Membuat 1m3 lantai kerja beton mutu f'c = 7,4 MPa slump (3-6) cm, w/c =0,87 1,091,676.59
A.4.1.1.5 Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66 1,314,982.10
A.4.1.1.5.a Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66 (menggunakan molen) 1,307,478.35
A.4.1.1.6 Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61 1,357,663.68
A.4.1.1.6.a Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61 (menggunakan molen) 1,350,159.93
A.4.1.1.7 Membuat 1m3 beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm ,w/c = 0,58 1,393,524.37
A.4.1.1.7.a Membuat 1m3 beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm ,w/c = 0,58 (menggunakan molen) 1,386,020.62
A.4.1.1.8 Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56 1,412,096.26
A.4.1.1.8.a Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56 (menggunakan molen) 1,404,592.51
A.4.1.1.9 Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53 1,443,964.64
A.4.1.1.9.a Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53 (menggunakan molen) 1,436,460.89
A.4.1.1.10 Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52 1,453,708.46
A.4.1.1.10.a Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52 (menggunakan molen) 1,446,204.71
A.4.1.1.11 Membuat 1m3 beton mutu f'c = 28,8 Mpa (K 325), slump (12 ± 2) cm ,w/c = 0,49 1,561,567.05
A.4.1.1.12 Membuat 1m3 beton mutu f'c = 31,2 Mpa (K 350), slump (12 ± 2) cm ,w/c = 0,48 1,574,356.24
A.4.1.1.13 Membuat 1m3 beton kedap air dengan strorox - 100 1,018,812.99
A.4.1.1.16 Membuat 1m PVC Waterstop lebar 300 mm 16,100.00
A.4.1.1.17 Pembesian 10 Kg dengan besi polos atau besi ulir (U24) 18,772.03
A.4.1.1.17.a Pembesian 1 Kg dengan besi polos atau besi ulir (U32) 18,772.03
A.4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh) 182,482.00
A.4.1.1.20 (K3) Pemasangan 1m2 bekisting untuk pondasi 212,888.00
A.4.1.1.20.a Pemasangan 1m2 bekisting untuk pondasi (papan mal) 156,605.85
A.4.1.1.21 (K3) Pemasangan 1m2 bekisting untuk sloof 224,865.25
A.4.1.1.21.a Pemasangan 1m2 bekisting untuk sloof (papan mal) 156,605.85
A.4.1.1.22 (K3) Pemasangan 1m2 bekisting untuk kolom 425,563.25
A.4.1.1.22.a Pemasangan 1m2 bekisting untuk kolom (papan mal) 375,255.35
A.4.1.1.23 (K3) Pemasangan 1m2 bekisting untuk balok 437,138.00
A.4.1.1.23.a Pemasangan 1m2 bekisting untuk balok (papan mal) 386,830.10
A.4.1.1.24 (K3) Pemasangan 1m2 bekisting untuk lantai 480,763.25
A.4.1.1.24.a Pemasangan 1m2 bekisting untuk lantai (papan mal) 430,455.35
A.4.1.1.25 (K3) Pemasangan 1m2 bekisting untuk dinding 434,700.00
A.4.1.1.25.a Pemasangan 1m2 bekisting untuk dinding (papan mal) 384,392.10
A.4.1.1.26 (K3) Pemasangan 1m2 bekisting untuk tangga 399,952.75
A.4.1.1.26.a Pemasangan 1m2 bekisting untuk tangga (papan mal) 349,644.85
A.4.1.1.27 Pemasangan 1m2 jembatan untuk pengecoran beton 127,990.63
A.4.1.1.35 Membuat 1m' kolom praktis beton bertulang (11 x 11) cm 111,060.91
A.4.1.1.36 Membuat 1m' ring balok beton bertulang (10 x 15) cm 135,596.59
B. 13.a.1 Membuat 1 m³ beton ready mix K 100 menggunakan pompa 1,892,123.75
B. 13.a.2 Membuat 1 m³ beton ready mix K 100 tidak menggunakan pompa 1,436,723.75
B. 13.b.1 Membuat 1 m³ beton ready mix K 125 menggunakan pompa 1,934,058.50
B. 13.b.2 Membuat 1 m³ beton ready mix K 125 tidak menggunakan pompa 1,478,658.50
B. 13.c.1 Membuat 1 m³ beton ready mix K 175 menggunakan pompa 2,034,701.90
B. 13.c.2 Membuat 1 m³ beton ready mix K 175 tidak menggunakan pompa 1,579,301.90
B. 13.d.1 Membuat 1 m³ beton ready mix K 225 menggunakan pompa 2,193,936.65
B. 13.d.2 Membuat 1 m³ beton ready mix K 225 tidak menggunakan pompa 1,738,536.65
B. 13.e.1 Membuat 1 m³ beton ready mix K 250 menggunakan pompa 2,244,375.65
B. 13.e.2 Membuat 1 m³ beton ready mix K 250 tidak menggunakan pompa 1,788,975.65
B. 13.f.1 Membuat 1 m³ beton ready mix K 300 menggunakan pompa 2,311,471.25
B. 13.f.2 Membuat 1 m³ beton ready mix K 300 tidak menggunakan pompa 1,856,071.25
B. 13.g.1 Membuat 1 m³ beton ready mix K 350 menggunakan pompa 2,428,888.55
B. 13.g.2 Membuat 1 m³ beton ready mix K 350 tidak menggunakan pompa 1,973,488.55
B. 13.h.1 Membuat 1 m³ beton ready mix K 400 menggunakan pompa 2,512,758.05
B. 13.h.2 Membuat 1 m³ beton ready mix K 400 tidak menggunakan pompa 2,057,358.05
B. 13.i.1 Membuat 1 m³ beton ready mix K 450 menggunakan pompa 2,596,627.55
B. 13.i.2 Membuat 1 m³ beton ready mix K 400 tidak menggunakan pompa 2,141,227.55

A.4.1.2 Harga Satuan Pekerjaan Beton Pracetak


A.4.1.2.5 Pembuatan 1 m2 Bekisting untuk Pelat Beton Pracetak Komponen Modular Bangunan Gedung ( 5 kali pakai) 19,906.50
A.4.1.2.6 Pembuatan 1 m2 Bekisting untuk Balok Beton Pracetak (10-12 kali pakai) 41,972.70
A.4.1.2.7 Pembuatan 1 m2 Bekisting untuk Kolom Beton Pracetak (10-12 kali pakai) 36,504.45
A.4.1.2.8 Pemasangan dan Membuka Cetakan 1 Buah Komponen Pelat Beton Pracetak 9,878.50
A.4.1.2.9 Pemasangan dan Membuka Cetakan 1 Buah Komponen Balok Beton Pracetak 15,950.50
A.4.1.2.10 Pemasangan dan Membuka Cetakan 1 Buah Komponen Kolom Beton Pracetak 12,914.50
A.4.1.2.11 Penuangan/Menebar Beton 1 m3 untuk Pelat Beton Pracetak 79,884.75
A.4.1.2.12 Penuangan/Menebar Beton 1 m3 untuk Balok Beton Pracetak 82,138.75
A.4.1.2.13 Penuangan/Menebar Beton 1 m3 untuk Kolom Beton Pracetak 140,328.75
A.4.1.2.14. Pemasangan 1 buah Komponen untuk Pelat Beton Pracetak Beserta Indeks Kenaikan Lantai Ereksi Pelat Hingga 24 Lantai 60,099.00
A.4.1.2.15 Pemasangan 1 buah Komponen untuk Pelat Beton Pracetak Beserta Indeks Kenaikan Lantai Ereksi Pelat Hingga 24 Lantai 54,717.00
A.4.1.2.17 Pemindahan 1 buah Komponen untuk Pelat Pracetak ( ± 20 m) 7,756.75
A.4.1.2.18 Pemindahan 1 buah Komponen untuk Balok Pracetak ( ± 20 m) 7,756.75
A.4.1.2.19 Pemindahan 1 buah Komponen untuk Kolom Pracetak ( ± 20 m) 7,756.75
A.4.1.2.22 Upah 1 titik Pekerjaan Grout pada Joint Beton Pracetak 71,691.00
A.4.1.2.23 Pemasangan 1 titik Bekisting Joint Pracetak 126,125.10
A.4.1.2.24 Pemasangan 1 titik Bekisting Joint Pracetak 62,933.75

A.4.2.1 Harga Satuan Pekerjaan Besi dan Alumunium


A.4.2.1.1 Pemasangan 1 kg besi profil 39,887.75
A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF 39,887.75
A.4.2.1.3 Pengerjaan 100 Kg pekerjaan perakitan 104,535.00
A.4.2.1.4 Pembuatan 1m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku 10,033.75
A.4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik 39,309.30
A.4.2.1.5.a Pengerjaan 10 cm pengelasan dengan las listrik (bangunan) 23,391.00
A.4.2.1.6 Pembuatan 1m2 rangka jendela besi scuare tube 188,467.75
A.4.2.1.7 Pemasangan 1 m2 Pintu Rolling Door Besi 1,010,717.75
A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC 949,888.50
A.4.2.1.9 Pemasangan 1 m2 Rolling door Aluminium 290,087.50
A.4.2.1.10 Pemasangan 1 m2 Rolling door Aluminium 138,713.00
A.4.2.1.11 Pemasangan 1 m kusen pintu allumunium 241,753.00
A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka allumunium 294,664.50
A.4.2.1.14 Pemasangan 1 m3 venetions blinds dan vertical blinds 101,619.75
A.4.2.1.15 Pemasangan 1 m2 terali besi strip (2x3) mm 484,357.00
A.4.2.1.16 Pemasangan 1 m2 kawat nyamuk 29,008.75
A.4.2.1.17 Pemasangan 1 m2 Jendela Nako dan Tralis 56,413.25
A.4.2.1.18 Pemasangan 1 m' talang datar/jurai seng bjls 28 lebar 90 cm 262,389.75
A.4.2.1.19 Pemasangan 1 m' talang 1/2 lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm 119,249.25
A.4.2.1.20 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x 120 cm, untuk Partisi 105,386.00
A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, untuk plafon 134,394.75
A.4.2.1.22 Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75 212,911.00
A.4.2.1.23 Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75 220,572.30
A.4.2.1.24 Pemasangan 1 m2 Pintu Aluminium Strip Lebar 8 cm 220,572.30
A.4.2.1.25 Pemasangan 1 m2 Venetions Blinds dan Vertical Blinds 101,619.75

A.4.4.1 Harga Satuan Pekerjaan Pasangan Dinding


A.4.4.1.1 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP 491,050.00
A.4.4.1.2 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 491,050.00
A.4.4.1.3 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP 491,050.00
A.4.4.1.4 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP 491,050.00
A.4.4.1.6 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP 481,332.50
A.4.4.1.7 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 2PP 254,092.50
A.4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP 246,479.50
A.4.4.1.9 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 4PP 241,960.00
A.4.4.1.10 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP 239,108.00
A.4.4.1.11 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 6PP 237,337.00
A.4.4.1.12 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 8PP 234,341.25
A.4.4.1.13 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3 KP : 10PP 230,891.25
A.4.4.1.14 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 1PP 218,559.80
A.4.4.1.15 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 2PP 219,990.40
A.4.4.1.16 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 3 PP 247,830.75
A.4.4.1.17 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 4 PP 243,702.25
A.4.4.1.17.a Pemasangan 1 m² dinding batako uk. 20/40/9 122,291.00
A.4.4.1.17.b Pemasangan 1 m² dinding batako uk. 20/40/7 119,416.00
A.4.4.1.19.a Pemasangan 1 m² dinding batako 15/30/7 221,754.50
A.4.4.1.23.a Pemasangan 1 m² dinding terawang (rooster) 18x18 campuran 1SP:4PP 768,947.50
A.4.4.1.23.b Pemasangan 1 cm2 dinding terawang (rooster) 30 x 30 campuran 1 SP : 4 PP 904,802.75
A.4.4.1.24 Pemasangan 1 cm2 dinding bata berongga ekspose 12x11x24 campuran 1 SP : 3 PP 83,691.25
A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai 54,941.25
A.4.4.1.26 Pemasangan 1m2 Dinding Bata Ringan Tebal 10cm dengan Mortar Siap Pakai 102,413.25

A.4.4.2 Harga Satuan Pekerjaan Plesteran


A.4.4.2.1 Pemasangan 1 m2 plesteran 1SP : 1 PP tebal 15 mm 92,006.90
A.4.4.2.2 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 83,473.90
A.4.4.2.4 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 77,176.50
A.4.4.2.14 Pemasangan 1 m2 plesteran 1SP : 3 PP tebal 20 mm 88,138.30
A.4.4.2.15 Pemasangan 1 m2 plesteran 1SP : 4 PP tebal 20 mm 103,258.50
A.4.4.2.19 Pemasangan 1 m2 Berapen 1SP : 5PP Tebal 15 mm 44,333.65
A.4.4.2.20 Pemasangan 1 m’ Plesteran Skoning 1SP : 3PP Lebar 10 cm 77,274.25
A.4.4.2.21 Pemasangan 1 m’ Plesteran Skoning 1SP : 3PP Lebar 10 cm 111,866.25
A.4.4.2.22 Pemasangan1 m2 Plesteran Traso 1SP : 2 Traso Tebal 10 mm 111,866.25
A.4.4.2.23 Pemasangan1 m2 Plesteran Ciprat (Kamprotan)1SP : 2PP 63,255.75
A.4.4.2.24 Pemasangan Finishing 1 m2 Dinding Siar Pasangan Bata Merah 37,015.05
A.4.4.2.25 Pemasangan Finishing 1m2 Dinding Siar Pasangan Conblock Ekspose 17,623.75
A.4.4.2.26 Pemasangan 1m2 Finishing Siar Pasangan Batu Kali, Campuran 1SP : 2PP 75,624.00
A.4.4.2.27 Pemasangan 1 m2 acian 47,581.25

A.4.4.3 Harga Satuan Pekerjaan Penutup Lantai dan Penutup Dinding


A.4.4.3.1 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 40cm x40cm 124,593.88
A.4.4.3.2 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 40cm x40cm 76,360.00
A.4.4.3.3 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 20cm x 20cm 81,247.50
A.4.4.3.5 Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30cm 168,935.00
A.4.4.3.6 Pemasangan 1m2 Lantai ubin Warna Ukuran 20cm x 20cm 234,628.75
A.4.4.3.7 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 40cm x 40cm 277,351.25
A.4.4.3.8 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 30cm x 30cm 311,592.50
A.4.4.3.9 Pemasangan 1m2 Lantai Ubin Granit Ukuran 40cm x 40cm 417,133.75
A.4.4.3.10 Pemasangan 1m2 Lantai Ubin Granit Ukuran 30cm x 30cm 417,133.75
A.4.4.3.11 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cmx40cm 277,351.25
A.4.4.3.12 Pemasangan 1m2 Lantai Ubin Teralux Ukuran 30cm x30cm 287,442.50
A.4.4.3.13 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 60cm x60cm 306,705.00
A.4.4.3.14 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 40cm x40cm 277,351.25
A.4.4.3.15 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 30cm x30cm 311,592.50
A.4.4.3.16 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 20 s.d. <30 cm 29,043.25
A.4.4.3.17 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 30 s.d. <40 cm 103,191.42
A.4.4.3.18 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 40 s.d. <50 cm 192,824.33
A.4.4.3.19 Pemasangan 1 m’ Plint Ubin Warna Ukuran 20 s.d. <30cm 116,464.33
A.4.4.3.20 Pemasangan 1 m’ Plint Ubin Warna Ukuran 30 s.d. <40cm 103,018.92
A.4.4.3.21 Pemasangan 1 m’ Plint Ubin Warna Ukuran 40 s.d. <50 cm 191,128.08
A.4.4.3.22 Pemasangan 1 m’ Plint Ubin Teraso Ukuran 30 s.d. <40cm 28,594.75
A.4.4.3.23 Pemasangan 1 m’ Plint Ubin Teraso Ukuran 40 s.d. <50 cm 28,594.75
A.4.4.3.24 Pemasangan 1 m’ Plint Ubin Granit Ukuran 30 s.d. <40 cm 28,594.75
A.4.4.3.25 Pemasangan 1 m’ Plint Ubin Granit Ukuran 30 s.d. <40 cm 28,594.75
A.4.4.3.26 Pemasangan 1 m’ Plint Ubin Teralux Kerang Ukuran 30 s.d. <40cm 28,594.75
A.4.4.3.27 Pemasangan 1 m’ Plint Ubin Teralux Kerang Ukuran 30 s.d. <40cm 28,594.75
A.4.4.3.28 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 30 s.d. <40cm 28,594.75
A.4.4.3.29 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 40 s.d. <50cm 28,594.75
A.4.4.3.30 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 60 s.d. <70cm 28,594.75
A.4.4.3.31 Pemasangan 1m2 Lantai Teraso Cor di Tempat, Tebal 3cm 77,165.00
A.4.4.3.32 Pemasangan 1m2 Lantai Keramik Artistik 10 s.d. <20cm 429,916.00
A.4.4.3.33 Pemasangan 1m2 Lantai Keramik Artistik Ukuran 20 s.d. <30 cm 765,874.91
A.4.4.3.34 Pemasangan 1 m2 lantai keramik ukuran 33cmx33cm 226,829.83
A.4.4.3.34.a Pemasangan 1 m2 lantai keramik ukuran 60 x 60 cm Polish (setara indogres) 561,959.00
A.4.4.3.34.b Pemasangan 1 m2 lantai keramik ukuran 60 x 60 cm Polish (setara indogres) 565,581.50
A.4.4.3.34.c Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Polish (setara indogres) 362,721.50
A.4.4.3.34.d Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Unpolish (setara indogres) 362,721.50
A.4.4.3.35 Pemasangan 1 m2 lantai keramik ukuran 30 x 30 cm Polish (setara Roman) 299,431.25
A.4.4.3.35.a Pemasangan 1 m2 lantai keramik ukuran 30 x 30 cm Unpolish (setara Roman) 299,431.25
A.4.4.3.35.b Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Polish (setara Roman) 311,506.25
A.4.4.3.35.c Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Unpolish (setara Roman) 311,506.25
A.4.4.3.36 Pemasangan 1 m2 lantai keramik ukuran 20 x 20 cm Polish (setara Roman) 283,130.00
A.4.4.3.36.a Pemasangan 1 m2 lantai keramik ukuran 20 x 20 cm Unpolish (setara Roman) 297,706.25
A.4.4.3.37 Pemasangan 1m2 Lantai Keramik Ukuran 30 s.d. <40 cm untuk Variasi/border 2,332,908.40
A.4.4.3.39 Pemasangan 1m2 Lantai Keramik Ukuran 30 s.d. <40 cm untuk Variasi/border 831,432.75
A.4.4.3.40 Pemasangan 1 m’ Plint Keramik Ukuran 20 s.d. <30 cm 2,245,070.25
A.4.4.3.41 Pemasangan 1 m’ Plint Internal Cove Artistik 5cm x 5cm x 20cm 2,859,529.74
A.4.4.3.42 Pemasangan 1 m2 Lantai Marmer Ukuran 100cm x 100cm 254,996.40
A.4.4.3.43 Pemasangan 1 m2 Lantai Karpet 205,976.50
A.4.4.3.44 Pemasangan 1 m2 Underlayer (Pelapis Bawah Karpet) 99,716.50
A.4.4.3.45 Pemasangan 1 m2 Lantai Parquet Kayu Solid 420,325.00
A.4.4.3.46 Pemasangan 1 m2 Lantai Kayu Gymfloor 384,100.00
A.4.4.3.47 Pemasangan 1 m2 Dinding Porselen 11cm x 11cm 278,041.25
A.4.4.3.48 Pemasangan 1 m2 Dinding Porselen 10cm x 20cm 420,704.50
A.4.4.3.49 Pemasangan 1 m2 Dinding Porselen 20cm x 20cm 342,205.50
A.4.4.3.50 Pemasangan 1 m2 Dinding Keramik Artistik 10cm x 20cm 458,700.50
A.4.4.3.51 Pemasangan 1 m2 Dinding Keramik Artistik 5cm x 20cm 357,661.50
A.4.4.3.52 Pemasangan 1 m2 Dinding Keramik 10cm x 20cm 458,700.50
A.4.4.3.53 Pemasangan 1 m2 Dinding Keramik 20cm x 20cm 342,205.50
A.4.4.3.54 Pemasangan 1 m2 Dinding Marmer 100cm x 100cm 2,014,955.25
A.4.4.3.55 Pemasangan 1 m2 Dinding Bata Pelapis (Super) 3cm x 7cm x 24cm 279,202.75
A.4.4.3.56 Pemasangan 1 m2 Dinding Batu Paras 172,212.50
A.4.4.3.57 Pemasangan 1 m2 Dinding Batu Tempel Hitam 387,262.50
A.4.4.3.58 Pemasangan 1 m2 Lantai Vynil Ukuran 30cm x 30cm 43,602.25
A.4.4.3.59 Pemasangan 1 m2 Wallpaper lebar 50 cm 70,610.00
A.4.4.3.60 Pemasangan 1m2 Floor Harderner 130,260.50
A.4.4.3.61 Pemasangan 1 m’ Plint Vynil 15cm x 30cm 23,207.00
A.4.4.3.62 Pemasangan 1 m’ Plint Kayu Tebal 2 cm Lebar 10 cm 74,732.64
A.4.4.3.63 Pemasangan 1 m2 Paving Block (Blok Beton) Natural tebal 6cm 326,544.23
A.4.4.3.64 Pemasangan 1 m2 Pavingblock (Blok Beton) Natural tebal 8cm 361,044.23
A.4.4.3.65 Pemasangan 1 m2 Paving Block ( Blok Beton) Berwarna Tebal 6cm 326,544.23
A.4.4.3.65.a Pemasangan 1 m2 paving block natural tebal 8 cm 343,121.48
A.4.4.3.65.b Pemasangan 1 m2 paving block natural tebal 10 cm 343,121.48
A.4.4.3.65.c Pemasangan 1 m2 paving block segi 6 natural tebal 7 cm 273,896.08
A.4.4.3.66 Pemasangan 1 m2 Pavingblock (Blok Beton) Berwarna Tebal 8cm 273,896.08
A.4.4.3.67.a Pemasangan 1 m2 paving stone 273,896.08
305,372.73
A.4.5.1 Satuan Pekerjaan Langit-Langit (plafond)
A.4.5.1.1 Pemasangan1 m2 Langit-Langit Serat Semen, Tebal 4 mm, 5 mm, dan 6 mm 73,910.50
A.4.5.1.2 Pemasangan 1 m2 Langit-Langit Akustik Ukuran 30 x 30 cm 15,565.25
A.4.5.1.3 Pemasangan 1 m2 Langit-Langit Akustik Ukuran 30 x 60 cm 34,810.50
A.4.5.1.4 Pemasangan 1 m2 Langit-Langit Kayu Lapis, Tebal 3 mm, 4 mm dan 6 mm 29,871.25
A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120x240) cm, tebal 6 mm 77,740.00
A.4.5.1.6 Pemasangan 1 m2 Langit-Langit Lambrisering Kayu, tebal 9 mm 425,355.68
A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm 59,805.06
A.4.5.1.7.a Pemasangan 1 m2 langit-langit GRC ukuran 120 x 240 mm tebal 4 mm 57,512.42
A.4.5.1.10 Pemasangan 1 m’ List Langit-Langit Kayu profil 31,570.38

A.4.5.2 Harga Satuan Pekerjaan Penutup Atap


A.4.5.2.1 Pemasangan 1 m2 Atap genteng Palentong Kecil 31,653.75
A.4.5.2.2 Pemasangan 1 m2 Atap genteng Palentong Kecil 346,811.25
A.4.5.2.3 Pemasangan1 m2 Atap Genteng Palentong Besar/Morando 74,180.75
A.4.5.2.4 Pemasangan 1 m’ Bubung Genteng Palentong Kecil 95,387.90
A.4.5.2.5 Pemasangan 1 m’ Bubung Genteng Kodok Glazuur 95,387.90
A.4.5.2.6 Pemasangan 1 m’ Bubung Genteng Palentong Besar 95,387.90
A.4.5.2.7 Pemasangan 1 m2 Roof Light Fibreglass 90cm x180cm 55,401.25
A.4.5.2.8 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 250cm x 5mm 30,446.25
A.4.5.2.9 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 225cm x 5mm 30,446.25
A.4.5.2.10 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm 29,382.50
A.4.5.2.11 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm 29,382.50
A.4.5.2.12 Pemasangan1 m2 Atap Serat Semen Gelombang 105cm x 300cm x 5 mm 29,382.50
A.4.5.2.15 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 240cm x 5mm 29,382.50
A.4.5.2.17 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 210cm x 5mm 29,382.50
A.4.5.2.18 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 150cm x 5mm 29,382.50
A.4.5.2.19 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 300cm x 6mm 29,382.50
A.4.5.2.20 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 270cm x 6mm 29,382.50
A.4.5.2.21 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 240cm x 6mm 29,382.50
A.4.5.2.22 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 210cm x 6mm 29,382.50
A.4.5.2.23 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 180cm x 6mm 29,382.50
A.4.5.2.24 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 92 cm 30,992.50
A.4.5.2.25 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 105 cm 30,992.50
A.4.5.2.26 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 108 cm 30,992.50
A.4.5.2.27 Pemasangan 1 m’ Nok/Bubung Paten (Permanen) 92 cm 73,168.75
A.4.5.2.28 Pemasangan 1 m’ Nok/Bubung Paten (Permanen) 105cm 30,992.50
A.4.5.2.29 Pemasangan 1 m’ Nok/Bubung Paten(Permanen) 108 cm 30,992.50
A.4.5.2.30 Pemasangan 1 m’ Nok/Bubung Setel Rata 92cm 36,518.25
A.4.5.2.31 Pemasangan 1 m’ Nok/Bubung Setel Rata 105 cm 30,992.50
A.4.5.2.32 Pemasangan 1 m2 Genteng Beton 56,350.00
A.4.5.2.32.a Pemasangan 1 m2 genteng metal Type Classic atap pelana 206,959.29
A.4.5.2.32.b Pemasangan 1 m2 genteng metal Type Royal atap pelana 215,920.32
A.4.5.2.32.c Pemasangan 1 m2 genteng metal Type Metal Stone atap pelana 239,412.75
A.4.5.2.33.a Pemasangan 1 m2 genteng metal Type Classic atap jurai 293,812.35
A.4.5.2.33.b Pemasangan 1 m2 genteng metal Type Royal atap jurai 307,598.55
A.4.5.2.33.c Pemasangan 1 m2 genteng metal Type metal Stone atap jurai 343,740.75
A.4.5.2.34 Pemasangan 1 m2 atap sirap kayu 249,716.75
A.4.5.2.35 Pemasangan 1 m2 atap sirap kayu 249,716.75
A.4.5.2.36 Pemasangan 1 m’ Nok/Bubung Genteng Beton 83,950.00
A.4.5.2.37 Pemasangan 1 m’ Nok/Bubung Genteng Aspal 93,615.75
A.4.5.2.38 Pemasangan 1 m' nok genteng metal 121,141.00
A.4.5.2.39 A.4.5.2.39. Pemasangan 1 m’ Nok/Bubung Atap Sirap 77,142.00
A.4.5.2.40 Pemasangan 1 m2 Atap Seng Gelombang 105cm x180cm 59,558.50
A.4.5.2.41 Pemasangan 1 m’ Nok/Bubung Atap Seng 29,727.50
A.4.5.2.41.a Pemasangan 1 m2 atap Zincalum Polos 0.40 232,512.75
A.4.5.2.41.b Pemasangan 1 m2 atap Zincalum Warna 0.40 242,052.00
A.4.5.2.42 Pemasangan 1 m2 Atap Aluminium Gelombang 95cm x 180cm 183,988.50
A.4.5.2.43 Pemasangan 1 m’ Nok/Bubung Atap Aluminium Gelombang 181,412.50
A.4.5.2.44 Pemasangan 1 m2 Lapisan Aluminium Foil 27,559.75

A.4.6.1 Harga Satuan Pekerjaan Kayu


A.4.6.1.1 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas I 24,572,625.00
A.4.6.1.1.a Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu belian 34,692,625.00
A.4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas II 21,661,687.50
A.4.6.1.3 Pembuatan dan pemasangan 1m2 pintu klamp standar,kayu kelas II 597,039.75
A.4.6.1.4 Pembuatan dan Pemasangan 1 m2 Pintu Klamp Sederhana, Kayu Kelas III 697,607.25
A.4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas I 1,137,099.30
A.4.6.1.5.a Pembuatan dan pemasangan 1m2 daun pintu panel, kayu belian 1,303,881.50
A.4.6.1.5.b Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas II 1,004,237.50
A.4.6.1.6 Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kelas I 804,447.08
A.4.6.1.6.a Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kelas II 724,730.00
A.4.6.1.7 Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu kelas I 1,445,896.38
A.4.6.1.8 Pembuatan dan pemasangan 1m2 pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90cm) 816,574.75
A.4.6.1.9 Pembuatan 1m2 pintu plywood rangkap, rangka expose kayu kelas I 925,178.30
A.4.6.1.10 Pemasangan 1m2 jalusi kusen, kayu kelas I 1,270,776.45
A.4.6.1.11 Pembuatan 1 m2 Teakwood Rangkap, Rangka Expose Kayu Kelas I 369,377.13
A.4.6.1.12 Pembuatan 1 m2 Teakwood Rangkap Lapis Formika, Rangka Expose 64,589.75
A.4.6.1.13 Pemasangan 1 m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas I, II dan III Bentang Sampai Dengan 6 Meter 2,605,785.00
A.4.6.1.14 Pemasangan 1m3 konstruksi kuda-kuda expose, kayu kelas I 16,730,401.25
A.4.6.1.15 Pemasangan 1m3 konstruksi gordeng, kayu kelas II 5,789,675.00
A.4.6.1.16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu kelas II 6,055,583.75
A.4.6.1.17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu Kelas II 40,701.95
A.4.6.1.18 Pemasangan 1m2 rangka atap sirap, kayu kelas II 968,392.00
A.4.6.1.19 Pemasangan 1m2 rangka langit-langit (50x100) cm, kayu kelas II 102,869.80
A.4.6.1.20 Pemasangan 1m2 rangka langit-langit (60x60) cm, kayu kelas II 97,527.48
A.4.6.1.21 Pemasangan 1m' lisplank ukuran (3x20) cm, kayu kelas I 142,494.94
A.4.6.1.22 Pemasangan 1m' lisplank ukuran (3x30) cm, kayu kelas I atau Kelas 2 143,745.75
A.4.6.1.23 Pemasangan 1m2 rangka dinding pemisah (60x120) cm, kayu kelas II 157,271.81
A.4.6.1.25 Pemasangan 1m2 dinding pemisah plywood rangkap, rangka kayu kelas II 393,727.80
A.4.6.1.26 Pemasangan 1m2 dinding lambrisering, dari papan kayu kelas I 102,025.82
A.4.6.1.27 Pemasangan 1m2 dinding lambrisering, dari plywood ukuran (120x240)cm 73,168.75
A.4.6.1.28 Pemasangan 1 m2 Dinding Bilik, Rangka Kayu Kelas III atau IV

A.4.6.2 Harga Satuan Pekerjaan Kunci dan Kaca


A.4.6.2.1 Pemasangan 1 buah kunci silinder 104,034.75
A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa 346,811.25
A.4.6.2.3 Pemasangan 1 Buah Kunci Tanam Kamar Mandi 253,851.00
A.4.6.2.4 Pemasangan 1 buah kunci silinder 171,971.00
A.4.6.2.5 Pemasangan 1 buah engsel pintu 59,367.60
A.4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu 38,959.13
A.4.6.2.7 Pemasangan 1 Buah Engsel Angin 44,249.13
A.4.6.2.8 Pemasangan 1 Buah Spring Knip untuk Jendela 27,301.00
A.4.6.2.9 Pemasangan 1 buah kait angin 43,861.00
A.4.6.2.10 Pemasangan 1 buah door closer 374,284.75
A.4.6.2.11 Pemasangan 1 buah kunci slot 33,413.25
A.4.6.2.12 Pemasangan 1 Buah Doorholder 33,413.25
A.4.6.2.13 Pemasangan 1 buah door stop 120,203.75
A.4.6.2.14 Pemasangan 1 Buah Rel Pintu Dorong 104,034.75
A.4.6.2.15 Pemasangan 1 Buah Kunci Lemari 43,356.73
A.4.6.2.16 Pemasangan 1 m2 Kaca Polos Tebal 3 mm 26,017.60
A.4.6.2.17 Pemasangan 1m2 kaca tebal 5 mm 281,030.10
A.4.6.2.18 Pemasangan 1m2 kaca tebal 8 mm 535,772.93
A.4.6.2.19 Pemasangan 1m2 kaca buram tebal 12 mm 855,774.23
A.4.6.2.20 Pemasangan 1m2 kaca cermin tebal 5 mm 556,071.00
A.4.6.2.22 Pemasangan 1 m2 Kaca Cermin Tebal 8 mm 534,399.25
A.4.6.2.23 Pemasangan 1 m2 Kaca Cermin Tebal 8 mm 27,301.00
A.4.6.2.24 Pemasangan 1 m2 Kaca Patri Tebal 5 mm 33,833.00

A.4.7.1 Harga Satuan Pekerjaan Pengecatan


A.4.7.1.1 1m2 Pengikisan/ pengerokan permukaan cat lama 20,081.00
A.4.7.1.2 1m2 Pencucian bidang permukaan tembok yang pernah di cat 19,550.00
A.4.7.1.3 1m2 Pengerokan karat pada permukaan baja cara manual 20,441.25
A.4.7.1.4 1m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 74,330.25
A.4.7.1.5 1m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup) 98,146.75
A.4.7.1.6 Pelaburan 1m2 bidang kayu dengan teak oil 131,272.50
A.4.7.1.7 Pelaburan 1m2 bidang kayu dengan polintur 88,288.95
A.4.7.1.8 Pelaburan 1m2 bidang kayu cat residu dan ter 36,650.50
A.4.7.1.9 Pelaburan 1m2 bidang kayu dengan vernis 55,556.50
A.4.7.1.10 1m2 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex 28,156.03
A.4.7.1.10.a 1m2 Pengecatan tembok baru Interior (setara Mowilex) 49,684.03
A.4.7.1.10.b 1m2 Pengecatan tembok baru Exterior (setara Mowilex) 55,664.03
A.4.7.1.10.c 1m2 Pengecatan tembok baru Interior (setara Dulux) 50,880.03
A.4.7.1.10.d 1m2 Pengecatan tembok baru Exterior (setara Dulux) 54,169.03
A.4.7.1.10.e 1m2 Pengecatan tembok baru Acian Exterior (setara Dulux) 63,541.53
A.4.7.1.11 1m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex 20,175.60
A.4.7.1.11.a 1m2 Pengecatan tembok lama Interior setara Mowilex 31,353.60
A.4.7.1.11.b 1m2 Pengecatan tembok lama Exterior setara Mowilex 35,493.60
A.4.7.1.11.c 1m2 Pengecatan tembok lama Interior setara Dulux 32,181.60
A.4.7.1.11.d 1m2 Pengecatan tembok lama Exterior setara Dulux 34,458.60
A.4.7.1.16 Pengecatan 1m2 permukaan baja dengan menie besi 41,213.13
A.4.7.1.22 Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis Cat Terakhir 188,600.00

A.5.1.1 Harga Satuan Pekerjaan Sanitasi Dalam Gedung


A.5.1.1.1 Pemasangan 1 Buah Closet Duduk/Monoblock 2,617,653.00
A.5.1.1.2 Pemasangan 1 Buah Closet Jongkok Porselen 619,907.50
A.5.1.1.3 Pemasangan 1 Buah Closet Jongkok Teraso 619,907.50
A.5.1.1.4 Pemasangan 1 Buah Urinoir 2,601,875.00
A.5.1.1.5 Pemasangan 1 Buah Wastafel 1,681,875.00
A.5.1.1.6 Pemasangan 1 Buah Bak Mandi Teraso Volume 0,30 m3 1,177,887.50
A.5.1.1.7 Pemasangan 1 Buah Bak Fibreglass Volume 0.3 m3 1,177,887.50
A.5.1.1.8 Pemasangan 1buah Bak Mandi Pasangan Bata Volume 0,30 m3 3,286,815.00
A.5.1.1.9 Pemasangan 1 Buah Bathtub Porselen 142,743.75
A.5.1.1.10 Pemasangan 1 buah Bak Beton volume 1 m3 6,129,546.00
A.5.1.1.11 Pemasangan 1 Buah Bak Air Fibreglass Volume 1 m3 497,490.00
A.5.1.1.16 Pemasangan 1 buah Bak Kontrol Pasangan Bata 30 x 30 cm Tinggi 35 cm dengan Tutup Beton 621,281.75
A.5.1.1.17 Pemasangan 1 buah Bak Kontrol Pasangan Bata 45cm x 45cm tinggi 50 cm dengan Tutup Beton 1,698,578.75
A.5.1.1.18 Pemasangan 1 buah Bak Kontrol Pasangan Bata 60cm x 60cm Tinggi 65 cm dengan Tutup Beton 1,406,569.20
A.5.1.1.19 Pemasangan 1 m’ Pipa Galvanis Diameter ½” 94,100.67
A.5.1.1.20 Pemasangan 1 m’ Pipa Galvanis Diameter ¾ ” 82,217.33
A.5.1.1.21 Pemasangan 1 m’ Pipa Galvanis Diameter 1” 122,323.58
A.5.1.1.22 Pemasangan 1 m’ Pipa Galvanis Diameter 1 ½” 180,952.50
A.5.1.1.23 Pemasangan 1 m’ Pipa Galvanis Diameter 3” 355,267.58
A.5.1.1.24 Pemasangan 1 m’ Pipa Galvanis Diameter 3” 488,955.08
A.5.1.1.25 Pemasangan 1m' pipa PVC tipe AW diameter 4" 244,919.20
A.5.1.1.26 Pemasangan 1 m’ Pipa PVC tipe AW Diameter ¾ ” 28,811.81
A.5.1.1.27 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1” 34,114.75
A.5.1.1.28 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1½” 34,114.75
A.5.1.1.29 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2” 25,103.06
A.5.1.1.30 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2½” 32,151.13
A.5.1.1.31 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3” 35,448.75
A.5.1.1.32 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 4” 181,658.31
A.5.1.1.33 Pemasangan 1 buah Bak Cuci Piring Stainlessteel 54,423.75
A.5.1.1.34 Pemasangan 1 buah Bak Cuci Piring Teraso 132,393.75
A.5.1.1.35 Pemasangan 1 buah Kran Diameter ½” atau ¾ ” 103,643.75
A.5.1.1.36 Pemasangan 1 buah Floor Drain 18,141.25
A.5.1.1.37 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah Ǿ 20 cm 694,523.33
A.5.1.1.38 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah diameter 15 cm 630,980.08
A.5.1.1.39 Pemasangan 1 m’ Pipa Beton Diameter 15 – 20 cm 588,233.24
A.5.1.1.40 Pemasangan 1 m’ Pipa Beton Diameter 30 – 100 cm 588,233.24

A.6.1.1 Harga Satuan Pekerjaan Sistem Distribusi Jaringan Listrik


A.6.1.1.1 Pemasangan 1 buah MCCB -

A.6.1.2 Harga Satuan Pekerjaan Sistem Pencahayaan


A.6.2.1.1 Pemasangan 1 Buah Titik Lampu -
A.2.2.1 Harga Satuan Pekerjaan Persiapan

A.2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.400 125,000.00 50,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.020 155,000.00 3,100.00
JUMLAH TENAGA KERJA 77,000.00
B BAHAN
Dolken Kayu 8-10/400 cm Batang 1.250 12,000.00 15,000.00
Semen Portland Kg 2.500 -
Seng gelombang Lbr 1.200 55,000.00 66,000.00
Pasir Beton m3 0.005 -
Koral Beton m3 0.009 -
Kayu 5/7 m3 0.072 4,755,000.00 342,360.00
Paku Biasa 2"-5" Kg 0.060 23,000.00 1,380.00
Mini besi Liter 0.450 52,000.00 23,400.00
JUMLAH HARGA BAHAN 448,140.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 525,140.00
E Overhead & Provit 15% x D 78,771.00
F Harga Satuan Pekerjaan ( D + E ) 603,911.00

A.2.2.1.3 (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.300 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.020 155,000.00 3,100.00
JUMLAH TENAGA KERJA 64,500.00
B BAHAN
Dolken Kayu 8-10/400 cm Batang 1.000 12,000.00 12,000.00
Semen Portland Kg 2.000 1,500.00 3,000.00
Kawat duri m 25.000 4,000.00 100,000.00
Pasir Beton m3 0.005 1,500.00 7.50
Koral Beton m3 0.009 125,000.00 1,125.00
Paku Biasa 2"-5" Kg 0.060 23,000.00 1,380.00
JUMLAH HARGA BAHAN 117,512.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 182,012.50
E Overhead & Provit 15% x D 27,301.88
F Harga Satuan Pekerjaan ( D + E ) 209,314.38

A.2.2.1.4 Pengukuran dan pemasangan 1m Bouwplank


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Kayu balok 5/7 m3 0.012 4,755,000.00 57,060.00
Paku 2"-3" Kg 0.020 23,000.00 460.00
Kayu papan 3/20 m3 0.007 2,558,000.00 17,906.00
JUMLAH HARGA BAHAN 75,426.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 100,651.00
E Overhead & Provit 15% x D 15,097.65
F Harga Satuan Pekerjaan ( D + E ) 115,748.65

A.2.2.1.5 (K3) Pembuatan 1m2 kantor sementara lantai plasteran


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.000 105,000.00 210,000.00
Tukang Kayu L.02 OH 2.000 125,000.00 250,000.00
Tukang Batu L.02 OH 1.000 125,000.00 125,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 636,250.00
B BAHAN
Dolken Kayu 8-10/400 cm Batang 1.250 12,000.00 15,000.00
Kayu m3 0.180 4,716,717.69 849,009.18
Paku biasa Kg 0.080 23,000.00 1,840.00
Besi strip Kg 1.100 17,000.00 18,700.00
Semen Portland Kg 35.000 1,500.00 52,500.00
Pasir pasang m3 0.150 125,000.00 18,750.00
Pasir beton m3 0.100 125,000.00 12,500.00
Koral beton m3 0.150 500,000.00 75,000.00
Bata merah Bh 30.000 2,000.00 60,000.00
Seng pelat Lbr 0.250 65,000.00 16,250.00
Jendela naco Bh 0.200 400,000.00 80,000.00
Kaca polos m2 0.080 150,000.00 12,000.00
Kunci tanam Bh 0.150 150,000.00 22,500.00
Plywood 4 mm Lbr 0.060 120,000.00 7,200.00
JUMLAH HARGA BAHAN 1,241,249.18
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,877,499.18
E Overhead & Provit 15% x D 281,624.88
F Harga Satuan Pekerjaan ( D + E ) 2,159,124.06

A.2.2.1.9 (K3) Pembersihan 1 m2 lapangan atau perataan


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 10,500.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 10,500.00
E Overhead & Provit 15% x D 1,575.00
F Harga Satuan Pekerjaan ( D + E ) 12,075.00

A.2.2.1.12 Pembuatan 1 m2 jalan sementara


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 105,775.00
B BAHAN
Batu belah m3 0.150 350,000.00 52,500.00
Batu pecah m3 0.090 335,000.00 30,150.00
Pasir pasang m3 0.010 125,000.00 1,250.00
JUMLAH HARGA BAHAN 83,900.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 189,675.00
E Overhead & Provit 15% x D 28,451.25
F Harga Satuan Pekerjaan ( D + E ) 218,126.25

A.2.2.1.13 Pembongkaran 1 m3 beton bertulang


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 13.334 105,000.00 1,400,070.00
Mandor L.04 OH 0.666 155,000.00 103,230.00
JUMLAH TENAGA KERJA 1,503,300.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,436,630.00
E Overhead & Provit 15% x D 215,494.50
F Harga Satuan Pekerjaan ( D + E ) 1,652,124.50

A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 6.667 105,000.00 700,035.00
Mandor L.04 OH 0.333 155,000.00 51,615.00
JUMLAH TENAGA KERJA 751,650.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 718,315.00
E Overhead & Provit 15% x D 107,747.25
F Harga Satuan Pekerjaan ( D + E ) 826,062.25
A.4.6.1.23.a Pemasangan 1m2 rangka dinding pemisah (60x120) cm, kayu belian
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang Kayu L.03 OH 0.450 125,000.00 56,250.00
Kepala Tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 79,765.00
B BAHAN
Balok kayu kelas II uk. 7/7 m3 0.028 14,814,000.00 414,792.00
Paku beton Kg 0.150 40,000.00 6,000.00
JUMLAH HARGA BAHAN 420,792.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 500,557.00
E Overhead & Provit 15% x D (maksimum) 75,083.55
F Harga Satuan Pekerjaan ( D + E ) 575,640.55
* untuk analisa ornamen 2018

A.4.2.1.9.a Pemasangan 1 m2 Aluminium Composite Panel (ACP)


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang Kayu L.03 OH 0.800 125,000.00 100,000.00
Kepala Tukang L.03 OH 0.080 145,000.00 11,600.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 120,620.00
B BAHAN
Alumunium Komposit + Rangka Besi m2 1.000 908,700.00 908,700.00
JUMLAH HARGA BAHAN 908,700.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,029,320.00
E Overhead & Provit 15% x D (maksimum) 154,398.00
F Harga Satuan Pekerjaan ( D + E ) 1,183,718.00
A.2.3.1 Harga Satuan Pekerjaan Tanah

A.3.2.1.1 Penggalian 1m3 tanah biasa sedalam 1m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.750 105,000.00 78,750.00
Mandor L.04 OH 0.025 155,000.00 3,875.00
JUMLAH TENAGA KERJA 82,625.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 82,625.00
E Overhead & Provit 15% x D 12,393.75
F Harga Satuan Pekerjaan ( D + E ) 95,018.75

A.3.2.1.2 Penggalian 1m3 tanah biasa sedalam 2 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 101,475.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 101,475.00
E Overhead & Provit 15% x D 15,221.25
F Harga Satuan Pekerjaan ( D + E ) 116,696.25

A.3.2.1.3 Menggali 1m3 tanah biasa sedalam 3 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.050 105,000.00 110,250.00
Mandor L.04 OH 0.067 155,000.00 10,385.00
JUMLAH TENAGA KERJA 120,635.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 120,635.00
E Overhead & Provit 15% x D 18,095.25
F Harga Satuan Pekerjaan ( D + E ) 138,730.25

A.3.2.1.4 Menggali 1m3 tanah keras sedalam 1 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Mandor L.04 OH 0.032 155,000.00 4,960.00
JUMLAH TENAGA KERJA 109,960.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 109,960.00
E Overhead & Provit 15% x D 16,494.00
F Harga Satuan Pekerjaan ( D + E ) 126,454.00

A.3.2.1.5 Menggali 1m3 tanah cadas sedalam 1 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Mandor L.04 OH 0.032 155,000.00 4,960.00
JUMLAH TENAGA KERJA 109,960.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 109,960.00
E Overhead & Provit 15% x D 16,494.00
F Harga Satuan Pekerjaan ( D + E ) 126,454.00

A.3.2.1.6 Menggali 1m3 tanah lumpur sedalam 1 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 105,000.00 126,000.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 132,975.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 132,975.00
E Overhead & Provit 15% x D 19,946.25
F Harga Satuan Pekerjaan ( D + E ) 152,921.25

A.3.2.1.8 Menggali 1m3 tanah lumpur sedalam 1 m


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.330 105,000.00 34,650.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 36,200.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 36,200.00
E Overhead & Provit 15% x D 5,430.00
F Harga Satuan Pekerjaan ( D + E ) 41,630.00

A.3.2.1.9 Pengurugan kembali 1 m3 galian tanah


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 60,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Pasir Urug M³ 1.200 125,000.00 150,000.00
JUMLAH HARGA ALAT 150,000.00
D Jumlah (A + B + C) 210,250.00
E Overhead & Provit 15% x D 31,537.50
F Harga Satuan Pekerjaan ( D + E ) 241,787.50

A.3.2.1.10 (K3) Pemadatan tanah 1 m3 tanah (per 20 cm)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 60,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 60,250.00
E Overhead & Provit 15% x D 9,037.50
F Harga Satuan Pekerjaan ( D + E ) 69,287.50

A.3.2.1.11 Pengurugan 1 m3 dengan pasir urug


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 60,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Pasir Urug M³ 1.200 125,000.00 150,000.00
JUMLAH HARGA ALAT 150,000.00
D Jumlah (A + B + C) 210,250.00
E Overhead & Provit 15% x D 31,537.50
F Harga Satuan Pekerjaan ( D + E ) 241,787.50

A.3.2.1.11a Pengurugan 1 m3 dengan Tanah Pilihan


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 60,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Tanah Pilihan (Paladis) M³ 1.200 284,000.00 340,800.00
JUMLAH HARGA ALAT 340,800.00
D Jumlah (A + B + C) 401,050.00
E Overhead & Provit 15% x D 60,157.50
F Harga Satuan Pekerjaan ( D + E ) 461,207.50

A.3.2.1.11b Pengurugan 1 m3 dengan Tanah Ex. Peniraman


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 60,250.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Tanah Ex. Peniraman M³ 1.200 190,000.00 228,000.00
JUMLAH HARGA ALAT 228,000.00
D Jumlah (A + B + C) 288,250.00
E Overhead & Provit 15% x D 43,237.50
F Harga Satuan Pekerjaan ( D + E ) 331,487.50
A.3.2.1 Harga Satuan Pekerjaan Pondasi

A.3.2.1.1 Pemasangan 1m3 pondasi batu belah campuran 1SP : 3PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.500 105,000.00 157,500.00
Tukang batu L.02 OH 0.750 125,000.00 93,750.00
Kepala tukang L.03 OH 0.075 145,000.00 10,875.00
Mandor L.04 OH 0.075 155,000.00 11,625.00
JUMLAH TENAGA KERJA 273,750.00
B BAHAN
Batu belah (10-15 cm) m3 1.200 350,000.00 420,000.00
Semen Portland Kg 202.000 1,500.00 303,000.00
Pasir pasang m3 0.485 125,000.00 60,625.00
JUMLAH HARGA BAHAN 783,625.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,057,375.00
E Overhead & Provit 15% x D 158,606.25
F Harga Satuan Pekerjaan ( D + E ) 1,215,981.25

A.3.2.1.2 Pemasangan 1m3 pondasi batu belah campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.500 105,000.00 157,500.00
Tukang batu L.02 OH 0.750 125,000.00 93,750.00
Kepala tukang L.03 OH 0.075 145,000.00 10,875.00
Mandor L.04 OH 0.075 155,000.00 11,625.00
JUMLAH TENAGA KERJA 273,750.00
B BAHAN
Batu belah (10-15 cm) m3 1.200 350,000.00 420,000.00
Semen Portland Kg 163.000 1,500.00 244,500.00
Pasir pasang m3 0.520 125,000.00 65,000.00
JUMLAH HARGA BAHAN 729,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,003,250.00
E Overhead & Provit 15% x D 150,487.50
F Harga Satuan Pekerjaan ( D + E ) 1,153,737.50
A.3.2.1.9 (K3) Pemasangan 1m3 pondasi batu kosong (anstamping)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.780 105,000.00 81,900.00
Tukang batu L.02 OH 0.390 125,000.00 48,750.00
Kepala tukang L.03 OH 0.039 145,000.00 5,655.00
Mandor L.04 OH 0.039 155,000.00 6,045.00
142,350.00
B BAHAN
Batu belah (10-15 cm) m3 1.200 350,000.00 420,000.00
Pasir urug m3 0.432 125,000.00 54,000.00
JUMLAH HARGA BAHAN 474,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 616,350.00
E Overhead & Provit 15% x D 92,452.50
F Harga Satuan Pekerjaan ( D + E ) 708,802.50

A.3.2.1.10 Pemasangan 1m3 pondasi siklop, 60% beton campuran 1 SP : 2PB : 3 Kr dan 40% batu belah
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.400 105,000.00 357,000.00
Tukang batu L.02 OH 0.850 125,000.00 106,250.00
Kepala tukang L.03 OH 0.085 145,000.00 12,325.00
Mandor L.04 OH 0.170 155,000.00 26,350.00
JUMLAH TENAGA KERJA 501,925.00
B BAHAN
Batu belah (10-15 cm) m3 0.480 350,000.00 168,000.00
Semen Portland Kg 194.000 1,500.00 291,000.00
Pasir beton m3 0.312 125,000.00 39,000.00
Kerikil (1-2 cm) m3 0.468 475,000.00 222,300.00
Besi beton Kg 126.000 13,500.00 1,701,000.00
Kawat beton Kg 1.800 25,000.00 45,000.00
JUMLAH HARGA BAHAN 2,466,300.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 2,968,225.00
E Overhead & Provit 15% x D 445,233.75
F Harga Satuan Pekerjaan ( D + E ) 3,413,458.75
A.3.2.1.11 Pemasangan 1m3 pondasi sumuran, diameter 100 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.400 105,000.00 252,000.00
Tukang batu L.02 OH 0.800 125,000.00 100,000.00
Kepala tukang L.03 OH 0.080 145,000.00 11,600.00
Mandor L.04 OH 0.119 155,000.00 18,445.00
JUMLAH TENAGA KERJA 382,045.00
B BAHAN
Batu belah (10-15 cm) m3 0.450 350,000.00 157,500.00
Semen Portland Kg 194.000 1,500.00 291,000.00
Pasir beton m3 0.312 125,000.00 39,000.00
Kerikil (1-2 cm) m3 0.468 475,000.00 222,300.00
JUMLAH HARGA BAHAN 709,800.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,091,845.00
E Overhead & Provit 15% x D 163,776.75
F Harga Satuan Pekerjaan ( D + E ) 1,255,621.75
A.4.1.1 Harga Satuan Pekerjaan Beton

A.4.1.1.1 Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 247.000 1,500.00 370,500.00
Pasir beton Kg 869.000 89.29 77,589.29
Kerikil (maks 30 mm) Kg 999.000 351.85 351,500.00
Air Liter 215.000
JUMLAH HARGA BAHAN 799,589.29
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,024,139.29
E Overhead & Provit 15% x D 153,620.89
F Harga Satuan Pekerjaan ( D + E ) 1,177,760.18

A.4.1.1.1.a Membuat 1m3 beton mutu f'c = 7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 247.000 1,500.00 370,500.00
Pasir beton Kg 869.000 89.29 77,589.29
Kerikil (maks 30 mm) Kg 999.000 351.85 351,500.00
Air Liter 215.000
JUMLAH HARGA BAHAN 799,589.29
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,017,614.29
E Overhead & Provit 15% x D 152,642.14
F Harga Satuan Pekerjaan ( D + E ) 1,170,256.43
A.4.1.1.2 Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 276.000 1500.00 414,000.00
Pasir beton Kg 828.000 89.29 73,928.57
Kerikil (maks 30 mm) Kg 1012.000 351.85 356,074.07
Air Liter 215.000
JUMLAH HARGA BAHAN 844,002.65
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,068,552.65
E Overhead & Provit 15% x D 160,282.90
F Harga Satuan Pekerjaan ( D + E ) 1,228,835.54

A.4.1.1.2.a Membuat 1m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm ,w/c =0,78 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 276.000 1500.00 414,000.00
Pasir beton Kg 828.000 89.29 73,928.57
Kerikil (maks 30 mm) Kg 1012.000 351.85 356,074.07
Air Liter 215.000
JUMLAH HARGA BAHAN 844,002.65
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,062,027.65
E Overhead & Provit 15% x D 159,304.15
F Harga Satuan Pekerjaan ( D + E ) 1,221,331.79
A.4.1.1.3 Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 299.000 1,500.00 448,500.00
Pasir beton Kg 799.000 89.29 71,339.29
Kerikil (maks 30 mm) Kg 1017.000 351.85 357,833.33
Air Liter 215.000
JUMLAH HARGA BAHAN 877,672.62
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,102,222.62
E Overhead & Provit 15% x D 165,333.39
F Harga Satuan Pekerjaan ( D + E ) 1,267,556.01
Catatan
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, buckling factor pasir = 20%

A.4.1.1.3.a Membuat 1m3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm ,w/c =0,72 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 299.000 1,500.00 448,500.00
Pasir beton Kg 799.000 89.29 71,339.29
Kerikil (maks 30 mm) Kg 1017.000 351.85 357,833.33
Air Liter 215.000
JUMLAH HARGA BAHAN 877,672.62
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,095,697.62
E Overhead & Provit 15% x D 164,354.64
F Harga Satuan Pekerjaan ( D + E ) 1,260,052.26
A.4.1.1.4 Membuat 1m3 lantai kerja beton mutu f'c = 7,4 MPa slump (3-6) cm, w/c =0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 105,000.00 126,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.060 155,000.00 9,300.00
JUMLAH TENAGA KERJA 163,200.00
B BAHAN
Semen Portland Kg 230.000 1,500.00 345,000.00
Pasir beton Kg 893.000 89.29 79,732.14
Kerikil (maks 30 mm) Kg 1027.000 351.85 361,351.85
Air Liter 200.000
JUMLAH HARGA BAHAN 786,083.99
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 949,283.99
E Overhead & Provit 15% x D 142,392.60
F Harga Satuan Pekerjaan ( D + E ) 1,091,676.59

A.4.1.1.5 Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 326.000 1,500.00 489,000.00
Pasir beton Kg 760.000 89.29 67,857.14
Kerikil (maks 30 mm) Kg 1029.000 351.85 362,055.56
Air Liter 215.000
JUMLAH HARGA BAHAN 918,912.70
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,143,462.70
E Overhead & Provit 15% x D 171,519.40
F Harga Satuan Pekerjaan ( D + E ) 1,314,982.10
A.4.1.1.5.a Membuat 1m3 beton mutu f'c = 14,5 MPa (K 175), slump (12 ± 2) cm ,w/c = 0,66 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 326.000 1,500.00 489,000.00
Pasir beton Kg 760.000 89.29 67,857.14
Kerikil (maks 30 mm) Kg 1029.000 351.85 362,055.56
Air Liter 215.000
JUMLAH HARGA BAHAN 918,912.70
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,136,937.70
E Overhead & Provit 15% x D 170,540.65
F Harga Satuan Pekerjaan ( D + E ) 1,307,478.35

A.4.1.1.6 Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 352.000 1,500.00 528,000.00
Pasir beton Kg 731.000 89.29 65,267.86
Kerikil (maks 30 mm) Kg 1031.000 351.85 362,759.26
Air Liter 215.000
JUMLAH HARGA BAHAN 956,027.12
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,180,577.12
E Overhead & Provit 15% x D 177,086.57
F Harga Satuan Pekerjaan ( D + E ) 1,357,663.68
A.4.1.1.6.a Membuat 1m3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm ,w/c = 0,61 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 352.000 1,500.00 528,000.00
Pasir beton Kg 731.000 89.29 65,267.86
Kerikil (maks 30 mm) Kg 1031.000 351.85 362,759.26
Air Liter 215.000
JUMLAH HARGA BAHAN 956,027.12
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,174,052.12
E Overhead & Provit 15% x D 176,107.82
F Harga Satuan Pekerjaan ( D + E ) 1,350,159.93

A.4.1.1.7 Membuat 1m3 beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm ,w/c = 0,58
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 371.000 1,500.00 556,500.00
Pasir beton Kg 698.000 89.29 62,321.43
Kerikil (maks 30 mm) Kg 1047.000 351.85 368,388.89
Air Liter 215.000
JUMLAH HARGA BAHAN 987,210.32
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,211,760.32
E Overhead & Provit 15% x D 181,764.05
F Harga Satuan Pekerjaan ( D + E ) 1,393,524.37
A.4.1.1.7.a Membuat 1m3 beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm ,w/c = 0,58 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 371.000 1,500.00 556,500.00
Pasir beton Kg 698.000 89.29 62,321.43
Kerikil (maks 30 mm) Kg 1047.000 351.85 368,388.89
Air Liter 215.000
JUMLAH HARGA BAHAN 987,210.32
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,205,235.32
E Overhead & Provit 15% x D 180,785.30
F Harga Satuan Pekerjaan ( D + E ) 1,386,020.62

A.4.1.1.8 Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 384.000 1,500.00 576,000.00
Pasir beton Kg 692.000 89.29 61,785.71
Kerikil (maks 30 mm) Kg 1039.000 351.85 365,574.07
Air Liter 215.000
JUMLAH HARGA BAHAN 1,003,359.79
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,227,909.79
E Overhead & Provit 15% x D 184,186.47
F Harga Satuan Pekerjaan ( D + E ) 1,412,096.26
A.4.1.1.8.a Membuat 1m3 beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm ,w/c = 0,56 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 384.000 1,500.00 576,000.00
Pasir beton Kg 692.000 89.29 61,785.71
Kerikil (maks 30 mm) Kg 1039.000 351.85 365,574.07
Air Liter 215.000
JUMLAH HARGA BAHAN 1,003,359.79
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,221,384.79
E Overhead & Provit 15% x D 183,207.72
F Harga Satuan Pekerjaan ( D + E ) 1,404,592.51

A.4.1.1.9 Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 406.000 1,500.00 609,000.00
Pasir beton Kg 684.000 89.29 61,071.43
Kerikil (maks 30 mm) Kg 1026.000 351.85 361,000.00
Air Liter 215.000 -
JUMLAH HARGA BAHAN 1,031,071.43
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,255,621.43
E Overhead & Provit 15% x D 188,343.21
F Harga Satuan Pekerjaan ( D + E ) 1,443,964.64
A.4.1.1.9.a Membuat 1m3 beton mutu f'c = 24,0 Mpa (K 275), slump (12 ± 2) cm ,w/c = 0,53 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 406.000 1,500.00 609,000.00
Pasir beton Kg 684.000 89.29 61,071.43
Kerikil (maks 30 mm) Kg 1026.000 351.85 361,000.00
Air Liter 215.000 -
JUMLAH HARGA BAHAN 1,031,071.43
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,249,096.43
E Overhead & Provit 15% x D 187,364.46
F Harga Satuan Pekerjaan ( D + E ) 1,436,460.89

A.4.1.1.10 Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 105,000.00 173,250.00
Tukang batu L.02 OH 0.275 125,000.00 34,375.00
Kepala tukang L.03 OH 0.028 145,000.00 4,060.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 224,550.00
B BAHAN
Semen Portland Kg 413.000 1,500.00 619,500.00
Pasir beton Kg 681.000 89.29 60,803.57
Kerikil (maks 30 mm) Kg 1021.000 351.85 359,240.74
Air Liter 215.000
JUMLAH HARGA BAHAN 1,039,544.31
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,264,094.31
E Overhead & Provit 15% x D 189,614.15
F Harga Satuan Pekerjaan ( D + E ) 1,453,708.46
A.4.1.1.10.a Membuat 1m3 beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm ,w/c = 0,52 (menggunakan molen)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.323 105,000.00 138,915.00
Tukang batu L.02 OH 0.189 125,000.00 23,625.00
Kepala tukang L.03 OH 0.019 145,000.00 2,755.00
Mandor L.04 OH 0.066 155,000.00 10,230.00
JUMLAH TENAGA KERJA 175,525.00
B BAHAN
Semen Portland Kg 413.000 1,500.00 619,500.00
Pasir beton Kg 681.000 89.29 60,803.57
Kerikil (maks 30 mm) Kg 1021.000 351.85 359,240.74
Air Liter 215.000
JUMLAH HARGA BAHAN 1,039,544.31
C PERALATAN
Sewa Molen sewa-hari 0.250 170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00
D Jumlah (A + B + C) 1,257,569.31
E Overhead & Provit 15% x D 188,635.40
F Harga Satuan Pekerjaan ( D + E ) 1,446,204.71

