STERLING 

MEP WORKS SCHEDULE
SL.NO. EAST & WEST TOWER FINISH DATE
1 ROOF 30‐Sep‐22
2 LEVEL 25 30‐Sep‐22
3 LEVEL 01 & 02 APARTMENT 27‐Sep‐22
4 LEVEL 01 FAHU 5‐Oct‐22
5 LEVEL 03 COMMON AREAS ‐ FIRE FIGHTING 20‐Oct‐22
6 DEWA LV INSPECTION (works ready) 27‐Sep‐22
7 BASEMENT 1 15‐Oct‐22
8 BASEMENT 2 25‐Oct‐22
TOWNHOUSES
9 PLASTER CLEARANCE 30‐Sep‐22
10 SCREED CLEARANCE 5‐Oct‐22
11 GRID CLEARANCE 15‐Oct‐22
GARDEN UNITS
12 PLASTER CLEARANCE 15‐Oct‐22
13 SCREED CLEARANCE 20‐Oct‐22
14 GRID CLEARANCE 30‐Oct‐22