Professional Documents
Culture Documents
Structural Quantity Analysis of Tall Buildings
Structural Quantity Analysis of Tall Buildings
1
Associate Director, HanmiParsons Co., Ltd.
2
President, Harmony Engineering Co.
Abstract
Structural construction costs of tall buildings recently built or under construction in Korea were investigated in
terms of unit material quantities and their costs. The comparative study for three composite and three reinforced
concrete projects of similar heights and design environments produced some statistical result within certain range
for unit structural quantity and cost, displaying relative economical advantage of reinforced concrete structures
compared to composite construction. The itemized investigation of structural construction cost gives a general
view for overall construction cost composition as well as the significance of selected structural members and their
materials in the cost of constructing high rise buildings. The cost of formwork considerably increased, especially
in reinforced concrete construction, implying that special regard should be paid to the selection of the formwork
system in the economical construction of tall concrete buildings.
Brace + Moment
ASEM Tower 41/B4 174.3 m Office 43 months 2000
Resisting Steel Frame
Brace + Moment
Star Tower
45/B8 202.7 m Office Resisting Steel Frame 74.5 months 2001
( I-Tower)
+ Outrigger truss
Composite Column +
59, 66, 59, 233.9 m
Tower Palace 1 Residential Steel Beam + Core 36 months 2002
44/B5 (66 story)
Wall + Outrigger Truss
Composite Column + 39 months
Tower Palace 2 55/B6 196.2 m Residential Steel beam + Core Wall (excluding 2002
+ Outrigger Truss excavation)
Composite Column +
Tower Palace 3 69/B6 261.2 m Residential Steel Beam + Core 36 months 2004
Wall + Belt Wall
Composite Column +
Mok-dong 69, 63, 54
256 m Residential Steel Beam + Outrigger 44 months 2003
Hyperion /B6
Truss
Samsung-dong 148.4 m
46, 39, 46 /B3 Residential Flat Plate + Core Wall 33 months 2004
I-Park (46 story)
3. Structural quantity analysis of tall a sum total. For a comparison of unit material
composite buildings quantities of three buildings, total material
Three towers of B, E and G, which are 66, 55 and quantities are divided by the gross floor areas of
69 story composite structures, respectively, on the their respective buildings. In this study, the gross
neighboring sites, were chosen for the study of floor area is defined as the sum of the floor areas for
structural quantities. With another 69 story all the floors including basements, for which the
Hyperion Project, these are the tallest luxury areas were obtained by projecting the plan of the 1st
residential complex apartments in Korea, designed floor to the foundation level. This gross floor area
with similar structural systems. For B, E and G of appears to be a little greater than the official gross
the plan configuration of a rectangle, a dumbbell floor area. It is noted that concrete unit volumes of
and a triangle, respectively, a structural system of three buildings are almost the same at 0.37 m3/m2
concrete core wall, composite columns, steel beams on the basis of gross floor area within 5 %
and metal deck was used in common. However, difference range. On the other hand, G used most
steel outriggers for B and E and concrete belt wall reinforcement with the smallest structural steel,
for G were used in mechanical rooms as different while E utilized the largest structural steel with the
lateral force resisting system structures. All the smallest reinforcement. The main reasons are, firstly,
foundations of three buildings are a mat system on that steel outriggers were used in B and E instead of
soils of similar bearing capacity, with the exception concrete belt wall in G, and secondly, that E has
of E, adopting single spread footings only for longer spans of 9.3 and 10.2 meters than those of
columns other than its cores. the other buildings, so that relatively heavy
Table 2 gives total structural quantities of members of steel beam were utilized in the situation
concrete, reinforcement and steel, which are of limited ceiling height. Thus, the summed unit
itemized for each structural member. All structural amounts of reinforcement and steel for three towers
quantities of different strengths of materials, do not give big differences.
especially for concrete, were added up to figure out
In order to compare the construction costs of three 176,911 won/m2, respectively, giving differences of 4.6
buildings, the structural quantities of Table 2 are and 1.8 %. The tallest G costs even less than the fourteen
transferred to direct construction costs for building story smaller E. The G utilized relatively more quantities
structures based on the price as of June, 2004. Formwork of concrete and reinforcement with smaller structural
cost and different costs for different concrete strengths steel amount, which appears to be the reason for the cost
are also taken into account in the process. Table 3 shows saving. This fact shows the importance of selected
that the tallest building, G, has the smallest cost of structural materials for the economical construction of
173,862 won/m2, while B and E have 181,839 and tall buildings.
