Maga Engineering (pvt) ltd.

Central Work Shop Homagama


Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/06 Period : June 2022


Project : Ruwanpura Expressway Project - Concrete Batching Plant - Horana

THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER
UTILIZATION AMOUNT (RS)
UTILIZATION UNIT (RS)

1 MGEN0098 MGE-98 Generator 300 KVA DRY Hrs - 108.00 1,050.00 113,400.00
2 MGEN0166 MGE-166 Generator 220 KVA DRY Hrs - 108.00 850.00 91,800.00
3 MTMX0069 LH-9949 Con.Truck Mixture 2.5 m3 DRY m3 - 500.00 385.00 192,500.00
4 MTMX0098 LK-7815 Con.Truck Mixture 2.5 m3 DRY m3 - 500.00 385.00 192,500.00
5 MTMX0099 LK-7940 Con.Truck Mixture 5.0 m3 DRY m3 - 500.00 715.00 357,500.00
Total (G) 947,700.00

AGREED CONTRACT SUM AFTER DISCOUNT


A PACKAGE -01 10,791,984,006.29 B/E = F 0.2321
B PACKAGE -02 10,577,490,431.61 Cost of idling of Machineries (G x F) 219,961.17
C PACKAGE -03 11,326,279,872.70
D PACKAGE -04 12,883,548,674.60
E TOTAL AMOUNT 45,579,302,985.20
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/02 Period : July 2022


Project : Ruwanpura Expressway Project - Coordinating Office
THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER UNIT
UTILIZATION AMOUNT (RS)
UTILIZATION (RS)
1 MACM0044 MAC-44 Air Compressor 185 CMF DRY Hrs - 81.00 660.00 53,460.00
2 MACM0062 MAC-62 Air Compressor 655 CMF DRY Hrs - 81.00 2,200.00 178,200.00
3 MACM0087 MAC-87 Air Compressor 655 CMF DRY Hrs - 81.00 2,200.00 178,200.00
4 MACM0144 MAC-144 Air Compressor 185 CMF DRY Hrs - 81.00 660.00 53,460.00
5 MACM0147 MAC-147 Air Compressor 185 CMF DRY Hrs - 81.00 660.00 53,460.00
6 MAPC0045 MAPC-45 Asphalt Cutter - DRY Day - 27.00 300.00 8,100.00
Machin
7 MBBE0026 MBB-26 Bar Bender - DRY Ton - 16.00 550.00 8,800.00
8 MBBE0041 MBB-41 Bar Bender - DRY Ton - 16.00 550.00 8,800.00
9 MBBE0058 MBB-58 Bar Bender - DRY Ton - 16.00 550.00 8,800.00
10 MBBE0090 MBB-90 Bar Bender - DRY Ton - 16.00 550.00 8,800.00
11 MBBE0098 MBB-98 Bar Bender - DRY Ton - 16.00 550.00 8,800.00
12 MBCU0042 MBC-42 Bar Cutter - DRY Ton - 16.00 550.00 8,800.00
13 MBDS0002 LJ-0357 Diesel Bowser 6,600 Ltr DRY Month 1.00 1.00 137,500.00 137,500.00
14 MBDS0004 LK-3522 Diesel Bowser 6,600 Ltr DRY Month 1.00 1.00 137,500.00 137,500.00
15 MBWT0005 MBW-05/LI-2964 Water Bowser 14,000 Ltr DRY Hrs - 108.00 300.00 32,400.00
16 MCCR0011 MC/C-11 Crane- Crawler 75 T DRY Hrs - 162.00 7,150.00 1,158,300.00
17 MCHM0005 MCH-05 Mobile Crane 20 T DRY Hrs - 108.00 2,450.00 264,600.00
18 MCHM0015 MCH-15/ZA- Crane-Rough Terrain 25 T DRY Hrs 19.60 108.00 3,300.00 356,400.00
2883
19 MCHM0018 MC/H-18 ZA- Mobile Crane 55 T DRY Hrs - 108.00 5,500.00 594,000.00
3625
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/02 Period : July 2022


Project : Ruwanpura Expressway Project - Coordinating Office
THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER UNIT
UTILIZATION AMOUNT (RS)
UTILIZATION (RS)
20 MCMX0182 MCM-182 Concrete Mixer 02 Bag DRY Day - 27.00 1,100.00 29,700.00
21 MCMX0295 MCM-295 Concrete Mixer 01 Bag DRY Day - 27.00 550.00 14,850.00
22 MCMX0296 MCM-296 Concrete Mixer 01 Bag DRY Day - 27.00 550.00 14,850.00
23 MCMX0298 MCM-298 Concrete Mixer 01 Bag DRY Day - 27.00 550.00 14,850.00
24 MCMX0299 MCM-299 Concrete Mixer 01 Bag DRY Day - 27.00 550.00 14,850.00
25 MDTR0001 MDT-01 Track Drill - DRY Hrs - 108.00 4,000.00 432,000.00
26 MDTR0007 MDT-07 Track Drill - DRY Hrs - 108.00 4,000.00 432,000.00
27 MEXC0026 MEX-26/ZA-3952 Excavator - Wheel DX 140 W DRY Hrs - 108.00 2,200.00 237,600.00
28 MGEN0011 MGE-11 Generator 37 KVA DRY Hrs - 108.00 275.00 29,700.00
29 MGEN0016 MGE-16 Generator 150 KVA DRY Hrs - 108.00 660.00 71,280.00
30 MGEN0055 MGE-55 Generator 150 KVA DRY Hrs - 108.00 660.00 71,280.00
31 MGEN0068 MGE-68 Generator 150 KVA DRY Hrs - 108.00 660.00 71,280.00
32 MGEN0074 MGE-74 Generator 125 KVA DRY Hrs - 108.00 660.00 71,280.00
33 MGEN0109 MGE-109 Generator 40 KVA DRY Hrs 20.00 108.00 330.00 35,640.00
34 MGEN0139 MGE-139 Generator 31.25 KVA DRY Hrs - 108.00 330.00 35,640.00
35 MGEN0141 MGE-141 Generator 125 KVA DRY Hrs - 108.00 660.00 71,280.00
36 MGEN0145 MGE-145 Generator 25 KVA DRY Day 27.00 27.00 900.00 24,300.00
37 MGEN0199 MGE-199 Generator 12 KVA DRY Day 27.00 27.00 900.00 24,300.00
38 MGEN0204 MGE-204 Generator 25 KVA DRY Day - 27.00 900.00 24,300.00
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/02 Period : July 2022


Project : Ruwanpura Expressway Project - Coordinating
1 Office
THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER UNIT
UTILIZATION AMOUNT (RS)
UTILIZATION (RS)
39 MGEN0218 MGE-218 Generator 500 KVA DRY Hrs - 108.00 1,650.00 178,200.00
40 MJEE0044 KR-9779 Jeep - DRY Month 1.00 1.00 165,000.00 165,000.00
41 MLTW0049 MLT-49 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
42 MLTW0054 MLT-54 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
43 MLTW0061 MLT-61 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
44 MLTW0064 MLT-64 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
45 MLTW0092 MLT-92 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
46 MLTW0138 MLT-138 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
47 MLTW0151 MLT-151 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
48 MLTW0168 MLT-168 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
49 MLTW0193 MLT-193 Lighting Tower - DRY Day - 27.00 850.00 22,950.00
50 MMBI0209 BAA-7748 Motor Cycle - DRY Month 1.00 1.00 5,500.00 5,500.00
51 MMBI0294 BBO-8863 Motor Cycle - DRY Month 1.00 1.00 5,500.00 5,500.00
53 MMBI0393 BGD-9241 Motor Cycle - DRY Month 1.00 1.00 5,500.00 5,500.00
54 MMBI0519 BIY-4448 Motor Cycle - DRY Month 1.00 1.00 5,500.00 5,500.00
55 MMCA0037 KE-1227 Car - DRY Month 1.00 1.00 48,400.00 48,400.00
56 MMGR0107 MMG-107 Motor Grader 12 Feet DRY Hrs - 108.00 1,800.00 194,400.00
57 MMLD0033 MML-33 Mini Loader - DRY Hrs - 108.00 825.00 89,100.00
58 MPCO0088 MP/C-88 Plate Compactor - DRY Day - 27.00 1,100.00 29,700.00
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/02 Period : July 2022


Project : Ruwanpura Expressway Project - Coordinating Office
THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER UNIT
UTILIZATION AMOUNT (RS)
UTILIZATION (RS)
59 MPCO0097 MP/C-97 Plate Compactor - DRY Day - 27.00 1,100.00 29,700.00
60 MPGE0142 MPG-142 Portable Generator 05 KVA DRY Hrs - 108.00 165.00 17,820.00
61 MRAM0794 MR-794 Rammer - DRY Day - 27.00 1,400.00 37,800.00
62 MRAM0799 MR-799 Rammer - DRY Day - 27.00 1,400.00 37,800.00
63 MRAM1019 MR-1019 Rammer - DRY Day - 27.00 1,400.00 37,800.00
64 MRAM1020 MR-1020 Rammer - DRY Day - 27.00 1,400.00 37,800.00
65 MRAM1053 MR-1053 Rammer - DRY Day - 27.00 1,400.00 37,800.00
66 MRVI0113 MRV-113 Roller Vibrator 05T 05 T DRY Hrs - 108.00 850.00 91,800.00
67 MRVI0133 MRV-133 Roller Vibrator 01T 01 T DRY Day - 27.00 2,200.00 59,400.00
68 MRVI0236 MRV-236 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
69 MRVI0270 MRV-270 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
70 MRVI0296 MRV-296 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
71 MRVI0298 MRV-298 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
72 MRVI0299 MRV-299 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
73 MRVI0325 MRV-325 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
74 MRVI0326 MRV-326 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
75 MRVI0327 MRV-327 Roller Vibrator 01T 01 T DRY Day - 27.00 2,000.00 54,000.00
76 MRVI0329 MRV-329 Roller Vibrator 08T 08 T DRY Hrs - 108.00 1,400.00 151,200.00
77 MRVT0042 MTR-42 Roller-Pneumatic( 11 T DRY Hrs - 108.00 1,800.00 194,400.00
TYR
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/02 Period : July 2022


Project : Ruwanpura Expressway Project - Coordinating Office
THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER UNIT
UTILIZATION AMOUNT (RS)
UTILIZATION (RS)
78 MTBM0019 LL-3027 Boom Truck 05 - 10 T DRY Day 26.00 27.00 9,100.00 245,700.00
79 MTBW0043 MT/B-43/RV- Tractor Bowser 3,000 Ltr DRY Month 1.00 1.00 6,600.00 6,600.00
5989
80 MTBW0049 MT/B-49/RW- Tractor Bowser 3,000 Ltr DRY Month 1.00 1.00 6,600.00 6,600.00
0345
81 MTBW0128 MTB-128/RY Tractor Bowser 4,000 Ltr DRY Month 1.00 1.00 6,600.00 6,600.00
9949
82 MTBW0129 MTB-129/RY- Tractor Bowser 3,000 Ltr DRY Month 1.00 1.00 6,600.00 6,600.00
9952
83 MTCA0020 MTC-20/LI-7918 Cargo Truck 07 T DRY Day 18.00 27.00 8,300.00 224,100.00
84 MTCA0026 LN-0884 Cargo Truck-Self 25 T DRY Day 18.00 27.00 10,350.00 279,450.00
Load
85 MTRA0094 RG-6770 Tractor - DRY Hrs 10.80 108.00 150.00 16,200.00
86 MTTR0019 GK-3928 Tractor Trailer - DRY Day - 27.00 1,000.00 27,000.00
87 MTTR0067 RW-9986 Tractor Trailer - DRY Day - 27.00 1,000.00 27,000.00
88 MWTR0005 MWT-05 Welding Transformer 300 AMP DRY Day - 27.00 275.00 7,425.00
89 MWTR0044 MWT-44 Welding Transformer 300 AMP DRY Day - 27.00 275.00 7,425.00
90 MWTR0102 MWT-102 Welding Transformer 300 AMP DRY Day - 27.00 275.00 7,425.00

Total (G) 7,946,155.00

AGREED CONTRACT SUM AFTER


A DISCOUNT
PACKAGE -01 10,791,984,006.29 B/E = F 0.2321
B PACKAGE -02 10,577,490,431.61 Cost of idling of Machineries (G x F) 1,844,302.58
C PACKAGE -03 11,326,279,872.70
D PACKAGE -04 12,883,548,674.60
E TOTAL 45,579,302,985.20
Maga Engineering (Pvt) Ltd
Project Name: Construction of Ruwanpura Expressway Phase 01
Employer: Ministry of Highways
Idling Plant, Machinery & Manpower Package-02

Period 2022 August


ACTIVITY PLANNED Category Daily Working Hours for Month

Employee No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Unit Total Uti. Amount Remarks


Idling Machinery & Motor Grader MMG 66 10 10 10 10 10 10 10 10 hrs 1,083,333.33
80.00
Equipment due to slow
down the work with effect MMG 69 10 10 10 10 10 10 10 10 hrs 80.00 716,666.67
from 19th of April 2024 MMG 73 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 716,666.67
310.00
MMG 75 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 716,666.67
Sheepfoot Roller MRV 343 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 400,000.00
Backhoe Loader MLBH 23 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 434,166.67
MLBH 25 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 434,166.67
Excavator 220 MEX 38 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 758,333.33
MEX 40 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 758,333.33
Mini Loader MML 130 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 210,000.00
MML 131 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 hrs 310.00 210,000.00
Rammer MRAM 1138 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 day 310.00 10,833.33
MRAM 1137 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 day 310.00 15,833.33
MRAM 1153 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 day 310.00 15,833.33
Truck 5 Cube LM 6267 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 day 310.00 271,111.11
Total Amount 6,751,944.44
Maga Engineering (pvt) ltd.
Central Work Shop Homagama
Tel: +94 112562565-7 Fax: +94 114440662 Email: cws@maga.lk

Invoice Number : CWS/P&M/22/05/06 Period : August 2022


Project : Ruwanpura Expressway Project - Concrete Batching Plant - Horana

THIS MONTH
NO MAGA NO REG NO TYPE CAPACITY HIRE CON. UNIT MINIMUM RATE PER
UTILIZATION AMOUNT (RS)
UTILIZATION UNIT (RS)

1 MGEN0098 MGE-98 Generator 300 KVA DRY Hrs - 108.00 1,050.00 113,400.00
2 MGEN0166 MGE-166 Generator 220 KVA DRY Hrs - 108.00 850.00 91,800.00
3 MTMX0069 LH-9949 Con.Truck Mixture 2.5 m3 DRY m3 - 500.00 385.00 192,500.00
4 MTMX0098 LK-7815 Con.Truck Mixture 2.5 m3 DRY m3 - 500.00 385.00 192,500.00
5 MTMX0099 LK-7940 Con.Truck Mixture 5.0 m3 DRY m3 - 500.00 715.00 357,500.00
Total (G) 947,700.00

AGREED CONTRACT SUM AFTER DISCOUNT


A PACKAGE -01 10,791,984,006.29 B/E = F 0.2321
B PACKAGE -02 10,577,490,431.61 Cost of idling of Machineries (G x F) 219,961.17
C PACKAGE -03 11,326,279,872.70
D PACKAGE -04 12,883,548,674.60
E TOTAL AMOUNT 45,579,302,985.20