A.4.1.1.11 Membuat 1m3 beton mutu f'c = 28,8 Mpa (K 325), slump (12 ± 2) cm ,w/c = 0,49
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 105,000.00 220,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.105 155,000.00 16,275.00
JUMLAH TENAGA KERJA 285,600.00
B BAHAN
Semen Portland Kg 439.000 1,500.00 658,500.00
Pasir beton Kg 670.000 89.29 59,821.43
Kerikil (maks 30 mm) Kg 1006.000 351.85 353,962.96
Air Liter 215.000
JUMLAH HARGA BAHAN 1,072,284.39
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,357,884.39
E Overhead & Provit 15% x D 203,682.66
F Harga Satuan Pekerjaan ( D + E ) 1,561,567.05
A.4.1.1.12 Membuat 1m3 beton mutu f'c = 31,2 Mpa (K 350), slump (12 ± 2) cm ,w/c = 0,48
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 105,000.00 220,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.105 155,000.00 16,275.00
JUMLAH TENAGA KERJA 285,600.00
B BAHAN
Semen Portland Kg 448.000 1,500.00 672,000.00
Pasir beton Kg 667.000 89.29 59,553.57
Kerikil (maks 30 mm) Kg 1000.000 351.85 351,851.85
Air Liter 215.000
JUMLAH HARGA BAHAN 1,083,405.42
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,369,005.42
E Overhead & Provit 15% x D 205,350.81
F Harga Satuan Pekerjaan ( D + E ) 1,574,356.24

A.4.1.1.13 Membuat 1m3 beton kedap air dengan strorox - 100


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.100 105,000.00 220,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.105 155,000.00 16,275.00
JUMLAH TENAGA KERJA 285,600.00
B BAHAN
Semen Portland Kg 400.000 1,500.00 600,000.00
Pasir beton m3 0.480 89.29 42.86
Kerikil (maks 30 mm) m3 0.800 351.85 281.48
Air Kg 1.200
JUMLAH HARGA BAHAN 600,324.34
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 885,924.34
E Overhead & Provit 15% x D 132,888.65
F Harga Satuan Pekerjaan ( D + E ) 1,018,812.99
A.4.1.1.16 Membuat 1m PVC Waterstop lebar 300 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang batu L.02 OH 0.040 125,000.00 5,000.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 14,600.00
B BAHAN
Waterstop lebar 300 mm m 1.050 75,000 78,750.00
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 14,000.00
E Overhead & Provit 15% x D 2,100.00
F Harga Satuan Pekerjaan ( D + E ) 16,100.00

A.4.1.1.17 Pembesian 10 Kg dengan besi polos atau besi ulir (U24)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang besi L.02 OH 0.070 125,000.00 8,750.00
Kepala tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 17,735.00
B BAHAN
Besi beton (Polos/ulir) (U24) Kg 10.500 13,500.00 141,750.00
Kawat beton Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 145,500.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 163,235.00
E Overhead & Provit 15% x D 24,485.25
F Harga Satuan Pekerjaan ( D + E ) 187,720.25
G Harga Satuan Pekerjaan per 1Kg besi 18,772.03
A.4.1.1.17.a Pembesian 1 Kg dengan besi polos atau besi ulir (U32)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang besi L.02 OH 0.070 125,000.00 8,750.00
Kepala tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 17,735.00
B BAHAN
Besi beton (Polos/ulir) (U32) Kg 10.500 13,500.00 141,750.00
Kawat beton Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 145,500.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 163,235.00
E Overhead & Provit 15% x D 24,485.25
F Harga Satuan Pekerjaan ( D + E ) 187,720.25
G Harga Satuan Pekerjaan per 1Kg besi 18,772.03

A.4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.025 105,000.00 2,625.00
Tukang besi L.02 OH 0.025 125,000.00 3,125.00
Kepala tukang L.03 OH 0.025 145,000.00 3,625.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 9,530.00
B BAHAN
Jaring kawat baja dilas Kg 10.200 14500 147,900.00
Kawat beton Kg 0.050 25000 1,250.00
JUMLAH HARGA BAHAN 149,150.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 158,680.00
E Overhead & Provit 15% x D 23,802.00
F Harga Satuan Pekerjaan ( D + E ) 182,482.00
A.4.1.1.20 (K3) Pemasangan 1m2 bekisting untuk pondasi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 105,000.00 54,600.00
Tukang kayu L.02 OH 0.260 125,000.00 32,500.00
Kepala tukang L.03 OH 0.026 145,000.00 3,770.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 94,900.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 10 cm Kg 0.300 23,000.00 6,900.00
Minyak bekisting Liter 0.100 -
JUMLAH HARGA BAHAN 90,220.00
C PERALATAN
-
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 185,120.00
E Overhead & Provit 15% x D 27,768.00
F Harga Satuan Pekerjaan ( D + E ) 212,888.00

A.4.1.1.20.a Pemasangan 1m2 bekisting untuk pondasi (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 105,000.00 54,600.00
Tukang kayu L.02 OH 0.260 125,000.00 32,500.00
Kepala tukang L.03 OH 0.026 145,000.00 3,770.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 94,900.00
B BAHAN
Papan Mal kelas III m³ 0.013 2,558,000.00 33,254.00
Paku 5 - 10 cm Kg 0.300 23,000.00 6,900.00
Cerucuk ф 6-8 cm - panj 4 m Btg 0.125 9,000.00 1,125.00
JUMLAH HARGA BAHAN 41,279.00
C PERALATAN
-
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 136,179.00
E Overhead & Provit 15% x D 20,426.85
F Harga Satuan Pekerjaan ( D + E ) 156,605.85
A.4.1.1.21 (K3) Pemasangan 1m2 bekisting untuk sloof
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 105,000.00 54,600.00
Tukang kayu L.02 OH 0.260 125,000.00 32,500.00
Kepala tukang L.03 OH 0.026 145,000.00 3,770.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 94,900.00
B BAHAN
Kayu kelas III m3 0.045 2,083,000.00 93,735.00
Paku 5 - 10 cm Kg 0.300 23,000.00 6,900.00
Minyak bekisting Liter 0.100 -
JUMLAH HARGA BAHAN 100,635.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 195,535.00
E Overhead & Provit 15% x D 29,330.25
F Harga Satuan Pekerjaan ( D + E ) 224,865.25

A.4.1.1.21.a Pemasangan 1m2 bekisting untuk sloof (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 105,000.00 54,600.00
Tukang kayu L.02 OH 0.260 125,000.00 32,500.00
Kepala tukang L.03 OH 0.026 145,000.00 3,770.00
Mandor L.04 OH 0.026 155,000.00 4,030.00
JUMLAH TENAGA KERJA 94,900.00
B BAHAN
Papan Mal kelas III m³ 0.013 2,558,000.00 33,254.00
Paku 5 - 10 cm Kg 0.300 23,000.00 6,900.00
Cerucuk ф 6-8 cm - panj 4 m Btg 0.125 9,000.00 1,125.00
JUMLAH HARGA BAHAN 41,279.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 136,179.00
E Overhead & Provit 15% x D 20,426.85
F Harga Satuan Pekerjaan ( D + E ) 156,605.85
A.4.1.1.22 (K3) Pemasangan 1m2 bekisting untuk kolom
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Plywood tebal 9 mm Lbr 0.350 220,000.00 77,000.00
Dolken kayu ɸ8-10cm - panj 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 249,605.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 370,055.00
E Overhead & Provit 15% x D 55,508.25
F Harga Satuan Pekerjaan ( D + E ) 425,563.25

A.4.1.1.22.a Pemasangan 1m2 bekisting untuk kolom (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Papan Mal kelas III m3 0.013 2,558,000.00 33,254.00
Dolken kayu ɸ8-10cm - panj 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 205,859.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 326,309.00
E Overhead & Provit 15% x D 48,946.35
F Harga Satuan Pekerjaan ( D + E ) 375,255.35
A.4.1.1.23 (K3) Pemasangan 1m2 bekisting untuk balok
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.018 3,355,000.00 60,390.00
Plywood tebal 9 mm Lbr 0.350 220,000.00 77,000.00
Dolken kayu ɸ(8-10)cm - panj 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 259,670.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 380,120.00
E Overhead & Provit 15% x D 57,018.00
F Harga Satuan Pekerjaan ( D + E ) 437,138.00

A.4.1.1.23.a Pemasangan 1m2 bekisting untuk balok (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.018 3,355,000.00 60,390.00
Papan Mal kelas III m3 0.013 2,558,000.00 33,254.00
Dolken kayu ɸ(8-10)cm - panj 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 215,924.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 336,374.00
E Overhead & Provit 15% x D 50,456.10
F Harga Satuan Pekerjaan ( D + E ) 386,830.10
A.4.1.1.24 (K3) Pemasangan 1m2 bekisting untuk lantai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Plywood tebal 9 mm Lbr 0.350 220,000.00 77,000.00
Dolken kayu galam, ɸ(8-10)cm 4 m Batang 6.000 12,000.00 72,000.00
JUMLAH HARGA BAHAN 297,605.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 418,055.00
E Overhead & Provit 15% x D 62,708.25
F Harga Satuan Pekerjaan ( D + E ) 480,763.25

A.4.1.1.24.a Pemasangan 1m2 bekisting untuk lantai (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.040 2,083,000.00 83,320.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Papan Mal kelas III m3 0.013 2,558,000.00 33,254.00
Dolken kayu galam, ɸ(8-10)cm 4 m Batang 6.000 12,000.00 72,000.00
JUMLAH HARGA BAHAN 253,859.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 374,309.00
E Overhead & Provit 15% x D 56,146.35
F Harga Satuan Pekerjaan ( D + E ) 430,455.35
A.4.1.1.25 (K3) Pemasangan 1m2 bekisting untuk dinding
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.030 2,083,000.00 62,490.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.020 3,355,000.00 67,100.00
Plywood tebal 9 mm Lbr 0.350 220,000.00 77,000.00
Dolken kayu, ɸ(8-10)cm panjang 4 m Batang 3.000 12,000.00 36,000.00
Penjaga jarak bekisting/spacer Buah 4.000 -
JUMLAH HARGA BAHAN 257,550.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 378,000.00
E Overhead & Provit 15% x D 56,700.00
F Harga Satuan Pekerjaan ( D + E ) 434,700.00

A.4.1.1.25.a Pemasangan 1m2 bekisting untuk dinding (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.030 2,083,000.00 62,490.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Balok kayu kelas II m3 0.020 3,355,000.00 67,100.00
Plywood tebal 9 mm m3 0.013 2,558,000.00 33,254.00
Dolken kayu, ɸ(8-10)cm panjang 4 m Batang 3.000 12,000.00 36,000.00
JUMLAH HARGA BAHAN 213,804.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 334,254.00
E Overhead & Provit 15% x D 50,138.10
F Harga Satuan Pekerjaan ( D + E ) 384,392.10
A.4.1.1.26 (K3) Pemasangan 1m2 bekisting untuk tangga
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.030 2,083,000.00 62,490.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.150 28,800.00 4,320.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Plywood tebal 9 mm Lbr 0.350 220,000.00 77,000.00
Dolken kayu ɸ(8-10)cm panjang 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 227,335.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 347,785.00
E Overhead & Provit 15% x D 52,167.75
F Harga Satuan Pekerjaan ( D + E ) 399,952.75

A.4.1.1.26.a Pemasangan 1m2 bekisting untuk tangga (papan mal)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 105,000.00 69,300.00
Tukang kayu L.02 OH 0.330 125,000.00 41,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.033 155,000.00 5,115.00
JUMLAH TENAGA KERJA 120,450.00
B BAHAN
Kayu kelas III m3 0.030 2,083,000.00 62,490.00
Paku 5 - 12 cm Kg 0.400 23,000.00 9,200.00
Minyak bekisting Liter 0.150 28,800.00 4,320.00
Balok kayu kelas II m3 0.015 3,355,000.00 50,325.00
Papan Mal kelas III m3 0.013 2,558,000.00 33,254.00
Dolken kayu ɸ(8-10)cm panjang 4 m Batang 2.000 12,000.00 24,000.00
JUMLAH HARGA BAHAN 183,589.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 304,039.00
E Overhead & Provit 15% x D 45,605.85
F Harga Satuan Pekerjaan ( D + E ) 349,644.85
A.4.1.1.27 Pemasangan 1m2 jembatan untuk pengecoran beton
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.02 OH 0.050 125,000.00 6,250.00
Kepala tukang L.03 OH 0.005 145,000.00 725.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,965.00
B BAHAN
Kayu kelas III (papan) m3 0.026 2,558,000.00 67,531.20
Paku 5 - 12 cm Kg 0.600 23,000.00 13,800.00
Dolken kayu ɸ(8-10)cm panjang 4 m Batang 0.500 12,000.00 6,000.00
JUMLAH HARGA BAHAN 87,331.20
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 111,296.20
E Overhead & Provit 15% x D 16,694.43
F Harga Satuan Pekerjaan ( D + E ) 127,990.63

A.4.1.1.35 Membuat 1m' kolom praktis beton bertulang (11 x 11) cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.180 105,000.00 18,900.00
Tukang batu L.02 OH 0.020 125,000.00 2,500.00
Tukang kayu L.02 OH 0.020 125,000.00 2,500.00
Tukang besi L.02 OH 0.020 125,000.00 2,500.00
Kepala tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.009 155,000.00 1,395.00
JUMLAH TENAGA KERJA 28,665.00
B BAHAN
Kayu kelas III m3 0.002 2,083,000.00 4,166.00
Paku 5 - 12 cm Kg 0.010 23,000.00 230.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Besi beton polos Kg 3.000 13,500.00 40,500.00
Kawat beton Kg 0.450 25,000.00 11,250.00
Semen portland Kg 4.000 1,500.00 6,000.00
Pasir beton m3 0.006 89.29 0.54
Kerikil m3 0.009 351.85 3.17
JUMLAH HARGA BAHAN 67,909.70
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 96,574.70
E Overhead & Provit 15% x D 14,486.21
F Harga Satuan Pekerjaan ( D + E ) 111,060.91
A.4.1.1.36 Membuat 1m' ring balok beton bertulang (10 x 15) cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.297 105,000.00 31,185.00
Tukang batu L.02 OH 0.033 125,000.00 4,125.00
Tukang kayu L.02 OH 0.033 125,000.00 4,125.00
Tukang besi L.02 OH 0.033 125,000.00 4,125.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,335.00
B BAHAN
Kayu kelas III m3 0.003 2,083,000.00 6,249.00
Paku 5 - 12 cm Kg 0.020 23,000.00 460.00
Minyak bekisting Liter 0.200 28,800.00 5,760.00
Besi beton polos Kg 3.600 13,500.00 48,600.00
Kawat beton Kg 0.050 25,000.00 1,250.00
Semen portland Kg 5.500 1,500.00 8,250.00
Pasir beton m3 0.009 89.29 0.80
Kerikil m3 0.015 351.85 5.28
JUMLAH HARGA BAHAN 70,575.08
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 117,910.08
E Overhead & Provit 15% x D 17,686.51
F Harga Satuan Pekerjaan ( D + E ) 135,596.59

B. 13.a.1 Membuat 1 m³ beton ready mix K 100 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang L.02 OH 0.250 125,000.00 31,250.00
Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
Beton Ready Mix K 100 m³ 1.020 1,072,500.00 1,093,950.00
JUMLAH HARGA BAHAN 1,093,950.00
C PERALATAN
Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,645,325.00
E Overhead & Profit (Contoh 15%) 15% x D 246,798.75
F Harga Satuan Pekerjaan (D+E) 1,892,123.75
B. 13.a.2 Membuat 1 m³ beton ready mix K 100 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix K 100 m³ 1.020 1,072,500.00 1,093,950.00
JUMLAH HARGA BAHAN 1,093,950.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,249,325.00


E Overhead & Profit (Contoh 15%) 15% x D 187,398.75
F Harga Satuan Pekerjaan (D+E) 1,436,723.75

B. 13.b.1 Membuat 1 m³ beton ready mix K 125 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 125 m³ 1.020 1,108,250.00 1,130,415.00
JUMLAH HARGA BAHAN 1,130,415.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,681,790.00
E Overhead & Profit (Contoh 15%) 15% x D 252,268.50
F Harga Satuan Pekerjaan (D+E) 1,934,058.50
B. 13.b.2 Membuat 1 m³ beton ready mix K 125 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix K 125 m³ 1.020 1,108,250.00 1,130,415.00
JUMLAH HARGA BAHAN 1,130,415.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,285,790.00


E Overhead & Profit (Contoh 15%) 15% x D 192,868.50
F Harga Satuan Pekerjaan (D+E) 1,478,658.50

B. 13.c.1 Membuat 1 m³ beton ready mix K 175 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 175 m³ 1.020 1,194,050.00 1,217,931.00
JUMLAH HARGA BAHAN 1,217,931.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,769,306.00
E Overhead & Profit (Contoh 15%) 15% x D 265,395.90
F Harga Satuan Pekerjaan (D+E) 2,034,701.90
B. 13.c.2 Membuat 1 m³ beton ready mix K 175 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 175 m³ 1.020 1,194,050.00 1,217,931.00
JUMLAH HARGA BAHAN 1,217,931.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,373,306.00


E Overhead & Profit (Contoh 15%) 15% x D 205,995.90
F Harga Satuan Pekerjaan (D+E) 1,579,301.90

B. 13.d.1 Membuat 1 m³ beton ready mix K 225 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 225 m³ 1.020 1,329,800.00 1,356,396.00
JUMLAH HARGA BAHAN 1,356,396.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,907,771.00
E Overhead & Profit (Contoh 15%) 15% x D 286,165.65
F Harga Satuan Pekerjaan (D+E) 2,193,936.65
B. 13.d.2 Membuat 1 m³ beton ready mix K 225 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 225 m³ 1.020 1,329,800.00 1,356,396.00
JUMLAH HARGA BAHAN 1,356,396.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,511,771.00


E Overhead & Profit (Contoh 15%) 15% x D 226,765.65
F Harga Satuan Pekerjaan (D+E) 1,738,536.65

B. 13.e.1 Membuat 1 m³ beton ready mix K 250 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 250 m³ 1.020 1,372,800.00 1,400,256.00
JUMLAH HARGA BAHAN 1,400,256.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 1,951,631.00
E Overhead & Profit (Contoh 15%) 15% x D 292,744.65
F Harga Satuan Pekerjaan (D+E) 2,244,375.65
B. 13.e.2 Membuat 1 m³ beton ready mix K 250 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 250 m³ 1.020 1,372,800.00 1,400,256.00
JUMLAH HARGA BAHAN 1,400,256.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,555,631.00


E Overhead & Profit (Contoh 15%) 15% x D 233,344.65
F Harga Satuan Pekerjaan (D+E) 1,788,975.65

B. 13.f.1 Membuat 1 m³ beton ready mix K 300 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 300 m³ 1.020 1,430,000.00 1,458,600.00
JUMLAH HARGA BAHAN 1,458,600.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,009,975.00
E Overhead & Profit (Contoh 15%) 15% x D 301,496.25
F Harga Satuan Pekerjaan (D+E) 2,311,471.25
B. 13.f.2 Membuat 1 m³ beton ready mix K 300 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 300 m³ 1.020 1,430,000.00 1,458,600.00
JUMLAH HARGA BAHAN 1,458,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,613,975.00


E Overhead & Profit (Contoh 15%) 15% x D 242,096.25
F Harga Satuan Pekerjaan (D+E) 1,856,071.25

B. 13.g.1 Membuat 1 m³ beton ready mix K 350 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 350 m³ 1.020 1,530,100.00 1,560,702.00
JUMLAH HARGA BAHAN 1,560,702.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,112,077.00
E Overhead & Profit (Contoh 15%) 15% x D 316,811.55
F Harga Satuan Pekerjaan (D+E) 2,428,888.55
B. 13.g.2 Membuat 1 m³ beton ready mix K 350 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 350 m³ 1.020 1,530,100.00 1,560,702.00
JUMLAH HARGA BAHAN 1,560,702.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,716,077.00


E Overhead & Profit (Contoh 15%) 15% x D 257,411.55
F Harga Satuan Pekerjaan (D+E) 1,973,488.55

B. 13.h.1 Membuat 1 m³ beton ready mix K 400 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 400 m³ 1.020 1,601,600.00 1,633,632.00
JUMLAH HARGA BAHAN 1,633,632.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,185,007.00
E Overhead & Profit (Contoh 15%) 15% x D 327,751.05
F Harga Satuan Pekerjaan (D+E) 2,512,758.05
B. 13.h.2 Membuat 1 m³ beton ready mix K 400 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 400 m³ 1.020 1,601,600.00 1,633,632.00
JUMLAH HARGA BAHAN 1,633,632.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,789,007.00


E Overhead & Profit (Contoh 15%) 15% x D 268,351.05
F Harga Satuan Pekerjaan (D+E) 2,057,358.05

B. 13.i.1 Membuat 1 m³ beton ready mix K 450 menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 450 m³ 1.020 1,673,100.00 1,706,562.00
JUMLAH HARGA BAHAN 1,706,562.00
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120 3,300,000.00 396,000.00
JUMLAH HARGA ALAT 396,000.00
D Jumlah (A+B+C) 2,257,937.00
E Overhead & Profit (Contoh 15%) 15% x D 338,690.55
F Harga Satuan Pekerjaan (D+E) 2,596,627.55
B. 13.i.2 Membuat 1 m³ beton ready mix K 400 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 1.000 105,000.00 105,000.00
2 Tukang L.02 OH 0.250 125,000.00 31,250.00
3 Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
4 Mandor L.04 OH 0.100 155,000.00 15,500.00
JUMLAH TENAGA KERJA 155,375.00
B BAHAN
1 Beton Ready Mix 450 m³ 1.020 1,673,100.00 1,706,562.00
JUMLAH HARGA BAHAN 1,706,562.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,861,937.00


E Overhead & Profit (Contoh 15%) 15% x D 279,290.55
F Harga Satuan Pekerjaan (D+E) 2,141,227.55
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
Untuk produksi pracetak bisa dilakukan dipabrik (cor di plant) atau di lapangan (cast in place). Indeks yang ada dalam pedoman ini hanya untuk
pekerjaan produksi yang dilakukan di lapangan, terutama untuk analisa cetakan (bekisting) pracetak baik untuk komponen kolom, balok
dan pelat.

A.4.1.2 Harga Satuan Pekerjaan Beton Pracetak


A.4.1.2.5 Pembuatan 1 m2 Bekisting untuk Pelat Beton Pracetak Komponen Modular Bangunan Gedung ( 5 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.007 105,000.00 735.00
Tukang kayu L.02 OH 0.076 125,000.00 9,500.00
Kepala tukang L.03 OH 0.008 145,000.00 1,160.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 11,550.00
B BAHAN
Lantai kerja t=10cm m3 0.008 -
Besi hollow (50 x 50x 3) mm Kg 9.394 -
Kayu kaso 5/7 (lebar 5 cm, tinggi 7 cm) m3 0.005 -
Phenol film 12mm Lbr 0.080 -
Minyak cetakan (bekisting) Liter 0.200 28,800.00 5,760.00
Dinabolt Ø 12mm (10 s.d.15cm) buah 2.000 -
JUMLAH HARGA BAHAN 5,760.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 17,310.00
E Overhead & Provit 15% x D 2,596.50
F Harga Satuan Pekerjaan ( D + E ) 19,906.50

A.4.1.2.6 Pembuatan 1 m2 Bekisting untuk Balok Beton Pracetak (10-12 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.004 105,000.00 420.00
Tukang kayu L.02 OH 0.038 125,000.00 4,750.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 5,905.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm, tinggi 7 cm) m3 0.005 4,755,000.00 23,775.00
Phenol film 12mm Lbr 0.043 -
Minyak cetakan (bekisting) Liter 0.200 28,800.00 5,760.00
Paku (5 s.d.7) cm Kg 0.046 23,000.00 1,058.00
Dinabolt Ø12mm (10 s.d.15cm) buah 0.693 -
JUMLAH HARGA BAHAN 30,593.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 36,498.00
E Overhead & Provit 15% x D 5,474.70
F Harga Satuan Pekerjaan ( D + E ) 41,972.70

A.4.1.2.7 Pembuatan 1 m2 Bekisting untuk Kolom Beton Pracetak (10-12 kali pakai)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.004 105,000.00 420.00
Tukang kayu L.02 OH 0.038 125,000.00 4,750.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 5,905.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm, tinggi 7 cm) m3 0.004 4,755,000.00 19,020.00
Phenol film 12mm Lbr 0.048 -
Minyak cetakan (bekisting) Liter 0.200 28,800.00 5,760.00
Paku (5 s.d.7) cm Kg 0.046 23,000.00 1,058.00
Dinabolt Ø12mm (10 s.d.15cm) buah 0.693 -
JUMLAH HARGA BAHAN 25,838.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 31,743.00
E Overhead & Provit 15% x D 4,761.45
F Harga Satuan Pekerjaan ( D + E ) 36,504.45

A.4.1.2.8 Pemasangan dan Membuka Cetakan 1 Buah Komponen Pelat Beton Pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.053 105,000.00 5,565.00
Tukang kayu L.02 OH 0.018 125,000.00 2,250.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 8,590.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 8,590.00
E Overhead & Provit 15% x D 1,288.50
F Harga Satuan Pekerjaan ( D + E ) 9,878.50

A.4.1.2.9 Pemasangan dan Membuka Cetakan 1 Buah Komponen Balok Beton Pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.089 105,000.00 9,345.00
Tukang kayu L.02 OH 0.030 125,000.00 3,750.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 13,870.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 13,870.00
E Overhead & Provit 15% x D 2,080.50
F Harga Satuan Pekerjaan ( D + E ) 15,950.50

A.4.1.2.10 Pemasangan dan Membuka Cetakan 1 Buah Komponen Kolom Beton Pracetak
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.071 105,000.00 7,455.00
Tukang kayu L.02 OH 0.024 125,000.00 3,000.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 11,230.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 11,230.00
E Overhead & Provit 15% x D 1,684.50
F Harga Satuan Pekerjaan ( D + E ) 12,914.50

A.4.1.2.11 Penuangan/Menebar Beton 1 m3 untuk Pelat Beton Pracetak


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.064 105,000.00 6,720.00
Tukang batu L.02 OH 0.244 125,000.00 30,500.00
Tukang vibrator L.02 OH 0.128 125,000.00 16,000.00
Kepala tukang L.03 OH 0.034 145,000.00 4,930.00
Mandor L.04 OH 0.073 155,000.00 11,315.00
JUMLAH TENAGA KERJA 69,465.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 69,465.00
E Overhead & Provit 15% x D 10,419.75
F Harga Satuan Pekerjaan ( D + E ) 79,884.75

A.4.1.2.12 Penuangan/Menebar Beton 1 m3 untuk Balok Beton Pracetak


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.069 105,000.00 7,245.00
Tukang batu L.02 OH 0.242 125,000.00 30,250.00
Tukang vibrator L.02 OH 0.138 125,000.00 17,250.00
Kepala tukang L.03 OH 0.037 145,000.00 5,365.00
Mandor L.04 OH 0.073 155,000.00 11,315.00
JUMLAH TENAGA KERJA 71,425.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 71,425.00
E Overhead & Provit 15% x D 10,713.75
F Harga Satuan Pekerjaan ( D + E ) 82,138.75

A.4.1.2.13 Penuangan/Menebar Beton 1 m3 untuk Kolom Beton Pracetak


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.610 105,000.00 64,050.00
Tukang batu L.02 OH 0.213 125,000.00 26,625.00
Tukang vibrator L.02 OH 0.122 125,000.00 15,250.00
Kepala tukang L.03 OH 0.033 145,000.00 4,785.00
Mandor L.04 OH 0.073 155,000.00 11,315.00
JUMLAH TENAGA KERJA 122,025.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 122,025.00
E Overhead & Provit 15% x D 18,303.75
F Harga Satuan Pekerjaan ( D + E ) 140,328.75

A.4.1.2.14. Pemasangan 1 buah Komponen untuk Pelat Beton Pracetak Beserta Indeks Kenaikan Lantai Ereksi Pelat Hingga
24 Lantai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Operator crane L.08 OH 0.067 170,000.00 11,390.00
Pembantu operator crane L.09 OH 0.067 100,000.00 6,700.00
Pekerja L.01 OH 0.067 105,000.00 7,035.00
Tukang batu L.02 OH 0.067 125,000.00 8,375.00
Tukang vibrator L.02 OH 0.134 125,000.00 16,750.00
Kepala tukang L.03 OH 0.067 145,000.00 9,715.00
Mandor L.04 OH 0.067 155,000.00 10,385.00
JUMLAH TENAGA KERJA 52,260.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.067
Sewa pipe support buah hari 1.100

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 52,260.00
E Overhead & Provit 15% x D 7,839.00
F Harga Satuan Pekerjaan ( D + E ) 60,099.00

Catatan: spesifikasi crane disesuaikan dengan kebutuhan


Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Pelat Pracetak
Lantai Indeks kenaikan lantai Lantai Indeks kenaikan lantai
ereksi pelat ereksi pelat
1 1,000 13 1,114
2 1,000 14 1,134
3 1,000 15 1,155
4 1,000 16 1,176
5 1,000 17 1,197
6 1,000 18 1,219
7 1,000 19 1,241
8 1,018 20 1,264
9 1,037 21 1,287
10 1,055 22 1,310
11 1,075 23 1,334
12 1,094 24 1,358

Pemasangan 1 buah Komponen untuk Pelat Beton Pracetak Beserta Indeks Kenaikan Lantai Ereksi Pelat Hingga
A.4.1.2.15
24 Lantai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Operator crane L.08 OH 0.061 3,250.00 198.25
Pembantu operator crane L.09 OH 0.061 2,000.00 122.00
Pekerja L.01 OH 0.061 105,000.00 6,405.00
Tukang batu L.02 OH 0.061 125,000.00 7,625.00
Tukang vibrator L.02 OH 0.122 125,000.00 15,250.00
Kepala tukang L.03 OH 0.061 145,000.00 8,845.00
Mandor L.04 OH 0.061 155,000.00 9,455.00
JUMLAH TENAGA KERJA 47,580.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane unit hari 0.061
Sewa pipe support buah hari 1.100

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 47,580.00
E Overhead & Provit 15% x D 7,137.00
F Harga Satuan Pekerjaan ( D + E ) 54,717.00

Indeks Pengali Menurut Tingkat Lantai Pemasangan Komponen untuk Balok Pracetak
Lantai Indeks kenaikan lantai Lantai Indeks kenaikan lantai
ereksi balok ereksi balok
1 1,000 13 1,068
2 1,000 14 1,080
3 1,000 15 1,092
4 1,000 16 1,104
5 1,000 17 1,116
6 1,000 18 1,129
7 1,000 19 1,141
8 1,011 20 1,154
9 1,022 21 1,166
10 1,034 22 1,179
11 1,045 23 1,192
12 1,057 24 1,206

A.4.1.2.17 Pemindahan 1 buah Komponen untuk Pelat Pracetak ( ± 20 m)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.019 105,000.00 1,995.00
Tukang batu L.02 OH 0.038 125,000.00 4,750.00
JUMLAH TENAGA KERJA 6,745.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane Unit hari 0.019
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 6,745.00
E Overhead & Provit 15% x D 1,011.75
F Harga Satuan Pekerjaan ( D + E ) 7,756.75

A.4.1.2.18 Pemindahan 1 buah Komponen untuk Balok Pracetak ( ± 20 m)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.019 105,000.00 1,995.00
Tukang batu L.02 OH 0.038 125,000.00 4,750.00
JUMLAH TENAGA KERJA 6,745.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane Unit hari 0.019
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 6,745.00
E Overhead & Provit 15% x D 1,011.75
F Harga Satuan Pekerjaan ( D + E ) 7,756.75

A.4.1.2.19 Pemindahan 1 buah Komponen untuk Kolom Pracetak ( ± 20 m)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.019 105,000.00 1,995.00
Tukang batu L.02 OH 0.038 125,000.00 4,750.00
JUMLAH TENAGA KERJA 6,745.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Sewa crane Unit hari 0.019
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 6,745.00
E Overhead & Provit 15% x D 1,011.75
F Harga Satuan Pekerjaan ( D + E ) 7,756.75

A.4.1.2.22 Upah 1 titik Pekerjaan Grout pada Joint Beton Pracetak


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Tukang batu L.02 OH 0.367 125,000.00 45,875.00
Kepala tukang L.03 OH 0.074 145,000.00 10,730.00
Mandor L.04 OH 0.037 155,000.00 5,735.00
JUMLAH TENAGA KERJA 62,340.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 62,340.00
E Overhead & Provit 15% x D 9,351.00
F Harga Satuan Pekerjaan ( D + E ) 71,691.00

A.4.1.2.23 Pemasangan 1 titik Bekisting Joint Pracetak

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.147 105,000.00 15,435.00
Tukang L.02 OH 0.147 125,000.00 18,375.00
Kepala Tukang L.03 OH 0.015 125,000.00 1,875.00
Mandor L.04 OH 0.005 125,000.00 625.00
JUMLAH TENAGA KERJA 36,310.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm, tinggi 7 cm) m3 0.012 4,755,000.00 57,060.00
Papan cor m3 0.004 2558000 10,232.00
Paku (5 s.d.7) cm Kg 0.264 23000 6,072.00
JUMLAH HARGA BAHAN 73,364.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 109,674.00
E Overhead & Profit (Contoh 15%) 15% x D 16,451.10
F Harga Satuan Pekerjaan (D+E) 126,125.10

A.4.1.2.24 Pemasangan 1 titik Bekisting Joint Pracetak

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.220 105,000.00 23,100.00
Tukang L.02 OH 0.022 125,000.00 2,750.00
Kepala Tukang L.03 OH 0.220 125,000.00 27,500.00
Mandor L.04 OH 0.011 125,000.00 1,375.00
JUMLAH TENAGA KERJA 54,725.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 54,725.00
E Overhead & Profit (Contoh 15%) 15% x D 8,208.75
F Harga Satuan Pekerjaan (D+E) 62,933.75
A.4.2.1 Harga Satuan Pekerjaan Besi dan Alumunium

A.4.2.1.1 Pemasangan 1 kg besi profil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 105,000.00 6,300.00
Tukang las konstruksi L.03 OH 0.060 125,000.00 7,500.00
Kepala tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 15,135.00
B BAHAN
Besi profil Kg 1.150 17,000.00 19,550.00
Kawat Las
JUMLAH HARGA BAHAN 19,550.00
C PERALATAN
Alat Las
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 34,685.00
E Overhead & Provit 15% x D 5,202.75
F Harga Satuan Pekerjaan ( D + E ) 39,887.75

A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 105,000.00 6,300.00
Tukang las konstruksi L.03 OH 0.060 125,000.00 7,500.00
Kepala tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 15,135.00
B BAHAN
Besi baja IWF Kg 1.150 17,000.00 19,550.00
JUMLAH HARGA BAHAN 19,550.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 34,685.00
E Overhead & Provit 15% x D 5,202.75
F Harga Satuan Pekerjaan ( D + E ) 39,887.75

A.4.2.1.3 Pengerjaan 100 Kg pekerjaan perakitan


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang besi konstruksi L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.001 145,000.00 145.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 23,920.00
B BAHAN
Solar Liter 1.000 8,100.00 8,100.00
Minyak pelumas Liter 0.100 28,800.00 2,880.00
JUMLAH HARGA BAHAN 10,980.00
C PERALATAN
1. Sewa alat Jam 0.800 70,000.00 56,000.00
JUMLAH HARGA ALAT 56,000.00
D Jumlah (A + B + C) 90,900.00
E Overhead & Provit 15% x D 13,635.00
F Harga Satuan Pekerjaan ( D + E ) 104,535.00

A.4.2.1.4 Pembuatan 1m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 105,000.00 4,200.00
Tukang besi konstruksi L.03 OH 0.020 125,000.00 2,500.00
Kepala tukang L.03 OH 0.002 145,000.00 290.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 7,300.00
B BAHAN
Besi siku L 30.30.3 Kg 15.000 -
Besi pelat baja Kg 38.800 -
Kawat las Kg 0.050 28,500.00 1,425.00
JUMLAH HARGA BAHAN 1,425.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 8,725.00
E Overhead & Provit 15% x D 1,308.75
F Harga Satuan Pekerjaan ( D + E ) 10,033.75

A.4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 105,000.00 4,200.00
Tukang besi konstruksi L.03 OH 0.020 125,000.00 2,500.00
Kepala tukang L.03 OH 0.002 145,000.00 290.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 7,300.00
B BAHAN
Kawat las listrik Kg 0.400 28,500.00 11,400.00
Solar Liter 0.300 8,100.00 2,430.00
Minyak pelumas Liter 0.040 28,800.00 1,152.00
JUMLAH HARGA BAHAN 14,982.00
C PERALATAN
Sewa alat Jam 0.170 70,000.00 11,900.00
JUMLAH HARGA ALAT 11,900.00
D Jumlah (A + B + C) 34,182.00
E Overhead & Provit 15% x D 5,127.30
F Harga Satuan Pekerjaan ( D + E ) 39,309.30

A.4.2.1.5.a Pengerjaan 10 cm pengelasan dengan las listrik (bangunan)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 105,000.00 4,200.00
Tukang besi konstruksi L.03 OH 0.020 125,000.00 2,500.00
Kepala tukang L.03 OH 0.002 145,000.00 290.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 7,300.00
B BAHAN
Kawat las listrik Kg 0.040 28,500.00 1,140.00
JUMLAH HARGA BAHAN 1,140.00
C PERALATAN
Sewa alat Jam 0.170 70,000.00 11,900.00
JUMLAH HARGA ALAT 11,900.00
D Jumlah (A + B + C) 20,340.00
E Overhead & Provit 15% x D 3,051.00
F Harga Satuan Pekerjaan ( D + E ) 23,391.00

A.4.2.1.6 Pembuatan 1m2 rangka jendela besi scuare tube


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.650 105,000.00 68,250.00
Tukang besi konstruksi L.03 OH 0.650 125,000.00 81,250.00
Kepala tukang L.03 OH 0.065 145,000.00 9,425.00
Mandor L.04 OH 0.032 155,000.00 4,960.00
JUMLAH TENAGA KERJA 163,885.00
B BAHAN
Besi scuare tube m 4.76
besi lis kaca (1x1) cm m 4.522
Pengelasan cm 20.000
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 163,885.00
E Overhead & Provit 15% x D 24,582.75
F Harga Satuan Pekerjaan ( D + E ) 188,467.75

A.4.2.1.7 Pemasangan 1 m2 Pintu Rolling Door Besi


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.650 105,000.00 68,250.00
Tukang besi konstruksi L.03 OH 0.650 125,000.00 81,250.00
Kepala tukang L.03 OH 0.065 145,000.00 9,425.00
Mandor L.04 OH 0.032 155,000.00 4,960.00
JUMLAH TENAGA KERJA 163,885.00
B BAHAN
Pintru gulung besi m2 1 715,000.00 715,000.00
JUMLAH HARGA BAHAN 715,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 878,885.00
E Overhead & Provit 15% x D 131,832.75
F Harga Satuan Pekerjaan ( D + E ) 1,010,717.75

A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.440 105,000.00 46,200.00
Tukang besi konstruksi L.03 OH 0.440 125,000.00 55,000.00
Kepala tukang L.03 OH 0.044 145,000.00 6,380.00
Mandor L.04 OH 0.022 155,000.00 3,410.00
JUMLAH TENAGA KERJA 110,990.00
B BAHAN
Pintru gulung besi m2 1.000 715,000.00 715,000.00
JUMLAH HARGA BAHAN 715,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 825,990.00
E Overhead & Provit 15% x D 123,898.50
F Harga Satuan Pekerjaan ( D + E ) 949,888.50

A.4.2.1.9 Pemasangan 1 m2 Rolling door Aluminium


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang besi konstruksi L.03 OH 1.000 125,000.00 125,000.00
Kepala tukang L.03 OH 0.100 145,000.00 14,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 252,250.00
B BAHAN
Rolling door aluminium m2 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 252,250.00
E Overhead & Provit 15% x D 37,837.50
F Harga Satuan Pekerjaan ( D + E ) 290,087.50

A.4.2.1.10 Pemasangan 1 m2 Rolling door Aluminium


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang besi konstruksi L.03 OH 0.800 125,000.00 100,000.00
Kepala tukang L.03 OH 0.080 145,000.00 11,600.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 120,620.00
B BAHAN
Sunscreen aluminium m2 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 120,620.00
E Overhead & Provit 15% x D 18,093.00
F Harga Satuan Pekerjaan ( D + E ) 138,713.00

A.4.2.1.11 Pemasangan 1 m kusen pintu allumunium


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang besi konstruksi L.03 OH 0.800 125,000.00 100,000.00
Kepala tukang L.03 OH 0.080 145,000.00 11,600.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 120,620.00
B BAHAN
Profil alumunium m 1.100 75,000.00 82,500.00
skrup fixer buah 2.000 2,500.00 5,000.00
Sealant Tube 0.060 35,000.00 2,100.00
JUMLAH HARGA BAHAN 89,600.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 210,220.00
E Overhead & Provit 15% x D 31,533.00
F Harga Satuan Pekerjaan ( D + E ) 241,753.00

A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka allumunium


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.085 105,000.00 8,925.00
Tukang besi konstruksi L.03 OH 0.085 125,000.00 10,625.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 21,630.00
B BAHAN
Pintu alumunium m 1.100 75,000.00 82,500.00
Profil kaca m 2.000 75,000.00 150,000.00
Sealant Tube 0.060 35,000.00 2,100.00
JUMLAH HARGA BAHAN 234,600.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 256,230.00
E Overhead & Provit 15% x D 38,434.50
F Harga Satuan Pekerjaan ( D + E ) 294,664.50

A.4.2.1.14 Pemasangan 1 m3 venetions blinds dan vertical blinds


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang besi konstruksi L.03 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 88,365.00
B BAHAN
Venetions blinds dan vertical blinds
m2 1.100
(tirai) -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 88,365.00
E Overhead & Provit 15% x D 13,254.75
F Harga Satuan Pekerjaan ( D + E ) 101,619.75

A.4.2.1.15 Pemasangan 1 m2 terali besi strip (2x3) mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.670 105,000.00 175,350.00
Tukang besi konstruksi L.03 OH 1.670 125,000.00 208,750.00
Kepala tukang L.03 OH 0.167 145,000.00 24,215.00
Mandor L.04 OH 0.083 155,000.00 12,865.00
JUMLAH TENAGA KERJA 421,180.00
B BAHAN
Besi strip Kg 6.177
Pengelasan Cm 27.080
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 421,180.00
E Overhead & Provit 15% x D 63,177.00
F Harga Satuan Pekerjaan ( D + E ) 484,357.00

A.4.2.1.16 Pemasangan 1 m2 kawat nyamuk


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang besi konstruksi L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.01 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Kawat Nyamuk m2 1.100
Pengelasan cm 11.110
Baja strip (0,2x2)cm Kg 1.716
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 25,225.00
E Overhead & Provit 15% x D 3,783.75
F Harga Satuan Pekerjaan ( D + E ) 29,008.75

A.4.2.1.17 Pemasangan 1 m2 Jendela Nako dan Tralis


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang besi konstruksi L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.02 145,000.00 2,900.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 49,055.00
B BAHAN

Jendela nako (rangka + kaca 5 mm) m2 1.100


-
Paku skrup 1cm - 2,5 cm Buah 10.000 -
Baja strip Kg 7.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 49,055.00
E Overhead & Provit 15% x D 7,358.25
F Harga Satuan Pekerjaan ( D + E ) 56,413.25

A.4.2.1.18 Pemasangan 1 m' talang datar/jurai seng bjls 28 lebar 90 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 49,055.00
B BAHAN
Seng pelat m 1.050 42,500.00 44,625.00
Paku 1cm - 2,5 cm Kg 0.015 23,000.00 345.00
Papan kayu kelas II atau III m3 0.019 7,060,000.00 134,140.00
JUMLAH HARGA BAHAN 179,110.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 228,165.00
E Overhead & Provit 15% x D 34,224.75
F Harga Satuan Pekerjaan ( D + E ) 262,389.75

A.4.2.1.19 Pemasangan 1 m' talang 1/2 lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang L.03 OH 0.300 125,000.00 37,500.00
Kepala tukang L.03 OH 0.030 145,000.00 4,350.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 58,840.00
B BAHAN
Seng pelat m 1.050 42,500.00 44,625.00
Paku 1cm - 2,5 cm Kg 0.010 23,000.00 230.00
Besi strip m3 0.500 -
JUMLAH HARGA BAHAN 44,855.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 103,695.00
E Overhead & Provit 15% x D 15,554.25
F Harga Satuan Pekerjaan ( D + E ) 119,249.25

A.4.2.1.20 Pemasangan 1 m2 Rangka Besi Hollow Galvanis 40.40 mm, Modul 60 x 120 cm, untuk Partisi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang L.03 OH 0.250 125,000.00 31,250.00
Kepala tukang L.03 OH 0.025 145,000.00 3,625.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 63,140.00
B BAHAN
Rangka metal hollow 40.40 m 35.000 -
Assesoris (perkuatan, las dll) Ls 100%xrangka 28,500.00 28,500.00
JUMLAH HARGA BAHAN 28,500.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 91,640.00
E Overhead & Provit 15% x D 13,746.00
F Harga Satuan Pekerjaan ( D + E ) 105,386.00

A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, untuk plafon
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang L.03 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 88,365.00
B BAHAN
Rangka metal hollow 40.40 m 4.000 -
Assesoris (perkuatan, las dll) Ls 100%xrangka 28,500.00 28,500.00
JUMLAH HARGA BAHAN 28,500.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 116,865.00
E Overhead & Provit 15% x D 17,529.75
F Harga Satuan Pekerjaan ( D + E ) 134,394.75

A.4.2.1.22 Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.734 105,000.00 77,070.00
Tukang L.03 OH 0.734 125,000.00 91,750.00
Kepala tukang L.03 OH 0.073 145,000.00 10,585.00
Mandor L.04 OH 0.037 155,000.00 5,735.00
JUMLAH TENAGA KERJA 185,140.00
B BAHAN
Baja ringan canai dingin C75 Btg 0.873 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan % 10
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 185,140.00
E Overhead & Provit 15% x D 27,771.00
F Harga Satuan Pekerjaan ( D + E ) 212,911.00

A.4.2.1.23 Pemasangan 1 M2 Atap Jurai/Limasan Rangka Atap Baja Ringan (Canai Dingin) Profil C75
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.760 105,000.00 79,842.00
Tukang L.03 OH 0.760 125,000.00 95,050.00
Kepala tukang L.03 OH 0.076 145,000.00 11,020.00
Mandor L.04 OH 0.038 155,000.00 5,890.00
JUMLAH TENAGA KERJA 191,802.00
B BAHAN
Baja ringan canai dingin C75 Btg 0.873 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan % 10
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 191,802.00
E Overhead & Provit 15% x D 28,770.30
F Harga Satuan Pekerjaan ( D + E ) 220,572.30

A.4.2.1.24 Pemasangan 1 m2 Pintu Aluminium Strip Lebar 8 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.760 105,000.00 79,842.00
Tukang L.03 OH 0.760 125,000.00 95,050.00
Kepala tukang L.03 OH 0.076 145,000.00 11,020.00
Mandor L.04 OH 0.038 155,000.00 5,890.00
JUMLAH TENAGA KERJA 191,802.00
B BAHAN
Profil aluminium m 4.400 -
Aluminium strip m 14.600 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 191,802.00
E Overhead & Provit 15% x D 28,770.30
F Harga Satuan Pekerjaan ( D + E ) 220,572.30

A.4.2.1.25 Pemasangan 1 m2 Venetions Blinds dan Vertical Blinds


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang L.03 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 88,365.00
B BAHAN
Venetions blinds dan m2 1.000
vertical blinds (tirai) -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 88,365.00
E Overhead & Provit 15% x D 13,254.75
F Harga Satuan Pekerjaan ( D + E ) 101,619.75
A.4.4.1 Harga Satuan Pekerjaan Pasangan Dinding

A.4.4.1.1 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 26.550 1,500.00 39,825.00
Pasir pasang m3 0.093 125,000.00 11,625.00
JUMLAH HARGA BAHAN 331,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 427,000.00
E Overhead & Provit 15% x D 64,050.00
F Harga Satuan Pekerjaan ( D + E ) 491,050.00

A.4.4.1.2 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 26.550 1,500.00 39,825.00
Pasir pasang m3 0.093 125,000.00 11,625.00
JUMLAH HARGA BAHAN 331,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 427,000.00
E Overhead & Provit 15% x D 64,050.00
F Harga Satuan Pekerjaan ( D + E ) 491,050.00

A.4.4.1.3 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 26.550 1,500.00 39,825.00
Pasir pasang m3 0.093 125,000.00 11,625.00
JUMLAH HARGA BAHAN 331,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 427,000.00
E Overhead & Provit 15% x D 64,050.00
F Harga Satuan Pekerjaan ( D + E ) 491,050.00

A.4.4.1.4 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 26.550 1,500.00 39,825.00
Pasir pasang m3 0.093 125,000.00 11,625.00
JUMLAH HARGA BAHAN 331,450.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 427,000.00
E Overhead & Provit 15% x D 64,050.00
F Harga Satuan Pekerjaan ( D + E ) 491,050.00

A.4.4.1.6 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang batu L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Bata merah Buah 140.000 2,000.00 280,000.00
Semen portland Kg 18.500 1,500.00 27,750.00
Pasir pasang m3 0.122 125,000.00 15,250.00
JUMLAH HARGA BAHAN 323,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 418,550.00
E Overhead & Provit 15% x D 62,782.50
F Harga Satuan Pekerjaan ( D + E ) 481,332.50

A.4.4.1.7 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 18.950 1,500.00 28,425.00
Pasir pasang m3 0.038 125,000.00 4,750.00
JUMLAH HARGA BAHAN 173,175.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 220,950.00
E Overhead & Provit 15% x D 33,142.50
F Harga Satuan Pekerjaan ( D + E ) 254,092.50

A.4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 14.370 1,500.00 21,555.00
Pasir pasang m3 0.040 125,000.00 5,000.00
JUMLAH HARGA BAHAN 166,555.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 214,330.00
E Overhead & Provit 15% x D 32,149.50
F Harga Satuan Pekerjaan ( D + E ) 246,479.50

A.4.4.1.9 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 11.500 1,500.00 17,250.00
Pasir pasang m3 0.043 125,000.00 5,375.00
JUMLAH HARGA BAHAN 162,625.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 210,400.00
E Overhead & Provit 15% x D 31,560.00
F Harga Satuan Pekerjaan ( D + E ) 241,960.00

A.4.4.1.10 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 9.680 1,500.00 14,520.00
Pasir pasang m3 0.045 125,000.00 5,625.00
JUMLAH HARGA BAHAN 160,145.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 207,920.00
E Overhead & Provit 15% x D 31,188.00
F Harga Satuan Pekerjaan ( D + E ) 239,108.00
A.4.4.1.11 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 6PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 8.320 1,500.00 12,480.00
Pasir pasang m3 0.049 125,000.00 6,125.00
JUMLAH HARGA BAHAN 158,605.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 206,380.00
E Overhead & Provit 15% x D 30,957.00
F Harga Satuan Pekerjaan ( D + E ) 237,337.00

A.4.4.1.12 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 8PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 6.500 1,500.00 9,750.00
Pasir pasang m3 0.050 125,000.00 6,250.00
JUMLAH HARGA BAHAN 156,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 203,775.00
E Overhead & Provit 15% x D 30,566.25
F Harga Satuan Pekerjaan ( D + E ) 234,341.25

A.4.4.1.13 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3 KP : 10PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 4.500 1,500.00 6,750.00
Kapur Padam m3 0.015 -
Pasir pasang m3 0.050 125,000.00 6,250.00
JUMLAH HARGA BAHAN 153,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 200,775.00
E Overhead & Provit 15% x D 30,116.25
F Harga Satuan Pekerjaan ( D + E ) 230,891.25

A.4.4.1.14 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 1PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 0.018 1,500.00 27.00
Kapur Padam m3 0.018 -
Pasir pasang m3 0.018 125,000.00 2,250.00
JUMLAH HARGA BAHAN 142,277.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 190,052.00
E Overhead & Provit 15% x D 28,507.80
F Harga Satuan Pekerjaan ( D + E ) 218,559.80

A.4.4.1.15 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata merah Buah 70.000 2,000.00 140,000.00
Semen portland Kg 0.014 1,500.00 21.00
Kapur Padam m3 0.014 -
Pasir pasang m3 0.028 125,000.00 3,500.00
JUMLAH HARGA BAHAN 143,521.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 191,296.00
E Overhead & Provit 15% x D 28,694.40
F Harga Satuan Pekerjaan ( D + E ) 219,990.40

A.4.4.1.16 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 3 PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
HB-20 Buah 12.500 2,500.00 31,250.00
Semen portland Kg 30.320 1,500.00 45,480.00
Pasir pasang m3 0.728 125,000.00 91,000.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 167,730.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 215,505.00
E Overhead & Provit 15% x D 32,325.75
F Harga Satuan Pekerjaan ( D + E ) 247,830.75

A.4.4.1.17 Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 4 PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
HB-20 Buah 12.500 2,500.00 31,250.00
Semen portland Kg 24.260 1,500.00 36,390.00
Pasir pasang m3 0.772 125,000.00 96,500.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 164,140.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 211,915.00
E Overhead & Provit 15% x D 31,787.25
F Harga Satuan Pekerjaan ( D + E ) 243,702.25

A.4.4.1.17.a Pemasangan 1 m² dinding batako uk. 20/40/9


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang batu L.02 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 60,465.00
B BAHAN
Batako 20/40/9 (cetak mesin) Bh 12.500 2,500.00 31,250.00
Semen Portland Kg 7.500 1,500.00 11,250.00
Pasir pasang m³ 0.027 125,000.00 3,375.00
JUMLAH HARGA BAHAN 45,875.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 106,340.00
E Overhead & Provit 15% x D 15,951.00
F Harga Satuan Pekerjaan ( D + E ) 122,291.00

A.4.4.1.17.b Pemasangan 1 m² dinding batako uk. 20/40/7


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang batu L.02 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 60,465.00
B BAHAN
Batako 20/40/7 (cetak mesin) Bh 12.500 2,300.00 28,750.00
Semen Portland Kg 7.500 1,500.00 11,250.00
Pasir pasang m³ 0.027 125,000.00 3,375.00
JUMLAH HARGA BAHAN 43,375.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 103,840.00
E Overhead & Provit 15% x D 15,576.00
F Harga Satuan Pekerjaan ( D + E ) 119,416.00

A.4.4.1.18 Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 3PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.320 105,000.00 33,600.00
Tukang batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.016 155,000.00 2,480.00
JUMLAH TENAGA KERJA 52,820.00
B BAHAN
HB-15 Buah 12.500 1,800.00 22,500.00
Semen portland Kg 24.260 1,500.00 36,390.00
Pasir pasang m3 0.772 125,000.00 96,500.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 155,390.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 208,210.00
E Overhead & Provit 15% x D 31,231.50
F Harga Satuan Pekerjaan ( D + E ) 239,441.50

A.4.4.1.19 Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.320 105,000.00 33,600.00
Tukang batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.016 155,000.00 2,480.00
JUMLAH TENAGA KERJA 52,820.00
B BAHAN
HB-15 Buah 12.500 1,800.00 22,500.00
Semen portland Kg 18.200 1,500.00 27,300.00
Pasir pasang m3 0.582 125,000.00 72,750.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 122,550.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 175,370.00
E Overhead & Provit 15% x D 26,305.50
F Harga Satuan Pekerjaan ( D + E ) 201,675.50

A.4.4.1.19.a Pemasangan 1 m² dinding batako 15/30/7


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.320 105,000.00 33,600.00
Tukang batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.016 155,000.00 2,480.00
JUMLAH TENAGA KERJA 52,820.00
B BAHAN
HB-15 m3 22.200 1,800.00 39,960.00
Semen portland Kg 18.200 1,500.00 27,300.00
Pasir pasang m3 0.582 125,000.00 72,750.00
JUMLAH HARGA BAHAN 140,010.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 192,830.00
E Overhead & Provit 15% x D 28,924.50
F Harga Satuan Pekerjaan ( D + E ) 221,754.50

A.4.4.1.20 Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 3PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
HB-10 Buah 12.500 1,800.00 22,500.00
Semen portland Kg 15.160 1,500.00 22,740.00
Pasir pasang m3 0.364 125,000.00 45,500.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 90,740.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 138,515.00
E Overhead & Provit 15% x D 20,777.25
F Harga Satuan Pekerjaan ( D + E ) 159,292.25

A.4.4.1.21 Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
HB-10 Buah 12.500 1,800.00 22,500.00
Semen portland Kg 15.160 1,500.00 22,740.00
Pasir pasang m3 0.364 125,000.00 45,500.00
Besi angker diameter 8 Kg 0.280 -
JUMLAH HARGA BAHAN 90,740.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 138,515.00
E Overhead & Provit 15% x D 20,777.25
F Harga Satuan Pekerjaan ( D + E ) 159,292.25

A.4.4.1.22 Pemasangan 1 m² dinding terawang (rooster) 18x18 campuran 1SP:3PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata rooster bauh 30.000 -
Semen portland Kg 11.000 1,500.00 16,500.00
Pasir pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 20,875.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 68,650.00
E Overhead & Provit 15% x D 10,297.50
F Harga Satuan Pekerjaan ( D + E ) 78,947.50

A.4.4.1.23 Pemasangan 1 m² dinding terawang (rooster) 18x18 campuran 1SP:4PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata Terawang Buah 30.000 -
Semen portland Kg 11.000 105,000.00 1,155,000.00
Pasir pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 1,159,375.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 1,207,150.00
E Overhead & Provit 15% x D 181,072.50
F Harga Satuan Pekerjaan ( D + E ) 1,388,222.50

A.4.4.1.23.a Pemasangan 1 m² dinding terawang (rooster) 18x18 campuran 1SP:4PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Kerawang ( roster ) 18 x 18 cm m3 30.000 20,000.00 600,000.00
Semen portland Kg 11.000 1,500.00 16,500.00
Pasir pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 620,875.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 668,650.00
E Overhead & Provit 15% x D 100,297.50
F Harga Satuan Pekerjaan ( D + E ) 768,947.50

A.4.4.1.23.b Pemasangan 1 cm2 dinding terawang (rooster) 30 x 30 campuran 1 SP : 4 PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Beton Ready Mix B 0 m3 11.870 60,500.00 718,135.00
Semen portland Kg 11.000 1,500.00 16,500.00
Pasir pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 739,010.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 786,785.00
E Overhead & Provit 15% x D 118,017.75
F Harga Satuan Pekerjaan ( D + E ) 904,802.75

A.4.4.1.24 Pemasangan 1 cm2 dinding bata berongga ekspose 12x11x24 campuran 1 SP : 3 PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata Berongga Buah 70.000 -
Semen portland Kg 14.000 1,500.00 21,000.00
Pasir pasang m3 0.032 125,000.00 4,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 72,775.00
E Overhead & Provit 15% x D 10,916.25
F Harga Satuan Pekerjaan ( D + E ) 83,691.25

A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.02 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Bata ringan tebal 7,5cm Buah 8.400 -
Mortar Siap Pakai (semen instan) Kg 0.473 -
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 47,775.00
E Overhead & Provit 15% x D 7,166.25
F Harga Satuan Pekerjaan ( D + E ) 54,941.25

A.4.4.1.26 Pemasangan 1m2 Dinding Bata Ringan Tebal 10cm dengan Mortar Siap Pakai
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.671 105,000.00 70,455.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 89,055.00
B BAHAN
Bata ringan tebal 7,5cm Buah 8.400 -
Mortar Siap Pakai (semen instan) Kg 0.063 -
JUMLAH HARGA BAHAN -
C PERALATAN
%
Peralatan (bahan) 10

-
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 89,055.00
E Overhead & Provit 15% x D 13,358.25
F Harga Satuan Pekerjaan ( D + E ) 102,413.25
A.4.4.2 Harga Satuan Pekerjaan Plesteran

A.4.4.2.1 Pemasangan 1 m2 plesteran 1SP : 1 PP tebal 15 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 54,750.00
B BAHAN
PC Kg 15.504 1,500.00 23,256.00
PP m3 0.016 125,000.00 2,000.00
JUMLAH HARGA BAHAN 25,256.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 80,006.00
E Overhead & Provit 15% x D 12,000.90
F Harga Satuan Pekerjaan ( D + E ) 92,006.90

A.4.4.2.2 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 54,750.00
B BAHAN
PC Kg 10.224 1,500.00 15,336.00
PP m3 0.020 125,000.00 2,500.00
JUMLAH HARGA BAHAN 17,836.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 72,586.00
E Overhead & Provit 15% x D 10,887.90
F Harga Satuan Pekerjaan ( D + E ) 83,473.90

A.4.4.2.4 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 54,750.00
B BAHAN
PC Kg 6.240 1,500.00 9,360.00
PP m3 0.024 125,000.00 3,000.00
JUMLAH HARGA BAHAN 12,360.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,110.00
E Overhead & Provit 15% x D 10,066.50
F Harga Satuan Pekerjaan ( D + E ) 77,176.50

A.4.4.2.14 Pemasangan 1 m2 plesteran 1SP : 3 PP tebal 20 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 105,000.00 27,300.00
Tukang batu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 57,215.00
B BAHAN
PC Kg 10.368 1,500.00 15,552.00
PP m3 0.031 125,000.00 3,875.00
JUMLAH HARGA BAHAN 19,427.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 76,642.00
E Overhead & Provit 15% x D 11,496.30
F Harga Satuan Pekerjaan ( D + E ) 88,138.30

A.4.4.2.15 Pemasangan 1 m2 plesteran 1SP : 4 PP tebal 20 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang batu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.022 155,000.00 3,410.00
JUMLAH TENAGA KERJA 73,310.00
B BAHAN
PC Kg 8.320 1,500.00 12,480.00
PP m3 0.032 125,000.00 4,000.00
JUMLAH HARGA BAHAN 16,480.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 89,790.00
E Overhead & Provit 15% x D 13,468.50
F Harga Satuan Pekerjaan ( D + E ) 103,258.50

A.4.4.2.19 Pemasangan 1 m2 Berapen 1SP : 5PP Tebal 15 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang batu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.03 OH 0.008 145,000.00 1,160.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,525.00
B BAHAN
Semen Portlan
Kg 5.184 1,500.00 7,776.00
Pasir Pasang m3 0.026 125,000.00 3,250.00
JUMLAH HARGA BAHAN 11,026.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 38,551.00
E Overhead & Provit 15% x D 5,782.65
F Harga Satuan Pekerjaan ( D + E ) 44,333.65

A.4.4.2.20 Pemasangan 1 m’ Plesteran Skoning 1SP : 3PP Lebar 10 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang batu L.03 OH 0.400 125,000.00 50,000.00
Kepala tukang L.03 OH 0.040 145,000.00 5,800.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 64,820.00
B BAHAN
Semen Portlan
Kg 0.500 1,500.00 750.00
Pasir Pasang m3 0.013 125,000.00 1,625.00
JUMLAH HARGA BAHAN 2,375.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,195.00
E Overhead & Provit 15% x D 10,079.25
F Harga Satuan Pekerjaan ( D + E ) 77,274.25

A.4.4.2.21 Pemasangan 1 m’ Plesteran Skoning 1SP : 3PP Lebar 10 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.450 105,000.00 47,250.00
Tukang batu L.03 OH 0.225 125,000.00 28,125.00
Kepala tukang L.03 OH 0.023 145,000.00 3,335.00
Mandor L.04 OH 0.023 155,000.00 3,565.00
JUMLAH TENAGA KERJA 82,275.00
B BAHAN
Semen Portlan
Kg 10.000 1,500.00 15,000.00
Serbuk Batu granit
Kg 15.000 -
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 97,275.00
E Overhead & Provit 15% x D 14,591.25
F Harga Satuan Pekerjaan ( D + E ) 111,866.25

A.4.4.2.22 Pemasangan1 m2 Plesteran Traso 1SP : 2 Traso Tebal 10 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.450 105,000.00 47,250.00
Tukang batu L.03 OH 0.225 125,000.00 28,125.00
Kepala tukang L.03 OH 0.023 145,000.00 3,335.00
Mandor L.04 OH 0.023 155,000.00 3,565.00
JUMLAH TENAGA KERJA 82,275.00
B BAHAN
Semen Portlan
Kg 10.000 1,500.00 15,000.00
Serbuk Batu Traso Kg 15.000 -
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 97,275.00
E Overhead & Provit 15% x D 14,591.25
F Harga Satuan Pekerjaan ( D + E ) 111,866.25

A.4.4.2.23 Pemasangan1 m2 Plesteran Ciprat (Kamprotan)1SP : 2PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,775.00
B BAHAN
Semen Portlan Kg 4.320 1,500.00 6,480.00
Pasir Pasang Kg 0.006 125,000.00 750.00
JUMLAH HARGA BAHAN 7,230.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 55,005.00
E Overhead & Provit 15% x D 8,250.75
F Harga Satuan Pekerjaan ( D + E ) 63,255.75

A.4.4.2.24 Pemasangan Finishing 1 m2 Dinding Siar Pasangan Bata Merah


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang batu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.03 OH 0.008 145,000.00 1,160.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,525.00
B BAHAN
Semen Portlan Kg 3.108 1,500.00 4,662.00
JUMLAH HARGA BAHAN 4,662.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 32,187.00
E Overhead & Provit 15% x D 4,828.05
F Harga Satuan Pekerjaan ( D + E ) 37,015.05

A.4.4.2.25 Pemasangan Finishing 1m2 Dinding Siar Pasangan Conblock Ekspose


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang batu L.03 OH 0.035 125,000.00 4,375.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 12,925.00
B BAHAN
Semen Portlan
Kg 1.600 1,500.00 2,400.00
JUMLAH HARGA BAHAN 2,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 15,325.00
E Overhead & Provit 15% x D 2,298.75
F Harga Satuan Pekerjaan ( D + E ) 17,623.75
A.4.4.2.26 Pemasangan 1m2 Finishing Siar Pasangan Batu Kali, Campuran 1SP : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang batu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 54,750.00
B BAHAN
Semen Portlan
Kg 6.340 1,500.00 9,510.00
Pasir Pasang m3 0.012 125,000.00 1,500.00
JUMLAH HARGA BAHAN 11,010.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 65,760.00
E Overhead & Provit 15% x D 9,864.00
F Harga Satuan Pekerjaan ( D + E ) 75,624.00

A.4.4.2.27 Pemasangan 1 m2 acian


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang batu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 36,500.00
B BAHAN
Semen PC Kg 3.250 1,500.00 4,875.00
JUMLAH HARGA BAHAN 4,875.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 41,375.00
E Overhead & Provit 15% x D 6,206.25
F Harga Satuan Pekerjaan ( D + E ) 47,581.25
A.4.4.3 Harga Satuan Pekerjaan Penutup Lantai dan Penutup Dinding

A.4.4.3.1 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 40cm x40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin abu-abu Buah 8.190 -
Semen portland Kg 0.045 1,500.00 67.50
Pasir pasang m3 0.500 125,000.00 62,500.00
JUMLAH HARGA BAHAN 62,567.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 108,342.50
E Overhead & Provit 15% x D 16,251.38
F Harga Satuan Pekerjaan ( D + E ) 124,593.88

A.4.4.3.2 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 30cm x30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin abu-abu Buah 11.870 -
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
JUMLAH HARGA BAHAN 20,625.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 66,400.00
E Overhead & Provit 15% x D 9,960.00
F Harga Satuan Pekerjaan ( D + E ) 76,360.00

A.4.4.3.3 Pemasangan 1m2 lantai ubin PC Abu-abu Ukuran 20cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.270 105,000.00 28,350.00
Tukang batu L.02 OH 0.135 125,000.00 16,875.00
Kepala tukang L.03 OH 0.014 145,000.00 2,030.00
Mandor L.04 OH 0.014 155,000.00 2,170.00
JUMLAH TENAGA KERJA 49,425.00
B BAHAN
Ubin abu-abu Buah 26.500 -
Semen portland Kg 10.400 1,500.00 15,600.00
Pasir pasang m3 0.045 125,000.00 5,625.00
JUMLAH HARGA BAHAN 21,225.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 70,650.00
E Overhead & Provit 15% x D 10,597.50
F Harga Satuan Pekerjaan ( D + E ) 81,247.50

A.4.4.3.5 Pemasangan 1m2 Lantai ubin Warna Ukuran 30cm x 30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.270 105,000.00 28,350.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 48,500.00
B BAHAN
Ubin warna Buah 11.870 -
Semen portland Kg 10.000 1,500.00 15,000.00
Semen Warna Kg 0.600 14,000.00 8,400.00
Pasir pasang m3 0.045 125,000.00 75,000.00
JUMLAH HARGA BAHAN 98,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 146,900.00
E Overhead & Provit 15% x D 22,035.00
F Harga Satuan Pekerjaan ( D + E ) 168,935.00

A.4.4.3.6 Pemasangan 1m2 Lantai ubin Warna Ukuran 20cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.270 105,000.00 28,350.00
Tukang batu L.02 OH 0.135 125,000.00 16,875.00
Kepala tukang L.03 OH 0.014 145,000.00 2,030.00
Mandor L.04 OH 0.014 155,000.00 2,170.00
JUMLAH TENAGA KERJA 49,425.00
B BAHAN
Ubin warna Buah 26.500 -
Semen portland Kg 10.400 1,500.00 15,600.00
Semen Warna Kg 1.000 14,000.00 14,000.00
Pasir pasang m3 0.045 125,000.00 125,000.00
JUMLAH HARGA BAHAN 154,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 204,025.00
E Overhead & Provit 15% x D 30,603.75
F Harga Satuan Pekerjaan ( D + E ) 234,628.75
A.4.4.3.7 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 40cm x 40cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin warna Buah 6.630 -
Semen portland Kg 9.800 1,500.00 14,700.00
Semen Warna Kg 1.300 14,000.00 18,200.00
Pasir pasang m3 0.045 125,000.00 162,500.00
JUMLAH HARGA BAHAN 195,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 241,175.00
E Overhead & Provit 15% x D 36,176.25
F Harga Satuan Pekerjaan ( D + E ) 277,351.25

A.4.4.3.8 Pemasangan 1m2 Lantai Ubin Teraso Ukuran 30cm x 30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 105,000.00 27,300.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 47,450.00
B BAHAN
Ubin teraso Buah 11.870 -
Semen portland Kg 10.000 1,500.00 15,000.00
Semen Warna Kg 1.500 14,000.00 21,000.00
Pasir pasang m3 0.045 125,000.00 187,500.00
JUMLAH HARGA BAHAN 223,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 270,950.00
E Overhead & Provit 15% x D 40,642.50
F Harga Satuan Pekerjaan ( D + E ) 311,592.50

A.4.4.3.9 Pemasangan 1m2 Lantai Ubin Granit Ukuran 40cm x 40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin Granit Buah 6.630 18,333.33 121,550.00
Semen portland Kg 9.800 1,500.00 14,700.00
Semen Warna Kg 1.300 14,000.00 18,200.00
Pasir pasang m3 0.045 125,000.00 162,500.00
JUMLAH HARGA BAHAN 316,950.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 362,725.00
E Overhead & Provit 15% x D 54,408.75
F Harga Satuan Pekerjaan ( D + E ) 417,133.75

A.4.4.3.10 Pemasangan 1m2 Lantai Ubin Granit Ukuran 30cm x 30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 105,000.00 27,300.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 47,450.00
B BAHAN
Ubin Granit Buah 11.870 18,333.33 217,616.67
Semen portland Kg 10.000 1,500.00 15,000.00
Semen Warna Kg 1.500 14,000.00 21,000.00
Pasir pasang m3 0.045 125,000.00 187,500.00
JUMLAH HARGA BAHAN 441,116.67
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 488,566.67
E Overhead & Provit 15% x D 73,285.00
F Harga Satuan Pekerjaan ( D + E ) 561,851.67

A.4.4.3.11 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40cmx40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin teralux Buah 6.630 -
Semen portland Kg 9.800 1,500.00 14,700.00
Semen Warna Kg 1.300 14,000.00 18,200.00
Pasir pasang m3 0.045 125,000.00 162,500.00
JUMLAH HARGA BAHAN 195,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 241,175.00
E Overhead & Provit 15% x D 36,176.25
F Harga Satuan Pekerjaan ( D + E ) 277,351.25

A.4.4.3.12 Pemasangan 1m2 Lantai Ubin Teralux Ukuran 30cm x30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 105,000.00 27,300.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 47,450.00
B BAHAN
Ubin teraso Buah 11.870 -
Semen portland Kg 10.000 1,500.00 15,000.00
Semen Warna Kg 1.500 14,000.00
Pasir pasang m3 0.045 125,000.00 187,500.00
JUMLAH HARGA BAHAN 202,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 249,950.00
E Overhead & Provit 15% x D 37,492.50
F Harga Satuan Pekerjaan ( D + E ) 287,442.50

A.4.4.3.13 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 60cm x60cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.240 105,000.00 25,200.00
Tukang batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.012 155,000.00 1,860.00
JUMLAH TENAGA KERJA 43,800.00
B BAHAN
Ubin Teralux Marmer Buah 3.100 -
Semen portland Kg 9.600 1,500.00 14,400.00
Semen Warna Kg 1.500 14,000.00 21,000.00
Pasir pasang m3 0.045 125,000.00 187,500.00
JUMLAH HARGA BAHAN 222,900.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 266,700.00
E Overhead & Provit 15% x D 40,005.00
F Harga Satuan Pekerjaan ( D + E ) 306,705.00

A.4.4.3.14 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 40cm x40cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang batu L.02 OH 0.125 125,000.00 15,625.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 45,775.00
B BAHAN
Ubin Teralux Marmer Buah 6.630 -
Semen portland Kg 9.800 1,500.00 14,700.00
Semen Warna Kg 1.300 14,000.00 18,200.00
Pasir pasang m3 0.045 125,000.00 162,500.00
JUMLAH HARGA BAHAN 195,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 241,175.00
E Overhead & Provit 15% x D 36,176.25
F Harga Satuan Pekerjaan ( D + E ) 277,351.25

A.4.4.3.15 Pemasangan 1m2 Lantai Ubin Teralux Marmer Ukuran 30cm x30cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.260 105,000.00 27,300.00
Tukang batu L.02 OH 0.130 125,000.00 16,250.00
Kepala tukang L.03 OH 0.013 145,000.00 1,885.00
Mandor L.04 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 47,450.00
B BAHAN
Ubin Teralux Marmer Buah 11.870 -
Semen portland Kg 10.000 1,500.00 15,000.00
Semen Warna Kg 1.500 14,000.00 21,000.00
Pasir pasang m3 0.045 125,000.00 187,500.00
JUMLAH HARGA BAHAN 223,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 270,950.00
E Overhead & Provit 15% x D 40,642.50
F Harga Satuan Pekerjaan ( D + E ) 311,592.50

A.4.4.3.16 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 20 s.d. <30 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin PC Buah 5.300 -
Semen portland Kg 1.650 1,500.00 2,475.00
Pasir Pasang Kg 0.004 125,000.00
JUMLAH HARGA BAHAN 2,475.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 25,255.00
E Overhead & Provit 15% x D 3,788.25
F Harga Satuan Pekerjaan ( D + E ) 29,043.25

A.4.4.3.17 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 30 s.d. <40 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin PC Buah 3.530 18,333.33 64,716.67
Semen portland Kg 1.240 1,500.00 1,860.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 66,951.67
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 89,731.67
E Overhead & Provit 15% x D 13,459.75
F Harga Satuan Pekerjaan ( D + E ) 103,191.42

A.4.4.3.18 Pemasangan 1 m’ Plint Ubin PC Abu-abu Ukuran 40 s.d. <50 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin PC Buah 2.650 53,833.33 142,658.33
Semen portland Kg 1.240 1,500.00 1,860.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 144,893.33
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 167,673.33
E Overhead & Provit 15% x D 25,151.00
F Harga Satuan Pekerjaan ( D + E ) 192,824.33

A.4.4.3.19 Pemasangan 1 m’ Plint Ubin Warna Ukuran 20 s.d. <30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin warna Buah 5.300 14,416.67 76,408.33
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 78,493.33
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 101,273.33
E Overhead & Provit 15% x D 15,191.00
F Harga Satuan Pekerjaan ( D + E ) 116,464.33

A.4.4.3.20 Pemasangan 1 m’ Plint Ubin Warna Ukuran 30 s.d. <40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin warna Buah 3.530 18,333.33 64,716.67
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 66,801.67
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 89,581.67
E Overhead & Provit 15% x D 13,437.25
F Harga Satuan Pekerjaan ( D + E ) 103,018.92

A.4.4.3.21 Pemasangan 1 m’ Plint Ubin Warna Ukuran 40 s.d. <50 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin warna Buah 2.650 53,333.33 141,333.33
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 143,418.33
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 166,198.33
E Overhead & Provit 15% x D 24,929.75
F Harga Satuan Pekerjaan ( D + E ) 191,128.08

A.4.4.3.22 Pemasangan 1 m’ Plint Ubin Teraso Ukuran 30 s.d. <40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin teraso Buah 3.530 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.23 Pemasangan 1 m’ Plint Ubin Teraso Ukuran 40 s.d. <50 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin teraso Buah 2.650 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.24 Pemasangan 1 m’ Plint Ubin Granit Ukuran 30 s.d. <40 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin granit Buah 3.530 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.25 Pemasangan 1 m’ Plint Ubin Granit Ukuran 30 s.d. <40 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Ubin granit Buah 2.650 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.26 Pemasangan 1 m’ Plint Ubin Teralux Kerang Ukuran 30 s.d. <40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Teralux marmer Buah 3.530 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.27 Pemasangan 1 m’ Plint Ubin Teralux Kerang Ukuran 30 s.d. <40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Teralux marmer Buah 2.630 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.28 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 30 s.d. <40cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Teralux marmer Buah 3.530 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75
A.4.4.3.29 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 40 s.d. <50cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Teralux marmer Buah 2.650 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.30 Pemasangan 1 m’ Plint Ubin Teralux Marmer Ukuran 60 s.d. <70cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 22,780.00
B BAHAN
Plint Teralux marmer Buah 1.700 -
Semen portland Kg 1.140 1,500.00 1,710.00
Semen Warna Kg 0.100 14,000.00
Pasir pasang m3 0.003 125,000.00 375.00
JUMLAH HARGA BAHAN 2,085.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 24,865.00
E Overhead & Provit 15% x D 3,729.75
F Harga Satuan Pekerjaan ( D + E ) 28,594.75

A.4.4.3.31 Pemasangan 1m2 Lantai Teraso Cor di Tempat, Tebal 3cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.360 105,000.00 37,800.00
Tukang batu L.02 OH 0.180 125,000.00 22,500.00
Kepala tukang L.03 OH 0.018 145,000.00 2,610.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 65,700.00
B BAHAN
Teraso Cor Buah 0.036 -
Semen Warna Kg 0.100 14,000.00 1,400.00
JUMLAH HARGA BAHAN 1,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,100.00
E Overhead & Provit 15% x D 10,065.00
F Harga Satuan Pekerjaan ( D + E ) 77,165.00

A.4.4.3.32 Pemasangan 1m2 Lantai Keramik Artistik 10 s.d. <20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Ubin Keramik Buah 53.000 3,460.00 183,380.00
Semen Portlan Kg 8.190 1,500.00 12,285.00
Pasir Pasang m3 0.045 125,000.00 5,625.00
Semen Warana Kg 3.200 14,000.00 44,800.00
JUMLAH HARGA BAHAN 246,090.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 373,840.00
E Overhead & Provit 15% x D 56,076.00
F Harga Satuan Pekerjaan ( D + E ) 429,916.00

A.4.4.3.33 Pemasangan 1m2 Lantai Keramik Artistik Ukuran 20 s.d. <30 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Ubin Keramik Buah 53.000 9,090.91 481,818.18
Semen Portlan Kg 8.190 1,500.00 12,285.00
Pasir Pasang m3 0.045 125,000.00 5,625.00
Semen Warana Kg 2.750 14,000.00 38,500.00
JUMLAH HARGA BAHAN 538,228.18
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 665,978.18
E Overhead & Provit 15% x D 99,896.73
F Harga Satuan Pekerjaan ( D + E ) 765,874.91
A.4.4.3.34 Pemasangan 1 m2 lantai keramik ukuran 33cmx33cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Ubin keramik Bh 1.050 12,222.22 12,833.33
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 77,500.00 38,750.00
JUMLAH HARGA BAHAN 69,493.33
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 197,243.33
E Overhead & Provit 15% x D 29,586.50
F Harga Satuan Pekerjaan ( D + E ) 226,829.83

A.4.4.3.34.a Pemasangan 1 m2 lantai keramik ukuran 60 x 60 cm Polish (setara indogres)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 60x60 cm Polished (ex Indogres) Bh 1.050 320,000.00 336,000.00
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 360,910.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 488,660.00
E Overhead & Provit 15% x D 73,299.00
F Harga Satuan Pekerjaan ( D + E ) 561,959.00

A.4.4.3.34.b Pemasangan 1 m2 lantai keramik ukuran 60 x 60 cm Unpolish (setara indogres)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 60x60 cm Unpolished (ex Indogres) Bh 1.050 323,000.00 339,150.00
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 364,060.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 491,810.00
E Overhead & Provit 15% x D 73,771.50
F Harga Satuan Pekerjaan ( D + E ) 565,581.50

A.4.4.3.34.c Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Polish (setara indogres)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 40x40 cm Polished (ex Indogres) Bh 1.050 155,000.00 162,750.00
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 187,660.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 315,410.00
E Overhead & Provit 15% x D 47,311.50
F Harga Satuan Pekerjaan ( D + E ) 362,721.50

A.4.4.3.34.d Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Unpolish (setara indogres)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 40x40 cm Unpolished (ex Indogres) Bh 1.050 155,000.00 162,750.00
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 187,660.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 315,410.00
E Overhead & Provit 15% x D 47,311.50
F Harga Satuan Pekerjaan ( D + E ) 362,721.50

A.4.4.3.35 Pemasangan 1 m2 lantai keramik ukuran 30 x 30 cm Polish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 30x30 cm Polish (ex Roman) m2 1.050 100,000.00 105,000.00
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 132,625.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 260,375.00
E Overhead & Provit 15% x D 39,056.25
F Harga Satuan Pekerjaan ( D + E ) 299,431.25

A.4.4.3.35.a Pemasangan 1 m2 lantai keramik ukuran 30 x 30 cm Unpolish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 30x30 cm Unpolish (ex Roman) m2 1.050 100,000.00 105,000.00
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 132,625.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 260,375.00
E Overhead & Provit 15% x D 39,056.25
F Harga Satuan Pekerjaan ( D + E ) 299,431.25

A.4.4.3.35.b Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Polish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 40x40 cm Polish (ex Roman) m2 1.050 110,000.00 115,500.00
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 143,125.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 270,875.00
E Overhead & Provit 15% x D 40,631.25
F Harga Satuan Pekerjaan ( D + E ) 311,506.25

A.4.4.3.35.c Pemasangan 1 m2 lantai keramik ukuran 40 x 40 cm Unpolish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 40x40 cm Unpolish (ex Roman) m2 1.050 110,000.00 115,500.00
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 143,125.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 270,875.00
E Overhead & Provit 15% x D 40,631.25
F Harga Satuan Pekerjaan ( D + E ) 311,506.25

A.4.4.3.36 Pemasangan 1 m2 lantai keramik ukuran 20 x 20 cm Polish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 20x20 cm Polish (ex Roman) Bh 1.050 86,500.00 90,825.00
Semen portland Kg 10.000 1,500.00 15,000.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 118,450.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 246,200.00
E Overhead & Provit 15% x D 36,930.00
F Harga Satuan Pekerjaan ( D + E ) 283,130.00

A.4.4.3.36.a Pemasangan 1 m2 lantai keramik ukuran 20 x 20 cm Unpolish (setara Roman)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Keramik 20x20 cm Unpolish (ex Roman) Bh 1.050 98,000.00 102,900.00
Semen portland Kg 10.400 1,500.00 15,600.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 131,125.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 258,875.00
E Overhead & Provit 15% x D 38,831.25
F Harga Satuan Pekerjaan ( D + E ) 297,706.25

A.4.4.3.37 Pemasangan 1m2 Lantai Keramik Ukuran 30 s.d. <40 cm untuk Variasi/border
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.050 105,000.00 110,250.00
Tukang batu L.02 OH 0.525 125,000.00 65,625.00
Kepala tukang L.03 OH 0.053 145,000.00 7,685.00
Mandor L.04 OH 0.053 155,000.00 8,215.00
JUMLAH TENAGA KERJA 191,775.00
B BAHAN
Ubin Keramik Bh 33.000 53,192.00 1,755,336.00
Semen portland Kg 9.800 1,500.00 14,700.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 4.370 14,000.00 61,180.00
JUMLAH HARGA BAHAN 1,836,841.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 2,028,616.00
E Overhead & Provit 15% x D 304,292.40
F Harga Satuan Pekerjaan ( D + E ) 2,332,908.40

A.4.4.3.39 Pemasangan 1m2 Lantai Keramik Ukuran 30 s.d. <40 cm untuk Variasi/border
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Plint Keramik Bh 10.600 65,000.00 689,000.00
Semen portland Kg 1.140 1,500.00 1,710.00
Pasir pasang m3 0.003 125,000.00 375.00
Semen warna Kg 0.050 14,000.00 700.00
JUMLAH HARGA BAHAN 691,785.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 722,985.00
E Overhead & Provit 15% x D 108,447.75
F Harga Satuan Pekerjaan ( D + E ) 831,432.75

A.4.4.3.40 Pemasangan 1 m’ Plint Keramik Ukuran 20 s.d. <30 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.090 105,000.00 9,450.00
Tukang batu L.02 OH 0.090 125,000.00 11,250.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Plint Keramik Bh 5.300 362,000.00 1,918,600.00
Semen portland Kg 1.140 1,500.00 1,710.00
Pasir pasang m3 0.003 125,000.00 375.00
Semen warna Kg 0.025 14,000.00 350.00
JUMLAH HARGA BAHAN 1,921,035.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,952,235.00
E Overhead & Provit 15% x D 292,835.25
F Harga Satuan Pekerjaan ( D + E ) 2,245,070.25

A.4.4.3.41 Pemasangan 1 m’ Plint Internal Cove Artistik 5cm x 5cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.750 105,000.00 78,750.00
Tukang batu L.02 OH 0.750 125,000.00 93,750.00
Kepala tukang L.03 OH 0.075 145,000.00 10,875.00
Mandor L.04 OH 0.038 155,000.00 5,890.00
JUMLAH TENAGA KERJA 189,265.00
B BAHAN
Internal Cove Bh 5.300 432,792.00 2,293,797.60
Semen portland Kg 1.140 1,500.00 1,710.00
Pasir pasang m3 0.003 125,000.00 375.00
Semen warna Kg 0.100 14,000.00 1,400.00
JUMLAH HARGA BAHAN 2,297,282.60
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 2,486,547.60
E Overhead & Provit 15% x D 372,982.14
F Harga Satuan Pekerjaan ( D + E ) 2,859,529.74

A.4.4.3.42 Pemasangan 1 m2 Lantai Marmer Ukuran 100cm x 100cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Internal Cove Bh 1.060 70,000.00 74,200.00
Semen portland Kg 8.190 1,500.00 12,285.00
Pasir pasang m3 0.045 125,000.00 5,625.00
Semen warna Kg 0.134 14,000.00 1,876.00
JUMLAH HARGA BAHAN 93,986.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 221,736.00
E Overhead & Provit 15% x D 33,260.40
F Harga Satuan Pekerjaan ( D + E ) 254,996.40

A.4.4.3.43 Pemasangan 1 m2 Lantai Karpet


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.170 105,000.00 17,850.00
Tukang Kayu L.02 OH 0.170 125,000.00 21,250.00
Kepala tukang L.03 OH 0.017 145,000.00 2,465.00
Mandor L.04 OH 0.009 155,000.00 1,395.00
JUMLAH TENAGA KERJA 42,960.00
B BAHAN
Karpet m3 1.050 125,000.00 131,250.00
Lem Karpet Kg 0.350 14,000.00 4,900.00
JUMLAH HARGA BAHAN 136,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 179,110.00
E Overhead & Provit 15% x D 26,866.50
F Harga Satuan Pekerjaan ( D + E ) 205,976.50

A.4.4.3.44 Pemasangan 1 m2 Underlayer (Pelapis Bawah Karpet)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.170 105,000.00 17,850.00
Tukang Kayu L.02 OH 0.170 125,000.00 21,250.00
Kepala tukang L.03 OH 0.017 145,000.00 2,465.00
Mandor L.04 OH 0.009 155,000.00 1,395.00
JUMLAH TENAGA KERJA 42,960.00
B BAHAN
Underlayer m3 1.050 - -
Lem Karet Kg 0.350 125,000.00 43,750.00
JUMLAH HARGA BAHAN 43,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 86,710.00
E Overhead & Provit 15% x D 13,006.50
F Harga Satuan Pekerjaan ( D + E ) 99,716.50

A.4.4.3.45 Pemasangan 1 m2 Lantai Parquet Kayu Solid


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Kayu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Parquet kayu m3 1.050 155,000.00 162,750.00
Lem Kayu Kg 0.600 125,000.00 75,000.00
JUMLAH HARGA BAHAN 237,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 365,500.00
E Overhead & Provit 15% x D 54,825.00
F Harga Satuan Pekerjaan ( D + E ) 420,325.00

A.4.4.3.46 Pemasangan 1 m2 Lantai Kayu Gymfloor


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Kayu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Parquet gymfloor m3 1.050 125,000.00 131,250.00
Lem Kayu Kg 0.600 125,000.00 75,000.00
JUMLAH HARGA BAHAN 206,250.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 334,000.00
E Overhead & Provit 15% x D 50,100.00
F Harga Satuan Pekerjaan ( D + E ) 384,100.00

A.4.4.3.47 Pemasangan 1 m2 Dinding Porselen 11cm x 11cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Porslen Doos 1.05 86,500.00 90,825.00
Semen Portlan Kg 9.3 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 0.500 14,000.00 7,000.00
JUMLAH HARGA BAHAN 114,025.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 241,775.00
E Overhead & Provit 15% x D 36,266.25
F Harga Satuan Pekerjaan ( D + E ) 278,041.25

A.4.4.3.48 Pemasangan 1 m2 Dinding Porselen 10cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Porslen buah 53.00 3,460.00 183,380.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 2.750 14,000.00 38,500.00
JUMLAH HARGA BAHAN 238,080.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 365,830.00
E Overhead & Provit 15% x D 54,874.50
F Harga Satuan Pekerjaan ( D + E ) 420,704.50

A.4.4.3.49 Pemasangan 1 m2 Dinding Porselen 20cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Tukang Batu L.02 OH 0.450 125,000.00 56,250.00
Kepala tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 164,250.00
B BAHAN
Porslen buah 26.00 3,460.00 89,960.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 1.940 14,000.00 27,160.00
JUMLAH HARGA BAHAN 133,320.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 297,570.00
E Overhead & Provit 15% x D 44,635.50
F Harga Satuan Pekerjaan ( D + E ) 342,205.50

A.4.4.3.50 Pemasangan 1 m2 Dinding Keramik Artistik 10cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Tukang Batu L.02 OH 0.450 125,000.00 56,250.00
Kepala tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 164,250.00
B BAHAN
Keramik Artistik buah 52.00 3,460.00 179,920.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 2.750 14,000.00 38,500.00
JUMLAH HARGA BAHAN 234,620.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 398,870.00
E Overhead & Provit 15% x D 59,830.50
F Harga Satuan Pekerjaan ( D + E ) 458,700.50

A.4.4.3.51 Pemasangan 1 m2 Dinding Keramik Artistik 5cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Tukang Batu L.02 OH 0.450 125,000.00 56,250.00
Kepala tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 164,250.00
B BAHAN
Keramik Artistik buah 1.04 86,500.00 89,960.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 2.900 14,000.00 40,600.00
JUMLAH HARGA BAHAN 146,760.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 311,010.00
E Overhead & Provit 15% x D 46,651.50
F Harga Satuan Pekerjaan ( D + E ) 357,661.50

A.4.4.3.52 Pemasangan 1 m2 Dinding Keramik 10cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Tukang Batu L.02 OH 0.450 125,000.00 56,250.00
Kepala tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 164,250.00
B BAHAN
Keramik buah 52.00 3,460.00 179,920.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 2.750 14,000.00 38,500.00
JUMLAH HARGA BAHAN 234,620.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 398,870.00
E Overhead & Provit 15% x D 59,830.50
F Harga Satuan Pekerjaan ( D + E ) 458,700.50

A.4.4.3.53 Pemasangan 1 m2 Dinding Keramik 20cm x 20cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.900 105,000.00 94,500.00
Tukang Batu L.02 OH 0.450 125,000.00 56,250.00
Kepala tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.045 155,000.00 6,975.00
JUMLAH TENAGA KERJA 164,250.00
B BAHAN
Keramik buah 26.00 3,460.00 89,960.00
Semen Portlan Kg 9.30 1,500.00 13,950.00
Pasir Pasang m3 0.018 125,000.00 2,250.00
Semen Warna Kg 1.940 14,000.00 27,160.00
JUMLAH HARGA BAHAN 133,320.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 297,570.00
E Overhead & Provit 15% x D 44,635.50
F Harga Satuan Pekerjaan ( D + E ) 342,205.50

A.4.4.3.54 Pemasangan 1 m2 Dinding Marmer 100cm x 100cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.300 105,000.00 136,500.00
Tukang Batu L.02 OH 0.650 125,000.00 81,250.00
Kepala tukang L.03 OH 0.065 145,000.00 9,425.00
Mandor L.04 OH 0.065 155,000.00 10,075.00
JUMLAH TENAGA KERJA 237,250.00
B BAHAN
Marmer buah 1.06 1,400,000.00 1,484,000.00
Semen Portlan Kg 12.44 1,500.00 18,660.00
Pasir Pasang m3 0.025 125,000.00 3,125.00
Semen Warna Kg 0.650 14,000.00 9,100.00
Paku 12cm buah 3.030 40,000.00
JUMLAH HARGA BAHAN 1,514,885.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,752,135.00
E Overhead & Provit 15% x D 262,820.25
F Harga Satuan Pekerjaan ( D + E ) 2,014,955.25

A.4.4.3.55 Pemasangan 1 m2 Dinding Bata Pelapis (Super) 3cm x 7cm x 24cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 182,500.00
B BAHAN
Bata Plastis buah 63.00 -
Semen Portlan Kg 12.44 1,500.00 18,660.00
Pasir Pasang m3 0.025 125,000.00 3,125.00
Semen Warna Kg 2.750 14,000.00 38,500.00
JUMLAH HARGA BAHAN 60,285.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 242,785.00
E Overhead & Provit 15% x D 36,417.75
F Harga Satuan Pekerjaan ( D + E ) 279,202.75

A.4.4.3.56 Pemasangan 1 m2 Dinding Batu Paras


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Batu pasar buah 1.10 -
Semen Portlan Kg 11.75 1,500.00 17,625.00
Pasir Pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 22,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 149,750.00
E Overhead & Provit 15% x D 22,462.50
F Harga Satuan Pekerjaan ( D + E ) 172,212.50

A.4.4.3.57 Pemasangan 1 m2 Dinding Batu Tempel Hitam


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Batu L.02 OH 0.350 125,000.00 43,750.00
Kepala tukang L.03 OH 0.035 145,000.00 5,075.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 127,750.00
B BAHAN
Batu Tempel Hutam buah 1.10 170,000.00 187,000.00
Semen Portlan Kg 11.75 1,500.00 17,625.00
Pasir Pasang m3 0.035 125,000.00 4,375.00
JUMLAH HARGA BAHAN 209,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 336,750.00
E Overhead & Provit 15% x D 50,512.50
F Harga Satuan Pekerjaan ( D + E ) 387,262.50

A.4.4.3.58 Pemasangan 1 m2 Lantai Vynil Ukuran 30cm x 30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang Batu L.02 OH 0.150 125,000.00 18,750.00
Kepala tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 37,915.00
B BAHAN
Vynil buah 11.87 -
Lem Karet Kg 0.35 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 37,915.00
E Overhead & Provit 15% x D 5,687.25
F Harga Satuan Pekerjaan ( D + E ) 43,602.25

A.4.4.3.59 Pemasangan 1 m2 Wallpaper lebar 50 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang Kayu L.02 OH 0.175 125,000.00 21,875.00
Kepala tukang L.03 OH 0.017 145,000.00 2,465.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 61,400.00
B BAHAN
Wallpaper m 2.20 -
Lem Karet Kg 0.25 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 61,400.00
E Overhead & Provit 15% x D 9,210.00
F Harga Satuan Pekerjaan ( D + E ) 70,610.00

A.4.4.3.60 Pemasangan 1m2 Floor Harderner


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.120 105,000.00 12,600.00
Tukang Batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 30,270.00
B BAHAN
Floor harderner Kg 5.00 16,600.00 83,000.00
JUMLAH HARGA BAHAN 83,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 113,270.00
E Overhead & Provit 15% x D 16,990.50
F Harga Satuan Pekerjaan ( D + E ) 130,260.50

A.4.4.3.61 Pemasangan 1 m’ Plint Vynil 15cm x 30cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang Batu L.02 OH 0.080 125,000.00 10,000.00
Kepala tukang L.03 OH 0.008 145,000.00 1,160.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 20,180.00
B BAHAN
vynil Buah 3.10 -
Lem Karet Kg 0.08 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 20,180.00
E Overhead & Provit 15% x D 3,027.00
F Harga Satuan Pekerjaan ( D + E ) 23,207.00

A.4.4.3.62 Pemasangan 1 m’ Plint Kayu Tebal 2 cm Lebar 10 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.120 105,000.00 12,600.00
Tukang Batu L.02 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 30,270.00
B BAHAN
Papan kayu kelas 1 m3 0.003 11,188,300.00 33,564.90
Paku/skrup 5cm Kg 0.05 23,000.00 1,150.00
JUMLAH HARGA BAHAN 34,714.90
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 64,984.90
E Overhead & Provit 15% x D 9,747.74
F Harga Satuan Pekerjaan ( D + E ) 74,732.64

A.4.4.3.63 Pemasangan 1 m2 Paving Block (Blok Beton) Natural tebal 6cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang Batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 96,201.50
B BAHAN
Pavingblock 6cm m2 1.100 165,000.00 181,500.00
Pasir beton m3 0.05 125,000.00 6,250.00
JUMLAH HARGA BAHAN 187,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 283,951.50
E Overhead & Provit 15% x D 42,592.73
F Harga Satuan Pekerjaan ( D + E ) 326,544.23

A.4.4.3.64 Pemasangan 1 m2 Pavingblock (Blok Beton) Natural tebal 8cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang Batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Pavingblock 8cm natural m2 1.100 165,000.00 181,500.00
Pasir beton m3 0.08 125,000.00 10,000.00
JUMLAH HARGA BAHAN 191,500.00
C PERALATAN
Peralatan % 10 -

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 313,951.50
E Overhead & Provit 15% x D 47,092.73
F Harga Satuan Pekerjaan ( D + E ) 361,044.23

A.4.4.3.65 Pemasangan 1 m2 Paving Block ( Blok Beton) Berwarna Tebal 6cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang Batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 96,201.50
B BAHAN
Pavingblock 8cm natural m2 1.100 165,000.00 181,500.00
Pasir beton m3 0.05 125,000.00 6,250.00
JUMLAH HARGA BAHAN 187,750.00
C PERALATAN
Peralatan % 10 -

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 283,951.50
E Overhead & Provit 15% x D 42,592.73
F Harga Satuan Pekerjaan ( D + E ) 326,544.23

A.4.4.3.65.a Pemasangan 1 m2 paving block natural tebal 8 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Paving block 8 cm natural m2 1.010 165,000.00 166,650.00
Stone Dust m3 0.008 350,000.00 2,625.00
JUMLAH HARGA BAHAN 169,275.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT 6,640.00
D Jumlah (A + B + C) 298,366.50
E Overhead & Provit 15% x D 44,754.98
F Harga Satuan Pekerjaan ( D + E ) 343,121.48

A.4.4.3.65.b Pemasangan 1 m2 paving block natural tebal 10 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Paving block 10 cm natural m2 1.010 165,000.00 166,650.00
Stone Dust m3 0.008 350,000.00 2,625.00
JUMLAH HARGA BAHAN 169,275.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT 6,640.00
D Jumlah (A + B + C) 298,366.50
E Overhead & Provit 15% x D 44,754.98
F Harga Satuan Pekerjaan ( D + E ) 343,121.48

A.4.4.3.65.c Pemasangan 1 m2 paving block segi 6 natural tebal 7 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Paving block segi 6 tebal 7 cm m2 1.010 105,400.00 106,454.00
Stone Dust m3 0.008 350,000.00 2,625.00
JUMLAH HARGA BAHAN 109,079.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT 6,640.00
D Jumlah (A + B + C) 238,170.50
E Overhead & Provit 15% x D 35,725.58
F Harga Satuan Pekerjaan ( D + E ) 273,896.08

A.4.4.3.66 Pemasangan 1 m2 Pavingblock (Blok Beton) Berwarna Tebal 8cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Pavingblock8cm berwarna m2 1.010 105,400.00 106,454.00
Pasir Beton m3 0.008 350,000.00 2,625.00
JUMLAH HARGA BAHAN 109,079.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT 6,640.00
D Jumlah (A + B + C) 238,170.50
E Overhead & Provit 15% x D 35,725.58
F Harga Satuan Pekerjaan ( D + E ) 273,896.08

A.4.4.3.67.a Pemasangan 1 m2 paving stone


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.500 105,000.00 52,500.00
Tukang batu L.02 OH 0.500 125,000.00 62,500.00
Kepala tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 122,451.50
B BAHAN
Paving stone m2 1.010 132,500.00 133,825.00
Stone Dust m3 0.008 350,000.00 2,625.00
JUMLAH HARGA BAHAN 136,450.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT 6,640.00
D Jumlah (A + B + C) 265,541.50
E Overhead & Provit 15% x D 39,831.23
F Harga Satuan Pekerjaan ( D + E ) 305,372.73
A.4.5.1 Satuan Pekerjaan Langit-Langit (plafond)

A.4.5.1.1 Pemasangan1 m2 Langit-Langit Serat Semen, Tebal 4 mm, 5 mm, dan 6 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.030 105,000.00 3,150.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 13,535.00
B BAHAN
Serat Semen m2 1.100 46,000.00 50,600.00
Paku tripleks Kg 0.010 13,500.00 135.00
JUMLAH HARGA BAHAN 50,735.00
C PERALATAN
Peralatan % 10 66,400.00 6,640.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 64,270.00
E Overhead & Provit 15% x D 9,640.50
F Harga Satuan Pekerjaan ( D + E ) 73,910.50

A.4.5.1.2 Pemasangan 1 m2 Langit-Langit Akustik Ukuran 30 x 30 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.030 105,000.00 3,150.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 13,535.00
B BAHAN
Akustik Lembar 12.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 13,535.00
E Overhead & Provit 15% x D 2,030.25
F Harga Satuan Pekerjaan ( D + E ) 15,565.25

A.4.5.1.3 Pemasangan 1 m2 Langit-Langit Akustik Ukuran 30 x 60 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.120 105,000.00 12,600.00
Tukang kayu L.03 OH 0.120 125,000.00 15,000.00
Kepala tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 30,270.00
B BAHAN
Akustik Lembar 5.800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 30,270.00
E Overhead & Provit 15% x D 4,540.50
F Harga Satuan Pekerjaan ( D + E ) 34,810.50

A.4.5.1.4 Pemasangan 1 m2 Langit-Langit Kayu Lapis, Tebal 3 mm, 4 mm dan 6 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Kayu Lapis Lembar 0.375 -
Paku tripleks Kg 0.030 25,000.00 750.00
JUMLAH HARGA BAHAN 750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,975.00
E Overhead & Provit 15% x D 3,896.25
F Harga Satuan Pekerjaan ( D + E ) 29,871.25

A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120x240) cm, tebal 6 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Tripleks (6 mm) Lembar 0.375 111,000.00 41,625.00
Paku tripleks Kg 0.030 25,000.00 750.00
JUMLAH HARGA BAHAN 42,375.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,600.00
E Overhead & Provit 15% x D 10,140.00
F Harga Satuan Pekerjaan ( D + E ) 77,740.00

A.4.5.1.6 Pemasangan 1 m2 Langit-Langit Lambrisering Kayu, tebal 9 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang kayu L.03 OH 0.800 125,000.00 100,000.00
Kepala tukang L.03 OH 0.080 145,000.00 11,600.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 201,800.00
B BAHAN
Kayu Papan m3 0.015 11,188,300.00 167,824.50
Paku tripleks Kg 0.010 25,000.00 250.00
JUMLAH HARGA BAHAN 168,074.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 369,874.50
E Overhead & Provit 15% x D 55,481.18
F Harga Satuan Pekerjaan ( D + E ) 425,355.68

A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 0.050 125,000.00 6,250.00
Kepala tukang L.03 OH 0.005 145,000.00 725.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 18,250.00
B BAHAN
Gypsum board Lembar 0.364 74,600.00 27,154.40
Paku skrup Kg 0.110 60,000.00 6,600.00
JUMLAH HARGA BAHAN 33,754.40
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 52,004.40
E Overhead & Provit 15% x D 7,800.66
F Harga Satuan Pekerjaan ( D + E ) 59,805.06

A.4.5.1.7.a Pemasangan 1 m2 langit-langit GRC ukuran 120 x 240 mm tebal 4 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 0.050 125,000.00 6,250.00
Kepala tukang L.03 OH 0.005 145,000.00 725.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 18,250.00
B BAHAN
GRC tebal 4 mm Lembar 0.364 79,700.00 29,010.80
Paku GRC Kg 0.110 25,000.00 2,750.00
JUMLAH HARGA BAHAN 31,760.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 50,010.80
E Overhead & Provit 15% x D 7,501.62
F Harga Satuan Pekerjaan ( D + E ) 57,512.42

A.4.5.1.10 Pemasangan 1 m’ List Langit-Langit Kayu profil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.03 OH 0.0075 145,000.00 1,087.50
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,452.50
B BAHAN
Genteng palentong Buah 25.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 27,452.50
E Overhead & Provit 15% x D 4,117.88
F Harga Satuan Pekerjaan ( D + E ) 31,570.38
A.4.5.2 Harga Satuan Pekerjaan Penutup Atap

A.4.5.2.1 Pemasangan 1 m2 Atap genteng Palentong Kecil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.11 OH 0.008 145,000.00 1,160.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,525.00
B BAHAN
Genteng palentong besar ( morando) buah 12.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 27,525.00
E Overhead & Provit 15% x D 4,128.75
F Harga Satuan Pekerjaan ( D + E ) 31,653.75

A.4.5.2.2 Pemasangan 1 m2 Atap genteng Palentong Kecil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.11 OH 0.008 145,000.00 1,160.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,525.00
B BAHAN
Genteng Kodok buah 25.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 27,525.00
E Overhead & Provit 15% x D 4,128.75
F Harga Satuan Pekerjaan ( D + E ) 31,653.75

A.4.5.2.3 Pemasangan1 m2 Atap Genteng Palentong Besar/Morando


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.11 OH 0.008 145,000.00 1,160.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 27,525.00
B BAHAN
List Kayu profil m 1.050 35,000.00 36,750.00
Paku Kg 0.010 23,000.00 230.00
JUMLAH HARGA BAHAN 36,980.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 64,505.00
E Overhead & Provit 15% x D 9,675.75
F Harga Satuan Pekerjaan ( D + E ) 74,180.75

A.4.5.2.4 Pemasangan 1 m’ Bubung Genteng Palentong Kecil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.11 OH 0.020 145,000.00 2,900.00
Mandor L.15 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 70,210.00
B BAHAN
Genteng Budung Buah 5.000 -
Semen Portlan Kg 8.000 1,500.00 12,000.00
Pasir pasang m3 0.032 23,000.00 736.00
JUMLAH HARGA BAHAN 12,736.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 82,946.00
E Overhead & Provit 15% x D 12,441.90
F Harga Satuan Pekerjaan ( D + E ) 95,387.90

A.4.5.2.5 Pemasangan 1 m’ Bubung Genteng Kodok Glazuur


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.11 OH 0.020 145,000.00 2,900.00
Mandor L.15 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 70,210.00
B BAHAN
Genteng Budung Buah 5.000 -
Semen Portlan Kg 8.000 1,500.00 12,000.00
Pasir pasang m3 0.032 23,000.00 736.00
JUMLAH HARGA BAHAN 12,736.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 82,946.00
E Overhead & Provit 15% x D 12,441.90
F Harga Satuan Pekerjaan ( D + E ) 95,387.90

A.4.5.2.6 Pemasangan 1 m’ Bubung Genteng Palentong Besar


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.11 OH 0.020 145,000.00 2,900.00
Mandor L.15 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 70,210.00
B BAHAN
Genteng Budung Buah 4.000 -
Semen Portlan Kg 8.000 1,500.00 12,000.00
Pasir pasang m3 0.032 23,000.00 736.00
JUMLAH HARGA BAHAN 12,736.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 82,946.00
E Overhead & Provit 15% x D 12,441.90
F Harga Satuan Pekerjaan ( D + E ) 95,387.90

A.4.5.2.7 Pemasangan 1 m2 Roof Light Fibreglass 90cm x180cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.067 125,000.00 8,375.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,175.00
B BAHAN
Rooflight 90x180 Lbr 0.600
Paku biasa ½”-1” Kg 0.050 1,500.00 23,000.00
JUMLAH HARGA BAHAN 23,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 48,175.00
E Overhead & Provit 15% x D 7,226.25
F Harga Satuan Pekerjaan ( D + E ) 55,401.25
A.4.5.2.8 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 250cm x 5mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.11 OH 0.008 145,000.00 1,160.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 26,475.00
B BAHAN
Serat semen gel 92x250 Lbr 0.500 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,475.00
E Overhead & Provit 15% x D 3,971.25
F Harga Satuan Pekerjaan ( D + E ) 30,446.25

A.4.5.2.9 Pemasangan 1 m2 Atap Serat Semen Gelombang 92cm x 225cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala tukang L.11 OH 0.008 145,000.00 1,160.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 26,475.00
B BAHAN
Serat semen gel 92x2,25 Lbr 0.600 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,475.00
E Overhead & Provit 15% x D 3,971.25
F Harga Satuan Pekerjaan ( D + E ) 30,446.25

A.4.5.2.10 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 92x200 Lbr 0.600 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.11 Pemasangan1 m2 Atap Serat Semen Gelombang 92cm x 200cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 92x180 Lbr 0.750 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.12 Pemasangan1 m2 Atap Serat Semen Gelombang 105cm x 300cm x 5 mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 105x300 Lbr 0.350 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.15 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 240cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 105x300 Lbr 0.440 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.17 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 210cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen Gel 105x210 Lbr 0.510 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.18 Pemasangan 1 m2 Atap Serat Semen Gelombang 105cm x 150cm x 5mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 105x150 Lbr 0.800 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.19 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 300cm x 6mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 108x300 Lbr 0.370 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.20 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 270cm x 6mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 108x270 Lbr 0.380 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.21 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 240cm x 6mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 108x240 Lbr 0.460 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.22 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 210cm x 6mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 108x210 Lbr 0.490 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50
A.4.5.2.23 Pemasangan 1 m2 Atap Serat Semen Gelombang 108cm x 180cm x 6mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Serat semen gel 108x180 Lbr 0.570 -
Paku pancing 6x23 Kg 0.120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,550.00
E Overhead & Provit 15% x D 3,832.50
F Harga Satuan Pekerjaan ( D + E ) 29,382.50

A.4.5.2.24 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 92 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Bubung Setel gel. Lbr 2.400 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.25 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 105 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Bubung Setel gel. Lbr 2.100 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.26 Pemasangan 1 m’ Nok/Bubung Setel Gelombang 108 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Bubung setel gel. Lbr 2.000 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.27 Pemasangan 1 m’ Nok/Bubung Paten (Permanen) 92 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Nok Paten 92cm Lbr 1.100 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.28 Pemasangan 1 m’ Nok/Bubung Paten (Permanen) 105cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Nok Paten 92cm Lbr 1.200 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.29 Pemasangan 1 m’ Nok/Bubung Paten(Permanen) 108 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Nok Paten 108cm Lbr 1.200 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.30 Pemasangan 1 m’ Nok/Bubung Setel Rata 92cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 31,755.00
B BAHAN
Nok Paten 108cm Lbr 1.100 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 31,755.00
E Overhead & Provit 15% x D 4,763.25
F Harga Satuan Pekerjaan ( D + E ) 36,518.25

A.4.5.2.31 Pemasangan 1 m’ Nok/Bubung Setel Rata 105 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.084 105,000.00 8,820.00
Tukang kayu L.03 OH 0.125 125,000.00 15,625.00
Kepala tukang L.11 OH 0.013 145,000.00 1,885.00
Mandor L.15 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 26,950.00
B BAHAN
Nok Setel rata 105cm Lbr 1.100 -
Paku skrup 3,5” Kg 6.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 26,950.00
E Overhead & Provit 15% x D 4,042.50
F Harga Satuan Pekerjaan ( D + E ) 30,992.50

A.4.5.2.32 Pemasangan 1 m2 Genteng Beton


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 49,000.00
B BAHAN
Genteng Beton buah 11.000 -
Paku skrup 3,5” Kg 0.030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 49,000.00
E Overhead & Provit 15% x D 7,350.00
F Harga Satuan Pekerjaan ( D + E ) 56,350.00

A.4.5.2.32.a Pemasangan 1 m2 genteng metal Type Classic atap pelana


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Type Classic 0.30 m2 1.300 107,892.00 140,259.60
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 144,859.60
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 179,964.60
E Overhead & Provit 15% x D 26,994.69
F Harga Satuan Pekerjaan ( D + E ) 206,959.29

A.4.5.2.32.b Pemasangan 1 m2 genteng metal Type Royal atap pelana


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Type Royal 0.30 m2 1.300 113,886.00 148,051.80
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 152,651.80
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 187,756.80
E Overhead & Provit 15% x D 28,163.52
F Harga Satuan Pekerjaan ( D + E ) 215,920.32

A.4.5.2.32.c Pemasangan 1 m2 genteng metal Type Metal Stone atap pelana


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Stone ( Type Classic 0.35 ) m2 1.300 129,600.00 168,480.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 173,080.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 208,185.00
E Overhead & Provit 15% x D 31,227.75
F Harga Satuan Pekerjaan ( D + E ) 239,412.75

A.4.5.2.33 Pemasangan 1 m2 Genteng Aspal 80cm x 100cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.300 125,000.00 37,500.00
Kepala tukang L.11 OH 0.003 145,000.00 435.00
Mandor L.15 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 60,485.00
B BAHAN
Genteng aspal Ukuran 0,8x1m bauh 1.500 -
Plywood 6mm Lbr 0.350 -
Paku biasa ½”-1” Kg 0.030 -
Plastik aerator buah 0.500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 60,485.00
E Overhead & Provit 15% x D 9,072.75
F Harga Satuan Pekerjaan ( D + E ) 69,557.75

A.4.5.2.33.a Pemasangan 1 m2 genteng metal Type Classic atap jurai


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Type Classic 0.30 m2 2.000 107,892.00 215,784.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 220,384.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 255,489.00
E Overhead & Provit 15% x D 38,323.35
F Harga Satuan Pekerjaan ( D + E ) 293,812.35

A.4.5.2.33.b Pemasangan 1 m2 genteng metal Type Royal atap jurai


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Type Royal 0.30 m2 2.000 113,886.00 227,772.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 232,372.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 267,477.00
E Overhead & Provit 15% x D 40,121.55
F Harga Satuan Pekerjaan ( D + E ) 307,598.55

A.4.5.2.33.c Pemasangan 1 m2 genteng metal Type metal Stone atap jurai


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala tukang L.11 OH 0.010 145,000.00 1,450.00
Mandor L.15 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 35,105.00
B BAHAN
Genteng Metal Stone ( Type Classic 0.35 ) m2 2.000 129,600.00 259,200.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 263,800.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 298,905.00
E Overhead & Provit 15% x D 44,835.75
F Harga Satuan Pekerjaan ( D + E ) 343,740.75

A.4.5.2.34 Pemasangan 1 m2 atap sirap kayu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.166 105,000.00 17,430.00
Tukang kayu L.03 OH 0.250 125,000.00 31,250.00
Kepala tukang L.11 OH 0.025 145,000.00 3,625.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 53,545.00
B BAHAN
Sirap kayu Buah 30.000 5,300.00 159,000.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 163,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 217,145.00
E Overhead & Provit 15% x D 32,571.75
F Harga Satuan Pekerjaan ( D + E ) 249,716.75

A.4.5.2.35 Pemasangan 1 m2 atap sirap kayu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.166 105,000.00 17,430.00
Tukang kayu L.03 OH 0.250 125,000.00 31,250.00
Kepala tukang L.11 OH 0.025 145,000.00 3,625.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 53,545.00
B BAHAN
Sirap kayu Buah 30.000 5,300.00 159,000.00
Paku biasa 1/2"-1" Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 163,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 217,145.00
E Overhead & Provit 15% x D 32,571.75
F Harga Satuan Pekerjaan ( D + E ) 249,716.75

A.4.5.2.36 Pemasangan 1 m’ Nok/Bubung Genteng Beton


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala tukang L.11 OH 0.020 145,000.00 2,900.00
Mandor L.15 OH 0.020 155,000.00 3,100.00
JUMLAH TENAGA KERJA 73,000.00
B BAHAN
Nok Genteng beton Buah 3.500 -
Paku biasa ½”-1” kg 0.050 23,000.00
Semen Portlan Kg 10.800 1,500.00
Pasir Pasang m3 0.032 125,000.00
Semen Warna Kg 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 73,000.00
E Overhead & Provit 15% x D 10,950.00
F Harga Satuan Pekerjaan ( D + E ) 83,950.00

A.4.5.2.37 Pemasangan 1 m’ Nok/Bubung Genteng Aspal


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.125 105,000.00 13,125.00
Tukang kayu L.03 OH 0.250 125,000.00 31,250.00
Kepala tukang L.11 OH 0.025 145,000.00 3,625.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 48,930.00
B BAHAN
Nok genteng aspal Buah 2.000 -
Paku biasa ½”-1” Kg 0.050 23,000.00 1,150.00
Kayu balok borneo m3 0.0035 8,950,000.00 31,325.00
JUMLAH HARGA BAHAN 32,475.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 81,405.00
E Overhead & Provit 15% x D 12,210.75
F Harga Satuan Pekerjaan ( D + E ) 93,615.75
A.4.5.2.38 Pemasangan 1 m' nok genteng metal
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.250 105,000.00 26,250.00
Tukang kayu L.03 OH 0.150 125,000.00 18,750.00
Kepala tukang L.11 OH 0.015 145,000.00 2,175.00
Mandor L.15 OH 0.013 155,000.00 2,015.00
JUMLAH TENAGA KERJA 49,190.00
B BAHAN
Nok genteng metal Buah 1.100 50,000.00 55,000.00
Paku biasa 1/2"-1" Kg 0.050 23,000.00 1,150.00
JUMLAH HARGA BAHAN 56,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 105,340.00
E Overhead & Provit 15% x D 15,801.00
F Harga Satuan Pekerjaan ( D + E ) 121,141.00

A.4.5.2.39 A.4.5.2.39. Pemasangan 1 m’ Nok/Bubung Atap Sirap


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.125 105,000.00 13,125.00
Tukang kayu L.03 OH 0.250 125,000.00 31,250.00
Kepala tukang L.11 OH 0.025 145,000.00 3,625.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 48,930.00
B BAHAN
Seng pelat 3’ x 6’ 90cmx180cm lbr 0.400 42,500.00 17,000.00
Paku biasa ½”-1” 1,5cm -2,5cm Kg 0.050 23,000.00 1,150.00
JUMLAH HARGA BAHAN 18,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,080.00
E Overhead & Provit 15% x D 10,062.00
F Harga Satuan Pekerjaan ( D + E ) 77,142.00

A.4.5.2.40 Pemasangan 1 m2 Atap Seng Gelombang 105cm x180cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.120 105,000.00 12,600.00
Tukang kayu L.03 OH 0.060 125,000.00 7,500.00
Kepala tukang L.11 OH 0.006 145,000.00 870.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 21,900.00
B BAHAN
Seng gel 3"x 6" Lbr 0.700 72,000.00 50,400.00
Paku biasa 1/2"-1" Kg 0.020 23,000.00 460.00
JUMLAH HARGA BAHAN 50,860.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 51,790.00
E Overhead & Provit 15% x D 7,768.50
F Harga Satuan Pekerjaan ( D + E ) 59,558.50

A.4.5.2.41 Pemasangan 1 m’ Nok/Bubung Atap Seng


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.070 125,000.00 8,750.00
Kepala tukang L.11 OH 0.007 145,000.00 1,015.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 26,445.00
B BAHAN
Seng pelat 3"x 6" bjls 28 Lbr 0.300 80,000.00 24,000.00
Paku biasa 1/2"-1" Kg 0.040 23,000.00 920.00
JUMLAH HARGA BAHAN 24,920.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 25,850.00
E Overhead & Provit 15% x D 3,877.50
F Harga Satuan Pekerjaan ( D + E ) 29,727.50

A.4.5.2.41.a Pemasangan 1 m2 atap Zincalum Polos 0.40


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.750 125,000.00 93,750.00
Kepala tukang L.11 OH 0.080 145,000.00 11,600.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 122,030.00
B BAHAN
Zincalume Gelombang Persegi 0.40 (polos) Lbr 1.050 75,900.00 79,695.00
Paku hak panjang 15 cm Kg 0.020 23,000.00 460.00
JUMLAH HARGA BAHAN 80,155.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 202,185.00
E Overhead & Provit 15% x D 30,327.75
F Harga Satuan Pekerjaan ( D + E ) 232,512.75

A.4.5.2.41.b Pemasangan 1 m2 atap Zincalum Warna 0.40


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.750 125,000.00 93,750.00
Kepala tukang L.11 OH 0.080 145,000.00 11,600.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 122,030.00
B BAHAN
Zincalume Gelombang Persegi 0.40(color) Lbr 1.050 83,800.00 87,990.00
Paku hak panjang 15 cm Kg 0.020 23,000.00 460.00
JUMLAH HARGA BAHAN 88,450.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 210,480.00
E Overhead & Provit 15% x D 31,572.00
F Harga Satuan Pekerjaan ( D + E ) 242,052.00

A.4.5.2.42 Pemasangan 1 m2 Atap Aluminium Gelombang 95cm x 180cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.750 125,000.00 93,750.00
Kepala tukang L.11 OH 0.080 145,000.00 11,600.00
Mandor L.15 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 122,030.00
B BAHAN
Aluminium gel Ukuran 95cmx180cm Lbr 0.750 50,000.00 37,500.00
Paku pancing Kg 0.020 23,000.00 460.00
JUMLAH HARGA BAHAN 37,960.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 159,990.00
E Overhead & Provit 15% x D 23,998.50
F Harga Satuan Pekerjaan ( D + E ) 183,988.50

A.4.5.2.43 Pemasangan 1 m’ Nok/Bubung Atap Aluminium Gelombang


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang kayu L.03 OH 1.000 125,000.00 125,000.00
Kepala tukang L.11 OH 0.100 145,000.00 14,500.00
Mandor L.15 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 157,750.00
B BAHAN
Nok standar buah 1.200 -
Paku pancing Kg 0.020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 157,750.00
E Overhead & Provit 15% x D 23,662.50
F Harga Satuan Pekerjaan ( D + E ) 181,412.50

A.4.5.2.44 Pemasangan 1 m2 Lapisan Aluminium Foil


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang kayu L.03 OH 0.050 125,000.00 6,250.00
Kepala tukang L.11 OH 0.005 145,000.00 725.00
Mandor L.15 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,965.00
B BAHAN
Aluminium foil m2 1.050 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 23,965.00
E Overhead & Provit 15% x D 3,594.75
F Harga Satuan Pekerjaan ( D + E ) 27,559.75
A.4.6.1 Harga Satuan Pekerjaan Kayu

A.4.6.1.1 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 7.000 105,000.00 735,000.00
Tukang Kayu L.03 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang L.03 OH 2.100 145,000.00 304,500.00
Mandor L.04 OH 0.350 155,000.00 54,250.00
JUMLAH TENAGA KERJA 3,718,750.00
B BAHAN
Kusen Kayu Kelas 1 (bengkirai) m3 1.100 16,000,000.00 17,600,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 17,648,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 21,367,500.00
E Overhead & Provit 15% x D (maksimum) 3,205,125.00
F Harga Satuan Pekerjaan ( D + E ) 24,572,625.00

A.4.6.1.1.a Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu belian
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 7.000 105,000.00 735,000.00
Tukang Kayu L.03 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang L.03 OH 2.100 145,000.00 304,500.00
Mandor L.04 OH 0.350 155,000.00 54,250.00
JUMLAH TENAGA KERJA 3,718,750.00
B BAHAN
Kusen Kayu Belian m3 1.100 24,000,000.00 26,400,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 26,448,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 30,167,500.00
E Overhead & Provit 15% x D (maksimum) 4,525,125.00
F Harga Satuan Pekerjaan ( D + E ) 34,692,625.00

A.4.6.1.2 Pembuatan dan pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 6.000 105,000.00 630,000.00
Tukang Kayu L.03 OH 18.000 125,000.00 2,250,000.00
Kepala Tukang L.03 OH 1.800 145,000.00 261,000.00
Mandor L.04 OH 0.300 155,000.00 46,500.00
JUMLAH TENAGA KERJA 3,187,500.00
B BAHAN
Kusen Kayu Kelas II m3 1.200 13,000,000.00 15,600,000.00
Paku 10cm kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 15,648,750.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 18,836,250.00
E Overhead & Provit 15% x D (maksimum) 2,825,437.50
F Harga Satuan Pekerjaan ( D + E ) 21,661,687.50

A.4.6.1.3 Pembuatan dan pemasangan 1m2 pintu klamp standar,kayu kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang Kayu L.03 OH 1.050 125,000.00 131,250.00
Kepala Tukang L.03 OH 0.105 145,000.00 15,225.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 186,015.00
B BAHAN
Papan kayu kelas II m3 0.040 8,300,000.00 332,000.00
Paku 5-7 cm kg 0.050 23,000.00 1,150.00
JUMLAH HARGA BAHAN 333,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 519,165.00
E Overhead & Provit 15% x D (maksimum) 77,874.75
F Harga Satuan Pekerjaan ( D + E ) 597,039.75

A.4.6.1.4 Pembuatan dan Pemasangan 1 m2 Pintu Klamp Sederhana, Kayu Kelas III
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 105,000.00 36,750.00
Tukang Kayu L.03 OH 1.050 125,000.00 131,250.00
Kepala Tukang L.03 OH 0.105 145,000.00 15,225.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 186,015.00
B BAHAN
Papan kayu kelas II m3 0.040 140,000.00 5,600.00
Paku 5-7 cm kg 0.050 8,300,000.00 415,000.00
JUMLAH HARGA BAHAN 420,600.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 606,615.00
E Overhead & Provit 15% x D (maksimum) 90,992.25
F Harga Satuan Pekerjaan ( D + E ) 697,607.25

A.4.6.1.5 Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan kayu kelas 1 (bengkirai) m3 0.040 11,188,300.00 447,532.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 457,532.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 988,782.00
E Overhead & Provit 15% x D (maksimum) 148,317.30
F Harga Satuan Pekerjaan ( D + E ) 1,137,099.30

A.4.6.1.5.a Pembuatan dan pemasangan 1m2 daun pintu panel, kayu belian
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan Kayu Belian m3 0.040 14,814,000.00 592,560.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 602,560.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,133,810.00
E Overhead & Provit 15% x D (maksimum) 170,071.50
F Harga Satuan Pekerjaan ( D + E ) 1,303,881.50
A.4.6.1.5.b Pembuatan dan pemasangan 1m2 daun pintu panel, kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan Kayu Kelas II (mabang) m3 0.040 8,300,000.00 332,000.00
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 342,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 873,250.00
E Overhead & Provit 15% x D (maksimum) 130,987.50
F Harga Satuan Pekerjaan ( D + E ) 1,004,237.50

A.4.6.1.6 Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.400 125,000.00 300,000.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 425,000.00
B BAHAN
Papan kayu kelas 1 (bengkirai) m3 0.024 11,188,300.00 268,519.20
Lem kayu kg 0.300 20,000.00 6,000.00
JUMLAH HARGA BAHAN 274,519.20
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 699,519.20
E Overhead & Provit 15% x D (maksimum) 104,927.88
F Harga Satuan Pekerjaan ( D + E ) 804,447.08