ͣ͢͡
΄ΖΒΣΤ͑΅ΠΨΖΣ ΈΠΣΝΕ͑΅ΣΒΕΖ͑ʹΖΟΥΖΣ
ͶΞΡΚΣΖ͑΄ΥΒΥΖ͑ͳΦΚΝΕΚΟΘ
͢͡͡
ͻΠΙΟ͑ΒΟΔΠΔΜ͑ͳΦΚΝΕΚΟΘ
ͿΠ͑͟ΠΗ͑΄ΥΠΣΚΖΤ
ͩ͡
ͳ
ͧ͡ Ͷ
ͥ͡
ͣ͡
͡
͡ ͦ͡ ͢͡͡ ͦ͢͡ ͣ͡͡ ͣͦ͡ ͤ͡͡
΄ΥΣΦΔΥΦΣΒΝ͑΄ΥΖΖΝ͑ΦΒΟΥΚΥΚΖΤ͙͑ΜΘΗ͠Ξ͚ͣ
Formwork costs occupy 14 to 18.6 % among total beams and slab, occupy 29.6, 51.6 and 37.9 % for B,
structural expenses; horizontal structural members, E and G, respectively. The high value of E occurs due
; ΚΝΝ͑͟ΈΠΟ
ͣͦ͢͝͡
͢͝͡͡͡
ʹΠΝΦΞΟ
΄ΥΖΖΝ͑ͳΖΒΞ
͑͑΄ΥΣ ΦΔΥΦΣ ΒΝ͑ʹΠΤΥ
ͨͦ͡ ʹΠΣΖ͑ΈΒΝΝ͑͑͜ͽΚΟΜ͑ͳΖΒΞ
΄ΝΒΓ
ͳΖΝΥ͑ΈΒΝΝ
ͦ͡͡
ͣͦ͡
͡
ͳͣ
ͳͥ
ͳͧ
ͧͪ
ͧͨ
ͧͦ
ͧͤ
ͧ͢
ͦͪ
ͦͨ
ͦͦ
ͦͤ
ͦ͢
ͥͪ
ͥͨ
ͥͦ
ͥͤ
ͥ͢
ͤͪ
ͤͨ
ͤͦ
ͤͤ
ͤ͢
ͣͪ
ͣͨ
ͣͦ
ͣͤ
ͣ͢
ͪ͢
ͨ͢
ͦ͢
ͤ͢
͢͢
ͪ
ͨ
ͦ
ͤ
͢
ͣ
ΠΠΗ
ͷΝΠΠ Σ
4. Structural quantity analysis of tall the other buildings in Seoul. In order to raise the
reinforced concrete buildings lateral stiffness of the building, partition walls were
Three 46-, 50- and 53-story reinforced concrete also designed as reinforced concrete structures, thus,
buildings of I, S and C residential projects, relatively lower cost for partition walls will be
respectively, were selected for comparison. The I and expended for completion later, compared to normal
S projects are in Seoul, while C project is located in practices. The I adopted spread footings for columns
Busan. Only one representative building of similar and a mat exclusively for the core, while other
height was chosen among several buildings of each buildings used mat foundations.
project. The I project was completed in 2004, and the Table 4 gives total structural quantities of concrete
S and C projects are currently under construction. The and reinforcement, which are itemized for each
structural system of I and S buildings is flat plate with structural member. Again, total structural quantities of
core and exterior columns, while the structure of C is different strengths of concrete were added up for a
core and bearing wall with outriggers at both summed total. It is seen that unit structural quantities
mechanical floor and roof, and belt wall from the of concrete and reinforcement on the basis of gross
basement 1 to 3rd floor. The C was designed against floor area for I, S, C buildings are 0.49, 0.56, 0.59
high wind pressure, which is more than twice that of m3 /m2 and 72.6, 88.2, 94.3 kgf/m2, respectively.
