Professional Documents
Culture Documents
Civ3205 Principles of Quantity Surveying I - Ok (First) - 1
Civ3205 Principles of Quantity Surveying I - Ok (First) - 1
Semester 2 – 2019/2020
LECTURE NOTES
CHAPTER 1: INTRODUCTION
1.1 INTRODUCTION
If one wants to find out exactly what a house will cost, he/she has to take out the
quantities of the different items of construction involved in the house, and then, assuming
suitable market rates he has to arrive at the cost of the proposed house.
The subject of taking out the quantities, assuming suitable rates and working out the costs
of a house or any other civil engineering structure, is known as quantity surveying. This
Module will deal with one part of taking out the quantities of the different items of
construction involved in the house and other civil engineering works assuming that other
jobs (i.e., preparation of drawings, assuming suitable rates and working out the costs)
have already been done or will be done by the concerned parties.
There are two separate and distinct practices of measurement in use for civil
engineering works and building works. They are:
The comparisons between the two types of works that necessitate different
method of measurement are as follows:
The details of building works are usually in a far more precise stage at the time
of preparation of Bills of Quantities (BoQs) than in the case of Civil Engineering
works.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 1
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
excavation rates. In Civil Engineering works, one big item is deemed to include
different other smaller items.
Some rates in building works are very small as a result of small items measured
separately.
There is a greater risk in pricing civil engineering works than building works due to
the uncertainty nature of the works involved.
1.3.4 Variations
In building works, there are no much variations since almost all the items can be
measured with certainty. In the absence of variations in design most building works
(with the exception of sub-structure, drainage and external works) will not be
subject to re-measurements and the Contractor will be paid for the quantities
incorporated in the Bills of Quantities.
Building work Bills of Quantities fully describe and accurately represents the works
to be executed. If this cannot be achieved the works are described as provisional
or given a bill of approximate quantities.
In the Introduction to building works (BW), SMM state that more detailed
information than is demanded in the documents should be given where necessary
in order to define the precise nature and extent of the required. For Civil
Engineering (CE) BoQ, a list of items giving brief identifying description and
estimated quantities of the woks comprised in contract are given.
In some larger civil engineering contracts, there are also some building works, take
for example a large Power Station contract.
The best procedure would appear to measure the main superstructure, the
supplementary buildings and probably the chimneys in accordance with the SMM
for building works. The reminder of the power station comprising heavy foundation
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 2
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
of piling, cooling towers, roads, sewers etc. are best measured in accordance with
CESMM.
1.3.7 Administration
The structure of the team concerned with the construction of a civil engineering
project is similar to that for building works. In Civil engineering works, the head of
construction team is an Engineer assisted by a Resident Engineer while for
buildings is an Architect assisted by the Clerks of Works.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 3
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
2.1 Introduction
The purpose of measuring building works is to establish the correct amount of work
to be done. This involves producing accurate quantities in a way which is
comprehensive, technically accurate and clear in its approach and presentation.
A Project Manager may require the gross floor area of a proposed office block
to establish a building budget at the initial stages of contract.
On smaller projects, an Estimator may need to measure the quantities from the
tender drawings and specifications as part of a tender submission.
The Architect was responsible for the creation of buildings as well as their design,
and he/she employed a number of master craftsmen who performed the work in
each trade. On completion each master craftsmen submitted an account for the
materials used and labour employed on the work. The need for Quantity Surveyors
became obvious for the following reasons:
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 4
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
b) Building owners became dissatisfied with the method adopted for settling the
costs of the work.
c) Some Craftsmen were not conversant with the preparation of these cost
accounts and hence they engaged Surveyors or measurers.
e) Some of the Craftsmen made extravagant claims for the waste of material on
the site.
Due to the above reasons, general Contractors became established during the
period of the industrial revolution and they submitted inclusive estimates covering
the work of all trades. Furthermore, they engaged Surveyors to prepare bills of
quantities on which their estimates were based.
