JO.

Shimizu-Bangun Cipta
Mega Kuningan Project

September October
No. Subcont T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
PH01 Usage PH03 Usage
PH01, 03 installation shedule
Mr. Yamasaki site visit from Japan
1 Condo activity

1.1 11F structure work (zoneA1) BANGKIT Half prop


AAC delivery
1.2 11F structure work (zoneA2) BANGKIT Full prop Half prop

1.3 12F structure work (zoneA1) BANGKIT Full prop Half prop
AAC delivery
1.4 12F structure work (zoneA2) BANGKIT 12F slab and beam Full prop Half prop

1.5 13F structure work (zoneA1) BANGKIT 13F slab and beam Full prop Half prop
AAC delivery
1.6 13F structure work (zoneA2) BANGKIT 13F slab and beam Full prop Half prop

1.7 14F structure work (zoneA1) BANGKIT 14F slab and beam Full prop Half prop
AAC delivery
1.8 14F structure work (zoneA2) BANGKIT 14F slab and beam Full prop Half prop

2 PH01 activity

2.1 PH01 TOBAMIX Delivery and installation Temporary usage (1month for official certificate)

3 SA activity

3.1 11F structure work (zoneA1) SNK Full prop Half prop
AAC delivery
3.2 11F structure work (zoneA2) SNK Full prop Half prop

3.3 12F structure work (zoneA1) SNK 12F slab and beam Full prop Half prop
AAC delivery
3.4 12F structure work (zoneA2) SNK 12F slab and beam Full prop Half prop

3.5 13F structure work (zoneA1) SNK 13F slab and beam Full prop Half prop

3.6 13F structure work (zoneA2) SNK


13F slab and beam Full prop H
4 PH03 activity

4.1 PH03 TOBAMIX Delivery and installation