DAFTAR KUANTITAS PEKERJAAN

25830

Galian Pas. Batu Galian Timbunan Timbunan Penyiapan Lapis Resap Lapis Resap Bahan Anti Pasangan Patok
KM Panjang untuk Agregat S LPA LPB HRS-WC Pengelupas Beton Baja Marka Rambu
Drainase Mortar Biasa Biasa Pilihan Badan Jalan Pengikat Perekat an Batu Pengarah

Satuan m m3 m3 m3 m3 m3 m² m3 m3 m3 Liter Liter Ton Kg m3 Kg m3


Segmen I
47+900 - 48+000 100 30 15 0.00 0.00 45.00 150 15 22.5 30 108.5 90 67.2 1.31 - - -
48+000 - 49+000 1000 300 150 0.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - -
49+000 - 50+000 1000 300 150 0.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - -
50+000 - 51+000 1000 300 150 0.00 14.06 450.00 1500 150 225 300 1085 672 13.10 1.00 130.00 1.00
51+000 - 51+260 260 78 39 0.00 14.06 117.00 390 39 58.5 78 282.1 234 174.72 3.41 2.00 260.00 2.00

Segmen II
51+660 - 52+000 340 102 51 204.00 0 153.00 510 51 76.5 102 368.9 306 228.48 4.46 6.36 827.32 -
52+000 - 53+000 1000 300 150 600.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - 6.48
53+000 - 54+000 1000 300 150 600.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - -
54+000 - 55+000 1000 300 150 600.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 6.36 827.32 -
55+000 - 56+000 1000 300 150 600.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - -
56+000 - 56+100 100 30 15 60.00 0 45.00 150 15 22.5 30 108.5 90 67.2 1.31 - - -

Segmen III
61+110 - 62+000 890 267 133.5 0.00 0 400.50 1335 133.5 200.25 267 965.65 801 598.08 11.66 6.36 827.32 -
62+000 - 63+000 1000 300 150 14.06 14.06 450.00 1500 150 225 300 1085 900 672 13.10 6.36 827.32 6.48
63+000 - 63+240 240 72 36 14.06 14.06 108.00 360 36 54 72 260.4 216 161.28 3.14 - - -

Segmen IV
75+300 - 76+000 700 210 105 375.00 0 315.00 1050 105 157.5 210 759.5 630 470.4 9.17 6.36 827.32 -
76+000 - 77+000 1000 300 150 0.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 6.36 827.32 -
77+000 - 78+000 1000 300 150 0.00 14.06 450.00 1500 150 225 300 1085 900 672 13.10 - - -
78+000 - 78+800 800 240 120 0.00 14.06 360.00 1200 120 180 240 868 720 537.6 10.48 1.00 130.00 1.00

TOTAL 13430.0 4029.0 2014.5 3067.13 182.8 6043.5 20145.0 2014.5 3021.8 4029.0 14571.6 11187.0 9025.0 176.0 42.2 5483.9 17.0 2,733.75 10.00 150.00
STONE MASONERY PADA DEUKER PLATE
Seksi 1 L
b
a a
0,20 0,20

0,20

0,40

0,10
d e d
0,10 0,10

Ukuran plat (m)


Dimensi Pasangan Batu (M) Luas Volume Total
No Lokasi Lebar Tinggi Bentang
e T B a b c d L (M2) (M3)
1 00 + 825 1.000 1.000 11.000 0.400 1.400 0.2600.600 1.800 1.760 19.36
2 01 + 150 1.000 1.000 10.000 0.400 1.400 0.2600.600 1.800 1.760 17.60
3 02 + 100 2.000 1.000 10.000 0.450 2.500 0.3300.800 2.900 2.520 25.20
4 02 + 739 2.000 1.000 10.000 0.450 2.500 0.3300.800 2.900 2.520 25.20
5 02 + 900 2.000 1.000 10.000 0.450 2.500 0.3300.800 2.900 2.520 25.20
6 03 + 366 2.000 1.000 10.000 0.450 2.500 0.3300.800 2.900 2.520 25.20
7 04 + 036 2.000 1.000 10.000 0.450 2.500 0.3300.800 2.900 2.520 25.20
SUB TOTAL VOLUME 162.96
TOTAL VOLUME SAMPAI HAL INI 162.96
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR

AGUS IR. RUSMAN KATIB ANDRI


Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER
STONE MASONERY PADA DEUKER PLATE
Seksi 1 L
b
a a
0,2 0,2

0,20

0,40

0,10
d e d
0,10 0,10

Ukuran plat (m)


Dimensi Pasangan Batu (M) Luas Volume Total
No Lokasi Lebar Tinggi Bentang
e T B a b c d L (M2) (M3)
8 05 + 697 2.00 1.00 10.00 0.45 2.50 0.33 0.80 2.90 2.52 25.20
9 06 + 420 2.00 1.00 10.00 0.45 2.50 0.33 0.80 2.90 2.52 25.20
10 06 + 711 2.00 1.00 10.00 0.45 2.50 0.33 0.80 2.90 2.52 25.20
11 03 + 125 2.00 1.00 10.00 0.45 2.50 0.33 0.80 2.90 2.52 25.20

SUB TOTAL VOLUME 100.8


TOTAL VOLUME SAMPAI HAL INI 263.76
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR
AGUS IR. RUSMAN KATIB ANDRI
Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER
SUMMARY!A1