In later years, it became the practice to employ one Surveyor only who prepared
an accurate bill of quantities and measured any variation that arose during the
progress of the job. This was the origin of the independent and unbiased Quantity
Surveyor as he operates today.
This is a document which provides a uniform basis for measuring building works
and it represents the essentials of good practice. It provides the rules of measuring
all items in building works and also provides the units of items such as cubic,
square, linear etc.
2. Quantities
This refers to the estimated amounts of labour and materials required in the
execution of the various items of the work and together these items give the total
requirements of the building contract.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 5
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
3. Bills of Quantities
4. Taking off
This is the measuring of quantities in which the dimensions are scaled or read from
drawings and entered in a recognized form or a specially ruled paper, called a
“dimension paper”.
5. Working-up
This comprises the squaring of dimensions and transferring the resultant lengths,
areas and volumes to an “Abstract Sheet”.
6. Preambles
These are able clauses inserted at the head of each work section bill covering
matters relating to the specific work section that should be brought to the
attention of the estimator as they will affect the rates that he/she inserts against
billed items of measured work.
7. Preliminaries
These are items in the bill of quantities entered for the purpose of setting out all
general liabilities and obligations of the Contractor. These are items required to be
executed at pre-commencement of the actual required work, during the work
and after the work completion.
9. Contractor
Is a person or corporate body whose bid to carry out the works has been
accepted by the Employer and eventually engaged to undertake the works.
10. Employer/Client
Is the party who employs the Contractor to carry out the works.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 6
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
This is the Contractor responsible for the total construction and completion process
of the project.
12. Subcontractor
This Contractor is chosen by the Architect, Client or Engineer to carry out certain
aspects of the work. They are appointed on the expenditure of a provisional sum
or prime cost sum included in the contract bills.
This means the Contractor’s costs associated with head office administration
proportioned to each contract, plus the main Contractor’s return on capital
investment.
Sum for works which cannot be measure accurately during taking off. It is a sum
provided for work or for costs which cannot be entirely foreseen, defined or
detailed at the time of tendering documents are issued. E.g., testing of materials,
progress photographs and contingencies. The sum is to be used under instruction.
Sum provided for work which is not completely designed but for which the
following information shall be provided;
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 7
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Sum provided for work that is not completely designed but for which the
information required for a defined provisional sum cannot be provided.
Is an allowance in the contract for the supply of necessary items not yet finally
selected, e.g. taps or door furniture.
25. Variations
These are the alterations or modifications of the design, quality or quantity of works
as shown upon the contract drawings and described by or referred to in the
contract bills. This includes the additions, omissions or substitution of any work or
the alteration of the type of standard or any materials.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 8
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
26. Ditto/Do
27. Extra-over
Additional sum of money allowed for items of work; normally used where the work
has become slightly different from that originally measured.
For example fittings such as bends and junctions to drain pipes are measured as
‘extra over’. This means that the pipe is measured along its full length including the
fittings length and the estimator when pricing the item assesses the extra cost for
the fittings as “extra over” the pipe length.
When measuring certain items of work, they are described as being extra-over
another item which has been previously measured. The estimator will price for the
extra or additional cost involved in the second item as compared with the first
item.
A typical example is the measurement of rainwater pipe and gutter fittings as e.o
cost of the pipe or gutter in which they occur and which has been measured over
the fittings.
30. Credit
Means a refund offered by the Contractor to the Employer in return for the benefit
of taking ownership of materials, goods, items, mechanical/electrical plant and
equipment, etc. arising from demolition or strip out works.
31. Daywork
This means the method of valuing work on the basis of time spent by the
Contractor’s workpeople, the materials used and the plant employed.
The unfair cutting usually to brick/blockwork in walls and roof covering materials at
the hip and valley.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 9
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
This is a document that is used to record the main Contractor’s price for
completing the project (i.e. his/her tender price). If accepted by the Employer,
the tender price will become the ‘contract sum’. The form of tender can be a
separate document.
This means a cost estimate prepared immediately before calling Tenders for
construction.
This means a cost estimate carried out after the evaluation of tenders to
corroborate the funds required by the Employer to complete the project.
In any measurement there are a number of essential factors that should always be
considered and applied to follow good established practice. These include;
a) Examine the drawing carefully to become familiar with the work and to
identify any parts where information is lacking.
b) Interpret carefully and apply in a sound and logical way of provisions in the
Standard Method of Measurement of building works. (SMM).
f) Adopt a logical sequence of items so that each one follows the preceding
one in a natural progression.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 10
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
1. Bills of quantities shall fully describe and accurately represent the works to be
executed. The billed description is to be comprehensive and sufficient to
enable the Estimator to fully understand what is required and to give a realistic
price. Those works whose extent cannot be determined with reasonable
degree of accuracy should be described as “Provisional”.
5. Billed items are generally “deemed to include” i.e. without the need for specific
mention: labour; materials unloading, storing, handling; fixing; use of plant;
waste of materials; square cutting; establishment charges and profit. It is
essential that the estimator is fully aware of all these items as he must include
for them when building up unit rates.
6. Works under water shall be so described stating whether canal, river or sea
water and the levels of high and low water.
Measured items, scaled or taken from drawings are entered on a special paper
known as a ‘dimension paper’. This dimension sheet is split into two identically
ruled parts each consisting of four columns as follows:
1 2 3 4 1 2 3 4
Key:
Column 1 – “Timesing column”. In which multiplying figures are entered when
there is more than one of the particular items being measured.
3/ 5.00
This means that the length of 5.00 m of the same item appears three times in the
measured drawing.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 11
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
3/ 5.00 15.00
3.00
1.50
0.50
5.00
3/ 5.00 15.00 Hor. dpc. 110 wide of single layer
of hessian base bit. felt to BS
743 ref A, lapd. 100 at jts.
(mesd net) & bedded in cm (1.3).
“Hor. dpc………………..” are in “Description column”.
a) Order of Dimensions
b) Spacing of Items
It is essential that ample space is left between all items on the dimension sheets so
that it is possible to enable any items which may have been omitted when the
dimensions were first taken off to be subsequently inserted without cramping the
dimension disproportionately.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 12
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
4.00
0.69
0.23
c) Waste
The right hand side of the description column is used for preliminary calculations,
build-up of lengths, explanatory notes, location of measured work, etc. This should
not be overlooked. All steps that have been taken in arriving at dimensions, no
matter how elementary or trivial they may appear should be entered in the waste
section.
d) Timesing
If there were five such items, then this dimension would be multiplied by five in the
timesing column:
If it was subsequently found that four more items of the above of the same
dimensions were to be provided, then a further four could be added in the
timesing column by the process known as “dotting on”, as indicated in the
example.
e) Grouping of Dimensions
i) Where the same dimension applies to more than one item the best
procedure is to segregate each of the separate description by an “&” sign
and to bracket the descriptions.
ii) Where more than one set of dimensions relate to the same description, the
dimensions should be suitably bracketed.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 13
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Abbreviations are used in the description space in order to save space and time.
There are standard and acceptable abbreviations used in measurement such as:
When measuring areas of excavation, concrete oversite, blockwork, etc., the best
practice is to measure the full area in the first instance and, subsequently adjust for
any voids or openings. E.g., Adjustment for blockwork are done when “taking off
the windows and doors openings.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 14
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
22
/7/ 2.00 Area of circle with 2 m radius (Area = πr2)
2.00
Where it is required to omit dimensions which have previously been recorded the
easiest method is to write the word “NIL” in the squaring column as shown in the
following example.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 15
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
1. Sheets should be suitably headed with the title and section of the job at the
top and numbered at the bottom. Example Drawing 10, doors section can be
seen as below.
2. At the top of the first dimension sheet for a job, it is good practice to enter a list
of the drawings from which the measurements have been taken with the
precise drawing number of each contract drawing carefully recorded.
1.1
Doors
10.1
The order of “taking off” mostly follows the order of construction. In a simple
building the order of taking off would probably be as follows:
i) Site clearance,
ii) Foundations up to and including damp-proof courses (excavations, concrete
footings, block/brickwork, hardcore and concrete slab),
iii) Brickwork and facework,
iv) Blockwork,
v) Floors,
vi) Roofs (including coverings and rainwater installations),
vii) Finishings (walls, ceilings and floors),
viii) Windows (including adjustment of openings),
ix) Doors (including adjustment of openings),
x) Fittings,
xi) Stairs,
xii) Plumbing installation,
xiii) Drainage work,
xiv) Other Services (Electrical etc.),
xv) External works (roads, paths, fences and grassed areas).
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 16
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
4.9 Descriptions
b) Order of wording – the first few words of a description should clearly indicate
the nature of the item being described.
During examinations the candidate will have to decide the queries as they arise,
but it will often be desirable for him/her to indicate briefly in the “waste” why
he/she has adopted a certain cause of action.
A Query Sheet
S/N QUERY ANSWER
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 17
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
4.1.1 Substructure
It is very important that the ‘taking off’ process is done in a logical order. This
simplifies the process and reduces the risk of omission of items.
A. EXCAVATIONS:
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 18
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
The average depth of excavation over the site is most conveniently found
by suitably weighting the depth at each point on the grid of levels,
according to the area that each level affects.
This involves taking the depths at the extreme corners of the area once,
intermediate points on the boundary twice and all other intermediate
points four times. The sum of the weighted depths is divided by the total
number of weightings (number of squares x 4) to give the average
weighted depth for the whole area. This method can only be used when
the levels are spaced the same distance apart in both directions.
For example for foundation trench 2 m deep below the stripped level will
have to be split in two sections:
Example;
Girth
L W
11.100 6.500
Add: Walls = 2/230 0.460 0.460
11.560 6.960
depth Len.
420 11.560
add fdns. 230 6.960
650 2/18.520
37.040
Less: Corners, 4/230 = 0.920
36.120
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 19
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Working space is required if the face requires formwork. All reinforced in-situ
concrete require formwork hence working space should be provided.
For in-situ plain concrete footing, concrete is poured against the sides of trenches
hence no working space is required. Allowance for working space shall be made
in the as follows;
a) 0.30 m from the face work requiring formwork not exceeding 1 m high,
b) 2 m for trenches to receive post tensioned concrete ground beams
c) 1 m for work which is over 1 m high from below the starting level of excavation.
Excavating pits to receive columns, isolated piers and the like are given in
cubic meters stating the starting level and the depth. Allowances for
working space are to be considered depending on the depth of pits and
the formwork requirements.
c) Earth filling to make up levels: If the filling is over 300 mm thick, it shall be
given in cubic meters and for the filling less than 300 mm thick, it shall be
given in square meters stating the average thickness.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 20
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
5) Disposal of water Disposal of water –This is done to keep excavation free from
water and is given as an item.
6) Planking and strutting. - Earthwork support which include the use of timber to
uphold the sides of excavation, plywood trench sheeting and light steel
trench sheeting and strutting. It is measured to the sides of trenches and given
as an item (Section D19) or can be measured in square meters.
B. MEASUREMENT OF FOUNDATIONS:
When the excavation is complete, the excavated trench is filled with foundations
which include:
3) Formwork (Section F19). Formwork for most of the surfaces are given in square
meters classifying them in groups according to the position requiring formwork.
Solid floors
Hardcore – This is measured as equal to the area of the void being filled (D20 in
SMM).
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 21
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Damp proof membrane – This is laid on top of the hardcore and normally
measured in square meter. The description of Damp proof membrane must
include particulars of materials used, thickness/gauge, number of layers and
the nature of bedding (Section G96 –G97).
Example 1
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 22
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 23
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Solution:
Assume that the site is covered by coffee plantations, it has 2 no. tree stamps measuring 950 mm birth and it is sloping. It
is required to excavate down to a level of 2.00 m, including top soil to a depth of 150 mm.
WEIGHTED
GROUND DEPTH OF DEPTH OF
POINT LEVEL EXCAVATN. (m) WEIGHTING EXCAVATN. COMMENT
A4 2.250 0.25 1 0.25 To do weighting, you look at how
D4 3.000 1.00 1 1.00 much area in terms of the no. of
D1 4.500 2.50 1 2.50 squares that is likely to affect
A1 3.750 1.75 1 1.75 the depth at each point.
B4 2.500 0.50 2 1.00 If you remove topsoil and excavate
C4 2.750 0.75 2 1.50 without without reducing levels,
D3 3.500 1.50 2 3.00 then your stating point is strip
D2 4.000 2.00 2 4.00 off.
C1 4.250 2.25 2 4.50 If av. depth of excav. is less than
B1 4.000 2.00 2 4.00 300 mm, unit of measurement is
A2 3.250 1.25 2 2.50 m2; if greater than 300 mm, unit
A3 2.750 0.75 2 1.50 of measure is m3.
B3 3.000 1.00 4 4.00
C3 3.250 1.25 4 5.00
C2 3.750 1.75 4 7.00
B2 3.500 1.50 4 6.00
SUM (∑) ∑W = 36 ∑WD = 49.50
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 24
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
4/ 2.10
2.10
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 26
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
L W Hardcore
4.000 4.500
Less: 0.230 0.230 5/ 3.77 150 mm thick hardcore bed c/o
3.770 4.270
Plinths over pads: Ht. L
4.27 granite broken stones to pass 75
1.100 1.500 mm ring, well rammed &
Less: 0.350 0.230 compacted & blinded with 50 mm
0.750 2)1.270 bed of sand, fin. level to rec.
Add: 0.150 0.635
0.900
conc. bed (m/s).
&
8/ 3.77 230 mm wall in burnt clay bricks Anti-termite treatment with
0.62 bedded in C.M 1:4. approved chemical toxic to
hardcore bed.
8/ 4.27 L W
3.770 4.270
0.62
Add: 2/150 = 0.300 0.300
4.070 4.570
6/2/ 0.64
0.90 5/ 4.07 Polythene hor. DPM not less
4.57 than 1000 gauge lapd. 100 at
4/3/ 0.64
jts.
0.90
Concrete floor
2/4/ 0.64 L W
0.90 3/4.000 = 12.000 4.500
Add: 0.230 0.230
12.230 4.730
8/ 3.77 Ddt: R.f & r
0.23 & 12.23 100 mm thick plain conc. C25
0.47 Add: Remove surplus exc. matls. 4.73 Surface bed, laid on blinded h/c
from site. bed (m/s).
4.27 2/ 4.23
8/
0.23 4.50 &
0.47 Steel fabric reinft. in slab to
0.64 BS 4483 ref. A142 w.200
32/
0.23 mesh, weight. 2.22 kg/m2,
0.75 wi.100 min. end & side laps.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 27
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
2/ 12.23 Sawn fwk to edge of surface bed 3/4000 = 12.000 2/4500 = 9.000
Add: 0.230 0.230
over 75 mm but n.e 150 mm
2/ 9.23 12.230 9.230
birth. 12.230
2/ 4.50 2/21.460
42.920
Add: 2/4500 = 9.000
51.920
8/ 3.77 Damp-proof course
Asbestos based 3 ply bit. felt dpc 51.92 19 mm two coats of cement/sand
8/ 4.27 230 mm girth bedded in c.m 0.33 (1:4) rendering on brickwalls.
32/ 0.64 (1:4) on brickwalls. &
Prep. & apply two coats of
black bit. pt. to rendered walls
Rendering to plinth wall ext.
externally
Above g.l = 250 Item Allow for keeping excavations
Below g.l = 75
325
free from water.
4.1.3 Superstructures
Walling can be of blocks, bricks, concrete, natural stones and other light materials
recommended by the design team to be used for walling.
Measurements
It is essential to measure the wall in a sequential order starting with external wall,
internal wall together with their incidental works if any.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 28
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
b) External walls
The length of external walling will be obtained by the method of girthing and the
height will normally be taken up to some convenient level, such as the general
eaves line. Any additional areas of the external wall such as gables parapets, wall
up to higher eaves level, etc., will be then taken off.
In measuring the wall, the measurer takes the whole area regardless whether there
are some voids and the adjustment of wall for window and doors openings will be
made when measuring the windows and doors.
c) Internal walls
Roofs are of two types namely; Pitched roofs and flat roofs. Both types can
conveniently be subdivided into two main sections for purposes of measurement,
i.e. construction and coverings. The order of measurement of these two sections
varies in practice, but on balance it is probably better to take the construction first
as this follows the order of construction on site.
a) Construction
The order of items should follow a logical sequence such as plates, rafters, ceiling
joist, collars, purlins, struts, ridge boards, and hip and valley rafters.
i) Timber works
The roof timbers such as rafters, ceiling joist, collars, purlins, struts, fascia
board, barge board, hip and valley rafters are all measured in linear meters
stating the size (thickness x width),
Size – Thickness x Width,
Kind and quality of timber,
Preliminary treatment of timber (e.g. Pressure impregnated).
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 29
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Where roof sections are drawn to a sufficiently large scale, the easiest method is to
scale the length of rafter off the drawing, taking the length from one extremity to
other of the rafter.
b) Coverings
Roof covering are of various types such as slates or tiles, corrugated or troughed
sheets, thatch, bitumen felt, etc.
Measurements:
Kind of sheeting,
Quality and gauge of sheeting and type,
Extent of side and end laps,
Nature and general spacing of the structural supports (e.g. Purlins),
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 30
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Measurements:
Square cutting around openings, raking cuttings, curved cuttings, valleys, hips and
vertical angles shall be given in linear meter separately.
The main areas of asphalt are measured in square meters stating the thickness
and the number of coats of asphalt. Furthermore, the asphalt item is to include the
underlay of felt, cork, fibreboard or similar material and any reinforcement.
The unit of measurement is the square meter and it is classified by slope. Full
particulars of felt are to be given such as extent of laps, nature of base and
method of securing felt to it and the nature of surface treatment if any. The
measurement of the main areas of roof covering will be followed by such linear
items.
Example 2
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 31
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Solution 2:
PROPOSED APARTMENT AT NDEJJE TRADING CENTRE Dwg. SP/01/002
Superstructure
6/2/ 4.97 50 mm x 150 mm Tie beams in
Pitched Roof
lengths n.e 9.0 m long.
Timber roof construction 6/2/
Plates
1 E.O for dovetailed & scarfed
10.130 13.130 jts. in 50 mm x 150 mm timber.
Less
O’hg. at eaves, 2/425 0.850 0.850 6/2/ 3.99 50 mm x 150 mm Principal
9.280 12.280 rafters.
9.280
2/21.560 6/2/ 2.51 50 mm x 150 mm Collar beams.
43.120
Less 6/2/ 1.70 50 mm x 100 mm Ties &
Crns. 4/2/230 1.840
Len.on int. face 41.280
Struts.
Add 2/4.500 9.000
50.280 (End of 6No. trusses)
Add laps at crns. 4/100 0.400
50.680 The following in 3No. bolted
treated pine trusses span 3.77
50.68 100 mm x 75 mm treated pine m x 1.32 m rise incdg all next
wall plate bedded in c.m (1:4) gusset plates and 12 mm dia. ms
and secured to brick wall with bolts.
galv. steel hoop iron 900 mm at
2 m c/c. 3/2/ 4.39 50 mm x 150 mm Tie beams in
Rafters lengths n.e 9.0 m long.
