Professional Documents
Culture Documents
Class7 7
Class7 7
ANANTH NATARAJAN
PMI
PROCESSES
• 5 Process Groups
• 10 Knowledge Areas
1. Project Integration Management
2. Project Scope Management
3. Project Time Management
4. Project Cost Management
5. Project Quality Management
6. Project Human Resource Management
7. Project Communications Management
8. Project Risk Management
9. Project Procurement Management
10. Project Stakeholder Management
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
PROCESS GROUPS
P ROJECT C ONTROL S YSTEM
Plan Control
schedule,
Initiate Execute
cost , scope,
quality
Project
Closing
Monitoring processes
M on
Delivery Processes
Yes
itor
Deviation
vs plan
PROCESS VS PROJECT
PROCESS PROJECT
• Repetitive • Non-repetitive
• Isolatable to single entity • Unique result
• New organizational • Time-bound
configurations • Difficult to measure
• Length
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
PROJECT RISK
• Project risk is defined by the Project Management Institute (PMI) as, "an
uncertain event or condition that, if it occurs, has a positive or negative
effect on a project’s objectives.” - PMI
RISK - OTHER DEFINITIONS
• Probability (quantifiable) of
Risk (subset of Uncertainty) undesirable deviation from baseline
response
Coordinated
e
igat
Mit
Systems
Information
Meetings,
Risk Analysis,
Qualitative
ect
D et
B OWTIE
Event
re ct
Cor
Corrections to
plan (Risk
Quantification,
forecasting)
v e nt
Pre
Good Collective
Planning
PERIODIC PROJECT REVIEW
INFORMATION RESPONSE
• Sharing • Speed
• Collaboration • Collective
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
P ROGRESS M EASUREMENT
Has the right thing been done to the right quality within the planned cost
and time?
• Scope
• Cost
• Schedule
EARNED Where have we been?
VALUE
MANAGEMENT
Reichel, 2006
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
• Orioginated with DoD (US)
• PERT
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
ESTIMATES TO COMPLETE
Item Questions
Reichel, 2006
EVM
FORMULAS
Schedule Variance (SV): SV = EV – PV
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
ESTIMATE AT COMPLETION
Future performance will be based on the budgeted cost EAC = AC + (BAC – EV)
Future cost performance will be based on past cost performance EAC = AC + [(BAC – EV) /
CPI]
Future cost performance will be influenced by past schedule EAC = AC + [(BAC -EV) /
performance (CPI x SPI)]
EAC = AC + [(BAC – EV) /
(0.8·CPI x 0.2·SPI)]
The Budget and Schedule are no longer valid EAC = AC + ETC
OPTIONS UPON DEVIATION
• Cancel Project
• Ignore Deviation
• Corrective action
• Revise plan
EVM IN PRACTICE
• US DoD
• A-12 Avenger II
CONFIDENTIAL - DO NOT DUPLICATE OR DISTRIBUTE WITHOUT WRITTEN PERMISSION FROM PROBLOCH LLC
LIMITATIONS OF EARNED VALUE