Professional Documents
Culture Documents
2019 - IEEE PESGM - Dual Hybrid Energy Storage
2019 - IEEE PESGM - Dual Hybrid Energy Storage
2019 - IEEE PESGM - Dual Hybrid Energy Storage
net/publication/335098015
CITATIONS READS
3 220
3 authors:
Abhisek Ukil
University of Auckland
222 PUBLICATIONS 2,771 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Abhisek Ukil on 10 August 2019.
Abstract—In PV microgrids, batteries are used to balance the and supercapacitor (SC) to support the load demand with RES,
power between the generation and loads side. In this paper, a the average power demand is met by the battery and the SC
Dual Hybrid Energy Storage System (DHESS) in microgrids is deal with the transient power since SC has high energy density
proposed to reduce the batteries life loss. the duel HESS can
work3 on two modes, one is responsible for charging, and another but low power density.
for discharging. The working mode changing is decided by the
state of charging (SOC) of each battery. An adaptive PQ control Many researches focus on increasing the lifespan of bat-
method in the three-phase inverter is presented to ensure the teries and operating batteries economically. Reference [13]
SOC in the safe range. The proposed system is developed in presented a control strategy for AC-DC microgrids to limit
MATLAB/SIMULINK environment and tested for the results. the charging and discharging rate of batteries optimally. Works
[14], [15] presented an approach to keep the SOC of batteries
I. I NTRODUCTION in a safe range. The authors in [16] adopted a dual BESS to
meet the load demand, one BESS is charging by RES, and
Comparing with the traditional energy source, the renewable another one is discharging to support loads, which can use
energy source (RES) such as the wind and polar source is batteries fully, and work mode of two can interchange based on
more suitable to satisfy the power need in the remote area. To the situation of SOC. Due to the various weather condition, the
integrate distributed generators (DGs), energy storage system state of interchange is difficult to catch, so it uses three-hourly
(ESS) and loads as a subsystem, the concept of microgrids indices to forecast the performance of RES, but it is much
were presented in [1], which can work in islanding mode and complex. Reference [17] established an optimization model
grid-connected mode. The energy management of microgrids to minimize the battery operation cost based on the battery
is aim to operate microgrids economically and keep the power lifetime algorithm.
reliable [2], [3]. The basic control methods of microgrids can
This paper proposes a dual HESS in PV microgrids working
be classified into grid-side control (inverter output control) and
with the adaptive PQ controller. One HESS is charging, and
power sharing control [2]. In inverter output control, stationary
another is discharging when the power is mismatching, and the
reference frame control is widely used, it can measure ac
adaptive PQ controller can sharing the power between main
current and voltage as the reference frame to regulate the
grid and the dual HESS to ensure the condition of working
DC magnitudes in DGs side. The authors in [4] presented
mode interchange can be met, all controller is local controllers
a stationary reference frame control based on PR controller
and the charge/discharge cycle is decreasing. This paper is
to reduce the stable state error. Reference [5] introduced a
organized as follows. In section II, the structure and control
double synchronous reference frame current controller to trade
strategy of normal HESS is introduced. In Section III, the
of the current oscillation. Droop control is a mature method
working mode of dual HESS is presented. In Section IV, the
for sharing the power in microgrids [6]. In [7], [8],authors
adaptive PQ control is presented, and The simulation result is
used droop control to manage power among multiple RESs.
shown in Section V, followed by conclusions in section VI.
PQ controller is used to controlling the output of active and
reactive power of the three-phase inverter [7].
II. C ONTROL SCHEME OF NORMAL HESS
ESS plays an important role in microgrids to supply or
absorb power when power imbalance caused by the instability The structure of a PV microgrid with HESS is shown in
and intermittent of RES. Studies [9] and [10] proposed the Fig. 1.
structure of ESS based on batteries to keep the power balance,
however, the high rate of charge and discharge cycle would Where, iP V , ib1 and iSC1 are the current of the PV, battery
damage the battery since the power density of batteries is low, and SC. VP V , Vb1 , VSC1 and VO are the voltage of the PV,
hence, [11] and [12] proposed HESS that is consist of a battery battery, SC and DC bus. SW 1 to SW 5 are the switches of DC-
III. C ONTROL SCHEME OF DUAL HESS
Z
0 1
SOC sc = SOC sc − ∗ isc ∗ dt, (6)
3600.Cnc
Fig. 1: The structure of HESS.
where SoCb0 , SoC 0 sc , Cnb and Cnsc are the initial SOC and
capacity of the battery and SC. Because the SC is only dealing
DC converters of PV, battery, and SC. If the power requirement with the transient power, so in this paper, the SOC of SC is
is greater than the output power of PV, HESS would discharge neglected.
to supply additional power, and if the output power is greater
According to [18], the effective discharge of batteries is
than load demand, HESS will absorb the rest of the power to
equal to the product of effective weighting factor and ampere-
keep the voltage of DC bus stable.
hours delivered, and the effective weighting factor is decided
The normal control method of HESS based on PI controllers by SOC, which can be seen in Fig. 3. It shows that if SOC
is presented in [12]. The control scheme is shown in Fig. 2. less than 0.5, delivering 1 Ah would lead to 1.3 Ah to the
The error between the Vref and VO is fed to a PI controller to lifetime. To avoid the battery is operated at a low SOC range,
generate the total current reference of HESS iT . The output the structure of DHESS and the control scheme are proposed
of the lower pass filter is, in this section.
In these cases, the SOC of DHESS does not catch the critical
condition to change the work mode, but the SOC of one of
the batteries is too low or high to discharging and charging.
To address this issue, an adaptive PQ control is presented in
this section to manage the power between the PV microgrid
and the main grid. The Fig. 6 shows a PV microgrid with
a DHESS in grid-connected mode under the control of PQ
controller.
When the DHESS should discharge (PHESS > 0), but the
Fig. 5: Dual HESS control scheme battery is out of power (SOC< L), P2ref is negative so that the
main grid can supply the additional power to DC loads instead
IV. A DAPTIVE PQ CONTROL IN GRID - CONNECTED MODE of the battery until PHESS < 0 or the DHESS changes the
working mode. Conversely, if the dual HESS should absorb
Because of the variable situation of RES and load demand, power but the battery is full (SOC> H), P2ref would increase
there are four special circumstance during the operation of the to ensure the rest of power go through to the main grid.
Enable signal Working mode
M ode1 M ode2
DHESS
Discharging 1 0
charging 0 1
TABLE I: Enable signal selection
V. S IMULATION R ESULT
B. Case 2: Performance of the adaptive PQ controller
The voltage on DC bus is regulated to 48V, and the
frequency of main grid is 50HZ, the system parameters is Fig. 9 and Fig. 10 show the simulation result. The initial
shown in Table II. working mode of DHESS is mode 1. During t0 to t1 , PHESS
TABLE II: System Parameters < 0, HESS2 is charging. At t1 , SOCb1 >L but SOCb2 >H,
so the P2ref increase to transfer more power from PV to
Parameter Value AC bus. After t1 , HESS2 take a few time to stop charging
VP V and IP V in MPP 24 V, 3 A due to the increasing of PP V 2 , the PP V 1 is decreasing which
DC bus Voltage (VO ) 48 V make HESS1 discharge. At t2 , PHESS > 0, so the charging
SC Voltage (VSC1 ) 32 V behaviour stops, and the P2ref back to the normal value,
Battery Voltage (Vb1 ) 24 V HESS1 continues discharging to keep power balance. At t3 ,
DC-DC Converters LP V =20 mH, SOCb1 <L and SOCb2 >H and PHESS is still greater than
LB =3 mH, LS =3 mH 0, the working mode change to mode 2, and HESS2 starts to
discharge instead of HESS1.
The simulation result is shown in Fig. 8. During t0 to t2 , A new control structure of DHESS in DC microgrids and
PHESS < 0, so the DHESS should charge. The initial working is proposed in this paper, which can regulate each battery
mode is mode 1, so HESS2 is charging. At t1 , SOCb1 <L and charge or discharge fully to increase the lifespan of batteries by
SOCb2 >H, so it changes to mode 2, HESS1 is charging. At avoiding to operation in low SOC range, and a relative adaptive
t2 , the load demand is increasing, which leads to PHESS > 0, PQ controller is presented to keep the SOC in safe range by
so the HESS2 start to discharging and HESS1 stops working. managing the output power of the three-phase inverter.
frame current controller for unbalanced grid-voltage conditions,” IEEE
Transactions on power electronics, vol. 27, no. 9, pp. 3934–3943, 2012.
[6] K. De Brabandere, B. Bolsens, J. Van den Keybus, A. Woyte, J. Driesen,
and R. Belmans, “A voltage and frequency droop control method for
parallel inverters,” IEEE Transactions on power electronics, vol. 22,
no. 4, pp. 1107–1115, 2007.
[7] A. Bidram and A. Davoudi, “Hierarchical structure of microgrids control
system,” IEEE Transactions on Smart Grid, vol. 3, no. 4, pp. 1963–1976,
2012.
[8] J. He and Y. W. Li, “An enhanced microgrid load demand sharing
strategy,” IEEE Transactions on Power Electronics, vol. 27, no. 9, pp.
3984–3995, 2012.
[9] J. Shimizukawa, K. Iba, Y. Hida, and R. Yokoyama, “Mitigation of
intermittency of wind power generation using battery energy storage
system,” in Universities Power Engineering Conference (UPEC), 2010
45th International. IEEE, 2010, pp. 1–4.
Fig. 9: The battery current of HESS1, HESS2 and the output [10] I. Serban and C. Marinescu, “Battery energy storage system for fre-
voltage DC bus in case 2. quency support in microgrids and with enhanced control features for
uninterruptible supply of local loads,” International Journal of Electrical
Power & Energy Systems, vol. 54, pp. 432–441, 2014.
[11] P. T. Moseley, “Energy storage in remote area power supply (raps)
systems,” Journal of Power Sources, vol. 155, no. 1, pp. 83–87, 2006.
[12] N. Mendis, K. M. Muttaqi, and S. Perera, “Management of battery-
supercapacitor hybrid energy storage and synchronous condenser for
isolated operation of pmsg based variable-speed wind turbine generating
systems,” IEEE Transactions on smart grid, vol. 5, no. 2, pp. 944–953,
2014.
[13] S. K. Kollimalla, A. Ukil, H. Gooi, U. Manandhar, and N. R. Tummuru,
“Optimization of charge/discharge rates of a battery using a two-stage
rate-limit control,” IEEE Transactions on Sustainable Energy, vol. 8,
no. 2, pp. 516–529, 2017.
[14] H. Mahmood, D. Michaelson, and J. Jiang, “A power management
strategy for pv/battery hybrid systems in islanded microgrids,” IEEE
Journal of Emerging and Selected topics in Power electronics, vol. 2,
no. 4, pp. 870–882, 2014.
[15] N. R. Tummuru, M. K. Mishra, and S. Srinivas, “Dynamic energy
management of renewable grid integrated hybrid energy storage system,”
IEEE Transactions on Industrial Electronics, vol. 62, no. 12, pp. 7728–
7737, 2015.
[16] Y. Yuan, X. Zhang, P. Ju, K. Qian, and Z. Fu, “Applications of battery
energy storage system for wind power dispatchability purpose,” Electric
Power Systems Research, vol. 93, pp. 54–60, 2012.
[17] B. Zhao, X. Zhang, J. Chen, C. Wang, and L. Guo, “Operation opti-
mization of standalone microgrids considering lifetime characteristics
of battery energy storage system,” IEEE transactions on sustainable
energy, vol. 4, no. 4, pp. 934–943, 2013.
[18] D. Jenkins, J. Fletcher, and D. Kane, “Lifetime prediction and sizing
of lead-acid batteries for microgeneration storage applications,” IET
Renewable Power Generation, vol. 2, no. 3, pp. 191–200, 2008.
Fig. 10: The P2ref and the output power of inverter in case 2.
R EFERENCES