R E PLA CE ME N T O F S W C P L A NT-1 D RU M S C R E E N

S YST E M 72 00 0 43 00 0
( 7 NOS ) & LC P I N P LA NT- 2, JU B AI L
FAC TO RY A CC E P TA NC E T E ST P RO CE D U R E PA G E 28 O F 45

I NS -A B -DS - 219 RE V: 0

Step Description Result


● In Control Builder M in online mode locate the Modbus_TCPConnect
function block for the each device.
● Check the following.
● No faults are forced on the link for any testing purposes.
23. ● The EN_C(Enable Connection) parameter value is TRUE. 
● Verify that the following Output parameter values are as follows.
● Valid: TRUE
● Error: FALSE
● Status: equals one (1)

7.4.3. Test Remedial

The level of re-testing necessary when a fault is found will depend upon the nature of the fault.
If the fault is due to documentation errors, then no re-testing is required but a copy of the
revised section of the respective documents must be attached to the PQ before it is closed.

When all FAT PQs have been successfully re-tested, the tester shall sign and date, Stage 4
section of the record below.

STAGE 4 TESTING
COMMENTS:

Test Result: Pass/Fail

Tester
ABB Date:
Signature:

Witness
GEMS Date:
Signature:

Witness
MARAFIQ Date:
Signature:

STATUS SECURITY LEVEL DOCUMENT ID. REV. LANG. PAGE

In Review Internal INS-AB-DS-219 0 en 28/45


© Copyright 2020 ABB. All rights reserved.