Professional Documents
Culture Documents
PM EM - Checklist
PM EM - Checklist
Develop Schedule
2 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
3 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
Building & Safety (Identify the Start R/W process (If necessary)
Case Manager) Submit project to Cultural Affairs (If
necessary)
Obtain Haul Route Permit
Obtain most recent utility drawings
SCAQMD from and coordinate with Q & S (if
necessary)
Fire Dept
Obtain Preliminary Geotechnical
Environmental Clearance from Report
the Environmental Group
Request Plans from Street Lighting,
Proceed with Design Phase LADOT, etc.(if necessary)
Develop 50% plans and specs.
Including GR's/GR's
Prepare 50% QA/QC checklist
4 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
5 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
7 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
8 of 9
This checklist to be filled out by the Project Engineer CIP No.: ______________
Contractor submits
Insurance
Bond
CSM to issue "Notice to Proceed"
Construction to Start
9 of 9