Download as pdf or txt
Download as pdf or txt
You are on page 1of 56

THE JOURNAL OF AACE® INTERNATIONAL -

COST
TM
THE AUTHORITY FOR TOTAL COST MANAGEMENT

November/December 2012

ENGINEERING www.aacei.org

INTEGRATED
COST-SCHEDULE
RISK ANALYSIS
ESTIMATE ACCURACY:
DEALING WITH REALITY
QUANTIFYING ESTIMATE ACCURACY
AND PRECISION FOR THE
PROCESS INDUSTRIES:
A REVIEW OF INDUSTRY DATA
COMMON ERRORS IN
DEALING WITH PROJECT RISK
CONTENTS

COST ENGINEERING

TECHNICAL ARTICLES
        5    Integrated Cost-Schedule Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP

      17    Estimate Accuracy: Dealing With Reality


John K. Hollmann, PE CCE CEP

      28    Quantifying Estimate Accuracy and


Precision for the Process Industries:
A Review of Industry Data
Alexander Ogilvie, Robert A. Brown Jr., Fredrick P. Biery and Paul Barshop

      39    Common Errors in Dealing With Project Risk


Joseph A. Lukas, PE CCE

ALSO FEATURED
                   2        AACE International Board of Directors                 45        2012-2013 Nominating Committee
                   2        Cost Engineering Journal Information                  46        The AACE International Online Store
                 16        2012 Statement of Ownership 49        Professional Services Directory
38        2013 Constitution and Bylaws 49        Index to Advertisers
Amendments                  52        Calendar of Events

THE AACE INTERNATIONAL ONLINE BUTTON  - This edition content online associated with that article or feature. Direct
of the Cost Engineering journal has access to additional ma- your browser to www.aacei.org and look for the online but-
terial on the AACE International website, www.aacei.org. ton to access additional resources. If you are already reading
Anytime you see the symbol at center, there is additional the electronic version, just click the online button directly.

COST ENGINEERING  NOVEMBER/DECEMBER 2012 1


CONTENTS
AACE INTERNATIONAL
BOARD OF DIRECTORS
PRESIDENT
Marlene Hyde, CCE EVP
COST ENGINEERING Established 1958
303.940.3200 / president@aacei.org Vol. 54, No.6/November/December 2012

PRESIDENT-ELECT Managing Editor Marvin Gelhausen


John J. Ciccarelli, PE CCE PSP mgelhausen@aacei.org
303.940.3200 / preselect@aacei.org
Art Director Noah Kinderknecht
PAST PRESIDENT nkinderknecht@aacei.org
Michael R. Nosbisch, CCC PSP
562.733.2472 / pastpres@aacei.org Graphic Designer Cevin Thornbrugh
cthornbrugh@aacei.org
VICE PRESIDENT-ADMINISTRATION
Martin Darley, CCC FRICS Advertising Sales Garth Leech
304.296.8444   fax - 304.291.5728
713.372.2426 / vpadmin@aacei.org gleech@aacei.org
VICE PRESIDENT-FINANCE
John C. Livengood, CFCC PSP HEADQUARTERS
202.669.1360 /vpfinance@aacei.org 1265 Suncrest Towne Centre Dr
Morgantown, WV 26505-1876
VICE PRESIDENT-TEC 800.858.COST    fax - 304.291.5728 
George Whyte, CCC CEP EVP
301.957.7434 /vptec@aacei.org AACE® International - The Authority for Total Cost Management
TM

VICE PRESIDENT-REGIONS
OUR VISION - To be the recognized technical authority in cost and schedule management
Julie Owen, CCC PSP
for programs, projects, products, assets, and services.
213.922.7313 / vpregions@aacei.org
DIRECTOR-REGION 1 OUR MISSION - The members of AACE® enable organizations around the world to achieve
Matthew Nicholas, PSP thier investment expectations by managing and controlling projects, programs, and port-
416.498.1303 / dirregion1@aacei.org folios; we create value by advancing technical knowledge and professional development.

DIRECTOR-REGION 2 Cost Engineering (ISSN: 0274-9696/12) is published bi-monthly by AACE International, Inc, 1265 Suncrest Towne Centre Dr,


Maria Cristina Baltazar, PSP Morgantown, WV 26505 USA. Periodicals postage paid at Morgantown, WV, and at additional mailing office. POSTMASTER:
410.276.0076 / dirregion2@aacei.org Send address changes to AACE International; 1265 Suncrest Towne Centre Dr, Morgantown, WV 26505-1876 USA. Customer
#7012359 (APC), Publications Mail Agreement No 40624074, Return undeliverable Canadian addresses to PO Box 503, RPO
DIRECTOR-REGION 3 West Beaver Creek, Richmond Hill, ON L4B 4R6. Single  copies:  US$9  members/  US$14  nonmembers  (both  +  shipping),
James H. Carson, CCC CEP excluding special inserts available to AACE members only. Subscription rates: United States, US$72/year; all other countries,
770.444.9799 / dirregion3@aacei.org US$91/year. Overseas airmail delivery is available at US$99. Subscriptions are accepted on an annual-year basis only. Copyright
© 2012 by AACE International, Inc. All rights reserved. This publication or any part thereof may not be reproduced in any form
DIRECTOR-REGION 4 without written permission from the publisher. AACE assumes no responsibility for statements and opinions advanced by the
Logan Anjaneyulu, CCC CEP PSP contributors to its publications. Views expressed by them or the editor do not necessarily represent the official position of Cost
949.608.7371/ dirregion4@aacei.org Engineering, its staff, or AACE International, Inc. Printed in York, PA, USA. Cost Engineering is a refereed journal. All technical
articles are subject to review by a minimum of three experts in the field. To submit a manuscript for peer review, see author
DIRECTOR-REGION 5 guidelines  at  www.aacei.org  and  submit  a  200  word  or  less  abstract  to  editor@aacei.org..  PHOTOCOPY PERMISSION:
Earl J. Seabrook, III, CCC Authorization to photocopy articles herein for internal or personal use, or the internal or personal use of specific clients, is
713.372.0521 / dirregion5@aacei.org granted by AACE International, Inc., provided that the base fee of US$4.00 is paid directly to Copyright Clearance Center, 222
Rosewood  Drive,  Danvers,  MA  01923  USA.  Telephone:  978.750.8400.  For  those  organizations  that  have  been  granted  a
DIRECTOR-REGION 6 photocopy  license  by  CCC,  a  separate  system  of  payment  has  been  arranged.  The  fee  code  for  users  of  the  transactional
Nicholas Kellar, CCC EVP PSP reporting service is ISSN-0274-9696/02 US$4.00. Payment should be sent directly to CCC. Copying for other than personal or
internal reference use without the express permission of AACE is prohibited. E-mail requests for photocopy permission on bulk
dirregion6@aacei.org
orders  may  be  sent  to  editor@aacei.org.  ADVERTISING COPY: Contact  Garth  Leech,  1265  Suncrest  Towne  Centre  Dr.,
DIRECTOR-REGION 7 Morgantown,  WV  26505-1876.  Telephone:  304.296.8444.  E-mail:  gleech@aacei.com  for  rates.  Advertisers  and  advertising
agencies assume liability for all content (including text, representation, and illustrations) of advertisements printed and also
Gulam Farooq Quadir, CCE
assume responsibility for any claims arising therefrom made against the publisher. The publisher reserves the right to reject
+966.50.3860575 /
any advertising that is not considered in keeping with the publication’s mission and standards. The publisher reserves the right
dirregion7@aacei.org to  place  the  word  advertisement with  copy  which,  in  the  publisher’s  opinion,  resembles  editorial  matter.  All  advertising
accepted  for  publication  in  Cost Engineering is  limited  to  subjects  that  directly  relate  to  the  cost  management  profession.
DIRECTOR-REGION 8
Current rate card available on request. COST ENGINEERING DEADLINES: Submissions for Cost Engineering must be received at
Keith Webb least 8 weeks in advance of the issue date. Send to: Editor, 1265 Suncrest Towne Centre Dr, Morgantown, WV 26505-1876 USA.
+61.8.93485045 / dirregion8@aacei.org Deadlines do not apply to technical papers.

DIRECTOR-REGION 9
Jim Perry Policy Concerning Published Columns, Features, and Articles
+33.14.7664729 / dirregion9@aacei.org
Viewpoints expressed in columns, features, and articles published in Cost Engineering journal are solely those
EXECUTIVE DIRECTOR of the authors and do not represent an official position of AACE International. AACE International is not en-
Dennis G. Stork dorsing or sponsoring the author’s work. All content is presented solely for informational purposes. Columns,
304.296.8444 / dstork@aacei.org features, and articles not designated as Technical Articles are not subject to the peer-review process.

2 COST ENGINEERING NOVEMBER/DECEMBER 2012


Bechtel is among the most respected engineering, procurement, and construction
companies in the world. We stand apart for our ability to get the job done right —
no matter how big, how complex, or how remote the project.

Opportunities in Project Controls include:


Project Estimators
Planners & Schedulers
Trend Engineers
Cost Engineers
Project Controls Managers
Discover more at bechtel.com/careers
CIVIL INFRASTRUCTURE
Bechtel is an Affirmative Action/Equal Opportunity Employer (AA/EOE).
COMMUNICATIONS

MINING & METALS

OIL, GAS & CHEMICAL

POWER

The ambition
to make history.
..........................................................................................................
Risk Analysis doesn’t have to be
complicated.
Acumen Risk: Risk ReInvented
Proactively reduce risk exposure with the first easy-to-use and truly
integrated cost/schedule risk analysis and risk register software tool.

Powerful analytics, consistently accurate results.

Coming September 18, 2012. Find out more:

www.projectacumen.com/risk
TECHNICAL ARTICLE

Integrated Cost-Schedule
Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP

Abstract: This article is based on AACE International Recommended Practice 57R- consistent results for project schedule
09 that defines the integrated analysis of schedule and cost risk to estimate the and cost in each iteration.
appropriate level of cost and schedule contingency reserve on projects. The main
contribution of this RP is to include the impact of schedule risk on cost risk and Context
the need to hold cost contingency reserves. Additional benefits include the ap- Corporate culture is important. The
plication of the risk drivers method of using risks to drive the Monte Carlo simu- organization should be “risk-aware.”
lation of a resource-loaded CPM schedule. By using the risks, one can prioritize Management sets this tone, must want to
the risks to cost, some of which are commonly thought of as risks to schedule, so know the truth about the risks to the
that risk mitigation may be conducted in an effective way. The methods presented project, and must view the risk analysis as
in the RP are based on integrating the cost estimate with the project schedule by an important input to project success.
resource-loading and costing the schedule’s activities. Using Monte Carlo tech-
Management must be seen to use the risk
niques one can simulate both time and cost simultaneously, permitting calculation
of the impacts of schedule risk on cost risk. This article was presented as analysis results as they make key project
RISK.1043 at the 2012 AACE International Annual Meeting in San Antonio, Texas. decisions. Without this condition the
It was ranked as the number three paper out of 99 presentations given and rated analysis will fail, no matter how much
at the Annual Meeting. sophisticated software and training the
staff has had, because the risk data will
Key Words: Contingency, cost, estimates, mitigation, Monte Carlo, projects, risk, not be high-quality.
and schedule Traditionally, schedule risk has not
been a major factor in assessments of

T
his article describes an exercise to improve the project’s cost risk. More recently cost risk analyses
improvement in cost risk prospects for success. have included attempts to represent
analysis over the traditional The platform of this cost risk analysis uncertainty in time, but usually these
methods that address cost risk is a resource-loaded project schedule. analyses occurred outside of the
without explicit reference, or any One may use a summary schedule or a framework of the project schedule.
reference at all to the project schedule detailed project schedule. The budget is Only recently have the tools been
and its risk. It is now known how to assigned to the activities using summary available to include a full analysis of the
represent the role that schedule risk has resources to insert the entire budget into impact of schedule uncertainty on the
in driving project cost, because the longer the schedule at the activity level. uncertainty in cost. The Monte Carlo tools
some resources, such as engineering or Monte Carlo simulation is the most first calculated labor cost proportional to
construction work, the more they cost. commonly used approach to analyzing the duration of activities. This was not a
One can also identify the risks that cause the impact of multiple risks on the overall complete assessment of cost risk because
overall cost (and schedule) objectives to project schedule or cost risk. Simulating a it ignored other cost-type risks that are
be placed in jeopardy, so one can use the resource-loaded project schedule derives not related to schedule such as risks
results to conduct a risk mitigation affecting the time dependent resources’

COST ENGINEERING NOVEMBER/DECEMBER 2012 5


• include representation of all the
work;
• has activities properly linked with
logic; and,
• includes enough detail to highlight
the main project milestones to be
used.

Experience shows that schedules of


300 – 1,000 activities can be used in a
risk analysis, even of projects as large as
$10 billion.
A detailed schedule may be used
but it has several limitations:

Table 1 — Example Project Cost by Activity • It is usually too difficult to identify


and correct a detailed schedule with
burn rate per day and the uncertainty in resources, some of which are time- many activities and logical
time-independent equipment or dependent and others are time- relationships for best practices.
material cost. independent: • Applying resources to activities is
The integrated cost-schedule risk more difficult for a detailed
analysis has several inputs, uses • Time dependent resources cost schedule than for a summary
specialized Monte Carlo simulation more the longer they are employed, schedule, even if summary
tools, and produces several valuable e.g., construction, detailed resources are used. And,
outputs. engineering, heavy-lift barges and • Simulation of the detailed schedule
drilling rigs, equipment, project with risks attached is often time
Inputs management team or procurement. consuming.
The Cost Estimate These resources may cost more or
The cost estimate is a basic input to less even if the activity duration is The first task in the risk analysis of
the risk analysis. Since the risk analysis fixed since the burn rate per day cost and schedule is to debug the
calculates the probability of achieving may be variable. schedule. The schedule needs to follow
the cost estimate and allows the • Time independent resources such as CPM scheduling recommended practices
organization to calculate the cost procured equipment and raw because it needs to calculate the
contingency reserve, the cost elements materials, even subcontracts milestone dates and critical paths
used as inputs need to be stated without (particularly before they are correctly during Monte Carlo simulation.
contingency embedded in them. A good awarded) may cost more or less It should be noted that the scheduling
rule is to make the cost estimate, for than the engineering estimate, but requirements for schedule risk analysis
each project element, the unbiased not because they take longer to and for high quality CPM schedules are
“most likely” estimate. Some estimators produce and deliver. the same.
are uncomfortable about stripping the The scheduling principles that are
contingency amounts from the estimate, In this article, the authors use a particularly important to the success of a
but the Monte Carlo simulation will re- simple project as an example. It is a Monte Carlo simulation include:
estimate the contingency reserve that is construction project estimated to cost
appropriate for: $624 million over a 28-month period. • All work needed to complete the
The cost estimate is shown in table 1. project must be represented in the
• the risks to the specific project’s schedule, because: (1) one does not
cost plan; and, The CPM Schedule know whether the critical path or
• the desired level of certainty of the The platform for the integrated cost- risk critical path will be a priority,
project management and other schedule risk analysis is a cost-loaded and (2) for integration of cost and
stakeholders. CPM schedule. To incorporate the schedule risk, one needs to be able
schedule risk into the cost risk, the to assign all the project cost to
The values of cost that will be schedule has to be taken into account appropriate activities.
assigned to the activities in the schedule directly and transparently. • The logic should not contain any
are based on the resources that will be For an integrated cost-schedule risk open ends, called “danglers.” This
used to accomplish and manage the analysis (and for schedule risk analysis) a means that: (1) each activity, except
work and the daily rate of those summary schedule needs to be: the first activity, needs a
resources. The cost of a project predecessor to drive its start date,
component may involve several assigned • integrated; and (2) each activity, except the final

6 COST ENGINEERING NOVEMBER/DECEMBER 2012


Figure 1 — Example Construction Project Schedule

delivery, needs a relationship from Simple Construction Case Study dependent resources; or “material-
its finish date to a successor. A simple schedule example of a 28- type”—time-independent resources, as
• The schedule should not rely on month construction project is shown in mentioned above. An alternative
constraints to force activities to start figure 1. This figure and several others method of applying resources to the
or finish by certain dates. It should shown in this article are screen shots schedule, when the cost estimate is not
use logic for this purpose. Date from Primavera Risk Analysis, formerly specified down to the detail of the
constraints can turn a CPM network Pertmaster Risk Expert, now owned by schedule activities, is to apply resources
into a calendar. Oracle. to hammocks that span the activities
• Lags and leads are appropriate only that get the resources.
in limited circumstances and are Resources Loaded into the CPM
generally to be avoided in project Schedule Resources
scheduling. And, Loading resources into the CPM Resources are applied to the
• The schedule used should be the schedule for the purpose of integrated schedule activities, Sometimes, in doing
statused current schedule. cost-schedule risk analysis can be this, the cost estimate and schedule have
accomplished using summary resources. evolved largely independently of one
These points are consistent with Summary resources are not sufficiently another and the cost estimates are not
those found in GAO Cost Estimating and detailed to perform resource leveling. consistent with the activity durations. It
Assessment Guide [1]. Their purpose is to get the entire budget is important that if the estimate and
It is good scheduling practice to into the project schedule. Simple schedule are initially developed
review the total float values to make categories of resources that can be given independently of one another, that they
sure they are reasonable. Large float budgeted values and placed on the are reconciled prior to holding the risk
values may indicate incomplete logic; activities they work on are needed. assessment, or else the implied “daily
and perhaps, the need to introduce and Resources used on the simple rates” of cost will be wrong.
logically link additional activities. construction project are shown in table The costs that result from placing
2. the resources on the example project
In addition, the resources need to schedule are shown in table 3.
be tagged as “labor-type”—time-
THE RISK DRIVER METHOD

Risk Data Inputs for the Risk Driver


Method
Applying first principles requires
that the risk to the project cost and
schedule is clearly and directly driven by
identified and quantified risks. In this
approach, the risks from the risk register
drive the simulation.
The risk driver method differs from
older, more traditional approaches—
wherein the activity durations and costs
are given a 3-point estimate which
results from the influence of potentially
Table 2 — Resources for Example Construction Project

COST ENGINEERING NOVEMBER/DECEMBER 2012 7


Table 3 — Cost Example Construction Project Showing Resources

several risks, which cannot be of very large and complex projects. Risks • The risk also has an impact on
individually distinguished and kept track to project schedule and cost include: project activities if it does occur.
of. Also, since some risks will affect This impact is specified as a range of
several activities, one cannot capture • risk events that may or may not possible impacts, stated in multiples
the entire influence of a risk using happen; and, of the activity’s estimated duration
traditional 3-point estimates of impact • uncertainties that will happen but and cost. If the risk does occur, the
on specific activities. with uncertain impact. durations and costs of the activities
Using the risk driver method, the in the schedule that the risk is
risks that are chosen for the analysis are Once the risks are identified from assigned to will be multiplied by the
generally those that are assessed to be the risk register, certain risks data are multiplicative impact factor that is
“high” and perhaps “moderate” risks collected: chosen from the impact range for
from the risk register. Risks are usually that iteration.
strategic risks rather than detailed, • Probability of occurring with some • The risks are then assigned to the
technical risks. measurable impact on activity activities and resources they affect.
While the risk data are collected in durations and/or costs. In any
interviews with project SMEs, new risks iteration during the Monte Carlo Collection of risk data relies on the
emerge and are analyzed. There may be simulation, a risk will occur or not processes of the risk identification and
perhaps 20-40 risks, even in the analysis depending on its probability. risk prioritization. It is important during

Table 4 — Example Risks and Their Parameters For The Case Stude

8 COST ENGINEERING NOVEMBER/DECEMBER 2012


risk data collection to be alert to management will be displeased with shorter together is called correlation. As
possible biases that crop up during them. shown below, the risk driver method
workshops. Some people want to The degree of correlation between causes correlation between activity
influence the results, while others the activity durations has long been durations, so one no longer has to
genuinely do not understand the viewed as being important for estimate (guess) at the correlation
concepts or have some cognitive bias understanding and estimating correctly coefficient between each pair of
that has to be overcome. One approach the project cost risk analysis. Correlation activities.
is to conduct risk interviews with arises if one risk affects two (or more) Probabilistic branching, or existence
individuals, or small groups, for which activities’ durations, or if a risk affects risk, requires another type of risk data—
there is a promise of confidentiality to the cost of two time-independent the probability that an activity and its
the participants. This is so they can talk resources. If a risk occurs, the degree to cost will exist on this project. Some risks
honestly and openly without fear that which their durations are longer and may cause activities to occur only if the

Table 5 — Assigning Risks to Activities

COST ENGINEERING NOVEMBER/DECEMBER 2012 9


distribution. For any iteration, the
software selects an impact
multiplicative factor at random from
the distribution. If the risk occurs
during that iteration, the
multiplicative factor selected
multiplies the duration of all the
activities to which the risk is
assigned.
• The cost risk factor is applied
differently depending on whether
the resource is labor-type or
equipment-type.
o For a labor-type resource, the
cost risk factor varies the daily
burn rate, representing more or
fewer resources applied, higher
or lower cost of those resources
per day. For these resources,
their total cost is also affected
Figure 2 — Histogram with Cumulative Distribution (S-Curve) by the uncertainty in the
for the Project Completion Date duration, but they may cost
more or less even if their
durations are as scheduled.
risk occurs. Some risk events such as the activities to which the risk is o For equipment-type resources,
failure of a test or a commissioning assigned. the cost risk factor varies the
activity, if they occur, may require new The risks operate on the cost and total cost. For these resources,
activities such as finding the root cause schedule as follows: the cost may be uncertain but it
of the failure, determining the recovery is not affected by time.
plan, executing the recovery plan, and • A risk has a probability of occurring
retesting the article. These activities will on the project. If that probability is Simulation Tools
all take time and increase project cost. 100%, then the risk occurs in every Monte Carlo simulation is the most
They can be inserted in the schedule as iteration. If the probability is less commonly applied method for
probabilistic branches, or existence than 100%, it will occur in that conducting quantitative risk analysis. A
activities, with time and cost percentage of iterations. Monte Carlo simulation calculates the
implications if they occur. • The risks’ impacts are specified by 3- possible project cost and schedule
point estimates of multiplicative values that may result from individual
Simulation Using the Risk Drivers factors, so a schedule risk will risks and translates them into project-
Method multiply the scheduled duration of level cost and schedule histograms or
In the simple example used in this the activity to which it is assigned. distributions from which statistical
article, the risks’ impacts are specified as The 3-point estimate, for instance, statements can be made.
ranges of multiplicative factors that are (low 90%, most likely 105% and high Since one does not know whether
then applied to the duration or cost of 120%), is converted to a triangular any risk will occur on any specific project

Table 6 — Summary Schedule Risk Analysis Results for the Example Construction Project

10 COST ENGINEERING NOVEMBER/DECEMBER 2012


Risk Data Used for the Construction
Case Study
The following is a sample case study,
but the risks are similar to those found
on real projects.
Suppose there is a project with the
activities shown in figure 1, and
resources/costs as shown in table 1, and
assigned to the activities as shown in
table 3. Also, suppose one has identified
risks through a workshop or interviews
and have elicited the probability and
time/cost impacts as shown in table 4.
After the risks are listed and their
parameters quantified, they need to be
assigned to the activities and their
resources. For this case study the risks
are assigned according to table 5.

Results From the Construction Case


Study Simulation
Figure 3 — Histogram with Cumulative Distribution (S-Curve) The schedule risk results from a
for the Project Cost Monte Carlo simulation are shown in the
histogram for the case study in figure 2.
or what its impact will be, one cannot a different combination of risks applied It shows that the deterministic date of
tell when a project will finish or how to this project schedule and cost. These 29 April 2013, is about 4% likely to be
much it will cost. One can only tell different combinations of input data achieved following the current plan and
probabilistically when the project might generally compute different completion without further risk mitigation actions.
finish and how much it might cost. dates and project costs. The Monte Carlo Next, suppose that the project
Suppose the simulation contains simulation provides probability stakeholders have agreed that their
3,000 iterations—separate runs using distributions of cost and schedule from acceptable level of confidence is at the
randomly-selected risk data—and which one can make probabilistic 80th percentile. At that point, it is 80%
creates 3,000 pseudo-projects. Each of statements about this project. likely that the current project plan with
the 3,000 projects could be the sample all of its risks will finish on that date or
project in this article, since it is based on earlier (and, if it is applied to cost, with

Table 7 — Summary Cost Risk Analysis Results for the Example Construction Project

Table 8 — Cost, Schedule and Interaction Effects

COST ENGINEERING NOVEMBER/DECEMBER 2012 11


that cost or less). At the P-80, the project
finishes on 26 November 2013, or
earlier, and needs about a 7-month
contingency reserve of time. These
results are shown in figure 2 and in table
6.
The cost risk results, including the
impact on cost of schedule risk, indicate
the need for a contingency reserve of
cost of about $169 million, or 27% at the
80th percentile (P-80). At that level there
is an 80 percent probability that the
project will cost $793 million or less,
given the risks and following the current
plan. These results are shown in figure 3
and table 7.
One can find out whether cost-type
risks or schedule-type risks are more
important in determining the cost Figure 4 — Cost and Time Results From the Simulation
contingency to, say the P-80 point. The
source of the cost contingency can be Correlation Between Cost and Schedule somewhat higher than is common in
discovered by eliminating all schedule The time-cost scatter diagram, these analyses.
risks, so as to compute the marginal shown in figure 4, is diffuse because
impact of cost risks, then repeating the there are some time-independent cost Probabilistic Branches or Project-
process by eliminating the cost risks and risks that affect the burn rate of labor- Busting Risks
computing the impact of schedule risks type resources and total cost of procured Some risks will add activities to the
on contingency. The results are shown in items. The cross-hairs shown on the project schedule if they occur, and hence
table 8. diagram cross at the deterministic point will add time and cost. Most often a
Table 8 shows that if only cost risks of 29 April 2013 and $624.2 million. The project plan assumes that the project
were present (the schedule is static) the sparse collection of points in the lower- goes well and that there are no major
cost contingency at the P-80 could be left quadrant indicate that there is only a problems. It is also common that
$78 million, whereas if only schedule 1% chance that this project will satisfy something goes wrong leading to a
risks were included (no cost risk on burn both cost and schedule targets without mandatory change in plans as the
rate or on procurement/materials), the contingency reserve. There is also a 95% project tries to recover from a
contingency needed at the P-80 is $103. chance that this project, following this discontinuous event. An example of this
These results depend on the case study plan, will overrun both cost and time problem might be the failure of the
assumptions, but in many examples of objectives. project at commissioning or final testing.
integrated cost and schedule risk There is clearly a positive slope These activities might be:
conducted on projects, the majority of running through the cloud or “football
the risk to cost arises from uncertainty in (US version) chart,” showing the strong • Determine the root cause of the
the schedule as it does in the example in impact on cost of schedule risks. The failure;
this article. correlation between time and cost is • Decide what to do;
77% in this case study, which is • Implement the action; and,

Figure 5 — Activities Added to Provide for a Risk That Commissioning May Not Complete Successfully

12 COST ENGINEERING NOVEMBER/DECEMBER 2012


specification that the commissioning will
fail 40% of the time.
The cost of the project goes up at
the P-80, since resources are placed on
the activities in the probabilistic branch.
The impact on cost and schedule of a
40% probable problem during
commissioning, (with the parameters
shown here), are shown in table 9.

Prioritized Risks to Schedule and Cost


If the risk results for the overall
schedule and cost are not “acceptable”
to the customer, the analyst can
prioritize the risks for the project
manager who will want to mitigate the
highest-priority risks.

• For schedule risk, one needs to


identify the most important risk by
taking each risk out entirely (make
Figure 6 — Schedule Impact of Probabilistic Branch on the probability = 0%) one-at-a-time
Commissioning and re-run the simulation to
determine the P-80 date, allowing
one to identify the risk that has the
• Re-test and, hopefully, pass the test activities, since when one introduces greatest marginal impact on the P-
this time. them they are given a duration of zero 80 date. Then, keeping the most
(0) days. Their uncertainty is represented important risk out, one explores the
One common characteristic of these by traditional 3-point estimates, but remaining risks to see which of
activities is that they are almost never their risk source is known. An those is next-most-important, and
found in the initial project schedule, implementation of probabilistic so forth. And,
which assumes success. However, in risk branching is shown in figure 5. The • For cost risk, this is done by taking
analysis, the possibility of test failure or probability that commissioning will not each risk out of the project one at a
some other discontinuous uncertain complete successfully the first time is time, computing the impact to the
event, must be modeled using existence estimated as 40%. P-80 cost compared to the all-in
risks or probabilistic branching. The schedule results for adding a results, and finding the risk that has
Suppose that the commissioning probabilistic branch are shown in figure the largest impact on the P-80 cost.
activity might uncover a problem that 6. Notice that the schedule is slightly bi- It is logical to identify the schedule
takes time to fix. Simple changes can be modal, with 60% of the results in the risks that have cost risk implications
made in the project schedule to left-hand part of the distribution and as described above, but the list of
accommodate this potentially project- 40% in the right-hand part. There is a bit the risks in order of priority may
busting occurrence. One cannot use the of a “shoulder” in the cumulative differ for time and for cost.
risk drivers that are assigned to existing distribution at 40%, that follows the

Table 9 — Schedule and Cost Impact of a 40% Probable Commissioning Risk

COST ENGINEERING NOVEMBER/DECEMBER 2012 13


Table 10 — Highest Priority Risks to Project Schedule at the P-80 Level of Confidence

Tables 10 and 11 show which risks These schedule risks may be missed of-effort resources, such as the project
are the most important for schedule and or underestimated if the cost risk management team or QA/QC, are
for cost. analysis does not explicitly handle the extreme examples of time-dependent
relationship of time and cost risk, as is resources, since if the project duration
Risk Mitigation Using Prioritized Risks shown in the approach described in this exceeds its planned duration the cost of
Using the prioritized risks in table 8, article. It is common to find that these resources will increase over their
one can recommend risk mitigation. The schedule risks are important in driving budgeted amount.
first thing to recognize is the inaccuracy cost risk. It reinforces the benefits of The integrated cost-schedule risk
of the estimates, which is viewed as integration of cost and schedule. analysis is based on:
moderate at risk impact multipliers of
95%, 105% and 115%. However, this risk Conclusion • A high quality CPM schedule.
is 100 % likely to occur, since estimating Integrating cost and schedule risk • A contingency-free estimate of
error is with one until project financial into one analysis, based on the project project costs that is loaded on the
completion, and it is assigned to each schedule loaded with costed resources activities of the schedule using
activity in the project, hence its from the cost estimate provides both: resources distinguishing them by
importance. The next item to be their time-dependent and time-
concerned about is the probability of • more accurate cost estimates than if independent nature.
problems during commissioning, which the schedule risk were ignored or • Good-quality risk data that is usually
is also the highest schedule risk. The next incorporated only partially; and, collected in risk interviews of the
largest item would be the unavailability • illustrates the importance of project team, management and
of key engineering staff. Down the list at schedule risk to cost risk when the others knowledgeable in the risk of
position five is the inaccuracy of the durations of activities using labor- the project. The risks from the risk
schedule. type (time-dependent) resources register are used as the basis of the
In fact, in the simple example the are risky. risk data in the risk driver method.
authors created for this article, only the The Risk Driver Method is based in
top risk to project cost is a pure cost risk. Many activities such as detailed the fundamental principle that
The other important risks are mostly engineering, construction or software identifiable risks drive overall cost
schedule risks (some with cost risk development are mainly conducted by and schedule risk and that one can
components, see table 4) that increase people who need to be paid even if their model this process. And,
cost if their activities are longer than work takes longer than scheduled. Level- • A Monte Carlo simulation software
assumed in the schedule. program that can simulate schedule

14 COST ENGINEERING NOVEMBER/DECEMBER 2012


Table 11 — Highest Priority Risks to Project Cost at the P-80 Level of Confidence

risk, burn-rate risk and time- REFERENCE ABOUT THE AUTHORS


independent resource risk. 1. GAO Cost Estimating and
Assessment Guide, US Government
The results include the standard Accountability Office, March 2009
histograms and cumulative distributions (GAO-09-3SP), pgs. 218-224.
of possible cost and time results for the Dr. David T. Hulett is
project. However, by simulating both RECOMMENDED READING with Hulett &
cost and time simultaneously, one can 1 AACE International Recommended Associates, LLC. He
collect the cost-time pairs of results and Practice No. 57R-09 Integrated Cost can be contacted by
hence show the scatter diagram and Schedule Risk Analysis Using sending e-mail to:
(“football chart”) that indicates the joint Monte Carlo Simulation of a CPM david.hulett@projectrisk.com
probability of finishing on time and on Model, AACE International,
budget. Also, one can derive the Morgantown, WV, 2011.
probabilistic cash flow for comparison 2 Hulett, D.T., Practical Schedule Risk Michael R. Nosbisch,
with the time-phased project budget. Analysis, Gower Publishing Limited, CCC PSP, and Past
The risks to schedule completion Farnham Surrey England. (2009): pg. President of AACE
and to cost can be prioritized, say at the 218. International is with
P-80 level of confidence, to help focus 3 Hulett, D.G., Integrated Cost- Project Time & Cost.
the risk mitigation efforts. If the cost and Schedule Risk Analysis, Gower He can be contacted
schedule estimates including Publishing Limited, Farnham Surrey by sending e-mail to:
contingency reserves are not acceptable England. (2011): pg. 211. mike.nosbisch@ptcinc.com
to the project stakeholders, the project
team should conduct risk mitigation
workshops and studies, deciding which
risk mitigation actions to take, and re-run
the Monte Carlo simulation to determine
the possible improvements to the
project’s objectives. ◆

COST ENGINEERING NOVEMBER/DECEMBER 2012 15


Now:What
“If schedules needed analysis,
is the difference between
Primavera would have included it.”
reviewing your P6 schedule and
reviewing your P6 XER file?

Everything

See more at
http://ScheduleAnalyzer.com

% Interfaces Directly with Database


% Hundreds of Reports & Analyses
% Advanced Longest Path Analysis
% Built-in Report & Editing Facility
% Drill-down from Dashboard to P6

16 COST ENGINEERING NOVEMBER/DECEMBER 2012


TECHNICAL ARTICLE

Estimate Accuracy:
Dealing With Reality
John K. Hollmann, PE CCE CEP

Abstract: This article reviews over 50 years of empirical cost estimate accuracy known to be a “disaster” when systemic
research and compares this reality to common but unrealistic management ex- risks are present [27].
pectations. The empirically-based accuracy research of John Hackney, Edward One researcher said this behavior
Merrow, Bent Flyvbjerg, and others on large projects in the process industries is verges on “criminal” [19]. Cost disasters
summarized. The article then highlights risk analysis methods documented in re- and criminality are economic in nature,
cent AACE Recommended Practices that yield outputs based upon and compara- but deadly serious to owners, investors
ble to empirical reality. Tragically, many cost engineers are facilitating and tax-payers; we must ultimately take
management’s collective and sometimes willful biases regarding accuracy by using responsibility for our role in their
flawed, unreliable risk analysis methods; those who use empirically valid practices economic well-being. To help improve on
face the fate of Cassandra. The article is intended as a fundamental reference on the situation, this article surveys the
the topic of accuracy, as well as a call for our profession to use reliable practices
research facts (reality), exposes flawed
and speak the truth to management. Readers will gain an understanding of esti-
mate accuracy reality, the risks that drive it, management’s biases about it, and practices. and highlights better practices.
methods that analyze risks and address the biases in a way that results in more The article summarizes data from
realistic accuracy forecasts, better contingency estimates and more profitable in- well referenced studies by others;
vestments. This article was first presented as RISK.1027 at the 2012 AACE Inter- however, the data confirms the author’s
national Annual Meeting in San Antonio, Texas. experience. The author’s data and
observations are added, as well as
Key Words: Cost estimate accuracy, recommended practices, and risk analysis observations by others. While fact and
opinion are mixed, it is hoped that

A
readers will draw the same conclusions as
ccuracy is a measure of how a and how well risk analysis methods
the article and work to improve the
cost estimate will differ from forecast it is generally poor.
situation.
the final actual outcome. It is Investment decision makers seem
also a measure of cost particularly unaware of our research and
Studies of Overall Estimate Accuracy
uncertainty or risk (these terms are recommended practices. Sometimes they
How accurate have cost estimates
essentially synonymous in Total Cost are aware, but seem to ignore them.
been for owners? To answer this,
Management (TCM). Worse, many cost engineers facilitate
references providing empirical data on
Empirical estimate accuracy data has management ignorance by standardizing
estimate accuracy and cost uncertainty
been researched for over 50 years [30]. In their wishful thinking (i.e., tunneling or
were sought. This article focuses on
addition, reasonably reliable practices for neglecting sources of uncertainty) as
engineering and construction projects in
quantifying project cost uncertainty have exemplified by bias towards 10%
the process (e.g., oil, gas, chemicals,
been recommended by AACE and others. contingency and +10/-10% range [42].
mining, metals, utilities, etc.) and
However, the level of industry Poor investment decisions may result
infrastructure (often associated with
understanding of the reality of accuracy from using risk analysis methods that are
process plant projects) industries. These

COST ENGINEERING  NOVEMBER/DECEMBER 2012 17


are generally characterized by various confidence levels. For [19]. Dr. Flyvbjerg has made the
complexity, unique work scopes, design comparison, the accuracies in table 1 are following statements regarding industry
change and sometimes new technology. summarized at approximate estimating practices: “We conclude that
The chosen references represent p10/p50/p90 confidence levels where the cost estimates used in public
academic, research, consulting and the “p” value indicates the percentage debates, media coverage, and decision
industry practitioner sources. Empirical that underran. If a mean was provided making for transportation infrastructure
research on defense, aerospace and IT (μ), it is shown as such. If p-values were development are highly, systematically,
projects was found but excluded; their not provided, they were approximated and significantly deceptive.” “(those)
experience is analogous but more from the mean and standard deviation who value honest numbers should not
extreme [13,16, and 20]. assuming a normal distribution; i.e., p90 trust the cost estimates presented by
Estimate accuracy and cost equals the mean plus 1.28 times infrastructure promoters and
uncertainty data from 12 empirical standard deviation (the ~ symbol forecasters.” He adds, “institutional
studies are summarized in table 1. These indicates an approximation.) This checks and balances—including
include over 1,000 projects with samples approximation underestimates the high financial, professional, or even criminal
ranging from about 20 to 250 projects range when actual/estimate accuracy penalties for consistent or foreseeable
each. The projects were typically large data is skewed to the high side (i.e., estimation errors—should be developed
enough to affect enterprise success (i.e., actual data is not normally distributed). to ensure the production of less
typically one million US dollars up to The project samples were not deceptive cost estimates [19].”
megaprojects). The costs studied are the scientifically random, but were not Merrow disagrees with Flyvbjerg in
costs to the owners. Study purposes selected specifically because their the following: “There is widely held
varied; however, the typical the estimates were inaccurate; the authors belief that large public sector projects
questions were: “what is the accuracy of generally considered the projects in their tend to overrun because the estimates
our estimates and why?” in reaction to a samples to be reasonably are deliberately low-balled. Our (IPA’s)
perceived preponderance of cost representative. Studies done in reaction analysis of large private sector projects
overruns. to overruns may be biased toward that suggests that no Machiavellian
experience; however, the number of explanation is required. Large projects
In summary, the approximate range studies and the variety of industries, have a dismal track record because we
of ranges for accuracy or uncertainty regions and project types covered have not adjusted our practices to fit the
around the reference amounts are as indicate that cost overruns are prevalent difficulty that the projects present [33].”
follows: for large process industry projects. Regardless of motives and causes,
The quality of the datasets varied, large process and infrastructure projects
• P10: -32% to +8% but in general the authors lament the (and defense, aerospace and IT) are
(average about -9%) poor state of historical project records. frequently overrunning our funding
• P50 or mean: 0% to +88% For many studies, the only reliable data estimates and by very large margins. The
(average about 21%) was the cost at the time of project search found no research that showed
• P90: +34% to 190% funding approval (i.e., sanction or otherwise. Further, as “forecasters” (as
(average about 70%) investment decision) and the cost at we are referred to by Flyvbjerg) we are
completion. However, some studies failing to reliably predict the proper
The “accuracy” shown is the were corrected for major scope changes point of funding including contingency,
percentage variation of the final actual and escalation, which many practitioners but the range of project cost uncertainty.
cost from the reference estimate. The would not expect an estimate to cover.
reference estimate was usually the basis The key observation is that in no Studies of Estimate Accuracy Progression
for an actual or defacto investment case was the nominal p90 value ever less Versus Level of Scope Definition
decision by the owner. Estimate names than +34% of the funding estimate (i.e., It is generally agreed that the less
are industry specific; for example, about +40 to +50% of the base estimate). well defined the project scope is, the
“feasibility” is the funding estimate for Also, the average mean or median wider the estimate accuracy range will
mining projects, but not for projects in overrun is about 21%. This is the best be. This is a premise of phase-gate
other industries. The reference picture we have of reality for large project systems. Table 2 summarizes
estimates usually include contingency; process industry projects with all their accuracy studies from among this
therefore, the accuracies are imperfections and risks (unfortunately, article’s sample that also addressed
understated in respect to base estimates causal data is lacking). accuracy and uncertainty at various
without contingency. From the author’s Arguably, the most notable studies levels of scope definition, approximated
experience, the contingency applied at are by John Hackney and Edward to AACE classifications (Class 5 to 1).
sanction is usually between 5 and 15 Merrow because these are the
percent. foundation for process industry phase- Complicating the comparison, each
The statistics provided ranged from gate project systems [22, 35]. However, study has different data attributes and
mean and standard deviations alone to the studies by Dr. Bent Flyvbjerg are uses different scope definition rating
distribution charts or tables or values at perhaps best known in the popular press schemes (i.e., AACE classification ratings

18 COST ENGINEERING NOVEMBER/DECEMBER 2012


Table 1 — Empirical Estimate Accuracy Studies (Typically From the Funding Estimate)

were not used). However, the author’s for-design, signed-off process and overrun; there is a huge potential for
experience is that process industry instrumentation diagrams (P&IDs) for all overruns if the scope is more poorly
funding decisions are being made based process and utility units; the author rarely defined than Class 3. Note that the
on scope definition somewhat better sees this level of definition at the time of Hackney and RAND models based on this
than AACE Class 4, but worse than Class 3. funds authorization [4]. data are available in working Excel tools
Research indicates that the design The key observation from table 2 is found at the AACE website
development necessary to thoroughly that even projects funded on better scope (www.aacei.org [11]).
mitigate definitional risk includes issued- definition (AACE Class 3) tend to be

COST ENGINEERING NOVEMBER/DECEMBER 2012 19


What Our Estimates Say and What uncertainty around quantities, rates, For a project with substantial risks
Owners Want Are the Same (i.e., pricing, and productivity; while (most large projects), the company
Wishful Thinking) unrealistically assuming the scope is accuracy ranges in table 4 have no
The next question is, “are the fixed, the execution strategy and plan is relevance. Unfortunately, targets tend to
overrunning projects within the cost never changed, no risk events occur and pre-determine risk analysis outcomes;
range of our risk analyses?” if they do, risk responses are always i.e., they drive the risk analysis
Unfortunately, they usually are not. The effective. The result is a range that outcomes seen in table 3 (owners get
author has reviewed many industry risk seems to be what the owner wants to what they ask for). Targets are prima
analyses by owner companies and their hear. facie evidence of risk ignorance
EPC contractors and their p90 forecast is So the next question is, “what does (tunneling) driven by the inflated
rarely great than 30% over the base the owner want to hear?” Table 4 expectations that phase-gate processes
estimate excluding contingency. Table 3 provides an indicative sample from alone will manage risks.
provides an indicative sample of risk different industry segments of owner Further, the communication of
analysis outcomes. accuracy range expectations as stated in targets by many owners is statistically
The first project risk analysis shown their phase-gate project scope meaningless. First, many misquote AACE
in table 3 had a p90 value of +45%; development processes. Recommended Practices by stating that
however, the risks on this project were The table compares the owner the targets are “per AACE” when no
extreme and while the team captured targets to the range-of-ranges in the AACE document includes specific targets
some of them, the range was overrun by AACE Recommended Practice 18R-97 [4]. Also, few state the confidence
the next phase estimate. P50 values are [4]. Is it coincidence that the owner p90 interval represented or the reference
often as little as 5% even for highly risky targets in table 4 are about the same as value that the range is around (the base
projects. The author’s experience is that the p90 values estimated in table 3? or the funded amount?).
despite extensive risk registers and By quoting specific accuracy range To wrap up the target/as-estimated
brainstorming sessions, most risk targets in their processes, owners versus actual accuracy discussion, figure
quantification is dominated by an display a dangerous misunderstanding 1 shows the averages of table 1 (Reality)
estimator’s bias in which the team of risk and estimating. Once a project and table 3 (As Estimated) as log-normal
consciously or unconsciously perceives plan reaches the target level of scope curves with p10/50/90 values
uncertainty in terms of estimate and definition (e.g., Class 3), the residual risk comparable to the table 1 and 3
takeoff assumptions and math (i.e., and its potential impact is a project averages for those confidence levels.
“estimator’s risks”). scope attribute and no estimator can Several of the studies and the
A high (p90) range of about +30% appreciably improve the accuracy range author’s experience suggest that the
reflects the perceived worst case by doing a “better estimate.” lognormal distribution of

Table 2 — Empirical Estimate Accuracy Studies (Progression by Level of Scope Definition)

20 COST ENGINEERING NOVEMBER/DECEMBER 2012


actual/estimate data is representative Studies show wide accuracy ranges the average overrun was about 71% of
[14,35]. Teams are assuming a p10/p90 with or without correction. In the the original project cost estimate”[37].
accuracy range around the base author’s benchmarking experience, Another mining article referenced a
estimate of about -10/+30% with a p50 major owner scope change (as opposed series of studies which indicate that
value of about 10%, while the reality is to design changes which owner costs overruns have been the norm in every
closer to -20/+120% with a p50 of about must cover) is uncommon (this may be time period since 1965 [38]:
20%. Arguably, a 20% or even 30% less true for public projects).
overrun will not render most projects • “A study of 18 mining projects,
unprofitable; however, a 120% overrun 2. We cannot forecast volatility and/or covering the period 1965 to 1981,
at p90 would. black swan events (i.e., unknown showed an average cost overrun of
unknowns). 33 percent, compared to feasibility
Challenging the Data : Nowhere to Hide study estimates.
The following are likely challenges While any one black swan event is • A study of 60 mining projects,
to this article’s findings along with the improbable, the probability of any black covering the period from 1980 to
author’s responses: swan or an equivalent confluence or 2001, showed average cost overruns
compounding of lesser risks occurring of 22 percent, with almost half of
1. The actual data includes the impact during the extended duration of large the projects reporting overruns of
of major scope changes and projects is likely. The accuracy findings more than 20 percent.
escalation. appear to hold for all time periods and • A review of 16 mining projects,
regions, in both hot and cold economies. carried out in the 1990s, showed an
Major scope change and escalation For example, Ernst & Young found average cost overrun of 25 percent”.
are by definition excluded from that mining projects estimated during
contingency [3]. In table 1, 7 of the 12 hot markets (when market risks were Historical experience alone is
studies corrected for price changes over known) were still overrunning during the enough to quantify the probability and
time and 3 corrected for major scope post-2008 recession; “Of the companies impact “unknown-unknowns” as a class.
changes (i.e., changes to basic project that reported project overruns publically We may not know the risk’s name, but
premises such as plant location, product (between Oct 2010 and March 2011), we know about what it will cost (i.e.,
specifications or capacity). Table 1.)

Table 3 — Reported Accuracy Ranges from Owner and EPC Contractor Risk Analyses

COST ENGINEERING NOVEMBER/DECEMBER 2012 21


Table 4 — Owner Phase-Gate Target Accuracy Ranges Vs. AACE Classes and Empirical Studies

Figure 1 — As Estimated (and Target) Accuracy Vs. Empirical Accuracy at Funding

3. Some systemic risks are difficult to established [4, 21, 22, 35, and 45]. While 4. Estimating “all” project cost risk is
measure and/or politically sensitive. including, “incompetent management,” not part of the job (not in my work
in a risk register is problematic, it is scope).
The tools for rating scope necessary to identify and quantify such
development, as well as competency risks. The risk analyst must have If one declared in the Basis of
and project system discipline (e.g., weak sufficient independence to do so. Estimate reports that, “most significant
change management) are well risks were excluded” and/or “past

22 COST ENGINEERING NOVEMBER/DECEMBER 2012


experience with similar projects was estimating) in which the team assigns (upstream oil) projects suffer
ignored,’ this challenge might have some cost ranges to line-items in their significant cost overruns. Indeed, as
validity. However, in the author’s estimate (i.e., contributing to estimator’s a general rule, 30 percent of such
experience, such statements (or bias) based on brainstorming, and then projects experience budget
confessions) are rarely made. runs the MCS, usually without overruns of 50 percent [41].”
Unfortunately, breaking risk down considering line-item dependency [24]. • Financier Jasper Bertisen of
(e.g., operational, project, strategic, The risks listed in the register (which Resource Capital Funds (RCF) had
enterprise, contextual, global, tend to exclude systemic risks) are not this observation: “the vast majority
background, etc. [42]) and disseminating explicitly included in these models. This of mining projects have been
responsibility for its analysis and is the method that research has shown coming in way over budget for the
quantification is a potential recipe for to be a “disaster” for projects with past couple of decades. As a result,
forecasting failure. Risks interact and systemic risks [27]. “Line-item ranging” RCF now automatically factors in an
often compound and cannot readily be (or activity duration ranging for average cost overrun of 25% when it
parsed for quantification like elements in schedule) fails in part because of faulty considers the cost of mining projects
a work breakdown. application (i.e., no dependencies), but [28].”
In summary, it is the author’s also because brainstorming is unable to
experience that these “challenges” are elicit the impacts of systemic risks on The prevailing use of flawed
usually just reasons for our failings; they individual estimate line items or analyses has damaged our collective
do not excuse them. We know better activities, and finally, the impact of risk credibility. This will be difficult to remedy
and the data is clear; with empirical register events are difficult to ascribe to because poor practices have become
insight added to other methods, risk is individual estimate line items in institutionalized. For example, in the
always quantifiable albeit imperfectly. aggregate. This method is not an AACE mining industry, the author commonly
Recommended Practice. finds companies funding projects at a
It is easy to conclude from the p80 level of confidence.
Flawed Practices and Lost Credibility research and observations that our risk This has evolved because (as
Flawed practices such as a bias analyses and contingency estimates are indicated by prior quotation) managers
toward estimator’s risk, misguided not credible for large process industry intuitively understand that the p50
targets, tunneling and parsing risk projects. Decision analysis expert John values we provide in our estimates are
quantification have been mentioned. Schulyer defines a credible analysis as, too low (i.e., often <10% contingency on
The 1990s also brought reengineering “one that gets used [44].” The following even the riskiest projects) and they
and downsizing to the industry with the statements by industry executives believe that the p80 level of about 15 to
loss of empirical data and analytical indicate that our analyses are not useful 20% contingency is more realistic.
skills. Concurrently, Monte Carlo (self-criticism by owner executives is However, it is “more realistic” because in
simulation (MCS) for spreadsheets was understandably more difficult to find): fact this forecast p80 is the p50 of the
introduced which made risk analysis “reality” that we fail to predict!
seem simple and doable regardless of • Schlumberger CEO Andrew Gould Cost engineers who do use realistic
skill level. stated: “...while not wishing to risk quantification practices are treated
Unfortunately, MCS was applied in embarrass any of my customers, I like Cassandra; management will not
“line-item ranging” (as opposed to range would add that many greenfield believe the truth after being fed

Figure 2 — Actual Cost/Appropriation Estimate For Small Projects

COST ENGINEERING NOVEMBER/DECEMBER 2012 23


Figure 3 — Balancing Of Over And Underruns When All Project Sizes Are Studied Together

unreality for decades. The real p80 or The Project Size Dichotomy representative distribution of
p90 is likely to be unprofitable; as shown There is less empirical research of actual/estimate values observed by the
in studies, the least p90 capital cost small project estimate accuracy because author for small project portfolios; often,
growth is >40 to 50%. If management these projects are individually less of a no projects overrun by more than 10%.
faced this reality, no project would ever threat to overall profitability and In this “cresting wave” pattern, most
be authorized without stellar scope shareholder’s perceptions. However, we projects spend all their funds, while
definition and optimization, top-notch know that the realities of small and large some return all or some of the excess; for
planning, team building, risk projects differ; small projects are biased this outcome, management and/or
management, and all of the other best to overestimating and underruns. As teams are rewarded. The more that
practices we know of. Isn’t that the stated by one researcher, “when a funds are wasted, the sharper the peak
point? Why are we facilitating anything project team sets a soft (cost) target, between 0.9 and 1.1. Perversely, the
less? Why do we let them assume that about half of the unneeded funds are more “accurate” the outcome, the less
poor practices are a safe bet when they usually spent…about 70% of small desirable (though best rewarded) it is;
are courting disaster! projects underrun” [29]. underruns and tight accuracy often
The lesson from the empirical This research also indicated that in indicate overfunding and wasted capital
history (table 1) and the practice history small project systems, overruns tend to rather than excellent project control
(table 2) is that we need to address the be punished. To avoid punishment (in discipline
entire scope of risks (project-specific, less disciplined cultures) teams avoid The small vs. large project overrun
systemic, and escalation) and the overruns by including “fat” (i.e., above- dichotomy can induce a kind of corporate
empirical “reality” of uncertainty on the-line contingency) in the base schizophrenia. Many owner companies
large process industry projects. Research estimate because high visibility have “major project” organizations that
by others points in the same direction contingency is often poorly received by are separate from small or plant-based
[16, 17, 18, 19, 22, 27, 32, 33, 42]. AACE management for any project size. This organizations. A newly formed major
is currently developing a Decision and can bias a company’s perception of risk project group will often inherit the small
Risk Management Professional (DRMP) and partly explain their misguided project system trait of risk-ignorance
Certification that will focus on risk targets. (expectation of underruns.) They do not
identification and quantification Few researchers study small projects appreciate that EPC contractors for major
competencies, including AACE because not only is record keeping lax, projects prepare base estimates with less
Recommended Practices that document but underruns are rewarded and are not fat because reviews expose fat and there
reliable methods. seen as a problem despite being is sometimes a bias to keep estimates
associated with wasteful capital low to see the project get funded. The
spending. Figure 2 shows a combination of small project target-

24 COST ENGINEERING NOVEMBER/DECEMBER 2012


reinforced tunneling and risk-free base Note that the previously discussed, Parametric Estimating – Example
estimates is a recipe for overruns on “line-item ranging” method, is not Models as Applied for the Process
large projects. explicitly in accordance with any of Industries [11].
Looking at an entire company above principles.
project portfolio, the combined • Escalation Risk:
distribution of accuracy data for small Risks differ in how they impact o 58R-10: Escalation Principles and
and large projects can look serenely project costs and therefore methods Methods Using Indices [6].
“normal.” Benchmarking data observed vary in how the risks are quantified. To o 68R-11: Escalation Estimating Using
by the author indicates that in a cover the whole scope of risks, AACE has Indices and Monte Carlo Simulation
population of all project sizes, the defined a risk breakdown [24] in respect [5].
P10/P90 range is about +/-20% around to quantification methods that includes:
the funding estimate, as illustrated in Regardless of the risk analysis
figure 3. Given just one distribution, • Project-Specific Risk: risk affecting methods used, the findings of this article
management will be unaware that there the specific project and plan; suggest that, at a minimum, you always
are two conflicting realities. • Systemic Risk: artifacts or inherent test your p90 outcomes (the “high”
attributes of the system, enterprise scenario given to the business
The Measurement Dilemma or strategy; and, organization to test the robustness of
Unfortunately, accuracy (i.e., • Escalation Risk: driven by their decision) against the empirical
actual/estimated cost) is often misused economics (which regionally may reality. If no other historical data is
as a measure of estimate “quality” (as in involve politics). available, this article provides actual
“a high quality estimate is an accurate examples to consider. If your p90 is 25%
estimate”) or estimating performance. Analogies for these risks suggested or less over the base estimate, ask why
This is inappropriate because, as by others include: operational (project), NO study ever showed less than about
discussed, the only way for an estimator strategic (enterprise), and contextual 40% for p90; what risks are you missing?
to deliver a targeted accuracy for a given (global) risks respectively [42]. Methods what impacts have you underestimated?
scope is to over-estimate the cost; risk that address these risk types can be Finally, and most important, ask “how
and project performance are not in the integrated to generate a “universal” cost can we improve project practices and
estimator’s control. risk profile to support decision making. scope in consideration of the risk
Faced with overruns, estimators and AACE also recommends that cost and reality?”
the team tend to hide behind the excuses schedule risk analysis be integrated.
discussed previously. Accuracy should be For each risk type, there are AACE Conclusion
used to measure the performance of the RPs for risk analysis methods that apply As a student of cost engineering and
risk management process (not the as follows (“how-to” descriptions for the editor/lead author of AACE’s Total
estimating process) in conjunction with these methods are covered in the Cost Management Framework process
project historical data including causal references): [26], I am dismayed by the extreme
information so we can improve our risk disconnect between our practices and
identification, analysis and • Project-Specific Risk: the long-known reality as shown in
quantification, and treatment. o 41R-08: Risk Analysis and figure 1. There is an ongoing failure to
Tight accuracy may indicate wasted Contingency Determination Using effectively address the reality of project
capital funds; accuracy measures must Range Estimating [12]. cost uncertainty and there is a lack of
always be accompanied by measures of o 44R-08: Risk Analysis and good historical data with causal
project control process discipline and Contingency Determination Using information. This has led to a credibility
project cost competitiveness (lower Expected Value [9]. crisis. It also raises an ethical question (if
absolute costs) or cost bias. o 57R-09: Integrated Cost and not a criminal one per Flyvbjerg); what
Schedule Risk Analysis Using Monte does it mean if we understand reality but
AACE Recommended Practices (RPs) Carlo Simulation of a CPM Model continue to use failed methods known to
There is an AACE RP that guides the [8]. be contrary to experience to the
selection and development of risk o 65R-11: Integrated Cost and potential detriment of our employers
quantification and contingency Schedule Risk Analysis and and clients? The AACE Canons of Ethics
estimating methods [2]. This RP provides Contingency Determination Using (item 2g) states: “When, as a result of
“principles” that any method should Expected Value [7]. their studies, members believe a
align with including; project(s) might not be successful…they
• Systemic Risk: should so advise their employer or
• start with identifying risk drivers; o 42R-08: Risk Analysis and client” [1]. In respect to large process
• link risk drivers and cost/schedule Contingency Determination Using industry projects, readers of this article
outcomes; and Parametric Estimating [10]. can consider themselves so advised.
• employ empiricism. o 43R-08: Risk Analysis and There are of course practitioners
Contingency Determination Using who do address the entire scope of cost

COST ENGINEERING NOVEMBER/DECEMBER 2012 25


risks (in AACE terms; systemic, project- Recommended Practice 40R-08, 12. AACE International, “Risk Analysis
specific and escalation), capture data AACE International, Morgantown, and Contingency Determination
and consider the empirical record [16, WV, (latest revision). Using Range Estimating,”
17, 18, 21, 42, and 43]. However, in the 3. AACE International, “Cost Recommended Practice 41R-08,
author’s experience, the application of Engineering Terminology,” AACE International, Morgantown,
robust practices is uncommon. At a Recommended Practice 10S-90, WV, (latest revision).
minimum, teams should at least test AACE International, Morgantown, 13. Arena, Mark, Robert S. Leonard,
their worst case analysis outcomes WV, (latest revision). Sheila E. Murray, and Obaid
against the empirical reality. They should 4. AACE International, “Cost Estimate Younossi, “Historical Cost Growth of
study this article’s references and their Classification System – As Applied in Completed Weapon System
own enterprise’s historical experience Engineering, Procurement, and Programs” TR-343, The RAND
(watching out for the small versus large Construction for the Process Corporation, 2006.
project behavioral dichotomy). And, they Industries,” Recommended Practice 14. Bertisen, Jasper and Graham A.
should then seek to improve their 18R-97, AACE International, Davis, 'Bias and Error in Mine Project
practices to improve on past outcomes. Morgantown, WV, (latest revision). Capital Cost Estimation,' The
The author does not agree with Dr. 5. AACE International, “Escalation Engineering Economist, 53: 2, 118
Flyvbjerg’s approach to using empiricism Estimating Using Indices and Monte — 139, 2008.
(i.e., “reference class forecasting” [19]) Carlo Simulation,” Recommended 15. Biery, Frederick, “Improving Mineral
which implies that biases are so Practice (draft) 68R-11, AACE Project Performance,” Canadian
intractable that we are doomed to International, Morgantown, WV, Institute of Mining, Metallurgy and
repeat the past. (latest revision). Petroleum Conference, May 2009.
The article also points out that 6. AACE International, “Escalation 16. Butts, Glenn and Kent Linton, “The
companies should not use accuracy as a Principles and Methods Using Joint Confidence Level Paradox; A
cost estimating quality measure; it is a Indices,” Recommended Practice History of Denial,” 2009 NASA Cost
risk management and project control 58R-10, AACE International, Estimating Symposium, NASA, April
process quality measure. Tight accuracy Morgantown, WV, (latest revision). 2009.
is often an indicator of wasted capital; 7. AACE International, “Integrated Cost 17. Curran, Kevin M., “Value-Based Risk
measures of project control process and Schedule Risk Analysis and Management (VBRM),” Cost
discipline and project cost Contingency Determination Using Engineering, AACE International,
competitiveness must accompany Expected Value,” Recommended AACE International, Morgantown,
accuracy measures. Practice (draft) 65R-11, AACE WV, February 2006.
In summary, this article references International, Morgantown, WV, 18. Curran, Kevin M and Michael
and summarizes over 50 years of (latest revision). Curran, “Handling the Truth in Risk
empirical cost estimate accuracy 8. AACE International, “Integrated Cost Management,” 2010 AACE
research on large projects in the process and Schedule Risk Analysis Using International Transactions, AACE
industries. It shows how this reality Monte Carlo Simulation of a CPM International, Morgantown, WV,
compares (or does not compare) to what Model,” Recommended Practice 2010.
we say and do. Recommended risk 57R-09, AACE International, 19. Flyvbjerg, Bent, Mette Skamris Holm
analysis methods have been highlighted. Morgantown, WV, (latest revision). and Søren Buhl, “Underestimating
Failed methods are exposed. It is hoped 9. AACE International, “Risk Analysis Costs in Public Works Projects; Error
that the facts, observations and opinions and Contingency Determination or Lie?” APA Journal, 68:3, 279-295,
brought together here will serve as a Using Expected Value,” 2002.
valuable reference on the topic of cost Recommended Practice 44R-08, 20. Flyvbjerg, Bent and Alexander
accuracy and uncertainty so that we can (latest revision). Budzier, “Why Your IT Project May
better speak the truth among ourselves 10. AACE International, “Risk Analysis Be Riskier Than You Think,” Harvard
and with management. The path to and Contingency Determination Business Review, September 2011.
more realistic uncertainty forecasts, Using Parametric Estimating,” 21. Gough, Martin and Peter Maidment,
better contingency estimates and more Recommended Practice 42R-08, “The Stability Model Method of Risk
profitable investments is clear and AACE International, Morgantown, Management and Early Prediction
documented by AACE International. ◆ WV, (latest revision). of Project Performance,” The Revay
11. AACE International, “Risk Analysis Report; Revay and Associated
REFERENCES and Contingency Determination Limited, February 2006.
1. AACE International, Canon of Ethics. Using Parametric Estimating – 22. Hackney, John W. (Kenneth K.
AACE International, Morgantown, Example Models as Applied for the Humphreys, Editor), Control &
WV, 2012. Process Industries,” Recommended Management of Capital Projects,
2. AACE International, “Contingency Practice 43R-08, AACE Chapter 18, AACE International,
Estimating – General Principles,” International, Morgantown, WV, Morgantown, WV, 2002.
(latest revision).

26 COST ENGINEERING NOVEMBER/DECEMBER 2012


23. Harbuck, Robert H, “Are Accurate 2011:11, Centre for Transport Factors For Improving Outcomes,”
Estimates Achievable During the Studies, Stockholm Sweden, 2011. Deloitte Touche Tohmatsu, March
Planning of Transportation 32. Merrow, Edward W., Industrial 2010.
Projects?,” 2007 AACE International Megaprojects, John Wiley & Sons, 41. Reddall, Braden (reporting), “Cost
Transactions, AACE International, Inc., New York, NY, 2011. Overruns Common on Oil Projects –
Morgantown, WV, 2007. 33. Merrow, Edward, W., “Why Large Schlumberger,” Thomson Reuters,
24. Hollmann, John K., “The Monte- Projects Fail More Often; Energy and Oil News, 2 June, 2011.
Carlo Challenge: A Better Megaproject Failures: 42. Rolstadås, Asbjørn, Per Willy
Approach,” 2007 AACE Understanding the Effects of Size,” Hetland, George Farage Jergeas and
International Transactions, AACE Presentation to the Joint Meeting of Richard E. Westney, Risk Navigation
International, Morgantown, WV, the AACE National Capital Section Strategies for Major Capital
(latest revision). and American Society of Mechanical Projects: Beyond the Myth of
25. Hollmann, John K., “Recommended Engineers Section, April 20, 2011. Predictability, Springer- Verlag
Practices for Risk Analysis and Cost 34. Merrow, Edward W. and Brett R London Limited, 2011.
Contingency Estimating,” 2009 Schroeder, “Understanding the 43. Schroeder, Brett and Jan A. Jackson,
AACE International Transactions, Costs and Schedule of Hydroelectric “Why Traditional Risk Management
AACE International, Morgantown, Projects,” 1991 AACE International Fails in the Oil and Gas Sector:
WV, 2009. Transactions, AACE International, Empirical Front-Line Evidence and
26. Hollmann, John K (editor), Total Morgantown, WV, 1991. Effective Solutions,” 2007 AACE
Cost Management Framework, 35. Merrow, Edward W., Kenneth E. International Transactions, AACE
AACE International, Morgantown, Phillips and Christopher W. Myers, International, Morgantown, WV,
WV, 2006. “Understanding Cost Growth and 2007.
27. Juntima, Gob and Scott E. Performance Shortfalls in Pioneer 44. Schulyer, John R., “Investment
Burroughs, “Exploring Techniques Process Plants,” R-2569-DOE, p48, Decision Making,” Chapter 14 of The
for Contingency Setting,” 2004 AACE The RAND Corporation, 1981. Engineer’s Cost Handbook, Editor
International Transactions, AACE 36. Merrow, Edward W., Lorraine Richard E. Westney, Marcel Dekker,
International, Morgantown, WV, McDonnell and R. Yilmaz Arguden, Inc., New York NY, 1997.
2004. “Understanding the Outcomes of 45. Stephenson, H. Lance, “Cost
28. Kosich, Dorothy, “Vast Majority of Megaprojects,” R-3560-PSSP, The Engineering Maturity Model
Mining Projects Experience Steeper RAND Corporation, 1988. (CEMM),” 2011 AACE International
Cost Over-runs,” MineWeb, 30 Nov 37. Mitchell, Paul, “Achieving Major Transactions, AACE International,
2011. Capital Project Effectiveness and Morgantown, WV, 2011.
29. Kulkarni, Phyllis, “Stop Punishing the Corporate Performance,” Effective 46. Thomas, Steve, “Project
Overruns,” InSites, IPA, Inc., Sept 7, Capital Project Execution: Mining Development Costs-Estimates Vs.
2011. and Metals, EYGH Limited, 2011. Reality,” Pincock Perspectives,
30. Linder, Stefan, “Fifty Years of 38. Noort, D.J., and C. Adams, “Effective November 2000.
Research on Accuracy of Capital Mining Project Management
Expenditure Project Estimates: A Systems” International Mine
Review of the Findings and Their Management Conference, ABOUT THE AUTHOR
Validity,” Center for Research in Australasian Institute of Mining and
Controllership and Management, Metallurgy, October 2006.
WHU - Otto Beisheim Graduate 39. Oil & Gas Journal Online Research John K. Hollmann is
School of Management, Vallendar, Center, US Pipeline Study 2009; with
Germany. April 2005. Actual vs. Estimate (database for Validation Estimating,
31. Lundberg, Mattias, Anchalee fee), Penwell Corporation, Houston LLC. He can be
Jenpanitsub and Roger Pyddoke, TX, 2009. contacted by sending
“Cost Overruns in Swedish Transport 40. Rath, Michael, Robert Spittle, Paul e-mail to:
Projects,” CTS working paper Osman and Nicholas Tawa. “Major jhollmann@validest.com
Water Capital Projects: Critical

COST ENGINEERING NOVEMBER/DECEMBER 2012 27


TECHNICAL ARTICLE

Quantifying Estimate Accuracy and


Precision for the Process Industries:
A Review of Industry Data
Alexander Ogilvie, Robert A. Brown Jr., Fredrick P. Biery
and Paul Barshop

Abstract: This article quantifies industry metrics for estimate accuracy based on comprehensive set of industry projects.
a sample of 462 capital projects executed by the process industries over the last Despite these limitations, these studies
20 years, comparing estimated costs at the various stages of project definition to were valuable as they provided a set of
actual costs, normalized for a number of factors. The authors then contrasted the industry norms that quantify estimate
results from the industry survey with industry expectations, as presented in AACE accuracy based on actual project data.
International Recommended Practice 18R-97. The results of our survey indicate In the absence of more robust
there is a much greater level of variability in estimate accuracy as compared to industry data, the cost engineering
industry expectations. Further analysis demonstrates that projects which have community has defaulted to a range of
completed a definitive project scope at authorization benefit from a reduction in sources to quantify typical estimate
estimate variability as compared to industry. This article was first presented as accuracy, including in-house data,
RISK.1100 at the 2012 AACE International Annual Meeting in San Antonio, Texas.
historical experience, or industry
standards and Recommended Practices
Key Words: Capital projects, cost, estimate accuracy, process industries and scope
(RP) [1]. The objective of this article is to
enhance industry’s understanding of

I
n virtually all applications and All of these stakeholders have estimate accuracy by providing
scenarios, a cost estimate’s value is different uses for the estimate, but share
benchmarks of estimate accuracy for a
related to its capacity to predict the a need in that they are relying on the range of estimate classifications. The
final cost of a planned scope of estimate to have a reasonable degree of authors calculate these metrics from a
work. The importance of an accurate accuracy. large sample of industry projects
estimate confronts the cost estimator The cost engineering community has executed by the oil and gas, chemical
from all directions—from: devoted a substantial amount of time to process, and mining and minerals
consider practices and processes to industries over the last 20 years. Given
• the business/project sponsor, who is improve estimate accuracy [5,16,17]. In the importance of achieving a reasonable
relying on the estimate to quantify contrast, only a limited number of articles
level of accuracy and precision for cost
the expected return on the capital and papers have also quantified the estimates, the goal of this article is to
invested; estimate accuracy ranges using actual provide an independent measure of
• to the finance group, who is relying industry data from completed projects estimate accuracy and compare these
on the estimate to manage quarterly [3,12,13]. In these instances, the data results against current industry
cash flow; and, presented were only for a subset of expectations.
• to the project controls group, who is industry (i.e., mining and minerals) or a
using the estimate as the basis for specific type of project (i.e., megaprojects Review and Definitions
project cost and schedule control or new technology projects), and The authors first considered the
during execution. therefore were limited in an ability to definition of estimate accuracy as this
quantify estimate accuracy for a concept has been such an important part

28 COST ENGINEERING NOVEMBER/DECEMBER 2012


of the cost estimating vernacular that target, precision is defined as the many of the models developed by the
the concept of an accurate estimate has absence of variation. Cost estimates financial industry to quantify risk as
evolved into a variety of potential with a wide confidence interval (e.g., see related to mortgage-backed securities
definitions. In this section, the authors the ±50 percent estimate) are focused on improving precision, but
will review and define estimate accuracy considered to be imprecise, while were entirely inaccurate with respect to
and estimate precision, both of which estimates with a small confidence the range of potential outcomes.
are closely related. interval are considered to be precise. In considering cost estimates and
The authors will also use these Figure 2 presents the outcome confidence intervals, both accuracy and
concepts to introduce AACE matrix between accuracy and precision. precision should be considered within
International Recommended Practice As based on figure 2, precision without the same context. Of course, the
18R-97 (and 17R-97), which serves as a accuracy is a potentially dangerous objective of cost estimating (as with
basis of comparison for our analysis phenomenon as it fools the users into an most related professions) is to achieve
[1,2]. Following a review of the unwarranted sense of confidence. For both accuracy and precision with respect
definitions, the authors will consider the example, one could argue (within to all cost estimates.
standard stage-gated capital project another article, paper, or forum) that
development work process for the
process industries and apply the AACE
International estimate classification to
this process.
Accuracy measures the closeness an
activity is able to achieve to meet a
desired value or target. For example, a
field goal kicker in football is considered
accurate if his field goal attempts are
consistently through the field goal posts.
AACE Technical Board Chair Larry
Dysert defines estimate accuracy as, “an
indication of the degree to which the
final cost outcome of a project may vary
from the single point value used as the
estimated cost of the project [6].” While
estimate accuracy is measured based on
a single point estimate, the accuracy of
an estimate is best represented as a
confidence interval ranging around the
single point estimate.
As presented in figure 1, the Figure 1 — Estimate Accuracy Presented as a Probability Density Function
concept of estimate accuracy can be
depicted using a standard probability
density function that quantifies the
potential minimum and maximum cost
for a cost estimate. Based on the
probability density curve as presented in
figure 1, it has become an industry norm
to present the estimate accuracy range
as a plus or minus (±) confidence interval
around the point estimate (e.g., a ±10
percent estimate translates that the
estimate will be accurate within 10
percent of the total point estimate;
conversely, a ±50 percent estimate will
be accurate within 50 percent of the
total point estimate).

In addition to estimate accuracy, it is


important to consider the concept of
estimate precision. While accuracy
measures one’s ability to achieve a
Figure 2 — Outcome Matrix for Accuracy and Precision

COST ENGINEERING NOVEMBER/DECEMBER 2012 29


Within the cost estimating • The expected precision of an and accuracy of the information which
community, the concept of a ±10 or ±50 estimate improves through the serves as the basis for that estimate.
percent estimate has evolved to describe classification system, with Class 1 In addition to the above points, the
potentially all aspects of an estimate, estimates exhibiting much less RP provides the expected accuracy range
including the estimating methods, expected variability than Class 5 and for each estimate classification. Table 1
estimating tools, estimate accuracy, Class 4 estimates. summarizes the expected accuracy
estimate precision, and inputs used for • The estimate classes show range guidelines. The RP has reached
the estimate. approximately the same degree of consensus that estimates improve with
accuracy with the average point respect to both accuracy and precision
Review of AACE International estimate for each class approaching, as a project progresses through
Recommended Practice 18R-97 on average, the actual project cost. development. However, the RP is unable
AACE International Recommended • The estimating methodology to reach consensus regarding the
Practice 18R-97 was developed to becomes more detailed and relative degree of precision for each
integrate all aspects of estimate complex as estimates progress estimate class.
accuracy within a common framework through FEL. As presented in table 1, each
and set of guidelines In the absence of • The degree of effort required to estimate class contains a range of both
robust historical data, this RP has prepare an estimate becomes minimum and maximum confidence
evolved into the de facto industry exponentially greater as estimates intervals. These ranges are insightful as
standard for estimate accuracy. Given progress through FEL. they provide some indication of the wide
that this RP will serve as a comparison • The data/project inputs required (as range of accuracy expectations that
against the results of this study, a brief measured by the percent of currently reside within Industry. Given
summary of this RP is provided. RP 18R- definition/engineering complete) to the variability of inputs for Class 4 and 5
97 provides a set of guidelines for develop an estimate become estimates, the Industry expected ranges
estimate classes considering projects greater and more detailed for lower show the least consensus in estimate
managed through a standard capital estimate classes. ranges as compared to the other
project development /definition process estimate classes.
(commonly known as the front-end The last point is perhaps the most
loading [FEL] process). Figure 3 valuable as it formalizes the linkage Project Life Cycle for the Process
tabularizes the characteristics of the five between the class of estimate and Industries
estimate classes developed in this RP. quality and completeness of data, Given the high capital requirements
The five estimate classes presented information, and deliverables that serve for the oil and gas and associated
provide guidelines for how estimates as inputs into the estimate. This concept process industries, most owner
progress from high-level approximations (i.e., inputs driving outputs) cannot be companies have adopted a formal,
to more detailed estimates as a project underscored as it maintains that the key stage-gated process to develop business
progresses through the FEL process. driver for estimate accuracy and ideas into working capital assets and
The major guidelines for this RP are precision resides in the completeness plants [4,9,10,11]. While the details of
summarized as follows: these processes vary by company, they

Figure 3 — Summary of AACE International Estimate Classification System

30 COST ENGINEERING NOVEMBER/DECEMBER 2012


adhere to a stage-gated process of stage-gated process serve as a basis for assess the financial gains of a capital
identify-select-define-execute-operate the AACE International Total Cost investment without some estimate of
to transform a business opportunity to a Management Framework [7]. the capital cost required to execute the
working plant [4,11]. Figure 4 depicts a generic stage- project).
In this model, the capital project is gated work process for capital project Most company project systems will
developed through a series of phases development. In most cases, the system require an estimate of a particular
with specific deliverables required to has five gates, with three (generically quality to meet the FEL pass-gate
finish a specific phase. Over time, the termed as appraise, select, and define) requirements. A review of these project
stage-gated process has become an composing project definition (or pre- systems shows that these classifications
industry standard for the development authorization), or the FEL stage. generally follow the AACE International
of capital projects and is used by most It is this portion of the project in categories with some variation in the
owners and contractors in the process which the cost estimator is generally the specific practices and related accuracy
industries. Past research has indicated most involved as each stage gate will classifications required by each company
that the stage-gated work process require an estimate of the planned (or even each business unit).
improves overall capital performance scope so the gate review can be For this reason, the cost estimates
[10,18]. In addition, the principles of a completed (e.g., a business lead cannot captured for each FEL stage may not, in

Table 1 — Expected Estimate Accuracy Ranges for AACE International Estimate Classification
(adopted from 18R-97)

Figure 4 — Stage Gated Process for Project Development

COST ENGINEERING NOVEMBER/DECEMBER 2012 31


Figure 5 — Matching The AACE International Estimate Classification With Typical FEL
Phases

some cases, directly match the AACE sample of projects executed by the Figure 6 presents summary
International estimate classifications. As process industries over a 20-year period characteristics for this industry sample.
such, one must not think of these data as from 1988 to 2008. Cost data for the The industry projects were executed by
corresponding directly to particular project sample was collected as part of 62 different owner companies and
AACE International classifications, but an overall industry benchmarking effort include a range of project scopes, project
rather the range of possible AACE as directed by Independent Project types, and locations. The industry
International classification requirements Analysis (IPA) and managed through IPA’s sample consisted primarily of large
enforced by this set of companies at a project evaluation system benchmarking capital projects with a mean cost of $64
particular gate. However, the authors process (PES® is a registered trademark million (with a range from $10 million to
argue, that as an industry sample, they of IPA). $3.3 billion). The projects were executed
do provide a good approximation of the For the project data collection, primarily in North America, but also in
AACE International estimate classes interviews were conducted by IPA Europe, Asia, and the rest of the world
(which are approximations themselves). project analysts with the project teams (ROW)—primarily the Middle East and
In addition, a review of industry with over 2,000 variables captured to South America.
project systems have many similarities to reflect each project’s technical scope, For each project, cost estimate data
the AACE International RP 18R-97. For characteristics, use of best practices, and were collected at four distinct points: at
example, as projects move closer to full- cost/schedule outcomes. The industry the end of each FEL gate (estimated
funds authorization, the accuracy of the dataset employed for this study included costs), as well as at project completion
estimate relative to the expected 462 completed large capital projects for (actual costs). Cost deviation metrics
outcome should improve, as well as the which estimated costs were collected at were calculated based on equation 1.
requirements for greater definition and the various FEL phases and actual costs Project costs were normalized to a
knowledge regarding the project scope at project completion. constant currency and time period to
and execution plan. Based on this
review of these industry systems, figure
5 merges the AACE International
Estimate Classification system with the
Stage-Gated Work process based on this
review of company standards and
norms.
In general, estimates at the end of
appraise (or FEL 1) correspond to AACE
International Class 5, estimates at the
end of select (FEL 2) correspond to AACE
International Class 4, and estimates at
the end of define (FEL 3) correspond to
AACE International Class 3.

Database Description and Metrics


Calculation
The authors quantified the estimate
accuracy ranges for industry from a Figure 6 — Industry Database of Projects by Project Type and Industry Sector

32 COST ENGINEERING NOVEMBER/DECEMBER 2012


remove any bias driven by general price greater than 0.00 indicate an overrun The probability distribution for FEL 1
escalation and currency fluctuation. The from the estimated costs, while values estimates indicates a log-normal (or right
costs collected included all project less than 0.00 indicate an underrun of skew) distribution with a majority of FEL
management, engineering, materials, actual costs versus the estimated costs. 1 estimates overrunning against the final
and labor costs expended on the project Figure 7 presents the distribution of costs. The author’s note that the
from the beginning of project definition cost deviations for the FEL 1 cost industry sample size for FEL 1 estimates
through the completion of construction estimates (or Class 5 estimates). At FEL is smaller than the other estimates
(as defined as mechanical completion). 1, the objective is to develop an order of primarily because of the difficulty in
For the estimates, included were magnitude/conceptual estimate to obtaining reliable early estimates from
both the base estimate as well as any determine the reasonableness of a Industry.
estimated contingency included in the project’s business case. These estimates Figure 8 presents the distribution of
estimate. Estimated escalation was generally serve as inputs into financial cost deviations for a set of estimates
excluded from this analysis as the models (e.g., to calculate net present published at FEL 2, as compared to the
authors normalized both estimated and value or return on capital) to assist final costs. This industry sample includes
actual costs to a constant dollar basis. business in allocating capital to the most 462 projects executed from 62 owner
In terms of scope and project profitable business opportunities. companies.
changes, the authors included all costs As shown in figure 7, the accuracy of As discussed in the background
associated with normal scope industry estimates at FEL 1 are extremely section, there exists among companies
development and project changes, variable with the cost deviation ranging some variability with regard to the
assuming there were no changes to the from −50 percent to over 200 percent at estimating requirements at the end of
underlying business case and overall the extremes. Industry will tend to FEL 2. However, in most cases,
project scope. Therefore, costs overrun these estimates with an mean companies will require an estimate that
associated with major scope changes overrun of 71 percent and median meets the AACE International Class 4
(e.g., increase in design capacity for a overrun of 38 percent. The standard requirements (with perhaps a few
unit) were excluded from the estimates deviation of 118 percent indicates the exceptions of requiring a Class 3
to maintain an “apples to apples” wide range of variability for industry FEL estimate).
comparison with the actual costs ,while 1 estimates. For Industry, the mean cost
costs associated with normal scope deviation for FEL 2 estimates was 15
development (e.g. increase equipment
spacing to improve unit maintenance)
was included in this analysis.
The currencies were normalized
using published exchange rates based on
the estimate month [15]. For actual
costs, currencies were normalized based
on an average exchange rate during the Equation 1
project execution schedule. Project
costs were also adjusted to remove the
effects of force majeure and other
uncontrollable external effects (e.g.,
labor strikes, natural disasters, etc.).

Study Results
This section presents the cost
deviation statistics for each FEL
phase/AACE International Estimate Class
based on the industry project sample.
Figures 7-9 present the cost deviation
distribution for estimates at the end of
FEL 1, FEL 2, and FEL 3, respectively.
Each figure presents the overall
distribution of cost deviation, as well as
the summary descriptive statistics (i.e.,
mean, median, standard deviation).
Based on the cost deviation metrics
as calculated using equation 1, a value of
0.00 means that the estimated costs
matches the actual cost exactly. Values Figure 7 — Cost Deviation Results for FEL 1 Estimates Compared to Actual Costs

COST ENGINEERING NOVEMBER/DECEMBER 2012 33


percent with a range of −61 to 224 18R-97 as summarized in table 2. This systems tend to systematically
percent. The median cost deviation is 5 comparison, presented in figure 10, underestimate projects during the initial
percent, indicating that Industry will highlights a number of disconnects with stages of the project definition process.
typically overrun the FEL 2 estimate. The respect to industry expectations and The mean cost deviation of 71 percent
standard deviation of 41 percent actual industry data. for FEL 1 estimates marks a substantial
indicates a relatively large degree of Perhaps the most striking difference departure from industry expectations.
variability for FEL 2 estimates. is the industry’s lack of precision for FEL From a cost estimator’s perspective,
Assuming a normal distribution, 1 estimates, as compared to the industry this degree of systematic
approximately 67 percent of industry FEL expectation. As discussed in the underestimating is not surprising given
2 estimates would fall between −26 and previous sections, it was industry’s that most projects (at that point in the
56 percent of the actual costs. As with expectation that while early estimates FEL process) have only established the
the FEL 1 estimates, the distribution for show a large degree of variability and most rudimentary project scope. From a
FEL 2 estimates indicates a left skew with imprecision, the overall accuracy (as business planning perspective, the
a greater percentage of FEL 2 estimates measured by the average cost deviation) results are troubling as they indicate that
overrunning rather than underrunning remains relatively constant through the the early estimates, which serve as input
the actual cost. estimate classes, with all industry into any business case and metrics (NPV,
Figure 9 shows the distribution of estimates (regardless of class) having a IRR, ROC), are systematically much lower
cost deviations from a set of estimates mean cost deviation at or near 0 percent. than the actual cost required for a typical
published at FEL 3, or full-funds The authors results show this project. From this perspective, these
authorization, against actuals. For most assumption to be incorrect as project early estimates may be insufficient to
industry project systems, the FEL 3
estimate will correspond to a Class 3
estimate; however, in some cases these
estimates may be closer to a Class 2
estimate.
As presented in figure 9, the mean
cost deviation for FEL 3 estimates is 8
percent with an overall range of −40 to
95 percent. The median value of 1
percent shows that the probability of an
overrun versus an underrun is virtually
identical with a 50 percent probability of
both. The overall variability is reduced
from the earlier FEL 1 and FEL 2
estimates, with the standard deviation of
30 percent. However, the authors note
that this degree of variability is much
greater than the ±10 percent confidence
level generally attributed to an Figure 8 — Cost Deviation Results for FEL 2 Estimates Compared to Actual Costs
authorization grade estimate. The
distribution of industry cost growth
shows a slight right skew, however, this is
much less pronounced that the FEL 1 and
FEL 2 estimates.

Comparison With AACE International


Estimate Classes
The results presented in figures 7 to
9 indicate that, as based on historical
performance from completed industry
projects, the actual cost deviation for
industry shows a greater degree of
variability and inaccuracy than current
expectations. As further analysis, the
authors have compared the industry
distributions presented in figures 7 to 9
against the expected accuracy ranges
taken from the AACE International RP
Figure 9 — Cost Deviation Results for FEL 3 Estimates Compared to Actual Costs

34 COST ENGINEERING NOVEMBER/DECEMBER 2012


serve as a robust input into any capital As with the FEL 1 estimates, the meet the AACE International Class 3
allocation process. industry sample of FEL 2 estimates expectation of precision with a median
A potential contributing factor to exhibited a lack of precision with these cost deviation of 1 percent. The mean
this finding is that during the business estimates being, on average, 14 percent cost deviation of 8 percent indicates
planning process, early estimates that above actual costs. While the overall some degree of right skew in the
may be near the actual cost (or even variability for FEL 2 estimates show an distribution, however this skew is much
conservative/higher than the industry improvement as compared to the FEL 1 less pronounced than in the previous
cost) are at a disadvantage because the estimates (the standard deviation for estimate classes.
high capital costs tend to “kill” these these estimates is 41 percent), this However, while the precision
projects because they may not meet a degree of variability is greater than the improves, the variability of the estimates
financial hurdle to move into later FEL AACE International Class 2 expectations. (as measured by the standard deviation
stages. The results for the FEL 2 estimates of 30 percent) is much greater than
In their review of estimating bias for are somewhat troubling, as it is in this industry expectations. As discussed in
the mining industry, Bertisen and Davis stage that most project systems will the review of estimate accuracy, the
also consider this hypothesis noting that require a capital project to have finalized majority of industry project systems will
for the mining industry, the scarcity of the project scope and location and require a “plus or minus 10 percent
project financing drives project sponsors completed early engineering and design estimate” for the authorization gate.
to enhance the project economics sufficient to complete a process flow Given that any project which
through lower capital estimates.[3] diagram and heat and material balances. exceeds the 10 percent threshold will
Further to this analysis, the authors Despite the requirements for closing usually require a supplemental
employed the Shapiro Wilk test for scope, Industry tends to systematically authorization, one could argue that this
statistical normality to test whether the underestimate the project costs. a ±10 percent threshold represents
FEL 1 industry estimates, on average, will For FEL 3 (or authorization grade) either the minimum or maximum range
overrun. As expected, the sample of estimates, both the precision and for the actual costs or a range in which
industry FEL 1 estimates failed this test accuracy of estimates improve from the the majority of capital projects, under
for statistical normality. previous classes. Unlike the FEL 1 and normal circumstances, will be
FEL 2 estimates, the FEL 3 estimates completed.

Figure 10 — Industry Estimate Accuracy as Compared to the AACE International RP 18R-97 Ranges

COST ENGINEERING NOVEMBER/DECEMBER 2012 35


A review of industry data will show
that approximately 66 percent of
industry projects will be completed with
a cost deviation ranging from -22 to 38
percent. The probability is approximately
50 percent that any given estimate will
meet the ±10 percent threshold.
It is argued that the ±10 percent
estimate for authorization is an
estimating concept that has evolved
from its intended purpose. This concept
has developed multiple meanings that
may, in fact, conflict with each other.
For example, it is likely while this
definition may be used by the cost
estimator to simply describe the overall
quality of an estimate, it is considered by
the business or project sponsor as an Figure 11 — Cost Deviation Results For FEL 3 Estimates With Finalized Project
absolute range to predict the final costs. Definition Compared to Actual Costs
If one accepts the latter definition, then
one must conclude that Industry is not Discussion: The Importance of the Level
achieving its objectives with respect to of Definition These points (as well as many other
estimate accuracy. Another potential As presented in figure 10, the results potential contributing factors) likely
conclusion is that the cost estimating from our industry survey show a contribute to the overall variability
community, as a whole, is doing an disconnect between industry’s experienced by Industry. However, the
inadequate job in communicating the expectation of estimate accuracy and authors will focus on the last point given
potential range of actual costs for any precision as compared with actual that IPA, as part of it project
given project when they describe an project data. Given the degree of benchmarking, routinely collects the use
estimate in these terms. difference between the industry of particular engineering and design
In either case, these results point to expectations and historical data, a practices employed during project
an overall lack of robustness for number of contributing factors to this definition.
Industry’s track record in quantifying risk difference are proposed. Potential IPA has developed a model to
(generally through contingency) for factors are summarized as follows: measure the completeness of a project’s
estimates. It is noted that the cost scope and key deliverables at
estimating community, using the most • There could be systemic issues for a authorization. This model, which is
advanced risk quantification and particular company or industry that termed the Front-End Loading (FEL)
contingency setting techniques, will set contributes to a pattern of Index is a quantitative measure of how
expectations to their clients (e.g., project overrunning or underrunning that well defined a capital project is at
teams, business sponsors) that the final combine to produce a broader authorization. It is noted that AACE
estimate will be within ±10 of the final distribution of variability. International RP 18R-97 references the
estimate. It is also noted that this • There are execution issues that “level of project definition” that
expectation is only met 50 percent of the occur on projects that one is not corresponds to each estimate class.
time. controlling, such as poor These data are presented in figure 3 and
Unlike the FEL 1 and FEL 2 management of resources, design are expressed as the percentage of
estimates, which are systematically changes, poor labor productivity, project definition complete.
underestimated, it is noted that the FEL poor planning, and/or a host of IPA’s FEL Index is a more robust
3 estimates, on average, have a cost other possibilities that drive the measure of the “level of project
deviation near 0 percent. However, larger than expected cost variations. definition” as it measures the status of
these estimates deviate from the AACE • The quantification of risk (through key deliverables related to the project
International RP as they show a larger the contingency setting exercise) is scope (e.g., process and instrumentation
degree of variability than expected with not robust enough to properly diagrams, plot plans). From a cost
respect to both underruns and overruns, identify and quantify risks to the estimating perspective, the FEL Index is
which indicates Industry is as likely to project [8]. And, useful as it provides a measure of the
underestimate risk as overestimate risk. • The cost estimates are being completeness of the project inputs used
developed with deficient inputs, to develop the estimate. Using the FEL
such as incomplete project design or index, one is able to segregate industry
underdeveloped project execution projects which have substantial gaps and
plans. uncertainties in their design, versus

36 COST ENGINEERING NOVEMBER/DECEMBER 2012


those projects which have completed all experienced by industry as based on a Capital Cost Estimation. The
key deliverables to a best practical level review of historical project data. Engineering Economist: 53, (April-
of project definition. Given this finding, one concludes June 2008): pp 118-139.
Figure 11 presents the distribution that the estimating community, as it is 4. Chuong, Yuteck. Project Estimate
of cost deviations for FEL 3 estimates currently presented to the sponsors and Reviews for Oil and Gas Projects.
from a subset of industry projects that gatekeepers of projects, is setting the 2007 AACE International
had completed all necessary design expectation of estimate accuracy that is Transactions. Morgantown, WV
engineering deliverables to support the not sustainable when compared to 2007.
authorization estimate. As presented in historical performance. In most cases, 5. Dysert, Larry. Scope Development
figure 11, the cost deviation for this the project stakeholders have an Problems in Estimating. 1997 AACE
sample of 253 projects shows unfounded sense of confidence that an International Transactions.
significantly less variability (i.e., greater estimate will accurately predict final cost Morgantown, WV: AACE
amount of precision) than the overall within its published ranges. International, 1997.
industry FEL 3 distribution. This disconnect between 6. Dysert, Larry. Is “Estimate Accuracy”
The mean cost deviation for FEL 3 expectations and reality is difficult for an Oxymoron. 2006 AACE
estimates that have achieved an both the cost estimating community and International Transactions.
appropriate level of engineering the project management community as Morgantown, WV: AACE
definition is 2 percent with a range of a whole. Would a decision board feel International 2006.
−35 to 70 percent. The standard comfortable authorizing a project with a 7. Hollman, John, editor. 2006. Total
deviation of 21 percent indicates that Class 3 estimate if it knew that there was Cost Management Framework: A
approximately 66 percent of this a less than 50 percent chance that it Process for Applying Skills and
industry subset will be completed with would actually come within its published Knowledge of Cost Engineering.
finals costs within ±20 percent of the range? The authors suspect that this is AACE International. Morgantown,
estimated cost. not the case. WV.
Using a standard t-test for statistical However, the authors note that one 8. Hollman, John. Estimate Accuracy:
difference, the authors found statistically tool that is available to the estimator and Dealing with Reality. 2012 AACE
significant differences for both the mean the gatekeeper is the knowledge that International Transactions.
and standard deviation of both project those chances greatly improve if the Morgantown, WV 2012.
sets (Pr < 0.0001 and 2*Pr < 0.0001, project has completed all key design 9. Jambhekar, Vijay and Stephen D.
respectively) between the well-defined deliverables at authorization. This means Weeks. Estimate Review and
project group and projects group that moving forward without any open scope, Assurance – Owners Challenges.
had gaps in engineering having the required deliverables to 2007 AACE International
The results in figure 11 clearly support quantity take-offs, and having a Transactions. Morgantown: WV
demonstrate that to improve estimate functionally integrated team that is 2007.
accuracy and precision, an organization aligned on that scope. Even then, 10. Lavingia, Nick. Improve Profitability
must first focus on project inputs and opportunities still clearly exist to Through Effective Project
completing those key deliverables which improve estimate accuracy to the point Management and TCM. 2003 AACE
are required to produce an accurate at which industry is actually capable of International Transactions.
estimate. This conclusion is not new to achieving the AACE International Morgantown: WV 2003.
the industry and has been a major classification standards in practice. ◆ 11. Lavingia, Nick. How to Create a
finding in a range of studies focusing on World Class Project Management
the outcomes of capital projects. Organization. 2006 AACE
[5,12,13,14] Given these results, one REFERENCES International Transactions.
must conclude that Industry should first 1. AACE International. Cost Estimate Morgantown: WV 2006.
and foremost focus on project Classification System -- As Applied in 12. Merrow, E., Kenneth S. Phillips, and
fundamentals to improve overall Engineering, Procurement, and Christopher W. Myers.
estimate accuracy. Construction for the Process Understanding Cost Growth and
Industries. Recommended Practice Performance Shortfalls in Pioneer
Conclusion 18R-97. AACE International. Process Plants. RAND/R-2569-DOE,
The authors’ data demonstrate that Morgantown, WV, (latest revision). Santa Monica, CA. The RAND
the AACE International estimate 2. AACE International. Cost Estimate Corporation, 1981
classifications express a set of ranges Classification System – Cost 13. Merrow, E. Understanding the
that roughly correspond with the degree Estimating and Budgeting. Outcomes of Megaprojects: A
of confidence in a given point estimate. Recommended Practice 17R-97. Quantitative Analysis of Very Large
However, the current level of variability AACE International, Morgantown, Civilian Projects. RAND/R-3560-
expected by industry (as quantified in WV September 2003. PSSP, Santa Monica, CA, The RAND
the AACE International RP 18R-97) does 3. Bertisen, J. and Graham A. Davis. Corporation, 1988.
not represent the overall variability Bias and Error in Mine Project

COST ENGINEERING NOVEMBER/DECEMBER 2012 37


14. Merrow, Edward W. Industrial ABOUT THE AUTHORS
Megaprojects. John Wiley & Sons,
Inc. New York, NY 2011.
15. Oanda Currency Converter,
http://www.oanda.com/currency/c
onverter/. Alexander Ogilvie is Fredrick P. Biery is
16. Smith, Mark A. and Richard L. with Independent with Independent
Tucker. An Assessment of the Project Analysis. He Project Analysis. He
Potential Problems Occurring in the can be contacted by can be contacted by
Engineering Phase of an Industrial sending an e-mail to: sending an e-mail to:
Project: A Report to Texaco, Inc. aogilvie@ipaglobal.com fbiery@ipaglobal.com
Austin, TX: The University of Texas,
1983.
17. The Construction Industry Institute.
Pre-Project Planning Handbook. CII
Special Publication 39-2. 1995. Robert A. Brown, Jr., is
18. Whiteside, James D. and Tyler with Independent Paul Barshop is with
Humes. Front-End Engineering and Project Analysis. He Independent Project
Design: Influence Over a Project’s can be contacted by Analysis. He can be
Outcomes. 2010 AACE International sending an e-mail to: contacted by sending
Transactions. Morgantown, WV: rbrown@ipaglobal.com an e-mail to:
2010. pbarshop@ipaglobal.com

2013 CONSTITUTION AND BYLAWS AMENDMENTS EXPLAINED


The Governance Task Force created a PowerPoint presen- as ex-officio members of their respective associate boards and
tation to explain its proposed amendments to the AACE Con- these positions could be filled by the current associate chair if
stitution and Bylaws. The PowerPoint presentation may be desired by the associate board.
viewed at http://www.aacei.org/mbr/gtf_recommendations.ppt The Second Recommended Change in the Board of Direc-
An online webinar is set for 8 a.m. Eastern Time on Nov. tors structure would be splitting the current Vice President-Re-
13 at https://www2.gotomeeting.com/register/251679458. gions into two positions, Vice President-North American
Registration is free but does require advance sign up. Regions and Vice President-International Regions. Consistent
AACE International Board of Directors is recommending with the direction of the current strategic direction to pursue
that members approve provisions to provide more direct rep- international growth, this structural change will assure that
resentation in the Association’s decision-making process by its there will always be international representation on the Board
three associate boards. In addition, the Governance Task Force of Directors while also assuring adequate attention is provided
recommends the creation of an Executive Committee to han- for the sections in North America. The two vice presidents for
dle routine administrative and executive functions requiring regions will be elected on alternate years for continuity pur-
Board of Directors attention. If approved by the membership poses. Regional representatives to the Board of Directors will
in an election in 2013, the net effect will be to expand the AACE remain unaffected.
International Board of Directors by three members in 2014-15. A Third Recommended Change is the creation of an Exec-
The recommended amendments include a provision for utive Committee comprised of the officers of the Association.
direct representation by the three associate boards, Technical, The Executive Committee will recommend actions for consid-
Education and Certification on the Board of Directors. Cur- eration of the entire Board. Any actions recommended will re-
rently, those entities are represented by a single officer, Vice quire a subsequent two-thirds approval by the entire Board of
President-TEC (Technical, Education and Certification). Directors by electronic ballot. The entire Board of Directors
As a result of the direct representation on the Board of Di- focus on strategic and policy issues when we are deliberating
rectors, the current position of Vice President-TEC would be as a Board of Directors. “Our task force firmly believes that
phased out. these recommended amendments are in the best interests of
Each associate board’s representative to the Board of Di- the Association in achieving our mission and vision. At the
rectors would be nominated by each associate board’s respec- same time we want to assure that all members have an oppor-
tive nominating committee and approved by two-thirds of the tunity to ask questions and express their opinions prior to vot-
respective associate board. The new positions would be enti- ing on the recommendations from February 1-March 15,
tled Vice President-Technical Board, Vice President-Education 2013,” Task Force Chair, Steve Revay stated.
Board and Vice-President-Certification Board. All would serve

38 COST ENGINEERING NOVEMBER/DECEMBER 2012


TECHNICAL ARTICLE

Common

in Dealing With Project Risk


Joseph A. Lukas, PE CCE

Abstract: Unfortunately, many people using risk management do not fully under- that should be followed when dealing
stand basic risk concepts and therefore use incorrect techniques in preparing and with risks. Here are the processes that are
implementing risk management plans. The author has reviewed and critiqued to be done as part of risk management
client risk management process and procedures, along with risk management [3]:
plans for projects, and the same mistakes reoccur on a regular basis. Based on
these reviews, this article will present the top ten errors people make in dealing • Prepare  a  Risk  Management  Plan—
with project risks and how these mistakes greatly reduce the value of risk man- This should be completed early in the
agement. The author has also done numerous projects where risk management project planning phase. First decide if
was successfully used, and this article will also discuss effective risk techniques risk management is needed. On
that should be used on all projects. If you think you know how to deal with project some small, simple projects it may
risks, read this article to see if you are making any of these common errors. You
not be value adding. But for most
may be surprised! This article was first presented as RISK.944 at the 2012 AACE
International Annual Meeting in San Antonio, Texas. projects risk management is needed.
The risk management plan should
Key Words: Contingency, projects, risk management, and schedule document the techniques, tools and
responsibilities for risk identification,
risk analysis, risk response planning

W
hen the word risk is used uncertain risk events, which can have and risk monitoring and control.
in casual conversation it good or bad impacts on the project. • Identify the Project Risks—The most
invariably has a negative Risk management includes the commonly used techniques are
connotation: risk is bad processes of identifying potential project brainstorming and checklists. As part
and should be avoided whenever risks, analyzing risks, planning responses of risk identification also identify any
possible. The dictionary reinforces this to the most important project risks, and triggers for each risk, which are early
negative connotation by defining risk as also monitoring and controlling risks over warning indicators that the risk event
the possibility of loss or injury, or the life of the project. The goal of risk may occur.
someone or something that creates or management is to maximize the effects of • Analyze  the  Project  Risks—The
suggests a hazard [1]. potential opportunities, and minimize or simplest technique is assigning a
However, for project management eliminate the threats to the project value for the probability and impact
risk has a less threatening and more objectives. of each risk and calculating the risk
realistic definition as, “any uncertain factor. The risks are then prioritized
event or condition that, if it occurs, has a Risk Management Process and the highest scores are the
positive or negative effect on a project’s Before exploring the common errors threats and opportunities that
objectives” [2]. In this expanded scope of made in dealing with risks, let’s review should be actively managed as part
understanding, risk is associated with the suggested process steps for managing of risk response planning. On larger
uncertainty—the possibility that things project risks. This will ensure a common projects advanced risk analysis using
will not go as planned because of understanding of the sequential actions

COST ENGINEERING  NOVEMBER/DECEMBER 2012 39


quantitative techniques, such as Error #1: Not Considering Opportunities
Monte Carlo analysis, may be Most project teams view risk as bad • Exploit – take steps to make sure the
appropriate. and to be avoided whenever possible, opportunity happens.
• Plan  Responses  for  Project  Risks— and therefore ignore the possibility that • Share – shares the opportunity with
The project team should decide on something beneficial might happen as a another group that is better
actions to be taken to deal with the result of a risk event. However, successful positioned to take advantage of it for
threats and opportunities. The project teams need to deal with all the benefit of the project.
responses should include the actions project risks, and using the simple • Enhance – take steps to increase the
to be taken to deal with the risk definition below will help you focus on probability and/or the positive
event before it may happen, along both good and bad risk events: impact of the opportunity (note that
with contingency plans that will be increasing the probability and/or
implemented if the risk event PROJECT RISKS = OPPORTUNITIES + impact values increases the risk
happens. And, THREATS factor value). And,
• Monitor  Control  Risks—Managing • Accept – take no steps to actively
risks is an ongoing process over the Consequently there are two kinds of pursue the opportunity, but take
entire life of the project. This risks to consider on projects—threats and advantage of the opportunity if it
includes identifying and dealing with opportunities. Threats are easier to happens.
any new risks. understand because when they occur
there is a negative impact on the project Let’s look at an example for each of
objectives. In contrast, a favorable or these response strategies, and how the
Common  Errors  Made  in  Managing advantageous impact on project identification and planning for a specific
Project Risks objectives when a risk event occurs is an opportunity might look:
The top ten errors project teams opportunity. Dealing with major threats
make with risk management will now be obviously needs to be done on projects, • Exploit—Your resource plan includes
listed. As noted, this is based on but don’t forget to consider and take adding Susan, a senior electrical
consulting work with numerous clients. advantage of opportunities. Many people engineer, starting in January, when
The list covers the mistakes in sequential have a difficult time thinking of project her work on another project will
order when doing risk management on a opportunities, so here are some finish. It’s now early November, and
project, and is not intended to be a examples from recent projects: you find out the other project has
prioritized list of errors. been cancelled. Looking at your
Here are the top ten risk errors made • Special pricing offered by a supplier. schedule, you realize changing the
on projects: • Competitive market conditions for a sequencing of some project work will
specific service. allow you to use Susan now and save
• Not considering opportunities; • Sudden availability of a key resource three weeks in your project
• Confusing risk causes, events, and for a short time period because of schedule. You contact the resource
impacts; another project being postponed. manager and request Susan be
• Using checklists and not looking for • Availability of some needed immediately reassigned to your
other possible risk events; equipment (such as servers or project. Reworking your schedule
• Underestimating impacts; desktop computers) from another and immediately requesting Susan is
• Not using 100% probability during company that is downsizing their exploiting the opportunity created by
project planning; operations. And, the cancellation of the other project.
• Not considering sensitivity with risks; • Availability of a government • Share—During the planning phase
• Calling risk response planning investment tax credit for work done for your laboratory renovation
mitigation; before a specified date. project, you discover a new flexible
• Not considering contingency plans piping technology that can reduce
along with response plans; Most project teams do develop plans service piping installation time for
• Not making team members to deal with threats, but unfortunately the lab benches by 30% with minimal
responsible for specific risk events; very few plan for opportunities. That is a cost impact. You preliminary plan is
and, mistake because planning will let you take based on using an internal
• Not making risk management an on- advantage of these opportunities if they maintenance group for the piping
going process. do occur. How many times have you work. However, they don’t have the
heard about ‘lost opportunities’ on knowledge and experience in
The rest of this article will cover each projects? That happens when specific working with the flexible piping
risk mistake in more detail, along with plans are not developed to make the technology. Since the lab bench
effective risk techniques that should be opportunities reality. piping is on the critical path and the
used on all projects. client sponsor wants to improve the
Listed next are the four risk response end date, you decide to outsource
strategies for opportunities [4]: this work to a contractor with

40 COST ENGINEERING NOVEMBER/DECEMBER 2012


Figure 1 — Effective Risk Identification Tool

expertise in flexible piping systems, opportunity for the painting identification process by not providing a
and release the internal contractor to earn some extra profit. focus on actual risk events and this is
maintenance group for work on The action of meeting with Jim and important because risk events have one
other projects. This is a share since getting his support increases the unique feature, and that is uncertainty!
you are taking advantage of the probability of the scope change
opportunity (using flexible piping) to being approved. • A risk  cause is a definite event or
shorten the schedule, and the • Accept—The testing team leader circumstance that exists. A cause is a
contractor is making a profit on the informs you there is a chance the fact and has no uncertainty. For
work. integration testing on your software example, multiple job opportunities
• Enhance—Your company has been development project will not take as for top notch programmers, resulting
selected as the painting contractor long as the plan shows, but the from a shortage of computer
for a bridge renovation project. The probability is low and best case it programmers in the region, would be
project specification calls for a paint might save up to one week for the a risk cause.
with a 15-year life. However, your one year project. You decide to • Risk  events are simply things that
company has developed a new epoxy record the opportunity in the risk may or may not happen. An example
paint that will last 30 years or more, register, but take no other actions at of a risk event would be losing one or
and it only costs 30% more than the this time since the impact to the more key software programmers to
standard paint (but has a higher project is minimal. another software company who
profit margin since it is a proprietary offers them more money.
product of your company). You notify Error  #2:  Confusing  Risk  Causes,  Events •      Risk impacts are the results that will
the project manager, Rita, of this and Impacts occur if the risk event happens. For
opportunity. She likes the added The first step taken by a team in the example above, if a key software
value, but the state Department of implementing the risk management plan programmer leaves for a higher
Transportation (DOT) Director will is risk identification, which is determining paying job, it probably will have an
have to approve the change. Rita which risks may affect the project and impact on the project cost and
suggests a meeting with the DOT understanding the characteristics of each schedule.
project engineer, Jim, to discuss the specific risk event. Common tools used by
benefits and enlist his support in many project teams for risk identification An effective risk identification
getting the change approved. Rita is are checklists and brainstorming along technique is expressing each project risk
confident Jim will support the scope with interviews of key project as a sentence. Your sentence should
change and help obtain the stakeholders. include the cause, risk event, and impact
necessary approval within the DOT. However, a common error during risk as shown below [5]:
This is an opportunity for the project identification is not differentiating
since the better paint will last between risk causes, risk events, and
substantially longer, plus an impacts. This failure can dilute the risk

COST ENGINEERING  NOVEMBER/DECEMBER 2012 41


Because of <Cause>, <Risk Event> Could To initially develop the checklist for There are four possible
Occur, Resulting In <Impact> group of similar projects, get some consequences for any risk event:
experienced project personnel together
Note that a risk event may have more and brainstorm the risk events they have • cost;
than one cause, and more than one encountered on projects. The checklist • schedule;
impact. This technique can be used to should be considered a dynamic • functionality; and
fully describe each identified project risk, document, and as previously unidentified • quality.
and is an effective method to help keep risk events occur on other projects, these
the project team focused on the actual risks should be added to the checklist. Each needs to be considered when
risk events. The lesson learned sessions done at deciding the risk impact value. However,
project completion is also a good place to it’s also important to prioritize these
One tool that can be useful during identify new risk events that should be impacts based on what’s most important
brainstorming sessions is the use of post- added to the risk checklist. for the project. In some cases it may be a
it notes as shown in figure 1. A separate When using checklists, it can be specific end date that must be met
sheet of chart paper is used to list risk helpful to segregate the risks into because of a government regulation, or
causes. The post-it note format has the categories. The exact grouping will maybe a fixed budget that cannot be
risk event description in the center, and depend on the needs of the organization. exceeded. If the most important driver
the cause numbers listed on the left. The One set of categories frequently used is for a project is meeting a completion
four possible impacts are listed on the by project phase: initiation, planning, date, then a risk event that will delay the
right side of the post-it note and the design, build, test, and deployment. For completion date should be assigned a
applicable impacts are circled. Risk the civil engineering company doing road bigger impact value compared to a risk
categories can be added at the top, and construction, a grouping that could be event that just impacts cost.
the post-it note is also used for risk used is design, government/regulatory, Shown in table 1 is the impact table
analysis, with values assigned for contractor, suppliers and weather. for a specific software development
probability and impact, and the Some teams have used the project [6]. For this project the budget
calculated risk factor. This format has categories of cost, schedule, quality and was fixed and was the most important
been successfully used on numerous functionality to organize their risks. This project driver—the budget could not be
projects. isn't a good idea, however, since these exceeded. Functionality and quality were
four categories are also the risk impacts, secondary drivers, and if the budget was
Error #3: Using Checklists and Not and many risk events will have more than in jeopardy, functionality reductions
Looking for Other Possible Risks one impact. What that means is that if could be considered. Schedule was least
Many organizations do similar you try using this set of categories you important, since the company had
projects over and over. Examples include won't be able to easily place risk events existing software in use and could
a civil engineering company specializing with multiple impacts into a single continue using the software if the
in road construction, or a computer category. completion date slipped.
programming company that only does As discussed above, a risk checklist is Let’s consider a sample risk event
data migration projects. Most of the risk not inherently a bad thing, but you must that has a cost impact score of 8, a
events will be the same from project to make sure the identification of any schedule impact value of 0, and impact
project, and in these situations the use of additional risks is done in conjunction scores of 4 for functionality and quality.
a risk checklist is effective. with use of the checklist. Use The obvious question is what impact
The problem with this approach is brainstorming to find new risks. One value would the project team use for this
complacency—making the false technique is to award a simple 'prize' risk event? Is it the average of the four
assumption that the only possible risk such as a car wash or movie ticket to the impact scores, which would be 4? The
events are included in the checklist. The team member who identifies the most answer is no! The correct method is using
checklist can certainly be a good place to new risk events not already on the the highest value for the impact score. In
start, provided it is not the only thing checklist. this case that value is 8, which is the cost
done to identify risks. Your team also impact score.
needs to ‘scan the horizon’ to identify any Error #4: Underestimating Impacts Be careful when discussing
other possible risk events not on the One area that some project teams prioritization of project drivers with
checklist that may impact the project. struggle with is underestimating the clients. The answer you’ll frequently here
For example, the civil engineering impacts of risk events. This may be is that everything is equally important!
company may have an excellent risk because of the optimistic nature of That’s an easy answer but most often not
checklist, but the company is awarded a project teams—especially early in the really true. If a client has a project with a
new project and the road will cross an old project. When the impacts are fixed end date that MUST be met, cost is
abandoned landfill. This will undoubtedly understated the risk factor calculations probably not as much a consideration. It
create some unique risk events for this become skewed, the prioritization may still be important—but not as much
new project which are not currently on becomes flawed, and the entire risk as schedule. A perfect example of this is
the checklist. management process is threatened. the year 2000 projects (Y2K). There was a

42 COST ENGINEERING NOVEMBER/DECEMBER 2012


definite end date of December 31, 1999, plan for the requirements document considered. Monte Carlo is a risk
and for clients that was the project driver. deliverable, listing the specific people at simulation technique, and can help better
each plant site needed for requirements understand the project risk events. With
Error #5: Not Using 100% Probability definition, and the dates of the planned risk simulation, when discussing the
During Project Planning meetings to define requirements. The probability and impact of a risk event,
At the beginning of this article a risk actions also included a contingency plan instead of a single value being identified
event was defined as having uncertainty, where if a person missed a meeting, the there is a most likely value, along with an
so it may be confusing now stating that a project sponsor was immediately notified optimistic and pessimistic value. Risk
risk event can have 100% probability and the sponsor contacted the simulation software can show the
during project planning. 100% probability appropriate plant manager to resolve the frequency of possible outcomes and a
means no uncertainty—it’s a fact. This is problem. By the time the project planning cumulative cost and/or schedule with
not a conundrum because before phase was completed, the risk probability overrun probabilities.
completion of project planning you will of having missed requirements dropped
take actions to deal with some of the from 100% down to around 30%. Error #7: Calling Risk Response Planning
project risks, and these actions should A final caution—don’t overuse the ‘Mitigation’
reduce the risk event probability below 100% probability approach. It should only A common mistake made by many
100%. Project execution cannot begin be used where the risk really will happen project organizations is calling risk
with risk events that have a probability of unless actions are taken and the impacts response planning ‘mitigation.” That is
100% because they are facts and the are major. Otherwise, you run the risk of incorrect, since mitigation is just one risk
project plan must be prepared to deal losing credibility. response technique and is specifically
with these facts. used for dealing with risks that are
However, giving a risk event a Error #6: Not Considering Sensitivity threats. Another term often used to
probability of 100% during project with Risk Analysis describe risk response planning is ‘risk
planning will obviously call lots of The simplest technique for management plan,’ and that’s also
attention to that risk event provided it qualitative risk analysis is assigning a incorrect since that is part of the project
also has a high impact—and that will value for the probability and impact of plan and describes what the team will do
either result in actions taken to reduce each risk and calculating the risk factor. to manage risks on the project. One final
the probability and/or impact to a lower The risks are then prioritized and the term that should not be used to describe
value, or changing the project plan to highest scores are the threats and risk response planning is ‘risk
eliminate the risk, or constructing the opportunities that should be actively assessment,’ which more correctly means
project plan to deal with the 100% reality managed as part of risk response identifying and analyzing risks—so the
of the risk event. planning. This simplified approach recommendation is to avoid use of this
An actual project example is a ignores the sensitivity around the term.
customized software development probability and impact values. In reality, The product of risk management is
project for use at company these are not fixed values, but are a range called the risk register and it includes the
manufacturing locations around the of values. list of identified risk, the risk analysis
world. Business was good and the On smaller projects qualitative risk results and the risk response plans
manufacturing areas were extremely analysis is usually ‘good enough.’ including contingency plans. The correct
busy. The project team correctly realized However, on larger projects advanced risk term to use for describing what steps will
a major risk event would be having analysis using quantitative techniques, be taken to deal with risks is, ‘risk
incomplete project requirements such as Monte Carlo analysis, should be response plan.’
resulting from an inability to get the
manufacturing representatives to take
time to meet and adequately explain
their requirements.
Incomplete requirements would
probably result in a solution design that
didn’t meet all of the manufacturing
plant needs. The project team gave the
risk of incomplete requirements a
probability of 100% and informed the
project sponsor the project would fail
unless this risk was dealt with during
project planning. A risk response plan
was developed and implemented for this
risk.
The actions taken included a
comprehensive schedule and resource Table 1 — Project Impact Table for a Sample Software Project

COST ENGINEERING NOVEMBER/DECEMBER 2012 43


Table 2 — Risk Register Example

When risk mistake #1 was discussed, on a software project. This provides more likely to happen for opportunities
the commonly used risk responses for the project team with a known cost, and less likely to happen for threats.
opportunities were described. Listed next and the threat of a cost overrun Contingency plans are more specifically
are the common risk responses for belongs to the vendor (along with the actions that will be taken if and when
threats [4]: the opportunity to complete the the risk event occurs. Risk response
work for less money and make more planning should deal with both!
• Reduce (Also called Mitigation)— profit). Let’s revisit the common risk
This response seeks to reduce the • Accept—This response is deciding responses for threats covered in mistake
probability and/or impact of a not to do anything about the risk. #7. The mitigation example was losing a
negative risk event. An example of This may be because no other key project resource because of a person
reduce is offering a performance actions are feasible, or the risk factor leaving the company. The contingency
bonus to a key project resource to isn’t significant. The response can be plan for this example would be
mitigate the potential of the person active acceptance, which means identifying a back-up resource (either
leaving the company before project developing a contingency plan if the internal or a contractor) that could step in
completion. The performance bonus risk event occurs. An example is and handle the work if the person does
reduces the probability of the person building a new store in upstate New leave the company. For the acceptance
leaving. York in January. It will snow—so example of building a store in upstate
• Eliminate (Also called Avoidance)— active acceptance is the best New York in winter weather, contingency
This response looks to eliminate the approach. You can’t control the planning could be adding some extra days
threat by taking actions to cause the weather! in the schedule as an allowance for non-
risk to go away completely. This is working days because of snow, and/or
usually done by eliminating the In summary, mitigation is just one including money in the budget for plastic
causes. When you avoid, the risk is risk response technique, and it is sheeting and space heaters so work can
gone! There is no need to do any specifically used for threats. Do not call continue even if snow occurs.
contingency planning, because the risk response planning ‘mitigation’—the One final comment is that not all
risk no longer exists. An example of correct term to use for describing what risks need a contingency plan! The
avoidance is a developer looking to steps will be taken to deal with risks is example used for transference was using
build a new store decides not to ‘risk response plan.’ a firm fixed price contract with a vendor
build in a certain town because of a for the data migration work on a software
hostile town board which probably Error #8: Not Considering Contingency project. The risk impact now belongs to
will hold up the zoning approval. Plans Along With Response Plans the vendor so the project team doesn’t
• Transfer—This response shifts some As mentioned with mistake #7, the need to worry about a cost overrun. The
or all of the threat to a third party. correct term to use for describing what example used for avoidance was a
The risk doesn’t go away, but the steps will be taken to deal with risks is developer looking to build a new store
ownership and impact of the risk ‘risk response plan,’ but don’t forget that deciding not to build in a certain town
belongs to somebody else. An should also include a contingency plan! because of a hostile town board. Since
example of transference is using a To clarify the difference, the risk the decision was made not to build in the
firm fixed price contract with a responses are actions taken before the town with a hostile town board, the risk
vendor for the data migration work risk event occurs to make the risk event

44 COST ENGINEERING NOVEMBER/DECEMBER 2012


no longer exists. In both cases a For each risk event, the responsible Second Edition, Simon & Schuster,
contingency plan is not pertinent. team member should provide a brief Inc., New York, (1979): pg. 1565.
status report on the risk response actions 2. A Guide to the Project Management
Error #9: Not Making Team Members taken and/or planned, along with Body of Knowledge, Fourth Edition,
Responsible for Specific Risks changes to the probability and/or impact Project Management Institute,
One observation is that some project values based on actions taken. The Newtown Square, PA, (2008): pg.
managers are not effective at delegating project team should also discuss if any 438.
work, and end up taking responsibility risk triggers have occurred, and whether 3. Lukas, Joseph A., It Works! Risk
where other team members could be any new potential risk events have Management on an IS Project,
used. Part of risk response planning is surfaced since the last meeting. Proceedings of the PMI Seminars
assigning ownership of each risk to an The key point is that risk and Symposium, Project
individual. management is an on-going process over Management Institute, Newtown
Assign each risk to a specific the entire life of the project! Watch for Square, PA, (2002): pg. 2.
individual on the project team, and the certain phrases that appear in people’s 4. Brady, David C., January 12, 2012,
project manager should minimize the conversation, such as “there is a chance Risk Treatment AACE® International
number of risks assigned to her/himself. that …” or “maybe this would cause Recommended Practice No. 63R-11
The assigned person should implement problems …” When you hear words like Public Review Draft, (Jan. 12, 2012):
the risk response plans, monitor the risk that, ask for clarification, and it may pgs 6-8.
and report on the risk status. Assign each become apparent that this is a new risk 5. Hillson, David. Project Risks,
risk to the team member who has the event and should be added to the risk Identifying Causes, Risks and Effects,
particular skills related to the risk. register. PM Network, (Sept. 2000): pgs. 48-
For example, a risk concerning the 51.
requirements elicitation work on a Conclusion 6. Lukas, Joseph A. Risk Management in
software project should be assigned to a Many people using risk management the Real World: A Look at an IS
business analyst, while a metallurgy risk use incorrect techniques in preparing and Project, Inside Project Management,
on a construction project should be implementing risk management plans. Element Journals, Rochester, NY.
handled by an engineer. This article has covered the top ten errors Volume 1, Number 6, (2001): pg. 13.
people make in dealing with project risks
Error #10: Not Making Risk Management and how these mistakes greatly reduce ABOUT THE AUTHOR
an On-going Process the value of risk management. Check how
Unfortunately, some project teams you are doing risk management on your
think of risk management as a task that is projects and see if you are making any of
started and completed as part of project these common errors. You may be
planning. The risk register is completed surprised! ◆ Joseph A. Lukas is with
and then filed away and forgotten. This is PMCentersUSA. he
the mistake—a risk management review REFERENCES can be contacted by
should be part of every project team 1. McKechnie, Jean (Editorial Staff sending e-mail to:
meeting! Shown in table 2 is a sample Supervisor), Webster’s New joe.lukas@pmcentersusa.com
risk register, which is a simple worksheet. Twentieth Century Dictionary,

2012-2013 NOMINATING AND AWARDS COMMITTEES


Past President Michael Nosbisch will serve as chair of the with biographical data, shall be made available to the membership along with
2012-13 Nominating Committee, which will include Ginette B. information regarding nominations by petition no later than November 15th
of each year.
Basak P.Eng FAACE; Philips Tharakan Mulackal CCE EVP, Section 4—Other nominations for the office of Director or the office of
Michael B. Pritchett CCE CEP, and Stephen P. Warhoe PE CCE an Officer of the Association may be made by petition signed by at least twenty
CFCC FAACE. The Nominating Committee will also serve as the (20) Members in good standing. The petitioners shall be responsible for (a)
2012-13 Awards Committee. obtaining in writing the agreement of the nominee to serve if elected, (b) se-
curing the biographical data of the nominee, (c) submitting the petitions, the
The responsibilities of the Nominating Committee are out- agreement, and the biographical data to be received by the Vice President-
lined in the Association Bylaws as follows: Administration no later than December 15th of each year. Each candidate’s
Section 2—The Nominating Committee shall be responsible for: (a) se- name and biographical data shall be made available to the membership no
lecting one or more nominees for each office, (b) obtaining the consent of later than December 31st of each year.
each nominee to serve if elected, and (c) securing biographical data of each To be eligible to vote, a member’s membership dues must be paid
nominee. The entire slate of candidates, complete with biographical data, shall through Dec. 31, 2012. Members also are restricted to voting for regional di-
be sent by the Nominating Committee to the Vice President-Administration rector candidates within the region where the member’s primary section affil-
no later than October 31st of each year. iation is located, according to the AACE records as of Dec. 31, 2012. Electronic
Section 3—The Nominating Committee’s slate of candidates, complete online voting will open on February 1 and concludes at 4 p.m. Eastern US Time
Zone on March 15.

COST ENGINEERING NOVEMBER/DECEMBER 2012 45


AACE INTERNATIONAL ONLINE STORE
more online at www.aacei.org
Skills and Knowledge of Cost Cost Engineering
Engineering, 5th Edition, Revised The international journal
Scott J. Amos, Editor, 2007 of cost estimation,
This updated and expanded guide for cost/schedule control,
fundamentals is an excellent choice for anyone project management,
interested in a concise reference to all aspects of and total cost
the profession. The new 5th edition includes management.
twenty-seven chapters on estimating, Subscriptions are
manufacturing and operating costs, scheduling, accepted on an annual
planning progress and cost control, and much basis. An automatic
more. This is a very useful book for those studying benefit of AACE
for the certification exam. 450 pages International
1595-02zip - Download - US$50.00 member/US$80 nonmember membership, also
available to nonmembers.
Paper version available through our Amazon.com link
5060-07 - US$72.00 (US)
- US$171.00 (other countries)
CCC/CCE Certification Study Guide, 
Please add US$80.00 for airmail
3rd Edition - US$61 electronic subscription
Michael B. Pritchett, CCE, Editor, 2006
The AACE International CCC/CCE Certification Cost Engineers’ Notebook          
Study Guide provides an all-encompassing This CD-ROM is an important reference for any
reference text to prepare for the exam. The project or cost professional. It includes data and
CCC/CCE Certification Study Guide provides procedures related to basic skills and knowledge
background information on how to become that all cost engineers should possess, extensive
certified; gives those studying for the certification material on capital and operating cost estimation,
exam a single reference text that includes theory, and papers in four subject areas: cost control,
worked problems with answers, references, and a planning and scheduling, project management, and
full discussion of key topics; allows students to economic analysis and business planning.
maximize their study time; and provides a concise 4060-28zip - Download
overview of the fundamentals of cost and project management. - US$65.00 member/US$105.00 nonmember
1825-36zip - Download - US$50.00 member/US$80 nonmember
Paper version available through our Amazon.com link AACE International Recommended Practices
Cost Engineering Terminology; Cost Estimate
Classification System; Estimate Preparation Costs in
PSP Certification Study Guide, 1st Edition the Process Industries; Project Code of Accounts;
Peter W. Griesmyer, Editor, 2008 Required Skills and Knowledge of a Cost Engineer;
This study guide is intended to assist you in your Roles and Duties of a Planning and Scheduling
study and review of the overall topics as one step Engineer; Profitability Methods; plus many more.
toward successful Planning and Scheduling Profes- 4060-05zip - Download
sional certification. The outline provides a listing of - US$70.00 member/US$110.00 nonmember
the terms you should know & topics for which you
should have a good understanding of how to apply The Total Cost Management Framework
the concepts to solve problems. Each chapter also John K. Hollmann, PE CCE, Editor, 2006
contains sample exercises, which test your knowl- 4060-20zip - Download
edge of that chapter's concepts. Additional sample
questions are provided in an appendix. - US$50.00 member/US$70.00 nonmember
Paper Version available through Amazon.com
1820-38zip - Download - US$50.00 member/US$80.00 nonmember
Paper version available through our Amazon.com link 2012 AACE International Transactions 
EVP Certification Study Guide,  5220-12 zip -
2nd Edition Download
Ken Cressman, CCC EVP and Gary C. Humphreys, - US$75.00
Editors, 2009 member
This study guide is intended to assist you in your - US$80.00
study and review of the overall topics as one step
toward successful Earned Value Professional certi- nonmember
fication. The outline provides a listing of the terms
you should know & topics for which you should For CD-ROM
have a good understanding of how to apply the con- version please
cepts to solve problems. Each chapter also contains contact AACE
sample exercises, which test your knowledge of that International
chapter's concepts. Headquarters
1820-40zip - Download - US$50.00 member/US$80.00 nonmember
Paper Version available through our Amazon.com link
The
The AACE
AACE International
International Professional
Professional Practice
Practice Guides
Guides (PPGs)
(PPGs)
Value; Earned Value Reporting; Applications of Earned PPG #14: Portfolio and Program Management,
Value Project Management; and more. 2nd Ed. 
Randy R. Rapp, PE CCE, Editor, 2007
PPG#6: Construction Cost Estimating, 2nd Ed. Covers: Enterprise Management: General Imperatives and
Dr. Douglas D. Gransberg, PE CCE, And Carla Lopez Concerns; Asset Requirements Elicitation and Analysis;
del Puerto, CCC, Editors, 2006 Asset Planning and Investment Decision-Making; Asset Per-
Covers: Recommended Practices; Estimating Theory; formance Assessment and Change Management; and Pro-
Conceptual, Parametric, and Range Estimating; Esti- gram Management.
mating Factors and Indices; Estimating Material Costs
and Quantity Surveying; Estimating Labor Costs; Esti- PPG #15: Life-Cycle Cost Analysis
mating Equipment Costs; Subcontracting Costs; Esti- Dr. Douglas D. Gransberg, PE CCE, and Carla Lopez
mating Overhead and Indirect Costs; Profit, del Puerto, CCC, Editors, 2007
Contingencies, and Mark-Ups; Estimating Interna- Covers: Life-Cycle Cost Theory; Life-Cycle Cost Methods,
tional Construction Costs; and more. Determining Discount Rate; Estimating Capital Cost of
Design and Construction; Estimating Operating Costs;
(PPGs) are a series of reference s that PPG#7: Cost Engineering in the Utility  Estimating Salvage/Residual Value; Estimating Sustain-
Industries, 2nd Ed. ability; Life-Cycle Cost Risk Analysis; Life -Cycle Cost
consists of selected Cost Engin eering  Dennis M. Thompson, Editor, 2007 Case Studies; Life-Cycle Cost Analysis in the Interna-
articles, AACE Inter national Transaction Covers: Auditing; Cost Estimating; Cost Modeling; tional Context
Cost/Schedule Control; Generation Power Plant; Nat-
papers, and other previously published ural Gas Industry; Nuclear Power Plant; Other Energy PPG #16: Cost Engineering in the 
documents to which AACE has rights. Related Topics; Planning and Scheduling; Project Global Environment
Management; Utility Rates; and Utility Property Valu- Kul B. Uppal, PE, Editor, 2007
ation. Covers: General Topics on International Projects; Appli-
cable AACE International Recommended Practices; Cost
Price per PPG:  PPG#8: Contingency, 2nd Ed. Estimating Methodology; Risk and Contingency; and
Kul B. Uppal, PE, Editor, 2005 Miscellaneous Topics
Download Member Price US$50.00 Covers: General Topics On Contingency; Cost Estimat-
Download Non-Member Price US$70.00 ing and Contingency; Risk Analysis and Contingency; PPG #17: Public Sector Estimating
and Other Related Topics. Joseph L. Macaluso, CCC, Editor, 2007
Price for the PPG Package  Covers: Basis of Estimates; Labor Costs; Overhead and
PPG #10: Project Delivery Methods, 2nd Ed.  Profit; Soft Costs; Bid/Estimate Reconciliation; and
includes all 21 PPGs: Dr. Douglas D. Gransberg, PE CCE, Tammy L. Mc- Change Orders
Cuen, and Keith Molenaar, Editors, 2008
Download Member Price US$874.00 Covers: Design-Bid-Build (DBB) – DBB Estimating, DBB PPG #18: Green Building
Download Non-Member Price Scheduling, DBB Project Management; Construction Joseph L. Macaluso, CCC, Editor, 2008
Management (CM) – CM Estimating, CM Scheduling, Covers: Recognition of Affects and Economic Costs on
US$1223.00 CM Project Management; Design-Build (DB) – DB Es- the Environment; Formulating Ways of Addressing
timating, DB Scheduling, DB Project Management; In- Green Building Strategies and Associated Economic
PPG#1: Contracts and Claims, 4th Ed. ternational Project Delivery; Constructability; and Costs; Specific Green Building Strategies and Project
James G. Zack Jr., Editor, 2008 Partnering. Costs; Budgeting and Justifying the Cost of Sustainable
Covers: Contract Administration; Management of Practices; Evaluating Competing Sustainable Strategies:
Construction Schedules; Schedule Control; Schedule PPG #11: Environmental Remediation &  Using Value Engineering; Evaluating Competing Sustain-
Float Ownership; Cost Control; Management of Decommissioning, 2nd Ed. able Strategies: Other Techniques
Change; Cost Impacts; Productivity Impacts; Manage- Richard A. Selg, CCE, Editor, 2009
ment and Analysis of Delay; Concurrent Delay Issues; Covers: Environmental Remediation Planning and PPG #19: Leadership and Management 
Pricing of Delay; and more. Scheduling Methodology; Cost Estimating, Project Con- of People
trols, Cost Modeling, and Reporting; Contingency Man- John J. Hannon, CEP, Editor, 2008
PPG#2: Risk, 2nd Ed. agement, Risk Analysis, and Environmental Regulations; Covers: Leadership; Teams; Leadership Roles; Motiva-
Keith D. Brienzo, PE, Editor, 2007 Benchmarking and Lessons Learned; Economics of En- tion; and Ethics.
Covers: Dictionary; Capital Investments; Cash Flow; vironmental and Waste Management; Cost-Effective
Competitive Bidding; Contingency Analysis; Contracts; Waste Minimization and Pollution Prevention; Design, PPG #20: Forensic Schedule Analysis
Cost Engineering; Currency Rates; Decision Trees; Eco- Construction Practices, and Other Related Topics. James G. Zack, Jr., CFCC, Editor, 2008
Covers: Recommended Practice No. 29R-03 Forensic
nomic Analysis; Escalation; Human Factors; Manufac-
Schedule Analysis; Synopsis of Recommended Practice;
turing; Research & Development; Safety & Health; PPG #12: Construction Project Controls
Basics of Schedule Delay Analysis; MIP-Observational
Schedule; Technological Risk; and Value Engineering. Dr. Douglas D. Gransberg, PE CCE, and James E.
Static Gross; MIP-Observational Static Periodic; MIP-Ob-
Koch, Editors, 2002
servational Dynamic Contemporaneous As-Is; MIP-Ob-
PPG#3: Cost Engineering in Aerospace and Avi- Covers: Introduction to Construction project Controls;
servational Dynamic Contemporaneous Split;
ation                   Cost Control; Schedule Control; Quality Control; Doc-
MIP-Observational Dynamic Modified or Recreated; MIP-
Sarwar A. Samad, Editor, 1998 ument Control; Computer Applications; and Interna-
Modeled Additive Single Base; MIP-Modeled Additive
Covers: Aerospace and Aviation. tional Project Controls
Multiple Base; MIP-Modeled Subtractive Single Simula-
tion; Non-CPM Schedule Delay Analysis Techniques;
PPG#4: Planning and Scheduling, 2nd Ed. PPG #13: Parametric and Conceptual  General Schedule Analysis Articles
Trevor X. Crawford, CCC, Editor, 2006 Estimating, 2nd Ed.
Covers: Planning; Schedule Development; Schedule Douglas W. Leo, CCC, Larry R. Dysert, CCC, and PPG#21: Cost Engineering in the Process 
Management/Control; and Classics. Bruce Elliott, CCC, Editor, 2004 Industries
Covers: Parametric/Conceptual Estimating; Classifica- Kul B. Uppal, PE CEP, Editor, 2009
PPG#5: Earned Value, 2nd Ed. tion; Methodology; Capacity Factoring; Process and Covers: General Topics on Process Industries; Cost Es-
Robert A. Marshall, Editor, 2007 Non-Process Industries; and Systems timating Methodology; Project Management; Inter-
Covers: Why Use Earned Value?; Basics of Earned national Projects; Scheduling; Construction Activities;
Value; Cost/Schedule Control System Criteria; Actual Risk Management; Project Controls; and Applicable
Physical Percent Complete; Productivity and Earned AACE International Recommended Practices.

More AACE Publications at the Online Store - www.aacei.org


PROFESSIONAL SERVICES DIRECTORY

All AACE International Books are


"Print-on-Demand" Products
AACE has reformatted each of its print products (i.e., the
Skills and Knowledge of Cost Engineering; CCC/CCE Certifi-
cation Study Guide; EVP Study Guide; PSP Study Guide; and
the TCM Framework) to be produced by a subsidiary of
Amazon.com. Each of these AACE publications became
available online from Amazon.com in 2012. We maintain a
link from the AACE website, www.aacei.org, to Amazon.com
and will recommend additional products as well. ◆

INDEX TO ADVERTISERS ADVERTISE


IN THE
Acumen, page 4 COST ENGINEERING
YOUR JOURNAL
ARES Corporation, back cover
VISIBILITY
Bechtel Corporation, page 3
REACH the entire AACE International mem-


D.R. McNatty and Associates, this page bership every month by placing an ad in the
Cost Engineering journal.
EcoSys, inside front cover
PLACE your products/services in front of


Faithful+Gould, page 48 over 50,000 users each month with a banner
Infinitrac, this page ad at our website, www.aacei.org.
EXHIBIT at the AACE International Annual


Management Technologies, this page
Meetings, and contact AACE International
Ron Winter Consulting, page 16 members face to face.

Sage Software, inside back cover CONTACT


Skire, Inc., page 16 Garth Leech
phone 1.304.296.8444 fax 1.304.291.5728
For additional information about the listed advertisers or about e-mail gleech@aacei.org
advertising with us, please phone Garth Leech, 1.304.296.8444
x122, or e-mail him at gleech@aacei.org
OR GO ONLINE AT www.aacei.org

COST ENGINEERING  NOVEMBER/DECEMBER 2012 49


Contrary to rumor, there is no certified League of TCM Heroes. Individuals who have earned
certifications such as the Certified Cost Consultant (CCC)/Certified Cost Engineer (CCE), Certified
Estimating Professional (CEP), Certified Forensic Claims Consultant (CFCC), Earned Value Profes-
sional (EVP), Planning & Scheduling Professional (PSP) and Certified Cost Technician (CCT) are:
• Not able to leap tall buildings in a single bound • Not more powerful than a locomotive
• Not faster than a speeding bullet • Not in possession of x-ray vision
But the AACE International Salary Survey did show that certificate holders earn an average
of $5,000 per year more than non-certification holders with the same age and experience!
If you want to be in the same salary “league” then visit
www.aacei.org for more information!
ARTICLE REPRINTS AND PERMISSIONS

COST ENGINEERING Vol. 54, No.6/November/December 2012


Members of AACE International have access to free downloads of selected articles
that are published with an AACE International reference number. These articles are
available at the online Virtual Library at www.aacei.org. Electronic files of each
month’s technical articles are posted and members can download an Adobe Acrobat
(PDF) version of any of the technical articles for free. You can search for articles
using the reference numbers listed in the Cost Engineering journal. Non-members
can subscribe to the AACE Virtual Library at an annual cost of US $100.00. AACE In-
ternational no longer offers reprints of individual articles.

Pages 5-15
Integrated Cost-Schedule Risk Analysis
Dr. David T. Hulett and Michael R. Nosbisch, CCC PSP
This article was presented as RISK.1043 at the 2012 AACE International Annual Meet-
ing in San Antonio, Texas.
Article Reference Number - 29188

Pages 17-27
Estimate Accuracy: Dealing With Reality
John K. Hollmann, PE CCE CEP
This article was first presented as RISK.1027 at the 2012 AACE International Annual Meet-
ing in San Antonio, Texas.
Article Reference Number - 29189

TO ORDER Pages 28-38


Contact: AACE International Publications Sales Quantifying Estimate Accuracy and Precision for the
at pubsales@aacei.org Process Industries: A Review of Industry Data
Alexander Ogilvie, Robert A. Brown Jr., Fredrick P. Biery
Photocopying Prices: and Paul Barshop
For permission to photocopy individual articles This article was first presented as RISK.1100 at the 2012 AACE International Annual
for personal use, or to request permission for Meeting in San Antonio, Texas.
bulk photocopying, please contact the Copy- Article Reference Number - 29190
right Clearance Center at 978.750.8400, and
pay the required photocopying fees. For any Pages 39-45
other use or reprint requests, please e-mail: Common Errors in Dealing With Project Risk
editor@aacei.org. Joseph A. Lukas, PE CCE
This article was first presented as RISK.944 at the 2012 AACE International Annual
Contact Us Meeting in San Antonio, Texas.
AACE International Article Reference Number - 29191
1265 Suncrest Towne Centre Dr
Morgantown, WV 26505-1876
USA
Phone: 304.296.8444
Fax: 304.291.5728

For Information Concerning


Other Reuse Requests
If you are seeking permission to quote or
translate into another language any material
from any issue of the Cost Engineering journal,
please contact our Managing Editor, Marvin
Gelhausen at mgelhausen@aacei.org

COST ENGINEERING  NOVEMBER/DECEMBER 2012 51


CALENDAR OF EVENTS
NOVEMBER 2012 4 The Federal Design & 27-30 AACE International
14-15 AACE International’s Construction Outlook Conference, Education Seminars,
International Total Cost Manage- AEC Science & Technology, LLC AACE International
ment Conference, Washington D.C. Convention Center Marriott Wardman Park
AACE International Washington D.C. Washington, D.C.
Hyatt Regency Dubai and Galleria Contact: phone 1.508.790.4751 Contact: phone 1-800-858-COST
Dubai, United Arab Emirates 1.800.996.3863 fax (304) 291-5728
Contact: phone 1-800-858-COST support@aecst.org info@aacei.org
fax (304) 291-5728 www.aacei.org
info@aacei.org APRIL 2013
www.aacei.org 17-19 Cost Engineering Event 2013 30-July 3 AACE International
- Total Cost Management; A World Education Seminars,
24 2012 ICEC Region 2 of Opportunities, Cost Engineering AACE International
(Europe/Near East) Meeting, Consultancy Marriott Wardman Park
The International Cost Engineering Ara Hotel Washington, D.C.
Council (ICEC) Zwijndrecht, Netherlands  Contact: phone 1-800-858-COST
FAST/AICE Premises Contact: +31 (0)78 620 0910 fax (304) 291-5728
Milan, Italy BDames@costengineering.eu info@aacei.org
Contact:  www.costengineering.eu www.aacei.org
www.icoste.org/category/meetings
JUNE 2013 Please submit items for future
28 - Dec 2 The First Australasia 18-23 ISEC-7, calendar listings at least 60
and South East Asia Structural The ISEC Society days in advance of desired
Engineering and Construction Campus Center of the University of publication.
Conference ASEA-SEC-1), Hawaii at Manoa
The ISEC Society Honolulu, HI AACE International, 
Curtin University Contact:  1265 Suncrest Towne Centre Dr,
Perth, Australia www.isec-society.org/ISEC_07/ Morgantown, WV 26505-1876
Contact: www.isec-society.org USA   
phone: 304-296-8444        
DECEMBER 2012 fax: 304-291-5728       
3-7 National BIM Conference, e-mail:  editor@aacei.org
AEC Science & Technology, LLC website: www.aacei.org
Washington D.C. Convention Center
Washington D.C.
Contact: phone 1.508.790.4751
1.800.996.3863
support@aecst.org

52 COST ENGINEERING NOVEMBER/DECEMBER 2012
JOB SITE,
MEET INSIGHT.
Learn about Sage solutions for estimating and construction.
» Visit our website at SageCRE.com/bidready to get the facts.
Make it easier for your estimators to bid on and win more projects with our business-aware, people-
connected applications for specialty and general contractors. Over 40,000 construction and real
estate firms, including over half of the ENR 400, rely on Sage solutions to manage more than 400,000
jobs and 5.7 million subcontracts every year. Join them and gain the insight to get job-ready today.
© 2012 Sage Software, Inc. and its aɉliated entities. All rights reserved.

Sage 50 • Sage 100 Contractor • Sage 300 Construction and Real Estate • Sage Construction Anywhere • Sage Estimating

Enabling Sage contractors of any size to achieve their ambitions.

You might also like