Professional Documents
Culture Documents
Cost Management Problems B 2
Cost Management Problems B 2
1) From the following information you are required to show the overhead cost per unit under Activity Based Costin
A 5000 20,000
B 60,000 120,000
You are required to calculate the cost per unit of each product A and B based on
a) Traditional method of charging overheads using machine hour rate method
b) Activity based costing method.
Total Overheads
Machine hour rate =
Total Machine hours
3) XYZ Limited manufactures three products A, B and C. the following table includes information relating to the ma
A 6000 15
B 8500 24
C 4800 18
The draft production overhead budget for next year contains the following departmental budgets:
Machines Oriented Overheads 16500
Setup costs 38920
Material ordering 24630
Material Handling 32480
The budget absorbs these overheads into production using a budgeted machine hour rate method.
However it has been proposed that the overhead budget be recalculate using activity based costing. The following
a) Calculate the production overhead budget per product using traditional costing system.
b) Recalculate the production overhead budget per product using activity based costing, tracing
c) Comment briefly on the differences disclosed between overheads traced by the present syste
Total Overheads
Machine hour rate =
Total Machine hours
4) PQ Limited manufactures four products A, B,C and D using the same plant and process. The following informatio
Product Budgeted Output (Units) Material Cost Per unit (Rs)
A 500 3
B 5000 5
C 600 16
D 7000 7
The draft production overhead budget for next year contains the following departmental budgets:
Machines Oriented Overheads 37,425
Setup costs 4355
Material ordering 1920
Material Handling 7580
Administration for spare parts 8600
These overheads costas are absorbed by products on a machine hour rate method
However it has been proposed that the overhead budget be recalculate using activity based costing. The following
a) Calculate the production overhead budget per product using traditional costing system.
b) Recalculate the production overhead budget per product using activity based costing, tracing
c) Comment briefly on the differences disclosed between overheads traced by the present syste
Total Overheads
Machine hour rate =
Total Machine hours
5) A company currently manufacture and sold four products. The details of the four products and relevant informatio
Product A B
Output in units 120 100
Cost per unit:
Direct materials 40 50
Direct labour 28 21
Machine hours (per unit) 4 3
The four products are similar and are usually produced in production runs of 20 units and sold in batches of 10 u
The production overheads is currently absorbed by using a machine hour rate, and the total of the production over
Machine department costs 10,430
Production costs 5,250
Stores receiving cost 3,600
Inspection and quality control costs 2,100
Material handling and dispatch 4,620
You have ascertained the cost drivers to be used are as listed below for the overheads shown:
Cost Cost Drivers
Production costs No. of production runs
Stores receiving Requisition raised
Inspection of quality control No. of production runs
Material handling and dispatch Orders executed
The number of requisitions raised on the stores was 20 per each product and the number of order executed wa
Total Overheads
Machine hour rate =
Total Machine hours
Product A 120 * 4
Product B 100 * 3
Product C 80 * 2
Product D 120 * 3
Total
Production cost
b) Production cost =
No. of production runs
6) A company currently manufacture and sold four products. The details of the four products and relevant informatio
Product A B
Output in units 720 600
Cost per unit:
Direct materials 42 45
Direct labour 10 9
Machine hours (per unit) 4 3
The four products are similar and are usually produced in production runs of 24 units and sold in batches of 12 u
The production overheads is currently absorbed by using a machine hour rate, and the total of the production over
Machine department costs 63,000
Setup cost 20,000
Stores receiving cost 15,000
Inspection and quality control costs 10,000
Material handling and dispatch 2,592
You have ascertained the cost drivers to be used are as listed below for the overheads shown:
Cost Cost Drivers
Setup cost No. of production runs
Stores receiving Requisition raised
Inspection of quality control No. of production runs
Material handling and dispatch Orders executed
The number of requisitions raised on the stores was 50 per each product and the number of order executed was
Machine department cost has to be apportioned between setup cost, stores receiving and inspection activity in 4:3
Total Overheads
Machine hour rate =
Total Machine hours
Product A 720 * 4
Product B 600 * 3
Product C 480 * 2
Product D 504 * 1
Total
Setup cost
a) Setup cost =
No. of production runs
7) Uma Limited makes 3 products using broadly the same production methods and equipment for each
A conventional product costing system is used at present although activity based costing system is being considere
Following activity volume are associated with the product line for the period as a whole
No of movement of
Product No of set ups
materials
P 75 12
Q 115 21
R 480 87
Total 670 120
Calculate CPU according to ABC and Traditional costing method
Calculation of Overheads
Setup cost
a) Setup cost =
No of setups
Inspection cost
d) Cost relating to Inspection =
No of Inspections
8) The following particulars are extracted from the books of a manufacturing company Limited. Calculate overhead
Total Overheads
Machine hour rate =
Total Machine hours
Product A 1500 * 2
Product B 15000 * 2
Total
8) A company currently manufacture and sold four products. The details of the four products and relevant informatio
Product A B
Output in units 240 200
Cost per unit:
Direct materials 80 100
Direct labour 56 42
Machine hours (per unit) 4 3
The four products are similar and are usually produced in production runs of 40 units and sold in batches of 10 u
The production overheads is currently absorbed by using a machine hour rate, and the total of the production over
Machine department costs 20,860
Setup cost 10,500
Stores receiving cost 7,200
Inspection and quality control costs 4,200
Material handling and dispatch 9,240
You have ascertained the cost drivers to be used are as listed below for the overheads shown:
Cost Cost Drivers
Setup cost No. of production runs
Stores receiving Requisition raised
Inspection of quality control No. of production runs
Material handling and dispatch Orders executed
The number of requisitions raised on the stores was 40 per each product and the number of order executed was
Total Overheads
Machine hour rate =
Total Machine hours
Setup cost
b) Setup cost =
No. of production runs
10) A company manufactures three products and the details are as follows.
