CEL 334CIVIL ENGINEERING SOFTWARE LAB

Problem No: 01

Date :

AIM

Draw the bar chart, determine the critical path and calculate the completion time of the following
logic. Also calculate the earliest starting time, latest starting time, free float and total floats of the
activities.

GIVEN DATA:
Activity A B C D E F G H
Duration(days) 2 7 4 5 6 8 3 10

A,E and H are the initial activities.

Activity A precedes activity B.

Activity B precedes activity C.

Activity F follows activity G follows activity C.

Activities F,G and H precede activity D.

NAME: MUHAMMED ASHRAF S6CE ROLL NO:20

1
ACTIVITY DIAGRAM AND GANT CAHRT

CRTICAL PATH

2
3
Problem No: 02

Date :

AIM

Draw the bar chart, determine the critical path and calculate the completion time of following logic.
Calculate the earliest starting time, latest finishing time, free floats and total floats of the activities.

GIVEN DATA:
Activity A B C E L M Q S W X
Duration(days) 10 5 5 6 7 9 8 8 5 6

All the start of the project W,A and L are the initial activities and are done.

Activity C follows activity W.

Activity E cannot be started until activity A finish

Activity S depends on the completion of activity L to start.

Activity M depends on the completion of activity B start.

Both activities M and C must be done before activity B starts.

Activity Q cannot start until activity A is done and it must be finished along with activity S before
activity X can start.

B,E and X are parallel activity and the project ends when they are completed.

NAME: MUHAMMED ASHRAF S6CE ROLL NO:20

4
ACTIVITY DIAGRAM AND BAR CHART

5
CRICAL PATH

6
Problem No: 03

Date :

AIM

Draw the bar chart, determine the critical path and calculate the completion time of following logic.
Calculate the earliest starting time, latest finishing time, free floats and total floats of the activities.

GIVEN DATA:
Activity A B C D E F G H J K L
Duration(days) 2 2 4 1 6 2 2 6 1 2 3

Activity A,B and C from the beginning and occur concurrently.

Activities D and B can be begin only when activity A is completed.

Activity F,G and H depends on the completion of activity E and C.

Activity J can begin only when activities B and D are completed.

Activity K follows activity F .

L is the last activity and it can begin only after activities J, K,G and H are completed.

NAME: MUHAMMED ASHRAF S6CE ROLL NO:20

7
ACTIVITY DIAGRAM AND BARCHART:

8
CRICAL PATH:

9
Problem No: 04

Date :

AIM

To draw the CPM network for the given project. Identify the critical path and calculate the
completion time of the project. Also calculate the ‘Earliest Starting Times’, ‘Latest Finishing
Times’, ’Free floats and ‘Total Floats’ of the activities.

GIVEN DATA
ACTIVITY DURATION
A 2
B 2
C 4
D 3
E 6
F 2
G 2
H 6
J 3
K 2
L 23
Activities A, B and C from the beginning and occur concurrently.

Activities D and E begin only when A is completed.

Activities F, G and H depend on the completion of E and C.

Activity J can begin only when B and D are completed.

Activity K follows F.

L is the last activity and it can begin only after J,K,G and H are completed.

NAME: MUHAMMED ASHRAF S6CE ROLL NO:20

10
ACTIVITY DIAGRAM AND BARCHART:

11
CRITICAL PATH

12
Problem No: 05

Date :

AIM

To draw the network diagram and organize the work using activity code and filter the activities
according to RESPONSIBILITY, PHASE and AREA. Also calculate the TOTAL PROJECT COST . Also level
the activities based on any resource.

GIVEN DATA
ACTIVITY DURATION PRECEDED RESOURCES RESPONSIBILITY
(day)
A 4 2L,2C,2JCB AE-PBR
B 8 A 2C JE-KLM
C 6 A 4L,4C,2JCB AE-ALUVA
D 8 C 2C JE-PBR
E 4 C 4C JE-PBR
F 12 E 4L,4C,2JCB AE-PBR
G 8 E 2L JE-KLM
H 2 A 4L JE-KLM
J 8 H 3C JE-PBR
K 6 F 4L,1C,2JCB AE-ALUVA
L 4 G,J 4L JE-KLM
M 4 D,J,L 4C JE-KLM
N 4 B 3C JE-PBR
O 4 M,N 4C JE-PBR
P 2 O 2E CE

DESCRIPTION COST OF RESOURCE/DAY RESOURSE AVAILABLE


Labour Rs:160(20) 6
Carpenter Rs:200(25) 6
JCB Rs:4000(500) 2
Engineer(AE+JE) Rs:800(100) 2

NAME:MUHAMMED ASHRAF S6CE ROLL NO:20

13
ACTIVITY DIAGRAM AND BAR CHART

14
CRITICAL PATH

15