SFMC PROJECT-RIYADH 28-Sep-22

S.r No PI Comments PICTURE Reply


1 Compliance of All Engineer's comments in the above submittals. Noted

2 Submission of fire test of ACP panels as per NFPA and SBC. Document Attached

3 Submission of final clean copy signed off by newly appointed / approved lead designer. Noted

4
Provide certification from VISTA Wall that the delivered aluminum frame is in accordance to Document Attached
their standard profile.

5
Provide Certification from Guardian Glass that the delivered glasses are in accordance to their Document Attached
standard.

6 Noted
All delivered panel to be installed in accordance to approved IFC / Shop Drawing.

7
Glass of delivered spandrel panel are (HS) heat strength is not in accordance to toughened glass Document Attached
/ fully tempered as per approved shop drawing.

8
Delivered panel for vision glass are heat strength (external) and Toughened/ tempered glass Document Attached
(internal). In the shop drawings are mentioned "external" for both sides.

9 Rectify the damage of sealent in ACP due to Transportation. Noted

10
Spot Hole and uneven level on Applied Sealant are found in between the Glass And Mullion, it Noted
should be rectify properly.

11 Approval is subject to compliance of comments in the above submittal. Noted

12 Document Attached

Provide approved structural calculation reflecting the dimension sizes of brackets Vu- 237 & Vu-
209

Document Attached

Provides codes of materials to be inspected according to VISTA Wall profile: and use the form of
13
AMG Material inspection request as per attached in the method of statement. Signature over Noted
Printed name with Material Engineer, QC Engineer, Qc Manager including stamp from AMG
company is required.

14
Installation of the inspected items above must be in accordance with the approved Noted
Architectural shop drawing.

15
Almost all vision glass that was replaced from GGI to UNIglass has still more serve distortion Noted
compared to benchmark

16
Shop Drawing for General Detail of Extruded Aluminum Cover Cap with Ref. MI-AA-A2-B01.02- Need to Resubmission
A0-WS-004-08-02 is code C. Approval of shop Drawing prior for installation is required .

17 Horizontal and Vertical EPDM Gasket including sealants Between glass to be check and rectify Noted
by ABV

18 Final acceptance is subject to compliance of comments in the above submittal Noted

19 Damages of sealant scratches of ACP during transportation and installation should be rectify Noted

Installation system of Extruded Aluminum Cover Cap is Code C due to expose screw as
20 commented in the submittal drawing with ref. MI-AA-A2-B01.02.A0-WS.004-08-02. Provide Need to Resubmission
Approved details including the elevation plan where it fixed

Provide stainless steel pan head self-tapping screw (AF-007) with sealant at point A. And used
21 rivet with sealant at B instead of the screw as per detail MI-MM-A2-B01.02-A0-90-094-08-00 Need to Resubmission
(22/94)