A.4.6.1.6.a Pembuatan dan pemasangan 1m2 pintu dan jendela kaca, kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.400 125,000.00 300,000.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 425,000.00
B BAHAN
Papan kayu kelas II (mabang) m3 0.024 8,300,000.00 199,200.00
Lem kayu kg 0.300 20,000.00 6,000.00
JUMLAH HARGA BAHAN 205,200.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 630,200.00
E Overhead & Provit 15% x D (maksimum) 94,530.00
F Harga Satuan Pekerjaan ( D + E ) 724,730.00

A.4.6.1.7 Pembuatan dan pemasangan 1m2 pintu dan jendela jalusi kayu kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Kayu L.03 OH 3.000 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.300 145,000.00 43,500.00
Mandor L.04 OH 0.050 155,000.00 7,750.00
JUMLAH TENAGA KERJA 531,250.00
B BAHAN
Papan kayu kelas I m3 0.064 11,188,300.00 716,051.20
Lem kayu kg 0.500 20,000.00 10,000.00
JUMLAH HARGA BAHAN 726,051.20
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,257,301.20
E Overhead & Provit 15% x D (maksimum) 188,595.18
F Harga Satuan Pekerjaan ( D + E ) 1,445,896.38

A.4.6.1.8 Pembuatan dan pemasangan 1m2 pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90cm)
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 105,000.00 73,500.00
Tukang Kayu L.03 OH 2.100 125,000.00 262,500.00
Kepala Tukang L.03 OH 0.210 145,000.00 30,450.00
Mandor L.04 OH 0.035 155,000.00 5,425.00
JUMLAH TENAGA KERJA 371,875.00
B BAHAN
Papan kayu Kelas II m3 0.025 8,300,000.00 207,500.00
Paku 1cm-2,5 cm kg 0.030 23,000.00 690.00
Lem kayu kg 0.500 20,000.00 10,000.00
Plywood tebal 4 mm ukuran (90x220) cm Lembar 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 338,190.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 710,065.00
E Overhead & Provit 15% x D (maksimum) 106,509.75
F Harga Satuan Pekerjaan ( D + E ) 816,574.75

A.4.6.1.9 Pembuatan 1m2 pintu plywood rangkap, rangka expose kayu kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.100 125,000.00 262,500.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 387,500.00
B BAHAN
Papan kayu kelas I m3 0.0256 11,188,300.00 286,420.48
Paku 1cm-2,5 cm kg 0.030 23,000.00 690.00
Lem kayu kg 0.500 20,000.00 10,000.00
Plywood tebal 4 mm ukuran (90x220) cm Lembar 1.000 120,000.00 120,000.00
JUMLAH HARGA BAHAN 417,110.48
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 804,610.48
E Overhead & Provit 15% x D (maksimum) 120,567.82
F Harga Satuan Pekerjaan ( D + E ) 925,178.30

A.4.6.1.10 Pemasangan 1m2 jalusi kusen, kayu kelas I


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.670 105,000.00 70,350.00
Tukang Kayu L.03 OH 2.000 125,000.00 250,000.00
Kepala Tukang L.03 OH 0.200 145,000.00 29,000.00
Mandor L.04 OH 0.335 155,000.00 51,925.00
JUMLAH TENAGA KERJA 401,275.00
B BAHAN
Papan kayu kelas I m3 0.060 11,188,300.00 671,298.00
Paku 1cm-2,5 cm kg 0.150 23,000.00 3,450.00
JUMLAH HARGA BAHAN 1,076,023.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 1,105,023.00
E Overhead & Provit 15% x D (maksimum) 165,753.45
F Harga Satuan Pekerjaan ( D + E ) 1,270,776.45
A.4.6.1.11 Pembuatan 1 m2 Teakwood Rangkap, Rangka Expose Kayu Kelas I
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 105,000.00 84,000.00
Tukang Kayu L.03 OH 2.400 125,000.00 300,000.00
Kepala Tukang L.03 OH 0.240 145,000.00 34,800.00
Mandor L.04 OH 0.040 155,000.00 6,200.00
JUMLAH TENAGA KERJA 425,000.00
B BAHAN
Papan Kayu m3 0.025 11,188,300.00 279,707.50
Paku 1 – 2,5 cm Kg 0.030 23,000.00 690.00
Lem kayu Kg 0.300 20,000.00 6,000.00
Teakwood 4 mm 90 x 220 cm Lembar 1.000 - -
JUMLAH HARGA BAHAN 286,397.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 321,197.50
E Overhead & Provit 15% x D (maksimum) 48,179.63
F Harga Satuan Pekerjaan ( D + E ) 369,377.13

A.4.6.1.12 Pembuatan 1 m2 Teakwood Rangkap Lapis Formika, Rangka Expose


Harga Satuan
No Kayu Kelas II Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.850 105,000.00 89,250.00
Tukang Kayu L.03 OH 2.550 125,000.00 318,750.00
Kepala Tukang L.03 OH 0.255 145,000.00 36,975.00
Mandor L.04 OH 0.043 155,000.00 6,665.00
JUMLAH TENAGA KERJA 451,640.00
B BAHAN
Papan Kayu m3 0.025 100,000.00 2,500.00
Paku 1 – 2,5 cm Kg 0.030 23,000.00 690.00
Lem kayu Kg 0.800 20,000.00 16,000.00
Teakwood 4 mm 90 x 220 cm Lembar 1.000 -
Formika 120x240 Lembar 0.500 -
JUMLAH HARGA BAHAN 19,190.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 56,165.00
E Overhead & Provit 15% x D (maksimum) 8,424.75
F Harga Satuan Pekerjaan ( D + E ) 64,589.75

A.4.6.1.13 Pemasangan 1 m3 Konstruksi Kuda-kuda Konvensional, Kayu Kelas I, II dan III Bentang Sampai Dengan 6 Meter
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 4.000 105,000.00 420,000.00
Tukang Kayu L.03 OH 12.000 125,000.00 1,500,000.00
Kepala Tukang L.03 OH 1.200 145,000.00 174,000.00
Mandor L.04 OH 0.200 155,000.00 31,000.00
JUMLAH TENAGA KERJA 2,125,000.00
B BAHAN
Balok kayu kelas II uk. 6/12 m3 1.100 11,000.00 12,100.00
Besi Strip tebal 5mm Kg 15.000 -
Paku 12 cm kg 5.600 23,000.00 128,800.00
JUMLAH HARGA BAHAN 140,900.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 2,265,900.00
E Overhead & Provit 15% x D (maksimum) 339,885.00
F Harga Satuan Pekerjaan ( D + E ) 2,605,785.00

A.4.6.1.14 Pemasangan 1m3 konstruksi kuda-kuda expose, kayu kelas I


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 6.700 105,000.00 703,500.00
Tukang Kayu L.03 OH 20.100 125,000.00 2,512,500.00
Kepala Tukang L.03 OH 2.010 145,000.00 291,450.00
Mandor L.04 OH 0.335 155,000.00 51,925.00
JUMLAH TENAGA KERJA 3,559,375.00
B BAHAN
Balok kayu kelas I uk. 5/10 m3 1.200 9,050,000.00 10,860,000.00
Besi strip tebal 5 mm kg 15.000 -
Paku 12 cm kg 5.600 23,000.00 128,800.00
JUMLAH HARGA BAHAN 10,988,800.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 14,548,175.00
E Overhead & Provit 15% x D (maksimum) 2,182,226.25
F Harga Satuan Pekerjaan ( D + E ) 16,730,401.25

A.4.6.1.15 Pemasangan 1m3 konstruksi gordeng, kayu kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 2.400 105,000.00 252,000.00
Tukang Kayu L.03 OH 7.200 125,000.00 900,000.00
Kepala Tukang L.03 OH 0.720 145,000.00 104,400.00
Mandor L.04 OH 0.120 155,000.00 18,600.00
JUMLAH TENAGA KERJA 1,275,000.00
B BAHAN
Balok kayu Kelas II Uk. 5/10 m3 1.100 3,355,000.00 3,690,500.00
Besi strip tebal 5 mm kg 15.000 - -
Paku 12 cm kg 3.000 23,000.00 69,000.00
JUMLAH HARGA BAHAN 3,759,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 5,034,500.00
E Overhead & Provit 15% x D (maksimum) 755,175.00
F Harga Satuan Pekerjaan ( D + E ) 5,789,675.00

A.4.6.1.16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Kaso-kaso 5 x 7cm m3 1.100 4,755,000.00 5,230,500.00
Reng 2 x 3 cm kg 0.0036 - -
Paku 5 dan 10 cm kg 0.250 40,000.00 10,000.00
JUMLAH HARGA BAHAN 5,240,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 5,265,725.00
E Overhead & Provit 15% x D (maksimum) 789,858.75
F Harga Satuan Pekerjaan ( D + E ) 6,055,583.75

A.4.6.1.17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu Kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.03 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 25,225.00
B BAHAN
Kaso-kaso 5 x 7cm m3 0.014 12,000.00 168.00
Reng (3 x 4) cm kg 0.0057 - -
Paku 5 dan 10 cm kg 0.250 40,000.00 10,000.00
JUMLAH HARGA BAHAN 10,168.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 35,393.00
E Overhead & Provit 15% x D (maksimum) 5,308.95
F Harga Satuan Pekerjaan ( D + E ) 40,701.95

A.4.6.1.18 Pemasangan 1m2 rangka atap sirap, kayu kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 105,000.00 12,600.00
Tukang Kayu L.03 OH 0.120 125,000.00 15,000.00
Kepala Tukang L.03 OH 0.012 145,000.00 1,740.00
Mandor L.04 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 30,270.00
B BAHAN
Kayu kelas II uk. 4/6 m3 0.165 5,070,000.00 836,550.00
Paku 5 - 10 cm m3 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 841,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 842,080.00
E Overhead & Provit 15% x D (maksimum) 126,312.00
F Harga Satuan Pekerjaan ( D + E ) 968,392.00

A.4.6.1.19 Pemasangan 1m2 rangka langit-langit (50x100) cm, kayu kelas II


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang Kayu L.03 OH 0.300 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.030 145,000.00 4,350.00
Mandor L.04 OH 0.075 155,000.00 11,625.00
JUMLAH TENAGA KERJA 69,225.00
B BAHAN
kaso-kaso 5 x7 cm m3 0.0154 4,755,000.00 73,227.00
Paku 7 cm - 10 cm Kg 0.200 23,000.00 4,600.00
JUMLAH HARGA BAHAN 77,827.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 89,452.00
E Overhead & Provit 15% x D (maksimum) 13,417.80
F Harga Satuan Pekerjaan ( D + E ) 102,869.80
A.4.6.1.20 Pemasangan 1m2 rangka langit-langit (60x60) cm, kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.03 OH 0.300 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.030 145,000.00 4,350.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 64,400.00
B BAHAN
kaso-kaso 5 x7 cm m3 0.0163 4,755,000.00 77,506.50
Paku 7 cm - 10 cm Kg 0.250 23,000.00 5,750.00
JUMLAH HARGA BAHAN 83,256.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 84,806.50
E Overhead & Provit 15% x D (maksimum) 12,720.98
F Harga Satuan Pekerjaan ( D + E ) 97,527.48

A.4.6.1.21 Pemasangan 1m' lisplank ukuran (3x20) cm, kayu kelas I


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 39,175.00
B BAHAN
Papan kayu kelas I m3 0.0108 11,188,300.00 120,833.64
Paku 5 dan 7 cm Kg 0.100 23,000.00 2,300.00
JUMLAH HARGA BAHAN 123,133.64
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 123,908.64
E Overhead & Provit 15% x D (maksimum) 18,586.30
F Harga Satuan Pekerjaan ( D + E ) 142,494.94

A.4.6.1.22 Pemasangan 1m' lisplank ukuran (3x30) cm, kayu kelas I atau Kelas 2
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.03 OH 0.200 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 39,175.00
B BAHAN
Papan kayu kelas I m3 0.011 11,188,300.00 123,071.30
Paku 5 dan 7 cm Kg 0.050 23,000.00 1,150.00
JUMLAH HARGA BAHAN 124,221.30
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 124,996.30
E Overhead & Provit 15% x D (maksimum) 18,749.45
F Harga Satuan Pekerjaan ( D + E ) 143,745.75

A.4.6.1.23 Pemasangan 1m2 rangka dinding pemisah (60x120) cm, kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Tukang Kayu L.03 OH 0.450 125,000.00 56,250.00
Kepala Tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 79,765.00
B BAHAN
Balok kayu kelas II uk. 7/7 m3 0.028 4,716,717.69 132,068.10
Paku 5 dan 7 cm Kg 0.150 23,000.00 3,450.00
JUMLAH HARGA BAHAN 135,518.10
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 136,758.10
E Overhead & Provit 15% x D (maksimum) 20,513.71
F Harga Satuan Pekerjaan ( D + E ) 157,271.81

A.4.6.1.25 Pemasangan 1m2 dinding pemisah plywood rangkap, rangka kayu kelas II
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 105,000.00 21,000.00
Tukang Kayu L.03 OH 0.600 125,000.00 75,000.00
Kepala Tukang L.03 OH 0.060 145,000.00 8,700.00
Mandor L.04 OH 0.010 155,000.00 1,550.00
JUMLAH TENAGA KERJA 106,250.00
B BAHAN
balok kayukelas II uk. 6/12 m3 0.028 4,224,000.00 118,272.00
Paku 5 dan 10 Kg 0.150 23,000.00 3,450.00
Plywood 4 mm,120 x 240 Lembar 0.860 120,000.00 103,200.00
Lem kayu Kg 0.560 20,000.00 11,200.00
JUMLAH HARGA BAHAN 236,122.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 342,372.00
E Overhead & Provit 15% x D (maksimum) 51,355.80
F Harga Satuan Pekerjaan ( D + E ) 393,727.80

A.4.6.1.26 Pemasangan 1m2 dinding lambrisering, dari papan kayu kelas I


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.600 105,000.00 63,000.00
Tukang Kayu L.03 OH 1.800 125,000.00 225,000.00
Kepala Tukang L.03 OH 0.180 145,000.00 26,100.00
Mandor L.04 OH 0.030 155,000.00 4,650.00
JUMLAH TENAGA KERJA 318,750.00
B BAHAN
Papan kayu kelas I m3 0.007 11,188,300.00 78,318.10
Paku 5 dan 10 Kg 0.100 23,000.00 2,300.00
Paku skrup 10 cm Kg 0.150 23,000.00 3,450.00
JUMLAH HARGA BAHAN 84,068.10
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 88,718.10
E Overhead & Provit 15% x D (maksimum) 13,307.72
F Harga Satuan Pekerjaan ( D + E ) 102,025.82

A.4.6.1.27 Pemasangan 1m2 dinding lambrisering, dari plywood ukuran (120x240)cm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.025 105,000.00 2,625.00
Tukang Kayu L.03 OH 0.075 125,000.00 9,375.00
Kepala Tukang L.03 OH 0.008 145,000.00 1,160.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 13,315.00
B BAHAN
Plywood 4 mm m3 0.400 120,000.00 48,000.00
Paku 1 dan 2,5 Kg 0.050 23,000.00 1,150.00
JUMLAH HARGA BAHAN 62,465.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 63,625.00
E Overhead & Provit 15% x D (maksimum) 9,543.75
F Harga Satuan Pekerjaan ( D + E ) 73,168.75

A.4.6.1.28 Pemasangan 1 m2 Dinding Bilik, Rangka Kayu Kelas III atau IV


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.03 OH 0.050 125,000.00 6,250.00
Kepala Tukang L.03 OH 0.005 145,000.00 725.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 18,250.00
B BAHAN
Bilik bambu m3 1.500 -
Kaso-kaso 5 cm x 7 cm m3 0.014 4,755,000.00 66,570.00
Paku Kg 0.012 23,000.00 276.00
List kayu 2cmx4xm m3 0.003 -
JUMLAH HARGA BAHAN 66,846.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 67,571.00
E Overhead & Provit 15% x D (maksimum) 10,135.65
F Harga Satuan Pekerjaan ( D + E ) 77,706.65
A.4.6.2 Harga Satuan Pekerjaan Kunci dan Kaca

A.4.6.2.1 Pemasangan 1 buah kunci silinder


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 105,000.00 6,300.00
Tukang Kayu L.02 OH 0.600 125,000.00 75,000.00
Kepala Tukang L.03 OH 0.060 145,000.00 8,700.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 90,465.00
B BAHAN
Kunci tanam antik buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 90,465.00
E Overhead & Provit 15% x D (maksimum) 13,569.75
F Harga Satuan Pekerjaan ( D + E ) 104,034.75

A.4.6.2.2 Pemasangan 1 Buah Kunci Tanam Biasa


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 105,000.00 1,050.00
Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 71,575.00
B BAHAN
Kunci tanam biasa buah 1.000 230,000.00 230,000.00
JUMLAH HARGA BAHAN 230,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 301,575.00
E Overhead & Provit 15% x D (maksimum) 45,236.25
F Harga Satuan Pekerjaan ( D + E ) 346,811.25

A.4.6.2.3 Pemasangan 1 Buah Kunci Tanam Kamar Mandi


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.005 105,000.00 525.00
Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 70,740.00
B BAHAN
Kunci tanam KM buah 1.000 150,000.00 150,000.00
JUMLAH HARGA BAHAN 150,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 220,740.00
E Overhead & Provit 15% x D (maksimum) 33,111.00
F Harga Satuan Pekerjaan ( D + E ) 253,851.00

A.4.6.2.4 Pemasangan 1 buah kunci silinder


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.005 105,000.00 525.00
Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 70,740.00
B BAHAN
Kunci silinder buah 1.000 78,800.00 78,800.00
JUMLAH HARGA BAHAN 78,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 149,540.00
E Overhead & Provit 15% x D (maksimum) 22,431.00
F Harga Satuan Pekerjaan ( D + E ) 171,971.00

A.4.6.2.5 Pemasangan 1 buah engsel pintu


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 22,624.00
B BAHAN
Engsel pintu buah 1.000 29,000.00 29,000.00
JUMLAH HARGA BAHAN 29,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 51,624.00
E Overhead & Provit 15% x D (maksimum) 7,743.60
F Harga Satuan Pekerjaan ( D + E ) 59,367.60
A.4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 105,000.00 1,050.00
Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.0005 155,000.00 77.50
JUMLAH TENAGA KERJA 15,077.50
B BAHAN
Engsel kupu-kupu buah 1.000 18,800.00 18,800.00
JUMLAH HARGA BAHAN 18,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 33,877.50
E Overhead & Provit 15% x D (maksimum) 5,081.63
F Harga Satuan Pekerjaan ( D + E ) 38,959.13

A.4.6.2.7 Pemasangan 1 Buah Engsel Angin


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Tukang Kayu L.02 OH 0.200 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.0005 155,000.00 77.50
JUMLAH TENAGA KERJA 38,477.50
B BAHAN
Engsel angin buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 38,477.50
E Overhead & Provit 15% x D (maksimum) 5,771.63
F Harga Satuan Pekerjaan ( D + E ) 44,249.13

A.4.6.2.8 Pemasangan 1 Buah Spring Knip untuk Jendela


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,740.00
B BAHAN
Spring knip buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 23,740.00
E Overhead & Provit 15% x D (maksimum) 3,561.00
F Harga Satuan Pekerjaan ( D + E ) 27,301.00

A.4.6.2.9 Pemasangan 1 buah kait angin


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,740.00
B BAHAN
Kait angin buah 1.000 14,400.00 14,400.00
JUMLAH HARGA BAHAN 14,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 38,140.00
E Overhead & Provit 15% x D (maksimum) 5,721.00
F Harga Satuan Pekerjaan ( D + E ) 43,861.00

A.4.6.2.10 Pemasangan 1 buah door closer


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 105,000.00 5,250.00
Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 75,465.00
B BAHAN
Door closer set 1.000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 325,465.00
E Overhead & Provit 15% x D (maksimum) 48,819.75
F Harga Satuan Pekerjaan ( D + E ) 374,284.75
A.4.6.2.11 Pemasangan 1 buah kunci slot
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang Kayu L.02 OH 0.200 125,000.00 25,000.00
Kepala Tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.001 155,000.00 155.00
JUMLAH TENAGA KERJA 30,155.00
B BAHAN
Kunci slot buah 1.000 18,900.00 18,900.00
JUMLAH HARGA BAHAN 18,900.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 29,055.00
E Overhead & Provit 15% x D (maksimum) 4,358.25
F Harga Satuan Pekerjaan ( D + E ) 33,413.25

A.4.6.2.12 Pemasangan 1 Buah Doorholder


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 105,000.00 5,250.00
Tukang Kayu L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 75,465.00
B BAHAN
Door holder buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A + B + C) 29,055.00
E Overhead & Provit 15% x D (maksimum) 4,358.25
F Harga Satuan Pekerjaan ( D + E ) 33,413.25

A.4.6.2.13 Pemasangan 1 buah door stop


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 105,000.00 1,050.00
Tukang Kayu L.02 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 15,775.00
B BAHAN
Door stop buah 1.000 88,750.00 88,750.00
JUMLAH HARGA BAHAN 88,750.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 104,525.00
E Overhead & Provit 15% x D (maksimum) 15,678.75
F Harga Satuan Pekerjaan ( D + E ) 120,203.75

A.4.6.2.14 Pemasangan 1 Buah Rel Pintu Dorong


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 105,000.00 6,300.00
Tukang Kayu L.02 OH 0.600 125,000.00 75,000.00
Kepala Tukang L.03 OH 0.060 145,000.00 8,700.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 90,465.00
B BAHAN
Rel pintu sorong buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 90,465.00
E Overhead & Provit 15% x D (maksimum) 13,569.75
F Harga Satuan Pekerjaan ( D + E ) 104,034.75

A.4.6.2.15 Pemasangan 1 Buah Kunci Lemari


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.025 105,000.00 2,625.00
Tukang Kayu L.02 OH 0.250 125,000.00 31,250.00
Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
Mandor L.04 OH 0.001 155,000.00 201.50
JUMLAH TENAGA KERJA 37,701.50
B BAHAN
Rel pintu sorong buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 37,701.50
E Overhead & Provit 15% x D (maksimum) 5,655.23
F Harga Satuan Pekerjaan ( D + E ) 43,356.73
A.4.6.2.16 Pemasangan 1 m2 Kaca Polos Tebal 3 mm
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 22,624.00
B BAHAN
Kaca Tebal 3mm m2 1.100 -
Silicone Sealant 300 ml buah 0.050 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 22,624.00
E Overhead & Provit 15% x D (maksimum) 3,393.60
F Harga Satuan Pekerjaan ( D + E ) 26,017.60

A.4.6.2.17 Pemasangan 1m2 kaca tebal 5 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.0008 155,000.00 124.00
JUMLAH TENAGA KERJA 22,624.00
B BAHAN
Kaca tebal 5 mm m2 1.100 200,000.00 220,000.00
Sealant kg 0.050 35,000.00 1,750.00
JUMLAH HARGA BAHAN 221,750.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 244,374.00
E Overhead & Provit 15% x D (maksimum) 36,656.10
F Harga Satuan Pekerjaan ( D + E ) 281,030.10

A.4.6.2.18 Pemasangan 1m2 kaca tebal 8 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.017 105,000.00 1,785.00
Tukang Kayu L.02 OH 0.170 125,000.00 21,250.00
Kepala Tukang L.03 OH 0.017 145,000.00 2,465.00
Mandor L.04 OH 0.0009 155,000.00 139.50
JUMLAH TENAGA KERJA 25,639.50
B BAHAN
Kaca tebal 8 mm m2 1.100 398,000.00 437,800.00
Sealant kg 0.07 35,000.00 2,450.00
JUMLAH HARGA BAHAN 440,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 465,889.50
E Overhead & Provit 15% x D (maksimum) 69,883.43
F Harga Satuan Pekerjaan ( D + E ) 535,772.93

A.4.6.2.19 Pemasangan 1m2 kaca buram tebal 12 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.025 105,000.00 2,625.00
Tukang Kayu L.02 OH 0.250 125,000.00 31,250.00
Kepala Tukang L.03 OH 0.025 145,000.00 3,625.00
Mandor L.04 OH 0.0013 155,000.00 201.50
JUMLAH TENAGA KERJA 37,701.50
B BAHAN
Kaca buram tebal 12 mm m2 1.100 640,000.00 704,000.00
Sealant kg 0.070 35,000.00 2,450.00
JUMLAH HARGA BAHAN 706,450.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 744,151.50
E Overhead & Provit 15% x D (maksimum) 111,622.73
F Harga Satuan Pekerjaan ( D + E ) 855,774.23

A.4.6.2.20 Pemasangan 1m2 kaca cermin tebal 5 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,740.00
B BAHAN
Kaca cermin 5 mm m2 1.100 418,000.00 459,800.00
JUMLAH HARGA BAHAN 459,800.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A + B + C) 483,540.00
E Overhead & Provit 15% x D (maksimum) 72,531.00
F Harga Satuan Pekerjaan ( D + E ) 556,071.00

A.4.6.2.22 Pemasangan 1 m2 Kaca Cermin Tebal 8 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.017 105,000.00 1,785.00
Tukang Kayu L.02 OH 0.170 125,000.00 21,250.00
Kepala Tukang L.03 OH 0.017 145,000.00 2,465.00
Mandor L.04 OH 0.009 155,000.00 1,395.00
JUMLAH TENAGA KERJA 26,895.00
B BAHAN
Kaca cermin 8 mm m2 1.100 398,000.00 437,800.00
JUMLAH HARGA BAHAN 437,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 464,695.00
E Overhead & Provit 15% x D (maksimum) 69,704.25
F Harga Satuan Pekerjaan ( D + E ) 534,399.25

A.4.6.2.23 Pemasangan 1 m2 Kaca Cermin Tebal 8 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 105,000.00 1,575.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 23,740.00
B BAHAN
Kaca wireglassed 5 mm m2 1.100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 23,740.00
E Overhead & Provit 15% x D (maksimum) 3,561.00
F Harga Satuan Pekerjaan ( D + E ) 27,301.00

A.4.6.2.24 Pemasangan 1 m2 Kaca Patri Tebal 5 mm


Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.075 105,000.00 7,875.00
Tukang Kayu L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 29,420.00
B BAHAN
Kaca wireglassed 5 mm m2 1.100 -
Silicone Sealant 300 ml tube 0.050
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 29,420.00
E Overhead & Provit 15% x D (maksimum) 4,413.00
F Harga Satuan Pekerjaan ( D + E ) 33,833.00
A.4.7.1 Harga Satuan Pekerjaan Pengecatan

A.4.7.1.1 1m2 Pengikisan/ pengerokan permukaan cat lama


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 16,215.00
B BAHAN
Soda api Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 1,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 17,465.00
E Overhead & Provit 15% x D (maksimum) 2,616.00
F Harga Satuan Pekerjaan ( D + E ) 20,081.00

A.4.7.1.2 1m2 Pencucian bidang permukaan tembok yang pernah di cat


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 16,215.00
B BAHAN
Sabun Kg 0.050 15,700.00 785.00
JUMLAH HARGA BAHAN 785.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 17,000.00
E Overhead & Provit 15% x D (maksimum) 2,550.00
F Harga Satuan Pekerjaan ( D + E ) 19,550.00

A.4.7.1.3 1m2 Pengerokan karat pada permukaan baja cara manual


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.008 155,000.00 1,240.00
JUMLAH TENAGA KERJA 16,990.00
B BAHAN
Sabun Kg 0.050 15,700.00 785.00
JUMLAH HARGA BAHAN 785.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 17,775.00
E Overhead & Provit 15% x D (maksimum) 2,666.25
F Harga Satuan Pekerjaan ( D + E ) 20,441.25
A.4.7.1.4 1m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang cat L.02 OH 0.009 125,000.00 1,125.00
Kepala tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,810.00
B BAHAN
Cat menie Kg 0.200 52,000.00 10,400.00
Plamuur Kg 0.150 31,500.00 4,725.00
Cat dasar Kg 0.170 70,000.00 11,900.00
Cat penutup Kg 0.260 100,000.00 26,000.00
Kuas buah 0.010 25,000.00 250.00
Pengencer Kg 0.030 25,000.00 750.00
Ampelas Lbr 0.200 4,000.00 800.00
JUMLAH HARGA BAHAN 54,825.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 64,635.00
E Overhead & Provit 15% x D (maksimum) 9,695.25
F Harga Satuan Pekerjaan ( D + E ) 74,330.25

A.4.7.1.5 1m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.070 105,000.00 7,350.00
Tukang cat L.02 OH 0.105 125,000.00 13,125.00
Kepala tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 21,520.00
B BAHAN
Cat menie Kg 0.200 52,000.00 10,400.00
Plamuur Kg 0.150 31,500.00 4,725.00
Cat dasar Kg 0.170 70,000.00 11,900.00
Cat penutup Kg 0.350 100,000.00 35,000.00
Kuas buah 0.010 25,000.00 250.00
Pengencer Kg 0.030 25,000.00 750.00
Ampelas Lbr 0.200 4,000.00 800.00
JUMLAH HARGA BAHAN 63,825.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 85,345.00
E Overhead & Provit 15% x D (maksimum) 12,801.75
F Harga Satuan Pekerjaan ( D + E ) 98,146.75
A.4.7.1.6 Pelaburan 1m2 bidang kayu dengan teak oil
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 105,000.00 4,200.00
Tukang cat L.02 OH 0.630 125,000.00 78,750.00
Kepala tukang L.03 OH 0.063 145,000.00 9,135.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 92,550.00
B BAHAN
Teak oil L 0.360 60,000.00 21,600.00
JUMLAH HARGA BAHAN 21,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 114,150.00
E Overhead & Provit 15% x D (maksimum) 17,122.50
F Harga Satuan Pekerjaan ( D + E ) 131,272.50

A.4.7.1.7 Pelaburan 1m2 bidang kayu dengan polintur


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.040 105,000.00 4,200.00
Tukang cat L.02 OH 0.060 125,000.00 7,500.00
Kepala tukang L.03 OH 0.160 145,000.00 23,200.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 35,365.00
B BAHAN
Polintur L 0.150 64,000.00 9,600.00
Polintur jadi L 0.372 64,000.00 23,808.00
Ampelas Lbr 2.000 4,000.00 8,000.00
JUMLAH HARGA BAHAN 41,408.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 76,773.00
E Overhead & Provit 15% x D (maksimum) 11,515.95
F Harga Satuan Pekerjaan ( D + E ) 88,288.95

A.4.7.1.8 Pelaburan 1m2 bidang kayu cat residu dan ter


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.006 155,000.00 930.00
JUMLAH TENAGA KERJA 11,430.00
B BAHAN
Residu atau ter L 0.350 58,400.00 20,440.00
JUMLAH HARGA BAHAN 20,440.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 31,870.00
E Overhead & Provit 15% x D (maksimum) 4,780.50
F Harga Satuan Pekerjaan ( D + E ) 36,650.50
A.4.7.1.9 Pelaburan 1m2 bidang kayu dengan vernis
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.160 105,000.00 16,800.00
Tukang cat L.02 OH 0.160 125,000.00 20,000.00
Kepala tukang L.03 OH 0.016 145,000.00 2,320.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 39,585.00
B BAHAN
Vernis L 0.150 45,000.00 6,750.00
Dempul Kg 0.050 31,500.00 1,575.00
Ampelas Lbr 0.100 4,000.00 400.00
JUMLAH HARGA BAHAN 8,725.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 48,310.00
E Overhead & Provit 15% x D (maksimum) 7,246.50
F Harga Satuan Pekerjaan ( D + E ) 55,556.50

A.4.7.1.10 1m2 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup Kg 0.260 28,000.00 7,280.00
JUMLAH HARGA BAHAN 13,130.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 24,483.50
E Overhead & Provit 15% x D (maksimum) 3,672.53
F Harga Satuan Pekerjaan ( D + E ) 28,156.03

A.4.7.1.10.a 1m2 Pengecatan tembok baru Interior (setara Mowilex)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup (setara mowilex) Kg 0.260 100,000.00 26,000.00
JUMLAH HARGA BAHAN 31,850.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 43,203.50
E Overhead & Provit 15% x D (maksimum) 6,480.53
F Harga Satuan Pekerjaan ( D + E ) 49,684.03
A.4.7.1.10.b 1m2 Pengecatan tembok baru Exterior (setara Mowilex)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar (setara mowilex) Kg 0.100 27,000.00 2,700.00
Cat penutup (setara mowilex) Kg 0.260 120,000.00 31,200.00
JUMLAH HARGA BAHAN 37,050.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 48,403.50
E Overhead & Provit 15% x D (maksimum) 7,260.53
F Harga Satuan Pekerjaan ( D + E ) 55,664.03

A.4.7.1.10.c 1m2 Pengecatan tembok baru Interior (setara Dulux)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup (setara dulux) Kg 0.260 104,000.00 27,040.00
JUMLAH HARGA BAHAN 32,890.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 44,243.50
E Overhead & Provit 15% x D (maksimum) 6,636.53
F Harga Satuan Pekerjaan ( D + E ) 50,880.03

A.4.7.1.10.d 1m2 Pengecatan tembok baru Exterior (setara Dulux)


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Plamuur Kg 0.100 31,500.00 3,150.00
Cat dasar Kg 0.100 27,000.00 2,700.00
Cat penutup (setara dulux) Kg 0.260 115,000.00 29,900.00
JUMLAH HARGA BAHAN 35,750.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 47,103.50
E Overhead & Provit 15% x D (maksimum) 7,065.53
F Harga Satuan Pekerjaan ( D + E ) 54,169.03
A.4.7.1.10.e 1m2 Pengecatan tembok baru Acian Exterior (setara Dulux)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.063 125,000.00 7,875.00
Kepala tukang L.03 OH 0.0063 145,000.00 913.50
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 11,353.50
B BAHAN
Cat dasar Alkali Kg 0.100 140,000.00 14,000.00
Cat penutup (setara dulux) Kg 0.260 115,000.00 29,900.00
JUMLAH HARGA BAHAN 43,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 55,253.50
E Overhead & Provit 15% x D (maksimum) 8,288.03
F Harga Satuan Pekerjaan ( D + E ) 63,541.53

A.4.7.1.11 1m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Interior setara Vinilex
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat dasar Kg 0.120 27,000.00 3,240.00
Cat penutup Kg 0.180 28,000.00 5,040.00
JUMLAH HARGA BAHAN 8,280.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 17,544.00
E Overhead & Provit 15% x D (maksimum) 2,631.60
F Harga Satuan Pekerjaan ( D + E ) 20,175.60

A.4.7.1.11.a 1m2 Pengecatan tembok lama Interior setara Mowilex


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat penutup (setara mowilex) Kg 0.180 100,000.00 18,000.00
JUMLAH HARGA BAHAN 18,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 27,264.00
E Overhead & Provit 15% x D (maksimum) 4,089.60
F Harga Satuan Pekerjaan ( D + E ) 31,353.60
A.4.7.1.11.b 1m2 Pengecatan tembok lama Exterior setara Mowilex
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat penutup (setara mowilex) Kg 0.180 120,000.00 21,600.00
JUMLAH HARGA BAHAN 21,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 30,864.00
E Overhead & Provit 15% x D (maksimum) 4,629.60
F Harga Satuan Pekerjaan ( D + E ) 35,493.60

A.4.7.1.11.c 1m2 Pengecatan tembok lama Interior setara Dulux


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat penutup (setara dulux) Kg 0.180 104,000.00 18,720.00
JUMLAH HARGA BAHAN 18,720.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 27,984.00
E Overhead & Provit 15% x D (maksimum) 4,197.60
F Harga Satuan Pekerjaan ( D + E ) 32,181.60

A.4.7.1.11.d 1m2 Pengecatan tembok lama Exterior setara Dulux


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.028 105,000.00 2,940.00
Tukang cat L.02 OH 0.042 125,000.00 5,250.00
Kepala tukang L.03 OH 0.0042 145,000.00 609.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 9,264.00
B BAHAN
Cat penutup (setara dulux) Kg 0.180 115,000.00 20,700.00
JUMLAH HARGA BAHAN 20,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 29,964.00
E Overhead & Provit 15% x D (maksimum) 4,494.60
F Harga Satuan Pekerjaan ( D + E ) 34,458.60
A.4.7.1.16 Pengecatan 1m2 permukaan baja dengan menie besi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.020 105,000.00 2,100.00
Tukang cat L.02 OH 0.200 125,000.00 25,000.00
Kepala tukang L.03 OH 0.020 145,000.00 2,900.00
Mandor L.04 OH 0.0025 155,000.00 387.50
JUMLAH TENAGA KERJA 30,387.50
B BAHAN
Menie besi Kg 0.100 52,000.00 5,200.00
Kwas Lbr 0.010 25,000.00 250.00
JUMLAH HARGA BAHAN 5,450.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 35,837.50
E Overhead & Provit 15% x D (maksimum) 5,375.63
F Harga Satuan Pekerjaan ( D + E ) 41,213.13

A.4.7.1.22 Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis Cat Terakhir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 105,000.00 42,000.00
Tukang cat L.02 OH 0.700 125,000.00 87,500.00
Kepala tukang L.03 OH 0.070 145,000.00 10,150.00
Mandor L.04 OH 0.02 155,000.00 3,100.00
JUMLAH TENAGA KERJA 142,750.00
B BAHAN
Cat dasar Kg 0.300 70,000.00 21,000.00
Pengencer Lbr 0.010 25,000.00 250.00
JUMLAH HARGA BAHAN 21,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 164,000.00
E Overhead & Provit 15% x D (maksimum) 24,600.00
F Harga Satuan Pekerjaan ( D + E ) 188,600.00
A.5.1.1 Harga Satuan Pekerjaan Sanitasi dan Perpipaan Dalam Gedung

A.5.1.1.1 Pemasangan 1 Buah Closet Duduk/Monoblock


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.075 105,000.00 7,875.00
Tukang Pipa L.02 OH 0.150 125,000.00 18,750.00
Kepala Tukang L.03 OH 0.015 145,000.00 2,175.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 29,420.00
B BAHAN
Closet duduk Unit 1.000 2,246,800.00 2,246,800.00
Perlengkapan Ls 6% x closet 2,246,800.00 134,808.00
JUMLAH HARGA BAHAN 2,246,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 2,276,220.00
E Overhead & Provit 15% x D (maksimum) 341,433.00
F Harga Satuan Pekerjaan ( D + E ) 2,617,653.00

A.5.1.1.2 Pemasangan 1 Buah Closet Jongkok Porselen


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Pipa L.02 OH 1.500 125,000.00 187,500.00
Kepala Tukang L.03 OH 0.150 145,000.00 21,750.00
Mandor L.04 OH 0.16 155,000.00 24,800.00
JUMLAH TENAGA KERJA 339,050.00
B BAHAN
Closet jongkok Unit 1.000 200,000.00 200,000.00
Pasangan bata 1PC:3PS Ls 0.036 2,000.00 72.00
JUMLAH HARGA BAHAN 200,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 539,050.00
E Overhead & Provit 15% x D (maksimum) 80,857.50
F Harga Satuan Pekerjaan ( D + E ) 619,907.50

A.5.1.1.3 Pemasangan 1 Buah Closet Jongkok Teraso


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Pipa L.02 OH 1.500 125,000.00 187,500.00
Kepala Tukang L.03 OH 0.150 145,000.00 21,750.00
Mandor L.04 OH 0.16 155,000.00 24,800.00
JUMLAH TENAGA KERJA 339,050.00
B BAHAN
Closet jongkok Unit 1.000 330,000.00 330,000.00
Pas. Bata 1PC:PS Ls 0.036 2,000.00 72.00
JUMLAH HARGA BAHAN 330,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 669,050.00
E Overhead & Provit 15% x D (maksimum) 100,357.50
F Harga Satuan Pekerjaan ( D + E ) 769,407.50

A.5.1.1.4 Pemasangan 1 Buah Urinoir


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Pipa L.02 OH 1.000 125,000.00 125,000.00
Kepala Tukang L.03 OH 0.100 145,000.00 14,500.00
Mandor L.04 OH 0.05 155,000.00 7,750.00
JUMLAH TENAGA KERJA 252,250.00
B BAHAN
Urinoir Lengkap Unit 1.000 2,000,000.00 2,000,000.00
Semen Portland Kg 6.000 1,500.00 9,000.00
Pasir pasang M3 0.010 125,000.00 1,250.00
JUMLAH HARGA BAHAN 2,010,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 2,262,500.00
E Overhead & Provit 15% x D (maksimum) 339,375.00
F Harga Satuan Pekerjaan ( D + E ) 2,601,875.00

A.5.1.1.5 Pemasangan 1 Buah Wastafel


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.000 105,000.00 105,000.00
Tukang Pipa L.02 OH 1.000 125,000.00 125,000.00
Kepala Tukang L.03 OH 0.100 145,000.00 14,500.00
Mandor L.04 OH 0.05 155,000.00 7,750.00
JUMLAH TENAGA KERJA 252,250.00
B BAHAN
Wastafel Lengkap Unit 1.200 1,000,000.00 1,200,000.00
Semen Portland Kg 6.000 1,500.00 9,000.00
Pasir pasang M3 0.010 125,000.00 1,250.00
JUMLAH HARGA BAHAN 1,210,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 1,462,500.00
E Overhead & Provit 15% x D (maksimum) 219,375.00
F Harga Satuan Pekerjaan ( D + E ) 1,681,875.00

A.5.1.1.6 Pemasangan 1 Buah Bak Mandi Teraso Volume 0,30 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.000 105,000.00 315,000.00
Tukang Pipa L.02 OH 4.500 125,000.00 562,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.9 155,000.00 139,500.00
JUMLAH TENAGA KERJA 1,024,250.00
B BAHAN
Bak Teraso Unit 1.000 -
Perlengkapan Ls 12% x bak - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 1,024,250.00
E Overhead & Provit 15% x D (maksimum) 153,637.50
F Harga Satuan Pekerjaan ( D + E ) 1,177,887.50

A.5.1.1.7 Pemasangan 1 Buah Bak Fibreglass Volume 0.3 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.000 105,000.00 315,000.00
Tukang Pipa L.02 OH 4.500 125,000.00 562,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.9 155,000.00 139,500.00
JUMLAH TENAGA KERJA 1,024,250.00
B BAHAN
Bak fibreglass Unit 1.000 -
Perlengkapan Ls 12% x bak - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 1,024,250.00
E Overhead & Provit 15% x D (maksimum) 153,637.50
F Harga Satuan Pekerjaan ( D + E ) 1,177,887.50

A.5.1.1.8 Pemasangan 1buah Bak Mandi Pasangan Bata Volume 0,30 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 6.00 105,000.00 630,000.00
Tukang Pipa L.02 OH 3.00 125,000.00 375,000.00
Kepala Tukang L.03 OH 0.30 145,000.00 43,500.00
Mandor L.04 OH 0.30 155,000.00 46,500.00
JUMLAH TENAGA KERJA 1,095,000.00
B BAHAN
Bata Merah Buah 150.000 2,000.00 300,000.00
Semen portlan Kg 120.000 1,500.00 180,000.00
Pasir Pasang m3 0.300 125,000.00 37,500.00
Porselen 11x11 Buah 360.000 3,460.00 1,245,600.00
JUMLAH HARGA BAHAN 1,763,100.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 2,858,100.00
E Overhead & Provit 15% x D (maksimum) 428,715.00
F Harga Satuan Pekerjaan ( D + E ) 3,286,815.00

A.5.1.1.9 Pemasangan 1 Buah Bathtub Porselen


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.075 105,000.00 7,875.00
Tukang Pipa L.02 OH 0.750 125,000.00 93,750.00
Kepala Tukang L.03 OH 0.075 145,000.00 10,875.00
Mandor L.04 OH 0.075 155,000.00 11,625.00
JUMLAH TENAGA KERJA 124,125.00
B BAHAN
Bathtub Buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 124,125.00
E Overhead & Provit 15% x D (maksimum) 18,618.75
F Harga Satuan Pekerjaan ( D + E ) 142,743.75

A.5.1.1.10 Pemasangan 1 buah Bak Beton volume 1 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.500 105,000.00 367,500.00
Tukang Pipa L.02 OH 4.500 125,000.00 562,500.00
Kepala Tukang L.03 OH 0.050 145,000.00 7,250.00
Mandor L.04 OH 0.018 155,000.00 2,790.00
JUMLAH TENAGA KERJA 940,040.00
B BAHAN
Beton 1:2:3 m3 0.900 -
Baja tulangan Kg 180.000 13,500.00 2,430,000.00
Kayu bekisting m2 8.000 -
Ubin porselen 20x20cm buah 500.000 3,920.00 1,960,000.00
JUMLAH HARGA BAHAN 4,390,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 5,330,040.00
E Overhead & Provit 15% x D (maksimum) 799,506.00
F Harga Satuan Pekerjaan ( D + E ) 6,129,546.00

A.5.1.1.11 Pemasangan 1 Buah Bak Air Fibreglass Volume 1 m3


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 105,000.00 31,500.00
Tukang Pipa L.02 OH 0.450 125,000.00 56,250.00
Kepala Tukang L.03 OH 0.045 145,000.00 6,525.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 96,600.00
B BAHAN
Bak air fibreglass Unit 1.000 300,000.00 300,000.00
Perlengkapan Kg 12% x Bak 300,000.00 36,000.00
JUMLAH HARGA BAHAN 336,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 432,600.00
E Overhead & Provit 15% x D (maksimum) 64,890.00
F Harga Satuan Pekerjaan ( D + E ) 497,490.00

A.5.1.1.16 Pemasangan 1 buah Bak Kontrol Pasangan Bata 30 x 30 cm Tinggi 35 cm dengan Tutup Beton
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 2.160 105,000.00 226,800.00
Tukang Pipa L.02 OH 0.720 125,000.00 90,000.00
Kepala Tukang L.03 OH 0.072 145,000.00 10,440.00
Mandor L.04 OH 0.011 155,000.00 1,705.00
JUMLAH TENAGA KERJA 328,945.00
B BAHAN
Bata Merah buah 40.000 2,000.00 80,000.00
Semen Portlan Kg 44.000 1,500.00 66,000.00
Pasir Pasang m3 0.070 125,000.00 8,750.00
Pasir Beton m3 0.060 75,000.00 4,500.00
Kerikil m3 0.070 435,000.00 30,450.00
Baja Tulangan Kg 1.600 13,500.00 21,600.00
JUMLAH HARGA BAHAN 211,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 540,245.00
E Overhead & Provit 15% x D (maksimum) 81,036.75
F Harga Satuan Pekerjaan ( D + E ) 621,281.75

A.5.1.1.17 Pemasangan 1 buah Bak Kontrol Pasangan Bata 45cm x 45cm tinggi 50 cm dengan Tutup Beton
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.200 105,000.00 336,000.00
Tukang Pipa L.02 OH 1.150 125,000.00 143,750.00
Kepala Tukang L.03 OH 0.011 145,000.00 1,595.00
Mandor L.04 OH 0.016 155,000.00 2,480.00
JUMLAH TENAGA KERJA 483,825.00
B BAHAN
Bata Merah buah 70.000 11,600.00 812,000.00
Semen Portlan Kg 77.000 1,500.00 115,500.00
Pasir Pasang m3 0.130 125,000.00 16,250.00
Pasir Beton m3 0.090 155,000.00 13,950.00
Kerikil m3 0.020 20,000.00 400.00
Baja Tulangan Kg 2.600 13,500.00 35,100.00
JUMLAH HARGA BAHAN 993,200.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 1,477,025.00
E Overhead & Provit 15% x D (maksimum) 221,553.75
F Harga Satuan Pekerjaan ( D + E ) 1,698,578.75

A.5.1.1.18 Pemasangan 1 buah Bak Kontrol Pasangan Bata 60cm x 60cm Tinggi 65 cm dengan Tutup Beton
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 3.200 105,000.00 336,000.00
Tukang Pipa L.02 OH 1.150 125,000.00 143,750.00
Kepala Tukang L.03 OH 0.011 145,000.00 1,595.00
Mandor L.04 OH 0.016 155,000.00 2,480.00
JUMLAH TENAGA KERJA 483,825.00
B BAHAN
Bata Merah buah 123.000 2,000.00 246,000.00
Semen Portlan Kg 114.000 1,500.00 171,000.00
Pasir Pasang m3 0.184 125,000.00 23,000.00
Pasir Beton m3 0.120 1,620,000.00 194,400.00
Kerikil m3 0.033 1,194,050.00 39,403.65
Baja Tulangan Kg 4.850 13,500.00 65,475.00
JUMLAH HARGA BAHAN 739,278.65
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 1,223,103.65
E Overhead & Provit 15% x D (maksimum) 183,465.55
F Harga Satuan Pekerjaan ( D + E ) 1,406,569.20

A.5.1.1.19 Pemasangan 1 m’ Pipa Galvanis Diameter ½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 105,000.00 5,670.00
Tukang Pipa L.02 OH 0.090 125,000.00 11,250.00
Kepala Tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.027 155,000.00 4,185.00
JUMLAH TENAGA KERJA 22,410.00
B BAHAN
Pipa galvanis ½” m 1.200 38,333.33 46,000.00
Perlengkapan Kg 35% x pipa 38,333.33 13,416.67
JUMLAH HARGA BAHAN 59,416.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 81,826.67
E Overhead & Provit 15% x D (maksimum) 12,274.00
F Harga Satuan Pekerjaan ( D + E ) 94,100.67

A.5.1.1.20 Pemasangan 1 m’ Pipa Galvanis Diameter ¾ ”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 105,000.00 5,670.00
Tukang Pipa L.02 OH 0.090 125,000.00 11,250.00
Kepala Tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.027 155,000.00 4,185.00
JUMLAH TENAGA KERJA 22,410.00
B BAHAN
Pipa galvanis 3/4” m 1.200 31,666.67 38,000.00
Perlengkapan Kg 35% x pipa 31,666.67 11,083.33
JUMLAH HARGA BAHAN 49,083.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 71,493.33
E Overhead & Provit 15% x D (maksimum) 10,724.00
F Harga Satuan Pekerjaan ( D + E ) 82,217.33

A.5.1.1.21 Pemasangan 1 m’ Pipa Galvanis Diameter 1”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 105,000.00 5,670.00
Tukang Pipa L.02 OH 0.090 125,000.00 11,250.00
Kepala Tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.027 155,000.00 4,185.00
JUMLAH TENAGA KERJA 22,410.00
B BAHAN
Pipa galvanis 1” m 1.200 54,166.67 65,000.00
Perlengkapan Kg 35% x pipa 54,166.67 18,958.33
JUMLAH HARGA BAHAN 83,958.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 106,368.33
E Overhead & Provit 15% x D (maksimum) 15,955.25
F Harga Satuan Pekerjaan ( D + E ) 122,323.58

A.5.1.1.22 Pemasangan 1 m’ Pipa Galvanis Diameter 1 ½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.108 105,000.00 11,340.00
Tukang Pipa L.02 OH 0.180 125,000.00 22,500.00
Kepala Tukang L.03 OH 0.018 145,000.00 2,610.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 37,225.00
B BAHAN
Pipa galvanis 1” m 1.200 77,500.00 93,000.00
Perlengkapan Kg 35% x pipa 77,500.00 27,125.00
JUMLAH HARGA BAHAN 120,125.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 157,350.00
E Overhead & Provit 15% x D (maksimum) 23,602.50
F Harga Satuan Pekerjaan ( D + E ) 180,952.50

A.5.1.1.23 Pemasangan 1 m’ Pipa Galvanis Diameter 3”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.135 105,000.00 14,175.00
Tukang Pipa L.02 OH 0.225 125,000.00 28,125.00
Kepala Tukang L.03 OH 0.023 145,000.00 3,335.00
Mandor L.04 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 46,720.00
B BAHAN
Pipa galvanis 3” m 1.200 169,166.67 203,000.00
Perlengkapan Kg 35% x pipa 169,166.67 59,208.33
JUMLAH HARGA BAHAN 262,208.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 308,928.33
E Overhead & Provit 15% x D (maksimum) 46,339.25
F Harga Satuan Pekerjaan ( D + E ) 355,267.58

A.5.1.1.24 Pemasangan 1 m’ Pipa Galvanis Diameter 3”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.135 105,000.00 14,175.00
Tukang Pipa L.02 OH 0.225 125,000.00 28,125.00
Kepala Tukang L.03 OH 0.023 145,000.00 3,335.00
Mandor L.04 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 46,720.00
B BAHAN
Pipa galvanis 4” m 1.200 244,166.67 293,000.00
Perlengkapan Kg 35% x pipa 244,166.67 85,458.33
JUMLAH HARGA BAHAN 378,458.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 425,178.33
E Overhead & Provit 15% x D (maksimum) 63,776.75
F Harga Satuan Pekerjaan ( D + E ) 488,955.08

A.5.1.1.25 Pemasangan 1 m’ Pipa PVC tipe AW Diameter ½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 105,000.00 3,780.00
Tukang Pipa L.02 OH 0.060 125,000.00 7,500.00
Kepala Tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 12,460.00
B BAHAN
Pipa PVC 1/2” m 1.200 5,850.00 7,020.00
Perlengkapan Kg 35% x pipa 5,850.00 2,047.50
JUMLAH HARGA BAHAN 9,067.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 21,527.50
E Overhead & Provit 15% x D (maksimum) 3,229.13
F Harga Satuan Pekerjaan ( D + E ) 24,756.63

A.5.1.1.26 Pemasangan 1 m’ Pipa PVC tipe AW Diameter ¾ ”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 105,000.00 3,780.00
Tukang Pipa L.02 OH 0.060 125,000.00 7,500.00
Kepala Tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 12,460.00
B BAHAN
Pipa PVC 3/4” m 1.200 8,125.00 9,750.00
Perlengkapan Kg 35% x pipa 8,125.00 2,843.75
JUMLAH HARGA BAHAN 12,593.75
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 25,053.75
E Overhead & Provit 15% x D (maksimum) 3,758.06
F Harga Satuan Pekerjaan ( D + E ) 28,811.81

A.5.1.1.27 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 105,000.00 3,780.00
Tukang Pipa L.02 OH 0.060 125,000.00 7,500.00
Kepala Tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 12,460.00
B BAHAN
Pipa PVC 1” m 1.200 11,100.00 13,320.00
Perlengkapan Kg 35% x pipa 11,100.00 3,885.00
JUMLAH HARGA BAHAN 17,205.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 29,665.00
E Overhead & Provit 15% x D (maksimum) 4,449.75
F Harga Satuan Pekerjaan ( D + E ) 34,114.75

A.5.1.1.28 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 1½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.036 105,000.00 3,780.00
Tukang Pipa L.02 OH 0.060 125,000.00 7,500.00
Kepala Tukang L.03 OH 0.006 145,000.00 870.00
Mandor L.04 OH 0.002 155,000.00 310.00
JUMLAH TENAGA KERJA 12,460.00
B BAHAN
Pipa PVC 1 m 1.200 11,100.00 13,320.00
Perlengkapan Kg 35% x pipa 11,100.00 3,885.00
JUMLAH HARGA BAHAN 17,205.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 29,665.00
E Overhead & Provit 15% x D (maksimum) 4,449.75
F Harga Satuan Pekerjaan ( D + E ) 34,114.75

A.5.1.1.29 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.054 105,000.00 5,670.00
Tukang Pipa L.02 OH 0.090 125,000.00 11,250.00
Kepala Tukang L.03 OH 0.009 145,000.00 1,305.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 18,690.00
B BAHAN
Pipa PVC 2” m 1.200 2,025.00 2,430.00
Perlengkapan Kg 35% x pipa 2,025.00 708.75
JUMLAH HARGA BAHAN 3,138.75
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 21,828.75
E Overhead & Provit 15% x D (maksimum) 3,274.31
F Harga Satuan Pekerjaan ( D + E ) 25,103.06

A.5.1.1.30 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 2½”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.081 105,000.00 8,505.00
Tukang Pipa L.02 OH 0.135 125,000.00 16,875.00
Kepala Tukang L.03 OH 0.0135 145,000.00 1,957.50
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 27,957.50
B BAHAN
Pipa PVC 2 ½” m 1.200 -
Perlengkapan Kg 35% x pipa - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 27,957.50
E Overhead & Provit 15% x D (maksimum) 4,193.63
F Harga Satuan Pekerjaan ( D + E ) 32,151.13

A.5.1.1.31 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 3”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.081 105,000.00 8,505.00
Tukang Pipa L.02 OH 0.135 125,000.00 16,875.00
Kepala Tukang L.03 OH 0.0135 145,000.00 1,957.50
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 27,957.50
B BAHAN
Pipa PVC 2 ½” m 1.200 1,850.00 2,220.00
Perlengkapan Kg 35% x pipa 1,850.00 647.50
JUMLAH HARGA BAHAN 2,867.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 30,825.00
E Overhead & Provit 15% x D (maksimum) 4,623.75
F Harga Satuan Pekerjaan ( D + E ) 35,448.75
A.5.1.1.32 Pemasangan 1 m’ Pipa PVC tipe AW Diameter 4”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.081 105,000.00 8,505.00
Tukang Pipa L.02 OH 0.135 125,000.00 16,875.00
Kepala Tukang L.03 OH 0.0135 145,000.00 1,957.50
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 27,957.50
B BAHAN
Pipa PVC 2 ½” m 1.200 83,875.00 100,650.00
Perlengkapan Kg 35% x pipa 83,875.00 29,356.25
JUMLAH HARGA BAHAN 130,006.25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 157,963.75
E Overhead & Provit 15% x D (maksimum) 23,694.56
F Harga Satuan Pekerjaan ( D + E ) 181,658.31

A.5.1.1.33 Pemasangan 1 buah Bak Cuci Piring Stainlessteel


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.030 105,000.00 3,150.00
Tukang Pipa L.02 OH 0.300 125,000.00 37,500.00
Kepala Tukang L.03 OH 0.0300 145,000.00 4,350.00
Mandor L.04 OH 0.015 155,000.00 2,325.00
JUMLAH TENAGA KERJA 47,325.00
B BAHAN
Bak cuci piring Unit 1.000 -
Waterdrain buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 47,325.00
E Overhead & Provit 15% x D (maksimum) 7,098.75
F Harga Satuan Pekerjaan ( D + E ) 54,423.75

A.5.1.1.34 Pemasangan 1 buah Bak Cuci Piring Teraso


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.050 105,000.00 5,250.00
Tukang Pipa L.02 OH 0.500 125,000.00 62,500.00
Kepala Tukang L.03 OH 0.0500 145,000.00 7,250.00
Mandor L.04 OH 0.025 155,000.00 3,875.00
JUMLAH TENAGA KERJA 78,875.00
B BAHAN
Bak cuci piring Unit 1.000 -
Waterdrain buah 1.000 -
Semen portland Kg 20.000 1,500.00 30,000.00
Pasir pasang m3 0.050 125,000.00 6,250.00
JUMLAH HARGA BAHAN 36,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 115,125.00
E Overhead & Provit 15% x D (maksimum) 17,268.75
F Harga Satuan Pekerjaan ( D + E ) 132,393.75

A.5.1.1.35 Pemasangan 1 buah Kran Diameter ½” atau ¾ ”


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 105,000.00 1,050.00
Tukang Pipa L.02 OH 0.400 125,000.00 50,000.00
Kepala Tukang L.03 OH 0.0400 145,000.00 5,800.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 57,625.00
B BAHAN
Keran Air buah 1.000 32,500.00 32,500.00
Sealtape buah 0.025 -
JUMLAH HARGA BAHAN 32,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 90,125.00
E Overhead & Provit 15% x D (maksimum) 13,518.75
F Harga Satuan Pekerjaan ( D + E ) 103,643.75

A.5.1.1.36 Pemasangan 1 buah Floor Drain


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.010 105,000.00 1,050.00
Tukang Pipa L.02 OH 0.100 125,000.00 12,500.00
Kepala Tukang L.03 OH 0.010 145,000.00 1,450.00
Mandor L.04 OH 0.005 155,000.00 775.00
JUMLAH TENAGA KERJA 15,775.00
B BAHAN
Floor drain buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 15,775.00
E Overhead & Provit 15% x D (maksimum) 2,366.25
F Harga Satuan Pekerjaan ( D + E ) 18,141.25

A.5.1.1.37 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah Ǿ 20 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.080 105,000.00 8,400.00
Tukang Pipa L.02 OH 0.040 125,000.00 5,000.00
Kepala Tukang L.03 OH 0.004 145,000.00 580.00
Mandor L.04 OH 0.004 155,000.00 620.00
JUMLAH TENAGA KERJA 14,600.00
B BAHAN
Pipa Tanah diameter 15 m 1.6 333,333.33 533,333.33
Semen Portlan Kg 35 1,500.00 52,500.00
Pasir Pasang m3 0.014 125,000.00 1,750.00
Pasir Urug m3 0.014 125,000.00 1,750.00
JUMLAH HARGA BAHAN 589,333.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 603,933.33
E Overhead & Provit 15% x D (maksimum) 90,590.00
F Harga Satuan Pekerjaan ( D + E ) 694,523.33

A.5.1.1.38 Pemasangan 1 m’ Pipa Air Limbah Jenis Pipa Tanah diameter 15 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.060 105,000.00 6,300.00
Tukang Pipa L.02 OH 0.030 125,000.00 3,750.00
Kepala Tukang L.03 OH 0.003 145,000.00 435.00
Mandor L.04 OH 0.003 155,000.00 465.00
JUMLAH TENAGA KERJA 10,950.00
B BAHAN
Pipa Tanah diameter 15 m 1.6 333,333.33 533,333.33
Semen Portlan Kg 0.93 1,500.00 1,395.00
Pasir Pasang m3 0.013 125,000.00 1,625.00
Pasir Urug m3 0.011 125,000.00 1,375.00
JUMLAH HARGA BAHAN 537,728.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 548,678.33
E Overhead & Provit 15% x D (maksimum) 82,301.75
F Harga Satuan Pekerjaan ( D + E ) 630,980.08

A.5.1.1.39 Pemasangan 1 m’ Pipa Beton Diameter 15 – 20 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang Pipa L.02 OH 0.070 125,000.00 8,750.00
Kepala Tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Pipa Tanah diameter 15 m 1.100 333,333.33 366,666.67
Semen Portlan Kg 0.027 1,500.00 40.50
Pasir Pasang m3 0.93 125,000.00 116,250.00
Pasir Urug m3 0.024 125,000.00 3,000.00
JUMLAH HARGA BAHAN 485,957.17
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 511,507.17
E Overhead & Provit 15% x D (maksimum) 76,726.08
F Harga Satuan Pekerjaan ( D + E ) 588,233.24

A.5.1.1.40 Pemasangan 1 m’ Pipa Beton Diameter 30 – 100 cm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.140 105,000.00 14,700.00
Tukang Pipa L.02 OH 0.070 125,000.00 8,750.00
Kepala Tukang L.03 OH 0.007 145,000.00 1,015.00
Mandor L.04 OH 0.007 155,000.00 1,085.00
JUMLAH TENAGA KERJA 25,550.00
B BAHAN
Pipa Tanah diameter 15 m 1.100 333,333.33 366,666.67
Bata Merah m3 0.550 2,000.00
Semen Portlan Kg 0.027 1,500.00 40.50
Pasir Pasang m3 0.93 125,000.00 116,250.00
Pasir Urug m3 0.024 125,000.00 3,000.00
JUMLAH HARGA BAHAN 485,957.17
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) 511,507.17
E Overhead & Provit 15% x D (maksimum) 76,726.08
F Harga Satuan Pekerjaan ( D + E ) 588,233.24
A.6.1.1 Harga Satuan Pekerjaan Sistem Distribusi Jaringan Listrik

A.6.1.1.1 Pemasangan 1 buah MCCB


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Upah % 100.000 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa listrik 5/8” btg 3.000 -
Kabel m 15.000 -
T Dus buah 1.000 -
L Bow buah 2.000 -
Klem biasa buah 24.000 -
MCCB (Boks MCB) buah 1.000 -
MCB buah 2.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) -
E Overhead & Provit 15% x D (maksimum) -
F Harga Satuan Pekerjaan ( D + E ) -

A.6.1.2 Harga Satuan Pekerjaan Sistem Pencahayaan

A.6.2.1.1 Pemasangan 1 Buah Titik Lampu


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Upah % 100.000 -
JUMLAH TENAGA KERJA -
B BAHAN
Pipa listrik 5/8” btg 3.000 -
Kabel m 15.000 -
T Dus buah 1.000 -
L Bow buah 2.000 -
Klem buah 24.000 -
Mangkok buah 1.000 -
Saklar buah 1.000 -
Fitting buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A + B + C) -
E Overhead & Provit 15% x D (maksimum) -
F Harga Satuan Pekerjaan ( D + E ) -

You might also like