TIME SCHEDULLE

PROGRAM : PROGRAM PENGELOLAAN PENDIDIKAN


DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

JANGKA WAKTU PELAKSANAAN 120 HARI KALENDER


NO. URAIAN PEKERJAAN JUMLAH HARGA BOBOT KET.
(%)
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16

A. PEKERJAAN PERSIAPAN Rp 20,500,000.00 3.80 0.951 0.951 0.951 0.951

B. SISTEM MANAJEMEN KESELAMATAN DAN Rp 30,115,000.00 5.59 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926 0.34926
KESEHATAN KERJA (SMK3)

C. PEKERJAAN REHAB RUANG KELAS Rp 132,502,400.00 24.59 3.51246 3.51246 3.51246 3.51246 3.51246 3.51246 3.51246

D. PEKERJAAN BANGUNAN RUANG GURU Rp 355,790,670.00 66.02 5.07851 5.07851 7.61777 7.61777 5.07851 7.61777 5.07851 5.07851 5.07851 3.80888 3.80888 3.80888 1.27

JUMLAH Rp 538,908,070.00 100.00

MINGGUAN 1.3 4.8 4.8 8.9 8.9 11.5 11.5 8.9 8.0 5.4 5.4 5.4 4.2 4.2 4.2 2.6
RENCANA
KUMULATIF - 1.3 6.1 10.9 19.9 28.8 40.3 51.8 60.7 68.7 74.1 79.5 85.0 89.1 93.3 97.4 100.0

Samarinda, 24 Juni 2021


PENAWAR PEKERJAAN
CV. AGWINDO RAYA

Stanley Agwin Rannu


Direktur
DAFTAR HARGA BAHAN/MATERIAL & UPAH
PROGRAM PENGELOLAAN PENDIDIKAN
PROGRAM : DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

NO BAHAN/MATERIAL, UPAH SATUAN HARGA & UPAH KETERANGAN


BAHAN/MATERIAL
1 Air (campuran beton) Ltr Rp 200.00
2 Batako Bh Rp 4,000.00
3 Batu Belah 15 cm / 20 cm M3 Rp 375,000.00
4 Besi beton (polos/ulir) Kg Rp 18,000.00
5 Besi Strip Kg Rp 15,000.00
6 Cat Dasar Kg Rp 65,000.00
7 Cat meni kayu Kg Rp 40,000.00
8 Cat minyak Penutup Ltr Rp 135,000.00
9 Cat Waterbase Penutup Ltr Rp 120,000.00
10 Engsel Pintu Bh Rp 50,000.00
11 Floor Drain Bh Rp 120,000.00
12 GRC Board 4 mm M2 Rp 80,000.00
13 Grendel Jendela Bh Rp 25,000.00
14 Ijuk M2 Rp 50,000.00
15 Kaca Bening 5mm M2 Rp 150,000.00
16 Kait Angin Bh Rp 25,000.00
17 Kawat Beton Kg Rp 22,000.00
18 Kayu bekisting M3 Rp 3,000,000.00
19 Kayu 5/5 meranti M3 Rp 2,800,000.00
20 Kayu Bengkirai (Balok) M3 Rp 6,500,000.00
21 Kayu Bengkirai (Papan) M3 Rp 6,700,000.00
22 Kayu Meranti (Balok) M3 Rp 2,800,000.00
23 Kayu Meranti (Papan) M3 Rp 3,000,000.00
24 Keramik ukuran (40 x 40) cm Bh Rp 17,000.00
26 Keramik ukuran (20 x 20) cm Bh Rp 4,000.00
26 Keramik ukuran (20 x 25) cm Bh Rp 5,000.00
27 Kerikil M3 Rp 350,000.00
28 Batu Pecah/split (maksimum 30 mm) M3 Rp 420,000.00
29 Kloset Jongkok Porselen Bh Rp 400,000.00
30 Koral Beton M3 Rp 420,000.00
31 Kran Air Bh Rp 100,000.00 Ukuran 1/2" atau 3/4"
32 Kunci Tanam Biasa Bh Rp 350,000.00
33 Lem kayu Kg Rp 25,000.00
34 Lis Plafond (Kayu Profil 1x4) M1 Rp 10,000.00
35 Minyak bekisting Ltr Rp 20,000.00
36 Paku biasa Kg Rp 20,000.00
37 Pipa Listrik 5/8 PVC Btg Rp 5,000.00
38 Kabel NYM 2×1,5 Roll Rp 800,000.00
39 Klem Kabel Dos Rp 5,000.00
40 Tee Doos Bh Rp 4,000.00
41 Fitting Bh Rp 15,000.00
42 Paku seng Kg Rp 25,000.00
43 Pasir Beton M3 Rp 320,000.00
44 Pasir Pasang M3 Rp 200,000.00
45 Pipa Penghawaan M1 Rp 5,000.00
46 Pipa PVC tipe AW Dia. 1/2" M1 Rp 7,000.00
47 Pipa PVC tipe AW Dia. 2" M1 Rp 25,000.00
48 Pipa PVC tipe AW Dia. 4" M1 Rp 50,000.00
49 Plamur Kg Rp 35,000.00
50 Plamir Kayu Kg Rp 40,000.00
51 Portland Cement Kg Rp 1,600.00
52 PVC Dia 4" (D) + By Pasang + Sambungan M1 Rp 75,000.00
53 Seal Tape Bh Rp 15,000.00
54 Semen warna Kg Rp 12,000.00
55 Atap Seng Soka Lbr Rp 140,000.00
NO BAHAN/MATERIAL, UPAH SATUAN HARGA & UPAH KETERANGAN
56 Bubungan soka Lbr Rp 35,000.00
57 Sirtu M3 Rp 100,000.00
58 MCB 1 Phasa Ttk Rp 85,000.00
59 Stop Kontak Ttk Rp 75,000.00
60 Lampu TL.20 Watt Bh Rp 175,000.00
61 Saklar Ganda Bh Rp 75,000.00
62 Saklar Tunggal Bh Rp 60,000.00

UPAH
1 Mandor OH Rp 180,000.00
2 Kepala Tukang OH Rp 170,000.00
3 Kepala Tukang Batu OH Rp 170,000.00
4 Kepala Tukang Cat OH Rp 170,000.00
5 Kepala Tukang Kayu OH Rp 170,000.00
6 Tukang Batu OH Rp 160,000.00
7 Tukang Besi OH Rp 160,000.00
8 Tukang Cat OH Rp 160,000.00
9 Tukang Instalatur Listrik OH Rp 160,000.00
10 Tukang Kayu OH Rp 160,000.00
11 Pekerja OH Rp 120,000.00
ANALISA HARGA SATUAN

PROGRAM : PROGRAM PENGELOLAAN PENDIDIKAN


KEGIATAN : DAK KAB. KUTAI
REHABILITASI BARAT
RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

BHN HARGA SATUAN


NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa sedalam 1 meter
TENAGA KERJA Pekerja OH 0.750 Rp 120,000.00 Rp 90,000.00
Mandor OH 0.025 Rp 180,000.00 Rp 4,500.00
Jumlah Rp 94,500.00
Cost + Profit 15% Rp 14,175.00
Jumlah Total Rp 108,675.00
Dibulatkan Rp 108,600.00
2 1 M3 Mengurug Sirtu Padat Untuk Peninggian Lantai Bangunan
BAHAN Sirtu M3 1.200 Rp 100,000.00 Rp 120,000.00
TENAGA KERJA Pekerja OH 0.250 Rp 120,000.00 Rp 30,000.00
Mandor OH 0.025 Rp 180,000.00 Rp 4,500.00
Jumlah Rp 154,500.00
Cost + Profit 15% Rp 23,175.00
Jumlah Total Rp 177,675.00
Dibulatkan Rp 177,600.00
PEKERJAAN PONDASI
3 1 M3 Pasangan Pondasi Batu Belah, Camp. 1 Pc : 5 Pp
BAHAN Batu Belah 15 cm / 20 cm M3 1.200 Rp 375,000.00 Rp 450,000.00
Portland Cement Kg 136.000 Rp 1,600.00 Rp 217,600.00
Pasir Pasang M3 0.544 Rp 200,000.00 Rp 108,800.00
TENAGA KERJA Pekerja OH 1.500 Rp 120,000.00 Rp 180,000.00
Tukang Batu OH 0.750 Rp 160,000.00 Rp 120,000.00
Kepala Tukang OH 0.075 Rp 170,000.00 Rp 12,750.00
Mandor OH 0.075 Rp 180,000.00 Rp 13,500.00
Jumlah Rp 1,102,650.00
Cost + Profit 15% Rp 165,397.50
Jumlah Total Rp 1,268,047.50
Dibulatkan Rp 1,268,000.00
PEKERJAAN BETON
4 1 M3 Beton Lantai Kerja f'c = 7,4 MPa (K100), sl ump (3-6) cm, w/c = 0
BAHAN Portland Cement Kg 230.000 Rp 1,600.00 Rp 368,000.00
Pasir Beton M3 0.638 Rp 320,000.00 Rp 204,160.00
Batu Pecah/split (maksimum 30 mm) M3 0.761 Rp 420,000.00 Rp 319,620.00
Air (campuran beton) Ltr 200.000 Rp 200.00 Rp 40,000.00
TENAGA KERJA Pekerja OH 1.200 Rp 120,000.00 Rp 144,000.00
Tukang Batu OH 0.200 Rp 160,000.00 Rp 32,000.00
Kepala Tukang OH 0.020 Rp 170,000.00 Rp 3,400.00
Mandor OH 0.060 Rp 180,000.00 Rp 10,800.00
Jumlah Rp 1,121,980.00
Cost + Profit 15% Rp 168,297.00
Jumlah Total Rp 1,290,277.00
Dibulatkan Rp 1,290,200.00
Catatan : bobot isi pasir = 1.400 Kg/m3, bobot kerikil = 1.350 Kg/m3, bukling factor pasir = 20 %
5 1 M3 Membuat sloof beton bertulang (200 Kg besi + bekisting)
BAHAN Kayu Bekisting M3 0.270 Rp 3,000,000.00 Rp 810,000.00
Paku biasa Kg 2.000 Rp 20,000.00 Rp 40,000.00
Minyak bekisting Ltr 0.600 Rp 20,000.00 Rp 12,000.00
Besi beton (polos/ulir) Kg 210.000 Rp 18,000.00 Rp 3,780,000.00
Kawat beton Kg 3.000 Rp 22,000.00 Rp 66,000.00
Portland Cement Kg 336.000 Rp 1,600.00 Rp 537,600.00
Pasir Beton M3 0.540 Rp 320,000.00 Rp 172,800.00
Kerikil M3 0.810 Rp 350,000.00 Rp 283,500.00
TENAGA KERJA Pekerja OH 5.650 Rp 120,000.00 Rp 678,000.00
Tukang Batu OH 0.275 Rp 160,000.00 Rp 44,000.00
Tukang Kayu OH 1.560 Rp 160,000.00 Rp 249,600.00
Tukang Besi OH 1.400 Rp 160,000.00 Rp 224,000.00
Kepala Tukang OH 0.323 Rp 170,000.00 Rp 54,910.00
Mandor OH 0.283 Rp 180,000.00 Rp 50,940.00
Jumlah Rp 7,003,350.00
Cost + Profit 15% Rp 1,050,502.50
Jumlah Total Rp 8,053,852.50
Dibulatkan Rp 8,053,800.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
Catatan : bobot isi pasir = 1.400 Kg/m3, bobot kerikil = 1.350 Kg/m3, bukling factor pasir = 20 %
6 1 M3 Membuat kolom beton bertulang (200 Kg besi + bekisting)
BAHAN Kayu Bekisting M3 0.400 Rp 3,000,000.00 Rp 1,200,000.00
Paku biasa Kg 4.000 Rp 20,000.00 Rp 80,000.00
Besi beton (polos/ulir) Kg 210.000 Rp 18,000.00 Rp 3,780,000.00
Kawat beton Kg 4.500 Rp 22,000.00 Rp 99,000.00
Portland Cement Kg 336.000 Rp 1,600.00 Rp 537,600.00
Pasir Beton M3 0.540 Rp 320,000.00 Rp 172,800.00
Kerikil M3 0.810 Rp 350,000.00 Rp 283,500.00
Kayu Meranti (Balok) M3 0.150 Rp 2,800,000.00 Rp 420,000.00
TENAGA KERJA Pekerja OH 7.050 Rp 120,000.00 Rp 846,000.00
Tukang Batu OH 0.275 Rp 160,000.00 Rp 44,000.00
Tukang Kayu OH 1.625 Rp 160,000.00 Rp 260,000.00
Tukang Besi OH 2.100 Rp 160,000.00 Rp 336,000.00
Kepala Tukang OH 0.403 Rp 170,000.00 Rp 68,510.00
Mandor OH 0.353 Rp 180,000.00 Rp 63,540.00
Jumlah Rp 8,190,950.00
Cost + Profit 15% Rp 1,228,642.50
Jumlah Total Rp 9,419,592.50
Dibulatkan Rp 9,419,500.00
Catatan : bobot isi pasir = 1.400 Kg/m3, bobot kerikil = 1.350 Kg/m3, bukling factor pasir = 20 %
7 1 M3 Membuat balok beton bertulang (200 Kg besi + bekisting)
BAHAN Kayu Bekisting M3 0.320 Rp 3,000,000.00 Rp 960,000.00
Paku biasa Kg 3.200 Rp 20,000.00 Rp 64,000.00
Besi beton (polos/ulir) Kg 210.000 Rp 18,000.00 Rp 3,780,000.00
Kawat beton Kg 3.000 Rp 22,000.00 Rp 66,000.00
Portland Cement Kg 336.000 Rp 1,600.00 Rp 537,600.00
Pasir Beton M3 0.540 Rp 320,000.00 Rp 172,800.00
Kerikil M3 0.810 Rp 350,000.00 Rp 283,500.00
Kayu Meranti (Balok) M3 0.140 Rp 2,800,000.00 Rp 392,000.00
TENAGA KERJA Pekerja OH 6.350 Rp 120,000.00 Rp 762,000.00
Tukang Batu OH 0.275 Rp 160,000.00 Rp 44,000.00
Tukang Kayu OH 1.625 Rp 160,000.00 Rp 260,000.00
Tukang Besi OH 1.400 Rp 160,000.00 Rp 224,000.00
Kepala Tukang OH 0.333 Rp 170,000.00 Rp 56,610.00
Mandor OH 0.318 Rp 180,000.00 Rp 57,240.00
Jumlah Rp 7,659,750.00
Cost + Profit 15% Rp 1,148,962.50
Jumlah Total Rp 8,808,712.50
Dibulatkan Rp 8,808,700.00
Catatan : bobot isi pasir = 1.400 Kg/m3, bobot kerikil = 1.350 Kg/m3, bukling factor pasir = 20 %
8 1 M3 Membuat plat beton bertulang (150 Kg besi + bekisting )
BAHAN Kayu Bekisting M3 0.320 Rp 3,000,000.00 Rp 960,000.00
Paku biasa Kg 3.200 Rp 20,000.00 Rp 64,000.00
Besi beton (polos/ulir) Kg 157.500 Rp 18,000.00 Rp 2,835,000.00
Kawat beton Kg 2.250 Rp 22,000.00 Rp 49,500.00
Portland Cement Kg 336.000 Rp 1,600.00 Rp 537,600.00
Pasir Beton M3 0.540 Rp 320,000.00 Rp 172,800.00
Kerikil M3 0.810 Rp 350,000.00 Rp 283,500.00
Kayu Meranti (Balok) M3 0.120 Rp 2,800,000.00 Rp 336,000.00
TENAGA KERJA Pekerja OH 5.300 Rp 120,000.00 Rp 636,000.00
Tukang Batu OH 0.275 Rp 160,000.00 Rp 44,000.00
Tukang Kayu OH 1.300 Rp 160,000.00 Rp 208,000.00
Tukang Besi OH 1.050 Rp 160,000.00 Rp 168,000.00
Kepala Tukang OH 0.265 Rp 170,000.00 Rp 45,050.00
Mandor OH 0.265 Rp 180,000.00 Rp 47,700.00
Jumlah Rp 6,387,150.00
Cost + Profit 15% Rp 958,072.50
Jumlah Total Rp 7,345,222.50
Dibulatkan Rp 7,345,200.00
Catatan : bobot isi pasir = 1.400 Kg/m3, bobot kerikil = 1.350 Kg/m3, bukling factor pasir = 20 %
PEKERJAAN DINDING
9 1 M2 Pas. Dinding Tebal batako 1/2 Bt., 1 Pc : 4 PP
BAHAN Batako Bh 17.000 Rp 4,000.00 Rp 68,000.00
Portland Cement Kg 14.370 Rp 1,600.00 Rp 22,992.00
Pasir pasang M3 0.040 Rp 200,000.00 Rp 8,000.00
TENAGA KERJA Pekerja OH 0.300 Rp 120,000.00 Rp 36,000.00
Tukang Batu OH 0.100 Rp 160,000.00 Rp 16,000.00
Kepala Tukang OH 0.010 Rp 170,000.00 Rp 1,700.00
Mandor OH 0.015 Rp 180,000.00 Rp 2,700.00
Jumlah Rp 155,392.00
Cost + Profit 15% Rp 23,308.80
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
Jumlah Total Rp 178,700.80
Dibulatkan Rp 178,700.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
PEKERJAAN PLESTERAN
10 1 M2 Plesteran 1 PC : 6 PP, Tbl 15 mm
BAHAN Portland Cement Kg 4.416 Rp 1,600.00 Rp 7,065.60
Pasir pasang M3 0.027 Rp 200,000.00 Rp 5,400.00
TENAGA KERJA Pekerja OH 0.300 Rp 120,000.00 Rp 36,000.00
Tukang Batu OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang OH 0.015 Rp 170,000.00 Rp 2,550.00
Mandor OH 0.015 Rp 180,000.00 Rp 2,700.00
Jumlah Rp 77,715.60
Cost + Profit 15% Rp 11,657.34
Jumlah Total Rp 89,372.94
Dibulatkan Rp 89,300.00
11 1 M3 Membuat & memasang kusen pintu & kusen jendela, kayu Bengkirai
BAHAN Kayu Bengkirai (Balok) M3 1.200 Rp 6,500,000.00 Rp 7,800,000.00
Paku biasa Kg 1.250 Rp 20,000.00 Rp 25,000.00
Lem kayu Kg 1.000 Rp 25,000.00 Rp 25,000.00
TENAGA KERJA Pekerja OH 6.000 Rp 120,000.00 Rp 720,000.00
Tukang Kayu OH 18.000 Rp 160,000.00 Rp 2,880,000.00
Kepala Tukang OH 1.800 Rp 170,000.00 Rp 306,000.00
Mandor OH 0.300 Rp 180,000.00 Rp 54,000.00
Jumlah Rp 11,810,000.00
Cost + Profit 15% Rp 1,771,500.00
Jumlah Total Rp 13,581,500.00
Dibulatkan Rp 13,581,500.00
12 1 M2 Membuat & memasang daun pintu panel, kayu kelas II
BAHAN Kayu Bengkirai (Papan) M3 0.040 Rp 6,700,000.00 Rp 268,000.00
Lem kayu Kg 0.500 Rp 25,000.00 Rp 12,500.00
TENAGA KERJA Pekerja OH 1.000 Rp 120,000.00 Rp 120,000.00
Tukang Kayu OH 3.000 Rp 160,000.00 Rp 480,000.00
Kepala Tukang OH 0.300 Rp 170,000.00 Rp 51,000.00
Mandor OH 0.050 Rp 180,000.00 Rp 9,000.00
Jumlah Rp 940,500.00
Cost + Profit 15% Rp 141,075.00
Jumlah Total Rp 1,081,575.00
Dibulatkan Rp 1,081,500.00
13 1 M2 Membuat & memasang pintu & jendela kaca, kayu Bengkirai
BAHAN Kayu Bengkirai (Papan) M 0.024 Rp 6,700,000.00 Rp 160,800.00
Lem kayu Kg 0.300 Rp 25,000.00 Rp 7,500.00
TENAGA KERJA Pekerja OH 0.800 Rp 120,000.00 Rp 96,000.00
Tukang Kayu OH 2.400 Rp 160,000.00 Rp 384,000.00
Kepala Tukang OH 0.240 Rp 170,000.00 Rp 40,800.00
Mandor OH 0.040 Rp 180,000.00 Rp 7,200.00
Jumlah Rp 696,300.00
Cost + Profit 15% Rp 104,445.00
Jumlah Total Rp 800,745.00
Dibulatkan Rp 800,700.00
14 1 M2 Pas. Jalusi kusen, kayu bengkirai
BAHAN Kayu bengkirai (Papan) M3 0.060 Rp 6,700,000.00 Rp 402,000.00
Paku biasa Kg 0.150 Rp 20,000.00 Rp 3,000.00
TENAGA KERJA Pekerja OH 0.670 Rp 120,000.00 Rp 80,400.00
Tukang Kayu OH 2.000 Rp 160,000.00 Rp 320,000.00
Kepala Tukang OH 0.200 Rp 170,000.00 Rp 34,000.00
Mandor OH 0.335 Rp 180,000.00 Rp 60,300.00
Jumlah Rp 899,700.00
Cost + Profit 15% Rp 134,955.00
Jumlah Total Rp 1,034,655.00
Dibulatkan Rp 1,034,600.00
15 1 M3 Pas. Kons. Kuda2 konvensional, kayu Bengkirai 5/10
BAHAN Kayu Bengkirai (Balok) M3 1.100 Rp 6,500,000.00 Rp 7,150,000.00
Besi Strip Kg 15.000 Rp 15,000.00 Rp 225,000.00
Paku biasa Kg 5.600 Rp 20,000.00 Rp 112,000.00
TENAGA KERJA Pekerja OH 4.000 Rp 120,000.00 Rp 480,000.00
Tukang Kayu OH 12.000 Rp 160,000.00 Rp 1,920,000.00
Kepala Tukang OH 1.200 Rp 170,000.00 Rp 204,000.00
Mandor OH 0.200 Rp 180,000.00 Rp 36,000.00
Jumlah Rp 10,127,000.00
Cost + Profit 15% Rp 1,519,050.00
Jumlah Total Rp 11,646,050.00
Dibulatkan Rp 11,646,000.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
16 1 M3 Pas. Kons. Gording, kayu Bengkirai
BAHAN Kayu Bengkirai (Balok) M3 1.100 Rp 6,500,000.00 Rp 7,150,000.00
Besi Strip Kg 15.000 Rp 15,000.00 Rp 225,000.00
Paku biasa Kg 3.000 Rp 20,000.00 Rp 60,000.00
TENAGA KERJA Pekerja OH 2.400 Rp 120,000.00 Rp 288,000.00
Tukang Kayu OH 7.200 Rp 160,000.00 Rp 1,152,000.00
Kepala Tukang OH 0.720 Rp 170,000.00 Rp 122,400.00
Mandor OH 0.120 Rp 180,000.00 Rp 21,600.00
Jumlah Rp 9,019,000.00
Cost + Profit 15% Rp 1,352,850.00
Jumlah Total Rp 10,371,850.00
Dibulatkan Rp 10,371,800.00
17 1 M2 Pas. Rangka langit2 (60 x 60)cm, kayu Meranti
BAHAN Kayu 5/5 Meranti M 0.016 Rp 2,800,000.00 Rp 45,640.00
Paku biasa Kg 0.250 Rp 20,000.00 Rp 5,000.00
TENAGA KERJA Pekerja OH 0.200 Rp 120,000.00 Rp 24,000.00
Tukang Kayu OH 0.300 Rp 160,000.00 Rp 48,000.00
Kepala Tukang OH 0.030 Rp 170,000.00 Rp 5,100.00
Mandor OH 0.010 Rp 180,000.00 Rp 1,800.00
Jumlah Rp 129,540.00
Cost + Profit 15% Rp 19,431.00
Jumlah Total Rp 148,971.00
Dibulatkan Rp 148,900.00
18 1 M1 Pas. Lisplang Ukuran ( 2 x 30 ) m, Kayu Meranti
BAHAN Kayu Meranti (Papan) M3 0.007 Rp 3,000,000.00 Rp 21,600.00
Paku biasa Kg 0.050 Rp 20,000.00 Rp 1,000.00
TENAGA KERJA Pekerja OH 0.100 Rp 120,000.00 Rp 12,000.00
Tukang Kayu OH 0.200 Rp 160,000.00 Rp 32,000.00
Kepala Tukang OH 0.020 Rp 170,000.00 Rp 3,400.00
Mandor OH 0.005 Rp 180,000.00 Rp 900.00
Jumlah Rp 70,900.00
Cost + Profit 15% Rp 10,635.00
Jumlah Total Rp 81,535.00
Dibulatkan Rp 81,500.00
PEKERJAAN PENUTUP LANTAI DAN DINDING
19 1 M2 Pas. Lantai keramik ukuran (40 x 40) cm
BAHAN Keramik ukuran (40 x 40) cm Bh 6.250 Rp 17,000.00 Rp 106,250.00
Portland Cement Kg 8.010 Rp 1,600.00 Rp 12,816.00
Pasir Pasang M3 0.045 Rp 200,000.00 Rp 9,000.00
Semen warna Kg 1.620 Rp 12,000.00 Rp 19,440.00
TENAGA KERJA Pekerja OH 0.700 Rp 120,000.00 Rp 84,000.00
Tukang Batu OH 0.350 Rp 160,000.00 Rp 56,000.00
Kepala Tukang OH 0.035 Rp 170,000.00 Rp 5,950.00
Mandor OH 0.035 Rp 180,000.00 Rp 6,300.00
Jumlah Rp 299,756.00
Cost + Profit 15% Rp 44,963.40
Jumlah Total Rp 344,719.40
Dibulatkan Rp 344,700.00
20 1 M2 Pas. Lantai keramik ukuran (20 x 20) cm
BAHAN Keramik ukuran (20 x 20) cm Bh 26.500 Rp 4,000.00 Rp 106,000.00
Portland Cement Kg 10.400 Rp 1,600.00 Rp 16,640.00
Pasir Pasang M3 0.045 Rp 200,000.00 Rp 9,000.00
Semen warna Kg 1.620 Rp 12,000.00 Rp 19,440.00
TENAGA KERJA Pekerja OH 0.700 Rp 120,000.00 Rp 84,000.00
Tukang Batu OH 0.350 Rp 160,000.00 Rp 56,000.00
Kepala Tukang OH 0.035 Rp 170,000.00 Rp 5,950.00
Mandor OH 0.035 Rp 180,000.00 Rp 6,300.00
Jumlah Rp 303,330.00
Cost + Profit 15% Rp 45,499.50
Jumlah Total Rp 348,829.50
Dibulatkan Rp 348,800.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
21 1 M2 Pas. Dinding keramik ukuran (20x25)cm
BAHAN Keramik ukuran (20 x 25) cm Bh 20.000 Rp 5,000.00 Rp 100,000.00
Portland Cement Kg 9.300 Rp 1,600.00 Rp 14,880.00
Pasir Pasang M3 0.018 Rp 200,000.00 Rp 3,600.00
Semen warna Kg 1.940 Rp 12,000.00 Rp 23,280.00
TENAGA KERJA Pekerja OH 0.900 Rp 120,000.00 Rp 108,000.00
Tukang Batu OH 0.450 Rp 160,000.00 Rp 72,000.00
Kepala Tukang OH 0.045 Rp 170,000.00 Rp 7,650.00
Mandor OH 0.045 Rp 180,000.00 Rp 8,100.00
Jumlah Rp 337,510.00
Cost + Profit 15% Rp 50,626.50
Jumlah Total Rp 388,136.50
Dibulatkan Rp 388,100.00
PEKERJAAN LANGIT LANGIT
22 1 M2 Pek. Plafond GRC
BAHAN GRC Board 4 mm M 1.100 Rp 80,000.00 Rp 88,000.00
Paku biasa Kg 0.010 Rp 20,000.00 Rp 200.00
TENAGA KERJA Pekerja OH 0.030 Rp 120,000.00 Rp 3,600.00
Tukang Kayu OH 0.070 Rp 160,000.00 Rp 11,200.00
Kepala Tukang Kayu OH 0.007 Rp 170,000.00 Rp 1,190.00
Mandor OH 0.002 Rp 180,000.00 Rp 360.00
Jumlah Rp 104,550.00
Cost + Profit 15% Rp 15,682.50
Jumlah Total Rp 120,232.50
Dibulatkan Rp 120,200.00
23 1 M1 Pek. Lis Plafond Kayu Profil 1 x 4 cm
BAHAN Lis Plafond (Kayu Profil 1x4) M 1.100 Rp 10,000.00 Rp 11,000.00
Paku biasa Kg 0.010 Rp 20,000.00 Rp 200.00
TENAGA KERJA Pekerja OH 0.050 Rp 120,000.00 Rp 6,000.00
Tukang Kayu OH 0.050 Rp 160,000.00 Rp 8,000.00
Kepala Tukang OH 0.005 Rp 170,000.00 Rp 850.00
Mandor OH 0.003 Rp 180,000.00 Rp 540.00
Jumlah Rp 26,590.00
Cost + Profit 15% Rp 3,988.50
Jumlah Total Rp 30,578.50
Dibulatkan Rp 30,500.00
PEKERJAAN PENUTUP ATAP
24 1 M2 Pas. Atap Seng Soka
BAHAN Atap Seng Soka Lbr 0.700 Rp 140,000.00 Rp 98,000.00
Paku seng Kg 0.020 Rp 25,000.00 Rp 500.00
TENAGA KERJA Pekerja OH 0.120 Rp 120,000.00 Rp 14,400.00
Tukang Kayu OH 0.060 Rp 160,000.00 Rp 9,600.00
Kepala Tukang Kayu OH 0.006 Rp 170,000.00 Rp 1,020.00
Mandor OH 0.006 Rp 180,000.00 Rp 1,080.00
Jumlah Rp 124,600.00
Cost + Profit 15% Rp 18,690.00
Jumlah Total Rp 143,290.00
Dibulatkan Rp 143,200.00
25 1 M1 Pas. Bubungan Soka
BAHAN Bubungan soka Lbr 1.100 Rp 35,000.00 Rp 38,500.00
Paku seng Kg 0.040 Rp 25,000.00 Rp 1,000.00
TENAGA KERJA Pekerja OH 0.150 Rp 120,000.00 Rp 18,000.00
Tukang Kayu OH 0.070 Rp 160,000.00 Rp 11,200.00
Kepala Tukang Kayu OH 0.008 Rp 170,000.00 Rp 1,360.00
Mandor OH 0.006 Rp 180,000.00 Rp 1,080.00
Jumlah Rp 71,140.00
Cost + Profit 15% Rp 10,671.00
Jumlah Total Rp 81,811.00
Dibulatkan Rp 81,800.00
PEKERJAAN KUNCI DAN KACA
26 1 Bh Pas. Engsel Pintu
BAHAN Engsel Pintu Bh 1.000 Rp 50,000.00 Rp 50,000.00
TENAGA KERJA Pekerja OH 0.015 Rp 120,000.00 Rp 1,800.00
Tukang Kayu OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang Kayu OH 0.015 Rp 170,000.00 Rp 2,550.00
Mandor OH 0.001 Rp 180,000.00 Rp 180.00
Jumlah Rp 78,530.00
Cost + Profit 15% Rp 11,779.50
Jumlah Total Rp 90,309.50
Dibulatkan Rp 90,300.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
27 1 Bh Pas. Kait Angin
BAHAN Kait Angin Bh 1.000 Rp 25,000.00 Rp 25,000.00
TENAGA KERJA Pekerja OH 0.015 Rp 120,000.00 Rp 1,800.00
Tukang Kayu OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang Kayu OH 0.015 Rp 170,000.00 Rp 2,550.00
Mandor OH 0.001 Rp 180,000.00 Rp 180.00
Jumlah Rp 53,530.00
Cost + Profit 15% Rp 8,029.50
Jumlah Total Rp 61,559.50
Dibulatkan Rp 61,500.00
28 1 Bh Pas. Kunci Tanam Biasa
BAHAN Kunci Tanam Biasa Bh 1.000 Rp 350,000.00 Rp 350,000.00
TENAGA KERJA Pekerja OH 0.010 Rp 120,000.00 Rp 1,200.00
Tukang Kayu OH 0.500 Rp 160,000.00 Rp 80,000.00
Kepala Tukang Kayu OH 0.010 Rp 170,000.00 Rp 1,700.00
Mandor OH 0.005 Rp 180,000.00 Rp 900.00
Jumlah Rp 433,800.00
Cost + Profit 15% Rp 65,070.00
Jumlah Total Rp 498,870.00
Dibulatkan Rp 498,800.00
29 1 M2 Pas. Kaca Bening tebal 5 mm
BAHAN Kaca Bening 5mm M2 1.100 Rp 150,000.00 Rp 165,000.00
TENAGA KERJA Pekerja OH 0.015 Rp 120,000.00 Rp 1,800.00
Tukang Kayu OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang Kayu OH 0.015 Rp 170,000.00 Rp 2,550.00
Mandor OH 0.001 Rp 180,000.00 Rp 135.00
Jumlah Rp 193,485.00
Cost + Profit 15% Rp 29,022.75
Jumlah Total Rp 222,507.75
Dibulatkan Rp 222,500.00
30 1 Bh Pas. Grendel Jendela
BAHAN Grendel jendela Bh 1.000 Rp 25,000.00 Rp 25,000.00
TENAGA KERJA Pekerja OH 0.015 Rp 120,000.00 Rp 1,800.00
Tukang Kayu OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang Kayu OH 0.015 Rp 170,000.00 Rp 2,550.00
Mandor OH 0.001 Rp 180,000.00 Rp 180.00
Jumlah Rp 53,530.00
Cost + Profit 15% Rp 8,029.50
Jumlah Total Rp 61,559.50
Dibulatkan Rp 61,500.00
PEKERJAAN SANITASI
31 1 Bh Memasang kloset jongkok porselin
BAHAN Kloset Jongkok Porselen Bh 1.000 Rp 400,000.00 Rp 400,000.00
Portland Cement Kg 6.000 Rp 1,600.00 Rp 9,600.00
Pasir Pasang M3 0.010 Rp 200,000.00 Rp 2,000.00
TENAGA KERJA Pekerja OH 1.000 Rp 120,000.00 Rp 120,000.00
Tukang Batu OH 1.500 Rp 160,000.00 Rp 240,000.00
Kepala Tukang Batu OH 1.500 Rp 170,000.00 Rp 255,000.00
Mandor OH 0.160 Rp 180,000.00 Rp 28,800.00
Jumlah Rp 1,055,400.00
Cost + Profit 15% Rp 158,310.00
Jumlah Total Rp 1,213,710.00
Dibulatkan Rp 1,213,700.00
