Professional Documents
Culture Documents
AACE g30273 Aace Ce Novdec2012
AACE g30273 Aace Ce Novdec2012
COST
TM
THE AUTHORITY FOR TOTAL COST MANAGEMENT
November/December 2012
ENGINEERING www.aacei.org
INTEGRATED
COST-SCHEDULE
RISK ANALYSIS
ESTIMATE ACCURACY:
DEALING WITH REALITY
QUANTIFYING ESTIMATE ACCURACY
AND PRECISION FOR THE
PROCESS INDUSTRIES:
A REVIEW OF INDUSTRY DATA
COMMON ERRORS IN
DEALING WITH PROJECT RISK
CONTENTS
COST ENGINEERING
TECHNICAL ARTICLES
5 Integrated Cost-Schedule Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP
ALSO FEATURED
2 AACE International Board of Directors 45 2012-2013 Nominating Committee
2 Cost Engineering Journal Information 46 The AACE International Online Store
16 2012 Statement of Ownership 49 Professional Services Directory
38 2013 Constitution and Bylaws 49 Index to Advertisers
Amendments 52 Calendar of Events
THE AACE INTERNATIONAL ONLINE BUTTON - This edition content online associated with that article or feature. Direct
of the Cost Engineering journal has access to additional ma- your browser to www.aacei.org and look for the online but-
terial on the AACE International website, www.aacei.org. ton to access additional resources. If you are already reading
Anytime you see the symbol at center, there is additional the electronic version, just click the online button directly.
VICE PRESIDENT-REGIONS
OUR VISION - To be the recognized technical authority in cost and schedule management
Julie Owen, CCC PSP
for programs, projects, products, assets, and services.
213.922.7313 / vpregions@aacei.org
DIRECTOR-REGION 1 OUR MISSION - The members of AACE® enable organizations around the world to achieve
Matthew Nicholas, PSP thier investment expectations by managing and controlling projects, programs, and port-
416.498.1303 / dirregion1@aacei.org folios; we create value by advancing technical knowledge and professional development.
DIRECTOR-REGION 9
Jim Perry Policy Concerning Published Columns, Features, and Articles
+33.14.7664729 / dirregion9@aacei.org
Viewpoints expressed in columns, features, and articles published in Cost Engineering journal are solely those
EXECUTIVE DIRECTOR of the authors and do not represent an official position of AACE International. AACE International is not en-
Dennis G. Stork dorsing or sponsoring the author’s work. All content is presented solely for informational purposes. Columns,
304.296.8444 / dstork@aacei.org features, and articles not designated as Technical Articles are not subject to the peer-review process.
POWER
The ambition
to make history.
..........................................................................................................
Risk Analysis doesn’t have to be
complicated.
Acumen Risk: Risk ReInvented
Proactively reduce risk exposure with the first easy-to-use and truly
integrated cost/schedule risk analysis and risk register software tool.
www.projectacumen.com/risk
TECHNICAL ARTICLE
Integrated Cost-Schedule
Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP
Abstract: This article is based on AACE International Recommended Practice 57R- consistent results for project schedule
09 that defines the integrated analysis of schedule and cost risk to estimate the and cost in each iteration.
appropriate level of cost and schedule contingency reserve on projects. The main
contribution of this RP is to include the impact of schedule risk on cost risk and Context
the need to hold cost contingency reserves. Additional benefits include the ap- Corporate culture is important. The
plication of the risk drivers method of using risks to drive the Monte Carlo simu- organization should be “risk-aware.”
lation of a resource-loaded CPM schedule. By using the risks, one can prioritize Management sets this tone, must want to
the risks to cost, some of which are commonly thought of as risks to schedule, so know the truth about the risks to the
that risk mitigation may be conducted in an effective way. The methods presented project, and must view the risk analysis as
in the RP are based on integrating the cost estimate with the project schedule by an important input to project success.
resource-loading and costing the schedule’s activities. Using Monte Carlo tech-
Management must be seen to use the risk
niques one can simulate both time and cost simultaneously, permitting calculation
of the impacts of schedule risk on cost risk. This article was presented as analysis results as they make key project
RISK.1043 at the 2012 AACE International Annual Meeting in San Antonio, Texas. decisions. Without this condition the
It was ranked as the number three paper out of 99 presentations given and rated analysis will fail, no matter how much
at the Annual Meeting. sophisticated software and training the
staff has had, because the risk data will
Key Words: Contingency, cost, estimates, mitigation, Monte Carlo, projects, risk, not be high-quality.
