Analyzed and solve the problem stated below.

The AAA University is considering building a new convention center on campus. The building would provide a new gymnasium for inter-school sports
activities, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction starts.

Immediate
Activity Description a m b t 𝝈
Predecessor
A Survey building site -- 3 7 5 6 .33
B Develop initial design -- 5 6 7 6 .33
C Obtain board approval A,B 7 11 9 10 .33
D Select architect C 2 6 4 5 .33
E Establish budget C 1 8 3 6 .33
F Finalize design D, E 6 17 10 14 .67
G Obtain financing E 8 15 10 13 .33
H Hire contractor F, G 4 8 6 7 .33

a. Draw a project network using circular nodes


b. Draw a project network using rectangular nodes showing the ES, EF, LS and LF.
c. Identify the critical path.
d. Develop an activity Gantt chart for the project.
e. What is the probability that the project will be completed after 47 weeks?
f. Determine the expected completion time of the project that is almost 100%.

b.)
A 0 6 D 16 21
6 0 6 5 17 22

C 6 16 F 22 36 H 36 43
START 14 22 36 7 36 43 FINISH
10 6 16

B 0 6 E 16 22 G 22 35
6 0 6 6 16 22 13 23 36

Activity ES EF LS LF Slack Critical Path


A 0 0 6 6 0 Yes
B 0 0 6 6 0 Yes
C 6 6 16 16 0 Yes
D 16 17 21 22 1 No
E 16 16 22 22 0 Yes
F 22 22 36 36 0 Yes
G 22 23 35 36 1 No
H 36 36 43 43 0 Yes

c.) Critical Path: A or B + C + E + F+ H; 6 + 10 + 6 + 14 + 7 = 43


d.)

Activity Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
A
B
C
D
E
F
G
H

e.)

SD is 𝝈 = √ .332 + .332 + .332 + .672 + .332


= √ 0.8889
𝝈 = .94

f.) 47-43
.94

= 4.26
a.) H7
7 8

F 14

3 C 10
5

A 6 D 5 E 6 G`