Professional Documents
Culture Documents
WASMReinforcement Case Studies Thompson Villaescusa 2014
WASMReinforcement Case Studies Thompson Villaescusa 2014
net/publication/270275406
CITATIONS READS
14 3,299
2 authors, including:
Ernesto Villaescusa
WA School of Mines - Curtin University Australia
163 PUBLICATIONS 1,438 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Ernesto Villaescusa on 02 February 2015.
Thompson, A.G
CRCMining/Western Australian School of Mines-Curtin University, Locked Bag 30, Kalgoorlie, WA,
6430, Australia
Email: A.Thompson@curtin.edu.au Ph: +61 8 9088 6162 Fax: +61 8 9088 6151
Villaescusa, E.
CRCMining/Western Australian School of Mines-Curtin University, Locked Bag 30, Kalgoorlie, WA,
6430, Australia
ABSTRACT: Rock reinforcement is widely used in tunnels and surface and underground mines. A large
number of proprietary products are available in various configurations of components. While the mechanical
properties of the primary element are available from product brochures, the associated component properties
may vary widely and adversely influence the overall performance of the system. Field pull out tests are most
commonly used to measure the system response in the toe anchor region. However, the response of the collar
region is less commonly considered but maybe more important. Several case studies are described in which
various components and systems of rock bolts and cable bolts have been subjected to static loading in the
laboratory and in the field. The results generally demonstrate the importance of considering the properties of all
the components and not simply those of the primary element. In some cases, the internal fixtures have strengths
much less than the elements. Often it has also been found that the fixture at the collar has significantly less
strength than the element and this will result in complete loss of function in restraining surface support hardware
such as plates, mesh and reinforced shotcrete.
Keywords: rock reinforcement, laboratory testing, field testing, case studies, rock bolts, cable bolts
1. INTRODUCTION
During more than two decades the writers have been involved in performing tests on rock reinforcement
components and systems. The need for testing has mostly arisen due to uncertainties associated with one or
more of the hardware components and the interactions between them. Often, the rock has not been recognised
by both hardware suppliers and their clients as being the most critical component influencing the overall
performance of a reinforcement system.
The results from a number of case studies will be presented to highlight some of the issues that have been
identified with various different reinforcement components and systems. In some instances, detailed
examination of the behaviour mechanisms and associated theoretical calculations are used to explain and
interpret the testing results.
The case studies to be presented have been divided into reinforcement component testing and system testing.
The component testing case studies demonstrate the test configurations used to define the mechanical properties
of basic elements, internal fixtures and external fixtures. Reinforcement systems testing case studies involve
both laboratory simulations and in situ performance evaluations.
2. REINFORCEMENT SYSTEMS
In order to fully understand the likely performance of different reinforcement systems in various rock masses, it
is firstly worthwhile reviewing the basic system components and how they interact in response to rock
movements. Reinforcement systems can be considered to be comprised of four components (i.e. rock, element,
internal and external fixtures) as shown in Fig. 1 with their interactions. It was detailed by Windsor and
Thompson (1993) that the basic function of a reinforcement system is to transfer load from the potentially
unstable region near an excavation to a stable region beyond the depth of instability as shown in Fig. 2.
1
0
2
1 3
COMPONENTS INTERACTIONS
0 The Rock 0 2
1 The Element 1 2
2 The Internal Fixture 1 3
3 The External Fixture 3 0
Flange welded
to anchor pipe
Embedment length
Embedment length
inInanchor
anchor zone l Stiffened
zone
ologica ity Deep Beam
ge ontinu
disc
Reinforcemen
Interface
Flange welded
to collar pipe
Collar zone
Collar zone Loading mass
comprising
steel disks
clamped to
Block
Block flange
Movement
Movement
Buffer Buffer
Plate External
Fixture
More recently (Thompson et al. 2012), it was verified that the original classification by Windsor and Thompson
(1993) of all reinforcement systems into one of three categories remained valid. The three categories, based on
the load transfer mechanisms between the reinforcement element and the rock surrounding the borehole, are:
CMC-Continuously Mechanically Coupled
CFC-Continuously Frictionally Coupled
DMFC-Discrete Mechanically or Frictionally Coupled
Examples of reinforcement systems within each of the categories are given in Table 1
Table 1 Classification of selected reinforcement systems
Category Description
Full column cement/resin grouted deformed bar
CMC
Cement grouted Standard Birdcage or Bulbed
Continuously Mechanically Coupled
strand
Friction rock stabilisers
CFC Continuously Frictionally Coupled Split tube (e.g. Split Set)
Expanded tube (e.g. Swellex, Omega)
Mechanical anchors
Expansion shell, wedge
Short cement/resin encapsulation
DMFC
Paddle , deformed bar
Discrete Mechanically or Frictionally Coupled
High deformation bolts
Cone, Modified Cone, Garford Solid Dynamic,
Roofex, D-Bolt
2
3. TESTING DOCUMENTATION
The basic principles outlined above have been used to design appropriate tests to measure the component
properties and the interactions between them within a reinforcement system. The results of testing programs are
often poorly documented. It is probably true to say that over reporting of the details of testing is preferable to the
omission of crucial information required for interpretation and use at a later time. The documentation required for
both laboratory and field test programs are essentially the same.
The documentation should include a complete description of each of the four generic components given in
Fig. 1 together with their physical and mechanical properties and their configuration for the test. The equipment
and methods used for sample preparation and installation prior to testing should all be detailed. An important
aspect of documentation is the date of sample preparation. The equipment used for loading and instrumentation
for recording data should be documented in detail. Again, the date of testing is a crucial piece of information,
especially for reinforcement systems that involve materials that have properties that change with time. Finally,
the results should be presented in an unambiguous way as recommended in Thompson et al. 2013). This is essential if
the information is to be used in analysis software or design where the system configuration is different from the test
configurations. For example, Table 2 provides a comprehensive check list for the information to be documented for
reinforcement component and system testing in the laboratory or in situ
Table 2 Check lists for component testing and system testing the laboratory or in situ.
Basic Information
System Components
Element
External Fixture
Internal Fixture
Component Materials
Physical Properties
Mechanical Properties
Component Testing
Element
External fixture
Plate
Laboratory Testing In Situ Testing
Borehole Formation Borehole Formation
Pipe material and dimensions Rock type and properties
Specimen and Test Configuration Borehole diameter or bit size
Lengths in double embedment test Specimen and Test Configuration
Date of sample preparation Anchor length and free length
Date of testing Date of installation
Equipment Used Date of testing
Testing machine Equipment Used
Monitoring Devices Hydraulic cylinder and pump
Load and displacement Monitoring Devices
Data Recording Load and displacement
Manual or data logger Data Recording
Test Procedure Manual or data logger
Loading or displacement rate Test procedure
Loading rate
Testing Results
Raw Data
Data Processing
Presentation of Results
Force-displacement response of anchor
Comments on Test Results
4. COMPONENT TESTING
The details of component testing can be found in various codes (e.g. ASTM 2010; Standards Australia 2007a,
2007b; British Standards 2007). It should be expected that reinforcement component manufacturers and
suppliers have conducted tests prior to making components available commercially. However the reality in some
3
cases is that components with apparently similar dimensions may have vastly different mechanical properties. In
extreme cases, there have been instances where the physical dimensions have varied to make it impossible to
assemble threaded components or threads have failed at forces much less than the rated force capacity of the
element. Consequently, dimensional checks and mechanical tests should be undertaken should any changes be
made in the metallurgical composition or manufacturing process of any components of a reinforcement system.
This may include the change in the supplier or type of cement used for forming a grout for encapsulation. A
change in the cement particle size distribution will completely change the physical properties of the grout in the
fluid state at a particular water/cement ratio and the strength of the cured and hardened material.
In addition to testing following any changes that may result in variation of physical and mechanical properties,
quality assurance testing of components should be undertaken at regular intervals. In the case of steel pre-
stressing strand used to form cable bolts, tests are conducted on each coil of material and may result in rejection
at this stage. ASTM F432-10 specifies that “The manufacturer shall select and test a minimum of two bolts,
threaded bars, threaded slotted bars, bearing and header plates, frictional anchorage devices, and washers
from each discontinuous turn or each 24 h of continuous production.” The frequency of testing of installed rock
reinforcement systems is usually less prescriptive in mining. Some regulatory authorities may suggest 5% of
bolts but it is unlikely that this number of bolts is tested. The frequency of testing for ground anchors used in
civil construction is governed by various codes of practice (e.g. British Standards 1989; Standards Australia
1973).
A solution to this problem was found by having a custom designed barrel with two tapered wedges as shown in
Fig. 4. The anchor is designed so that the wedges do not get jammed between the barrel and strand. Fig. 5 shows
the difference between non-complying results and a complying test with ultimate strain >3.5%. An additional
benefit is that the set of wedges intermediate between the barrel and standard three-part wedges has an outer
taper that allows for easy release of the anchor following a test; otherwise, the strand must be cut to remove it
from the testing machine.
4
Fig. 4 Special barrel and wedge for strand testing
250
200
Force (kN)
150
100
50
0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
Strain (%)
Fig. 5 Chart showing non-complying (Strand#1 and Strand#2) and complying (Strand#3) force-strain curves for
15.2mm diameter strand
5
Fig. 6 Electronic displacement transducers mounted with a gauge length of 500mm on deformed bar
300
250
200
Force (kN)
150
100
50
0
0.0 5.0 10.0 15.0 20.0
Strain (%)
It is worth noting at this point that bonded strain gauges used for field instrumentation studies will be limited to
measurement of less than about 3% strain. For measurement of >3% strains, mechanical devices are required to
measure relative displacement between anchor points located apart by a known gauge length (e.g. Hyett et al.
2012). However, as detailed by Thompson and Windsor (1993), the average strain over the gauge may under-
estimate the peak strain for a continuously coupled reinforcement system, especially if the gauge does not span
across a dilating discontinuity in the rock mass.
6
The Kiruna bolt is designed to be inserted in a borehole that has been pre-filled with cement grout with the
objective of being a “one-pass” system with the slot and wedge anchor providing immediate reinforcement
action prior to curing of the cement grout. An attempt was made in the 1990s to introduce these bolts or an
alternative slot and wedge bolt in an Australian mine. The anchor sections are shown in Fig. 8.
A systematic study examined the feasibility of using either of these bolts with the available mechanized drilling
and installation equipment. One part of the study looked solely at the geometry of the slot and wedge anchor and
borehole. A complementary program of testing was used to assess the strength of the slot and wedge anchors.
The first change to both bolts was the decision to increase the recommended borehole diameter from 32mm to
36mm. The consequences of this change became quickly apparent simply by examining the geometry of the
anchors and the wedge movement necessary to cause the element to expand radially and interact with the
borehole. For 36mm diameter boreholes, it was predicted that the slot lengths needed to be >90mm (Kiruna
bolt) and >105mm (alternative bolt) compared with the actual lengths of 103mm and 150mm, respectively.
However, the formed boreholes were actually larger and in soft rock the wedge displacements also needed to be
greater than the available slot length.
Pull tests were performed on both bolt types. The maximum forces recorded for the Kiruna bolt varied between
<5kN in soft rock to ~12kN in hard rock. The maximum forces for the alternative bolt were 35kN in soft rock
and up to ~70kN in hard rock. In both cases, these initial anchorage values were deemed to be unacceptably low
and neither bolt was implemented.
7
It is the writers’ belief that element rotation with the bail located without the end of the borehole reaction may
be responsible for instances of untensionable bolts due to breakage of the bail and misalignment of the leaves; or
possibly one or both leaves dropping past the cone.
Assuming that the anchor is set properly within the borehole, there are other considerations as to the
effectiveness of the anchor. Equations involving the anchor geometry and equilibrium of the forces shown in
Fig. 10 may be used to show that:
b r (1)
D/2
cone rock
SB SR
L
N
R
SB
SR
shell
Fig. 10 Expansion shell anchor geometry showing the internal and external forces
Eq. (1) indicates that the friction angle for the interface between the cone and the inner leaf surface must be less
than the friction angle for the interface between the outer shell and the rock by an amount greater than the taper
angle of the cone and inner leaf interface. In many cases, this condition is unlikely to be achieved because
anchors are manufactured from cast components with an inherent roughness; the friction angle associated with
this less than smooth surface is then often increased following zinc coating.
8
The radial (R) and longitudinal (SR) forces at the interface between the shell and the rock shown in Fig. 10 can
be converted to approximate equivalent normal (r) and longitudinal () stresses by the following equations:
T
r (2)
DL tan b
T
(3)
DL
9
Fig. 11 Set up of split tube ring and combined domed and large plate prior to tension test.
10
= wedge taper angle
In particular it was shown, both theoretically and by measurement, that the maximum tension is only about 40%
of the applied peak force when the installation force is applied to directly to the wedge. That is, the tension in
the strand, and also between the plate and rock, was about 36kN after applying an installation force of 100kN
(footnote b in Table 3).
The in-service performance of barrel and wedge strand anchors has often been poor (e.g. Thompson 2004;
Hassell et al. 2006). The anchors have been observed to slip relative to the strand as shown in Fig. 13 and to
provide little resistance to rock movements; in some cases, the anchors are missing resulting in complete loss of
restraint for surface hardware such as plates and mesh or shotcrete and the nearby rock.
Systematic laboratory studies were conducted by Thompson (2004) on several barrel and wedge anchor
specimens. Table 3 provides the details of the initial anchor installations and their conditions at the time of
testing. Corrosion was permitted to develop by keeping the anchors in humid conditions, with access to oxygen,
inside a semi-sealed tube. The surface conditions of new and corroded anchors are shown in Fig. 14.
Table 3 Anchor installation and condition at time of testing
11
Fig. 14 Comparison of new anchor with anchor subjected to 6 months exposure in a mildly corrosive artificial
environment
Error! Not a valid bookmark self-reference. provides a summary of the peak and residual forces measured
for all the specimens tested and the failure modes. Apart from the control test specimens 1 and 2 used to confirm
that anchors can mobilise the strength of the strand. All other anchors failed by slipping of the strand within the
anchors at forces less than about 20% of the strand force capacity. This is attributed to the inability of the wedge
to slide relative to the barrel as a result of corrosion.
Table 4 Summary of anchor strengths
Peak Residual
No. Force Force Failure Mode
(kN) (kN)
1/2 >250 0 Rupture of one or two wires
3 ~22 ~10 Wedge/strand interface slip
4 ~50 ~13 Wedge/strand interface slip
5 ~45 ~20 Wedge/strand interface slip
6 ~50 ~25 Wedge/strand interface slip
7 ~45 ~20 Wedge/strand interface slip
8 ~55 ~30 Wedge/strand interface slip
12
Cadby (1981) showed the importance of further reducing the bearing friction through the use of different low
friction material washers placed between the nut and underlying steel washer.
Computer software has been developed by the first writer to simulate the various threads used for rock bolts.
These threads include “fine” machined metric threads and “coarse” rolled threads. The major differences in
these threads are the pitch and general surface conditions that result. The software includes a database of these
different thread types and the friction coefficients associated with various thread conditions ranging from
smooth, lubricated surfaces to rough, corroded surfaces. Software simulations will now be used to demonstrate
for a single applied torque level the large variability of bolt tensions that can result for different threads and
surface conditions. Table 5 presents a selection of results for the element tension resulting from the application
of 200Nm torque to the nut. Apart for the wide variation of tension values, the features of the results are:
The tension is lower for larger diameter bolts.
The tension is lower for a coarse thread compared with a fine thread.
Light lubrication increases the tension by about 25%.
Corrosion reduces the tension by about 30%.
The use of grease and a friction reducing washer can substantially increase the tension.
It is the writers’ opinion that in most mining operations Clean and Dry installation conditions are at best used. It
is also apparent that a single value of installation torque is not appropriate for all the different threads with
which rock bolts are provided. It should also be noted that coarse threads are more susceptible than fine threads
to loosening by vibration. This is consistent with the measurements made of lower torques required to loosen
nuts on coarse threads than fine threads.
Table 5 Variation of element tension for different threads and installation conditions
13
StrandPlate1 StrandPlate2 StrandPlate3
250
200
Force (kN)
150
100
50
0
0 10 20 30 40
Displacement (mm)
Fig. 16 Results for tests on flat plates used with cable bolts
8. SYSTEMS TESTING
It is first worthwhile to state that it is virtually impossible in a field test to measure the overall response of a
reinforcement system. The main reason for this is that it is not possible to cause and measure the dilation of an
internal discontinuity. In an axial pull test, the measured response is a combination of element displacement
relative to the rock in the toe anchor region and the extension of the element between the anchor region and the
point of application of the loading.
On the other hand, in the laboratory, it is possible to conduct a test as shown in Fig. 17 in which the overall
system response can be measured. This type of test was first used in the late 1970s and early 1980s in Australia
(e.g. Fuller and Cox 1975;Hutchins et al. 1990) and has continued to be used routinely (e.g. Villaescusa and
Wright 1997, 1999; Thompson et al. 2004). The test has become known as the double embedment or split pipe
test and originally used equal embedment lengths to facilitate data processing by assuming approximately equal
pull out from either side of the simulated discontinuity. The double embedment test has subsequently been
adopted by other organisations in a number of countries such as the USA (e.g. Goris 1990a, 1990b), Canada
(e.g. Bawden et al. 1992), Finland (e.g. Satola and Aromaa 2004) and UK (e.g. British standards 2009). In some
of these test programs, unequal embedment lengths were used resulting in less certain contributions to the total
discontinuity separation. The test configuration was ideally suited to CMC systems. In more recent testing
programs, the WA School of Mines has developed a procedure for manufacturing simulated boreholes in which
friction rock stabilisers have been installed and tested (Player et al. 2009). These simulated boreholes have
subsequently been used for resin encapsulated rock bolts and may also be used to assess the performance of
expansion shell anchors.
14
Grouted Pipe Embedment
Length 1
Simulated
Discontinuity
Embedment
Reinforcement
Length 2
Element
Fig. 18 Secura and Posimix bolts showing paddle and spiral mixing arrangements, respectively
Despite the modifications to enhance mixing, problems associated mainly with larger diameter boreholes still
occur. Unreported case studies have shown that drilling in soft rock may result in borehole diameters in excess
of 1cm greater than the bit size due to erosion by the drilling water. The problems with large boreholes include
poor mixing, often near the toe of the borehole due to over-drilling the length, gloving due to the bolt punching
through the cartridge, over spinning resulting in damage to the partially cured resin and loss of effective
encapsulation length. Many of these problems cannot be identified from in situ pull out tests.
A purpose-built drill rig (Fig. 19) capable of overcoring reinforcement elements within a production mining
environment was developed in order to undertake a systematic investigation of the entire length of fully
encapsulated rock bolts in situ. The investigations reported in detail by Villaescusa et al. (2008) involved both
visual inspections by splitting the recovered rock cores containing the bolts and laboratory tests on samples such
as those shown in Fig. 20.
15
Fig. 19 WASM bolt overcoring operations
The overcoring data show that the best resin mixing and bolt encapsulation occurs within the middle region of
the bolt for the majority of the current bolt and borehole size combinations, reinforcement systems and
installation practices used in the Australian hard rock mining industry. In all cases of low load transfer, poor
resin mixing was identified as the main cause. In addition, the majority of the overcored bolts had no resin at the
collar region, indicating that effective plating of the bolts is very important for long term effectiveness. The
worst conditions in terms of encapsulation and load transfer were found towards the toe region of the bolts.
16
Theoretical considerations detailed in Thompson and Finn (1999) showed that the increase in load transfer could
be associated mainly with the strength of the cement grout and the area of contact with rock along the split in the
tube. This is confirmed by the results given in Table 6 where the increase in resistance to pull out is more
pronounced for the larger borehole (i.e. wider slot) and also by the observations reported in Villaescusa and
Wright (1997) where the pull out strengths showed a steady increase when measured at 2, 3, 4, 5.5 and 7 hours
after grout placement. It was also found that the pull out strengths were higher with lower water/cement ratio,
higher strength, grouts. Other factors that may affect the load transfer include the higher resistance to radial
compression and deviations in the borehole diameter profile. It is worth noting that measured borehole profiles
show that diameter generally decreases towards the toe of the borehole.
