Organizational 

Outcome 1: Ensure Safe and Reliable National Road System‐ Bridge Program, Widening of Permanent Bridges, Busay Br. (B00196LZ)
along Daang Maharlika (LZ)

Daraga, Albay 2nd LD

DETAILED UNIT PRICE ANALYSIS (DUPA)
10092021v1
Item No.: 413(4)f
Description: Expansion Joint, Rubber (Multiplex) Expansion Joints
Unit of Measurement: l.m.
Output Per Hour ‐ As Submitted: 8.00
Output Per Hour ‐ As Evaluated:

Designation No. of No. of  Hourly


Amount
Labor Person Hours Rate
Construction Foreman 1 1                 85.72                      85.72
Skilled Laborer 1 1                 62.06                      62.06
Unskilled Laborer 2 1                 47.83                      95.66
A.1

Sub‐Total for A.1 ‐ As Submitted P                    243.44
No. of No. of  Hourly
Labor Amount
Person Hours Rate

A.2

Sub‐Total for A.2 ‐ As Evaluated P
Name and Capacity No. of No. of  Hourly
Amount
Equipment Units Hours Rate
Minor Tools (10% of Labor Cost)                      24.34
B.1

Sub‐Total for B.1 ‐ As Submitted P                      24.34
No. of No. of  Hourly
Equipment Amount
Units Hours Rate

B.2

Sub‐Total for B.2 ‐ As Evaluated P
C.1 Total (A.1+ B.1) ‐ As Submitted                    267.78
C.2 Total (A.2+ B.2) ‐ As Evaluated
D.1 Output Per Hour ‐ As Submitted                        8.00
D.2 Output Per Hour ‐ As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) ‐ As Submitted P                      33.47
E.2 Direct Unit Cost (C.2 ÷ D.2) ‐ As Evaluated P
Name and Specification Unit
Unit Quantity Amount
Materials Cost
Expansion Joint Tubber (Multiplex) Expansion Joints l.m. 1.000000            9,146.24                 9,146.24
Miscellaneous (5% of Materials' Cost)                    457.31
F.1

Sub‐Total for F.1 ‐ As Submitted P                 9,603.55


Unit
Materials Unit Quantity Amount
Cost

F.2

Sub‐Total for F.1 ‐ As Submitted P                          ‐
G.1 Direct Unit Cost (E.1 + F.1) ‐ As Submitted P                 9,637.03
G.2 Direct Unit Cost (E.2 + F.2) ‐ As Evaluated P
H.1 Overhead, Contingencies & Miscellaneous (OCM) ‐ As Submitted 12% of G.1                 1,156.44
H.2 Overhead, Contingencies & Miscellaneous (OCM) ‐ As Evaluated of G.1
I.1 Contractor's Profit (CP) ‐ As Submitted 8% of G.1                    770.96
I.2 Contractor's Profit (CP) ‐ As Evaluated of G.1
J.1 Value Added Tax (VAT) ‐ As Submitted 5% of (G.1 + H.1 + I.1)                    578.22
J.2 Value Added Tax (VAT) ‐ As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost ‐ As Submitted (G.1 + H.1 + I.1 + J.1)               12,142.65
K.2 Total Unit Cost ‐ As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: Checked/Reviewed by:

SALVADOR MARC R. BOTIN BRIGILDO M. FABIA
Organizational Outcome 1: Ensure Safe and Reliable National Road System‐ Bridge Program, Widening of Permanent Bridges, Busay Br. (B00196LZ)
along Daang Maharlika (LZ)

Daraga, Albay 2nd LD

DETAILED UNIT PRICE ANALYSIS (DUPA)
10092021v1
Engineer II Assistant Division Chief
Planning and Design Division Planning and Design Division