Super Hornet CLIN 3 & 6 - 3 Weeks Look Ahead - 22 September 2022

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

PROJECT NO.

W912ER21F0131  
SUPER HORNET F-18 (CLIN 3 - GENERAL PURPOSE WAREHOUSE - FACILITY G), AL JABER AIR BASE, KUWAIT
22-Sep-22
3 WEEKS LOOK AHEAD SCHEDULE

Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Super Hornet Training Facility & Warehouse Design, AJAB, Kuwait - 22 September 2022 491d 0% 22-Sep-21 A 08-Jan-23 13d
CLIN 3 - General Purpose Warehouse - Facility G 491d 0% 22-Sep-21 A 08-Jan-23 13d
Project Duration 486d 0% 22-Sep-21 A 08-Jan-23 13d
PM1050 General Purpose Warehouse - Total Project Duration 486d 0% 22-Sep-21 A 08-Jan-23 13d
General Requirements 491d 0% 22-Sep-21 A 08-Jan-23 13d
GEN1100 Access Passes 486d 0% 22-Sep-21 A 08-Jan-23 13d
Submittals & Approvals 174d 0% 03-Oct-21 A 24-Oct-22 55d
Submittals 131d 0% 20-Oct-21 A 24-Oct-22 55d
SUB1370 Submittal for conrete quality plan for exterior pavement 15d 90% 20-Oct-21 A 24-Oct-22 32d
SUB1070 Submittals for communication works 30d 90% 01-Dec-21 A 29-Sep-22 36d
SUB1350 Submittal for access control, intrusion detection system 30d 90% 01-Dec-21 A 11-Oct-22 66d
SUB1050 Submittals for fire suppression works 30d 90% 04-Jan-22 A 28-Sep-22 42d
Approvals 153d 0% 03-Oct-21 A 05-Oct-22 63d
APP1020 Approvals for plumbing works 30d 95% 03-Oct-21 A 28-Sep-22 19d
APP1370 Approvals for conrete quality plan for exterior pavement 30d 90% 09-Dec-21 A 29-Sep-22 32d
APP1070 Approvals for communication works 30d 80% 28-Dec-21 A 03-Oct-22 27d
APP1350 Approvals for access control, intrusion detection system 30d 90% 10-Jan-22 A 02-Oct-22 66d
APP1050 Approvals for fire suppression works 30d 80% 16-Feb-22 A 05-Oct-22 42d
Procurement of Long Lead Items 193d 0% 24-Feb-22 A 30-Nov-22 26d
Procurement 193d 0% 24-Feb-22 A 30-Nov-22 26d
MAT1760 Procurement of Fire Hose Reels with Cabinet 100d 60% 24-Feb-22 A 03-Nov-22 51d
MAT1210 Procurement of Electrical Panel Boards 90d 95% 05-Apr-22 A 20-Oct-22 62d
MAT1300 Procurement of LED lights 100d 20% 20-Apr-22 A 28-Oct-22 49d
MAT1090 Procurement of Comm. Racks 100d 95% 28-Apr-22 A 09-Oct-22 64d
MAT1220 Procurement of Loading Dock Levelers 72d 0% 23-Jul-22 A 27-Oct-22 59d
MAT1060 Procurement of Sliding Steel Doors 55d 0% 15-Aug-22 A 22-Oct-22 63d
MAT1200 Procurement of Furnitures, Steel Shelves, Kitchen Appliances, Cabinets, Countertop
70d 0% 22-Sep-22 30-Nov-22 13d
MAT1190 Procurement of Door Hardwares 20d 0% 12-Oct-22 31-Oct-22 56d
Delivery 20d 0% 13-Jul-22 A 10-Oct-22 64d
MAT1095 Delivery of Comm. Racks 1d 95% 13-Jul-22 A 10-Oct-22 64d
MAT1075 Delivery of Fire Alarm Components 1d 95% 30-Aug-22 A 29-Sep-22 25d
Construction Works 253d 0% 11-Jan-22 A 30-Oct-22 79d
Demolition Works 30d 0% 11-Jan-22 A 02-Oct-22 89d
GPW.SITE1020 Remove existing barbed wire fence & gates 30d 80% 11-Jan-22 A 02-Oct-22 89d
Substructures 5d 0% 30-Mar-22 A 06-Oct-22 19d
Warehouse 5d 0% 30-Mar-22 A 06-Oct-22 19d
SOG 5d 0% 30-Mar-22 A 06-Oct-22 19d
GPW.SUB1180 Expansion joints, construction joints, isolation joints 5d 60% 30-Mar-22 A 06-Oct-22 19d
General Purpose Warehouse & Loading Dock - Structural Works 10d 0% 30-Aug-22 A 03-Oct-22 61d
GPW.ST1040 Supply & install door canopies & window sunshades 10d 70% 30-Aug-22 A 03-Oct-22 61d

  Page 1 of 3    
    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
General Purpose Warehouse - Interior Construction 120d 0% 22-May-22 A 22-Oct-22 65d
Architectural Works 20d 0% 09-Aug-22 A 13-Oct-22 62d
Perimeter Walls 10d 0% 26-Sep-22 06-Oct-22 37d
GPW.AR1040 Construct aerated concrete planks for elec. room ceiling (Fire rated sheet) 10d 0% 26-Sep-22 06-Oct-22 37d
Dry Areas 14d 0% 09-Aug-22 A 13-Oct-22 44d
GPW.AR1090 Painting works 14d 75% 09-Aug-22 A 13-Oct-22 44d
WetAreas 7d 0% 13-Sep-22 A 10-Oct-22 65d
GPW.AR1230 Supply & install floor tiles 6d 50% 13-Sep-22 A 02-Oct-22 65d
GPW.AR1240 Ceiling works 6d 0% 03-Oct-22 10-Oct-22 65d
Mechanical Works 57d 0% 24-Jul-22 A 22-Oct-22 65d
Drainage System 8d 0% 11-Oct-22 19-Oct-22 67d
GPW.MEC1020 Supply & install sanitary fixtures 8d 0% 11-Oct-22 19-Oct-22 67d
GPW.MEC1030 Supply & install toilet accessories 6d 0% 11-Oct-22 17-Oct-22 69d
Water Supply System 4d 0% 26-Sep-22 29-Sep-22 19d
GPW.MEC1060 Supply & install expansion tank 4d 0% 26-Sep-22 29-Sep-22 19d
Compressed Air System 8d 0% 29-Aug-22 A 04-Oct-22 71d
GPW.MEC1100 Install air compressor 8d 90% 29-Aug-22 A 04-Oct-22 71d
Interior HVAC Works 49d 0% 24-Jul-22 A 22-Oct-22 57d
GPW.MEC1150 Ductworks 20d 95% 24-Jul-22 A 09-Oct-22 43d
GPW.MEC1190 Duct insulation works 15d 95% 24-Jul-22 A 13-Oct-22 64d
GPW.MEC1170 Supply & install condensate pipes 10d 90% 03-Aug-22 A 22-Oct-22 56d
GPW.MEC1180 Suppl & install refrigerant pipes 10d 90% 04-Aug-22 A 22-Oct-22 56d
GPW.MEC1160 Install indoor HVAC units 12d 0% 26-Sep-22 10-Oct-22 56d
Electrical Works 28d 0% 23-Jul-22 A 16-Oct-22 66d
GPW.ELEC1080 Install electrical panel boards 12d 80% 23-Jul-22 A 25-Sep-22 76d
GPW.ELEC1070 Supply & install ground rod 10d 90% 23-Jul-22 A 03-Oct-22 76d
GPW.ELEC1010 Supply & install overhead conduits & cable trays 14d 80% 02-Aug-22 A 16-Oct-22 37d
Telecommunication System Works 114d 0% 22-May-22 A 19-Oct-22 47d
Voice & Data System 114d 0% 22-May-22 A 19-Oct-22 47d
GPW.COM1010 Install raceways (conduits, cable trays) 20d 90% 22-May-22 A 19-Oct-22 43d
Comm 7. Room 14d 0% 21-Sep-22 A 12-Oct-22 53d
GPW.COM1050 Painting of walls 4d 20% 21-Sep-22 A 29-Sep-22 53d
GPW.COM1060 Supply & install ladder rack 10d 0% 01-Oct-22 12-Oct-22 53d
Electronic Security System (ESS) 20d 0% 18-Jul-22 A 19-Oct-22 21d
GPW.COM1100 Install raceways (conduits, cable trays) 20d 90% 18-Jul-22 A 19-Oct-22 21d
Fire Alarm & Fire Protection Works 55d 0% 18-Jul-22 A 17-Oct-22 61d
Fire Alarm System 55d 0% 18-Jul-22 A 16-Oct-22 46d
GPW.FA1010 Supply & install raceways 20d 90% 18-Jul-22 A 27-Sep-22 46d
GPW.FA1020 Supply & install cables & wires 15d 60% 28-Aug-22 A 16-Oct-22 46d
Fire Suppression System 29d 0% 27-Jul-22 A 17-Oct-22 61d
GPW.FA1050 Supply & install overhead fire protection pipes & fire hose pipes 12d 90% 27-Jul-22 A 10-Oct-22 42d
GPW.FA1060 Supply & install vertical fire protection pipes & valves 6d 90% 21-Aug-22 A 02-Oct-22 67d
GPW.FA1070 Supply & install sprinkler heads 6d 0% 11-Oct-22 17-Oct-22 61d
Site Utilities 100d 0% 22-May-22 A 12-Oct-22 68d
Water Distribution System 4d 0% 09-Oct-22 12-Oct-22 64d
GPW.SITE1220 Connection to water mains 4d 0% 09-Oct-22 12-Oct-22 64d

  Page 2 of 3    
    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Electrical Utilities 6d 0% 22-May-22 A 28-Sep-22 79d
GPW.SITE1340 Supply & install lightning protection system 6d 80% 22-May-22 A 28-Sep-22 79d
GPW.SITE1350 Supply & install grounding system 6d 85% 26-May-22 A 28-Sep-22 79d
Mechanical Yard 10d 0% 14-Jul-22 A 06-Oct-22 73d
GPW.SITE1550 Install outdoor HVAC units 10d 95% 14-Jul-22 A 06-Oct-22 73d
Vehicle Parking Shelter 21d 0% 25-Sep-22 19-Oct-22 66d
Superstructure 21d 0% 25-Sep-22 19-Oct-22 66d
GPW.SITE1650 Asphalt works 6d 0% 25-Sep-22 01-Oct-22 66d
GPW.SITE1680 Supply & install wheelstops 4d 0% 02-Oct-22 05-Oct-22 73d
GPW.SITE1690 Electrical works 15d 0% 02-Oct-22 19-Oct-22 66d
GPW.SITE1700 Laying of gravel 4d 0% 06-Oct-22 11-Oct-22 73d
Site Improvements 54d 0% 10-Aug-22 A 30-Oct-22 57d
Concrete Pavement Test Section 54d 0% 21-Aug-22 A 27-Oct-22 33d
GPW.SI1370 Contraction & construction joints 4d 45% 21-Aug-22 A 26-Sep-22 33d
GPW.SI1380 Inspection of Test Section 1d 0% 27-Sep-22 27-Sep-22 33d
GPW.SI1390 Flexural Strength Test for Test Section 1d 0% 28-Sep-22 28-Sep-22 33d
GPW.SI1400 Prepare & submit Test Reports for Test Section 10d 0% 29-Sep-22 11-Oct-22 33d
GPW.SI1410 Approval of Test Section 14d 0% 12-Oct-22 27-Oct-22 33d
Heavy Duty Concrete Pavement 15d 0% 10-Aug-22 A 30-Oct-22 32d
GPW.SI1020 Formworks & dowels 15d 50% 10-Aug-22 A 30-Oct-22 32d
Concrete Sidewalk 5d 0% 12-Oct-22 18-Oct-22 67d
GPW.SI1110 Contraction & expansion joints 5d 0% 12-Oct-22 18-Oct-22 67d
Asphalt Pavement 9d 0% 12-Sep-22 A 12-Oct-22 32d
GPW.SI1210 Grading & compaction of aggregate base course 4d 60% 12-Sep-22 A 10-Oct-22 32d
GPW.SI1220 Prime coat 2d 0% 11-Oct-22 12-Oct-22 32d
Security Fence 10d 0% 09-Oct-22 20-Oct-22 49d
GPW.SI1300 Supply & install chain link fabric 10d 0% 09-Oct-22 20-Oct-22 49d

  Page 3 of 3    
    
PROJECT NO. W912ER21F0131  
SUPER HORNET F-18 (CLIN 6 - FUNCTIONAL AIRCREW TRAINING CENTER - FACILITY K), AL JABER AIR BASE, KUWAIT
22-Sep-22
3 WEEKS LOOK AHEAD SCHEDULE

Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Super Hornet Training Facility & Warehouse Design, AJAB, Kuwait - 22 September 2022 400d 0% 22-Sep-21 A 04-Dec-22 10d
CLIN 6 - Functional Aircrew Training Center - Facility K 400d 0% 22-Sep-21 A 04-Dec-22 10d
Project Duration 385d 0% 22-Sep-21 A 04-Dec-22 0d
SP40 Functional Aircrew Training Center - Total Project Duration 380d 2% 22-Sep-21 A 04-Dec-22 0d
SP50 Rooms 168 & 167 - Project Duration 201d 2% 22-Sep-21 A 27-Oct-22 25d
General Requirements 370d 0% 22-Sep-21 A 04-Dec-22 0d
GEN1110 Access Passes 365d 2% 22-Sep-21 A 04-Dec-22 0d
Submittals & Approvals 40d 0% 09-Jan-22 A 02-Oct-22 25d
Submittals 30d 0% 09-Jan-22 A 25-Sep-22 25d
SUB1340 Submittals for fire alarm works 30d 90% 09-Jan-22 A 25-Sep-22 25d
Approvals 37d 0% 09-Jan-22 A 02-Oct-22 25d
APP1340 Approvals for fire alarm works 30d 80% 09-Jan-22 A 02-Oct-22 25d
APP1270 Approvals for communication works 30d 90% 19-Jan-22 A 28-Sep-22 23d
Procurement of Long Lead Items 228d 0% 05-Jan-22 A 30-Nov-22 -15d
Procurement 228d 0% 05-Jan-22 A 30-Nov-22 -15d
MAT1750 Procurement of Fire Alarm Components & Accessories 80d 90% 05-Jan-22 A 05-Oct-22 30d
MAT1490 Procurement of LED lights 100d 95% 10-Mar-22 A 29-Sep-22 40d
MAT1690 Procurement of Door Hardwares 100d 60% 15-Mar-22 A 14-Oct-22 33d
MAT1790 Procurment of furniture 120d 0% 02-Jul-22 A 30-Nov-22 -15d
Delivery 70d 0% 03-Mar-22 A 06-Oct-22 34d
MAT1780 Delivery of Fire Alarm Components & Accessories 1d 95% 03-Mar-22 A 06-Oct-22 30d
MAT1500 Delivery of LED lights 1d 95% 25-Apr-22 A 30-Sep-22 40d
MAT1800 Delivery of Roll up door 1d 80% 02-Jun-22 A 23-Sep-22 36d
Construction works 206d 0% 05-Feb-22 A 24-Oct-22 51d
Renovation of Rooms 168 (TOFT 1), 167 (BDS/MOC #1), 268A, 268B 43d 0% 27-Jul-22 A 13-Oct-22 29d
Rooms 168, 167, 268A, 268B - Communication Works 5d 0% 27-Jul-22 A 03-Oct-22 29d
ATC.COM0030 Install comm. components & accessories 5d 90% 27-Jul-22 A 03-Oct-22 29d
Rooms 168, 167, 268A, 268B - Electronic Security System 11d 0% 03-Sep-22 A 04-Oct-22 33d
ATC.COM0070 Install ESS components & accessories 11d 90% 03-Sep-22 A 04-Oct-22 33d
Rooms 168, 167, 268A, 268B - Testing & Commissioning 15d 0% 26-Sep-22 13-Oct-22 29d
ATC.TC1080 Testing & Commissioning - electrical system 3d 0% 26-Sep-22 28-Sep-22 41d
ATC.TC1100 Testing, Adjusting, Balancing - HVAC system 3d 0% 01-Oct-22 03-Oct-22 37d
ATC.TC1110 Testing & Commissioning - access control system 3d 0% 05-Oct-22 09-Oct-22 33d
ATC.TC1090 Testing & Commissioning - communication works 3d 0% 11-Oct-22 13-Oct-22 29d
Renovation of Other Areas 206d 0% 05-Feb-22 A 24-Oct-22 51d
Rooms 162 (TOFT 2), 161 (BDS/MOC #2), 262A, 262B 143d 0% 05-Feb-22 A 18-Oct-22 25d
Rooms 162, 161, 262A, 262B - Architectural Works 16d 0% 18-May-22 A 13-Oct-22 24d
ATC.AR1280 Rooms 161, 162, 262A, 262B - Ceiling works 7d 95% 18-May-22 A 13-Oct-22 24d
ATC.AR1290 Room 162 - Install overhead roll-up doors 12d 50% 29-May-22 A 05-Oct-22 24d
Rooms 162, 161, 262A, 262B - Electrical Works 10d 0% 05-Feb-22 A 18-Oct-22 25d

  Page 1 of 2    
    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.ELEC1110 Install LED lights 10d 90% 05-Feb-22 A 18-Oct-22 25d
Rooms 162, 161, 262A, 262B - Electronic Security System 10d 0% 18-Aug-22 A 11-Oct-22 31d
ATC.COM1130 Install ESS components & accessories 10d 75% 18-Aug-22 A 11-Oct-22 31d
Rooms 162, 161, 262A, 262B - Modify Existing Fire Alarm Loop 10d 0% 23-Feb-22 A 10-Oct-22 33d
ATC.FA1100 Install fire alarm components & accessories 10d 90% 23-Feb-22 A 10-Oct-22 33d
Secure Storage - Rooms 173, 173A, 271, 272 118d 0% 20-Feb-22 A 10-Oct-22 35d
Room 173, 173A, 271, 272 - Architectural Works 4d 0% 20-Feb-22 A 26-Sep-22 43d
ATC.AR1100 Room 173 - Install overhead door 4d 50% 20-Feb-22 A 26-Sep-22 43d
Room 173, 173A, 271, 272 - Electrical Works 10d 0% 07-Jun-22 A 09-Oct-22 36d
ATC.ELEC1220 Install LED lights 10d 60% 07-Jun-22 A 09-Oct-22 36d
Room 173, 173A, 271, 272 - Electronic Security System 15d 0% 11-Aug-22 A 10-Oct-22 32d
ATC.COM1160 Install ESS components & accessories 15d 95% 11-Aug-22 A 10-Oct-22 32d
Room 118 - LCT 1,Room117 - LCT 2, Room 108 - F-18 COMM, Room 170 - Elec. Room 124d 0% 05-Feb-22 A 24-Oct-22 24d
Room 118,117, 108, 170 - Electrical Works 10d 0% 05-Feb-22 A 09-Oct-22 34d
ATC.ELEC1030 Install LED lights 10d 90% 05-Feb-22 A 09-Oct-22 34d
Room 108 - Communication Works 37d 0% 28-Apr-22 A 17-Oct-22 26d
ATC.COM1000 Room 108 - Install comm. equipment cabinet 10d 90% 28-Apr-22 A 06-Oct-22 26d
ATC.COM1010 Room 108 - Laying of fiber obtic cable 8d 90% 22-Aug-22 A 17-Oct-22 26d
ATC.COM1030 Room 108 - Install & install ladder rack 8d 90% 03-Sep-22 A 17-Oct-22 26d
ATC.COM1020 Room 108 - Install & terminate patch panels 8d 0% 09-Oct-22 17-Oct-22 26d
Room 118,117, 108 - Electronic Security System 10d 0% 01-Sep-22 A 03-Oct-22 37d
ATC.COM1250 Install ESS components & accessories 10d 90% 01-Sep-22 A 03-Oct-22 37d
Room 118,117, 108 - Modify Existing Fire Alarm Loop 23d 0% 19-Apr-22 A 24-Oct-22 24d
ATC.FA1020 Supply & install fire extinguishers 5d 80% 19-Apr-22 A 24-Oct-22 24d
ATC.FA1180 Install fire alarm components & accessories 10d 90% 10-May-22 A 17-Oct-22 26d
Corridors 50d 0% 07-Aug-22 A 16-Oct-22 51d
Corridors - Electrical Works 10d 0% 02-Oct-22 13-Oct-22 23d
ATC.DEMO1340 Re-install LED lights 10d 0% 02-Oct-22 13-Oct-22 23d
Corridors - Telecommunication Works 20d 0% 22-Sep-22 16-Oct-22 27d
ATC.COM1040 Disconnect & remove existing fiber optic cable 8d 0% 22-Sep-22 01-Oct-22 23d
ATC.COM1050 Supply & install above ceiling cable tray 10d 0% 22-Sep-22 03-Oct-22 27d
ATC.COM1060 Laying of fiber obtic cable 10d 0% 04-Oct-22 16-Oct-22 27d
Corridors - Electronic Security System 10d 0% 07-Aug-22 A 29-Sep-22 23d
ATC.COM1220 Install ESS components & accessories 10d 70% 07-Aug-22 A 29-Sep-22 23d
Corridors - Mechanical Works 10d 0% 03-Oct-22 16-Oct-22 51d
ATC.MEC1070 Re-install existing mechanical equipment devices 10d 0% 03-Oct-22 16-Oct-22 51d
Room 101 - Classroom 6d 0% 25-Aug-22 A 28-Sep-22 45d
Room 101 - Architectural Works 6d 0% 25-Aug-22 A 28-Sep-22 45d
ATC.AR1310 Install doors & door hardware 6d 90% 25-Aug-22 A 28-Sep-22 45d
Building Commissioning 20d 0% 22-Sep-22 16-Oct-22 31d
ATC.TC1010 Testing & Commissioning - sanitary sewer system 4d 0% 22-Sep-22 26-Sep-22 47d
ATC.TC1040 Testing, adjusting, balancing - HVAC system 4d 0% 01-Oct-22 04-Oct-22 40d
ATC.TC1120 Testing & Commissioning - electronic security system 4d 0% 11-Oct-22 16-Oct-22 31d