LETTER OF APPROVAL/COMMENTS FOR DRAWING / DOCUMENTS

Client : Gujarat State Electricity Corporation Limited (GSECL)


Project : EPC with three years O&M for TTP and partial RO plant
for Treatment of TSW along with potable water scheme
from sweet water at Bhavnagar Lignite Thermal Power
701,Rembrandt,Opp.Associated Petrol
Pump, C.G Road, Ellis bridge,
Station, Padva.
Ahmedabad-380006 Contractor : Gharpure Engineering & Constructions (P) Limited
Unit / Eqpt Name : Plant Earthing Layout
Date: 27.09.2022
We here with convey our approval/comments on the documents listed below. Review of drawings/ documents in
accordance with contract Documents does not absolve Vendor/contractor from any responsibilities for their accuracy
of the design, performance and safety of the plant / works or any other obligations under the contract and Indian
Statutory laws nor does it limit the employer’s rights under the contract. Drawing / Document approval shall be read
in conjunction with this comments letter.

DRAWING / DOCUMENT REVIEW STATUS


D: Not accepted Insufficient details. Return
A: Approved for construction / Manufacture.
without review.
B: Approved with comments. Construction/ E: Retained for Information only.
Manufacture may commence subject to
compliance of comments, Resubmit for review
and approval.
C: Resubmit for review after incorporating
comments.

Sr. Drg. / Doc. Description Rev.


No. No.
1 Plant Earthing Layout (Doc. No.: 00286-DEP-EE-DWG-009) (Transmittal No._170, dtd.29/08/2022) R2

Comments
 It shall be contractor responsibility to install Grid conductor length 120Mt. considered laid along the length of
plant area & Grid conductor length 100Mt. considered laid along the width of plant area for earthing
calculation. Approval shall be subject to same.
 Galvanizing of GI Earthing strip considered shall be as per IS:2629 as per tender.
 Earthing for Lightning system as per IS:2309 shall be provided as per tender / statutory authority requirements.
 The earthing strip quantity is reviewed as per the length considered by contractor. Contractor shall have to
provide the earthing strip length / quantity on higher side, if required at site, as per site condition / requirements.
 Contractor to ensure that earth resistance shall not exceed 1Ω at any point and shall provide additional earth pits
/ strips, if required at site, as per IS-3043:2018 / Tender specification.
 It will be contractor responsibility to demonstrate and to measure earth resistance at any point of Earthing
system shall be less than one ohm / as per latest statutory norms requirements to Engg.-In-Charge of client.
 Provide Copper earth strip/ copper cable between PLC Panel and Earth pit as per specification.
 For Instrument earth pit provide copper pipe as per specification.