Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

RISK ASSESSMENT

Activity: Crane-Hydra-Deployment for Lifting-Lowering

Location: Department: Date of Assessment:

RA Reference: Revision: 00 PTW Reference:

Assessment Team: Supporting Documents: Reference Documents:


(Method Statement/Drawings) (Standards/Procedures/Manuals)

Approval granted for work to proceed

Approval NOT granted for work to proceed. Please revise the Risk Assessment to include additional safeguards
Name: Designation: Signatures:

Distribution:

General Guidelines: Hierarchy of Hazard Controls:


1. Risk Assessment (also called Job Safety Analysis) is a qualitative hazard identification technique used for (In order from most effective to least effective)
identifying, assessing and controlling major hazard(s) associated with a specific task or operation where Elimination (by design or process changes)
Permit to Work (PTW) precautions are deemed insufficient to execute the job safely. Substitution (with less hazardous material or equipment)
2. No such work should be allowed to proceed until the Risk Assessment has been completed and approved by Isolation (with barriers, machine guards)
a competent authority (normally Site Manager/Superintendent). Engineering Controls (interlocks, ESD system)
3. Risk Assessment should be carried out by a competent person and conducted in a team environment, Administrative Controls (procedures, job rotations,
involving all relevant parties. training)
4. Only trained and experienced staff should be deployed to execute high-risk jobs. Warning Systems (signs, labels)
5. Conduct RA well in advance as part of the work planning process. Personal Protective Equipment
6. Address all direct and indirect hazards associated with the task.
7. This RA shall be conducted in conjunction with the above referenced PTW. A copy of the approved Risk Abbreviations:
Assessment must be attached to the permit throughout the work duration. ALARP : As Low as Reasonably Practicable
8. Use the 5x5 Risk Assessment Matrix (provided separately) to assess the potential risks.
PTW : Permit to Work
9. When determining safeguards, consider the ‘Hierarchy of Hazard Controls’ provided on this page.
10. Communicate RA to all relevant personnel through meetings/toolbox talks before starting work. ESD : Emergency Shutdown
11. Record Risk Assessment and revise if necessary. RA : Risk Assessment
P : Probability (Likelihood)
C : Consequences
R : Risk (H = High, M = Medium, L = Low)

Page 1 of 4 HSE DOCUMENTS


RISK ASSESSMENT

S/ Initial Risk Residual Risk


Hazards Safeguards Action by
N P C R (Low/ALARP)
1 1. Preparation and checking before entry  Fire extension due  Crane/ Hydra must have a valid permit for entry Project ALARP Level
2. Entry inside plant to spark generated E 4 V inside red roads Engineer/supervi
3. Preparation and checking before H sor/HSE in charge
 Damage due to  Crane/ Hydra must be certified for use by the P&M
Lifting hitting against department
4. Lifting/ Lowering of the load pipe/equipment  Driver must have a safe driving licence. Spark
 Injury to people arrestor must be healthy
around  Check LEL in the proposed route of the Crane/
 Property damage / Hydra. Switch off the engine and evaluate if the
Exposure to toxic F&G alarm is sounded
release/ fire due  Crane/ Hydra will move with a speed of less than 10
to falling of lifted Kmph
load/ crane  Identify all pits near to the route, barricaded
toppling due to /highlight if required
improper usage of  Use wheel jammers to prevent accidental
the crane movement of the Crane /Hydra
 Exposure to  Keep the Crane / Hydra on gear when parked.
HC/toxic release Follow Vehicle entry procedure
due to Crane rope  Do not leave the crane / Hydra unattended when
getting entangled parked near plant and machinery
with a small-bore  Do not allow to move people in the route of Crane/
connection Hydra
 Property damage /  Crane/ Hydra reverse horn must be working and
toxic release/fire assistant to guide while reversing
due to dropping of
the load to Following things are to be ascertained before lifting:
slippage of slings,  Object load;
rupture of slings,  lift radius;
crane brake  load height;
 load centre of gravity;
failure, rupture of
 load suspension point;
crane rope wire,
 Slew Limitation;
slippage of rope
 counterweight;
wire from the
 Bearing load on the ground;
anchor point  Safe working load;
 Property damage/  Object dimension (if more than 25m2), safe
exposure to toxic approach. Also, give the request form to P&M
release/fire due to depth so that the correct crane is allocated
toppling or  Check on Crane /Hydra:
collapse on the  Crane load test certificate, Daily log sheet,
Page 2 of 4 HSE DOCUMENTS
RISK ASSESSMENT
Fortnightly / monthly service and inspection
checklist must be available and updated. The safe
load indicator (SLI) is working. If not working
capacity loading will not exceed 60%
All limit switches are functioning. The free-fall
system is blocked. No hydraulic oil leakage
Lifting plan to be prepared if: load wt is more than
15T or Boom length above 55m or two cranes used
for single lift or capacity loading more than 85% or
using mobile crane rated above 200T
 Identification and marking any small SBC at risk and
pointing out the risk to the crane operator and
signaler
 Lifting weight to be with guide rope. Optimal setting
crane of the crane and restricting crane movement. Also
 Electrical shock barricade the crane
hazard due to  Crane has undergone regular and competent
entangling with service, inspection
overhead  Control of slings wear and tear and the attachment
electrical cables to the load
 Hazard due to high  Crane capacity loading (85 % with working SLI, 60 %
wind velocity if SLI is not working)
  Load weight and lifting radius must be known and
within crane capacity
 The area must be barricaded; people should not be
allowed under lifted load
 low-capacity loading, working SLI, setting of crane
outriggers on the solid foundation
 Proper operators under the outriggers required.
The outriggers must always be extended in their full
length
 Elec. Overhead line is at least 6.0 m above from tip
of the crane
 Wind speed should be less than 19.4 knots (35
km/hr). For personnel lifting wind speed should be
less than 14 knots

Page 3 of 4 HSE DOCUMENTS


RISK ASSESSMENT

The Risk Matrix Likelihood


Consequences People Assets Environmen Reputation A B C D E
t
5-Catastrophic Multiple Fatalities Extensive damage Extensive Effect International impact VERY
HIGH
4-Severe Single fatality or Permanent total Severe damage Severe Effect National impact
disability
3-Critical Major injury or health effects (long Major damage Major Effect Major impact
term or permanent partial disability) MEDIUM HIGH

2-Marginal Minor injury or health effects leading to Minor effect Minor Effect Minor impact
LTI/RWC/MTC
1-Negligible Single injury or health effects, requiring Slight effect Slight Effect Slight impact
first aid LOW

Likelihood Descriptor to assist in Qualitative Assessment of Likelihood/Frequency of Occurrence.


A Has occurred in a similar industry worldwide, or judged likely to have occurred.
B Has occurred regionally within a similar industry, or judged likely to have occurred.
C Has occurred at [worksite], or judged likely to have occurred.
D Has occurred several times at [worksite], or judged likely to have occurred.
E It May occurred several times at the same [worksite], Location or judged likely to have occurred.

Assessed by: Date: Signature:

Reviewed by: Date: Signature:

Page 4 of 4 HSE DOCUMENTS

You might also like