01 + 150
JULI 02 + 100
05 + 697
06 + 420
MEI 06 + 711
04 + 178

00 + 825
01 + 150
02 + 100
02 + 739
02 + 900
03 + 366
04 + 036
05 + 697
06 + 420
06 + 711
03 + 125

JULI

1m 19.360 2 38.72
2m 25.200 9 226.8
265.52
STONE MASONRY PADA INLET/APRON DEUKER PLATE

c
2m 2m
d

DIMENSI PROFIL (m) Luas Panjang Volume (M3)


No. Lokasi
a b c d e (M2) (M) Inlet Outlet
1 00 + 825 0.30 1.00 0.40 0.60 0.20 0.590 2.00 2.360 2.360
2 01 + 150 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
3 02 + 100 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
4 02 + 739 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
5 02 + 900 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
6 03 + 366 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
7 04 + 036 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
SUB TOTAL VOLUME 146.32
TOTAL VOLUME SAMPAI HAL INI 146.32
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR

AGUS IR. RUSMAN KATIB ANDRI


Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER
STONE MASONRY PADA INLET/APRON DEUKER PLATE

c
10 m 10 m
d

DIMENSI PROFIL (m) Luas Panjang Volume (M3)


No. Lokasi
a b c d e (M2) (M) Inlet Outlet
8 05 + 697 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
9 06 + 420 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
10 06 + 711 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800
11 03 + 125 0.30 1.00 0.40 0.60 0.20 0.590 10.00 11.800 11.800

SUB TOTAL VOLUME 94.40


TOTAL VOLUME SAMPAI HAL INI 240.72
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR

AGUS IR. RUSMAN KATIB ANDRI


Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER
BETON K - 250
PLAT, TUMPUAN DAN LEANING PADA DEUKER PLATE

L 0,15
b
a a
0,20 0,20 0,20 0,40
C C

0,20

T T I II

1,25
0,40

0,40 0,40 III

0,10 0,10
IV 0,40
d e d
0,10 0,10 0,30
Ukuran plat (m) Luas
Dimensi Beton Volume (m3)
No. Lokasi Lebar Tinggi Bentang (m2)
e T B a b c Plat Tumpuan Plat Tumpuan Leaning
1 00 + 825 1.00 1.00 10.00 0.40 1.40 0.26 0.36 0.26 3.64 2.64 0.08 6.36
2 01 + 150 1.00 1.00 10.00 0.40 1.40 0.26 0.36 0.26 3.64 2.64 0.08
3 02 + 100 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
4 02 + 739 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
5 02 + 900 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
6 03 + 366 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
7 04 + 036 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
SUB TOTAL VOLUME 70.328
TOTAL VOLUME SAMPAI HAL INI 70.328
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR

AGUS IR. RUSMAN KATIB ANDRI


Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER

BETON K - 250
PLAT, TUMPUAN DAN LEANING PADA DEUKER PLATE
L 0,15 Seksi 1
b
a a
0,20 0,20 0,20 0,40
C C

0,20

T T I II

1,25
0,40

0,40 0,40 III

0,10 0,10
IV 0,40
d e d
0,10 0,10 0,30
Ukuran plat (m) Luas
Dimensi Beton Volume (m3)
No. Lokasi Lebar Tinggi Bentang (m2)
e T B a b c Plat Tumpuan Plat Tumpuan Leaning
8 05 + 697 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
9 06 + 420 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
10 06 + 711 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15
11 03 + 125 2.00 1.00 10.00 0.45 2.50 0.33 0.83 0.31 8.25 3.12 0.15

SUB TOTAL VOLUME 46.08


TOTAL VOLUME SAMPAI HAL INI 116.41
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR
AGUS IR. RUSMAN KATIB ANDRI
Nip. 19620808 200701 1 012 SITE ENGINEER QUANTITY ENGINEER
SUMMARY!A1

825 448,325
1,150 448,650 0 3300 450900 454200
2,100 449,600 3300 3579 454200 454479
2,739 450,239 3651 3703 454551 454603
2,900 450,400 3726 5049 454626 455949
3,366 450,866 5353 6354 456253 457254
4,036 451,536 6658 7754 457558 458654
5,697 453,197 0 3000
6,420 453,920
6,711 454,211
3,125 450,625
0

1m 6.3640 2 12.73
2m 11.520 9 103.68
116.41
LAPIS RESAP PEREKAT

0.12

LEBAR LEBAR RATA- PANJANG LUAS TOTAL


NO STA RATA (M') LUAS (M2) JUMLAH
(M') (M') (M2)

Seksi 2, Panjang jalan = 22500m


Jalan Lurus = 70 % 15750 0.12 3.00 0.36 1,969 708.75
Jalan Tikungan = 30 % 6750 0.12 20.00 2.40 844 2,025.00

Seksi 3, Panjang jalan = 2130 m

SUB TOTAL VOLUME 2,733.75


TOTAL SAMPAI HAL INI 2,733.75
DISETUJUI DIPERIKSA DIBUAT
PENGAWAS LAPANGAN KONSULTAN KONTRAKTOR

AGUS Rusman Katib Andri


Nip. 19620808 200701 1 012 Site Engineer Quantity Engineer