and schedule Traditionally, schedule risk has not
been a major factor in assessments of
T
his article describes an exercise to improve the project’s cost risk. More recently cost risk analyses
improvement in cost risk prospects for success. have included attempts to represent
analysis over the traditional The platform of this cost risk analysis uncertainty in time, but usually these
methods that address cost risk is a resource-loaded project schedule. analyses occurred outside of the
without explicit reference, or any One may use a summary schedule or a framework of the project schedule.
reference at all to the project schedule detailed project schedule. The budget is Only recently have the tools been
and its risk. It is now known how to assigned to the activities using summary available to include a full analysis of the
represent the role that schedule risk has resources to insert the entire budget into impact of schedule uncertainty on the
in driving project cost, because the longer the schedule at the activity level. uncertainty in cost. The Monte Carlo tools
some resources, such as engineering or Monte Carlo simulation is the most first calculated labor cost proportional to
construction work, the more they cost. commonly used approach to analyzing the duration of activities. This was not a
One can also identify the risks that cause the impact of multiple risks on the overall complete assessment of cost risk because
overall cost (and schedule) objectives to project schedule or cost risk. Simulating a it ignored other cost-type risks that are
be placed in jeopardy, so one can use the resource-loaded project schedule derives not related to schedule such as risks
results to conduct a risk mitigation affecting the time dependent resources’
delivery, needs a relationship from Simple Construction Case Study dependent resources; or “material-
its finish date to a successor. A simple schedule example of a 28- type”—time-independent resources, as
• The schedule should not rely on month construction project is shown in mentioned above. An alternative
constraints to force activities to start figure 1. This figure and several others method of applying resources to the
or finish by certain dates. It should shown in this article are screen shots schedule, when the cost estimate is not
use logic for this purpose. Date from Primavera Risk Analysis, formerly specified down to the detail of the
constraints can turn a CPM network Pertmaster Risk Expert, now owned by schedule activities, is to apply resources
into a calendar. Oracle. to hammocks that span the activities
• Lags and leads are appropriate only that get the resources.
in limited circumstances and are Resources Loaded into the CPM
generally to be avoided in project Schedule Resources
scheduling. And, Loading resources into the CPM Resources are applied to the
• The schedule used should be the schedule for the purpose of integrated schedule activities, Sometimes, in doing
statused current schedule. cost-schedule risk analysis can be this, the cost estimate and schedule have
accomplished using summary resources. evolved largely independently of one
These points are consistent with Summary resources are not sufficiently another and the cost estimates are not
those found in GAO Cost Estimating and detailed to perform resource leveling. consistent with the activity durations. It
Assessment Guide [1]. Their purpose is to get the entire budget is important that if the estimate and
It is good scheduling practice to into the project schedule. Simple schedule are initially developed
review the total float values to make categories of resources that can be given independently of one another, that they
sure they are reasonable. Large float budgeted values and placed on the are reconciled prior to holding the risk
values may indicate incomplete logic; activities they work on are needed. assessment, or else the implied “daily
and perhaps, the need to introduce and Resources used on the simple rates” of cost will be wrong.
logically link additional activities. construction project are shown in table The costs that result from placing
2. the resources on the example project
In addition, the resources need to schedule are shown in table 3.
be tagged as “labor-type”—time-
THE RISK DRIVER METHOD
several risks, which cannot be of very large and complex projects. Risks • The risk also has an impact on
individually distinguished and kept track to project schedule and cost include: project activities if it does occur.
of. Also, since some risks will affect This impact is specified as a range of
several activities, one cannot capture • risk events that may or may not possible impacts, stated in multiples
the entire influence of a risk using happen; and, of the activity’s estimated duration
traditional 3-point estimates of impact • uncertainties that will happen but and cost. If the risk does occur, the
on specific activities. with uncertain impact. durations and costs of the activities
Using the risk driver method, the in the schedule that the risk is
risks that are chosen for the analysis are Once the risks are identified from assigned to will be multiplied by the
generally those that are assessed to be the risk register, certain risks data are multiplicative impact factor that is
“high” and perhaps “moderate” risks collected: chosen from the impact range for
from the risk register. Risks are usually that iteration.
strategic risks rather than detailed, • Probability of occurring with some • The risks are then assigned to the
technical risks. measurable impact on activity activities and resources they affect.
While the risk data are collected in durations and/or costs. In any
interviews with project SMEs, new risks iteration during the Monte Carlo Collection of risk data relies on the
emerge and are analyzed. There may be simulation, a risk will occur or not processes of the risk identification and
perhaps 20-40 risks, even in the analysis depending on its probability. risk prioritization. It is important during
Table 4 — Example Risks and Their Parameters For The Case Stude
Table 6 — Summary Schedule Risk Analysis Results for the Example Construction Project
Table 7 — Summary Cost Risk Analysis Results for the Example Construction Project
Figure 5 — Activities Added to Provide for a Risk That Commissioning May Not Complete Successfully
Tables 10 and 11 show which risks These schedule risks may be missed of-effort resources, such as the project
are the most important for schedule and or underestimated if the cost risk management team or QA/QC, are
for cost. analysis does not explicitly handle the extreme examples of time-dependent
relationship of time and cost risk, as is resources, since if the project duration
Risk Mitigation Using Prioritized Risks shown in the approach described in this exceeds its planned duration the cost of
Using the prioritized risks in table 8, article. It is common to find that these resources will increase over their
one can recommend risk mitigation. The schedule risks are important in driving budgeted amount.
first thing to recognize is the inaccuracy cost risk. It reinforces the benefits of The integrated cost-schedule risk
of the estimates, which is viewed as integration of cost and schedule. analysis is based on:
moderate at risk impact multipliers of
95%, 105% and 115%. However, this risk Conclusion • A high quality CPM schedule.
is 100 % likely to occur, since estimating Integrating cost and schedule risk • A contingency-free estimate of
error is with one until project financial into one analysis, based on the project project costs that is loaded on the
completion, and it is assigned to each schedule loaded with costed resources activities of the schedule using
activity in the project, hence its from the cost estimate provides both: resources distinguishing them by
importance. The next item to be their time-dependent and time-
concerned about is the probability of • more accurate cost estimates than if independent nature.
problems during commissioning, which the schedule risk were ignored or • Good-quality risk data that is usually
is also the highest schedule risk. The next incorporated only partially; and, collected in risk interviews of the
largest item would be the unavailability • illustrates the importance of project team, management and
of key engineering staff. Down the list at schedule risk to cost risk when the others knowledgeable in the risk of
position five is the inaccuracy of the durations of activities using labor- the project. The risks from the risk
schedule. type (time-dependent) resources register are used as the basis of the
In fact, in the simple example the are risky. risk data in the risk driver method.
authors created for this article, only the The Risk Driver Method is based in
top risk to project cost is a pure cost risk. Many activities such as detailed the fundamental principle that
The other important risks are mostly engineering, construction or software identifiable risks drive overall cost
schedule risks (some with cost risk development are mainly conducted by and schedule risk and that one can
components, see table 4) that increase people who need to be paid even if their model this process. And,
cost if their activities are longer than work takes longer than scheduled. Level- • A Monte Carlo simulation software
assumed in the schedule. program that can simulate schedule
Everything
See more at
http://ScheduleAnalyzer.com
Estimate Accuracy:
Dealing With Reality
John K. Hollmann, PE CCE CEP
Abstract: This article reviews over 50 years of empirical cost estimate accuracy known to be a “disaster” when systemic
research and compares this reality to common but unrealistic management ex- risks are present [27].
pectations. The empirically-based accuracy research of John Hackney, Edward One researcher said this behavior
Merrow, Bent Flyvbjerg, and others on large projects in the process industries is verges on “criminal” [19]. Cost disasters
summarized. The article then highlights risk analysis methods documented in re- and criminality are economic in nature,
cent AACE Recommended Practices that yield outputs based upon and compara- but deadly serious to owners, investors
ble to empirical reality. Tragically, many cost engineers are facilitating and tax-payers; we must ultimately take
management’s collective and sometimes willful biases regarding accuracy by using responsibility for our role in their
flawed, unreliable risk analysis methods; those who use empirically valid practices economic well-being. To help improve on
face the fate of Cassandra. The article is intended as a fundamental reference on the situation, this article surveys the
the topic of accuracy, as well as a call for our profession to use reliable practices
research facts (reality), exposes flawed
and speak the truth to management. Readers will gain an understanding of esti-
mate accuracy reality, the risks that drive it, management’s biases about it, and practices. and highlights better practices.
methods that analyze risks and address the biases in a way that results in more The article summarizes data from
realistic accuracy forecasts, better contingency estimates and more profitable in- well referenced studies by others;
vestments. This article was first presented as RISK.1027 at the 2012 AACE Inter- however, the data confirms the author’s
national Annual Meeting in San Antonio, Texas. experience. The author’s data and
observations are added, as well as
Key Words: Cost estimate accuracy, recommended practices, and risk analysis observations by others. While fact and
opinion are mixed, it is hoped that
A
readers will draw the same conclusions as
ccuracy is a measure of how a and how well risk analysis methods
the article and work to improve the
cost estimate will differ from forecast it is generally poor.
situation.
the final actual outcome. It is Investment decision makers seem
also a measure of cost particularly unaware of our research and
Studies of Overall Estimate Accuracy
uncertainty or risk (these terms are recommended practices. Sometimes they
How accurate have cost estimates
essentially synonymous in Total Cost are aware, but seem to ignore them.
been for owners? To answer this,
Management (TCM). Worse, many cost engineers facilitate
references providing empirical data on
Empirical estimate accuracy data has management ignorance by standardizing
estimate accuracy and cost uncertainty
been researched for over 50 years [30]. In their wishful thinking (i.e., tunneling or
were sought. This article focuses on
addition, reasonably reliable practices for neglecting sources of uncertainty) as
engineering and construction projects in
quantifying project cost uncertainty have exemplified by bias towards 10%
the process (e.g., oil, gas, chemicals,
been recommended by AACE and others. contingency and +10/-10% range [42].
mining, metals, utilities, etc.) and
However, the level of industry Poor investment decisions may result
infrastructure (often associated with
understanding of the reality of accuracy from using risk analysis methods that are
process plant projects) industries. These
were not used). However, the author’s for-design, signed-off process and overrun; there is a huge potential for
experience is that process industry instrumentation diagrams (P&IDs) for all overruns if the scope is more poorly
funding decisions are being made based process and utility units; the author rarely defined than Class 3. Note that the
on scope definition somewhat better sees this level of definition at the time of Hackney and RAND models based on this
than AACE Class 4, but worse than Class 3. funds authorization [4]. data are available in working Excel tools
Research indicates that the design The key observation from table 2 is found at the AACE website
development necessary to thoroughly that even projects funded on better scope (www.aacei.org [11]).
mitigate definitional risk includes issued- definition (AACE Class 3) tend to be
Table 3 — Reported Accuracy Ranges from Owner and EPC Contractor Risk Analyses
3. Some systemic risks are difficult to established [4, 21, 22, 35, and 45]. While 4. Estimating “all” project cost risk is
measure and/or politically sensitive. including, “incompetent management,” not part of the job (not in my work
in a risk register is problematic, it is scope).
The tools for rating scope necessary to identify and quantify such
development, as well as competency risks. The risk analyst must have If one declared in the Basis of
and project system discipline (e.g., weak sufficient independence to do so. Estimate reports that, “most significant
change management) are well risks were excluded” and/or “past
unreality for decades. The real p80 or The Project Size Dichotomy representative distribution of
p90 is likely to be unprofitable; as shown There is less empirical research of actual/estimate values observed by the
in studies, the least p90 capital cost small project estimate accuracy because author for small project portfolios; often,
growth is >40 to 50%. If management these projects are individually less of a no projects overrun by more than 10%.