It is of interest to compare I and S with the same lower expense of formwork for the taller S. Although
structural system. Without structural quantities of there may be many issues to be considered in the
foundation, these buildings utilized almost the same high-rise building construction, special respect should be
unit quantities of concrete and presented a 15 % given to the selection of proper cost-effective formwork
difference in the usage of reinforcement. For taller S system for reinforced concrete structures. Efficient
building, relatively more reinforcement was used for planning of formwork activity may significantly reduce
vertical members. The discrepancy might occur due to the construction cost of tall buildings.
differential effectiveness of lateral/vertical load The unit construction costs for structural materials are
resisting systems of the buildings. rearranged into unit costs for structural members
The tallest C utilized the largest structural material including formwork cost in Table 5. Note that itemized
quantities, which are 5 to 7 % more than the unit construction cost comparison for I and S yields almost
material quantities of S building. It is noted that, for C, similar unit cost result for each structural member, while
more concrete and reinforcement were used for vertical C has a considerably different pattern of cost
members with less materials for slab, compared to I and composition. Wall cost of C, which was designed against
S. Unlike the other buildings, cumulative material relatively strong wind in coastal area, is 89,671 won/m2,
amounts of vertical members of C reaches more than approximately two times those of the other projects,
50 % of total unit material quantities. occupying 52.3 % of total structural cost, due to a large
Through the similar process as for the previous cost increase for its structural and formwork quantities.
composite structures, Table 5 shows the unit costs of This steep cost increase for wall member of the taller C
148,430, 157,618 and 171,455 won/m2, for I, S and C, seems to be the main reason why the difference of
respectively. Although total unit cost increases with construction cost between S and C becomes larger than
height, the costs of I and S with the same structural their material quantity gap of Table 4.
system in Seoul differs only by 6.2 %, while that of C Overall construction costs for vertical members
building with a different system in Busan gives a big occupy 52.8, 47.4 and 58.3 % for I, S and C,
difference of 15.5 %. respectively, which appear to be bigger than their
Unit cost comparison per material shows the cost proportions of materials in Table 4. As noted from the
composition of three buildings well. The total formwork wall structure for C, vertical members of tall buildings
cost of C is 70,983 won/m2, which is much higher than in general seem to require more construction cost than
61,153 and 53,117 won/m2 of the other structures. Total other horizontal structural members. Therefore, a
unit material cost without formwork occupies 58 to 66 % structural design with smaller structural material
of total construction cost, so that overall formwork cost quantities for vertical members of tall buildings is
for reinforced concrete buildings ranges 34 to 42 % of desirable for more economic structural construction.
total structural cost. This result is in contrast with 14 to Similar to the foundation result for the previous
19 % in the composite structures. A relatively large gap composite structures, cost comparison for three
between the structural material quantities of I and S in reinforced concrete structures shows considerable
Table 4 becomes reduced in the construction cost economic advantage of the combined footings of I
comparison between the two buildings mostly due to over all mat systems of the other projects. Although
Table 5. Unit direct construction costs for tall composite building structures
Unit Cost per Material Unit Cost for Structural Members Unit Cost
Project
Material *Won/m2 % Str. Mem. *Won/m2 % Comparison
Concrete 42,154 28.4 Wall + Link 48,685 32.8
Reinforcement 45,123 30.4 Column 29,686 20.0
I(46F) Formwork 61,153 41.2 Slab 67,172 45.3 100
Foundation 2,887 1.9
Total 148,430 100 Total 148,430 100
Concrete 45,236 28.7 Wall + Link 43,818 27.8
Reinforcement 55,797 35.4 Column 30,893 19.6
Str. Steel 3,468 2.2 Slab 63,835 40.5
S(50F) 106.2
Formwork 53,117 33.7 Beam 7,408 4.7
Foundation 11,664 7.4
Total 157,618 100 Total 157,618 100
Concrete 44,235 25.8 Wall 89,671 52.3
Reinforcement 56,237 32.8 Column 10,288 6.0
Formwork 70,983 41.4 Slab 41,835 24.4
C(53F) Beam 16,631 9.7 115.5
Outrigger 4,286 2.5
Foundation 8,744 5.1
Total 171,455 100 Total 171,455 100
* $1 # 1,200 Won