The breakups of the overheads based on the activities are given below
Total Overheads
Labour hour rate =
Total labour hours
Setup cost
a) Setup cost =
No of Machine setups
Machine expenses
d) Machine Expenses =
No of Machine hrs
Material Receipts
e) Material Receipts =
No of Material Receipts
Total
---
---
22,000
240
100
120000
Rs 500 per
purchase order
80 + 160
210000
Rs 2100 per setup
40 + 60
Total no. of purchase orders Total no. of setups
160 20
384 44
d costing. The following information has been provided for this purpose:
Product C
1200
23.32
27984
4800
5.83
16,500 16500
1500 + 2125 + 1200 4825
38,920 38,920
1+4+2 7
24630 24,630
1 + 3 +2 6
32,480 32,480
3 + 10 + 3 16
Product C
(2 * 5560) = 11120
(2 * 4105) = 8210
(3 * 2030) = 6090
29524.00
4800
6.15
d costing. The following information has been provided for this purpose:
250
1250
600
10500
12600
Product C Product D
600 10500
4.75 4.75
2850 49875
600 7000
4.75 7.125
37,425 37425
250 + 1250 + 600 + 10500 12600
4,355 4,355
1 + 6 +2 + 8 17
1920 1920
1+4+1+4 10
7580 7580
2 + 10 + 3 + 12 27
8600 8600
2+5+1+4 12
Product C Product D
1782 31185
512.34 2049.36
192 768
842.22 3368.88
716.66 2866.64
4045.22 40237.88
600 7000
6.74203333333333 5.74826857142857
30 60
14 21
2 3
sold in batches of 10 units.
al of the production overhead for the period has been analysed as follows:
heads shown:
er of order executed was 42, each order being for a batch of a product.
480
300
160
360
1300
Product C Product D
(80 * 30) = 2400 (120 * 60) = 7200
(80 * 14) = 1120 (120 * 21) = 2520
3520 9720
6720 16920
10,430 10,430
480 + 300 + 160 + 360 1300
5,250 5,250
6+5+4+6 21
3600 3600
20 + 20 + 20 + 20 80
2100 2100
6+5+4+6 21
4620 4620
12 + 10 + 8 + 12 42
Product C Product D
(80 * 30) = 2400 (120 * 60) = 7200
(80 * 14) = 1120 (120 * 21) = 2520
3520 9720
1283.2 2887.2
1000 1500
900 900
400 600
880 1320
7983.20 16927.20
40 48
7 8
2 1
sold in batches of 12 units.
al of the production overhead for the period has been analysed as follows:
of order executed was 192, each order being for a batch of 12 products.
inspection activity in 4:3:2
2880
1800
960
504
6144
Product C Product D
19200 24192
3360 4032
22,560 28,224
17280 9072
39,840 37,296
480 504
83 74
20000 + 28000 48,000
30 + 25 + 20 + 21 96
2592 2592
60 + 50 + 40 + 42 192
Product C Product D
19200 24192
3360 4032
22,560 28,224
10000 10500
9000 9000
5,000 5250
540 567
47100.00 53541.00
480 504
98.125 106.232142857143
Number of Inspection
150
180
670
1,000
1125
1250
21000
23375
229075
130900
98175
196350
654500
Product R
175000
42000
217,000
588000
805,000
7000
115
229075 229075
75 + 115 + 480 670
130900 130900
1125 + 1250 + 21000 23375
98175 98175
12 + 21 + 87 120
196350 196350
150 + 180 + 670 1000
Product R
175000
42000
217,000
164112
117600
71,177
131,555
701443.38
7000
100.206196428571
3000
30000
33000
220,000 220000
3000 + 30000 33000
200,000 200,000
40 + 60 100
240,000 240,000
80 + 160 240
and relevant information are given below for a period:
C D
160 240
60 120
28 42
2 3
of order executed was 84, each order being for a batch of 10 products.
Product C Product D
9600 28800
4480 10080
14,080 38,880
6400 14400
20,480 53,280
160 240
128 222
20,860 20,860
960 + 600 + 320 + 720 2600
10,500 10,500
6+5+4+6 21
7200 7200
40 + 40 + 40 + 40 160
4200 4200
6+5+4+6 21
9240 9240
24 + 20 + 16 + 24 84
Product C Product D
9600 28800
4480 10080
14,080 38,880
2566.4 5774.4
2000 3000
1800 1800
800 1200
1,760 2640
23006.40 53294.40
160 240
143.79 222.06
Product Z
15000000
8000000
23,000,000
1835200
24,835,200
50000
496.704
750000 750000
3000 + 5000 + 7000 15000
450000 450000
10000 + 7000 + 8000 25000
240000 240000
250 + 400 + 550 1200
1440000 1440000
50000 + 90000 + 100000 240000
240000 240000
3000 + 4200 + 4800 12000
Product Z
15000000
8000000
23,000,000
350000
144000
110000
600,000
96,000
24300000.00
50000
486
Rs. 3.42 per
Machine hr
Rs 250 per
production run
Rs 45 per
requisition raised
Rs 100 per
production run
Rs 180 per
requisition raised
Rs 250 per
production run
Rs 818.125 per
movement of
material
Rs 196.35 per
Imspection
Rs 6.67 per
Machine hrs
Rs 1000 per
purchase order
Rs 20 per Macchine
hr
Rs 8.02 per
Machine hr
Rs 500 per
production run
Rs 45 per
requisition raised
Rs 200 per
production run
Rs 18 per quality
inspection
Rs 200 per
production order
Rs 6 per Machine
hr
Rs 20 per Material
Receipt