faced this reality, no project would ever threat to overall profitability and In this “cresting wave” pattern, most
be authorized without stellar scope shareholder’s perceptions. However, we projects spend all their funds, while
definition and optimization, top-notch know that the realities of small and large some return all or some of the excess; for
planning, team building, risk projects differ; small projects are biased this outcome, management and/or
management, and all of the other best to overestimating and underruns. As teams are rewarded. The more that
practices we know of. Isn’t that the stated by one researcher, “when a funds are wasted, the sharper the peak
point? Why are we facilitating anything project team sets a soft (cost) target, between 0.9 and 1.1. Perversely, the
less? Why do we let them assume that about half of the unneeded funds are more “accurate” the outcome, the less
poor practices are a safe bet when they usually spent…about 70% of small desirable (though best rewarded) it is;
are courting disaster! projects underrun” [29]. underruns and tight accuracy often
The lesson from the empirical This research also indicated that in indicate overfunding and wasted capital
history (table 1) and the practice history small project systems, overruns tend to rather than excellent project control
(table 2) is that we need to address the be punished. To avoid punishment (in discipline
entire scope of risks (project-specific, less disciplined cultures) teams avoid The small vs. large project overrun
systemic, and escalation) and the overruns by including “fat” (i.e., above- dichotomy can induce a kind of corporate
empirical “reality” of uncertainty on the-line contingency) in the base schizophrenia. Many owner companies
large process industry projects. Research estimate because high visibility have “major project” organizations that
by others points in the same direction contingency is often poorly received by are separate from small or plant-based
[16, 17, 18, 19, 22, 27, 32, 33, 42]. AACE management for any project size. This organizations. A newly formed major
is currently developing a Decision and can bias a company’s perception of risk project group will often inherit the small
Risk Management Professional (DRMP) and partly explain their misguided project system trait of risk-ignorance
Certification that will focus on risk targets. (expectation of underruns.) They do not
identification and quantification Few researchers study small projects appreciate that EPC contractors for major
competencies, including AACE because not only is record keeping lax, projects prepare base estimates with less
Recommended Practices that document but underruns are rewarded and are not fat because reviews expose fat and there
reliable methods. seen as a problem despite being is sometimes a bias to keep estimates
associated with wasteful capital low to see the project get funded. The
spending. Figure 2 shows a combination of small project target-
Abstract: This article quantifies industry metrics for estimate accuracy based on comprehensive set of industry projects.
a sample of 462 capital projects executed by the process industries over the last Despite these limitations, these studies
20 years, comparing estimated costs at the various stages of project definition to were valuable as they provided a set of
actual costs, normalized for a number of factors. The authors then contrasted the industry norms that quantify estimate
results from the industry survey with industry expectations, as presented in AACE accuracy based on actual project data.
International Recommended Practice 18R-97. The results of our survey indicate In the absence of more robust
there is a much greater level of variability in estimate accuracy as compared to industry data, the cost engineering
industry expectations. Further analysis demonstrates that projects which have community has defaulted to a range of
completed a definitive project scope at authorization benefit from a reduction in sources to quantify typical estimate
estimate variability as compared to industry. This article was first presented as accuracy, including in-house data,
RISK.1100 at the 2012 AACE International Annual Meeting in San Antonio, Texas.
historical experience, or industry
standards and Recommended Practices
Key Words: Capital projects, cost, estimate accuracy, process industries and scope
(RP) [1]. The objective of this article is to
enhance industry’s understanding of
I
n virtually all applications and All of these stakeholders have estimate accuracy by providing
scenarios, a cost estimate’s value is different uses for the estimate, but share
benchmarks of estimate accuracy for a
related to its capacity to predict the a need in that they are relying on the range of estimate classifications. The
final cost of a planned scope of estimate to have a reasonable degree of authors calculate these metrics from a
work. The importance of an accurate accuracy. large sample of industry projects
estimate confronts the cost estimator The cost engineering community has executed by the oil and gas, chemical
from all directions—from: devoted a substantial amount of time to process, and mining and minerals
consider practices and processes to industries over the last 20 years. Given
• the business/project sponsor, who is improve estimate accuracy [5,16,17]. In the importance of achieving a reasonable
relying on the estimate to quantify contrast, only a limited number of articles
level of accuracy and precision for cost
the expected return on the capital and papers have also quantified the estimates, the goal of this article is to
invested; estimate accuracy ranges using actual provide an independent measure of
• to the finance group, who is relying industry data from completed projects estimate accuracy and compare these
on the estimate to manage quarterly [3,12,13]. In these instances, the data results against current industry
cash flow; and, presented were only for a subset of expectations.
• to the project controls group, who is industry (i.e., mining and minerals) or a
using the estimate as the basis for specific type of project (i.e., megaprojects Review and Definitions
project cost and schedule control or new technology projects), and The authors first considered the
during execution. therefore were limited in an ability to definition of estimate accuracy as this
quantify estimate accuracy for a concept has been such an important part
Table 1 — Expected Estimate Accuracy Ranges for AACE International Estimate Classification
(adopted from 18R-97)
some cases, directly match the AACE sample of projects executed by the Figure 6 presents summary
International estimate classifications. As process industries over a 20-year period characteristics for this industry sample.
such, one must not think of these data as from 1988 to 2008. Cost data for the The industry projects were executed by
corresponding directly to particular project sample was collected as part of 62 different owner companies and
AACE International classifications, but an overall industry benchmarking effort include a range of project scopes, project
rather the range of possible AACE as directed by Independent Project types, and locations. The industry
International classification requirements Analysis (IPA) and managed through IPA’s sample consisted primarily of large
enforced by this set of companies at a project evaluation system benchmarking capital projects with a mean cost of $64
particular gate. However, the authors process (PES® is a registered trademark million (with a range from $10 million to
argue, that as an industry sample, they of IPA). $3.3 billion). The projects were executed
do provide a good approximation of the For the project data collection, primarily in North America, but also in
AACE International estimate classes interviews were conducted by IPA Europe, Asia, and the rest of the world
(which are approximations themselves). project analysts with the project teams (ROW)—primarily the Middle East and
In addition, a review of industry with over 2,000 variables captured to South America.
project systems have many similarities to reflect each project’s technical scope, For each project, cost estimate data
the AACE International RP 18R-97. For characteristics, use of best practices, and were collected at four distinct points: at
example, as projects move closer to full- cost/schedule outcomes. The industry the end of each FEL gate (estimated
funds authorization, the accuracy of the dataset employed for this study included costs), as well as at project completion
estimate relative to the expected 462 completed large capital projects for (actual costs). Cost deviation metrics
outcome should improve, as well as the which estimated costs were collected at were calculated based on equation 1.
requirements for greater definition and the various FEL phases and actual costs Project costs were normalized to a
knowledge regarding the project scope at project completion. constant currency and time period to
and execution plan. Based on this
review of these industry systems, figure
5 merges the AACE International
Estimate Classification system with the
Stage-Gated Work process based on this
review of company standards and
norms.
In general, estimates at the end of
appraise (or FEL 1) correspond to AACE
International Class 5, estimates at the
end of select (FEL 2) correspond to AACE
International Class 4, and estimates at
the end of define (FEL 3) correspond to
AACE International Class 3.
Study Results
This section presents the cost
deviation statistics for each FEL
phase/AACE International Estimate Class
based on the industry project sample.
Figures 7-9 present the cost deviation
distribution for estimates at the end of
FEL 1, FEL 2, and FEL 3, respectively.
Each figure presents the overall
distribution of cost deviation, as well as
the summary descriptive statistics (i.e.,
mean, median, standard deviation).
Based on the cost deviation metrics
as calculated using equation 1, a value of
0.00 means that the estimated costs
matches the actual cost exactly. Values Figure 7 — Cost Deviation Results for FEL 1 Estimates Compared to Actual Costs
Figure 10 — Industry Estimate Accuracy as Compared to the AACE International RP 18R-97 Ranges
Common
Abstract: Unfortunately, many people using risk management do not fully under- that should be followed when dealing
stand basic risk concepts and therefore use incorrect techniques in preparing and with risks. Here are the processes that are
implementing risk management plans. The author has reviewed and critiqued to be done as part of risk management
client risk management process and procedures, along with risk management [3]:
plans for projects, and the same mistakes reoccur on a regular basis. Based on
these reviews, this article will present the top ten errors people make in dealing • Prepare a Risk Management Plan—
with project risks and how these mistakes greatly reduce the value of risk man- This should be completed early in the
agement. The author has also done numerous projects where risk management project planning phase. First decide if
was successfully used, and this article will also discuss effective risk techniques risk management is needed. On
that should be used on all projects. If you think you know how to deal with project some small, simple projects it may
risks, read this article to see if you are making any of these common errors. You
not be value adding. But for most
may be surprised! This article was first presented as RISK.944 at the 2012 AACE
International Annual Meeting in San Antonio, Texas. projects risk management is needed.
The risk management plan should
Key Words: Contingency, projects, risk management, and schedule document the techniques, tools and
responsibilities for risk identification,
risk analysis, risk response planning
W
hen the word risk is used uncertain risk events, which can have and risk monitoring and control.
in casual conversation it good or bad impacts on the project. • Identify the Project Risks—The most
invariably has a negative Risk management includes the commonly used techniques are
connotation: risk is bad processes of identifying potential project brainstorming and checklists. As part
and should be avoided whenever risks, analyzing risks, planning responses of risk identification also identify any
possible. The dictionary reinforces this to the most important project risks, and triggers for each risk, which are early
negative connotation by defining risk as also monitoring and controlling risks over warning indicators that the risk event
the possibility of loss or injury, or the life of the project. The goal of risk may occur.
someone or something that creates or management is to maximize the effects of • Analyze the Project Risks—The
suggests a hazard [1]. potential opportunities, and minimize or simplest technique is assigning a
However, for project management eliminate the threats to the project value for the probability and impact
risk has a less threatening and more objectives. of each risk and calculating the risk
realistic definition as, “any uncertain factor. The risks are then prioritized
event or condition that, if it occurs, has a Risk Management Process and the highest scores are the
positive or negative effect on a project’s Before exploring the common errors threats and opportunities that
objectives” [2]. In this expanded scope of made in dealing with risks, let’s review should be actively managed as part
understanding, risk is associated with the suggested process steps for managing of risk response planning. On larger
uncertainty—the possibility that things project risks. This will ensure a common projects advanced risk analysis using
will not go as planned because of understanding of the sequential actions
expertise in flexible piping systems, opportunity for the painting identification process by not providing a
and release the internal contractor to earn some extra profit. focus on actual risk events and this is
maintenance group for work on The action of meeting with Jim and important because risk events have one
other projects. This is a share since getting his support increases the unique feature, and that is uncertainty!
you are taking advantage of the probability of the scope change
opportunity (using flexible piping) to being approved. • A risk cause is a definite event or
shorten the schedule, and the • Accept—The testing team leader circumstance that exists. A cause is a
contractor is making a profit on the informs you there is a chance the fact and has no uncertainty. For
work. integration testing on your software example, multiple job opportunities
• Enhance—Your company has been development project will not take as for top notch programmers, resulting
selected as the painting contractor long as the plan shows, but the from a shortage of computer
for a bridge renovation project. The probability is low and best case it programmers in the region, would be
project specification calls for a paint might save up to one week for the a risk cause.
with a 15-year life. However, your one year project. You decide to • Risk events are simply things that
company has developed a new epoxy record the opportunity in the risk may or may not happen. An example
paint that will last 30 years or more, register, but take no other actions at of a risk event would be losing one or
and it only costs 30% more than the this time since the impact to the more key software programmers to
standard paint (but has a higher project is minimal. another software company who
profit margin since it is a proprietary offers them more money.
product of your company). You notify Error #2: Confusing Risk Causes, Events • Risk impacts are the results that will
the project manager, Rita, of this and Impacts occur if the risk event happens. For
opportunity. She likes the added The first step taken by a team in the example above, if a key software
value, but the state Department of implementing the risk management plan programmer leaves for a higher
Transportation (DOT) Director will is risk identification, which is determining paying job, it probably will have an
have to approve the change. Rita which risks may affect the project and impact on the project cost and
suggests a meeting with the DOT understanding the characteristics of each schedule.
project engineer, Jim, to discuss the specific risk event. Common tools used by
benefits and enlist his support in many project teams for risk identification An effective risk identification
getting the change approved. Rita is are checklists and brainstorming along technique is expressing each project risk
confident Jim will support the scope with interviews of key project as a sentence. Your sentence should
change and help obtain the stakeholders. include the cause, risk event, and impact
necessary approval within the DOT. However, a common error during risk as shown below [5]:
This is an opportunity for the project identification is not differentiating
since the better paint will last between risk causes, risk events, and
substantially longer, plus an impacts. This failure can dilute the risk
When risk mistake #1 was discussed, on a software project. This provides more likely to happen for opportunities
the commonly used risk responses for the project team with a known cost, and less likely to happen for threats.
opportunities were described. Listed next and the threat of a cost overrun Contingency plans are more specifically
are the common risk responses for belongs to the vendor (along with the actions that will be taken if and when
threats [4]: the opportunity to complete the the risk event occurs. Risk response
work for less money and make more planning should deal with both!
• Reduce (Also called Mitigation)— profit). Let’s revisit the common risk
This response seeks to reduce the • Accept—This response is deciding responses for threats covered in mistake
probability and/or impact of a not to do anything about the risk. #7. The mitigation example was losing a
negative risk event. An example of This may be because no other key project resource because of a person
reduce is offering a performance actions are feasible, or the risk factor leaving the company. The contingency
bonus to a key project resource to isn’t significant. The response can be plan for this example would be
mitigate the potential of the person active acceptance, which means identifying a back-up resource (either
leaving the company before project developing a contingency plan if the internal or a contractor) that could step in
completion. The performance bonus risk event occurs. An example is and handle the work if the person does
reduces the probability of the person building a new store in upstate New leave the company. For the acceptance
leaving. York in January. It will snow—so example of building a store in upstate
• Eliminate (Also called Avoidance)— active acceptance is the best New York in winter weather, contingency
This response looks to eliminate the approach. You can’t control the planning could be adding some extra days
threat by taking actions to cause the weather! in the schedule as an allowance for non-
risk to go away completely. This is working days because of snow, and/or
usually done by eliminating the In summary, mitigation is just one including money in the budget for plastic
causes. When you avoid, the risk is risk response technique, and it is sheeting and space heaters so work can
gone! There is no need to do any specifically used for threats. Do not call continue even if snow occurs.
contingency planning, because the risk response planning ‘mitigation’—the One final comment is that not all
risk no longer exists. An example of correct term to use for describing what risks need a contingency plan! The
avoidance is a developer looking to steps will be taken to deal with risks is example used for transference was using
build a new store decides not to ‘risk response plan.’ a firm fixed price contract with a vendor
build in a certain town because of a for the data migration work on a software
hostile town board which probably Error #8: Not Considering Contingency project. The risk impact now belongs to
will hold up the zoning approval. Plans Along With Response Plans the vendor so the project team doesn’t
• Transfer—This response shifts some As mentioned with mistake #7, the need to worry about a cost overrun. The
or all of the threat to a third party. correct term to use for describing what example used for avoidance was a
The risk doesn’t go away, but the steps will be taken to deal with risks is developer looking to build a new store
ownership and impact of the risk ‘risk response plan,’ but don’t forget that deciding not to build in a certain town
belongs to somebody else. An should also include a contingency plan! because of a hostile town board. Since
example of transference is using a To clarify the difference, the risk the decision was made not to build in the
firm fixed price contract with a responses are actions taken before the town with a hostile town board, the risk
vendor for the data migration work risk event occurs to make the risk event
•
D.R. McNatty and Associates, this page bership every month by placing an ad in the
Cost Engineering journal.
EcoSys, inside front cover
PLACE your products/services in front of
▲
•
Faithful+Gould, page 48 over 50,000 users each month with a banner
Infinitrac, this page ad at our website, www.aacei.org.
EXHIBIT at the AACE International Annual
▲
•
Management Technologies, this page
Meetings, and contact AACE International
Ron Winter Consulting, page 16 members face to face.
Pages 5-15
Integrated Cost-Schedule Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP
This article was presented as RISK.1043 at the 2012 AACE International Annual Meet-
ing in San Antonio, Texas.
Article Reference Number - 29188
Pages 17-27
Estimate Accuracy: Dealing With Reality
John K. Hollmann, PE CCE CEP
This article was first presented as RISK.1027 at the 2012 AACE International Annual Meet-
ing in San Antonio, Texas.
Article Reference Number - 29189
52 COST ENGINEERING NOVEMBER/DECEMBER 2012
JOB SITE,
MEET INSIGHT.
Learn about Sage solutions for estimating and construction.
» Visit our website at SageCRE.com/bidready to get the facts.
Make it easier for your estimators to bid on and win more projects with our business-aware, people-
connected applications for specialty and general contractors. Over 40,000 construction and real
estate firms, including over half of the ENR 400, rely on Sage solutions to manage more than 400,000
jobs and 5.7 million subcontracts every year. Join them and gain the insight to get job-ready today.
© 2012 Sage Software, Inc. and its aɉliated entities. All rights reserved.
Sage 50 • Sage 100 Contractor • Sage 300 Construction and Real Estate • Sage Construction Anywhere • Sage Estimating