1276-R0-STP_Kalyan Sagar_Mahoba June 27th; 2022

GEO TECHNICAL INVESTIGATION


REPORT

AT THE SITE FOR

PROPOSED CONSTRUCTION OF SEWERAGE TREATMENT


PLANT AT KALYAN SAGAR POND, MAHOBA.

SUBMITTED TO

OFFICE OF THE EXECUTIVE ENGINEER


UTTAR PRADESH SMALL INDUSTRICE CORPORATION
LIMITED, KANPUR, UTTAR PRADESH.

NAME OF CONTRACTOR

M/s. CONSTRO INFRATECH PVT. LTD.,


INDRA NAGAR, LUCKNOW

AJ TECHNICAL CONSULTANT
111/215, HARSH NAGAR, KANPUR-208 012
PHONES: 9807920716, 9140082024
e-mail: anshul.chitranshi@gmail.com
C O N T E N T S

1. INTRODUCTION: ........................................................................................................................................................ 1

2. SCOPE OF WORK: ...................................................................................................................................................... 1

3. PROJECT LOCATION: ................................................................................................................................................ 2

4. OBSERVATIONS AT SITE: ........................................................................................................................................ 4

5. FIELD INVESTIGATION: ........................................................................................................................................... 4

6. LABORATORY TESTS: .............................................................................................................................................. 8

7. WATER TABLE: ........................................................................................................................................................ 10

8. DETAILS OF SOIL STRATA: ................................................................................................................................... 10

9. CALCULATIONS AND RESULTS: .......................................................................................................................... 11

10 RECOMMENDATIONS: ............................................................................................................................................ 18

APPENDICES
APPENDIX A: BOREHOLES LOCATION PLAN...............................................................................................................20

APPENDIX B: TABLE 1-5: SUMMARY OF TEST RESULTS ................................................................................21-25


APPENDIX C : GRAPH 1-5: PARTICAL GRADATION CURVE .............................................................................26-30
APPENDIX D : GRAPH 1-5: SPT CORRECTION .......................................................................................................31-35
APPENDIX E : GRAPH 1-2: TRI-AXIAL COMPRESSION TEST GRAPHS............................................................36-37
APPENDIX F: SITE PHOTOGRAPHS................. ................................................................................38-38

_________________________________________________________________________________________________
AJ Technical Consultant
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
111/215 Harsh Nagar Kanpur-208012
Tel.:09807920716, 9140082024
e-mail: anshul.chitranshi@gmail.com

June 27th; 2022

ACKNOWLEDGEMENTS

The present exhaustive geotechnical exploration work for the construction for proposed

construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar

Pradesh, was an interesting task. While working on this job, the field investigations at the site,

and testing, analysis and calculation for safe bearing capacities for different type and shape of

foundation, have immediately enriched our under standings, exposure and experience of a

wide array of soil mechanics.

We are pleased to convey our sincere thanks to Mr. Rajeev Tripathi, Executive Engineer,

Uttar Pradesh Small Industrice Corporation Limited, Kanpur, Uttar Pradesh, for his their co-

operation and concerned office staff, for their help rendered during and prior to the

investigation work.

This job involved extensive investigation and analysis works, and many of our research

scholars, well qualified and experienced technical project staff and technical assistants were

involved during in-situ test for boring works, amidst extreme conditions at the site.

for AJ Technical Consultant for AJ Technical Consultant

Ramesh Kushwaha Anshul Chitranshi


B.Tech (Civil), Proprietor
M.Tech. (Structures)
Principal Consultant

_____________________________________________________________________________________________
Registered office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

1. INTRODUCTION:
This report deals with Geo-technical investigation at the site for

proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond,

Mahoba, Uttar Pradesh. The work of conducting the detailed Geotechnical Investigation has

been awarded to us wide work order No. Nill on dated Nill, scope of which includes

investigation in field, laboratory testing of bulk samples collected from the site and submission

of the test report.

Geotechnical investigation carried out, with the locations which were planned by the

client. Purpose of the investigation is to determine the nature and properties of soil strata in the

bore holes and representing them through log sections showing the levels, nature and

properties of various strata up to a sufficient depth below the level suitable for foundation,

proneness of site to artesian conditions, seismic disturbance and other engineering properties of

soil.

This report includes the detailed methodology of investigation, collection of samples,

field and laboratory test result including their interpretation/ analysis, recommendations on the

properties of soils required for design of foundation and suggesting suitable type of foundation

with safe allowable bearing capacity for safe and strong foundation.

2. SCOPE OF WORK:
For the proposed construction of structure, it is required to determine

the safe allowable bearing capacity together with necessary engineering characteristics of

underlying soil strata. Since the safe bearing capacity of soils must be evaluated on the

considerations covering shear failure and permissible settlement of sub-soil strata as per IS:

6403-1981, IS: 1904-1978 and IS: 8009 (part-I)-1976 hence the scope of work is as follows:

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 1
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

2.1 Boring five numbers of boreholes of 150 mm diameter within the proposed area of

construction maximum depth of borehole up to 4.95 meter.

2.2 Conducting the Standard Penetration Test (SPT) at every 1.50 metre interval or at

change of strata in all the boreholes.

2.3 Collecting disturbed soil samples at every 1.50 metre interval or at change of strata

from the boreholes.

2.4 Collecting undisturbed soil samples from the boreholes at 1.00 metre interval for first

two metre and then at 3.00 interval.

2.5 Transporting all the disturbed and undisturbed soil samples collected during the field

investigation to our soil mechanics laboratory in Kanpur.

2.6 Conducting the laboratory test on all the soil samples collected during field

investigation for determination of their engineering characteristics.

2.7 Compilation of field and laboratory test results, working out the safe allowable bearing

capacity and preparing the report including detailed recommendations and necessary

precautions.

3. PROJECT LOCATION:
The sites for proposed construction of of Sewerage

Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

3.1. Geology:
The district Mahoba forms a part of the Bundelkhand Massif. The area is

underlain by Granite and basic intrusive of Precambrian age. Quaternary alluvial material

overlying the Precambrian granites unconformable marks a bid hiatus in the stratigraphic

history of the area. Geological sequence of the formation present in the district as follows.

