The AAA University is considering building a new convention center on campus. The building would provide a new gymnasium for inter-school sports
activities, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction starts.
Immediate
Activity Description a m b t 𝝈
Predecessor
A Survey building site -- 3 7 5 6 .33
B Develop initial design -- 5 6 7 6 .33
C Obtain board approval A,B 7 11 9 10 .33
D Select architect C 2 6 4 5 .33
E Establish budget C 1 8 3 6 .33
F Finalize design D, E 6 17 10 14 .67
G Obtain financing E 8 15 10 13 .33
H Hire contractor F, G 4 8 6 7 .33
b.)
A 0 6 D 16 21
6 0 6 5 17 22
C 6 16 F 22 36 H 36 43
START 14 22 36 7 36 43 FINISH
10 6 16
B 0 6 E 16 22 G 22 35
6 0 6 6 16 22 13 23 36
Activity Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
A
B
C
D
E
F
G
H
e.)
f.) 47-43
.94
= 4.26
a.) H7
7 8
F 14
3 C 10
5
A 6 D 5 E 6 G`
G 13
1 4
A`
B 6 6