Professional Documents
Culture Documents
External Elec Vashistha
External Elec Vashistha
Date: 15/04/2022
GST:- 09AUPPS8970E1ZS
Sub: Work order for External Electrical works along with supply,
installation, testing, Commissioning and handover in all respect at
Orion One32 marketing office project of WellGrow Infotech Pvt ltd.
1. PARTIES:
AND
This Work Order sets out the major points and is not intended to be
exhaustive. The detailed terms and conditions concerning the execution of
Work shall be recorded in Articles of Agreement, General Conditions of
Contract (GCC) and Special Conditions of Contract (SCC) (hereinafter
collectively referred to as “Contract Documents”) and this Work Order
shall form part of the definitive Contract Documents to be executed between
the Parties. No understanding purporting to modify or change any terms,
conditions or specifications of this Work Order shall be recognized unless it is
in writing and signed by both the Parties.
3. SCOPE OF WORK:
3.1 The scope of Work under this service order includes installation, testing,
commissioning & hand over of External Electrical work in all respects at Site
in accordance with the specifications & Bill of Quantities (BOQ), enclosed
herewith as Annexure A.
3.2 The general character and the scope of the Work is defined in the
specifications and BOQ. The Contractor shall carry out the Work as per
agreed specifications and in accordance with the Contract Documents and to
the satisfaction of WIPL.
3.3 Where any parts of the Work may be executed by any sub-contractors
appointed by the Contractor in accordance with this Work Order, such
responsibility and liability of the Contractor shall cover and extend to the work
of all such sub-contractors.
4. CONTRACT PRICE:
The total value for execution of Work by the Contractor shall be Rs 677250/-
(Rupees Six lac seventy seven thousand two hundred and fifty only), subject
to deduction of income tax deductable at source (TDS). GST is exclusive.
This is an item rate contract and payment will be made as per actual work done
at site.
2) Retention Money:
5% retention money of DLP period can be released only against the
irrevocable Bank Guarantee (BG) for 03 months.
3 ) Approvals:
5) Schedule of Rates:
b. The rates and prices shall be firm till the completion of the
entire works and shall not be subject to escalation due to any
reason whatsoever. The Contractor agrees that if the scope of
works is reduced or increased for any reason there shall be no
change in the rates for the various items of works. The
Contractor also agrees that if there are any reduction(s) in
Taxes, Duties and / or Statutory Levies, the rates and prices
of the items shall be reduced accordingly.
6) Liquidated Damages:
7) Site Supervision:
8) Other Conditions:
b) Contractor shall cover all work under the requisite Contractor All
Risk Policy that are in vogue. CAR policy act as applicable, shall
be taken out by the contractor and copies of it lodged with
Client.
The Contractor shall set up suitable stores at its own cost and shall
be responsible for the safe custody of the equipment/material in the
premises till the entire tenure of the work.
b.) All R.A. bills must be duly stamped and signed by the
contractor.
c.) All R.A. bills bust be in the name of Client ““WellGrow Infotech
Pvt. Ltd.”
d.) All R.A. bills must be supported with all the required documents.
e.) All R.A. bills must be supported with covering letter with the
summary of bill and with the complete break up of taxes etc.