MOS - Core Cutting Repair
MOS - Core Cutting Repair
Date: 23-06-2022
Page|2
Table of Contents
1. Purpose
2. Scope of work
3. Reference Documents
4. Material
5. Manpower
6. Equipment & Tools
7. Quality Assurance and Control
Page|3
1. Purpose
This method of statement shows and explains the procedure that must be followed for the
construction of additional beam support at the place of coring hole rib damage.
2. Scope of Work
While working on coring hole, the precast slab’s rib was damaged. To provide an extra
support at weakened rib, an additional support beam shall be constructed. This proposed
beam shall rest on existing structural beam. Below is the procedure to be followed :
Step 1. Removing the existing water proofing slab, as per required dimensions (300mm
wideX300mm deep) as shown in the attached drawings below.
Step 2. Existing precast slab to be chipped at 1 metre interval until existing slab steel is
exposed. Then, the stirrups of the proposed beam shall be tied.
Step 3. After installing the steel of the proposed beam, formwork shall be prepared.
Step 4. Concrete shall be poured and curing will be done continuously until required
strength of concrete is achieved.
Step 5. After curing, the entire working area will be restored as per existing water proofing
system.
Page|4
Page|5
3. Reference documents
4. Material
Reinforcement steel
Cement concrete
Water proofing system
Sand
Gravel
5. Manpower
Superviser – 1
Page|6
Safety officer - 1
Carpenter - 2
Steel Fixer - 1
Skilled Labors – 2
Hand Tools
Safety Gear
Page|7