13.130
Less 2/450 = 900 3/2/ 1 E.O for dovetailed & scarfed
2/230 = 460 jts. in 50 mm x 150 mm timber.
2/50 = 100 1.460
2.400)11.670 3/2/ 3.52 50 mm x 150 mm Principal
5+1 = 6
4.500 rafters.
Less 230
50 0.280 3/2/ 2.22 50 mm x 150 mm Collar beams.
2.400)4.220
2+1 = 3 3/2/ 1.50 50 mm x 100 mm Ties &
Struts
The following in 6No. bolted
treated pine trusses span 4.27 m (End of 3No. trusses)
x 1.49 m rise incdg all next Com. Rafters per bay
600)2400
gusset plates and 12 mm dia. ms 4-1 = 3
bolts. No. of bays
2.4)4.220 2.4)11.670
2 5
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 32
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 34
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
3. Finishing (Section S)
Major Finishing classifications are walls, floors and ceiling. The classifications
depend on which kind of materials e.g.
Insitu finishing,
Tiles, slab, block finishing,
Plain sheeting finishing e.g. plywood, soft board
b) Terrazzo Finishing
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 35
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Horizontal floor and paving, cross falls and slopes not exceeding 15 degrees from
horizontal shall be given separately in square meters.
Work to walls and ceilings shall each be given separately in square meters
describing if to battering walls, to sloping walls etc.
The area of ceiling is measured between wall surfaces in square meters, followed
by any associated labour such as arises to beams.
The measurement is taken from the floor to ceiling. Work behind wood skirting and
the like shall be dealt with the work of walls disregarding any ground.
Timber skirtings and picture rails as well as cornices, fillets etc. are measured in
linear meters stating the size and describing the labours and including any
supporting grounds.
Dividing strips are given in linear meters stating end, angles and intersections shall
be deemed to be included with the item.
4.1 Doors
a) Door shutters
The measurement of doors can be subdivided into internal and external doors,
and the dimensions of each of these two classes of door broken down into;
Door
Adjustment of opening
Measurements
Doors shall be given in square meters stating the thickness and the number of
doors (each leaf being counted as one door).
Doors may also be enumerated stating the size.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 36
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Classification
i) Flash doors stating the construction of the core, the finished thickness of the
door, the kind, quality and the thickness of the facing materials and the
method of fixing of facing material to the core.
ii) Boarded doors stating the thickness of the boarding, ledges, braces and
framing and the method of jointing the board covering or filling.
iii) Panelled doors stating the nominal thickness of the framing, the number and
nominal thickness of the panels and where moulded stating whether the
mouldings are worked on the solid or planted on and whether on one or both
side. Panelled doors with open panels for glass shall be so described.
Door frames and linings are measure in linear meters giving full description of all
the labours and the size of the member.
4.2 Adjustments
When adjusting the opening, care must be taken to cover all the appropriate
items by adopting a logical order of ‘taking off’ such as deduction of walls,
external and internal finishings, - skirting, and flooring.
4.3 Sundries
Holes in timber – Holes for bolts and the like shall each be enumerated separately
stating the size of bolts and the thickness of timber.
4.4 Iron-mongery
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 37
PRINCIPLES OF QUANTITY SURVEYING I – CIV3205 (2019/2020)
Generally, work on surface over 300 mm girth shall be given in square meters.
Those not exceeding 300 mm girth shall be in linear meters
Those not exceeding 0.10 square meter shall be enumerated
On general surfaces,
On wood, frames, wood windows and glazed wood doors,
On metal windows and glazed metal doors,
On structural steelwork,
On grilles, balustrades, railing and mesh,
On gutters,
On pipes,
On bars, cables, conduits, straps and ducting.
© 2020: Principles of Quantity Surveying I Notes. Ndejje Univ. By: Patrick Sekigongo. Email: sphrug@gmail.com. Mob. +256 776 647330 Page 38