32 1 M1 Memasang Pipa PVC tipe AW Dia. 1/2"
BAHAN Pipa PVC tipe AW Dia. 1/2" M 1.200 Rp 7,000.00 Rp 8,400.00
Perlengkapan - 1.000 Rp 2,000.00 Rp 2,000.00
TENAGA KERJA Pekerja OH 0.036 Rp 120,000.00 Rp 4,320.00
Tukang Batu OH 0.060 Rp 160,000.00 Rp 9,600.00
Kepala Tukang Batu OH 0.006 Rp 170,000.00 Rp 1,020.00
Mandor OH 0.002 Rp 180,000.00 Rp 324.00
Jumlah Rp 25,664.00
Cost + Profit 15% Rp 3,849.60
Jumlah Total Rp 29,513.60
Dibulatkan Rp 29,500.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
33 1 M1 Memasang Pipa PVC tipe AW Dia. 2"
BAHAN Pipa PVC tipe AW Dia. 2" M 1.200 Rp 25,000.00 Rp 30,000.00
Perlengkapan - 1.000 Rp 2,000.00 Rp 2,000.00
TENAGA KERJA Pekerja OH 0.054 Rp 120,000.00 Rp 6,480.00
Tukang Batu OH 0.090 Rp 160,000.00 Rp 14,400.00
Kepala Tukang Batu OH 0.009 Rp 170,000.00 Rp 1,530.00
Mandor OH 0.003 Rp 180,000.00 Rp 486.00
Jumlah Rp 54,896.00
Cost + Profit 15% Rp 8,234.40
Jumlah Total Rp 63,130.40
Dibulatkan Rp 63,100.00
34 1 M1 Memasang Pipa PVC tipe AW Dia. 4"
BAHAN Pipa PVC tipe AW Dia. 4" M 1.200 Rp 50,000.00 Rp 60,000.00
Perlengkapan - 1.000 Rp 2,000.00 Rp 2,000.00
TENAGA KERJA Pekerja OH 0.081 Rp 120,000.00 Rp 9,720.00
Tukang Batu OH 0.135 Rp 160,000.00 Rp 21,600.00
Kepala Tukang Batu OH 0.014 Rp 170,000.00 Rp 2,380.00
Mandor OH 0.004 Rp 180,000.00 Rp 738.00
Jumlah Rp 96,438.00
Cost + Profit 15% Rp 14,465.70
Jumlah Total Rp 110,903.70
Dibulatkan Rp 110,900.00
35 1 Bh Memasang Kran 3/4" atau 1/2"
BAHAN Kran Air Bh 1.000 Rp 100,000.00 Rp 100,000.00
Seal Tape Bh 0.025 Rp 15,000.00 Rp 375.00
TENAGA KERJA Pekerja OH 0.010 Rp 120,000.00 Rp 1,200.00
Tukang Batu OH 0.100 Rp 160,000.00 Rp 16,000.00
Kepala Tukang Batu OH 0.010 Rp 170,000.00 Rp 1,700.00
Mandor OH 0.005 Rp 180,000.00 Rp 900.00
Jumlah Rp 120,175.00
Cost + Profit 15% Rp 18,026.25
Jumlah Total Rp 138,201.25
Dibulatkan Rp 138,200.00
36 1 Bh Memasang Floor Drain
BAHAN Floor Drain Bh 1.000 Rp 120,000.00 Rp 120,000.00
TENAGA KERJA Pekerja OH 0.010 Rp 120,000.00 Rp 1,200.00
Tukang Batu OH 0.100 Rp 160,000.00 Rp 16,000.00
Kepala Tukang Batu OH 0.010 Rp 170,000.00 Rp 1,700.00
Mandor OH 0.005 Rp 180,000.00 Rp 900.00
Jumlah Rp 139,800.00
Cost + Profit 15% Rp 20,970.00
Jumlah Total Rp 160,770.00
Dibulatkan Rp 160,700.00
37 1 Unit Septicktank & Peresapan
BAHAN & Galian Tanah M3 8.807 Rp 108,600.00 Rp 956,440.20
TENAGA KERJA Pas. Trasram M3 1.494 Rp 1,787,000.00 Rp 2,669,778.00
Pasir Urug M3 1.281 Rp 177,600.00 Rp 227,505.60
Urugan Kembali M3 2.169 Rp 25,000.00 Rp 54,225.00
Plester Trasram M2 13.440 Rp 89,300.00 Rp 1,200,192.00
Ijuk M2 1.350 Rp 50,000.00 Rp 67,500.00
Plat Beton M3 0.281 Rp 7,345,200.00 Rp 2,064,001.20
Acian Semen Licin M2 13.440 Rp 40,000.00 Rp 537,600.00
Pipa Penghawaan M1 0.600 Rp 5,000.00 Rp 3,000.00
Koral Beton M3 0.900 Rp 350,000.00 Rp 315,000.00
PVC Dia 4" (D) + By Pasang + Sambungan M1 9.000 Rp 75,000.00 Rp 675,000.00
Jumlah Rp 8,770,242.00
Cost + Profit 15% Rp 1,315,536.30
Jumlah Total Rp 10,085,778.30
Dibulatkan Rp 10,085,700.00
PEKERJAAN PENGECATAN
38 1 M2 Pengecatan Bidang Kayu Lama
BAHAN Plamir kayu Kg 0.150 Rp 40,000.00 Rp 6,000.00
Cat Dasar Kg 0.170 Rp 65,000.00 Rp 11,050.00
Cat waterbase penutup Kg 0.170 Rp 120,000.00 Rp 20,400.00
TENAGA KERJA Pekerja OH 0.070 Rp 120,000.00 Rp 8,400.00
Tukang Cat OH 0.075 Rp 160,000.00 Rp 12,000.00
Kepala Tukang Cat OH 0.008 Rp 170,000.00 Rp 1,275.00
Mandor OH 0.003 Rp 180,000.00 Rp 450.00
Jumlah Rp 59,575.00
Cost + Profit 15% Rp 8,936.25
Jumlah Total Rp 68,511.25
Dibulatkan Rp 68,500.00
BHN HARGA SATUAN
NO. KEBUTUHAN SATUAN INDEKS JUMLAH
UPAH BAHAN/UPAH
39 1 M2 Pengecatan Bidang Kayu Baru (Cat minyak) 1 Lps Plamir, 1 Lps Cat Dasar, 2 Lps Cat Penutup
BAHAN Cat Meni kayu Kg 0.200 Rp 40,000.00 Rp 8,000.00
Plamir kayu Kg 0.150 Rp 40,000.00 Rp 6,000.00
Cat Dasar Kg 0.170 Rp 65,000.00 Rp 11,050.00
Cat minyak Penutup Kg 0.260 Rp 135,000.00 Rp 35,100.00
TENAGA KERJA Pekerja OH 0.070 Rp 120,000.00 Rp 8,400.00
Tukang Cat OH 0.009 Rp 160,000.00 Rp 1,440.00
Kepala Tukang Cat OH 0.006 Rp 170,000.00 Rp 1,020.00
Mandor OH 0.003 Rp 180,000.00 Rp 450.00
Jumlah Rp 71,460.00
Cost + Profit 15% Rp 10,719.00
Jumlah Total Rp 82,179.00
Dibulatkan Rp 82,100.00
40 1 M2 Pengecatan Tembok Baru : 1 Lps Plamir, 1 Lps Cat Dasar, 2 Lps Cat Penutup
BAHAN Plamur Kg 0.100 Rp 40,000.00 Rp 4,000.00
Cat Dasar Kg 0.100 Rp 65,000.00 Rp 6,500.00
Cat waterbase penutup Kg 0.260 Rp 120,000.00 Rp 31,200.00
TENAGA KERJA Pekerja OH 0.020 Rp 120,000.00 Rp 2,400.00
Tukang Cat OH 0.063 Rp 160,000.00 Rp 10,080.00
Kepala Tukang Cat OH 0.006 Rp 170,000.00 Rp 1,071.00
Mandor OH 0.003 Rp 180,000.00 Rp 450.00
Jumlah Rp 55,701.00
Cost + Profit 15% Rp 8,355.15
Jumlah Total Rp 64,056.15
Dibulatkan Rp 64,000.00
41 1 M2 Pengecatan Tembok Lama : 1 Lps Cat Dasar, 2 Lps Cat Penutup
BAHAN Cat Dasar Kg 0.120 Rp 65,000.00 Rp 7,800.00
Cat waterbase penutup Kg 0.180 Rp 120,000.00 Rp 21,600.00
TENAGA KERJA Pekerja OH 0.028 Rp 120,000.00 Rp 3,360.00
Tukang Cat OH 0.042 Rp 160,000.00 Rp 6,720.00
Kepala Tukang Cat OH 0.004 Rp 170,000.00 Rp 714.00
Mandor OH 0.003 Rp 180,000.00 Rp 450.00
Jumlah Rp 40,644.00
Cost + Profit 15% Rp 6,096.60
Jumlah Total Rp 46,740.60
Dibulatkan Rp 46,700.00
PEKERJAAN INSTALASI LISTRIK
42 1 Titik Pemasangan Titik Lampu
BAHAN Pipa Listrik 5/8 PVC Kabel NYM 2×1,5 btg 1.500 Rp 5,000.00 Rp 7,500.00
Kabel NYM 2×1,5 roll 0.100 Rp 800,000.00 Rp 80,000.00
Klem Kabel doos 0.100 Rp 5,000.00 Rp 500.00
Tee Doos bh 1.000 Rp 4,000.00 Rp 4,000.00
Fitting bh 1.000 Rp 15,000.00 Rp 15,000.00
TENAGA KERJA
TENAGA KERJA Pekerja OH 0.300 Rp 120,000.00 Rp 36,000.00
Tukang Instalatur Listrik OH 0.150 Rp 160,000.00 Rp 24,000.00
Kepala Tukang OH 0.075 Rp 170,000.00 Rp 12,750.00
Jumlah Rp 179,750.00
Cost++Profit
Cost Profit15%
15% Rp 26,962.50
Jumlah Total Rp 206,712.50
Dibulatkan Rp 206,700.00

43 1 Ttk MCB 1 Phasa Ttk 1.000 Rp 85,000.00


44 1 Ttk Stop Kontak Ttk 1.000 Rp 75,000.00
45 1 Bh Lampu TL.20 Watt Bh 1.000 Rp 175,000.00
46 1 Bh Saklar Ganda Bh 1.000 Rp 75,000.00
47 1 Bh Saklar Tunggal Bh 1.000 Rp 60,000.00
ANALISA HARGA SATUAN
SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3)

PROGRAM : PROGRAM PENGELOLAAN PENDIDIKAN


KEGIATAN : DAK KAB. KUTAIRUANG
REHABILITASI BARATKELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
Jenis Pekerjaan : SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3)
Satuan Pembayaran : LS

NO URAIAN SATUAN VOL HAGA SATUAN TOTAL KET


I Penyiapan RK3K terdiri atas:
1 Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Set - Rp -
2 Pembuatan Kartu Identitas Pekerja (KIP) Paket 1.00 Rp 1,000,000.00 Rp 1,000,000.00

II Sosialisasi dan Promosi K3 terdiri dari :


1 Induksi K3 (Safety Induction ); Ls - Rp -
2 Pengarahan K3 (safety briefing) : Pertemuan Keselamatan Paket 1.00 Rp 2,500,000.00 Rp 2,500,000.00
(Safety Talk dan/atau Tool Box Meeting );
3 Pelatihan K3; Org - Rp -
4 Simulasi K3 Org - Rp -
5 Spanduk (banner) ; Lb - Rp -
6 Poster; Lb - Rp -
7 Papan Informasi K3. BH - Rp -

III Alat Pelindung Kerja / Diri terdiri atas:


1 Jaring Pengaman (Safety Net); Ls - Rp -
2 Tali Keselamatan (Life Line); Ls - Rp -
3 Penahan Jatuh (Safety Deck); Ls - Rp -
4 Pagar Pengaman (Guard Railling); Ls - Rp -
5 Pembatas Area (RestrictedArea ). Ls - Rp -
6 Alat Pemadam Api Ringan (APAR); Bh 2.00 Rp 1,500,000.00 Rp 3,000,000.00
7 Topi Pelindung (Safety Helmet) ; Bh 3.00 Rp 80,000.00 Rp 240,000.00 Staf & Tamu
8 Pelindung Mata (Goggles,Spectacles ); Psg - Rp -
9 Tameng Muka (Face Shield ); Bh - Rp -
10 Masker Selam (Breathing Apparatus ); Bh - Rp -
11 Pelindung Telinga (EarPlug, EarMuff); Psg - Rp -
12 Pelindung Pernafasan dan Mulut (Masker ) Bh - Rp -
13 Sarung Tangan (Safety Gloves ); Psg 5.00 Rp 35,000.00 Rp 175,000.00
14 Sepatu Keselamatan (Safety Shoes ) ;untuk Staf Psg - Rp -
15 Sepatu Kerja (Boots ) ; Psg 5.00 Rp 250,000.00 Rp 1,250,000.00
16 Penunjang Seluruh Tubuh (Full Body Harness ); Bh - Rp -
17 Jaket Pelampung (LifeVest ); Bh - Rp -
18 Rompi Keselamatan (SafetyVest ); Bh 5.00 Rp 150,000.00 Rp 750,000.00
19 Celemek (Apron/Coveralls ); Bh - Rp -
20 Pelindung Jatuh (FallArrester ); Bh - Rp -

IV Asuransi Dan Perijinan terdiri atas:


1 BPJS Ketenagakerjaan Dan Kesehatan Kerja Ls - Rp -
2 Surat Ijin Kelaikan Alat; Alat/Kend - Rp -
3 Surat Ijin Operator; Lb/alat - Rp -
4 Surat Ijin Pengesahan Panitia Pembina Keselamatan Dan Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00
Kesehatan Kerja

V Personil K3 terdiri atas:


1 Ahli K3 Paket - Rp -
2 Petugas K3 Paket 1.00 Rp 15,000,000.00 Rp 15,000,000.00 Risiko K3
3 Petugas Tanggap Darurat; Paket - Rp - Sedang/
Kecil
4 Petugas P3K; Paket - Rp -
5 Petugas Pengatur Lalu Lintas (Flagman ); Paket - Rp -
6 Petugas Medis. Paket - Rp -
NO URAIAN SATUAN VOL HAGA SATUAN TOTAL KET
VI Fasilitas sarana kesehatan;
1 Peralatan P3K( Kotak P3K, Tandu, Tabung Oksigen,Obat Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00
Luka, Perban)
2 Ruang P3K (Tempat Tidur Pasien, Stetoskop,Timbangan Ls - Rp -
Berat Badan)
3 Peralatan Pengasapan (Fogging) ; Ls - Rp -
4 Obat Pengasapan. Ls - Rp -

VII Rambu-Rambu terdiri atas:


1 Rambu Petunjuk; Bh - Rp -
2 Rambu Larangan Bh - Rp -
3 Rambu Peringatan; Bh 2.00 Rp 500,000.00 Rp 1,000,000.00
4 Rambu Kewajiban; Bh - Rp -
5 Rambu Informasi; Bh - Rp -
6 Rambu Pekerjaan Sementara; Bh - Rp -
7 Tongkat Pengatur Lalu Lintas (Warning LightsStick ); Bh - Rp -
8 Kerucut Lalu Lintas (Traffic Cone) ; Bh - Rp -
9 Lampu Putar (RotaryLamp ); Bh - Rp -
10 Lampu Selang Lalu Lintas. Bh - Rp -

VIII Kegiatan dan Peralatan Terkait Pengendalian Risiko K3


1 Sirine; Bh - Rp -
2 Bendera K3; Bh 1.00 Rp 200,000.00 Rp 200,000.00
3 Jalur Evakuasi (Escape Route ); Ls - Rp -
4 Lampu Darurat (Emergency Lamp ); Bh - Rp -
5 Program Inspeksi Dan Audit Internal; Ls - Rp -
6 Pelaporan dan Penyelidikan Insiden. Ls - Rp -

TOTAL SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3) Rp 30,115,000.00


MOBILISASI & DEMOBILISASI
PROGRAM PENGELOLAAN PENDIDIKAN
PROGRAM :
DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
Jenis Pekerjaan : Mobilisasi & Demobilisasi
Satuan Pembayaran : Ls

HARGA JUMLAH
No. URAIAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
A SEWA TANAH M2 - -
PERALATAN LS - -
B
Lihat Lembar 1.2.2
C FASILITAS KONTRAKTOR
1 Base Camp M2 - -
2 Kantor M2 - -
D FASILITAS DIREKSI
1 Akomodasi Ls - -
2 Sewa Kendaraan Roda 2 Bh - -
3 Sewa Kendaraan Roda 4 - (4 bulan) Bh 1.00 10,000,000 10,000,000
E FASILITAS PENGUJIAN LABORATORIUM
1 Test Bahan Konstruksi Unit - -
2 Job Mix Formula Unit - -
F MOBILISASI LAINNYA
1 Papan Nama Proyek Bh 1.00 500,000 500,000
2 Asbuilt Drawing Ls 1.00 10,000,000 10,000,000
G DEMOBILISASI Ls - -
TOTAL BIAYA MOBILISASI & DEMOBILISASI 20,500,000
(A + B + C + D + E + F + G)

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi diatas sudah termasuk
over-head dan laba serta seluruh pajak dan bea (kecuali PPN) dan pengeluaran lainnya.
BILL OF QUANTITY (BOQ)
PROGRAM PENGELOLAAN PENDIDIKAN
PROGRAM : DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH


PEKERJAAN

A. PEKERJAAN PERSIAPAN
1 Mobilisasi & Demobilisasi 1.00 LS Rp 20,500,000.00 Rp 20,500,000.00
SUBTOTAL A. Rp 20,500,000.00

B. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3)


1 Sistem Manajemen Keselamatan Dan Kesehatan Kerja (SMK3) 1.00 LS Rp 30,115,000.00 Rp 30,115,000.00
SUBTOTAL B. Rp 30,115,000.00

C. PEKERJAAN REHAB RUANG KELAS


1 Pas. Keramik 40x40 Ruangan dan Teras 180.00 M2 Rp 344,700.00 Rp 62,046,000.00
2 Pas. Engsel Pintu 9.00 Bh Rp 90,300.00 Rp 812,700.00
3 Pas. Kunci Tanam Biasa + Handle Pintu 3.00 Bh Rp 498,800.00 Rp 1,496,400.00
4 Pek. Cat Dinding dan Kolom Pilar Teras 427.00 M2 Rp 46,700.00 Rp 19,940,900.00
5 Pek. Cat Kusen + Daun Pintu dan Jendela 21.30 M2 Rp 68,500.00 Rp 1,459,050.00
6 Pas. Atap Seng Soka 264.00 M2 Rp 143,200.00 Rp 37,804,800.00
7 Pas. Nok / Bubungan Soka 22.00 M1 Rp 81,800.00 Rp 1,799,600.00
8 Pas. Lisplang Meranti 2/30 68.00 M1 Rp 81,500.00 Rp 5,542,000.00
9 Pek. Cat Lisplang 19.50 M2 Rp 82,100.00 Rp 1,600,950.00
SUBTOTAL C. Rp 132,502,400.00

D. PEKERJAAN BANGUNAN RUANG GURU


D-I PEKERJAAN TANAH DAN PONDASI
1 Galian Pondasi 33.00 M3 Rp 108,600.00 Rp 3,583,800.00
2 Pas. Batu Kali 1:5 23.00 M3 Rp 1,268,000.00 Rp 29,164,000.00
3 Urug Sirtu Peninggian Bangunan 75.00 M3 Rp 177,600.00 Rp 13,320,000.00
SUBTOTAL D-I Rp 46,067,800.00

D-II PEKERJAAN BETON


1 Beton Sloof 11/20 + Besi + Begesting 1.40 M3 Rp 8,053,800.00 Rp 11,275,320.00
2 Beton Kolom Praktis 11/11 0.70 M3 Rp 9,419,500.00 Rp 6,593,650.00
3 Beton Kolom Teras 15/30 0.60 M3 Rp 9,419,500.00 Rp 5,651,700.00
4 Beton Ringbalk 11/20 1.40 M3 Rp 8,808,700.00 Rp 12,332,180.00
5 Beton Rabat Lantai Dalam Bangunan 1:3:5 tebal 5cm 4.70 M3 Rp 1,290,200.00 Rp 6,063,940.00
6 Beton Plat Kanopi Tebal 7cm atas kusen 0.30 M3 Rp 7,345,200.00 Rp 2,203,560.00
7 Beton Rabat Tepi Bangunan 1:3:5 tebal 5cm 2.00 M3 Rp 1,290,200.00 Rp 2,580,400.00
SUBTOTAL D-II Rp 46,700,750.00

D-III PEKERJAAN DINDING DAN LANTAI


1 Pas. Dinding Batako 1:4 162.00 M2 Rp 178,700.00 Rp 28,949,400.00
2 Pas. Keramik Lantai 40x40 83.00 M2 Rp 344,700.00 Rp 28,610,100.00
3 Pas. Keramik Lantai KM/WC 20x20 3.60 M2 Rp 348,800.00 Rp 1,255,680.00
4 Pas. Keramik Dinding KM/WC 20x25 11.70 M2 Rp 388,100.00 Rp 4,540,770.00
5 Plesteran Dinding 1:6 + Acian Dinding 325.40 M2 Rp 89,300.00 Rp 29,058,220.00
SUBTOTAL D-III Rp 92,414,170.00
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
PEKERJAAN
D-IV PEKERJAAN KUSEN PINTU DAN JENDELA + PENGGANTUNG
1 Pas. Kusen Pintu Bengkirai 5/10 0.10 M3 Rp 13,581,500.00 Rp 1,358,150.00
2 Pas. Daun Pintu Bengkirai 7.20 M2 Rp 1,081,500.00 Rp 7,786,800.00
3 Pas. Engsel Pintu 15.00 Bh Rp 90,300.00 Rp 1,354,500.00
4 Pas. Kunci Tanam Biasa + Handle Pintu 5.00 Bh Rp 498,800.00 Rp 2,494,000.00
5 Pas. Kusen Jendela Bengkirai 5/10 + Boven KM/WC 0.30 M3 Rp 13,581,500.00 Rp 4,074,450.00
6 Pas. Daun Jendela Rangka Kaca 9.60 M2 Rp 1,081,500.00 Rp 10,382,400.00
7 Pas. Kait Angin Jendela 24.00 Bh Rp 61,500.00 Rp 1,476,000.00
8 Pas. Grendel Jendela 12.00 Bh Rp 61,500.00 Rp 738,000.00
9 Pas. Kaca Bening tebal 5 mm 4.80 M2 Rp 222,500.00 Rp 1,068,000.00
10 Pas. Jalusi kusen, kayu bengkirai 4.40 M2 Rp 1,034,600.00 Rp 4,552,240.00
SUBTOTAL D-IV Rp 35,284,540.00

D-V PEKERJAAN ATAP DAN PLAFOND


1 Pas. Kuda-Kuda Kayu Bengkirai 5/10 0.50 M3 Rp 11,646,000.00 Rp 5,823,000.00
2 Pas. Gording Bengkirai 5/10 1.00 M3 Rp 10,371,800.00 Rp 10,371,800.00
3 Pas. Atap Seng Soka 142.00 M2 Rp 143,200.00 Rp 20,334,400.00
4 Pas. Nok / Bubungan Soka 11.70 M1 Rp 81,800.00 Rp 957,060.00
5 Pas. Lisplang Meranti 2/30 46.90 M1 Rp 81,500.00 Rp 3,822,350.00
6 Pas. Rangka Plafond Meranti 5/5 133.00 M2 Rp 148,900.00 Rp 19,803,700.00
7 Pas. Plafond GRC 4 mm 133.00 M2 Rp 120,200.00 Rp 15,986,600.00
8 Pas. List Plafond Kayu 1/4 213.00 M1 Rp 30,500.00 Rp 6,496,500.00
SUBTOTAL D-V Rp 83,595,410.00

D-VI PEKERJAAN ELEKTRIKAL


1 Pas. Titik Lampu 8.00 Ttk Rp 206,700.00 Rp 1,653,600.00
2 Pas. Saklar Tunggal 4.00 Bh Rp 60,000.00 Rp 240,000.00
3 Pas. Saklar Ganda 1.00 Bh Rp 75,000.00 Rp 75,000.00
4 Pas. Stop Kontak 8.00 Ttk Rp 75,000.00 Rp 600,000.00
5 Pas. MCB 1 Phasa 1.00 Ttk Rp 85,000.00 Rp 85,000.00
6 Pas. Lampu TL 20 Watt 8.00 Bh Rp 175,000.00 Rp 1,400,000.00
SUBTOTAL D-VI Rp 4,053,600.00

D-VII PEKERJAAN SANITASI


1 Pas. Kloset Jongkok 2.00 Bh Rp 1,213,700.00 Rp 2,427,400.00
2 Pas. Pipa PVC 4" AW 8.00 M1 Rp 110,900.00 Rp 887,200.00
3 Pas. Pipa PVC 2" AW 12.00 M1 Rp 63,100.00 Rp 757,200.00
4 Pas. Pipa PVC 1/2" AW 24.00 M1 Rp 29,500.00 Rp 708,000.00
5 Pas. Kran air 1/2" 2.00 Bh Rp 138,200.00 Rp 276,400.00
6 Pas. Floor Drain (Ovur) 2.00 Bh Rp 160,700.00 Rp 321,400.00
7 Pas. Septictank Beton + Plat Penutup Beton 10cm 1.00 Unt Rp 10,085,700.00 Rp 10,085,700.00
SUBTOTAL D-VII Rp 15,463,300.00

D-VIII PEKERJAAN PENGECATAN


1 Pek. Cat Dinding dan Kolom Pilar Teras 325.40 M2 Rp 64,000.00 Rp 20,825,600.00
2 Pek. Cat Plafond 133.00 M2 Rp 64,000.00 Rp 8,512,000.00
3 Pek. Cat Lisplang 21.00 M2 Rp 82,100.00 Rp 1,724,100.00
4 Pek. Cat Kusen + Daun Pintu dan Jendela 14.00 M2 Rp 82,100.00 Rp 1,149,400.00
SUBTOTAL D-VIII Rp 32,211,100.00
TOTAL D Rp 355,790,670.00
CV AGWINDO RAYA
GENERAL CONTRACTOR & SUPPLIER
JL. PATTIMURA RT 14 BLOK D NO 1 SAMARINDA SEBERANG , KALTIM 75134
TLP 0541.4104493 – 085247631212, Email : agwindoraya@gmail.com

REKAPITULASI
BILL OF QUANTITY (BOQ)
PROGRAM PENGELOLAAN PENDIDIKAN
PROGRAM : DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

NO. URAIAN PEKERJAAN JUMLAH HARGA

A. PEKERJAAN PERSIAPAN Rp 20,500,000.00

B. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA (SMK3) Rp 30,115,000.00

C. PEKERJAAN REHAB RUANG KELAS Rp 132,502,400.00

D. PEKERJAAN BANGUNAN RUANG GURU Rp 355,790,670.00

JUMLAH Rp 538,908,070.00

P.P.N. 10 % Rp 53,890,807.00

JUMLAH + PPN Rp 592,798,877.00

DIBULATKAN Rp 592,798,000.00

TERBILANG : LIMA RATUS SEMBILAN PULUH DUA JUTA TUJUH RATUS SEMBILAN PULUH DELAPAN RIBU RUPIAH

Samarinda, 24 Juni 2021


PENAWAR PEKERJAAN
CV. AGWINDO RAYA

Stanley Agwin Rannu


Direktur
CV AGWINDO RAYA
GENERAL CONTRACTOR & SUPPLIER
JL. PATTIMURA RT 14 BLOK D NO 1 SAMARINDA SEBERANG , KALTIM 75134
TLP 0541.4104493 – 085247631212, Email : agwindoraya@gmail.com

REKAPITULASI PERHITUNGAN TINGKAT KOMPONEN DALAM NEGERI (TKDN)

PROGRAM PENGELOLAAN PENDIDIKAN


PROGRAM :
DAK KAB. KUTAI BARAT
KEGIATAN : REHABILITASI RUANG KELAS SDN 013 BARONG TONGKOK
LOKASI : KEC. BARONG TONGKOK
T.A : 2021
SUMBER DANA : DAK KAB. KUTAI BARAT

NILAI GABUNGAN BARANG/JASA Rp 592,798,000.00


TKDN
URAIAN PEKERJAAN TOTAL
DN LN
Rp % KDN Barang/Jasa Gabungan
Barang
I. Material Langsung (Bahan Baku) 406,659,428.00 8,299,172.00 414,958,600.00 70% 68.60% 0.98%
II. Peralatan (Barang Jadi) 58,687,002.00 592,798.00 59,279,800.00 10% 9.90% 0.99%
A. Sub-Total Barang 465,346,430.00 8,891,970.00 474,238,400.00 80% 78.50% 1.97%
Jasa
III. Manajemen Proyek dan 40,310,264.00 7,113,576.00 47,423,840.00 8% 6.80% 1.20%
Perekayasaan
IV. Alat Kerja / Fasilitas Kerja 14,078,952.50 740,997.50 14,819,950.00 3% 2.38% 0.13%
V. Konstruksi dan Fabrikasi 26,409,150.90 266,759.10 26,675,910.00 5% 4.46% 0.04%
VI. Jasa Umum 28,750,703.00 889,197.00 29,639,900.00 5% 4.85% 0.15%
B. Sub-Total Jasa 109,549,070.40 9,010,529.60 118,559,600.00 20% 18.48% 1.52%
C. TOTAL Biaya (A+B) 574,895,500.40 17,902,499.60 592,798,000.00 100% 96.98% 3.49%

Capaian Nilai TKDN diatas dinyatakan sendiri oleh : Samarinda, 24 Juni 2021
PENAWAR PEKERJAAN
CV. AGWINDO RAYA

Stanley Agwin Rannu


Direktur