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 2
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

Geological succession of the formation

Precambrian Bundelkhand massif: This group mainly comprises granites that crop out as

isolated or clustered hillocks. Granites occurring in the district reflect considerable

heterogeneity in color texture grain size and composition. Most common granite in the district

is medium grain pink color composed of quartz, feldspar with mafic minerals biotite and

hornblende. Occasionally Corse grain feldspar quartz veins are also encountered in granite.

The granite are profusely and extensively jointed and fractured. The quartz reef trending NE-

SW occurs as narrow ridge. These reefs are composed of fine grained compact silicon material

and are milky white in color. The Bundelkhand Granite is traversed by basic intrusive mainly

dolerite of pre and post Cambrian age. They trend EW to NW-SE direction. The granites are

uncomfortably overlain by Quaternary alluvium consisting of Gravel, Sand and Clay. The

thickness of overburden varies from 5 to 40.0 m

3.2. Rainfall & Climate:


The average annual rainfall is 864 mm. The climate is typical

subtropical punctuated by long and intense summer. About 87% of the annual rainfall is

received from south-west monsoon. May is the hottest month with temperature shooting upto

47.5°C. With the advance of monsoon by about mid June, tempeature starts decreasing.

January is usually the coldest month with the temperature going upto 8.3°C.

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 3
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

The relative humidity is highest during south-west monsoon

ranging between 80% to 85% with its lowest around 30% during peak summer months of April

and May.

3.3. Seismicity:
Mahoba district falls under moderate seismic hazard region i.e. Zone-II

as per latest Seismic Hazard Zonation Map of India provided by Bureau of Indian

Standards IS: 1893 (part-I), 2016.

4. OBSERVATIONS AT SITE:

The following observations have been made at the site:-


4.1 No effects of saltpetre have been observed however a mild effect of termite has been

observed at the site.

5. FIELD INVESTIGATION:
The field investigation work at this site was carried out from

June 09th, 2022 to June 09th, 2022. The following investigation work was carried out:

5.1. Five numbers of boreholes of diameter 150 mm were made within the proposed

layout. The boreholes progress using manual winch machine Casing was used to keep

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 4
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

the borehole stable. All the Bore holes (marked as BH-1, BH-2, BH-3, BH-4 & BH-5)

were made up to the depth of 4.95 metre within the layout for the proposed structure.

The locations of boreholes have been reported in “BOREHOLES LOCATION PLAN”

in Appendix A.

5.2. Standard Penetration Tests were conducted at 1.50 metre as per the procedure in IS

2131-1981 in all the bore holes. For conducting the test, the bottom of the borehole

was properly cleaned and split spoon sampler was properly seated in position in the

borehole. The split spoon sampler resting on the bottom of borehole was allowed to

sink under its own weight; then the sampler was allowed to penetrate 15 cm with the

blows of the hammer 63.50 kg weight falling free through 75cm, thereafter the split

spoon sampler was further driven by another 15 cm. For the 3rd and final drive, the

sampler was further allowed to penetrate 15 cm. The number of blows required to

affect each 15 cm of penetration was recorded. The first 15 cm of drive is considered

to be seating drive.

Structure of SPT Sampler

The total blows of penetration for the second and third 15 cm of penetration is termed

the penetration resistance N. The N’ values are indicative of the compactness/ relative

density of cohesion less soils and consistency of cohesive soils.

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 5
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

In case the blows count of SPT in soil (including the number of blows of seating)

exceeds 100, the corresponding penetration was recorded and this particular test at that

depth stopped. If the total penetration is more than the seating penetration of 15 cm,

then breakup of blows count for 15 cm seating penetration and for remaining portion

of penetration is also given.

SPT ‘N’ values are correlated with relative of non-cohesive stratum as per BS: 5930

(1999) - for sandy strata and with consistency of cohesive stratum.

CORRELATION FOR CORRELATION FOR SAND/NON-


CLAY/PLASTIC SILT PLASTIC SILT
Consistency of Penetration Value Relative Density Penetration Value
clays of sand
Very Soft 0 to 2 Blows Very loose 0 to 4 Blows
Soft 3 to 4 Blows Loose 5 to 10 Blows
Medium Stiff 5 to 8 Blows Medium 11 to 30 Blows
Stiff 9 to 16 Blows Dense 31 to 50 Blows
Very Stiff 17 to 32 Blows Very Dense Above 50
Hard Above 32
In this method, the sampler acts as a probe and the driving energy is supplied by the

fall of the drop weight. The values of ‘N’ depend on the compactness or relative

density of the materiel. In hard formations, the testing is discontinued if ‘N’ value is

found to be more than 100. It is termed as refusal.

‘N’ value depends upon degree of saturation and over burden pressure of the

formation. Silty fine sand and fine sand below the water table develop pore water

pressure depending on the in-situ void ratio which in turn affects the effective stress.

This change in effective stress influences the ‘N’ value considerably. Terzaghi and

peck have recommended a correction for ‘N’ values in case of saturated silty and fine

sand when the ‘N’ observed in the field is higher than 15.

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 6
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

Modified value ‘N’= 15+ (N-15)/2.

Soil sample obtained from standard spoon sampler for all above standard penetration

tests were collected in the polythene bags of suitable size. These samples were

property seal, labelled, record and carefully transported to the laboratory for testing.

The results have been reported in Table 1 to 5 of Appendix B under the title

“SUMMARY OF TEST RESULTS”

5.3. Disturbed soil samples were tried to be collected at every 1.50 metre interval and at

significant change of stratum. Soil from cutting edge of SPT samplers and retained in

split spoon sampler, used for Standard Penetration Tests was taken as disturbed

samples. These samples were placed without delay in adequately sealed polythene

bags. Where the collection of disturbed soil samples could not be collected from SPT

samples, Shelby tubes were driven and retained soil samples were obtained. The

laboratory tests were conducted on the collected soil samples and reported in Table 1

to 5 of Appendix B under the title “SUMMARY OF TEST RESULTS”.

5.4. Undisturbed soil samples were tried to be collected in accordance with IS: 2132-

1986. Undisturbed soil samples (UDS) was obtained at every 3.00 metre interval.

Undisturbed samples were collected using 100 mm dia and 450 mm

long MS tubes provided with sampler head with ball check arrangement. Collection of

Undisturbed samples in very hard cohesive soils/ dense granular soils/gravels/ cobbles/

pebbles/ boulders, refusal strata is practically not possible and such collected samples

will not truly represent the undisturbed conditions.

Immediately after taking and undisturbed sample in a tube, the adopter

head was removed along with the disturbed material. The visible ends of the samples

shall each be trimmed off any wet disturbed soil. The ends will then be coated

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 7
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

alternately with four layers of just molten wax. More molten wax will then be added to

give a total thickness of not less than 25mm. The laboratory test results have been

reported in Table 1 to 5 of Appendix B under the title “SUMMARY OF TEST

RESULTS”.

5.5. The depth at which ground water is struck during boring was carefully noted and the

depth of water table was ascertained subsequently in the completed borehole by the

following method.

The water table in the borehole was allowed to stabilize after 9, 24, 33 and 45 hours. It

was ensured that last two reading are identical.

6. LABORATORY TESTS:
The following laboratory tests were conducted to determine the

engineering characteristics of sub-soils:

6.1. Natural moisture contents were determined by oven drying method as per IS 2720

(part II)-1973. The results have been reported in table 1 to table 5 “SUMMARY OF

TEST RESULTS” of Appendix B.

6.2. Bulk & Dry density of soil strata were obtained using Shelby tubes in accordance

with IS 2720 (part XXIX)-1975. The results have been reported in table 1 to table 5:

“SUMMARY OF TEST RESULTS” of Appendix B.

6.3. Mechanical sieve analysis test were performed in accordance with IS 2720 (Part

IV) - 1985, for the purpose of identification by grain size analysis, on coarse part of

the soil samples and the results have been reported in table 1 to table 5

“SUMMARY OF TEST RESULTS” of appendix B.

6.4. Particle size analysis test by hydrometer method were performed in accordance

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 8
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

with IS 2720 (Part IV) - 1965 on the part of soil samples obtained after the sieve

analysis. The results have been reported in table 1 to table 5 “SUMMARY OF TEST

RESULTS” of appendix B.

6.5. Atterbergs’ limits tests were performed in accordance with IS 2720 (part V)-1985

and results have been reported in table 1 to table 5 “SUMMARY OF TEST

RESULTS” of Appendix B.

6.6. Specific gravity tests were performed in accordance with IS 2720 (part III-sec. 1) -

1980 and the results have been reported in table 1 to table 5 “SUMMARY OF TEST

RESULTS” of Appendix B.

6.7. Consolidation tests were performed on cohesive soil samples in accordance with IS:

2720 (part XV)-2011. The results have been reported Table 1 to 5 “SUMMARY OF

TEST RESULTS” of Appendix B.

6.8. Tri-axial Compression Test under Unconsolidated Un-drained (UU) conditions as

per IS: 2720 (Part-XI)-2011 were performed on the undisturbed soil samples

obtained during the field investigation. The results have been reported in table 1 to 5

“SUMMARY OF TEST RESULTS” of Appendix B.

6.9. Shrinkage Limit tests were performed in accordance with IS 2720 (part-VI) -1972

and the results have been reported in table 1 to 5 “SUMMARY OF TEST

RESULTS” of Appendix B.

6.10. Free Swell Index were performed in accordance with IS 2720 (part-XL) -1977 and

the results have been reported in table 1 to 5 “SUMMARY OF TEST RESULTS” of

Appendix B.

6.11. Direct shear tests were performed as per IS 2720 (part XI)-1971, on the undisturbed

soil samples obtained during the field investigation. The results and the density of

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 9
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

samples have been reported in table 1 to table 5 “SUMMARY OF TEST RESULTS”

of Appendix B.

7. GROUND WATER TABLE:


The ground water table at this site was not encountered during the boring

operation..

Date of
GPS Co-ordinate Ground
InvestigationSPT Hammer Depth of
Borehole Water
Sampler Drop Borehole
No. Table
Starting Ending Type method (m)
Latitude Longitude (m)
Date Date

BH-1 25.281956° 79.888192° 9-7-2022 9-7-2022 Standard Wire rope 4.95

Not Encountered
BH-2 25.281972° 79.888005° 9-7-2022 9-7-2022 Standard Wire rope 4.95

BH-3 25.282102° 79.888142° 9-7-2022 9-7-2022 Standard Wire rope 4.95

BH-4 25.282232° 79.887924° 9-7-2022 9-7-2022 Standard Wire rope 4.95

BH-5 25.281837° 79.888357° 9-7-2022 9-7-2022 Standard Wire rope 4.95

8. DETAILS OF SOIL STRATA:


The classification of soil strata have been done with the

help of soil characteristics obtained in laboratory tests as per IS 1498-1978. The detailed nature

of the soil strata have been reported in table 1 to table-5: “SUMMARY OF TEST RESULTS”

of Appendix B.

In general the soils found at this site consist of non-expansive

inorganic silts and clays of low to intermediate plasticity till the depth of investigation. Soils

found are non-expansive in nature and contains no harmful salts

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 10
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at


Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

9. CALCULATIONS AND RESULTS:

The safe allowable bearing capacity of the foundation

for the proposed building structure has been calculated on the shear failure criteria suggested as

per IS 6403-1981, IS: 1904-1978 and Settlement Criteria as per IS: 8009 (part-I)-1976.

Looking at the site condition, sub soil stratification and type of proposed structure, calculations

have been done for Isolated & strip footing.

9.1 SHEAR FAILURE CRITERIA:

Based on C- values:


Mixed (Interpolation in between
Type of shear failure =
General and Local shear failure)

Factor of safety (F.S.) = )


2.50
Depth of critical water table = 0.00 meter
Net allowable bearing capacity: = qna (kN/m2)
qna = (1 / F.S.) [0.667c Nc Sc dc + q (Nq - 1) Sq dq + 0.5 B  N S dW’]

Where,
B = Width of foundation (metre)

D = Depth of foundation (metre)

 = Angle of shearing resistance (degree)

c = Cohesion intercept (kN/m2)

 = Bulk density of soil above the base of footing (kN/m3)

q = d = Effective overburden (kN/m2)

Nc, Nq, N = Bearing capacity coefficient based on initial void ratio e0

dc, dq, d = depth factors

W’ = Water table correction factor

___________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 11
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

9.1.1 Isolated footing for building structure:


Shape Factors:
Sc = 1.30
Sq = 1.20
S  = 0.80
Substituting the values, the value of qna can be calculated as per table below:

Bore
Hole B D  c eo  q Nc Nq N dc dq d W’ qna
No.
BH-1 1.50 1.00 9.2 45.0 0.749 19.090 9.09 6.93 1.78 0.63 1.12 1.06 1.06 0.50 104.99

BH-1 1.50 1.50 9.2 45.0 0.749 19.090 13.64 6.93 1.78 0.63 1.18 1.09 1.09 0.50 111.97

BH-2 1.50 1.00 9.8 52.0 0.722 18.490 8.49 7.24 1.93 0.76 1.12 1.06 1.06 0.50 126.41

BH-2 1.50 1.50 9.8 52.0 0.722 18.490 12.74 7.24 1.93 0.76 1.18 1.09 1.09 0.50 134.66

BH-3 1.50 1.00 8.5 72.0 0.725 17.980 7.98 6.88 1.76 0.61 1.12 1.06 1.06 0.50 163.68

BH-3 1.50 1.50 8.5 72.0 0.725 17.980 11.97 6.88 1.76 0.61 1.18 1.09 1.09 0.50 173.55

BH-4 1.50 1.00 9.7 56.0 0.717 17.910 7.91 7.24 1.94 0.76 1.12 1.06 1.06 0.50 135.55

_______________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 12
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

Bore
Hole B D  c eo  q Nc Nq N dc dq d W’ qna
No.
BH-4 1.50 1.50 9.7 56.0 0.717 17.910 11.87 7.24 1.94 0.76 1.18 1.09 1.09 0.50 144.16

BH-5 1.50 1.00 8.3 52.0 0.734 18.570 8.57 6.78 1.71 0.57 1.12 1.06 1.06 0.50 117.57

BH-5 1.50 1.50 8.3 52.0 0.734 18.570 12.86 6.78 1.71 0.57 1.18 1.09 1.09 0.50 125.03

9.1.2 Strip footing for Underground Tank Structure:


Shape Factors:
Sc = 1.00
Sq = 1.00
S  = 1.00
Substituting the values, the value of qna can be calculated as per table below:

Bore
Hole B D  c eo  q Nc Nq N dc dq d W’ qna
No.
BH-1 1.00 2.50 8.5 50.0 0.730 18.760 21.90 6.85 1.74 0.60 1.44 1.22 1.22 0.50 117.66

BH-1 1.00 3.50 8.5 50.0 0.730 18.760 30.66 6.85 1.74 0.60 1.62 1.31 1.31 0.50 134.57

_______________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 13
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

Bore
Hole B D  c eo  q Nc Nq N dc dq d W’ qna
No.
BH-1 1.00 4.50 8.5 50.0 0.730 18.760 39.42 6.85 1.74 0.60 1.80 1.40 1.40 0.50 151.86

BH-2 1.00 2.50 14.5 57.0 0.697 18.910 22.28 8.92 2.79 1.54 1.43 1.21 1.21 0.50 180.33

BH-2 1.00 3.50 14.5 57.0 0.697 18.910 31.19 8.92 2.79 1.54 1.60 1.30 1.30 0.50 207.89

BH-2 1.00 4.50 14.5 57.0 0.697 18.910 40.10 8.92 2.79 1.54 1.77 1.38 1.38 0.50 236.37

BH-3 1.00 2.50 13.0 60.0 0.681 18.880 22.20 8.59 2.63 1.39 1.43 1.21 1.21 0.50 181.05

BH-3 1.00 3.50 13.0 60.0 0.681 18.880 31.08 8.59 2.63 1.39 1.60 1.30 1.30 0.50 208.23

BH-3 1.00 4.50 13.0 60.0 0.681 18.880 39.96 8.59 2.63 1.39 1.77 1.39 1.39 0.50 236.24

BH-4 1.00 2.50 8.0 70.0 0.676 18.610 21.53 6.99 1.81 0.66 1.44 1.22 1.22 0.50 165.06

BH-4 1.00 3.50 8.0 70.0 0.676 18.610 30.14 6.99 1.81 0.66 1.62 1.31 1.31 0.50 187.92

BH-4 1.00 4.50 8.0 70.0 0.676 18.610 38.75 6.99 1.81 0.66 1.80 1.40 1.40 0.50 211.20

BH-5 1.00 2.50 9.5 75.0 0.689 19.570 23.93 7.35 1.99 0.81 1.44 1.22 1.22 0.50 187.63

BH-5 1.00 3.50 9.5 75.0 0.689 19.570 33.50 7.35 1.99 0.81 1.62 1.31 1.31 0.50 214.09

_______________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 14
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

Bore
Hole B D  c eo  q Nc Nq N dc dq d W’ qna
No.
BH-5 1.00 4.50 9.5 75.0 0.689 19.570 43.07 7.35 1.99 0.81 1.79 1.40 1.40 0.50 241.12

_______________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 15
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

9.2 SETTLEMENT CRITERIA:

Soil strata at this site mainly consists of silty clays, hence the

settlement of the soil layers below the base of footing has been calculated on the basis of SPT

values obtained during the field Investigation.

Settlement for applied pressure (Sf) = (qs x Su x Df)/ (W’x100)

Where,

qs = Permissible pressure (kN/m2)

Su = Settlement for unit pressure of 1.00 kg/cm2

W’ =Water table correction factor


N = Corrected average SPT value
B = Base width
D = Depth of footing
Df = depth factor
Rf = Rigidity factor (1.00 & 0.80 for Isolated & Strip footing)
The settlement of isolated & strip footing at different depth and base width can be calculated as

per the following table:

9.2.1 Isolated footing for building structure:

Bore
B D N Su W' qs Rf Df Sf
No.
BH-1 1.50 1.00 19.35 11.0 0.50 104.99 1.00 0.81 19

BH-1 1.50 1.50 19.35 11.0 0.50 111.97 1.00 0.74 18

BH-2 1.50 1.00 18.50 11.0 0.50 126.41 1.00 0.81 22

BH-2 1.50 1.50 18.50 11.0 0.50 134.66 1.00 0.74 22

BH-3 1.50 1.00 15.36 18.0 0.50 163.68 1.00 0.81 48

BH-3 1.50 1.50 15.36 18.0 0.50 173.55 1.00 0.74 46

BH-4 1.50 1.00 20.91 13.0 0.50 135.55 1.00 0.81 28

__________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 16
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

Bore
B D N Su W' qs Rf Df Sf
No.
BH-4 1.50 1.50 20.91 13.0 0.50 144.16 1.00 0.74 28

BH-5 1.50 1.00 19.51 13.0 0.50 117.57 1.00 0.81 23

BH-5 1.50 1.50 19.51 13.0 0.50 125.03 1.00 0.74 24

The calculated values of the settlement are within the permissible limits of 50 mm

9.2.2 Strip footing for Underground Tank structure:

Bore
B D N Su W' qs Rf Df Sf
No.
BH-1 1.00 2.50 17.52 12.0 0.50 117.66 0.80 0.70 16

BH-1 1.00 3.50 17.52 12.0 0.50 134.57 0.80 0.66 17

BH-1 1.00 4.50 17.52 12.0 0.50 151.86 0.80 0.64 19

BH-2 1.00 2.50 17.29 12.0 0.50 180.33 0.80 0.70 24

BH-2 1.00 3.50 17.29 12.0 0.50 207.89 0.80 0.66 27

BH-2 1.00 4.50 17.29 12.0 0.50 236.37 0.80 0.64 29

BH-3 1.00 2.50 13.43 17.0 0.50 181.05 0.80 0.70 35

BH-3 1.00 3.50 13.43 17.0 0.50 208.23 0.80 0.66 38

BH-3 1.00 4.50 13.43 17.0 0.50 236.24 0.80 0.64 41

BH-4 1.00 2.50 19.88 9.0 0.50 165.06 0.80 0.70 17

BH-4 1.00 3.50 19.88 9.0 0.50 187.92 0.80 0.66 18

BH-4 1.00 4.50 19.88 9.0 0.50 211.20 0.80 0.64 20

BH-5 1.00 2.50 19.48 9.0 0.50 187.63 0.80 0.70 19

BH-5 1.00 3.50 19.48 9.0 0.50 214.09 0.80 0.66 20

BH-5 1.00 4.50 19.48 9.0 0.50 241.12 0.80 0.64 22

The calculated values of the settlement are within the permissible limits of 60 mm.

__________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 17
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

10 RECOMMENDATIONS:

Keeping in mind, the field test results, laboratory test results and IS codes of practice the following

recommendations are hereby made:

10.1 Under Ground Tank Structure:

Strip footing shall be provided for the walls of proposed

underground tank structure. The depth and corresponding safe allowable bearing capacity shall

be appropriately taken from the table below:

Depth of foundation Safe bearing capacity


(metre) (kN/m2)
2.50 115.00
3.50 135.00
4.50 150.00

10.2 Building Structure:

Isolated footing shall be provided for the column of proposed building

structure. The depth and corresponding safe allowable bearing capacity shall be appropriately

taken from the table below

Depth of foundation Safe bearing capacity


(metre) (kN/m2)
1.00 105.00
1.50 110.00

10.3 All depth referred in recommendation of safe bearing capacity have been measured from existing

level of ground.

__________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 18
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

10.4 Since all the locations incorporated in this report does not consist of harmful chemicals, Ordinary

Portland Cement may be used for all civil constructions.

10.5 If any loose pocket strata are found during the excavation, the foundation shall be laid only after

ensuring that the same has been cleared and appropriate remedial measures have been adopted

for AJ Technical Consultant for AJ Technical Consultant

Ramesh Kushwaha Anshul Chitranshi


B.Tech (Civil), Proprietor
M.Tech. (Structures)
Principal Consultant

__________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 19
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX – A
BORE HOLES LOCATION PLAN

__________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 20
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX ‘B’
TABLE 01 : SUMMARY OF TEST RESULTS
Bore No.: 01 Diameter of Bore hole: 150 mm Casing Lowered: 3.00 m Method of drilling: Percussion Starting Date: 09-07-2022
Ground Elevation: -NA Water Table: Not Encountered Ending Date: 09-07-2022
Description/
FIELD TEST RESULT LABORATORY TEST RESULT
Classification
Shear Strength Consolidation Shrinkage/
SPT Test Result
Grain Size Analysis Index Property Parameters Characteristic Swelling
Depth Below NGL

Description of soil

PRECONSOLIDATI
Soil Classification
Nature of Sample

Coarse Sand (%)

Moisture Content

Plastic Index (%)

Free Swell Index


Angle of Friction
Plastic Limit (%)

Specific Gravity
Liquid Limit (%)
N2 (First Drive)

Shrinkage Limit
Observed SPT

Swell Pressure
Fine Sand (%)
Medium Sand

ON PRESSURE
N' (Correct N)

Type of Test
Bulk Density
N1 (Seating

N3 (Second

Cohesion C
RL in Meter

Dry Density

(Degree) Φ

Void Ratio,
N (N2+N3)

Gravel (%)

(Kg/cm2)
Clay (%)
Mapping

(gm/cc)

(gm/cc)
(Meter)

Silt (%)

kN/m2
Drive)

Drive)

(%)

(%)

Gs

Cc
1.00 U - - - - - CI 8 3 4 6 64 15 24.60 1.909 1.532 35 22 13 2.68 UU 45 9.2 - 0.749 - - - -

1.50 D 4 4 9 13 18.46 - - - - - - - 15.10 - - - - - - - - - - - - - - -


Inorganic clays of
2.50 U - - - - - intermediate CI 4 1 1 23 53 18 21.10 1.876 1.549 37 22 16 2.68 UU 50 8.5 0.19 0.730 - - - -
plasticity
3.00 D 7 8 9 17 20.25 - - - - - - - 23.10 - - - - - - - - - - - - - - -

4.50 D 9 6 8 14 14.79 - - - - - - - 14.50 - - - - - - - - - - - - - - -

Notations: UU= Unconsolidated Undrained Tri-axial compression Test on Undisturbed Sample, RUU= Unconsolidated Undrained Tri-axial compression Test on Remoulded disturbed Samples, DST=Direct Shear Test on
Undisturbed samples, RDST=Direct Shear Test on remoulded samples, R=Refusal strata (SPT Value>=100)

________________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 21
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX ‘B’
TABLE 02 : SUMMARY OF TEST RESULTS
Bore No.: 02 Diameter of Bore hole: 150 mm Casing Lowered: 3.00 m Method of drilling: Percussion Starting Date: 09-07-2022
Ground Elevation: -NA Water Table: Not Encountered Ending Date: 09-07-2022
Description/
FIELD TEST RESULT LABORATORY TEST RESULT
Classification
Shear Strength Consolidation Shrinkage/
SPT Test Result
Grain Size Analysis Index Property Parameters Characteristic Swelling
Depth Below NGL

Description of soil

PRECONSOLIDATI
Soil Classification
Nature of Sample

Coarse Sand (%)

Moisture Content

Plastic Index (%)

Free Swell Index


Angle of Friction
Plastic Limit (%)

Specific Gravity
Liquid Limit (%)
N2 (First Drive)

Shrinkage Limit
Observed SPT

Swell Pressure
Fine Sand (%)
Medium Sand

ON PRESSURE
N' (Correct N)

Type of Test
Bulk Density
N1 (Seating

N3 (Second

Cohesion C
RL in Meter

Dry Density

(Degree) Φ

Void Ratio,
N (N2+N3)

Gravel (%)

(Kg/cm2)
Clay (%)
Mapping

(gm/cc)

(gm/cc)
(Meter)

Silt (%)

kN/m2
Drive)

Drive)

(%)

(%)

Gs

Cc
1.00 U - - - - - CI 0 1 2 4 73 20 18.80 1.849 1.556 33 18 16 2.68 UU 52 9.8 - 0.722 - - - -

1.50 D 5 8 7 15 21.46 - - - - - - - 21.80 - - - - - - - - - - - - - - -


Inorganic clays of
2.50 U - - - - - intermediate CI 8 9 11 13 41 18 19.75 1.891 1.579 37 19 18 2.68 UU 57 14.5 0.18 0.697 - - - -
plasticity
3.00 D 4 5 8 13 15.54 - - - - - - - 16.20 - - - - - - - - - - - - - - -

4.50 D 7 9 9 18 19.05 - - - - - - - 23.40 - - - - - - - - - - - - - - -

Notations: UU= Unconsolidated Undrained Tri-axial compression Test on Undisturbed Sample, RUU= Unconsolidated Undrained Tri-axial compression Test on Remoulded disturbed Samples, DST=Direct Shear Test on
Undisturbed samples, RDST=Direct Shear Test on remoulded samples, R=Refusal strata (SPT Value>=100)

________________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 22
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX ‘B’
TABLE 03 : SUMMARY OF TEST RESULTS
Bore No.: 03 Diameter of Bore hole: 150 mm Casing Lowered: 3.00 m Method of drilling: Percussion Starting Date: 09-07-2022
Ground Elevation: -NA Water Table: Not Encountered Ending Date: 09-07-2022
Description/
FIELD TEST RESULT LABORATORY TEST RESULT
Classification
Shear Strength Consolidation Shrinkage/
SPT Test Result
Grain Size Analysis Index Property Parameters Characteristic Swelling
Depth Below NGL

Description of soil

PRECONSOLIDATI
Soil Classification
Nature of Sample

Coarse Sand (%)

Moisture Content

Plastic Index (%)

Free Swell Index


Angle of Friction
Plastic Limit (%)

Specific Gravity
Liquid Limit (%)
N2 (First Drive)

Shrinkage Limit
Observed SPT

Swell Pressure
Fine Sand (%)
Medium Sand

ON PRESSURE
N' (Correct N)

Type of Test
Bulk Density
N1 (Seating

N3 (Second

Cohesion C
RL in Meter

Dry Density

(Degree) Φ

Void Ratio,
N (N2+N3)

Gravel (%)

(Kg/cm2)
Clay (%)
Mapping

(gm/cc)

(gm/cc)
(Meter)

Silt (%)

kN/m2
Drive)

Drive)

(%)

(%)

Gs

Cc
1.00 U - - - - - Inorganic clays of CL 12 1 1 9 64 13 16.60 1.798 1.542 30 21 9 2.66 UU 72 8.5 0.14 0.725 - - - -

1.50 D 7 5 8 13 18.72 low plasticity - - - - - - - 18.20 - - - - - - - - - - - - - - -

2.50 U - - - - - CI 5 0 0 3 70 22 18.90 1.888 1.588 36 23 13 2.67 UU 60 13 0.15 0.681 - - - -


Inorganic clays of
3.00 D 4 5 5 10 12.00 intermediate - - - - - - - 17.70 - - - - - - - - - - - - - - -
plasticity
4.50 D 5 6 8 14 14.86 - - - - - - - 19.60 - - - - - - - - - - - - - - -

Notations: UU= Unconsolidated Undrained Tri-axial compression Test on Undisturbed Sample, RUU= Unconsolidated Undrained Tri-axial compression Test on Remoulded disturbed Samples, DST=Direct Shear Test on
Undisturbed samples, RDST=Direct Shear Test on remoulded samples, R=Refusal strata (SPT Value>=100)

________________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 23
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX ‘B’
TABLE 04 : SUMMARY OF TEST RESULTS
Bore No.: 04 Diameter of Bore hole: 150 mm Casing Lowered: 3.00 m Method of drilling: Percussion Starting Date: 09-07-2022
Ground Elevation: -NA Water Table: Not Encountered Ending Date: 09-07-2022
Description/
FIELD TEST RESULT LABORATORY TEST RESULT
Classification
Shear Strength Consolidation Shrinkage/
SPT Test Result
Grain Size Analysis Index Property Parameters Characteristic Swelling
Depth Below NGL

Description of soil

PRECONSOLIDATI
Soil Classification
Nature of Sample

Coarse Sand (%)

Moisture Content

Plastic Index (%)