Table 6 Summary of peak loads recorded in pull tests on Split Sets before and after grouting
17
300
Embedment
>2500
Length (mm)
Force (kN)
200
1500
1000
100
500
0 10 20 30
Displacement (mm)
Fig. 21 CMC reinforcement system responses for different embedment lengths of plain strand
300
Rupture Force (265 kN)
250
Peak Force (kN)
200
Sliding
150 Rupture
100 Critical
Length
50 (2200 mm)
0
0 1000 2000 3000 4000
Encapsulation Length (mm)
Fig. 22 Extrapolation used to predict critical embedment length for cement encapsulated strand cable bolts
18
The external fixture case studies showed that the force capacity available for restraint of surface hardware such
as mesh may be far less than the element capacity; that is, punching failure through a plate, failure of a split tube
ring or sliding of a barrel and wedge anchor.
Other issues, not directly related to testing, that arose during the case studies were the important influences that
installation conditions have on the subsequent performance of reinforcement systems. This applied to all internal
and external fixtures. The importance of clean and lubricated surfaces was clearly demonstrated for threaded
internal and external fixtures and for barrel and wedge anchors used in conjunction with cable bolts.
In conclusion, the component test results presented clearly demonstrate that the element strength should not be
used as the sole indicator of likely maximum force capacity of the overall reinforcement system.
ACKNOWLEDGEMENTS
The writers wish to acknowledge the following organisations for their support over many years going back to
the late 1970s; CSIRO, AMIRA International, Rock Technology Pty Ltd, WA School of Mines/Curtin
University, CRCMining, and the many other supporting organisations including mining companies and
reinforcement suppliers. The contributions of many colleagues are also gratefully acknowledged.
REFERENCES
ASTM (2010) F432-10 Standard Specification for Roof, Rock Bolts, Accessories, 18p, ASTM, West
Conshohocken
Bawden WF, Hyett AJ, Lausch P (1992) An experimental procedure for the in situ testing of cable bolts Int J
Rock Mech Min Sc, Geoemech Abstr, 29(1), 525-533, Pergamon, London
British Standards (1989). BS 8081-89 Code of practice for Ground anchorages,176p, BSi, London
British Standards (2007) BS 7861-1:2007 Strata reinforcement support system components used in coal mines –
Part 1: Specification for rock bolting, 44p,BSi, London
British Standards (2009) BS 7861-2:2009 Strata reinforcement support systems components used in coal mines
– Part 2: Specification for flexible systems for roof reinforcement, 48p, BSi, London
Fuller PG, Cadby GW (1981) Pre-tensioning Rock Bolts, Technical Report No 113, CSIRO, Melbourne
Fuller PG, Cox RHT (1975) Mechanics of load transfer from steel tendons to cement based grout In: Proc 5th
Aust Conf on the Mechanics of Structures, Materials, 189-203, Melbourne
Goris JM (1990) Laboratory evaluation of cable bolt supports (in two parts) 1 Evaluations of supports using
conventional cables, USBM RI 9308
Goris JM 1990 Laboratory evaluation of cable bolt supports (in two parts) 2 Evaluations of supports using
conventional cables with steel buttons, birdcage cables, epoxy-coated cables, USBM RI 9342
Hassell RC, Villaescusa E, Thompson AG (2006) Testing, evaluation of corrosion on cable bolt anchors In: 41st
US Rock Mechanics Symposium, Golden, June 17-21, Paper 06-996, 11p, ARMA, Washington
Hoek E, Kaiser PK, Bawden WF (1995) Support of Underground Excavations in Hard Rock, 215p, Balkema,
Rotterdam
Hutchin WR, Bywater S, Thompson AG, Windsor CR (1990) A versatile grouted cable dowel reinforcing
system for rock The AusIMM Proceedings, No 1, 25-29, AusIMM. Melbourne
Hyett AJ, Mitri H, Spearing AJS (2012) Validation of two new technologies for monitoring the in situ
performance of rock bolts. AIMS 2012, 177-190, RWTH-Aachen University, Aachen.
Karabom GJ (1965) Variable mechanical roof bolt tension the causes and potential cures , 8p, United States.
Mining Enforcement and Safety Administration
Lang TA (1961) Theory and practice of rock bolting Trans Am Inst Min Metall Pet Eng, 220, 333-348
19
Malecki HN, Hardy MP, Brest van Kempen CJH (1985) Tension-Torque Relationship for Mechanical Anchored
Roof Bolts, In: 4th Int Conference on Ground Control, 18-25, West Virginia University, Morgantown
Player JR, Villaescusa E, Thompson AG (2009) Dynamic testing of friction rock stabilisers In: Diederichs M,
Grasselli G (eds), RockEng09, Rock Engineering in Difficult Conditions, Toronto, 9-15 May, Paper 4027, 12p,
CIM, Montreal
Rosso RS (1977) An investigation of the effects of hardened washers on the uniformity of roof bolt tension and
resulting ground control in an underground mine, , OFR78-40, 201p, USBM Office of the Assistant Director-
Mining, Salt Lake City
Satola I, Aromaa J (2004) The corrosion of rock bolts, cable bolts In: Villaescusa E, Potvin Y (eds), Ground
Support in Mining and Underground Construction, Balkema, Leiden, 521-528
Standards Australia (1973) Ground anchorages. In Prestressed Concrete Code CA35, 50-53, Standards
Australia, Sydney
Standards Australia (2007a) ASNZS 46721:2007 Steel prestressing materials Part 1: General requirements, 44p,
Standards Australia, Sydney
Standards Australia (2007b) ASNZS 46721:2007 Steel prestressing materials Part 2: Testing requirements, 16p,
Standards Australia, Sydney
Thompson AG, (1992) Tensioning reinforcing cables In: Proc Int Symp on Rock Support, Sudbury June 5-9,
eds PK Kaiser, DR McCreath, 285-291, Balkema, Rotterdam
Thompson AG (2004) Performance of cable bolt anchors – An Update In: Karzulovic A, Alfaro MA (eds),
MassMin2004, Santiago, August 22-25, Instituto de Ingenerios de Chile, Santiago,, 317-323
Thompson AG, Finn DJ (1999) The performance of grouted split tube rock bolt systems In: Rock Support and
Reinforcement Practice Villaescusa E, Potvin Y (eds), Ground Support in Mining and Underground
Construction, Balkema, Leiden, 91-102
Thompson AG, Player JR, Villaescusa E (2004) Simulation, analysis of dynamically loaded reinforcement
systems Villaescusa E, Potvin Y (eds), Ground Support in Mining and Underground Construction, Balkema,
Leiden, 341-358
Thompson AG, Villaescusa E, Windsor CR (2012) Ground Support Terminology and Classification: An Update
Journal of Geotechnical and Geological Engineering, 30(3), 553-580
Thompson AG, Villaescusa E, Windsor CR (2013) Planning, documenting reinforcement system test programs
In: Anagnostou G, Ehrbar H (eds), World Tunnel Congress 2013 Underground – the way to the future, Geneva
24-31 May, Paper 1534, 8p
Thompson AG, Windsor CR (1993) Theory and Strategy for Monitoring the Performance of Rock
Reinforcement. Proc. Australian Conference on Geotechnical Instrumentation and Monitoring in Open Pit and
Underground Mining, Kalgoorlie, 21-23 June, 473-482,: Balkema, Rotterdam
Thompson AG, Windsor CR (1995) Tensioned cable bolt reinforcement – an integrated case study In Proc 8th
Int Cong on Rock Mechanics, Tokyo, June, V2, 679-683, Balkema, Rotterdam
Thompson AG, Windsor CR (1998) Cement grouts in theory and reinforcement practice In: Proc of NARMS
98,Cancun, Paper Aus-330-2, 10p
Villaescusa E, Varden R, Hassell R (2008) Quantifying the performance of resin anchored rock bolts in the
Australian underground hard rock mining industry Int J Rock Mech, Min Sc, 45, 94-102, Elsevier, London
Villaescusa E, Wright J (1997) Permanent excavation support using cement grouted Split Set bolts The
AusIMM Proceedings, No 1, 65-69, AusIMM, Melbourne
20
Villaescusa E, Wright J (1999) Reinforcement of underground excavations using the CT Bolt In: Villaescusa E,
Windsor CR, Thompson AG (eds) Rock Support and Reinforcement Practice in Mining, Balkema, Rotterdam,
109-115
Windsor CR, Thompson AG (1993) Rock reinforcement - Technology, testing, design and evaluation In:
Hudson JA (ed), Comprehensive Rock Engineering, Pergamon, Oxford, Volume 4, Chapter 16, 451-484
21