Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

9/7/2014

Developments in Power Sector during May 2014

1. IMPORTANT DEVELOPMENTS:

1.1 Capacity Addition in Generation:

i. Thermal capacity of 2586.10 MW has been added during the month of May, 2014 after commissioning of Ramgarh CCPP / STG (50 MW) by
RRVUNL in Rajasthan; Kalisindh TPP, U-I (600 MW) by RRVUNL in Rajasthan; Derang TPP, Unit-1 (600 MW) by JIPL in Odisha, Dhuvaran
CCPP, Unit-I, (376.10 MW) by GSECL in Gujarat; Sasan UMPP, Unit-4 (660 MW) by SPL in Madhya Pradesh and Dhariwal TPP, Unit-2 (300
MW) by Dhariwal Infrastructure Ltd. in Maharashtra.

ii. Hydro capacity of 130 MW has been added during the month of May, 2014 after commissioning of Parbati-II, U-IV, HE by NHPC Ltd. in H.P.

iii. No Nuclear capacity has been added during the month of May, 2014.

1.2 Transmission Addition:

In the transmission sector, stringing of 1395 ckt. Kms. of transmission lines have been completed during the month of May, 2014 against the MoU
target for stringing of 7000 ckt. Kms. fixed for the financial year 2014-15.

1.3 Electricity Generation:

i. The electricity generation in the country during the month of May, 2014 was 89,662 Million Units (MUs) as against 84,350 MU during the
corresponding month of the year 2013, showing a growth of 6.30%. Thermal generation in May, 2014 increased by 6.52%, Nuclear generation
has increased by 5.29% and Hydro generation also increased by 6.76% over same month last year. Overall electricity generation was
103.56% of the programme for the month.

ii. The actual electricity generation from nuclear plants during the month was 9.79% more than the programme for the month. Coal based
generation has a growth rate of 8.63% but Lignite based generation has a negative growth of 1.46% and the Gas based (including Liquid fuel)
generation has also a negative growth rate of 15.97% as compared to last year same month mainly on account of decreased gas output from
KG-D6 and also higher cost of alternate fuel.

iii. Plant Load Factor:- All India % PLF during the month of May, 2014 was 68.15% against the target of 67.43% fixed for May, 2014. The PLF for
the Central Sector, State Sector, Private Sector (IPP) and Private Sector (Utilities) plants were 78.15%, 60.45%, 66.56% and 72.94%
respectively.

iv. The actual electricity generation from hydro power plants during May, 2014 was 6.07% higher than the program for the month. It had a growth
of 6.76% as compared to last year same month.

1.4 Re-structured APDRP Implementation

Re-structured APDRP was launched on 31.07.2008 as a Central Sector Scheme with a programme size of INR 51.577 Crore.

Projects under the scheme are to be taken up in two parts. Part-A is the projects for establishment of baseline data and IT applications for energy
accounting / auditing & IT based consumer service centres and Part-B is regular distribution strengthening projects.

Part-A projects worth INR 5348.34 Crore covering all the eligible towns (1412) in the country have already been sanctioned. 72 Supervisory Control
and Data Acquisition (SCADA) projects worth INR 1601.28 Crore have also been sanctioned for Nineteen States / UTs (Maharashtra, Uttar Pradesh,
Gujarat, Rajasthan, Tamil Nadu, Andhra Pradesh, Madhya Pradesh, Kerala, Bihar, Punjab, West Bengal, Assam, J&K, Chhattisgarh, Uttrakhand,
Haryana, Jharkhand. Puducherry and Odisha) under Part-A. 1244 projects worth INR 31139.71 Crore have been approved to Twenty Six States
(Andhra Pradesh, Gujarat, Haryana, Himachal Pradesh, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Punjab, Rajasthan, Sikkim, Tamil Nadu,
Tripura, Chhattisgarh, Uttar Pradesh, West Bengal, Bihar, Assam, J&K, Uttarakhand, Puducherry, Manipur, Meghalaya, Jharkhand, Mizoram and
Odisha) under Part-B.

1.5 RGGVY Implementation:

As on 31 May 2014, 1,08,373 villages have been electrified and free electricity connections have been provided to 217.76 lakh BPL households under
RGGVY.

2. OTHER IMPORTANT ACTIVITIES:

2.1 PROBLEMS IN IMPLEMENTING THE DECISIONS TAKEN BY THE CABINET / CABINET COMMITTEES:

At present there is no specific problem to report.

2.2 DEPARTURE FROM THE TRANSACTION OF BUSINESS RULES / ESTABLISHED POLICY OF THE GOVERNMENT:

There is no departure from the transaction of Business Rules / Established Policy of the Government.

2.3 IMPORTANT POLICY DECISIONS / MATTERS UNDER CONSIDERATION:

At present there is no policy decisions / matters under consideration.

2.4 COMPLIANCE STATUS OF DECISIONS OF COMMITTEE OF SECRETARIES: At present there is no decision pending for implementation.

2.5 ITEMS PENDING IN THE CABINET SECRETARIAT: There is nothing to report in this regard.

2.6 REQUEST FOR EXPEDITING: At present there is no request for expending.

2.7 CASE PENDING FOR SANCTION FOR PROSECUTION FOR MORE THAN THREE MONTHS.
1/8
9/7/2014
2.7 CASE PENDING FOR SANCTION FOR PROSECUTION FOR MORE THAN THREE MONTHS.

At present there is no such case pending for more than 3 months.

3. FUEL ISSUES:

3.1 Coal Supply:

i. Domestic Supply:

The overall coal stock position, which was 17.99 Million Tonne as on 1st May, 2014 decreased to 15.42 Million Tonne (MT) as on 29th May,
2014. In comparison to 1st May, 2014, the number of critical power stations (having less than 7 days of coal stock) increased from 22 to 28
and the number of super critical stations (having less than 4 days of coal stock) increased from 14 to 20. The average coal stock at power
stations was for 11 days of generation against the normative requirement for 21 days.

ii. Import of Coal:

To bridge the gap between demand for coal and its domestic supply as well as to build reasonable stock of coal, an import target of 54 Million
Tonne (MT) coal for the year 2014-15 has been assigned to the Power Utilities in the country, for the plants designed on domestic coal. In
addition, coal import requirement in respect of power stations designed on imported coal was assessed as 40 MT. The provisional import of
coal by the Power Utilities during the year 2014-15 (Up to 31st May, 2014) was approximately 14.516 MT.

3.2 Gas Supply ( for Month of May 2014)

Gas supply to power sector from KG-D6 has been zero since April, 2014 whereas APM, Non-APM and RLNG gas supply to power sector has been
approximately 26.39 mmscmd.

4. HYDRO SECTOR PROJECTS:

4.1 Hydro Capacity Addition :

S. No. Projects name & Unit No. Target (MW) Fixed Target Achieved (MW) Critical Area / Date of Commissioning

1. Parbati III U#4, in HP by NHPC - - 130 22.05.2014

4.2 Status of Environmental / Forest Clearances in respect of Hydro Electric projects:

DHUKWAN small hydro power (24 MW):

Final (2nd Stage) Forest diversion has been cleared by Central Nodal Forest officer, Lucknow and letter has been sent to Principal Secretary
(Forest), Government of UP on 17th September, 2013 for further necessary action. File for issue of Gazette notification is in circulation in
GoUP

JHELAM TAMAK Hydro Power Project (108 MW):

Land case for Stage-1 forest clearance of 88.29 Ha land of Jhelam Tamak was submitted to GoUK on 30.11.2012. GoUK has forwarded the
case with their recommendations to MoEF, New Delhi on 17th December, 2013. Supreme Court has issued Judgement on 13th August, 2013
to MoEF & GoUK not to issue EC & FC to 24 projects under review and examination till further order which includes Jhelam Tamak Hydro
Power Project also.

