Maersk Oil Qatar AS Sime Darby Engineering Sdn. Bhd. Construction Inspection Test Sheet: E01/3-A Electrical HV Cable MOQ-16

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Maersk Oil Qatar AS

Sime Darby Engineering Sdn. Bhd.


MOQ-16
Construction Inspection Test Sheet : E01/3-A
Sime Darby Engineering
ELECTRICAL HV CABLE Sdn Bhd

Job No. : Tag No :


Location : Platform :
System : Sub System :
A. GENERAL INFORMATION
1. From :
2. To :
3. Pair/Core & Size :
4. Outer Sheath Colour :
5. Termination Drawing :
B. INSPECTION CHECKS OK N/A P/L
1. Check cable against specification and drawings.
2. Check cable against data in cable schedule.
3. Glanding/locknuts/bonding correct (Near end).
4. Glanding/locknuts/bonding correct (Far end).
5. Cable marking correct outside/inside panels (Near end).
6. Cable marking correct (Far end).
7. Termination in accordance with drawings (Near end).
8. Termination in accordance with drawings (Far end).
9. Number/ferruling correct (Near end).
10. Number/ferruling correct (Far end).
11. Cable grouping correct.
12. Clamping/cleating correct (Area acceptance).
13. Cable mechanically protected (Area acceptance).
14. Cable screens should be checked to confirm that their connection to earth
is passed through the core balance CT where fitted.
15. Confirm cable screens are earthed at both ends.
16. Confirm cable idents fitted on either side of all transits.
17. Prior to any IR or preassure testing a continuity test should be carried out. This
should include a continuity check of the cable screens.
18. INSTALLATION TEST
Record earth loop resistance at switchgear end. <1, 0 ohm

Record resistance gland body to earth Bar at switchgear end. <0.01 ohm

IR test prior to HIPOT.(5kV for 11kV cables. 2.5kV for 3kV cables)
L1 to L2/L3/screens/ L2 to L1/L3/screens/ L3 to L1/L2/screens/
armour and earth armour and earth armour and earth >150 Mohm
MΩ MΩ MΩ
High Voltage Pressure Test
L1 to E L2 to E L3 to E
µA µA µA
Note 2 other phases connected to Ground during test

IR test after HIPOT.(5kV for 11kV cables. 2.5kV for 3kV cables)
L1 to L2 L2 to L3 L1 to L3
MΩ MΩ MΩ >150 Mohm
REV 0 : 20Feb09 SHEET 1 OF 2
Maersk Oil Qatar AS
Sime Darby Engineering Sdn. Bhd.
MOQ-16
Construction Inspection Test Sheet : E01/3-A
Sime Darby Engineering
ELECTRICAL HV CABLE Sdn Bhd

Job No. : Tag No :


Location : Platform :
System : Sub System :
C. REMARKS
# Attach Block diagram & Termination drawing with this Test Sheet.

# Note : 1. 15kV test with 34.8kV for 1 mins


# 2. 3kV test with 7.2kV form 1 mins

# Cable should be disconnected from switchgear during test.

REVIEWED BY
COMPLETED BY APPROVED BY VERIFIED BY
CA MOQ
Name
Signature
Date
REV 0 : 20Feb09 SHEET 2 OF 2