Free Swell Index


Angle of Friction
Plastic Limit (%)

Specific Gravity
Liquid Limit (%)
N2 (First Drive)

Shrinkage Limit
Observed SPT

Swell Pressure
Fine Sand (%)
Medium Sand

ON PRESSURE
N' (Correct N)

Type of Test
Bulk Density
N1 (Seating

N3 (Second

Cohesion C
RL in Meter

Dry Density

(Degree) Φ

Void Ratio,
N (N2+N3)

Gravel (%)

(Kg/cm2)
Clay (%)
Mapping

(gm/cc)

(gm/cc)
(Meter)

Silt (%)

kN/m2
Drive)

Drive)

(%)

(%)

Gs

Cc
1.00 U - - - - - Inorganic clays of CL 6 0 0 10 70 14 15.20 1.791 1.555 33 19 14 2.67 UU 56 9.7 0.13 0.717 - - - -

1.50 D 8 5 9 14 20.18 low plasticity - - - - - - - 17.50 - - - - - - - - - - - - - - -

2.50 U - - - - - CI 3 0 0 7 70 20 16.40 1.861 1.599 38 21 17 2.68 UU 70 8 0.16 0.676 - - - -


Inorganic clays of
3.00 D 9 8 10 18 21.65 intermediate - - - - - - - 17.60 - - - - - - - - - - - - - - -
plasticity
4.50 D 8 5 12 17 18.11 - - - - - - - 18.80 - - - - - - - - - - - - - - -

Notations: UU= Unconsolidated Undrained Tri-axial compression Test on Undisturbed Sample, RUU= Unconsolidated Undrained Tri-axial compression Test on Remoulded disturbed Samples, DST=Direct Shear Test on
Undisturbed samples, RDST=Direct Shear Test on remoulded samples, R=Refusal strata (SPT Value>=100)

________________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 24
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX ‘B’
TABLE 05 : SUMMARY OF TEST RESULTS
Bore No.: 05 Diameter of Bore hole: 150 mm Casing Lowered: 3.00 m Method of drilling: Percussion Starting Date: 09-07-2022
Ground Elevation: -NA Water Table: Not Encountered Ending Date: 09-07-2022
Description/
FIELD TEST RESULT LABORATORY TEST RESULT
Classification
Shear Strength Consolidation Shrinkage/
SPT Test Result
Grain Size Analysis Index Property Parameters Characteristic Swelling
Depth Below NGL

Description of soil

PRECONSOLIDATI
Soil Classification
Nature of Sample

Coarse Sand (%)

Moisture Content

Plastic Index (%)

Free Swell Index


Angle of Friction
Plastic Limit (%)

Specific Gravity
Liquid Limit (%)
N2 (First Drive)

Shrinkage Limit
Observed SPT

Swell Pressure
Fine Sand (%)
Medium Sand

ON PRESSURE
N' (Correct N)

Type of Test
Bulk Density
N1 (Seating

N3 (Second

Cohesion C
RL in Meter

Dry Density

(Degree) Φ

Void Ratio,
N (N2+N3)

Gravel (%)

(Kg/cm2)
Clay (%)
Mapping

(gm/cc)

(gm/cc)
(Meter)

Silt (%)

kN/m2
Drive)

Drive)

(%)

(%)

Gs

Cc
1.00 U - - - - - Inorganic clays of CL 0 0 0 5 79 16 20.60 1.857 1.540 34 22 12 2.67 UU 52 8.3 0.14 0.734 - - - -

1.50 D 5 8 6 14 20.01 low plasticity - - - - - - - 22.70 - - - - - - - - - - - - - - -

2.50 U - - - - - CI 7 1 1 4 64 23 23.30 1.957 1.587 40 24 16 2.68 UU 75 9.5 0.17 0.689 - - - -


Inorganic clays of
3.00 D 6 9 7 16 19.02 intermediate - - - - - - - 24.60 - - - - - - - - - - - - - - -
plasticity
4.50 D 10 8 11 19 19.95 - - - - - - - 22.90 - - - - - - - - - - - - - - -
Notations: UU= Unconsolidated Undrained Tri-axial compression Test on Undisturbed Sample, RUU= Unconsolidated Undrained Tri-axial compression Test on Remoulded disturbed Samples, DST=Direct Shear Test on
Undisturbed samples, RDST=Direct Shear Test on remoulded samples, R=Refusal strata (SPT Value>=100)

________________________________________________________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 25
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-C
GRAPH-1: PARTICLE GRADATION CURVE (BH-1)
Clay Silt Fine Sand Med. Sand C.Sand Gravel

100.0

90.0 1.00 Metre

80.0
2.50 Metre
70.0
Percentage Finer

60.0

50.0

40.0

30.0

20.0

10.0

0.0
0.001 0.010 0.100 1.000 10.000

Particle size (mm)

Gravel : Particle Size >4.75 mm Fine Sand: 0.075mm< Particle Size ≤0.425 mm
Coarse Sand : 2.00mm< Particle Size ≤4.75 mm Silt : 0.002mm< Particle Size ≤0.075 mm
Medium Sand : 0.425mm< Particle Size ≤2.00 mm Clay : <0.002 mm

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 26
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-C
GRAPH-2: PARTICLE GRADATION CURVE (BH-2)
Clay Silt Fine Sand Med. Sand C.Sand Gravel

100.0

90.0 1.00 Metre

80.0
2.50 Metre
70.0
Percentage Finer

60.0

50.0

40.0

30.0

20.0

10.0

0.0
0.001 0.010 0.100 1.000 10.000

Particle size (mm)

Gravel : Particle Size >4.75 mm Fine Sand: 0.075mm< Particle Size ≤ 0 . 4 2


Coarse Sand : 2.00mm< Particle Size ≤4.75 mm Silt : 0.002mm< Particle Size ≤0.075 mm
Medium Sand : 0.425mm< Particle Size ≤2.00 mm Clay : <0.002 mm

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 27
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-C
GRAPH-3: PARTICLE GRADATION CURVE (BH-3)
Clay Silt Fine Sand Med. Sand C.Sand Gravel

100.0

90.0 1.00 Metre

80.0
2.50 Metre
70.0
Percentage Finer

60.0

50.0

40.0

30.0

20.0

10.0

0.0
0.001 0.010 0.100 1.000 10.000

Particle size (mm)

Gravel : Particle Size >4.75 mm Fine Sand: 0.075mm< Particle Size ≤ 0 . 4 2


Coarse Sand : 2.00mm< Particle Size ≤4.75 mm Silt : 0.002mm< Particle Size ≤0.075 mm
Medium Sand : 0.425mm< Particle Size ≤2.00 mm Clay : <0.002 mm

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 28
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-C
GRAPH-4: PARTICLE GRADATION CURVE (BH-4)
Clay Silt Fine Sand Med. Sand C.Sand Gravel

100.0

90.0 1.00 Metre

80.0
2.50 Metre
70.0
Percentage Finer

60.0

50.0

40.0

30.0

20.0

10.0

0.0
0.001 0.010 0.100 1.000 10.000

Particle size (mm)

Gravel : Particle Size >4.75 mm Fine Sand: 0.075mm< Particle Size ≤ 0 . 4 2


Coarse Sand : 2.00mm< Particle Size ≤4.75 mm Silt : 0.002mm< Particle Size ≤0.075 mm
Medium Sand : 0.425mm< Particle Size ≤2.00 mm Clay : <0.002 mm

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 29
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-C
GRAPH-5: PARTICLE GRADATION CURVE (BH-5)
Clay Silt Fine Sand Med. Sand C.Sand Gravel

100.0

90.0 1.00 Metre

80.0
2.50 Metre
70.0
Percentage Finer

60.0

50.0

40.0

30.0

20.0

10.0

0.0
0.001 0.010 0.100 1.000 10.000

Particle size (mm)

Gravel : Particle Size >4.75 mm Fine Sand: 0.075mm< Particle Size ≤ 0 . 4 2


Coarse Sand : 2.00mm< Particle Size ≤4.75 mm Silt : 0.002mm< Particle Size ≤0.075 mm
Medium Sand : 0.425mm< Particle Size ≤2.00 mm Clay : <0.002 mm

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 30
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-D
GRAPH-1: SPT CORRECTION & PLOT FOR BORE No. 01
Bore Hole No. 01 Depth of water table: Not Encountered
Depth Bulk Overburden SPT
SPT Correction SPT
of density Pressure after
Recorded 3 2 Factor Corrected
sample (t/m ) (t/m ) dilatancy
1.50 13 1.909 2.863 13.00 1.42 18.46
3.00 17 1.876 5.677 17.00 1.19 20.25
4.50 14 1.876 8.491 14.00 1.06 14.79

SPT N Value
0 5 10 15 20 25
0.00
Depth (metre)

SPT Recorded
SPT Corrected
5.00

10.00

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 31
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-D
GRAPH-2: SPT CORRECTION & PLOT FOR BORE No. 02
Bore Hole No. 02 Depth of water table: Not Encountered
Depth Bulk Overburden SPT
SPT Correction SPT
of density Pressure after
Recorded 3 2 Factor Corrected
sample (t/m ) (t/m ) dilatancy
1.50 15 1.849 2.773 15.00 1.43 21.46
3.00 13 1.891 5.609 13.00 1.20 15.54
4.50 18 1.891 8.445 18.00 1.06 19.05

SPT N Value
0 5 10 15 20 25
0.00
Depth (metre)

SPT Recorded
SPT Corrected
5.00

10.00

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 32
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-D
GRAPH-3: SPT CORRECTION & PLOT FOR BORE No. 03
Bore Hole No. 03 Depth of water table: Not Encountered
Depth Bulk Overburden SPT
SPT Correction SPT
of density Pressure after
Recorded 3 2 Factor Corrected
sample (t/m ) (t/m ) dilatancy
1.50 13 1.798 2.697 13.00 1.44 18.72
3.00 10 1.888 5.529 10.00 1.20 12.00
4.50 14 1.888 8.361 14.00 1.06 14.86

SPT N Value
0 5 10 15 20 25
0.00
Depth (metre)

SPT Recorded
SPT Corrected
5.00

10.00

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 33
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-D
GRAPH-4: SPT CORRECTION & PLOT FOR BORE No. 04
Bore Hole No. 04 Depth of water table: Not Encountered
Depth Bulk Overburden SPT
SPT Correction SPT
of density Pressure after
Recorded 3 2 Factor Corrected
sample (t/m ) (t/m ) dilatancy
1.50 14 1.791 2.687 14.00 1.44 20.18
3.00 18 1.861 5.479 18.00 1.20 21.65
4.50 17 1.861 8.271 17.00 1.07 18.11

SPT N Value
0 5 10 15 20 25
0.00
Depth (metre)

SPT Recorded
SPT Corrected
5.00

10.00

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 34
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-D
GRAPH-5: SPT CORRECTION & PLOT FOR BORE No. 05
Bore Hole No. 05 Depth of water table: Not Encountered
Depth Bulk Overburden SPT
SPT Correction SPT
of density Pressure after
Recorded 3 2 Factor Corrected
sample (t/m ) (t/m ) dilatancy
1.50 14 1.857 2.786 14.00 1.43 20.01
3.00 16 1.957 5.721 16.00 1.19 19.02
4.50 19 1.957 8.656 19.00 1.05 19.95

SPT N Value
0 5 10 15 20 25
0.00
Depth (metre)

SPT Recorded
SPT Corrected
5.00

10.00

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 35
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-E
GRAPH-1: TRI-AXIAL COMPRESSION TEST GRAPH

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 36
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan
Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-E
GRAPH-2: TRI-AXIAL COMPRESSION TEST GRAPH

________________________________________________________________________________________________________
Registered Office: 111/215 Harsh Nagar, Kanpur, Uttar Pradesh Phone: 9807920716 Page 37
AJ Technical Consultant 1276_STP_Kalyan Sagar Pond
Register No: UP43D0021003)
(Under Registered Govt. of India MSME)
Revision: R0

Geotechnical Investigation for proposed construction of Sewerage Treatment Plant (STP) at Kalyan Sagar Pond, Mahoba, Uttar Pradesh.

APPENDIX-F
SITE PHOTOGRAPHS

End of Report