An expert committee under chairmanship of Prof. Ravi Chopra was constituted by MoEF to make a detailed study of the impacts of HEPs on
the biodiversity of Alaknanda and Bhagirathi river basins. Final decision in the matter is awaited.

BOKANG BAILING Hydro Power Project (330 MW):

Proposal for carrying out drilling / drifting work under Survey & Investigation was forwarded by Principal Secretary, GoUK to MoEF on
21.06.2013 for further consideration of NBWL. DIG (Wild Life), MoEF, Gol on 02.07.2013 requested CWLW, GoUK to submit some documents
so that the proposal can be considered by NBWL. All the documents have been submitted to DIG (Wild Life), MoEF. As per the Supreme
Court directives, the proposal has not been considered by NBWL regarding drilling / drifting work under Survey & Investigation in their meeting
held on 4th September, 2013 and further it has been informed that the proposal can be considered only after getting clearance of Supreme
Court.

(b) Status of Environmental Clearances:

JHELAM TAMAK Hydro Power Project (108 MW):

Regarding Environment Clearance, EAC in its 67th meeting held on 6th June, 2013 has asked THDCIL to submit a detailed note with plans of
Nandadevi Biosphere Reserve (NDBR) and Valley of Flower (VOF) on the cumulative impact of Dhauli Ganga projects and mitigation measures
to counter adverse impact on biodiversity of both NDBR and VOF for consideration of EAC in their next meeting while considering environment
clearance. In the mean time Supreme Court has issued Judgement on 13th August, 2013 to MoEF & GoUK not to issue EC & FC to 24
projects under review and examination till further order which includes Jhelam Tamak Hydro Power Project also.

An expert committee under chairmanship of Prof. Ravi Chopra was constituted by MoEF to make a detailed study of the impacts of HEPs on
the biodiversity of Alaknanda and Bhagirathi river basins. Final decision in the matter is awaited.

4.3 important Development in respect of 101 MW Tripura Gas Based Power Project, Monarchak, Tripura, in May 2014:

Civil works of cooling tower completed. Erection and commissioning works are in progress.

65% of laying of Pipeline for Raw Water completed. Construction of Intake structure in progress.

2/8
9/7/2014

For Fire Fighting system construction of Clarified / Fire Water Reservoir & piping works completed. Diesel Pump commissioned and motor
driven pump alignment is in progress. Jockey pump air receiver tank placed in site.

In Pre Treatment Plant, 92% works completed. Roof slab completed.

99% DM Plant civil works completed. Finishing works are in progress. Erection of DM tank is in progress together with fixing of frontal pipes of
vassals. Hydro test for both DM tanks completed, sand blasting in progress.

Bottom Raft of Effluent Treatment Plant completed, walls are in progress.

80% Erection and commissioning works of Compressed Air System including grouting of compressors completed.

In STG Auxiliaries erection works, erection of Air Evacuation System and Gland Steam Condenser completed. Placement of Lube oil tank /
AOP / EOP completed. Piping works are in progress.

Erection of GTG Control & Relay Panels completed. Cabling is in advanced stage of completion.

DCS equipment and Control desk panels have been placed in position. Cabling & termination works is in progress.

5. THERMAL SECTOR PROJECTS:

S. Projects Name & Unit No. Target Fixed Target Achieved Critical Area/ Date of
No. (MW) (MW) Commissioning

1 Talwandi Sabo TPP / U-1 / Sterlite 660 The Unit was slipping*

1 Ramgarh CCPP / STG, by RRVUNL in Rajasthan. 50 01.05.2014

2 Kalisindh TPP/Unit#1, by RRVUNL in Rajasthan 600 02.05.2014

3 Derang TPP / Unit#1 by JIPL in Odisha 600 10.05.2014

4 Dhuvaran CCPP/Unit#1 by GSECL in Gujarat 376.10 21.05.2014

5 Sasan UMPP / Unit#4 by SPL in Madhya Pradesh 660 21.05.2014

6 Dhariwal TPP / Unit#2 by Dhariwal Infrastructure Ltd. in 300 28.05.2014


Maharashtra

TOTAL 660 2586.10

*Commissioned on 17/06/2014

5.1 Status Report of NTPC-BHEL Power Project Pvt Ltd. (NBPPL) for the Month of May, 2014

5.1.1 Manufacturing Plant at Mannavaram: Mannavaram manufacturing plant is getting ready to start Plant Production and Manufacturing activities
from the second quarter of FY 14-15 with the readiness of following systems & Facilities.

Manufacturing Facilities / Machines:

Total Number of facilities/ Machines - 24 nos.

Out of 24 Nos. - 18 nos. of facilities / Machines received at site.

Power Supply arrangement for manufacturing plant - Electrical Equipments & systems.

Erection of three transformers (25 MVA) completed. Erection of 2 DC-Sets of 1000VA, One DG set of 500VA and DG Stack completed.
Erection of Switch Gear Panels and Bus Duct completed.

Construction of major buildings (Civil works):

Major civil & structural works of Main Fabrication Block, Administrative Block, stores buildings, Canteen, Dispensary etc., completed.

5.1.2 EPC Orders under execution:

1 x 500 MW Feroze Gandhi Unchahar TPP:

Site Enabling Works started on 18th February, 2014. Site leveling works in Main plant area are under progress and 6000 m3 completed
out of 35000m3.

BTG and Engineering Consultancy works awarded to BHEL on 15/11/13.

Ordering of equipment for site construction power supply works completed.

Palatana 2 x 363.3 MW Combined Cycle Power Plant:

NBPPL scope is BOP including Civil and E&C thereof. The total order value is INR 186.80 Crore.

Unit-1: Commissioned & dedicated to the Nation by President of India on 21.06.2013.

Unit-2: Major NBPPL scope of works completed and systems made ready for unit commissioning.

Namrup 1 x 100 MW Combined Cycle Power Plant:


3/8
9/7/2014
Namrup 1 x 100 MW Combined Cycle Power Plant:

NBPPL scope is BOP, Civil and E&C Works of entire plant. The total order value is INR 198.9 Crore.

A total of 118 packages out of 138 ordered and balance packages are under various stages of ordering.

BHEL PSER terminated NBPPL for execution of site Works under NBPPL Scope.

Monarchak 1 x 100 MW Combined Cycle Power Plant:

NBPPL scope is BOP including E&C works of Entire Plant. The total order value is INR 114 Crore.

122 KV outgoing lines & Switch yard charging completed on 21st January, 2014.

5.1.3 Efforts made for Order Booking:

Business sharing Strategy with BHEL - ISG: NBPPL registered as a qualified vendor of BHEL: ISG to supply CHP equipments on the strength
of TCA with DMW.

Tie up with BHEL - Ranipet: NBPPL is registered as BHEL / Ranipet''s sub vendor on 10.08.13, for under taking the structural fabrication jobs
of BHEL / Ranipet.

Tie up with AP Genco: NBPPL approached and submitted its status of manufacturing plant to AP Genco and requested for orders on spares
requirement in their operating plants.

6. "ENERGY EFFICIENCY AND CONSERVATION ISSUES"

6.1 Standards & Labeling (S&L)

i. A technical committee meeting for Refrigerator was held on 2nd May, 2014 for the revision of energy performance standards of direct cool
Refrigerator which would be applicable from 1st January, 2015. The program will be made mandatory w.e.f. 1st January, 2015 and the way
forward for Frost Free Refrigerators labeling program was also discussed.

ii. The first technical committee meeting for Solar Water Heater (SWH) for discussion on parameters for energy performance, identification of
types & testing standards for SWH was held on 16th May, 2014.

iii. A technical committee meeting for Distribution Transformers for discussing the total losses at 50% and 100% loading, inclusion of dry type
transformers in existing labeling plan, revised star labeling plan and time lines for implementation was held on 5th May, 2014.

6.2 Super Efficient Equipment Program (SEEP)

Cost of super-efficient fan, has declined substantially due to BEE''s efforts on market transformation. Today, the price difference between super-
efficient (about 43 watts power consumption) and ordinary fans (70 watts) is INR 100 only.

7 Capacity Addition / Power Generation / Stringing of Transmission Lines / Village Electrification / Electricity Connection to BPL
Families:

In response to Cabinet Secretariat''s OM, information pertaining to Ministry of Power is placed at Annexure-I.

8. Progress Made vis-a-vis target finalized for FY 13-14 in the meeting of Steering Group Held on 9th July, 2013 to Accelerate
Infrastructure Investment.

In response to Cabinet Secretariat''s ID, status report in respect of identified projects pertaining to Ministry of Power is placed at Annexure-II.

9. Compliance status of the Decisions of the........Cabinet / Cabinet Committees:

In response to the Cabinet Secretary''s D. O. letter dated 11th May, 2011 regarding the compliance status of the decisions of the Cabinet/ Cabinet
Committees pending for implementation, the information may treated as NIL.

Annexure-I

i. Target vs. Achievement of Capacity Addition, Power Generation, Village Electrification and Electricity Connection to BPL Households

2014-15 Target Cumulative Achievement at the end of Cumulative Achievement at the end of
the month of reporting in 2014-15 (up to 31.05.2014) corresponding month in 2013-14 (up to
31.05.2013)

Capacity Addition 17800.3* 3251.10 1852

Power Generation (BU) 1023 176.814 162.220

Transmission Lines (ckm) 20,882 2490 1693

Village Electrified including 15000 2567 2864


Intensification

Electric Connection to BPL 15 0.92 1.68


Households (Nos. in Lakhs)
4/8
9/7/2014
Households (Nos. in Lakhs)

* Includes 2000 MW of nuclear capacity.

(ii) State / Progress of Environmental Clearance / Forest Clearance issues

(A) Issues pertaining to Environment / Forest Clearances

1. Forest Clearances pending due to reconstitution of Standing Committee of National Board of Wildlife (NBWL):

Reconstitution of Standing Committee of the NBWL pending since September, 2013; following 2 lines are critical:

SI. Name of the Brief status of the Brief history of issues pending with MoEF
No. Project / project
Location

1. Gwalior - Jaipur Under Construction Proposal for GIB Sanctuary discussed in SBWI meeting on July 29, 2013 at Bhopal.
765 KV S/C line (Project linked with Proposal forwarded to MoEF on 25.09.13 for recommendations of NBWL. Term of Standing
27.47 ha, (Madhya Odisha (Part-C) IPPs) Committee of NBWL expired. The meeting shall take place only after reconstitution of the
Pradesh) Committee.

2. Kishenpur-New Under Construction Proposal discussed and recommended in SBWL meeting on 25.07.2013. Proposal
Wanpoh 400 KV (Northern Region) forwarded to MoEF on 06.01.2014 for recommendations of NBWL. The meeting shall take
D/C Line 2.35 ha (System Strengthening place only after reconstitution of the Committee.
(J&K) Scheme - XVI)

2. Requirement of Certificate concerning compliance under Forest Right Act (FRA), 2006

MoEF circular linear projects such as transmission lines have been exempted from FRA stipulations requiring No Objection Certificate (NOC) from 100%
Gram Sabha. This has been done on pursuance from MoP wherein it was clarified that for construction of transmission line being over-head through any land
area (including forest areas wherever involved) as only Right of Way (RoW) is involved and there is no physical land encroachment except for Tower
construction. Also since the line lengths being typically large and so covering typically large length of several districts in a State, obtaining NOC from every
Gram Sabha may not be practicable.

However, MoEF circular requiring the above exemptions to be processed as per stated formats has led to a confusion wherein the Competent Authority -
District Collector - is interpreting the circular - as if the exemption has been withdrawn. Therefore they are again treating transmission line as non-linear
project and so requiring FRA clearance as for non-linear projects which clearly is against the said circular. MoEF needs to clarify the situation through an
OM to all concerned.

