Professional Documents
Culture Documents
Rail Welding
Rail Welding
Rail Welding
8.1 General
Rail connections are rail joints or welds for producing a rail track from individual rail sections. If
possible, stagger the rail joints relative to the carrier joints and the concrete beam joints. This
also applies if the rails are continuously welded. Level out the rail joints vertically and laterally
in order to prevent jolting during travel. Provide an adequate lateral guide when using open
and bolted connections (fishplates or rail supports).
Rail connections
Connections can be open, bolted/with fishplate or welded, depending on whether the joint is
an end joint (square butt end joint), an inclined T-joint (mitre joint) or a step joint.
Open track joints must be prevented if possible, but you can not always avoid them e.g. in the
case of separable or mobile tracks.
Fish joints should only be used for systems that are utilised for a short time. Do not use tracks
with fishplate joints for continuous operation.
The step joint causes the highest costs due to its design. The travel smoothness characteris-
tics are not as good as with an inclined T-joint.
As the only joint that is permanently capable of bearing loads, POLYSIUS recommends the
welded rail joint in the form of a square butt end joint or, still better, in the form of an inclined
T-joint.
17
9 Welding the rail joints
The end faces of the individual lengths can be produced by saw cutting or flame cutting. If they
are flame cut, rails of steel grades R200 or R220 have to be preheated to 400 °C. Apply the
preheating uniformly over the entire profile and over a rail length of at least 100 mm on both
sides of the heat application point. Subsequently maintain the temperature level for a period of
approx. 5 minutes.
If making a weld joint by the metal-arc welding process, join the individual lengths with a weld
reinforcement of approx. 3 mm in such a way that a square butt joint with a root-face spacing
of 15 to 20 mm is formed between the end faces of the rail ends.
1000 mm 15...20 mm
copper or ceramic base plate with a
groove to enable better through-
welding and to hold the slag. Manu-
facture these base plates to suit the
size of rail foot. Attach copper cheek
plates that fit the shape of the rail
profile to each side of the rails.
These copper cheek plates must
have spacers to create the neces-
sary interspace between the web
and the cheek plates to enable the Rail chair base plate
Heat insulation mat
slag to run off. Hold the cheek Elastic intermediate layer
15...20 mm 1000 mm
9.1.4 Preheating
18
9.2 Welding
9.2.1 General
Always weld a butt joint without interruption. Weld the entire rail joint without allowing the tem-
perature to fall below the preheat level. At first, consecutively weld the rail foot and the rail
web. Perform the preheating throughout this time. Preheat again if heat losses occur as a re-
sult of delays!
First fasten the weld pool backups underneath the rail foot.
After welding the foot, attach the copper cheek plates at both sides of the web and hold them
in place by means of a wire clip or a screw clamp.
Weld the rail head in several layers. At first, weld the joint gap up to a height of 2/3 of the rail
head with a rod electrode that is approved for the grade of rail steel concerned.
Weld the last third of the rail head with a surfacing electrode (a rod electrode is generally
used) that is suited to and approved for the hardness of the rail material.
If you use rod electrodes, be sure to redry and process them in accordance with the manufac-
turer's specifications. Comply with the electrode manufacturer's specifications when setting the
amperage and the polarity.
Ensure that the cooling takes place as slowly as possible, e.g. by covering the welded joint
with mineral wool.
Finally, dress the weld must by either manual or mechanical grinding, using a steel ruler to
check the permissible deviations in accordance with the provided tolerance table. If sagging of
the rail is detected as a result of shrinkage of the weld joint, compensate for the sag by creat-
ing a triangular preheated area in the area of the weld seam at the rail foot and the web. Cre-
ate the triangular preheated area simultaneously on the left and right by means of two burners.
Weld the last third of the rail head with a wear-resistant surfacing rod electrode that is suited to
and approved for the hardness of the rail material.
19
9.2.5 Rod electrodes for surface welding
- Coated rod electrode EN 14700 E Fe1 (acc. to EN 14700)
These are thick-coated, basic coated rod electrodes with good welding characteristics that are
weldable with direct current at the positive pole. The melted-off weld metal has a hardness of
at least 300 HB and can be machined with high-speed tool steels.
20