DAILY PROGRESS REPORT

Project : Geotechnical Drilling at PT Freeport Indonesia Levee Project


Date Thursday, February 16, 2017
Project Number : 168712011
Location : Timika, Papua, Indonesia Weather Morning : Sunny
Area : Old west levee area Day : Sunny
Client : PT Freeport Indonesia Afternoon : Sunny
Consultant : PT Geotechnical & Environmental Services Indonesia (Golder Associates)
Contractor drilling : PT. KPPN
HEALTH SAFETY AND ENVIRONMENT
Personnel in Work Equipment Number Incidents/Injuries Today To Date Briefing/Meeting/Drills Today To Date
Project Manager 0 Drilling Rig 2 Fatality 0 0 Kick off meeting
Field Engineer and FI Staff 2 LV 2 Days Away from Work 0 0 Toolbox Meetings 2 231
Drilling Team 11 Nearmiss 0 0 Safety Inspection 2
Driver 1 First Aid 0 0 Safety audit (Conduct by PM)
Total 14 Total 4 Total 0 0 Total 2 233
Man Hours (Personnel x Man Hours Total To
140 16090
Hour) Date
HSE NOTES & ISSUES
No safety issue reported

PROGRESS RECORD
ON PROGRESS
NO WORK ITEM Plan depth Volume REMARKS

Geotechnical Drilling Borehole ID meter progress depth SPT UDS VS %

1 RIG 1 BH-WMA20-000 25.00 25.00 8 8 100% Completed


2 RIG 2 BH-WMA35-120 25.00 0% Moving and Setup Rig

Total 25.00 8 8 0
COMPLETED
Stecking Out (Handheld GPS) Actual Samples
NO AREA BOREHOLE ID Date Started Date Completed
Easting Northing Elevation Depth SPT UDS VS UCS
1 BH-WMA040-000 714254 9467278 8 25.00 25-Jun-16 29-Jun-16 7 9 - -
2 West - Southern Levee Extensions BH-WMA035-1139 711747 9465525 9 25.00 30-Jun-16 2-Jul-16 11 5 - -
3 BH-WMA020-000 710826 9464374 9 25.00 3-Jul-16 5-Jul-16 10 6 - -
4 BH-WOTN4-386 710244 9512755 129 30.00 7-Jul-16 29-Jul-16 7 - - -
5 BH-WOTN5-317 710131 9512029 104 30.00 30-Jul-16 17-Aug-16 5 - - -
Old West Levee
6 BH-WMA265-926 710667 9508485 72 30.00 18-Aug-16 30-Aug-16 5 - - -
7 BH-WMA255-314 710655 9507498 75 30.00 31-Aug-16 17-Sep-16 8 - - -
8 BH-EMA045-075 721508 9468217 3 25.00 19-Sep-16 26-Sep-16 5 10 5 -
9 East - Southern Levee Extensions BH-EMA030-000 722069 9465304 14 25.00 27-Sep-16 1-Oct-16 12 4 - -
10 BH-EMA020-075 721205 9463075 13 25.00 2-Oct-16 6-Oct-16 9 6 - -
11 A BH-EMA145-000-S 717351 9487759 24 11.00 11-Oct-16 19-Oct-16 - - - -
East Levee (Seepage)
11 B BH-EMA145-000-SR 717340 9487776 21 14.90 20-Oct-16 28-Oct-16 20 7 - -
12 BH-EMA95-000-U 721238 9477112 22 15.20 31-Oct-16 3-Nov-16 12 11 - -
13 BH-EMA60-000-U 721756 9471365 13 15.25 4-Nov-16 7-Nov-16 13 13 - -
14 East Levee (Upstream) BH-EMA50-000-U 721461 9469364 19 15.20 9-Nov-16 17-Nov-16 16 14 - -
15 BH-EMA65-000-U 721879 9472176 9 15.20 19-Nov-16 21-Nov-16 16 12 - -
16 BH-EMA80-000-U 722171 9474899 12 15.20 22-Nov-16 25-Nov-16 16 13 - -
17 BH-WMA120-000-U 715995 9482597 14 15.35 26-Nov-16 7-Dec-16 13 15 - -
18 BH-WMA50-000-U 715935 9469249 16 15.00 9-Dec-16 14-Dec-16 13 15 - -
19A West Levee (Upstream) BH-WMA125-000-U 715837 9483585 13 8.90 15-Dec-16 17-Dec-16 5 7 - -
19B BH-WMA125-000-UR 715829 9483609 31 15.30 19-Dec-16 24-Dec-16 13 9 - -
20 BH-WMA105-000-U 715773 9479125 25 15.35 26-Dec-16 30-Dec-16 13 12 - -
21 BH-WMA190-76 711307 9495143 34 25.00 6-Jan-17 19-Jan-17 14 - - -
22 BH-WMA195-0 711100 9496611 64 25.00 8-Jan-17 30-Jan-17 16 - - -
Old West Levee
23 BH-WMA175-540 711375 9491775 27 25.24 20-Jan-17 8-Feb-17 15 - - -
24 BH-WMA165-600 712320 9489670 12 25.00 31-Jan-17 8-Feb-17 15 1 - -
25 BH-WOTN6-0 712860 9511699 13 10.15 9-Feb-17 10-Feb-17 1 - - -
WL Northern Extension
26 BH-WOTN7-600 712040 9510554 65 10.00 9-Feb-17 15-Feb-17 5 - - -
27 West - Southern Levee Extensions BH-WMA20-000 709782 9462966 10 25.00 11-Feb-17 16-Feb-17 8 8 - -

Total 491.85 303 177 5


FIELD ACTIVITY
RIG 1 (BH-WMA20-000) Engineer : RHT
Time (Hours) Activity Planning For Next Day
07:00 - 08:30 WIT Travel from camp to location of drilling 1. Move Rig, accessories and equipment to BH-WMA18-
08:30 - 09:00 WIT Toolbox meeting and drilling preparation 430
09:00 - 13:30 WIT Continue drilling from 21.50-25.00 m depth (End Of Hole) 2. Setting Rig, accessories and water supply
13:30 - 16:30 WIT Pull out HQ casing, Rig down and preparation for moving Rig
16:30 - 18:00 WIT Housekeeping and back to camp
RIG 2 (BH-WMA35-120) Engineer : Agung (Freeport staff) & RHT
Time (Hours) Planning For Next Day
07:00 - 08:00 WIT Travel from camp to location of drilling 1. Setting accessories Rig and water supply
08:00 - 08:30 WIT Toolbox meeting 2. Start drilling at BH-WMA35-120
08:30 - 10:30 WIT Waiting crane truck for moving Rig, accessories and equipment
10:30 - 12:15 WIT Loading Rig, accessories and equipment onto crane truck
12:15 - 14:15 WIT Moving Rig, accessories and equipment from BH-WOTN7-600 (WL Northern Extension) to BH-WMA35-120 (WL
Southern Extension)
14:15 - 16:30 WIT Unloading Rig, accessories and equipment - Setting Rig
16:30 - 18:00 WIT Housekeeping and back to camp

Figure 1. Check water level at BH-WMA20-000 (Rig 1) Figure 2. Corebox sample at BH-WMA20-000 from 19.50-25.00 m depth_EOH (Rig 1)

Figure 3. Preparation for moving Rig (Rig 1) Figure 4. Loading Rig at BH-WOTN7-600 (Rig 2)

Figure 5. Unloading Rig and accessories at BH-WMA35-120 (Rig 2) Figure 6. Rig up at BH-WMA35-120 (Rig 2)
SITE PLAN

Old West Levee

WL Northern Levee Extension

Seepage - East Levee

Upstream - West Levee

Upstream - East Levee

West Levee Southern


Extension

East Levee Southern


Extension

GEOTECHNICAL INVESTIGATION NOTES & ISSUES

Reported by: Acknowledge by:


Golder Associates Freeport Indonesia

Roma Hablim Tanjung Aditya Putra


Field Engineer Client Representative