(iii) Status of Project Costing of INR 1000 Crore or more Or Projects which are considered Critical: Nil

Annexure-II

Milestones for award of 2 UMPPs (Bedabahal in Odisha & Cheyyur, Tamil Nadu)

S. Action Time Deadline Original Date as Revised date (as on 29.5.2014) for Odisha UMPP/Cheyyur UMPP
No. Period agreed per RfQ Document
(in to
weeks)

1 Approval of SBDs 4 15 Aug Approved by EGoM in meetings dated 8.8.2013 and 23.8.2013.
by EGoM 13 Minutes dated 9.9.2013 has been received from Cabinet Secretariat.
Based on decision taken SBDs have been finalized.

Odisha Cheyyur Odisha UMPP Cheyyur UMPP


UMPP UMPP

2 Issue of RFQ 4 23 Aug 25.9.2013 26.9.2013 Issued on 25.9.2013 Issued on 26.9.2013


13

3 Pre-Application 10 12 Sep Held on Held on Held on 15 Oct 13 Held on 15 Oct 13


conference / Issue 13 15 Oct 13 15 Oct 13
of clarifications

4 RFQ Application 15 7 Oct 13 11 Nov 13 11 Nov 13 25 Nov 13 28 Nov 13


Date

5 Issue of RFP 17 7 Nov 13 10 Dec 11 Dec 27 Dec 13 27 Dec 13


13 13

6 Pre-Bid conference 21 22 Nov 13 24 Dec 26 Dec 03 Feb 14 03 Feb 14


/ Issue of 13 13
5/8
9/7/2014
clarifications

7 RFP Bids 24 7 Jan 14 03 Feb 04 Feb 07 Oct 14 22 Sep 14


14 14

8 Bid Evaluation 26 22 Jan 14 03 Feb 04 Feb 07 Oct 14 22 Sep 14


14 14

9 Award / LOA 28 31 Jan 14 26 Feb 27 Feb Within 30 days of RfP Bids Within 30 days of RfP Bids
14 14

Note: "RfQ for Odisha UMPP and Cheyyur UMPP have been issued on 25.9.2013 and 26.9.2013 respectively. Applications from nine firms have been
received for Odisha UMPP. Applications from 8 firms have been received for Cheyyur UMPP. RfP for both projects have been issued on 27.12.2013. The bid
due date for the projects was 04.06.2014 and 21.05.2014 respectively and is now extended by 4 months. Accordingly action dates on future events are
revised.

Northern Region System Strengthening Scheme, NRSS-XXIX (BPC - RECTPCL) Transmission Elements

LILO of both circuits of Uri-Wagoora 400 Kv D/C Line at Amargarh (on Multi-Circuit Towers),

Establishment of 7x105 MVA (1-ph). 400/220 kV GIS Substation at Amargarh,

Jalandhar - Samba 400 kV D/C Line,

Samba - Amargarh 400 kV D/C line routed through Akhnoor / Rajouri sector.

Name of the SPV: NRSS XXIX Transmission Limited

Estimated Project Cost: INR 2621 Crore

Target Timelines

S. No. Milestone Target Date Progress

1. RfQ Issuance 26.07.2013 Issued on 02.08.2013

2. RfQ Submission 10.09.2013 17.09.2013

3. Date of Short-listing of Bidders to participate in RFP 30.09.2013 07.10.2013

4. Date of Issuance of RfP Documents 09.12.2013 09.12.2013

5. Pre-Bid Conference Date 24.12.2013 26.12.2013

6. Date of Finalization & Issuance of TSA 31.01.2014 31.01.2014

7. Date of Opening of Non-Financial Bids 07.02.2014 09.05.2014

8. Date of Opening of Financial Bids 14.02.2014 16.05.2014

9. Date of Issuance of Lol 22.02.2014 23.05.2014

10. Date of Transfer of SPV to Selected Bidders 04.03.2014

Northern Region System Strengthening Scheme, NRSS-XXXI (Part-A) (BPC - RECTPCL) Transmission Elements

Establishment of a 7x105 MVA (1-ph). 400/220 kV GIS Substation at Kala Amb.

LILO of both circuits of Karcham Wangtoo - Abdullapur 400 KV D/C Line at Kala Amb quad (on Multi Ckt towers)

40% Series Compensation on 400 kV Karcham Wangtoo-Kala Amb quad D/C line at Kala Amb ends.

Name of the SPV: NRSS XXXI (A) Transmission Limited

Estimated Project Cost: INR 225 Crore

Target Timelines

Sl.No. Milestone Target Date Progress

1. RfQ Issuance 26.07.2013 Issued on 01.08.2013

6/8
9/7/2014

2. RfQ Submission 10.09.2013 16.09.2013

3. Date of Short-listing of Bidders to participate in RFP 30.09.2013 07.10.2013

4. Date of Issuance of RfP Documents 09.12.2013 09.12.2013

5. Pre-Bid Conference Date 24.12.2013 26.12.2013

6. Date of Finalization & Issuance of TSA 31.01.2014 31.01.2014

7. Date of Opening of Non-Financial Bids 07.02.2014 07.02.2014

8. Date of Opening of Financial Bids 14.02.2014 14.02.2014

9. Date of Issuance of Lol 22.02.2014 26.02.2014

10. Date of Transfer of SPV to Selection Bidders 04.03.2014 12.05.2014@

@Selected bidder is PGCIL.

Northern Region System Strengthening Scheme, NRSS-XXXI (Part-B) (BPC - RECTPCL) Transmission Elements

Kurukshetra - Malerkotla 400 kV D/C Line,


Malerkotla - Amrisar 400 KV D/C Line.

Name of the SPV: NRSS XXXI (B) Transmission Limited

Estimated Project Cost: INR 370 Crore

Target Timelines

S. No. Milestone Target Date Progress

1. RfQ Issuance 30.07.2013 31.07.2013

2. RfQ Submission 13.09.2013 16.09.2013

3. Date of Short-listing of Bidders to participate in RFP 02.10.2013 07.10.2013

4. Date of Issuance of RfP Documents 09.12.2013 09.12.2013

5. Pre-Bid Conference Date 24.12.2013 26.12.2013

6. Date of Finalization & Issuance of TSA 31.01.2014 31.01.2014

7. Date of Opening of Non-Financial Bids 07.02.2014 07.02.2014

8. Date of Opening of Financial Bids 14.02.2014 14.02.2014

9. Date of Issuance of Lol 22.02.2014 26.02.2014

10. Date of Transfer of SPY to Selection Bidders 04.03.2014 12.05.2014@

@ Selected bidder is Essel lnfra projects Ltd.

ATS of Unchahar TPS (BPC - RECTPCL)

[In lieu of Northern Region System Strengthening Scheme (RSSS-XXXIII) and ATS for Tanda Expansion (TPS)]

Unchahar - Fatehpur 400 kV D/C line

Two Nos of 400 kV Line bays at Unchahar by NTPC Ltd,


Two Nos. of 400 kV Line bays at Fatehpur by POWERGRID.

Name of the SPV: Unchahar Transmission Limited

Estimated Project Cost: INR 70 Crore

Target Timelines

S. No. Milestone Target Date Progress

1. RTQ issuance Not applicable 11.01.2013

2. RTQ Submission Not applicable 26.02.2013

7/8
9/7/2014
3. Date of Short-listing of Bidders to participate in RFP Not applicable 03.05.2013

4. Date of Issuance of RfP Documents Not applicable 17.10.2013

5. Pre-Bid Conference Date 15.11.2013 18.11.2013

6. Date of Finalization & Issuance of TSA 08.01.2014 08.01.2014

7. Date of Opening of Non-Financial Bids 15.01.2014 15.01.2014

8. Date of Opening of Financial Bids 04.02.2014 04.02.2014

9. Date of Issuance of Lol 14.02.2014 14.02.2014

10. Date of Transfer of SPV to Selected Bidders 17.03.2014 24.03.2014@

@Selected bidder is PGCIL.

8/8

You might also like