MEMORANDUM
I. Contractual Data:
II. Justification
The contractor requested for Contract Time Extension No. 1 due to unworkable days
caused by the inclement weather condition on site and the issuance of Work
Suspension Order No. 1 by reason of inability to secure the following permits and
clearances of the project, to wit:
Page 2 of 3
E. Recommendation
In view of the foregoing, we are recommending for the approval of Contract Time
Extension No. 1 due to the above-cited reasons, thereby adjusting the contract
duration from Seven Hundred Twenty (720) Calendar Days to Eight Hundred Forty-
Nine (849) and revising target completion date from August 17, 2021 to December
13, 2023.
Prepared by:
Reviewed by:
Page 3 of 3
Checked by:
Recommending Approval:
Approved by: