Professional Documents
Culture Documents
TMC 411
TMC 411
The essential content in the TMC 411 has been incorporated into T HR CI 12110 ST Earthworks
and Formation, Version 1.0. The section 13 is contained in the T HR CI 12101 ST Geotechnical
Problem management, Version 1.0.
Authorisation:
Technical content Checked and Interdisciplinary Authorised for
prepared by approved by coordination release
checked by
Signature
Date
The SMS document reference on CTN 13/04 has changed to SMS-06-GD-3066 Guide to
managing construction hazards.
Documents listed in Table 1 are presented as legacy RailCorp documents and shall be read in
conjunction with this technical note and interpreted according to the interpretation guides listed in
Table 2.
There have been several embankment destabilisations reported as a result of excavations into
the toe of embankments. As shown in the photographs (Figure 1 to Figure 5), it appears that the
toe was cut to create access at the expense of embankment stability.
Removing the toe restraint, which is an integral part of the earth structure, leads to slip failure
progressing towards the track. This is one of the worst forms of destabilisation for dynamic
loading. It was noted that vertical cuts were left unsupported until track patrol discovered the slip
failure.
Each incident led to emergency repairs being undertaken to reinstate the embankment with
temporary speed restrictions to manage the risk until repairs had been completed.
Embankment toes and slopes shall not be disturbed by any means including cuts, cable and pipe
trenches or otherwise as this directly affects the stability of the earth structure.
Any trenching at the toe of cuttings for cable routes, cess drainage and so on, shall not be carried
out without a stability assessment or advice from the geotechnical engineer. Trenches especially
at top of soil/soft rock cuttings and embankments shall not be left open overnight. Water ponding
in trenches can result in slope failures (see Figure 4 and Figure 5).
Excavation work shall not commence without a risk assessment and implementation of
appropriate controls.
Refer to TMC 411 Earthworks and SMS-06-GD-3066 Guide to managing construction hazards for
requirements for excavation work including planning of works, risk assessment, excavation work
plans and excavation procedures. Also, refer to ESC 540 Service Installations within the Rail
Corridor for detailed requirements for the location and installation of cables and pipes by
trenching.
Figure 3 - Vertical toe cut with high risk for slip failure
Figure 4 - Cable trench left open at top of soil/soft rock cutting allowed ponding water to enter slope
leading to failure (see Figure 5)
Figure 5 - Failure due to cable trench left open at top of soil/soft rock cutting
Authorisation:
Technical content Checked and Interdisciplinary Authorised for
prepared by approved by coordination release
checked by
Signature
TMC 411
Engineering Manual
EARTHWORKS
Version 2.0
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in
any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered, stored or transmitted by
any person without the prior consent of RailCorp
Document control
Revision Date of Approval Summary of change
Superseded by T HR CI 12110 ST
2.0 July, 2010 Changes detailed in chapter revisions
1.2 November 2009 Format change throughout
1.1 October 2007 C1-6 “Safety and Environmental” deleted, except two requirements
moved to C3-1, New C2-6 “Ground anchors” to be consistent with
ESC 350, C3-1 added requirements re not undermining adjacent
structures & relocation of services
1.0 October 2006 First issue as a RailCorp document. Includes content from C 1100
Contents
Chapter 1 General....................................................................................................................................... 6
Superseded by T HR CI 12110 ST
C1-1 Purpose....................................................................................................................................... 6
C1-2 How to read the Manual.............................................................................................................. 6
C1-3 References.................................................................................................................................. 6
C1-4 Definitions, abbreviations and acronyms .................................................................................... 6
Chapter 2 Management Requirements ..................................................................................................... 9
Chapter 3 Competencies.......................................................................................................................... 10
Chapter 4 Assessment, Planning and Documentation......................................................................... 11
C4-1 Adjoining Property..................................................................................................................... 11
C4-2 Preservation Items .................................................................................................................... 11
C4-3 Rehabilitation ............................................................................................................................ 11
C4-4 Drainage.................................................................................................................................... 11
C4-5 Erosion and Siltation ................................................................................................................. 11
C4-6 Sloping Ground ......................................................................................................................... 11
C4-7 Slope Stability ........................................................................................................................... 12
C4-8 Soft or Compressible Foundation Soils .................................................................................... 12
C4-9 Reactive Soils ........................................................................................................................... 12
C4-10 Low Density or Potentially Collapsing Soils.............................................................................. 12
C4-11 Existing Filled Ground............................................................................................................... 12
C4-12 Site Investigations..................................................................................................................... 12
C4-13 Non-potable Water .................................................................................................................... 12
C4-14 Trenches ................................................................................................................................... 13
C4-15 Compaction Moisture Content .................................................................................................. 13
C4-16 Surcharging of Slopes............................................................................................................... 13
C4-17 Calculation of Quantities ........................................................................................................... 13
C4-18 Physical Separation of Dissimilar Materials.............................................................................. 13
C4-19 Geosynthetics ........................................................................................................................... 13
C4-20 Construction Activities Vibrations.............................................................................................. 13
C4-21 Contamination ........................................................................................................................... 13
C4-22 Retaining Walls ......................................................................................................................... 14
C4-23 Potential Acid Sulfate Soils ....................................................................................................... 14
C4-24 Investigation and Planning........................................................................................................ 14
C4-25 Documentation .......................................................................................................................... 14
Chapter 5 Acceptance Standards ........................................................................................................... 16
C5-1 General ..................................................................................................................................... 16
C5-2 Vertical Tolerances ................................................................................................................... 16
C5-3 Horizontal Tolerances ............................................................................................................... 16
Chapter 6 Earthworks & Formation ........................................................................................................ 17
C6-1 Formation .................................................................................................................................. 17
C6-2 Compaction Standards ............................................................................................................. 17
C6-3 Non-compliance with Compaction Standards........................................................................... 17
C6-4 Drainage.................................................................................................................................... 17
C6-5 Ground Anchors ........................................................................................................................ 17
C6-6 Train Examination Areas........................................................................................................... 18
C6-7 Walkways .................................................................................................................................. 18
Chapter 7 Preparation for Earthworks.................................................................................................... 19
C7-1 General ..................................................................................................................................... 19
C7-2 Earthworks Plan ........................................................................................................................ 19
C7-3 Site Clearing.............................................................................................................................. 19
C7-4 Spoil .......................................................................................................................................... 20
Chapter 1 General
Superseded by T HR CI 12110 ST
C1-1 Purpose
This document specifies procedures for the construction and maintenance of cuttings,
embankments and track formation.
Guidelines for the rehabilitation of existing track formation are given in TMC 403 “Track
Reconditioning Guidelines”.
Any requirements from standards have been included in the sections of the manual and shown
shaded. The shaded sections are extracts from RailCorp Standard ESC 410 “Earthworks and
Formation”, unless noted otherwise.
C1-3 References
AS 1141 Methods for sampling and testing aggregates
AS 1289 Methods for testing soils for engineering purposes
AS 1726 Geotechnical site investigations
ESC 410 Earthworks and Formation
SPC 301 Structures Construction
SPC 411 Earthworks Materials Specification
TMC 403 Track Reconditioning Guidelines
TMC 421 Track Drainage Manual
NSW Government Environmental Planning and Assessment Act
RailCorp Environmental Management System
SMS-06-GD-0378 System Guide - Excavation and Earthworks
Contaminated Material that may contain toxic substances or soluble compounds harmful
Material: to environment, water supply or agriculture.
Cutting: An earth or rock excavation within the works site that is made below an
Superseded by T HR CI 12110 ST
existing surface to create the railway formation.
Dispersive soil: Soil that has the ability to pass rapidly into suspension in the presence of
water
Earthworks: The activities covered by this specification
Earthworks Level at the centre of the earthworks prior to placing of the capping
Level: layer.
Embankment: An earth or rock fill structure above an existing and/or excavated surface to
create the rail track formation.
Expansive Soil: Soil that will suffer a high volume change when in contact with
water. Any increase or decrease in the moisture content of such soil, would
cause swelling or shrinkage, respectively. This type of soil is also called
“Reactive Soil” and “Swelling Soil”.
Formation: The earthworks structure including all Foundation, Structural Treatment and
Capping Layer, on which ballast is laid
Formation Level: Finished level at the centre of the formation preparatory to laying ballast. It
includes the required capping layer.
Formation Width: Width at formation level
Foundation A special layer or treated zone at the base of a formation for the purpose of
Treatment: reinforcing, strengthening or drainage.
General Fill: The lower zone of the embankment.
Site Supervisor: A qualified civil engineer or a competent person with delegated engineering
authority for earthworks supervision.
Soluble Soil: Soil containing perishable particles such as gypsum or rock salt.
Superseded by T HR CI 12110 ST
Stockpile: Placement of material that has been selected, loaded, transported and
unloaded in a heap outside the confines of a borrow pit or of an excavation
that forms part of the works.
Structural Zone: The upper zone of the embankment. Its thickness varies from 500 mm to
1000 mm, depending on the CBR of the general fill/subgrade.
Tolerance: Range between the limits within which a dimension or position lies.
Top Soil: A natural surface soil that may contain organic matter.
Unsuitable The material that occurs in the borrow site or below the foundation level of
Material: embankment and is not considered as suitable due to its adverse
characteristics as specified in Clause 8.
Chapter 3 Competencies
Superseded by T HR CI 12110 ST
Design of earthworks is to be approved by the Geotechnical Engineer.
Earthworks shall only be carried out under the supervision of the Site Supervisor.
Some aspects of the earthworks may require the approval of the Geotechnical Engineer.
Certification of the track during earthworks or after earthworks has been completed may only be
undertaken by persons with the following competency:
− TDT B38 - Maintain track geometry.
C4-3 Rehabilitation
Rehabilitation of areas which are affected by different construction activities such as borrow areas,
stockpiles, excavated or fill batters, spoil disposal areas, haul routes, stormwater control, camp,
office and workshop sites, should be included in drawings and specifications so that materials such
as topsoil, mulched native vegetation (which can contain useful seed stock and nutrients) and bulk
fill materials used for rehabilitation are identified and preserved for re-use. Rehabilitation works
should be completed before the constructor vacates the site.
C4-4 Drainage
Temporary and permanent diversion of permanent or ephemeral watercourses prior to or during
construction of the earthworks and associated works may affect the quantity or quality, or both, of
the stormwater run-off. Therefore, special provisions may be necessary to minimize the effects and
to protect the legal rights of adjacent and downstream landowners. Failure in providing for such
provisions could lead to litigation and delay in completion of the earthworks projects.
Approval from the relevant authorities should be obtained prior to either the placement of fill on
flood-prone lands or construction of drainage structures, i.e., culverts in natural watercourses.
The placement of fill or construction of cuts may impact the flow of subsurface water and may lead
to localised instability. Special provisions may be necessary to account for the potential effect of
the works in such cases.
− Benching of the surface of the natural ground to assist in the placing of the fill and to key the
fill to the foundation soil;
− Berms or benches above, within, or at the foot of cuts to intercept stormwater run-off or
detritus; and/or other
− Special works.
C4-14 Trenches
Excavations for trenches require special consideration for support. Relevant authorities place
limitations on the maximum depth to which trenches may be excavated without shoring. In this
Superseded by T HR CI 12110 ST
regard, safety regulations should be considered.
The effect of trench excavation on the stability of any adjacent embankment, cutting, formation,
track or structure shall also be considered.
C4-19 Geosynthetics
Proprietary products are available with particular properties suitable to act as a filter, drainage layer
and/or physical separator to allow water flow whilst avoiding migration of soil particles or as a
tensile reinforcement element. Such materials may be construction expedients, or may form part of
the permanent earthworks. Geosynthetics should be carefully chosen for the intended purpose in
accordance with SPC 411 and have an adequate service life under the intended conditions.
C4-21 Contamination
Any known or suspected ground or groundwater contamination should be investigated. Relevant
authorities have set limits on the quantity of contaminants permitted in ground, in various
applications. Removal of contaminated soil from the site is likely to require special consideration,
such as classification. Similarly, allowing contaminated soil to be imported or to remain on site may
require approval from the relevant authorities. The impact of any investigation on planned
Superseded by T HR CI 12110 ST
earthworks, including safety and environmental aspects, should always be considered.
C4-25 Documentation
Documentation is an important consideration in all earthworks projects. The relevant documents
should include:
Such documentation will typically include (or have consciously excluded), the following, as well as
any other matters that may be of particular importance to the particular project:
− Adequate specification and drawings to allow the proper planning, execution and supervision
of the works. Plans, sections and elevations should clearly show areas of earthworks,
identifying areas which require specific treatments. Particularly on larger projects, the
specification and drawings should adequately define the followings:
∼ The areas in which spoil may be dumped or stockpiled;
∼ Restrictions on clearing and stripping;
∼ Drainage requirements during and after construction;
∼ Criteria for selection of materials for placement in various parts of the fill and for material
to be excluded from fill. Material descriptions should be clear, unambiguous and in
accordance with AS 1726;
Superseded by T HR CI 12110 ST
∼ Criteria for standard of surface trim of completed earthworks;
∼ Details of tests, including minimum frequency, to be carried out for testing to ensure the
fill complies with the specified criteria;
∼ The scope of the commission to be given to the geotechnical inspection and testing
authority;
∼ Either the methods to be used for construction or the requirements to be met by test in
the finished project. It is generally unwise to mix performance and method specifications.
Where a performance specification is adopted, restrictions on methods should be limited
to those absolutely necessary (for example, to limit the risk of damage to nearby
structures).
− Site investigation information, together with details of, and provisions for, access to any further
relevant information for the purpose of design or construction planning. Selective provision of
available site investigation data can give rise to serious problems, either engineering or legal,
or both, and should not be done without due consideration of the issues involved.
− Any other relevant information in the possession of the designer.
C4-25.2 Construction
Adequate records need to be kept during construction, including conditions encountered, works as
executed, as built drawings, testing records and any alterations to the specification and drawings.
As a minimum, these records should show the followings:
− The finished surface of the capping shall be within 25mm of the level shown on the drawings
and:
∼ The algebraic difference of the deviations from the correct level for any two points
20 metres apart on the centreline shall not exceed 15mm.
∼ The deviation from a three (3) metre straight edge laid on the surface parallel to the
centreline shall not exceed 10mm.
The width of the capping layer from the design centreline to the finished top of embankment slopes
or toe of batters in cuttings shall be not less than the dimensions required by Appendix 3.
When the capping layer is tested with a three (3) metre straight edge laid perpendicular to the
centre line the deviation from design profile shall not exceed 10mm concavity.
The formation for single track mainlines and single track sidings shall comply with the appropriate
dimensions shown in Appendix 1.
The formation for double track mainlines and double track sidings shall comply with the appropriate
dimensions shown in Appendix 2.
The formation for multiple track mainlines and multiple track sidings shall comply with the
appropriate dimensions shown in Appendix 2, subject to the requirement that the water from one
track shall not cross another track to get away. For example, if there are three tracks, there shall be
at least one subsurface centre drain.
Where reduced shoulder distances exist due to physical constraints, an assessment is to be made
of the need for safety refuges, handhold devices and limited clearance signs. The requirements are
specified in ESC 350 “Retaining Walls and Platforms”.
C6-4 Drainage
Cess drains; sub-surface drains, top drains and interceptor drains shall be provided for cuttings and
are to comply with the requirements in ESC 420 “Track Drainage”.
Ground anchors shall comply with the requirements of AS 4678 “Earth-retaining structures” and
Technical Specification S38 “Permanent Rock Anchors” in RailCorp Engineering Specification SPC
301 “Structures Construction”.
The design of ground anchors shall include mitigation against the effects of stray currents.
The designer shall specify requirements for testing. Test procedures shall comply with Technical
Specification S38.
The designer shall specify requirements for long term monitoring, if any.
Ground anchors shall not extend under private property without the approval of the Chief Engineer
Civil.
The train examination area is not to be assumed as available for road access purposes.
C6-7 Walkways
Where nominated, walkways are to be provided for staff to walk along the track cess. The
minimum requirement is to cover walkways with a 50 mm layer of 10 mm single sized aggregate as
in Appendices 1 and 2.
Earthworks shall be carried out so as not to undermine any adjacent track, formation, embankment,
cutting or structure.
Excavation work shall be planned and managed in accordance with SMS-06-GD-0378 System
Guide - Excavation and Earthworks.
Environmental protection of the site shall be in accordance with the RailCorp Environmental
Management System.
Services that are located within the construction zone may require relocation so as not to adversely
affect the performance of the completed earthworks.
− Excavation sequence and proposals for the management of all materials in the earthworks,
including the use of topsoil, procurement and control of imported materials, materials from
borrow sites, and spoil;
− Preliminary identification of zones of potentially unsuitable materials, and management of
disposal and replacement of unsuitable materials;
− Methods to be employed to ensure that materials of the specified or higher quality are
identified made available and incorporated into the work at the sites where the quality of the
material has been specified. The details include any sorting, isolating, processing, and
placement of the materials proposed for such use. Processing may include screening,
crushing, blending, and modification of the material;
− Sources of materials and testing proposed for Structural Treatment;
− Procedures proposed for procuring and managing materials from borrow sites where
applicable;
− Procedures proposed for the treatment of foundations;
− Procedures and mass haul diagram proposed for the management of excavation and the
placement of earth and rock fill embankments, and rock facing, to ensure that no deficiency of
earth fill occurs and conformity requirements are met.
− Methods to demonstrate that the specified compaction has been achieved over the full depth
and width of each layer and that specified layer thickness is not exceeded.
Clearing includes removal and disposal of all trees, stumps, logs, timber, scrub, vegetation, minor
structures, refuses and other material unsuitable for incorporation in the work.
Holes left after grubbing under proposed embankments are to be filled with sound material and
compacted in layers as for embankments.
Regarding fauna and flora of the site, approval shall be taken from the environmental division prior
to clearing and grubbing.
Superseded by T HR CI 12110 ST
C7-3.1 Removal of Topsoil and Unsuitable Material
Most naturally occurring soils, with the exceptions specified in the following section, are capable of
being compacted to form a general fill. Similarly, weathered rock that can be ripped and broken
down by compaction, will be generally suitable for use as structural fill.
Topsoil shall be removed over the area which will be occupied by the completed works plus a
clearance of 2 metres. Topsoil suitable for vegetation propagation shall be placed in a stockpile
clear of the work to enable its re-use in landscaping and revegetation.
After stripping of top soil covering each embankment foundation or upon reaching the designed
floor of cuttings, earthworks processes are held to allow inspection of foundation. Where unsuitable
material for forming structural fill is found, such unsuitable material should be either removed to
spoil or used in non-critical areas as directed by the Geotechnical Engineer. The material that has
been removed in accordance with this Clause must either be replaced with suitable material or
treated as directed.
− Topsoil, organic soils, such as severely root-affected subsoils, peat, logs, stumps. Top soils
containing organic materials can be used for landscaping purposes, if necessary.
− Free draining material susceptible to scouring or piping such as very fine clean sand, wind
blown sand and non-cohesive silt.
− Organic silt and clay with CBR<1.
− Expansive or swelling soils which undergo large volume changes due to change in moisture
content. These materials either be removed to spoil or treated by additives as directed by the
Geotechnical Engineer.
− Dispersive soils, which are easily suspended in standing water or eroded by running water.
− Materials that contain substances which can be dissolved or leached in the presence of
moisture such as gypsum and sodium chloride.
− Contaminated materials containing toxic substances which may be harmful to environment,
water supply or agriculture.
− Collapsible soils in foundation are also considered as unsuitable material and shall either be
removed or treated as directed by the Geotechnical Engineer.
− Fill that contains wood, metal, plastic, boulder or other deleterious materials, in sufficient
proportions to affect the required performance of the fill.
− Saline, chemically aggressive or polluted soils, and carbonate soils where acid disposal may
occur.
Dispersive, expansive and soluble soils can be used only in accordance with guidelines provided
by the Geotechnical Engineer.
Where unsuitable material exists in excessive depths, the advice of the Geotechnical Engineer is
sought.
All materials unsuitable for incorporation in the work shall be disposed off-site, unless approved for
re-use on site e.g. as noise barriers.
C7-4 Spoil
Spoil is surplus material fro excavations which is not required to complete the Works as specified,
or materials from excavations whose quality deems to be unacceptable for incorporation in the
Works.
Except for contaminated materials, spoil generated from the work must be disposed of in the
manner and at locations shown on the Drawings or specified by the site supervisor. Disposal of
non- contaminated material within the site may be by flattening of batter slopes of embankments,
Superseded by T HR CI 12110 ST
uniform widening of embankments or stockpiling.
Embankment widening or batter flattening work is deemed to form part of the embankment
construction and must be carried out in accordance with C7-3. The spoil must be spread and
compacted as specified for materials in embankments. Effective drainage must be maintained for
the whole embankment.
If the proposed stockpile locations are outside the works site, all necessary written approvals,
including environmental approvals must be obtained. This may require segregation by material
type, classification and, where required, disposal at facilities appropriately licensed to receive the
particular materials.
Contaminated materials are considered as unsuitable material and must be stockpiled and/or
removed from the works site in accordance with Clause 7.3.2.
Cut batters shall be benched as shown on Drawings to provide drainage and erosion control, to
provide geotechnical stability, and to allow access for maintenance purpose. The bench widths
shall not be less than shown on the Drawings. The floor of the bench must not vary from levels
shown on the Drawings by more than (+0mm/-100mm). The bench must have a crossfall to drain
water away from cut face immediately below the bench, and longitudinal drainage must be
provided and maintained. Bench drains shall be constructed progressively as each batter face is
complete.
Before entering and excavating the borrow, all necessary permits shall be acquired and the
contractor shall comply with any requirements of the Environmental Planning Act, 1998, the Local
Government Planning Scheme, local laws, local planning policies and land owners, as appropriate.
C7-8 Blasting
For any blasting operation, all necessary licences from the appropriate authorities shall be obtained
and comply with all Government Regulations relating to transport, storage, handling and the use of
explosives.
The Vibration and Air Blast Management Plan must contain review and verification of the
requirements set by appropriate authorities to ensure that the public, building structures and
infrastructure are protected.
All blasts shall be monitored for ground vibration and air blast to ensure that the blasting methods,
peak particle velocity and air blast do not cause damage to property as indicated in the following
table:
Superseded by T HR CI 12110 ST
Point of Potential Damage (within 1 km from Blast Overpressure Peak Particle
the proposed blast site) Level [dB(linear)] Velocity
When blasting operations are being carried out, precautions must be taken relating to the safety of
persons and animals and appropriate approval taken from the environmental division prior to the
operation.
Any road likely to be affected by the blast must be closed to traffic and the appropriate signs
erected.
Where pre-splitting or line drilling is carried out, the centre to centre spacing of drill holes must not
exceed the following:
Chapter 8 Embankments
Superseded by T HR CI 12110 ST
C8-1 Preparation of embankment base
Preparation includes clearing, grubbing, removal of topsoil and removal of unsuitable material and
subsequent restoration as described in C7-3.
It also includes cutting of terraces into slopes, scarifying and compaction of embankment base and
provision of drainage works as specified below.
The terraces are to be cut progressively as the embankment is constructed (refer to Appendix 4).
Suitable material excavated in cutting the terraces may be incorporated in the embankment but
unsuitable material must be disposed off-site as described in C7.3.2.
In cases where collapsible soil is found as the subgrade, the material is considered unsuitable for
construction of embankment and shall be removed or treated by ponding following heavy
compaction.
Soluble soils or rocks (such as gypsum and salt rock) are not permitted to be present in the
subgrade of the embankment and shall either be removed or treated to eliminate any potential of
leaching in the future. Any remedial measure in this regard should be approved by the
Geotechnical Engineer
The area of the base of the embankment shall be scarified to a depth of 100mm, parallel to the
embankment axis.
A layer of general fill 100mm thick shall be spread over the scarified area, and the whole area shall
be compacted to Compaction B standard as detailed in C6-2.
It will comprise a geotextile fabric (as specified in SPC 411 and approved by the Geotechnical
Engineer) laid along the base and around a layer of free draining filter material to a depth of
300mm, and spall protection provided at the outlet.
The free draining filter material shall be crushed rock, river gravel or slag composed of sound, hard,
strong and durable particles, and complying with SPC 411. The filter material shall not contain clay
or silt fines more than 5%.
The material shall be placed and spread in such a way as to avoid segregation and to ensure that it
is not contaminated during construction with foreign materials.
The filter material shall be spread in uniform layers to give the specified compacted thickness in
such a manner as to avoid damage to the fabric.
Compaction is to be obtained using at least 8 passes of a vibratory roller of static drum load of 6
tonnes.
Bad ground, seepage or springs encountered during embankment preparation may require
additional special treatment (refer to Appendix 4). Obtain advice from the Geotechnical Engineer.
− Structural Zone.
General fill is the embankment below the structural zone.
The thickness of the structural zone (H) is determined by the following relationship with the general
fill in the embankment:
− for general fill with CBR* of 3 to 8%, H = 500 mm
− for general fill with CBR* of 1 to 3%, H = 1000 mm.
* (Soaked California Bearing Ratio, Standard Compaction).
Material for use in the structural zone shall comply with SPC 411.
Material not complying with the above requirements is only to be used with the approval of the
Geotechnical Engineer.
Embankments shall be constructed in full width horizontal layers. Normally layers should not
exceed 200 mm thickness unless it can be shown that the specified compaction can be obtained
for a thicker layer. For this purpose, prior approval of the Geotechnical Engineer is necessary.
Layers or pockets of substantially varying material should be avoided. The maximum particle size
should be less than 2/3 of the compacted layer thickness.
Construction shall be carried out in such a manner as to ensure adequate drainage of the works,
and to avoid scour and erosion. The top of the earthworks is to be trimmed in accordance with the
requirements for preparation for capping.
Each layer of material must be trimmed prior to and during compaction. Compaction must be
completed promptly to ensure moisture content remains conforming and uniform and to minimise
the possibility of rain damage.
Fill batter faces should be compacted as a separate operation or, alternatively, overfilled and cut
back. The trimmed and compacted batter face should have a roughed surface to reduce run-off
velocities and aid revegetation, if required.
Immediately prior to the placement of the capping, the fill shall be trimmed by grading to the final
profile and compacted by a minimum of three passes of a smooth steel drum roller which has a
static mass not less than 10 tonnes.
The finished, rolled surface shall be true to profile to a tolerance of +0 to -30 mm, and shall be free
of depression and ruts.
Field testing for Relative Compaction control shall be carried out in accordance with SPC 411 or
more frequently as determined by the Geotechnical Engineer or Site Supervisor.
Compaction shall be carried out at a moisture content, which will allow the specified compaction to
be achieved, normally within 2 per cent of optimum moisture content. If there is insufficient
moisture in the material for it to be compacted as specified, water must be added. The added water
must be applied uniformly and thoroughly mixed with the material until a homogeneous mixture is
obtained.
The material which is too wet must not be compacted until it has dried out so that the moisture
content is within the specified range. The drying process may be assisted by aeration or, where
approved by the Geotechnical Engineer, by use of hydrated or quick lime. Addition of lime should
be considered if rain occurs during a possession. Alternatively, the wet material may be removed to
a stockpile site for drying out and later use. Bond between layers is to be ensured, if necessary by
wetting or scarifying.
If rain is threatening or the site is to be left unattended, the upper surfaces of fills should be
crowned and, if possible, sealed with rubber-tyred or smooth-wheeled plant and graded to prevent
ponding.
In hot, dry seasons, and in rare cases where potentially expansive soils are to be utilized (with
approval of the Geotechnical Engineer), compaction moisture content shall be 2-3% above the
Optimum.
− Ensuring that the moisture content of materials during placement avoids near saturation at the
specified density.
− Providing drainage on the surface of fills and preventing the ponding of water on fill layers.
− Selecting appropriate earthmoving and compaction equipment.
The type of compaction equipments is dependent on the nature of the materials to be compacted.
The suitable equipments for various types of fill materials are summarized in the following table:
Superseded by T HR CI 12110 ST
Equipment Most Suitable Soils
1 Smooth wheel rollers, static or Well-graded sand and gravel
vibrating mixtures, crushed rock
2 Rubber-tyred rollers Coarse-grained soils with
some fines
3 Grid rollers Weathered rock, well-graded
coarse soils
4 Sheepsfoot rollers:
Static Fine-grained soils with more
than 2% fines
As for static, sand-gravel
Vibrating
mixtures
5 Vibrating plate (light) Coarse grained soils with 4-
8% fines
6 Tampers, rollers All types
7 Impact rollers, impact compaction Wide range of soil types and
moisture regimes
At each sample location selected, field density test and field moisture content test is carried out and
a sample is taken for laboratory maximum dry density test.
Field (in-situ) density and laboratory tests shall be carried out in accordance with relevant
Australian Standards. The test results must be representative of the tested layer at its full depth,
width and length. Sample forms for reporting the earthworks tests are given in Appendices 5 and 6.
The relative compaction value and the characteristic relative compaction must be rounded off to the
nearest 0.1%. Frequency of the testing shall be in accordance with the provisions as recommended
in SPC 411.
Suitable plant for test rolling procedures may consist of the following:
− Static smooth steel wheeled rollers with a mass of not less than 12 t and a load intensity under
either the front or rear wheels of not less than 6 t/m width of wheel.
− Pneumatic tyred plant with a mass of not less than 20 t and a ground contact pressure under
either the front or rear wheels of not less than 450 kPa per tyre. The area over which this
ground contact pressure is applied should be not less than 0.035 m2 per tyre.
− Highway truck with rear axle or axles loaded to not less than 8 t each with tyres inflated to 550
kPa.
Fill layers should be test-rolled immediately following completion of compaction. If further test-
rolling is required at some later date, the surface should be moisture-conditioned, as required, and
given not less than four coverage of the testing roller before test rolling resumes.
Superseded by T HR CI 12110 ST
Any areas where visible deformation or springing is detected by test-rolling should be rectified and
represented for test-rolling, or the opinion of the designer should be sought.
Where unstable areas exceed 20% of the area being considered by test-rolling, the whole of the
area should be ripped, re-compacted and re-presented for test rolling.
An alternative method for test-rolling is to use an impact roller or impact compaction, a non-circular
towed or self-propelled module that imparts a high energy dynamic force. Impact rollers can be
utilized to identify weak zones or soft spots, but will tend to loosen the surface layer.
The completed batter must be free of rills running down the face of batter. Any loose material on
the batter shall be promptly removed as the work progresses.
Fill batter faces should be compacted as a separate operation, or alternatively, overfilled and cut
back.
If water storage next to the embankment is expected, stability analysis for steady seepage and
sudden draw down cases should be considered and risk of overtopping assessed.
Any compacted layer which has deteriorated after an interruption in the earthmoving operation,
should be rectified before further material is placed over it.
Rock used for rock facing must have a Point Load Strength Index (Is) greater than 1 MPa and
Wet/Dry strength variation not more than 35% and a minimum dimension of 500 mm.
The rock facing must be built up in layers ahead of each layer of filling. Rock must be place in such
a manner that its least dimension is vertical such that mechanical interlock between larger stones
occurs. Any rock deposited in the rock facing which has an excess of fine material surrounding it
must be removed together with the excess fine material and replaced. The space between larger
batter rocks and adjacent fill material must be filled with progressively smaller rocks to form a
graded filter which prevents the migration of fines out of the fill material , but which does not overfill
the voids between larger rocks, or cause the larger rocks to lose contact with one another.
Where adjacent geology and the terrain are likely to produce moisture flow through the
embankment, a drainage blanket with properties specified by SPC 411 of minimum 300 mm
thickness must be provided at the base of the fill.
Where wave action or inundation may occur, a geotextile in accordance to SPC 411 must be
placed between the rock facing and the graded filter. In this case the earth fill and filter are placed
ahead of the rock facing.
Extreme caution must be exercised whilst placing rock facing. The outer rock layer must be placed
in such a manner as to prevent spillage down the batter. Under no circumstances the rocks should
be allowed to be dislodged and rolled onto any adjacent track or roadway in use.
Chapter 9 Cuttings
Superseded by T HR CI 12110 ST
C9-1 General
Construction of cuttings shall provide for excavation of material within the limits of the batters
including benching and terracing of cut batters; cleaning of batter surfaces; treatment of cutting
floors; and foundation treatment below the embankment. Cuttings in both soil and rock should
provide a stable, safe foundation for the structure.
