TC Phasing Matrix - Operator's Early Move in For Special Event Vs Permanent Occupancy - Updated
TC Phasing Matrix - Operator's Early Move in For Special Event Vs Permanent Occupancy - Updated
Small Power X Megger test, Loop Impedance Test X Cold Test, Live Test
Rev 0 - 20220902
Pre Action / FM 200 / DELUGE Final Commissioning (Including
X System commisioning X
FOAM system interface with FA)
Fire Damper Drop Test / MSFD X System commisioning X Final Commissioning (Including
Functional interface with FA)
KEU - Fire suppression system, ESP, Fire suppression system Demand Control
Make up air balancing, Demand X Exhaust / Make-up air balancing X
ESP
Control Interface with Fire alarm
Testing of UPS
Testing of all Field devices like Cables (VSWR NEDAA Requirements. Full
Tetra X test) X Testing of Coverage of Radios, Work X Commissioning of System.
station, Interfaces
Testing of all Field devices like cables, Camera Control Room Operation and alarms, Full commissioning via network.
CCTV/ ANPR X X Software interface with other systems, X Server Failover test. Network
Images. SIRA Inspection. Redundancy Test.
IPTV X Testing of all Field devices like cables. X Video Testing, Performance Testing X Full commissioning
ATP1.
via network from
Testing of all Field devices like cables, AV Room Commissioning, Ball Room
AV X Speakers, Network Switches, SAI Panels , X Commissioning, Interfaces, Full
Meeting Rooms. commissioning Via Network.
PA/BGM X Testing of all Field devices like cables X Testing of Speakers X Work station, Server Interfaces, Full
commissioning Via network.
Gate Barriers/ Bollards X Testing of Cables X Testing of Operation, loop testing, X Interfaces, Graphics
Rev 0 - 20220902
Digital information display X Testing of all Field devices like cables. X Content Testing, Performance Testing X Content Testing, Performance Testing
CONDITIONS
1. The above agreement for Phase 2 (reduced T&C activites) requirements prior to Nov 11 2022 Special event is based on the condition that all the MEP systems will be
adequately manned from the time of preparing for the special event and until the end of special event.
2.Please note the Operator's access to site for preparing for the special event along with the Special Event taking place is subject to approvals from the
relevant Authorities.
3. It is mandatory for the Contractor to complete all Phase 3 T&C activites and offer for inspections to CML & DEC for sign off prior to issuance of ToC.
4. Prior to raising for the Phase 2 T&C activites DEC to be provided with the marked up drawings of the areas that are part of the Nov11 special event. SBJV to raise for the
T&C activites for Phase 2 only for areas that are shown in the marked plans (i.e special event areas)
Rev 0 - 20220902