Professional Documents
Culture Documents
Saep-387 2021
Saep-387 2021
SAEP-387
Thermoplastic Liners for New and Existing Pipelines
Document Responsibility: Nonmetallic Standards Committee
Contents
SUMMARY OF CHANGES.................................................................................................................... 3
I SCOPE .............................................................................................................................................. 5
DOCUMENT HISTORY........................................................................................................................ 26
Summary of Changes
Paragraph Number
Change Type Technical Change(s)
(Addition, Modification, Deletion,
Previous Revision Current Revision New)
(22 January 2019) (02 June 2021)
I Scope
This document establishes the minimum technical requirements for the material
selection, specification, design, manufacture, installation, and operation of
thermoplastic internal liners. This procedure is an addendum to all parts of
NACE SP0304:2004 which covers Thermoplastic Liners for Oilfield Pipelines to
be used in pressurized systems as listed in SAES-L-132.
The use of these internal liners is for rehabilitating existing carbon steel
pipelines and flowlines as well as for new pipelines and flowlines. Lining with
thermoplastic material is applicable to aboveground, buried and sub-sea
pipelines.
Internally lined piping systems for transporting corrosive fluids including acids
and alkaline solutions are the scope of 01-SAMSS-025 Plastic-lined Ferrous
Metal Pipe, Fittings and Flanges.
Any deviation from the requirements herein shall follow internal company
procedure SAEP-302.
III References
All referenced specifications, standards, codes, drawings, and similar material
are considered part of this engineering procedure to the extent specified,
applying the latest version, unless otherwise stated.
Section 2: Definitions
[Addition]
Batch: A lot supplied by the compound manufacturer having an
individual identification number or code.
SDR: Standard Dimension Ratio; Nominal outside diameter of liner /
Nominal wall thickness
CRA: Corrosion Resistant Alloy
ID: Nominal internal diameter
OD: Nominal outside diameter
UV: Ultra violet light
Liner installer: The party that conduct all or part of the project design,
engineering, liner procurement, construction, commissioning, or
management of a project.
Bell hole: Excavations made at a section joints of a pipeline for the
purpose of pulling of a thermoplastic liner section.
Butt fusion welding: A method of joining plastic pipe wherein the two
ends to be joined are heated to the molten state for a period of time
under pressure. After the cooling period, the joint exhibits strength
either similar/higher than the pipe.
End connector: A device used to provide a leak-tight structural
connection between two sections of lined pipe. The lining is terminated
inside the end connector.
Inspector: Professional assigned to ensure a project's compliance
with its specifications and statutory requirements.
Ovality: Ovality is the deviation from roundness as a result of
extrusion, coiling, handling, or installation.
Permeation: Diffusion of liquid and gas through a plastic layer under
the influence of pressure and temperature. Permeation is a
physiochemical mass transfer phenomenon involving diffusion of a
solute through a porous medium. The driving force for mass transfer
is the presence of an activity (e.g., concentration) gradient with respect
to the solute.
Smooth wall liner: Liner that is manufactured with a uniform wall
cross section with no grooves.
Grooved liner: Liner that is manufactured with grooves on the outside
surface. Grooves shall be uniform and the minimum wall thickness will
not consider the depth of the groove.
from water, or at very low levels, and within its limited maximum
operating temperatures.
Liner manufacturers shall submit the relevant PA (minimum) material
specification at the specified operating conditions. This procedure
shall comply with the requirements of ASTM D4066 and/or ASTM
F1733 or equivalent ISO Standard.
3.11 [Addition] Liner material
Polyethylene Raised Temperature (PE-RT)
Polyethylene raised temperature (PE-RT) shall be used as a base case
liner material for water injection and disposal lines when the design
temperature of the thermoplastic lined pipe exceeds 70ºC (158ºF) and
up to maximum operating temperature 82ºC (180ºF).
PE-RT resin shall be type II per ISO 24033 and/or ISO 22391-2 or
equivalent ASTM standard. The mechanical and physical test reports
as per ISO 22391-2 shall be submitted.
Liner manufacturer selected by the liner installer shall perform fitness
for purpose 1,000 hr. internal pressure test for pipe + butt-welded joint
specimens at 95°C (203ºF) and a pressure corresponding to a
hydrostatic hoop stress of 3.6 MPa. At least 3 specimens shall be
submitted. Minimum size for initial approval shall be 200 mm (8”). For
approval of additional sizes, 165 hr. pressure tests are acceptable
following the same parameters as above.
3.12 [Addition] Liner material
Polyvinylidene Fluoride (PVDF)
For liner applications, unplasticized PVDF copolymer based on
vinylidene fluoride (VF2) and chlorotrifluoroethylene (CTFE) shall be
used in water and hydrocarbon applications. Other grades of
copolymer or unplasticized PVDF shall be assessed by the CSD Non-
metallic Engineering Group before acceptance.
Manufacturers shall submit the relevant PVDF (minimum) material
specification at the specified operating conditions. This procedure
shall comply with the requirements of ASTM F491 or equivalent ISO
standards.
3.13 [Addition] Liner material
Table 1 lists recommended maximum operating temperature for the
use of thermoplastic liner as a function of fluid composition. However,
unless otherwise specified in SAES-L-132, the maximum operating
temperature and intended application shall be specified and agreed
with the CSD
PE-RT 180ºF (82ºC)-Base Case 180ºF (82ºC) 180ºF (82ºC) Not Applicable
4 Liner design
4.1 (d) [Addition]
Pressure cycles are permitted if they are within the pressure surge
allowance (e.g., surge stem from valve and pump shut on/of).
Conversely, lining shall not be utilized in applications that will include
continuous pressure cycling while utilizing duplex and multiplex
pumps.
4.1 (f) [Addition]
When using thermoplastic liner for pipeline rehabilitation applications,
the damaged steel pipes shall be repaired for any leaks or metal loss
and they shall pass the hydrostatic pressure testing as specified in 6.3.
4.1 (j) [Addition]
If the pipeline requires scraping facility as per SAES-L-410, it shall be
noted that the utilization of any scraping (e.g., foam pig) or inspection
tool (e.g., modified MFL) shall be reviewed by the liner installer. Scraping
procedure shall also strictly adhere to the liner installer recommendation.
4.5 [Modification]
The design of liner system shall be carried out by the liner installer for
the approved engineering contractor.
5 Liner design aspects
5.1.2 [Modification]
This procedure shall be limited to tight fit liners only. Loose fit, neutral,
and perforated liners are not allowed.
5.6 [Addition] Vent point and venting
For grooved liner pipelines, the vent point shall include a valve to allow
open / close of the vent. The design of the vent point assembly shall be
proposed by the liner installer. The minimum number of vent points shall
be one at each flanged end of a section of lined pipe. Venting can be
operated by installing valve to be closed or opened during normal
operation. Venting can also be used to monitor the integrity of the liner.
Pressure gauges needs to be installed to monitor the pressure inside
the annulus.
When checking the vents for pressure or bleeding-off the pressure,
they shall be dealt with in the same manner as breaking the integrity of
any system:
• 2 operators are required;
• 1 safety person;
• Self-contained breathing apparatus shall be worn by worker
performing task;
• Safety person shall be upwind and a safe distance away;
• Record the vent pressure on the venting log sheet;
• Annular pressure needs to be kept below 50 psig (3.4 barg)
at all times;
• Vents are to be left in the closed position at all times;
Note:
Venting procedure provided by the liner installer shall be strictly complied.
For smooth liner pipelines in non-sour service, such as water injection
lines, the vent point shall be plugged. venting during operation are
normally plugged.
Lined pipelines in sour service, such as sour water disposal and multi-
phase hydrocarbons with H2S, shall have a system to transport the
permeated gas to the bore.
5.7 [Addition] Spacing between vent points
Vent/passive re-injection point is usually installed at each flanged end
particularly for water service, stabilized crude oil and oil/water mixture.
Flangeless connections can be designed with or without vent points.
For critical applications such as multiphase system, gas and
unstabilized crude oil additional vents shall be needed. The liner
installer is responsible for determining the spacing between the vent
points.
The steel contractor shall install weld O’let fittings a maximum of 75 –
100 mm (3” – 4”) distance from flange weld to serve as part of the liner
vent piping system. The weld O’let shall be installed to each flange
end, at the 12 o’clock position. Following the installation of the vent
weld O’let on the pipe, drilling out of the vent hole shall be performed
by the steel contractor at the size of maximum 3.2 mm (⅛ in). Vent
tubing shall be connected with the host pipe by utilizing a thread-o-let
connection and it shall be inspected through a non-destructive testing
before the insertion of the liner as per the liner installer recommended
procedure.
The vent tubing shall include a pressure gauge able to read from a
minimum of 3.4 barg (50 psig) to the maximum allowable operating
pressure of the lined pipe.
Liner installer shall determine the length of the pipeline and the number
of vent tubing that can be connected using a jumper before connecting
with a passive re-injection system or to an exit to the atmosphere.
Grooved liner requires to incorporate steel screen mesh to prevent any
extrusion of the liner through the vent hole.
5.8 [Addition] Other design aspects
Routing of the pipeline shall be properly studied in the design phase to
incorporate long radius bends to allow for longer length pull. If flanged
system is used, routing optimization study will aid in reducing number
of flanges.
5.9 [Addition] Design of end connectors
In general, flanged connections are considered for termination at the
ends of pipeline sections. The thermoplastic stub-ends shall be made
from the same material as the liner and have the same internal
diameter as the liner.
provide the plate size and the gauge running procedure prior to
installation.
• In case a gauging plate cannot be passed through (e.g., cement
lined pipe), a short section of liner can be pulled through the host
steel/carrier pipe to assess the internal condition of the pipeline.
Damage extending deeper than 10% of the liner nominal wall
thickness shall not be allowed for lining activity.
• Locations for cutting and flanging of the line and any requirement for
separate spooled sections needs to be determined. The longest
continuous length of liner which can be installed in straight pipe
depends on diameter and wall thickness, but is generally reduced in
practice by local curvature of the line. Breaks are also required at
road crossings, changes in ID and any bends of radius less than 20D
(recommended minimum bend where possible is 40D).
• Flanges welded to the steel pipeline requires to have a matching
bore and with a minimum internal radius which is required to
provide a smooth interface between CS flange and the HDPE stub-
end to avoid any sharp corners touching the HDPE. Roto-lined
reducers are recommended in case of lining telescopic carbon steel
lines.
Figure 1 - Typical flange configuration for pipe liner [Ref. CSA Z662]
− At the end of the hydrotest the vents shall all remain closed
After the hydrotest and until the lining being implemented, the
following shall be met:
− The pipeline shall be left cleaned, dried properly after
hydrotest and ensure flange ends protected from entering
to any sand, dust/ingress while preventing any microbial
corrosion situation.
− If the lining will not be conducted in short time after
hydrotesting, the pipeline shall always be kept dried
utilizing the liner installer recommended practice.
− Ensure that pipe ends are protected against the foreign
particles intrusion until the liner insertion.
Note:
It is prudent that the steel pipeline requires to be lined within short period of time after the
hydrotesting and the liner installer shall develop an implementation plan accordingly.
7 Liner operation
7.4 [Addition] Liner operation
An operational procedure shall be developed for all lined pipelines and
flowlines. This procedure shall as a minimum address the following
aspects:
• Operating envelope
• Venting
• Pigging
• Start-up procedure
• Routine operations
• De-pressurizing
If toxic gases (e.g., H2S) are present in the vent tubing and cannot be
re-injected back to the bore, it shall be cleaned with supervision of the
liner installer while following the liner installer recommended practice
and adhering to the requirements stated in section 5.6.
After the start-up, the lined pipeline shall be monitored for any leakage
while the vent tubing shall be checked for any pressure build-up at a
regular interval. Monitoring frequency shall be adjusted based on the
built-up pressure in the annulus. Vent shall not be opened if the lined
pipeline annulus pressure exceeds the bore pressure. Vent tubing shall
be checked for blockage at a regular interval.
V. Documentation [Addition]
• Location of any valves and fittings (e.g., tees) installed in the pipeline.
• Condition of internal surface of the carbon steel pipeline (new/used,
roughness, penetration of welds, etc.)
• Fluid composition (incl. inhibitors, chemicals, etc.).
• Expected minimum/maximum ambient temperatures during installation.
• Minimum/maximum operating temperature of the system.
• Maximum design temperature.
• Minimum/maximum operating pressure of the system.
• Maximum rate of de-pressurization of the system.
• Indication of likelihood of large pressure fluctuations (surge, water
hammer)
• Preferred type of liner material and thickness (if known).
• Possibility and frequency of local venting. If nothing is specified it can be
assumed that the venting frequency is once per one to three months.
• Requirements for valves at gas venting points, requirements for gas
monitoring, limitations on gas venting rates and any restrictions on venting
locations.
• Design life.
The manufacturer shall maintain a quality manual which describes the quality
program. All prior revisions shall be retained for a period of not less than five
years.
For HDPE material, the liner manufacturer shall comply with the Quality Control
(QC) test requirements specified in Section 5 of 01-SAMSS-051. For any other
materials, e.g., PE-RT, PA, PVDF, liner manufacturer shall submit a copy of their
quality assurance plan to the CSD Non-metallic Engineering Group for review.
Shop fabricated joints shall be part of this quality plan and any relevant
imperfections observed, e.g., weld defects, scratches, and notches in the welded
joints, shall result in rejection of the welded pipe.
The liner installer shall submit a quality test plan for fittings, stub-end, vent piping,
and steel mesh screen, if used, in compliance with this procedure requirement.
Drawings that showing dimensions and tolerances, for stub-end, lined pipe
connection, passive re-injection system shall be submitted for approval to the
Buyer’s Representative. The drawing shall show the fittings pressure rating and
the parent pipes SDR value.
Straight lengths liner shall be stored on horizontal racks and given support to
prevent damage. Coils shall be stored stacked flat one on top of another.
Covers shall be used to prevent ingress of moisture or dirt inside the grooves of
the liner.
Document History
02 June 2021 Major revision.
22 January 2019 Editorial revision.
26 April 2018 Merger of 01-SAMSS-050 and SAEP-387 and overlaying with NACE RP0304.