Name : Mrabet Ahmed

Email : ahmed.mrabet@ezar-ltd.com
Function : Lead Discipline Engineer

Planned Period Weekly Progress


Tasks Work Place LAY OUT FINAL PRODUCT (Result).. Remarks/proposition /amelioration
Planned Duration (per hours) Planned duration (per days) Progress Actual Duration

PR 171-34

Preparing general documentations for the Template daily report , Risk Waiting for Approval from
project PR 171-34 Assessement , Safety Plan , Monthly 90% Company
Office Report Template
Preparing list of technical datasheet of Consulting and preparation of 40% Ongoing
materials Office documents
Preparing of quantities for technical offres Detailed quantities related to
for suppliers 100% Done
Office engineering
Preparing QC documentation for the project ITP Template and , WPS and painting 100% Done
Office Procedure

Start Up of the project and ensure Company 0% Waiting for Manpower


Discipline rules Ensuring the suitable start up of the
Site project and organization of team
Working on applying procedure and Project Project Progress and prevention of 0% Waiting for Manpower
Execution Plan Site obstacles
Pr 171-72
Following up Project documentation Office Approval from client , preparation for invoicement 100% Done
Following Up Project Schedule Office Project Progress and site Organization 80% Done
WEEKLY AMELIORATION OBJECTIVE
Goal : Start Up of the project MP 16-52 , corrective actions for GTS 07-18 , Recovery Plans for GTS 07-18 64%
Name : Mrabet Ahmed
Email : ahmed.mrabet@ezar-ltd.com
Function : Lead Discipline Engineer

Tasks Work Place LAY OUT FINAL PRODUCT (Result)..

PR 171-34

Review general documentations for Template daily report ,


the project PR 171-34 Risk Assessement , Safety
Plan , Monthly Report
Office Template

Continue Preparing list of technical


datasheet of materials Consulting and preparation
Office of documents

Start Up of the project and ensure Ensuring the suitable start


Company Discipline rules up of the project and
Site organization of team
Working on applying procedure and Project Progress and
Project Execution Plan Site prevention of obstacles
PR 171-29
Preparation for the kickoff meeting Scope review
Pr 171-72
Following Up Project Schedule Project Progress and site
Office Organization
WEEKLY AMELIOR

Goal : Start Up of the project MP 16-52 , Preparing kickoff meeting PR 171-29


Planned Period Weekly Progress
Planned Duration (per hours) Planned duration (per days) Progress Actual Duration

90%

8h

40%
8h

0%
12 h
0%
12 h

24 h 0%

80%
8h
WEEKLY AMELIORATION OBJECTIVE

42%
Remarks/proposition /amelioration

Waiting for Approval from


Company

Ongoing

Waiting for Manpower

Waiting for Manpower

Done
Tasks Work Place

Preparing personal template for weekly planning


Preparing general template to display team work planning

Site visit for data collection relative to Project xxx

Tender preparation ….

WEEKLY AMEL
Goal :
Planned Period
LAY OUT FINAL PRODUCT (Result)..
Planned Duration (per hours) Planned duration (per days)

Doc ref ,,,, 60 hours 30 days


Doc ref ,,,,

Site vistit Report Ref….

Tender doc ref …

WEEKLY AMELIORATION OBJECTIVE


Weekly Progress
Remarks/proposition /amelioration
Progress Actual Duration

60%

60%
Tasks Work Place

Preparing personal template for weekly planning


Preparing general template to display team work planning

Site visit for data collection relative to Project xxx

Tender preparation ….

WEEKLY AMEL
Goal :
Planned Period
LAY OUT FINAL PRODUCT (Result)..
Planned Duration (per hours) Planned duration (per days)

Doc ref ,,,, 60 hours 30 days


Doc ref ,,,,

Site vistit Report Ref….

Tender doc ref …

WEEKLY AMELIORATION OBJECTIVE


Weekly Progress
Remarks/proposition /amelioration
Progress Actual Duration

100% 30 days

90%