C9-2 Excavation
Excavation shall be carried out to the lines, levels, dimensions and slopes shown on the Drawings.
The excavated faces shall be neatly trimmed and the top edges of the cuttings neatly rounded.
Under cutting of the slopes shall not be permitted under any circumstances.
Excavation shall be carried out in such a manner as to prevent erosion or slip; working faces shall
be limited to safe height and slopes, and surfaces shall be drained to avoid ponding and erosion.
Batters will generally require fattening at the ends of cuttings owing to the presence of less stable
material. In all cuttings, undulations in the general plane of the batter shall not be permitted.
Overhanging and loose or unstable materials likely to slip shall be cut back, removed or stabilised.
Rock cuttings and exposed surfaces shall be excavated so as to obtain smooth, uniformly trimmed
surface.
Excavation at the base of cutting shall be finished at a level to suit the capping thickness, with
cross falls and cess drains provided.
Prior to placing formation materials and carrying any designed foundation treatment, the cutting
floor shall be tested and inspected by the Geotechnical Engineer.
Slopes shown on the Drawings represent the estimated requirements for the expected types of
material and will be subject to re-determination on the basis of site inspection and investigation
during excavation. Where necessary, advice shall be obtained from the Geotechnical Engineer.
Superseded by T HR CI 12110 ST
Batters in cuttings shall be carried around curves in an even and regular manner. Finished batters
shall not have a slope steeper than that specified.
If the batter is over-excavated beyond the tolerance applicable for the batter slope line, or after
cleaning the batter is beyond the tolerance applicable, the batter must be restored to specified
slopes and stability to the satisfaction of the Geotechnical Engineer. Proposals for restoration must
take into account long-term stability, durability, and consideration of urban design solutions.
The tolerances for the excavation of batters shall comply with the figures provided in the following
table:
Undulations in the general plane of the batter will not be permitted. The completed batter must be
free of rills running down the face of the batter.
C9-4 Benching
Cut batters shall be benched as shown on Drawings to provide drainage and erosion control.
Benches shall be maintained and cleaned of loose earth, stones, and boulders throughout the
works.
All material on the cutting floor shall be ripped or loosened to a depth of 200 mm below the
designed floor level for the width of overlying general or structural fill. The maximum dimension of
any particles in the ripped or loosened zone shall not exceed 150 mm.
C9-6 Compaction
Compaction of the top 150mm layer in the base of cuttings or of material required to fill over-
excavation shall be 95 per cent maximum modified dry density as determined by AS 1289 Test
5.2.1 or shall be solid rock.
The compacted material shall have a soaked CBR of at least 8%. If the measured CBR is less than
8%, reinforcement of the cutting base by geofabrics may be considered.
Following excavation to the cutting floor, a terrace shall be excavated for the width of the
embankment to a depth of 600 mm below and parallel to the cutting floor as shown in the following
figure:
Capping material shall comply with Engineering Specification SPC 411 Earthworks Materials.
Material proposed for capping shall be a well-graded natural or artificially blended sandy-gravely
soil. It shall have sufficient fines to provide a sealing layer and to permit it to be compacted to high
densities by static or vibratory steel - tyred rollers or by ballasted pneumatic - tyred rollers.
Materials such as natural ridge gravel free from vegetable matter, ripped sandstones with low clay
content and crushed and blend tough, durable rock or slag, have been found to meet material
properties of this specification.
The earthworks in embankments shall be placed and compacted to a level 30 millimetres above
the base of the capping layer. Immediately prior to the placement of the capping, the fill shall be
trimmed by grading to the final profile and compacted by a minimum of three passes of a smooth
steel drum roller, which has a static mass not less than 10 tonnes.
The finished, rolled surface shall be true to profile to a tolerance of +0 to -40mm, and shall be free
of depressions and ruts. No traffic other than that required to place the capping shall be allowed on
the finished surface.
The capping material shall be transported from the source to the work in vehicles which are so
constructed that loss of material does not occur. The material shall be suitably damp to prevent
segregation during transit.
Where required for compaction purposes, water shall be added as necessary to achieve optimum
moisture content and mixed uniformly with the capping material by approved mechanical means.
Compaction shall achieve a minimum dry density of 95 per cent Maximum Dry Density as
determined by AS 1289, Test 5.2.1.
The capping material shall be well mixed throughout the layer so that all voids are filled. The top of
the final layer shall be graded and trimmed, and material shall be added as necessary to produce
an even sealing layer.
Sites for embankment widening are to be approved by the Civil Maintenance Engineer. All work is
to be in accordance with this Manual.
C11-2 Preparation
C11-2.1 Survey
The embankment widening shall be properly set out using batter pegs for toe of embankment and
necessary survey for drainage structures.
Care is to be taken to ensure that moisture is not trapped between the existing and the widened
embankment, and water does not pond against the toe of the embankment.
The capping layer is to be at a level below the track capping level or track formation level, with a
crossfall of 1 in 30 away from the track.
Cess drains, catch drains and mitre drains are to be provided in accordance with other standards.
Drains down the embankment are to be protected from erosion.
Appropriate erosion control is to be carried out including topsoiling, mulching and revegetation of
embankment slope with grass and native plants.
C12-2 Construction
Care shall be exercised in constructing earthworks within 5 metres of structures to avoid damage to
the structures.
Non-vibratory compaction equipment shall be used within this distance and adjacent to the
structure as defined in the following table:
Selected backfill shall be placed adjacent to structures in accordance to the following table. The
selected backfill shall consist of a granular material having a maximum dimension not exceeding 50
mm and a plasticity index, determined in accordance with AS 1289.3.3.1, neither less than 2 nor
more than 12. In the table, H = overall height of the structure.
Selected Backfill
Structure Type
Width Height
Bridge Abutments 2m H
Box Culverts, Precast Culverts H/3 H + 300 mm
Corrugated Steel Pipes and Arches 0.5 m H + 500 mm
Retaining Walls H/3 H
Select fill adjacent to structures
The fill shall be placed in horizontal layers with a compacted thickness between 100 mm and 150
mm.
Layers shall be placed simultaneously on both sides of box culverts to avoid differential loading.
Compaction shall start at the wall and proceed away from it.
The existing slope behind the structures shall be cut in the form of successive horizontal terraces,
each terrace being at least 1 meter in width and 600 mm in height.
In case of spill-through abutments, rocks shall not be dumped against the columns or retaining
walls but shall be built up evenly by hand placing around or against such structures.
In the case of framed structures, embankments at both ends of the structure shall be brought up
simultaneously and the difference between the levels of the embankments at the respective
abutments shall not exceed 500 mm unless otherwise specified in the Drawings or within the
specifications.
Adjacent to weep holes, free draining filter material encapsulated in a suitable geotextile fabric
should be placed, horizontally for at least 300 mm from, and vertically for 450 mm above the weep
- hole. Free draining material must be provided by broken stone or river gravel consisting of clean,
Superseded by T HR CI 12110 ST
hard, durable particles graded from 50 mm to 10 mm such that:
C12-3 Excavation
Care should also be exercised when excavating within 5 metres of structures (for example near
overhead wiring structures when benching into slopes for embankment widening or when
excavating for track reconditioning).
When excavating adjacent to structures, there is a risk that the footings may be undermined or the
structure destabilized, resulting in structural failure and potential collapse.
Excavations in the vicinity of structure footings are therefore not permitted unless documented
engineering advice and approval are obtained.
No excavation should be made within this 5m distance without prior analysis of structure stability
with respect to the effects of the excavation.
No excavation shall be made below the base of the footings of any structure (for example bridges,
retaining walls and station platform walls) without prior analysis of structure stability with respect to
the effects of the excavation.
Maintenance staff should be aware of the warning signs that could point to potential geotechnical
problems so that investigation of the problem can be undertaken by the Geotechnical Services
Section. For this purpose, a regular inspection of the tracks with due attention to the stability of the
surrounding slopes and buildings is required.
The supporting track structure should be inspected during track patrols and detailed walking
inspections.
C13-2.9 Settlement
Railway track embankment may experience two types of settlements:
Subsoils made of loose, fine grained sand under groundwater table may suffer excessive
settlement due to liquefaction caused by high dynamic loadings such as earthquakes.
If any of these conditions are noticed by track maintenance staff, they should immediately be
reported to their controlling officer who will arrange for the Geotechnical Services Section to
investigate.
CL
Shoulder Distance Shoulder Distance
Rail Level
1.5 :1 1.5 :1
1000 min. Ballast Formation Level
1 in 30 1 in 30 Earthwork Level
1 in 10
Capping Layer
Batter Slope
Natural
Surface
EMBANKMENT
Where space permits,
increase this distance to
allow for mechanized
maintenance equipment.
1000 min
CL
Batter Slope
Batter Slope
Top Drain
1.5 :1 1.5 :1
1 in 30 Ballast 1 in 30
CUTTING
CL
1250
50 min.
Rail Level
1.5 :1 1 in 30
1.5 :1
1 in 30 Formation Level
Earthwork Level
1 in 30 1 in 30
Capping Layer
Batter Slope
1.5 :1 1.5 :1
1 in 30 Ballast 1 in 30 Top Drain
EARTH
ROCK Capping Layer Additional area to be used for
drainage where grade in cutting is
Cess Drain less than 1 in 200 or where
CUTTING additional drainage is required.
3 :1 3 :1
1.5 :1 1.5 :1
Ballast
1 in 30 1 in 30 1 in 30
1 in 30
Capping Subsurface Drain
Surface Drain
CENTRE DRAIN
Shoulder Distance
50 min.
1.5 :1
1 in 30 Ballast
1 in 30
Capping
TERRACE
EXISTING SLOPE
PROPOSED NEW
SLOPE
AC OR CONCRETE
PIPE 150 DIAM MIN 800 mm POROUS
MATERIAL
300 mm
EMBANKMENT CONSTRUCTION IN LAYERS REMOVAL OF SOIL
SEE DETAIL A
COMPACTED IN 200 mm LAYERS
SPALLING PROTECTION
100 mm TO 150 mm DRAINAGE BLANKET
ROCK AT ZONES OF PERMEABILITY 1.0 m
300 mm
DETAIL A
TYPICAL BENCHING PROCEDURE
EARTHWORKS CONSTRUCTION
Materials testing: Refer to material type, source, purpose of testing, sampling methods and
locations, test types, sample reference numbers, results obtained, and to whom distributed
Field density testing: Refer to types of test, section of work to which tests apply, test locations
and levels, test reference numbers, results obtained, and to whom distributed.
Laboratory compaction testing: Refer to test methods, location of sampling, sample reference
number, results obtained, and to whom distributed.
Works meeting geotechnical requirements: Refer to work type (e.g. stripping, subgrade
compaction), basis of assessment (e.g., inspection, test reference numbers, and the like), extent of
works apparently complying and requirements met*.
Remarks: Include observations on works, site conditions, meetings or conversations on site, and
the like.
Remarks:
Signed: