Professional Documents
Culture Documents
Background
Background
Background:
• This case is that of a Public Interest Litigation (PIL),
concerning the seismic and ecological safety of the
construction and implementation of the Tehri Hydro Power
Project and Dam. It is a quintessential case of supposed lack
of due diligence on the part of the government both in terms
of possible damage to the environment and in the safety of
this project against earthquakes given its seismically prone
location.
Facts:
• Petition filed under article 32 of the constitution of india
• Filed for public interest purpose by Tehri Bandh Virodhi
Sangarsh Samiti and others
• It has been filed against the construction and
implementation of Tehri Hydro projection and construction
of the tehri dam
• The petitioners claims that the safety aspect hasn’t been
taken into consideration
• They assert that if the dam is constructed then it is a serious
threat to life, ecology and the environment of the entire
northern india as the site is prone to earthquake
• It has been shown that the the project was considered by
Environmental Appraisal Committee of Environment and
forests, committee of secretaries, high level committee
comprising experts of scientific and specialized
organizations and also by a renowned expert of
international repute.
• Thus the UOI considered the question of safety of the
project from various details more than pnce and on being
satisfied with the reports of the experts gave clearance to
the project.
• it was argued by the petitioner's advocate that the seismic
experts in india and abroad are of view that past records of
earthquake show that the likely length of fracture along the
convergence boundary is of order of 200-300 km and this
was not applied its mind to this very important aspect in
preparing the project.
• The project was first considered by the environmental
appraisal committee of the ministry of environment and
forests and the said committee, taking into consideration the
convergence boundary is of order of 200-300 km and this
was not applied its mind to this very important aspect in
preparing the project.
• The project was first considered by the environmental
appraisal committee of the ministry of environment and
forests and the said committee, taking into consideration the
geological and seismic setting and the consequences and
risks.
• A high level committee was also set up consisting of Shri
D.P. Dhoundial, Director General, Geological Survey of
India as Chairman, Prof. V.K. Gaur, Secretary, Department
of Ocean Development, Dr D. Guptasarma, Director,
National Geological Research Institute, Dr C.D. Thatte,
Member, Central Water Commission, Prof. L.S. Srivastava,
Head, Department of Earthquake Engineering, University of
Roorkee and Shri S.K. Shrone, Director, Geological Survey
of India as members of the said Committee. The Committee
looked into all the necessary safety aspect while also
considering the worst case scenarios
Issue:
Whether the government did sufficient inquiry into the
safety aspect of the construction of the dam?
Was the project structurally viable given the heightened
seismic activity in the area, especially due to its reservoir
like nature?
Judgement:
Judgement: