Monthly Report - April 2023
Monthly Report - April 2023
Team Handling:
1 Perstorp ETP Datasheets of mechanical Process Documents approved For Process : Pravin
equipment’s in B code For Mechanical
Datasheets of Instruments P&ID approved in B code Equipment’s : Pravin
Preparation of Mechanical GA Layout approved in B code For Instrument:
Preparation of Civil GA Completed Mechanical GA Pravin/Nitin
Preparation of Mech. GA drawings and submitted to For Mechanical/Civil
Preparation of Plant Layout and consultants for further GA/Layout : Pravin
Piping Layout approval. For QAP :
Review of RCC drawing from 3D model completed 90%. Pravin/Surrender
Dhabalia
Preparation and review of PDMS
Module
Review of Vessel Sizing
Calculations
QAP approvals.
2 Taloja CETP Monitoring and resolving the Blower installation Pravin/ Jitendra
critical parts of Taloja CETP like completed. Kadam
blowers installation, Electrical VFD given for the repairs
components replacement, centrifuge Centrifuge repair work is
operation going on.