Professional Documents
Culture Documents
Ashraf Primavera
Ashraf Primavera
Ashraf Primavera
Problem No: 01
Date :
AIM
Draw the bar chart, determine the critical path and calculate the completion time of the following
logic. Also calculate the earliest starting time, latest starting time, free float and total floats of the
activities.
GIVEN DATA:
Activity A B C D E F G H
Duration(days) 2 7 4 5 6 8 3 10
1
ACTIVITY DIAGRAM AND GANT CAHRT
CRTICAL PATH
2
3
Problem No: 02
Date :
AIM
Draw the bar chart, determine the critical path and calculate the completion time of following logic.
Calculate the earliest starting time, latest finishing time, free floats and total floats of the activities.
GIVEN DATA:
Activity A B C E L M Q S W X
Duration(days) 10 5 5 6 7 9 8 8 5 6
All the start of the project W,A and L are the initial activities and are done.
Activity Q cannot start until activity A is done and it must be finished along with activity S before
activity X can start.
B,E and X are parallel activity and the project ends when they are completed.
4
ACTIVITY DIAGRAM AND BAR CHART
5
CRICAL PATH
6
Problem No: 03
Date :
AIM
Draw the bar chart, determine the critical path and calculate the completion time of following logic.
Calculate the earliest starting time, latest finishing time, free floats and total floats of the activities.
GIVEN DATA:
Activity A B C D E F G H J K L
Duration(days) 2 2 4 1 6 2 2 6 1 2 3
L is the last activity and it can begin only after activities J, K,G and H are completed.
7
ACTIVITY DIAGRAM AND BARCHART:
8
CRICAL PATH:
9
Problem No: 04
Date :
AIM
To draw the CPM network for the given project. Identify the critical path and calculate the
completion time of the project. Also calculate the ‘Earliest Starting Times’, ‘Latest Finishing
Times’, ’Free floats and ‘Total Floats’ of the activities.
GIVEN DATA
ACTIVITY DURATION
A 2
B 2
C 4
D 3
E 6
F 2
G 2
H 6
J 3
K 2
L 23
Activities A, B and C from the beginning and occur concurrently.
Activity K follows F.
L is the last activity and it can begin only after J,K,G and H are completed.
10
ACTIVITY DIAGRAM AND BARCHART:
11
CRITICAL PATH
12
Problem No: 05
Date :
AIM
To draw the network diagram and organize the work using activity code and filter the activities
according to RESPONSIBILITY, PHASE and AREA. Also calculate the TOTAL PROJECT COST . Also level
the activities based on any resource.
GIVEN DATA
ACTIVITY DURATION PRECEDED RESOURCES RESPONSIBILITY
(day)
A 4 2L,2C,2JCB AE-PBR
B 8 A 2C JE-KLM
C 6 A 4L,4C,2JCB AE-ALUVA
D 8 C 2C JE-PBR
E 4 C 4C JE-PBR
F 12 E 4L,4C,2JCB AE-PBR
G 8 E 2L JE-KLM
H 2 A 4L JE-KLM
J 8 H 3C JE-PBR
K 6 F 4L,1C,2JCB AE-ALUVA
L 4 G,J 4L JE-KLM
M 4 D,J,L 4C JE-KLM
N 4 B 3C JE-PBR
O 4 M,N 4C JE-PBR
P 2 O 2E CE
13
ACTIVITY DIAGRAM AND BAR CHART
14
CRITICAL PATH
15