Surveying 4
Answers:
CUT AND FILL SECTIONS 1. 996.18 m3 5. 12.63 m2
Problem 4: 2. 10 m 6. 28.14 m2
Given the following cross sections 3. 2:1 7. 815.40 m3
Base for cut = 9m Sideslope = 1:1 4. 47.4 m2`
Base for fill = 8m Sideslope = 1.5:1
Station 3+000
5.48 0 5.0
+0.98 +3.05 +0.50
Station 3+060
6.76 0 4.63
-1.84 -1.22 -0.42
Problem 5:
From Station 0+200 with center height of 1.4 m in fill,
the ground line makes a uniform slope of +5% to
station 0+260 whose center height is 2.8 m in cut.
Assuming both sections to be trapezoidal with a
roadway of 10m and sideslope of 2:1
a. Compute the grade of the finished roadway.
b. How far from station 0+200 will the filling extend?
c. What is the area of the section at station 0+250?
Review Innovations CE Review November 2022 – Surveying 3
Level Cross Section It is assumed that the volume between successive cross
sections is the average of their areas multiplied by the
distance between them.
L
Ve = (A1 + A 2 )
2
L
Vp = (A1 + 4A m + A 2 )
6
PRISMOIDAL CORRECTION
Three Level Cross Section
Cp =
L
(c1 − c2 )(d1 − d 2 )
12
V p = Ve − C p