PERINCIAN PERHITUNGAN IURAN PROYEK

SESUAI PERMENAKER NO 44 TAHUN 2015

Nama Proyek BELANJA JASA KONSULTASI PERENCANAAN (GF)


Lokasi Proyek #REF!

NILAI PROYEK 5,419,963,845


PPN/IMB 100/110
NILAI PROYEK - PPN/IMB 4,927,239,859

Batas I Rp100,000,000
Batas II Rp400,000,000
Batas III Rp500,000,000
Batas IV Rp4,000,000,000
Batas V selebihnya

TARIF NILAI PROYEK Jumlah Bayar

0,24% Rp100,000,000 Rp240,000

0,19% Rp400,000,000 Rp760,000

0,15% Rp500,000,000 Rp750,000

0,12% Rp3,927,239,859 Rp4,712,688

0,10% Rp0 Rp0

IURAN YANG DIBAYAR Rp6,462,688

Iuran tersebut diatas agar dibayarkan melalui Bank Pembangunan Daerah Jawa Barat Dan Banten (BJB)
CAB. TASIKMALAYA, NO REKENING : 0050020032700 Rp6,462,688
JADWAL PELAKSANAAN (TIME SCHEDULE)
#REF!
TAHUN ANGGARAN 2021

BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6


SUB JUMLAH BOBOT
NO URAIAN PEK ERJAAN M1 M2 M3 M4 M5 M6 M7 M8 M9 M 10 M 11 M 12 M 13 M 14 M 15 M 16 M 17 M 18 M 19 M 20 M 21 KET.
7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147
(Rp) %

#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 100
#REF! #REF!
#REF! #REF! 90
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! 2.00 3.00 3.00 3.00 3.20 #REF!
80
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 70
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 60
#REF! #REF! #REF! #REF! #REF! #REF!
50
#REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
40
#REF! #REF! #REF! #REF! 1.50 2.00 2.00 #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 30
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! 0.50 0.50 #REF!
20
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! 10

#REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 10
#REF! #REF! #REF! #REF! #REF! #REF! 0
10
#REF! #REF! #REF! #REF! #REF! #REF! 10

JUMLAH #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH KUMULATIF #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

#REF!
#REF!

#REF!
#REF!
REKAPITULASI RENCANA ANGGARAN BIAYA
RINCIAN RENCANA ANGGARAN BIAYA
KEGIATAN : BELANJA JASA KONSULTASI PERENCANAAN (GF)
PEKERJAAN : JASA KONSULTASI PERENCANAAN (GF)
LOKASI : Kota Tasikmalaya
TAHUN ANGGARAN : 2021

SUB JUMLAH
NO URAIAN PEK ERJAAN
(Rp)

I PEKERJAAN PERSIAPAN 326,040,946.83


II PEKERJAAN PELAKSANAAN
A BANGUNAN GUDANG FARMASI
A.I PEKERJAAN TANAH DAN PONDASI 703,672,096.78
A.II PEKERJAAN BETON 1,614,514,433.52
A.III PEKERJAAN BAJA 16,151,261,267.20
A.IV PEKERJAAN DINDING 311,362,045.86
A.V PEKERJAAN KUSEN PINTU & JENDELA 1,259,037.50
A.VI PEKERJAAN PENUTUP ATAP & CLADDING 1,748,125,781.28
A.VII PEKERJAAN PLAFON 101,189,075.56
A.VIII PEKERJAAN LANTAI 77,854,332.44
A.IX PEKERJAAN PENGECATAN 123,799,434.56
A.X PEKERJAAN ELEKTRIKAL #NAME?
A.XI PEKERJAAN SANITASI #REF!
A.XII PEKERJAAN SALURAN DAN LAINNYA #REF!
B BANGUNAN GENSET
B.I PEKERJAAN TANAH DAN PONDASI 74,848,207.97
B.II PEKERJAAN BETON 228,498,147.31
B.III PEKERJAAN DINDING 19,249,207.48
B.IV PEKERJAAN KUSEN PINTU & JENDELA 1,388,362.50
B.V PEKERJAAN PLAFON 3,070,159.20
B.VI PEKERJAAN PENGECATAN 222,033,006.15
B.VII PEKERJAAN ELEKTRIKAL #NAME?
B.VIII PEKERJAAN SANITASI #REF!
C BANGUNAN POS JAGA
C.I PEKERJAAN TANAH DAN PONDASI 49,185,468.53
C.II PEKERJAAN BETON 94,562,367.69
C.III PEKERJAAN DINDING 84,538,405.49
C.IV PEKERJAAN KUSEN PINTU & JENDELA 399,100.00
C.V PEKERJAAN PLAFON 551,350.80
C.VI PEKERJAAN LANTAI 3,135,410.30
C.VII PEKERJAAN PENGECATAN 100,223,602.50
C.VIII PEKERJAAN ELEKTRIKAL #NAME?
C.IX PEKERJAAN SANITASI #REF!
D PEKERJAAN LAIN LAIN
D.I PEK. PAGAR 469,139,796.73
JUMLAH Rp. #NAME?
PPn 10% #NAME?
T O T A L Rp. #NAME?
DIBULATKAN Rp. #NAME?

TERBILANG : #NAME?

Tasikmalaya, . . . . . . . . . . 2021
Diperiksa : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan Konsultan Perencana
Dinas Kesehatan Kota Tasikmalaya CV. CID CONSULTANT

Hj. SUSILAWATI SIFIATI, SKM., M.SI. IRWAN HARYANTO


NIP.19681111 199603 2 003 Direktur

Disetujui :
PA / PPK
Dinas Kesehatan Kota Tasikmalaya
UUS SUPANGAT, dr.
NIP.19700903 200604 1 008
RINCIAN RENCANA ANGGARAN BIAYA

KEGIATAN : BELANJA JASA KONSULTASI PERENCANAAN (GF)


PEKERJAAN : JASA KONSULTASI PERENCANAAN (GF)
LOKASI : Kota Tasikmalaya
TAHUN ANGGARAN : 2021

KODE HARGA SAT. JML. HARGA


NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.4 2,275 m2 67,500.00 153,586,125.00
2 Papan Nama Proyek ( 80 x 120 cm) U&B 1.00 bh 300,000.00 300,000.00
3 Pek. Pengurugan sirtu A.2.3.1.9 2,515.00 m2 58,300.00 146,624,721.83
4 Pas. Direksi keet A.2.2.1.14 9.00 m2 736,900.00 6,632,100.00
5 Penyedian air kerja + listrik kerja U&B 1.00 ls 3,000,000.00 3,000,000.00
6 Biaya Sistem Manajemen Kesehatan Keselamatan 1.00 ls 15,898,000.00 15,898,000.00
konstruksi (SMK3)
JUMLAH I 326,040,946.83
II PEKERJAAN PELAKSANAAN
A BANGUNAN GUDANG FARMASI
A.I PEKERJAAN TANAH DAN PONDASI
1 Mobilisasi dan Demobilisasi alat pancang U&B 1.00 ls 65,000,000.00 65,000,000.00
2 Pengadaan Tiang Pancang Segi Tiga 28x28x28 cm K-450 U&B 144.00 m' 225,000.00 32,400,000.00
3 Pek. Pemasangan Tiang pancang & Penyambungan A.4.1.1.36 128.00 m' 115,300.00 16,603,200.00
4 Pek. Loading Test Beban Langsung U&B 2.00 ttk 1,500,000.00 3,000,000.00
5 Pek. Potong Kepala Tiang pancang A.2.2.1.7 0.63 m3 376,700.00 236,266.24
6 Pek. Pengukuran & Bouwplank A.2.2.1.13 128.00 m' 1,473,900.00 188,659,200.00
7 Pek. Galian tanah A.2.3.1.10 347.45 m3 58,300.00 20,256,268.54
8 Pek. Urugan kembali A.2.3.1.5 86.86 m3 164,000.00 14,245,403.26
9 Pek. Urugan pasir bawah pondasi A.2.3.1.7 18.54 m3 5,800.00 107,522.72
10 Pek. Aanstamping A.4.1.1 42.19 m3 - -
11 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.4 92.81 m3 744,500.00 69,096,449.40
12 Pek. Lantai kerja pondasi setempat A.4.1.1.15 0.83 m3 12,800.00 10,649.60
13 Pek. Pilecap ( P1 )
- Beton K225 A.4.1.1.18 4.61 m3 15,200.00 70,041.60
- Besi beton A.4.1.1.27 1,833.28 kg 104,000.00 190,661,492.74
- Bekisting A.4.1.1.6 7.68 m2 1,011,700.00 7,769,856.00
14 Pek. Pilecap ( P2 )
- Beton K225 A.4.1.1.18 2.05 m3 15,200.00 31,129.60
- Besi beton A.4.1.1.27 777.76 kg 104,000.00 80,886,693.89
- Bekisting A.4.1.1.6 4.10 m2 1,011,700.00 4,143,923.20
15 Pek. Urugan Sirtu Perataan Elevasi Lantai A.2.3.1.9 180.00 m3 58,300.00 10,494,000.00
JUMLAH A.I 703,672,096.78
A.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 20/35
- Beton K225 A.4.1.1.18 7.12 m3 15,200.00 108,281.15
- Besi beton A.4.1.1.27 2,233.69 kg 104,000.00 232,303,449.83
- Bekisting A.4.1.1.7 37.49 m2 1,032,600.00 38,714,239.20
2 Pek. Beton Sloof S2 15/20
- Beton K225 A.4.1.1.18 3.21 m3 15,200.00 48,760.08
- Besi beton A.4.1.1.27 544.18 kg 104,000.00 56,594,834.15
- Bekisting A.4.1.1.7 21.39 m2 1,032,600.00 22,083,183.60
3 Pek. Beton Kolom Praktis 13/13
- Beton K100 A.4.1.1.15 4.23 m3 12,800.00 54,149.22
- Besi beton A.4.1.1.27 802.23 kg 104,000.00 83,431,637.45
- Bekisting A.4.2.1.11 32.54 m2 143,500.00 4,669,719.60
4 Pek. Kolom K1 30/50
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
- Beton K225 A.4.1.1.18 13.45 m3 15,200.00 204,379.20
- Besi beton A.4.1.1.27 1,002.80 kg 104,000.00 104,291,136.89
- Bekisting A.4.1.1.8 71.71 m2 1,048,800.00 75,211,545.60
5 Pek. Kolom K2 25/45
- Beton K225 A.4.1.1.18 6.72 m3 15,200.00 102,189.60
- Besi beton A.4.1.1.27 1,138.36 kg 104,000.00 118,389,937.54
- Bekisting A.4.1.1.8 43.79 m2 1,048,800.00 45,929,049.60
6 Pek. Beton Balok Lintel 13/15 diatas kusen
- Beton K100 A.4.1.1.15 1.06 m3 12,800.00 13,603.20
- Besi beton A.4.1.1.27 172.68 kg 104,000.00 17,958,635.14
- Bekisting A.4.2.1.12 11.40 m2 - -
7 Pek. Beton Balok 13/15 Elv. +4.00
- Beton K100 A.4.1.1.15 4.34 m3 12,800.00 55,518.53
- Besi beton A.4.1.1.27 680.25 kg 104,000.00 70,745,594.40
- Bekisting A.4.2.1.12 44.92 m2 - -
8 Pek. Beton Balok BB 20/50 Elv. +4.00
- Beton K225 A.4.1.1.18 1.20 m3 15,200.00 18,240.00
- Besi beton A.4.1.1.27 206.71 kg 104,000.00 21,497,838.34
- Bekisting A.4.1.1.9 7.20 m2 1,073,900.00 7,732,080.00
9 Pek. Pelat Beton Elv. +0.00
- Pek. Urugan pasir A.2.3.1.7 62.35 m3 5,800.00 361,611.15
- Pek. Lantai kerja A.4.1.1.15 31.17 m3 12,800.00 399,019.20
- Beton K225 A.4.1.1.18 112.72 m3 15,200.00 1,713,406.32
- Besi beton A.4.1.1.27 5,340.37 kg 104,000.00 555,398,694.86
- Wiremesh M6 A.4.1.1.35 1,246.94 m2 90,100.00 112,348,843.50
- Bekisting A.4.1.20 70.07 m2 334,300.00 23,423,732.40
- Pek. Floor hardener A.4.5.2.14 642.62 m2 24,700.00 15,872,636.81
11 Pek. Meja Beton
- Beton K100 A.4.1.1.15 0.07 m3 12,800.00 860.16
- Besi beton A.4.1.1.27 8.38 kg 104,000.00 871,977.60
- Bekisting A.4.1.20 0.50 m2 334,300.00 167,150.00
12 Pek. Lantai rabat beton/ beton tumbuk 1:3:5
- Beton A.4.1.1.15 8.42 m3 12,800.00 107,827.20
- Bekisting A.4.1.20 11.04 m2 334,300.00 3,690,672.00
JUMLAH A.II 1,614,514,433.52
A.III PEKERJAAN BAJA
1 Pek. Kolom K1 WF 400.200.8.13 A.4.2.1.16 1,183.27 kg 360,600.00 426,687,818.26
Pek. Angkur Ø19 L500 U&B 72.00 bh 27,500.00 1,980,000.00
2 Pek. Kolom K2 WF 250.125.6.9 A.4.2.1.16 561.23 kg 360,600.00 202,379,756.11
Pek. Angkur Ø19 L500 U&B 32.00 bh 27,500.00 880,000.00
3 Pek. Balok B2 WF 250.125.6.9 A.4.2.1.16 2,133.90 kg 360,600.00 769,484,347.70
Pek. Bolt ∅16-A325 U&B 80.00 bh 13,000.00 1,040,000.00
4 Pek. Balok B1 HC 400.200.8.13 A.4.2.1.16 15,324.17 kg 360,600.00 5,525,894,494.93
BOLT ∅16-A325 U&B 216.00 bh 13,000.00 2,808,000.00
5 Pek. Gording C 150.65.20.2,3 A.4.2.1.19 6,336.66 kg 1,260,000.00 7,984,193,910.79
BOLT ∅10-A325 U&B 320.00 bh 11,250.00 3,600,000.00
6 Pek. Trekstang Ø12 A.4.2.1.19 199.75 kg 1,260,000.00 251,679,960.00
7 Pek. Bracing Ø16 A.4.2.1.19 363.63 kg 1,260,000.00 458,169,384.96
8 Pek. Balok B2 Kanopy WF 250.125.6.9 A.4.2.1.16 379.20 kg 360,600.00 136,740,811.14
Angkur Ø16 L300 U&B 16.00 bh 19,000.00 304,000.00
9 Pek. Gording Kanopy C 150.65.20.2,3 A.4.2.1.19 305.67 kg 1,260,000.00 385,148,783.31
BOLT ∅10-A325 U&B 24.00 bh 11,250.00 270,000.00
JUMLAH A.III 16,151,261,267.20
A.IV PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.2.14 1,051.16 m2 75,500.00 79,362,844.25
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
2 Pek. Plesteran Dinding A.4.4.2.9 2,089.54 m2 66,300.00 138,536,236.80
3 Pek. Plesteran Beton A.4.4.2.9 382.75 m2 66,300.00 25,376,338.26
4 Pek. acian A.4.4.3.28 2,472.29 m2 25,500.00 63,043,298.10
5 Pek. Dinding Keramik A.4.5.1.8 31.38 m2 160,700.00 5,043,328.45
JUMLAH A.IV 311,362,045.86
A.V PEKERJAAN KUSEN PINTU & JENDELA
1 Pek. kusen tipe P1 A.4.2.1.5 6.00 unit 22,400.00 134,400.00
2 Pek. kusen tipe P2 A.4.2.1.6.a 2.00 unit 183,100.00 366,200.00
3 Pek. kusen tipe PB1 A.4.2.1.2.a 4.95 m2 33,500.00 165,825.00
4 Pek. kusen tipe PB2 A.4.2.1.2.a 11.48 m2 33,500.00 384,412.50
5 Pek. kusen tipe J1 A.4.4.1 5.00 unit - -
6 Pek. Kusen RD A.4.2.1.23 2.00 unit 104,100.00 208,200.00
7 Pek. kusen BV2 A.4.4.1.15 6.00 unit - -
JUMLAH A.V 1,259,037.50
A.VI PEKERJAAN PENUTUP ATAP & CLADDING
1 Pek. Rangka baja ringan U&B 936.59 m2 130,000.00 121,757,116.00
2 Pek. Bubble Alumuniun Foil A.4.6.2.15 936.59 m2 55,000.00 51,512,626.00
3 Pek. Penutup atap bitument A.4.6.1.5. 936.59 m2 1,357,900.00 1,271,799,906.28
4 Pek. Bubungan/ nok genteng aspal A.4.6.2 31.00 m' - -
5 Pek. Cladding ACP A.4.4.1.16 708.98 m2 385,200.00 273,098,133.00
6 Pek. Talang Datar Zincalume A.4.4.1.21 60.00 m' 250,300.00 15,018,000.00
7 Pek. Huruf Stainless Steel U&B 1,245.00 cm 12,000.00 14,940,000.00
JUMLAH A.VI 1,748,125,781.28
A.VII PEKERJAAN PLAFON
1 Pek. Rangka hollow galvanis A.4.4.1.24 472.59 m2 - -
2 Pek. Plafon Gypsum board A.4.5.2.33 229.48 m2 341,400.00 78,342,978.38
3 Pek. Plafon GRC A.4.5.2.34 6.82 m2 51,500.00 351,101.25
4 Pek. Penutup Atas Plafon A.4.5.2.34 236.29 m2 51,500.00 12,169,095.94
5 Pek. Profil Plafon A.4.5.2.38 219.70 m' 47,000.00 10,325,900.00
JUMLAH A.VII 101,189,075.56
A.VIII PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.7 11.81 m3 5,800.00 68,525.01
2 Pek. Lantai Granit 60x60 A.4.5.2.21 234.05 m2 24,700.00 5,780,926.94
3 Pek. Plint t=10cm Granit 60x60 A.4.4.3.53 305.80 m' 215,500.00 65,899,900.00
4 Pek. Lantai Granit 60x60 Antislip A.4.5.2.22 11.25 m2 25,900.00 291,375.00
5 Pek. Plint t=10cm Granit 60x60 Antislip A.4.4.3.53 15.00 m' 215,500.00 3,232,500.00
6 Pek. Lantai keramik 25x25 Antislip A.4.4.3.69 6.82 m2 378,600.00 2,581,105.50
JUMLAH A.VIII 77,854,332.44
A.IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.5.1.1.28 2,125.39 m2 52,500.00 111,583,080.00
2 Pek. Pengecatan Plafon A.5.1.1.29 236.29 m2 51,700.00 12,216,354.56
JUMLAH A.IX 123,799,434.56
A.X PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-17 52.00 ttk 118,440.00 6,158,880.00
2 Pas. Instalasi stopkontak #NAME? 21.00 ttk #NAME? #NAME?
3 Penangkal Petir + grounding #NAME? 2.00 ttk #NAME? #NAME?
- Aksesoris
4 Pas. Lampu RMI 2x18 Watt U&B 27.00 bh 269,000.00 7,263,000.00
5 Pas. Down Light 5 Watt U&B 3.00 bh 91,355.00 274,065.00
6 Pas. Lampu Baret U&B 2 bh 125,000.00 250,000.00
7 Pas. Lampu gantung U&B 20 bh 2,650,000.00 53,000,000.00
8 Pas. Stop Kontak #NAME? 21.00 bh #NAME? #NAME?
9 Pas. Stop Kontak AC #NAME? 5.00 bh #NAME? #NAME?
10 Pas. Saklar ganda #NAME? 14.00 bh #NAME? #NAME?
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
11 Pas. Saklar tunggal #NAME? 4.00 bh #NAME? #NAME?
12 Box Schreeng In-bouw C4 U&B 1.00 bh 52,500.00 52,500.00
13 Pentanahan (Grounding) Netral Sistem & Pentanahan Body U&B 1.00 ls 658,400.00 658,400.00
14 Fire Extinguiser (APAR) + Bracket U&B 5.00 bh 1,350,000.00 6,750,000.00
15 Pas. AC 1 Pk U&B 5.00 bh 6,250,000.00 31,250,000.00
16 Pas. Kipas Angin U&B 7.00 bh 975,000.00 6,825,000.00
JUMLAH A.X #NAME?
A.XI PEKERJAAN SANITASI
1 Pek. Sanitair
- Pas. Closet jongkok Sistem Jet Dihit. F-08 2.00 bh 6,632,600.00 13,265,200.00
- Pas. Wastafel Dihit. F-10 1.00 bh 1,605,700.00 1,605,700.00
- Pas. Kran dinding Dihit. K-43 4.00 bh 39,500.00 158,000.00
- Pas. Floor Drain Dihit. I-05 3.00 bh 289,100.00 867,300.00
2 Instalasi Pemipaan Air Bersih
- Pek. Sumur Bor + Pemipaan P-13 1.00 unit 341,470.00 341,470.00
- Pek. Tandon Air P-14 1.00 unit #REF! #REF!
- Pipa PVC dia. 3/4" Dihitung 12.00 m' - -
- Pipa PVC dia. 1/2" Dihit. O-07 46.00 m' 410,625,900.00 18,888,791,400.00
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls 1,888,883,100.00 1,888,883,100.00
3 Instalasi Pemipaan Air Kotor
- Pipa PVC-D dia. 1 1/2" P-02 2.00 m' 462,840.00 925,680.00
- Pipa PVC dia. 3" P-05 18.00 m' #REF! #REF!
- Pipa PVC dia. 4" P-06 30.00 m' #REF! #REF!
- Pipa air hujan PVC dia. 4" P-06 117.36 m' #REF! #REF!
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls #REF! #REF!
5 Septictank P-11 1.00 unit 1,120,700.00 1,120,700.00
6 Resapan P-12 1.00 unit 93,670.00 93,670.00
JUMLAH A.XI #REF!
A.XII PEKERJAAN SALURAN DAN LAINNYA
1 Pek. Saluran Grafel Beton 1/2 Ø 30 cm P-08 130.80 m' #REF! #REF!
2 Pek. Tangga besi A.4.2.1.15 206.37 kg 1,150,100.00 237,341,306.58
JUMLAH A.XII #REF!
B BANGUNAN GENSET
B.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran & Bouwplank A.2.2.1.13 32.00 m' 1,473,900.00 47,164,800.00
2 Pek. Galian tanah A.2.3.1.10 19.90 m3 58,300.00 1,160,111.70
3 Pek. Urugan kembali A.2.3.1.5 4.97 m3 164,000.00 815,859.00
4 Pek. Urugan pasir bawah pondasi A.2.3.1.7 6.29 m3 5,800.00 36,464.60
5 Pek. Aanstamping A.4.1.1 6.60 m3 - -
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.4 14.52 m3 744,500.00 10,810,140.00
7 Pek. Lantai kerja pondasi setempat A.4.1.1.15 1.82 m3 12,800.00 23,340.80
8 Pek. Pilecap
- Beton K225 A.4.1.1.18 0.92 m3 15,200.00 14,008.32
- Besi beton A.4.1.1.27 117.36 kg 104,000.00 12,205,224.35
- Bekisting A.4.1.1.6 2.30 m2 1,011,700.00 2,330,956.80
9 Pek. Urugan Sirtu Perataan Elevasi Lantai A.2.3.1.9 4.93 m3 58,300.00 287,302.40
JUMLAH B.I 74,848,207.97
B.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 20/25
- Beton K225 A.4.1.1.16 1.55 m3 15,200.00 23,607.12
- Besi beton A.4.1.1.27 241.75 kg 104,000.00 25,141,678.85
- Bekisting A.4.1.1.7 7.72 m2 1,032,600.00 7,971,672.00
2 Pek. Beton Kolom Praktis 13/13
- Beton K100 A.4.1.1.15 0.23 m3 12,800.00 2,898.69
- Besi beton A.4.1.1.27 43.32 kg 104,000.00 4,505,149.21
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
- Bekisting A.4.2.1.11 1.74 m2 143,500.00 249,977.00
3 Pek. Kolom K3 20/20
- Beton K225 A.4.1.1.18 1.07 m3 15,200.00 16,294.40
- Besi beton A.4.1.1.27 42.73 kg 104,000.00 4,443,905.61
- Bekisting A.4.1.1.8 10.72 m2 1,048,800.00 11,243,136.00
4 Pek. Beton Balok Lintel diatas kusen
- Beton K100 A.4.1.1.15 0.47 m3 12,800.00 5,990.40
- Besi beton A.4.1.1.27 78.38 kg 104,000.00 8,151,451.78
- Bekisting A.4.2.1.12 5.16 m2 - -
5 Pek. Beton Balok B1 15/25 Elv. +3.00
- Beton K225 A.4.1.1.18 1.13 m3 15,200.00 17,100.00
- Besi beton A.4.1.1.27 198.70 kg 104,000.00 20,665,253.61
- Bekisting A.4.1.1.9 9.75 m2 1,073,900.00 10,470,525.00
7 Pek. Pelat Beton Elv. +3.00
- Beton K225 A.4.1.1.18 4.01 m3 15,200.00 61,001.86
- Besi beton A.4.1.1.27 678.78 kg 104,000.00 70,592,998.32
- Bekisting A.4.1.20 33.01 m2 334,300.00 11,033,772.08
8 Pek. Pelat Lantai Elv. +0.00
- Pek. Urugan pasir A.2.3.1.7 3.14 m3 5,800.00 18,183.00
- Pek. Lantai kerja A.4.1.1.15 1.57 m3 12,800.00 20,064.00
- Beton K225 A.4.1.1.18 4.33 m3 15,200.00 65,800.80
- Besi beton A.4.1.1.27 511.76 kg 104,000.00 53,222,691.60
- Bekisting A.4.1.20 1.72 m2 334,300.00 574,996.00
JUMLAH B.II 228,498,147.31
B.III PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.2.14 53.60 m2 75,500.00 4,047,026.50
2 Pek. Plesteran Dinding A.4.4.2.9 165.60 m2 66,300.00 10,979,352.93
3 Pek. acian A.4.4.3.28 165.60 m2 25,500.00 4,222,828.05
JUMLAH B.III 19,249,207.48
B.IV PEKERJAAN KUSEN PINTU & JENDELA
1 Pek. kusen tipe PB1 A.4.2.1.2.a 4.95 m2 33,500.00 165,825.00
2 Pek. kusen tipe PB3 A.4.2.1.2.a 3.83 m2 33,500.00 128,137.50
3 Pek. kusen tipe LV1 A.4.4.1.1 6.00 unit 182,400.00 1,094,400.00
JUMLAH B.IV 1,388,362.50
B.V PEKERJAAN PLAFON
1 Pek. Plafon Expose 33.44 m2 91,800.00 3,070,159.20
JUMLAH B.V 3,070,159.20
B.VI PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.5.1.1.28 165.60 m2 52,500.00 8,694,057.75
2 Pek. Pengecatan Plafon A.5.1.1.29 33.44 m2 51,700.00 1,729,054.80
3 Pek. Pengecatan Waterproofing Dihit. F-02 37.94 m2 5,576,900.00 211,609,893.60
JUMLAH B.VI 222,033,006.15
B.VII PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-17 6.00 ttk 118,440.00 710,640.00
2 Pas. Instalasi stopkontak #NAME? 1.00 ttk #NAME? #NAME?
- Aksesoris
3 Lampu RMI 2x18 Watt U&B 4.00 bh 269,000.00 1,076,000.00
4 Lampu baret U&B 2.00 bh 125,000.00 250,000.00
5 Stop Kontak #NAME? 1.00 bh #NAME? #NAME?
6 Saklar ganda #NAME? 2.00 bh #NAME? #NAME?
7 Saklar tunggal #NAME? 1.00 bh #NAME? #NAME?
8 Fire Extinguiser (APAR) + Bracket U&B 1.00 bh 1,350,000.00 1,350,000.00
- Pek. Penyambungan Listrik PLN
9 Biaya Pemasangan Listrik 5500 watt U&B 1.00 lot 8,800,000.00 8,800,000.00
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
10 Kabel NYY 4 x 10 mm - 25.00 m' 372,000.00 9,300,000.00
11 Panel SDP U&B 1.00 bh 203,000.00 203,000.00
12 Ohm Saklar u/PLN & Diesel U&B 1.00 bh 203,000.00 203,000.00
13 Pentanahan (Grounding) Netral Sistem & Pentanahan Body U&B 1.00 ls 658,400.00 658,400.00
JUMLAH B.VII #NAME?
B.VIII PEKERJAAN SANITASI
1 Instalasi Pemipaan Air Kotor
- Pipa air hujan PVC dia. 4" P-06 18.00 m' #REF! #REF!
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls #REF! #REF!
JUMLAH B.VIII #REF!
C BANGUNAN POS JAGA
C.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran & Bouwplank A.2.2.1.13 22.00 m' 1,473,900.00 32,425,800.00
2 Pek. Galian tanah A.2.3.1.10 29.81 m3 58,300.00 1,738,156.20
3 Pek. Urugan kembali A.2.3.1.5 7.45 m3 164,000.00 1,222,374.00
4 Pek. Urugan pasir bawah pondasi A.2.3.1.7 1.82 m3 5,800.00 10,532.80
5 Pek. Aanstamping A.4.1.1 3.90 m3 - -
6 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.4 8.58 m3 744,500.00 6,387,810.00
7 Pek. Lantai kerja pondasi setempat A.4.1.1.15 0.13 m3 12,800.00 1,638.40
8 Pek. Pilecap
- Beton K225 A.4.1.1.18 0.46 m3 15,200.00 7,004.16
- Besi beton A.4.1.1.27 58.68 kg 104,000.00 6,102,612.17
- Bekisting A.4.1.1.6 1.15 m2 1,011,700.00 1,165,478.40
9 Pek. Urugan Sirtu Perataan Elevasi Lantai A.2.3.1.9 2.13 m3 58,300.00 124,062.40
JUMLAH C.I 49,185,468.53
C.II PEKERJAAN BETON
1 Pek. Beton Sloof S1 20/25
- Beton K225 A.4.1.1.18 0.91 m3 15,200.00 13,890.90
- Besi beton A.4.1.1.27 143.10 kg 104,000.00 14,882,708.51
- Bekisting A.4.1.1.7 4.51 m2 1,032,600.00 4,659,607.50
2 Pek. Beton Kolom Praktis 13/13
- Beton K100 A.4.1.1.15 0.28 m3 12,800.00 3,623.36
- Besi beton A.4.1.1.27 72.32 kg 104,000.00 7,521,576.19
- Bekisting A.4.2.1.11 2.18 m2 143,500.00 312,471.25
3 Pek. Kolom K3 20/20
- Beton K225 A.4.1.1.18 0.54 m3 15,200.00 8,147.20
- Besi beton A.4.1.1.27 29.13 kg 104,000.00 3,029,557.94
- Bekisting A.4.1.1.8 5.36 m2 1,048,800.00 5,621,568.00
4 Pek. Beton Balok Lintel diatas kusen
- Beton K100 A.4.1.1.15 0.15 m3 12,800.00 1,872.00
- Besi beton A.4.1.1.27 24.57 kg 104,000.00 2,555,407.30
- Bekisting A.4.2.1.12 1.61 m2 - -
5 Pek. Beton Balok B1 15/25 Elv. +3.00
- Beton K225 A.4.1.1.18 0.64 m3 15,200.00 9,690.00
- Besi beton A.4.1.1.27 112.82 kg 104,000.00 11,732,920.24
- Bekisting A.4.1.1.9 5.53 m2 1,073,900.00 5,933,297.50
6 Pek. Pelat Beton Elv. +3.00
- Beton K225 A.4.1.1.18 1.75 m3 15,200.00 26,561.09
- Besi beton A.4.1.1.27 338.03 kg 104,000.00 35,154,802.80
- Bekisting A.4.1.20 9.26 m2 334,300.00 3,094,665.91
JUMLAH C.II 94,562,367.69
C.III PEKERJAAN DINDING
1 Pekerjaan Pasangan Dinding A.4.4.2.14 29.25 m2 75,500.00 2,208,533.55
2 Pekerjaan Plesteran Dinding A.4.4.2.9 85.36 m2 66,300.00 5,659,089.54
3 Pek. acian A.4.4.3.28 85.36 m2 25,500.00 2,176,572.90
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
4 Pek. Dinding Keramik A.4.5.1.8 10.11 m2 160,700.00 1,623,873.50
5 Pek. Ornamen hollow galvanis A.4.2.1.15 63.36 kg 1,150,100.00 72,870,336.00
JUMLAH C.III 84,538,405.49
C.IV PEKERJAAN KUSEN PINTU & JENDELA
1 Pek. kusen tipe PJ1 A.4.2.1.9 1.00 unit - -
2 Pek. kusen tipe P2 A.4.2.1.6.a 1.00 unit 183,100.00 183,100.00
3 Pek. kusen tipe BV1 A.4.4.1.14 1.00 unit - -
4 Pek. Glass block U&B 8.00 bh 27,000.00 216,000.00
JUMLAH C.IV 399,100.00
C.V PEKERJAAN PLAFON
1 Pek. Plafon Expose 6.01 m2 91,800.00 551,350.80
JUMLAH C.V 551,350.80
C.VI PEKERJAAN LANTAI
1 Pek. Urugan pasir bawah lantai A.2.3.1.7 0.49 m3 5,800.00 2,826.05
2 Pek. Lantai Granit 60x60 A.4.5.2.21 3.17 m2 24,700.00 78,360.75
3 Pek. Plint t=10cm Granit 60x60 A.4.4.3.53 6.50 m' 215,500.00 1,400,750.00
4 Pek. Lantai Granit 60x60 Antislip A.4.5.2.22 4.75 m2 25,900.00 123,025.00
5 Pek. Plint t=10cm Granit 60x60 Antislip A.4.4.3.53 3.90 m' 215,500.00 840,450.00
6 Pek. Lantai keramik 25x25 Antislip A.4.4.3.69 1.82 m2 378,600.00 689,998.50
JUMLAH C.VI 3,135,410.30
C.VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.5.1.1.28 85.36 m2 52,500.00 4,481,179.50
2 Pek. Pengecatan Plafon A.5.1.1.29 6.01 m2 51,700.00 310,510.20
3 Pek. Pengecatan Waterproofing Dihit. F-02 17.11 m2 5,576,900.00 95,431,912.80
JUMLAH C.VII 100,223,602.50
C.VIII PEKERJAAN ELEKTRIKAL
- Instalasi
1 Pas. Instalasi lampu P-17 3.00 ttk 118,440.00 355,320.00
2 Pas. Instalasi stopkontak #NAME? 1.00 ttk #NAME? #NAME?
- Aksesoris
3 Lampu RMI 2x18 Watt U&B 1.00 bh 269,000.00 269,000.00
4 Lampu baret U&B 1.00 bh 125,000.00 125,000.00
5 Pas. Down Light 5 Watt U&B 1.00 bh 91,355.00 91,355.00
6 Stop Kontak #NAME? 1.00 bh #NAME? #NAME?
7 Saklar ganda #NAME? 1.00 bh #NAME? #NAME?
8 Saklar tunggal #NAME? 1.00 bh #NAME? #NAME?
9 Box Panel ListrikBox Schreeng In-bouw C4 U&B 1.00 bh 52,500.00 52,500.00
10 Fire Extinguiser (APAR) + Bracket U&B 1.00 bh 1,350,000.00 1,350,000.00
JUMLAH C.VIII #NAME?
C.IX PEKERJAAN SANITASI
1 Pek. Sanitair
- Pas. Closet jongkok Sistem Jet Dihit. F-08 1.00 bh 6,632,600.00 6,632,600.00
- Pas. Kran dinding Dihit. K-43 1.00 bh 39,500.00 39,500.00
- Pas. Floor Drain Dihit. I-05 1.00 bh 289,100.00 289,100.00
2 Instalasi Pemipaan Air Bersih
- Pipa PVC dia. 3/4" Dihitung 45.00 m' - -
- Pipa PVC dia. 1/2" Dihit. O-07 4.00 m' 410,625,900.00 1,642,503,600.00
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls 164,250,400.00 164,250,400.00
3 Pek. Instalasi Pemipaan Air Kotor
- Pipa PVC-D dia. 3" P-05 6.00 m' #REF! #REF!
- Pipa PVC-D dia. 4" P-06 25.00 m' #REF! #REF!
- Pek. Pipa Air hujan Pvc AW 4" P-06 9.00 m' #REF! #REF!
- Instalasi pipa + material bantu (support, lem, socket dll) - 1.00 ls #REF! #REF!
JUMLAH C.IX #REF!
D PEKERJAAN LAIN LAIN
KODE HARGA SAT. JML. HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA Rp. Rp.
1 2 3 4 5 6
PEK. PAGAR
D.I PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah A.2.3.1.10 51.53 m3 58,300.00 3,003,942.48
2 Pek. Urugan kembali A.2.3.1.5 12.88 m3 164,000.00 2,112,549.60
3 Pek. Urugan pasir bawah pondasi A.2.3.1.7 3.68 m3 5,800.00 21,346.32
4 Pek. Pondasi batu kali, 1 pc : 5 ps A.3.2.1.4 32.24 m3 744,500.00 24,005,658.00
5 Pek. Lantai kerja pondasi setempat A.4.1.1.15 0.67 m3 12,800.00 8,524.80
DII PEKERJAAN BETON
1 Pek. Pilecap P4
- Beton K225 A.4.1.1.18 2.50 m3 15,200.00 37,962.00
- Besi beton A.4.1.1.27 318.04 kg 104,000.00 33,075,681.21
- Bekisting A.4.1.1.6 8.33 m2 1,011,700.00 8,422,402.50
2 Pek. Beton Sloof S2 15/20
- Beton K225 A.4.1.1.18 3.27 m3 15,200.00 49,646.24
- Besi beton A.4.1.1.27 842.13 kg 104,000.00 87,581,635.32
- Bekisting A.4.1.1.7 24.45 m2 1,032,600.00 25,245,004.80
3 Pek. Kolom K2
- Beton K225 A.4.1.1.18 0.33 m3 15,200.00 5,044.50
- Besi beton A.4.1.1.27 58.09 kg 104,000.00 6,041,573.74
- Bekisting A.4.1.1.8 2.07 m2 1,048,800.00 2,165,772.00
4 Pek. Kolom K3
- Beton K225 A.4.1.1.18 5.40 m3 15,200.00 82,049.60
- Besi beton A.4.1.1.27 711.23 kg 104,000.00 73,967,500.34
- Bekisting A.4.1.1.8 53.98 m2 1,048,800.00 56,614,224.00
5 Pek. Beton Balok Lintel
- Beton K100 A.4.1.1.15 2.39 m3 12,800.00 30,623.42
- Besi beton A.4.1.1.27 399.64 kg 104,000.00 41,562,042.91
- Bekisting A.4.2.1.12 26.38 m2 - -
DIII PEKERJAAN DINDING
1 Pek. Pasangan Dinding A.4.4.2.14 246.91 m2 75,500.00 18,641,403.00
2 Pek. Plesteran Dinding A.4.4.2.9 493.81 m2 66,300.00 32,739,735.60
3 Pek. Plesteran Beton A.4.4.2.9 101.23 m2 66,300.00 6,711,847.35
4 Pek. acian A.4.4.3.28 595.05 m2 25,500.00 15,173,685.75
DIV PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding A.5.1.1.28 595.05 m2 52,500.00 31,239,941.25
DV PEKERJAAN PERAPIHAN
1 Pembersihan sisa pekerjaan - 1.00 ls 600,000.00 600,000.00
JUMLAH D.I 469,139,796.73
REKAPITULASI RENCANA ANGGARAN BIAYA
RINCIAN RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN TEMPAT BERMAIN


LOKASI : Jl. Nagarakasih
TAHUN ANGGARAN : 2022

NO URAIAN PEK ERJAAN SUB JUMLAH


(Rp)
I PEKERJAAN PERSIAPAN 781,440.00
II PEKERJAAN PELAKSANAAN
A PEMBANGUNAN TEMPAT BERMAIN 35,191,783.00
A.I PEKERJAAN TANAH DAN PONDASI 358,581.00
A.II PEKERJAAN BETON 919,596.00
A.III PEKERJAAN DINDING 1,117,350.00
A.IV PEKERJAAN LANTAI 9,689,856.00
A.V PEKERJAAN ATAP KANOPY 21,356,400.00
A.VI BIAYA OPERASIONAL DAN PERENCANAAN 1,750,000.00

JUMLAH Rp. 35,973,223.00


DIBULATKAN Rp. 35,000,000.00

TERBILANG : #NAME?
RINCIAN RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN TEMPAT BERMAIN


LOKASI : Jl. Nagarakasih
TAHUN ANGGARAN : 2022

KODE HARGA SAT. JML. HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
ANALISA Rp. Rp.

I PEKERJAAN PERSIAPAN 781,440.00


1 Pek. pembersihan lahan A.2.2.1.9 47.36 m2 16,500.00 781,440.00
JUMLAH I 781,440.00
II PEKERJAAN PELAKSANAAN
A PEMBANGUNAN TEMPAT BERMAIN
A.I PEKERJAAN TANAH DAN PONDASI 358,581.00
Pasir Urug A.2.3.1.11 2.37 m3 151,300.00 358,581.00
JUMLAH A.I 358,581.00
A.II PEKERJAAN BETON 919,596.00
Balok
Beton K225 A.4.1.1.7 0.19 m3 1,032,600.00 196,194.00
Pembesian A.4.1.1.17 30.06 kg 15,800.00 474,948.00
Bekisting A.4.1.1.23 0.86 m2 288,900.00 248,454.00
JUMLAH A.II 919,596.00
A.III PEKERJAAN DINDING 1,117,350.00
Pek. Pasangan Dinding A.4.4.1.10 3.90 m2 76,300.00 297,570.00
Pek. Plesteran Dinding A.4.4.2.5 7.80 m2 65,400.00 510,120.00
Pek. acian A.4.4.2.27 7.80 m2 39,700.00 309,660.00
JUMLAH A.III 1,117,350.00
A.IV PEKERJAAN LANTAI 9,689,856.00

Pek. Lantai Keramik A.4.4.3.35 47.36 m2 204,600.00 9,689,856.00


JUMLAH A.IV 9,689,856.00

A.V PEKERJAAN ATAP KANOPY 21,356,400.00


Rangka Atap Baja Ringan 54.76 M2 180,000.00 9,856,800.00
Penutup Atap Polycarbonate Alderon Twinlite Greca 6mm 54.76 m2 210,000.00 11,499,600.00
JUMLAH A.V 21,356,400.00
A.VI BIAYA OPERASIONAL DAN PERENCANAAN 1,750,000.00
BIAYA Operasional 875,000.00 875,000.00
Biaya Pembuatan RAB 875,000.00 875,000.00
JUMLAH A.VI 1,750,000.00
HARGA SATUAN PEKERJAAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2021

KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A.2.2.1.1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter 70,800.00
A.2.2.1.10 Pembuatan 1 m2 steger/perancah dari bambu 376,700.00
A.2.2.1.12 Pembuatan 1 m2 jalan sementara 105,100.00
A.2.2.1.13 Pembongkaran 1 m3 beton bertulang 1,473,900.00
A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata 736,900.00
A.2.2.1.15 Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm 10,100.00
A.2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter 240,600.00
A.2.2.1.3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 2 meter 62,000.00
A.2.2.1.4 Pengukuran dan pemasangan 1 m' Bouwplank 67,500.00
A.2.2.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran 614,300.00
A.2.2.1.6 Pembuatan 1 m2 rumah jaga (konstruksi kayu) 310,200.00
A.2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan 376,700.00
A.2.2.1.8 Pembuatan 1 m2 bedeng pekerja 376,700.00
A.2.2.1.9 Pembersihan 1 m2 lapangan dan perataan 16,500.00
B A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m3 tanah sedalam 1 m 81,400.00
A.2.3.1.10 Pemadatan tanah 1m3 tanah(per 20) 58,300.00
A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug 151,300.00
A.2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan 29,000.00
A.2.3.1.14 Pengurugan 1 m3 sirtu padat 174,300.00
A.2.3.1.15 Pengurugan 1m3 Tanah Subur 108,300.00
A.2.3.1.2 Penggalian 1 m3 tanah sedalam 2 m 99,400.00
A.2.3.1.3 Penggalian 1 m3 tanah sedalam 3 m 117,800.00
A.2.3.1.4 Menggali 1 m3 tanah keras sedalam 1 m 108,300.00
A.2.3.1.5 Menggali 1 m3 tanah cadas sedalam 1 m 164,000.00
A.2.3.1.6 Menggali 1 m3 tanah lumpur sedalam 1 m 130,800.00
A.2.3.1.7 Pengerjaan Stripping 1 m2 tanah tebing setinggi 1 m 5,800.00
A.2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 meter 35,600.00
A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah 58,300.00
C A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP 702,700.00
A.3.2.1.10 Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB 2,712,000.00
A.3.2.1.11 Pemasangan 1 m3 pondasi sumuran, diameter 100 cm 891,600.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP 796,700.00
A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 766,100.00
A.3.2.1.4 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 744,500.00
A.3.2.1.5 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP 710,200.00
A.3.2.1.6 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1KP : 2PP 637,600.00
A.3.2.1.7 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 KP : 10 PP 656,200.00
A.3.2.1.8 Pemasangan 1 m3 pondasi batu belah campuran ¼ SP : 1 KP : 4PP 636,300.00
A.3.2.1.9 Pemasangan 1 m3 batu kosong (anstamping) 388,100.00
D A.4.1.1 HARGA SATUAN PEKERJAAN BETON
E A.4.1.1 HARGA SATUAN PEKERJAAN BEKISTING
A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 Mpa 890,700.00
A.4.1.1.10 Membuat 1 m3 beton mutu f'c = 26.4 Mpa (K 300) 1,081,600.00
A.4.1.1.11 Membuat 1 m3 beton mutu f'c = 28.8 Mpa (K 325) 1,170,700.00
A.4.1.1.12 Membuat 1 m3 beton mutu f’c = 31.2 MPa, slump (120 ± 20) mm 1,180,900.00
A.4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox – 100 1,134,100.00
A.4.1.1.14 Pemasangan 1 m’ PVC Waterstop lebar 150 mm 10,600.00
A.4.1.1.15 Pemasangan 1 m’ PVC Waterstop lebar 200 mm 12,800.00
A.4.1.1.16 Pemasangan 1 m’ PVC Waterstop lebar 230 - 320 mm 14,100.00
A.4.1.1.17 Pembesian 1 kg dengan besi polos atau besi ulir 15,800.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.1.1.18 Pemasangan 1 kg kabel prategang (prestressed) polos/strands 15,200.00


A.4.1.1.19 Pemasangan 1 M2 Jaring Kawat Baja (wiremesh) 146,600.00
A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 Mpa 990,400.00
A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi 193,500.00
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk Sloof 205,200.00
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk Kolom 282,300.00
A.4.1.1.23 Pemasangan 1 m2 bekisting untuk Balok 288,900.00
A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai 337,300.00
A.4.1.1.25 Pemasangan 1 m2 bekisting untuk Dinding 337,800.00
A.4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga 258,100.00
A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton 104,000.00
A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12.2 Mpa 950,800.00
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang 90,100.00
A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang 115,300.00
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100) 818,000.00
A.4.1.1.5 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 175) 982,000.00
A.4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200) 1,011,700.00
A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225) 1,032,600.00
A.4.1.1.8 Membuat 1 m3 beton mutu f'c = 21.7 Mpa (K 250) 1,048,800.00
A.4.1.1.9 Membuat 1 m3 beton mutu f'c = 24 Mpa (K 275) 1,073,900.00
A.4.1.20 Pemasangan 1 M' Penetrasi Mini Pile Beton 28 X 28 X 28 cm, Mutu K-450 334,300.00
F A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.1 Pemasangan 1 kg besi profil 32,300.00
A.4.2.1.10 Pemasangan 1 m2 rolling door alluminium -
A.4.2.1.11 Pemasangan 1 m kusen pintu dan jendela alumunium 143,500.00
A.4.2.1.12 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm -
A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alluminium 548,100.00
A.4.2.1.14 Pemasangan 1 m2 venetions blinds dan vertical blinds -
A.4.2.1.15 Pemasangan 1 m2 terali besi strip (2 x 3) mm 1,150,100.00
A.4.2.1.16 Pemasangan 1 m2 kawat nyamuk 360,600.00
A.4.2.1.18 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 126,800.00
A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm 1,260,000.00
A.4.2.1.2 Pemasangan 1 kg besi Baja Iwf 34,800.00
A.4.2.1.2.a Pemasangan 1 kg besi Plat 33,500.00
A.4.2.1.2.b Pemasangan 1 kg besi CNP 32,300.00
A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.0,3 mm, modul 60 x 60 cm, untuk plafond 90,600.00
A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.1,7 mm, modul 60 x 120 cm, untuk partisi 182,200.00
A.4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75 138,200.00
A.4.2.1.23 Pemasangan 1 m daun jendela alumunium 30/70 104,100.00
A.4.2.1.24 Pemasangan 1 m daun pintu alumunium 30/100 127,500.00
A.4.2.1.25 Pemasangan 1 m daun pintu alumunium 30/120 19,600.00
A.4.2.1.3 Pengerjaan 100 kg pekerjaan perakitan 36,100.00
A.4.2.1.4 Pemasangan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku 1,099,100.00
A.4.2.1.4a Pemasangan pintu besi pelat baja tebal 2 mm, rangka hollow galvanis 18,201,200.00
A.4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik 22,400.00
A.4.2.1.6 Pembuatan 1 m2 rangka jendela besi scuare tube 499,800.00
A.4.2.1.6.a Pembuatan 1 kg Lantai scuare Plat 183,100.00
A.4.2.1.7 Pemasangan pintu rolling door besi 27,879,000.00
A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC -
A.4.2.1.9 Pemasangan 1 m2 sunscreen alluminium -
G A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP 182,400.00
A.4.4.1.10 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 5PP 76,300.00
A.4.4.1.11 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 6PP 75,300.00
A.4.4.1.12 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 8PP 73,200.00
A.4.4.1.13 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 10PP -
A.4.4.1.14 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :1PP -
A.4.4.1.15 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP -
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.4.1.16 Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP 385,200.00
A.4.4.1.17 Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 4PP 386,400.00
A.4.4.1.18 Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 3PP 323,700.00
A.4.4.1.19 Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 4PP 324,400.00
A.4.4.1.2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 170,800.00
A.4.4.1.20 Pemasangan 1m2 dinding conblock HB10 campuran 1SP : 3PP 270,000.00
A.4.4.1.21 Pemasangan 1m2 dinding conblock HB10 campuran 1SP : 4PP 250,300.00
A.4.4.1.22 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :3PP -
A.4.4.1.23 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP 497,300.00
A.4.4.1.24 Pemasangan 1 cm2 dinding bata berongga ekspose 12x11x24 campuran 1SP :3PP -
A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai 145,000.00
A.4.4.1.26 Pemasangan 1m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai 157,300.00
A.4.4.1.27 1 m2 PARTISI GIFSUM, RANGKA BAJA RINGAN 212,000.00
A.4.4.1.3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP 162,800.00
A.4.4.1.4 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP 158,900.00
A.4.4.1.5 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP 158,200.00
A.4.4.1.7 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP 87,100.00
A.4.4.1.8 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 3PP 81,500.00
A.4.4.1.9 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 4PP 78,300.00
H A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.1 Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm 76,900.00
A.4.4.2.10 Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm 64,200.00
A.4.4.2.11 Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm 65,300.00
A.4.4.2.12 Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm 59,400.00
A.4.4.2.13 . Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm 94,700.00
A.4.4.2.14 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm 75,500.00
A.4.4.2.15 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm 73,000.00
A.4.4.2.16 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm 87,500.00
A.4.4.2.17 Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm 86,300.00
A.4.4.2.18 Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm 89,300.00
A.4.4.2.19 Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm 38,900.00
A.4.4.2.2 Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 70,800.00
A.4.4.2.20 Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm 65,400.00
A.4.4.2.21 Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm -
A.4.4.2.22 Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1cm -
A.4.4.2.23 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 53,400.00
A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah 30,700.00
A.4.4.2.25 Pemasangan 1 m2 finishing siar pasangan conblock ekspose 14,600.00
A.4.4.2.26 Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP 64,000.00
A.4.4.2.27 Pemasangan 1 m2 acian 39,700.00
A.4.4.2.28 Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP) 153,300.00
A.4.4.2.29 Pemasangan 1 m2 plesteran acian mortar siap pakai (MSP) 37,900.00
A.4.4.2.3 Pemasangan 1 m2 pelesteran 1SP : 3PP tebal 15mm 68,200.00
A.4.4.2.30 Pemasangan 1 m2 Dinding partisi double GRC 267,300.00
A.4.4.2.4 Pemasangan 1 m2 pelesteran 1SP : 4PP tebal 15mm 66,300.00
A.4.4.2.5 Pemasangan 1 m2 pelesteran 1SP : 5PP tebal 15mm 65,400.00
A.4.4.2.6 Pemasangan 1 m2 pelesteran 1SP : 6PP tebal 15mm 64,600.00
A.4.4.2.7 Pemasangan 1 m2 pelesteran 1SP : 7 PP tebal 15mm 64,100.00
A.4.4.2.8 Pemasangan 1 m2 pelesteran 1SP : 8 PP tebal 15mm 63,700.00
A.4.4.2.9 Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm 66,300.00
I A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A.4.4.3.1 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40cm x 40 cm 66,700.00
A.4.4.3.10 Pemasangan 1 m2 lantai ubin granit ukuran 30 cm x 30 cm 90,500.00
A.4.4.3.11 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40 cm x 40 85,600.00
A.4.4.3.12 Pemasangan 1 m2 lantai ubin teralux ukuran 30 cm x 30 cm 90,500.00
A.4.4.3.13 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 60 cm x 60 292,300.00
A.4.4.3.14 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40 cm x 40 142,700.00
A.4.4.3.15 Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30 cm x 30 144,400.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.4.3.16 Pemasangan 1 m’ plint ubin PC abu-abu ukuran 15 cm x 20 cm 25,000.00


A.4.4.3.17 Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10 cm x 30 cm 48,300.00
A.4.4.3.18 Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10 cm x 40 cm 24,200.00
A.4.4.3.19 Pemasangan 1 m’ plint ubin warna ukuran 10cm x 20cm 26,300.00
A.4.4.3.2 Pemasangan 1 m2 lantai keramik ukuran 30 cm x30 cm unpolised 119,200.00
A.4.4.3.20 Pemasangan 1 m’ plint ubin warna ukuran 10cm x 30cm 25,500.00
A.4.4.3.21 Pemasangan 1 m’ plint ubin warna ukuran 10 cm x 40 cm 25,500.00
A.4.4.3.22 Pemasangan 1 m’ plint ubin teraso ukuran 10cm x 30cm 25,500.00
A.4.4.3.23 Pemasangan 1 m’ plint ubin teraso ukuran 10cm x 30cm 25,500.00
A.4.4.3.24 Pemasangan 1 m’ plint ubin granit ukuran 10 cm x 40 cm 25,500.00
A.4.4.3.25 Pemasangan 1 m’ plint ubin granit ukuran 10 cm x 30 cm 25,500.00
A.4.4.3.26 Pemasangan 1 m’ plint ubin teralux kerang ukuran 10cm x 40cm 25,500.00
A.4.4.3.27 Pemasangan 1 m’ plint ubin teralux kerang ukuran 10cm x 30cm 25,500.00
A.4.4.3.28 Pemasangan 1 m’ plint ubin teralux marmer ukuran 10 cm x 60 cm 25,500.00
A.4.4.3.28.A Pemasangan 1 m’ hospital plint ukuran 10 cm x 60 cm 165,800.00
A.4.4.3.29 Pemasangan 1 m’ plint ubin teralux marmer ukuran 10 cm x 40 cm 25,500.00
A.4.4.3.3 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 cm 71,000.00
A.4.4.3.30 Pemasangan 1 m’ plint ubin teralux marmer ukuran 10 cm x 30 cm 25,500.00
A.4.4.3.31 Pemasangan 1m2 lantai teraso cor di tempat, tebal 3 cm 65,200.00
A.4.4.3.32 Pemasangan 1m2 lantai keramik artistik 10 cm x 20 cm 184,200.00
A.4.4.3.33 Pemasangan 1 m2 lantai keramik artistik 10 cm x 10 cm atau 5 cm x 20 cm 190,800.00
A.4.4.3.34 Pemasangan 1 m2 lantai keramik ukuran 33 cm x 33 cm 151,400.00
A.4.4.3.35 Pemasangan 1 m2 lantai keramik ukuran 30 cm x 30 cm warna/corak/antislip 204,600.00
A.4.4.3.36 Pemasangan 1m2 lantai keramik ukuran 20 cm x 20 cm 156,200.00
A.4.4.3.37 Pemasangan 1m2 lantai keramik ukuran 10 cm x 33 cm untuk variasi/border 272,100.00
A.4.4.3.38 Pemasangan 1m2 lantai keramik mozaik ukuran 30 cm x 30 cm 233,800.00
A.4.4.3.39 Pemasangan 1 m’ plint keramik ukuran 10 cm x 20 cm 37,100.00
A.4.4.3.4 Pemasangan 1 m2 lantai ubin warna ukuran 40 cm x 40 cm 190,200.00
A.4.4.3.40 Pemasangan 1 m’ plint keramik ukuran 10 cm x 10 cm 27,900.00
A.4.4.3.41 Pemasangan 1 m’ plint keramik ukuran 5 cm x 20 cm 26,300.00
A.4.4.3.42 Pemasangan 1 m’ plint internal cove artistik 5 cm x 5 cm x 20 cm 186,300.00
A.4.4.3.43 Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm 146,100.00
A.4.4.3.44 Pemasangan 1 m2 lantai karpet 88,000.00
A.4.4.3.45 Pemasangan 1 m2 underlayer (pelapis bawah karpet) 75,800.00
A.4.4.3.46 Pemasangan 1 m2 lantai parquet kayu 203,800.00
A.4.4.3.47 Pemasangan 1 m2 lantai kayu gymfloor 203,800.00
A.4.4.3.48 Pemasangan 1 m2 dinding porselen 11 cm x 11 cm 200,400.00
A.4.4.3.49 Pemasangan 1 m2 dinding porselen 10 cm x 20 cm 233,200.00
A.4.4.3.5 Pemasangan 1 m2 lantai ubin warna ukuran 30 cm x 30 cm 153,700.00
A.4.4.3.50 Pemasangan 1 m2 dinding porselen 20 cm x 20 cm 203,700.00
A.4.4.3.51 Pemasangan 1 m2 dinding keramik artistik 10 cm x 20 cm 215,500.00
A.4.4.3.52 Pemasangan 1 m2 dinding keramik artistik 5 cm x 20 cm 217,600.00
A.4.4.3.53 Pemasangan 1 m2 dinding keramik 10 cm x 20 cm 215,500.00
A.4.4.3.54 Pemasangan 1 m2 dinding keramik 20 cm x 20 cm 203,700.00
A.4.4.3.55 Pemasangan 1 m2 dinding marmer 100 cm x 100 cm 261,300.00
A.4.4.3.56 Pemasangan 1 m2 dinding bata pelapis 3 cm x 7 cm x 24 cm 291,900.00
A.4.4.3.57 Pemasangan 1 m2 dinding batu paras 328,200.00
A.4.4.3.58 Pemasangan 1 m2 dinding batu tempel hitam 346,400.00
A.4.4.3.59 Pemasangan 1 m2 lantai vynil ukuran 30 cm x 30 cm 57,600.00
A.4.4.3.6 Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm 137,200.00
A.4.4.3.60 Pemasangan 1 m2 wallpaper lebar 50 cm 234,000.00
A.4.4.3.61 Pemasangan 1m2 floor harderner 144,700.00
A.4.4.3.62 Pemasangan 1 m’ plint vynil 15cm x 30cm 30,100.00
A.4.4.3.63 Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm 41,500.00
A.4.4.3.64 Pemasangan 1 m2 paving block natural tebal 6 cm 188,200.00
A.4.4.3.65 Pemasangan 1 m2 paving block natural tebal 8 cm 714,300.00
A.4.4.3.66 Pemasangan 1 m2 paving block berwarna tebal 6 cm 204,900.00
A.4.4.3.67 Pemasangan 1 m2 paving block berwarna tebal 8 cm 281,500.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.4.3.68 Pemasangan 1 m2 keramik stepnozing 289,500.00


A.4.4.3.69 Pemasangan 1 M2 Lantai Granit 60 x 60 Cm Warna / Corak Polised 378,600.00
A.4.4.3.7 Pemasangan 1 m2 lantai ubin teraso ukuran 40 cm x 40 cm 85,600.00
A.4.4.3.70 Pemasangan 1 M2 Lantai Granit 60 x 60 Cm Warna / Corak Unpolised 378,600.00
A.4.4.3.71 Pemasangan 1 m2 dinding Granit 30 x 60 cm 482,600.00
A.4.4.3.72 Pemasangan 1 m2 lantai keramik ukuran 30 cm x 60 138,200.00
A.4.4.3.72 Pemasangan 1 m2 Batu Sikat 356,700.00
A.4.4.3.8 Pemasangan 1 m2 lantai ubin teraso ukuran 30 cm x 30 cm 90,500.00
A.4.4.3.9 Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm 85,600.00
J A.4.5.1 HARGA SATUAN PEKERJAAN PENUTUP PLAFOND
A.4.5.1.1 Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 49,700.00
A.4.5.1.10 Pemasangan 1 m2 rangka besi hollow 1x40.40.1,3 mm, modul 60 x 60 cm, plafond 217,800.00
A.4.5.1.11 Pemasangan 1 m' list langit-langit gypsum 28,800.00
A.4.5.1.12 Pemasangan 1 m' plafond up ceilling gypsum board lebar 15 cm, tebal 9 mm 99,000.00
A.4.5.1.2 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm 30,200.00
A.4.5.1.3 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm 30,200.00
A.4.5.1.4 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm 25,400.00
A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm 52,800.00
A.4.5.1.6 Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm 253,300.00
A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240) cm, tebal 9 mm 51,200.00
Dihit. J-01 Pemasangan 1 m2 langit-langit GRC board ukuran (120x240) cm, tebal 4 mm 49,300.00
A.4.5.1.8 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium 160,700.00
A.4.5.1.9 Pemasangan 1 m’ list langit-langit kayu profil 23,200.00
K A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.1 Pemasangan 1 m2 atap genteng palentong kecil 106,300.00
A.4.5.2.10 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm 24,700.00
A.4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 1.80 m x 5 mm 24,700.00
A.4.5.2.12 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 3.00 m x 4 mm 24,700.00
A.4.5.2.13 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.70 m x 4 mm 24,700.00
A.4.5.2.14 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.40 m x 4 mm 24,700.00
A.4.5.2.15 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.10 m x 4 mm 24,700.00
A.4.5.2.16 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 1.50 m x 4 mm 24,700.00
A.4.5.2.17 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 3.00 m x 6 mm 24,700.00
A.4.5.2.18 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.70 m x 6 mm 24,700.00
A.4.5.2.19 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.40 m x 6 mm 24,700.00
A.4.5.2.2 Pemasangan 1 m2 atap genteng kodok 133,900.00
A.4.5.2.20 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.10 m x 6 mm 24,700.00
A.4.5.2.21 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 1.80 m x 6 mm 24,700.00
A.4.5.2.22 Pemasangan 1 m’ bubung stel gelombang 0.92 m 25,900.00
A.4.5.2.23 Pemasangan 1 m’ bubung stel gelombang 1.05 m 25,900.00
A.4.5.2.24 Pemasangan 1 m’ bubung stel gelombang 1.08 m 25,900.00
A.4.5.2.25 Pemasangan 1 m’ nok paten 0.92 m 25,900.00
A.4.5.2.26 Pemasangan 1 m’ nok paten 1.05 m 25,900.00
A.4.5.2.27 Pemasangan 1 m’ nok paten 1.08 m 25,900.00
A.4.5.2.28 Pemasangan 1 m’ nok stel 0.92 m 30,600.00
A.4.5.2.29 Pemasangan 1 m’ nok stel 1.05 m 25,900.00
A.4.5.2.3 Pemasangan 1 m2 atap genteng palentong besar/super 67,600.00
A.4.5.2.30 Pemasangan 1 m2 genteng beton 129,200.00
A.4.5.2.31 Pemasangan 1 m2 genteng bitument 188,881.55
A.4.5.2.32 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana 235,500.00
A.4.5.2.33 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai 341,400.00
A.4.5.2.34 Pemasangan 1 m2 atap sirap kayu 51,500.00
A.4.5.2.35 Pemasangan 1 m’ nok genteng beton 167,100.00
A.4.5.2.36 Pemasangan 1 m’ nok genteng aspal 176,900.00
A.4.5.2.37 Pemasangan 1 m’ nok genteng metal 149,600.00
A.4.5.2.38 Pemasangan 1 m’ nok sirap 47,000.00
A.4.5.2.39 Pemasangan 1 m2 atap seng gelombang 21,200.00
A.4.5.2.4 Pemasangan 1 m' bubung genteng palentong 128,200.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.5.2.40 Pemasangan 1 m’nok atap seng 25,700.00


A.4.5.2.41 Pemasangan 1 m2 atap alumunium 301,900.00
A.4.5.2.43 Pemasangan 1 m2 alumunium foil/sisalation 32,600.00
A.4.5.2.44 Pemasangan 1 m’ nok alumunium 149,600.00
A.4.5.2.5 Pemasangan 1 m’ bubung genteng kodok glazuur 85,900.00
A.4.5.2.6 Pemasangan 1 m’ bubung genteng palentong besar 85,900.00
A.4.5.2.7 Pemasangan 1 m2 roof light fibreglass 90 x 180 24,400.00
A.4.5.2.8 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm 25,600.00
A.4.5.2.9 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm 25,600.00
L A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I 18,380,500.00
A.4.6.1.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I dan II 613,100.00
A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I 584,100.00
A.4.6.1.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II 458,000.00
A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 mete -
A.4.6.1.14 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I -
A.4.6.1.15 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II -
A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II -
A.4.6.1.17 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II -
A.4.6.1.18 Pemasangan 1 m2 rangka atap sirap, kayu kelas II -
A.4.6.1.19 Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III -
A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II dan III 7,764,300.00
A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 103,100.00
A.4.6.1.21 Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II -
A.4.6.1.22 Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II -
A.4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III 141,300.00
A.4.6.1.25 Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II -
A.4.6.1.26 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I -
A.4.6.1.27 Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm -
A.4.6.1.28 Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV -
A.4.6.1.29 Pemasangan 1 m' talang datar/jurai seng bjls -
A.4.6.1.3 Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II 282,300.00
A.4.6.1.30 Pemasangan 1 m2 listplank ukuran (100 x 20) cm, woodplank motif kayu 63,400.00
A.4.6.1.4 Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III 282,300.00
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I 1,357,900.00
A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela, kayu kelas I dan II 731,900.00
A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi, kayu kelas I dan II 770,200.00
A.4.6.1.8 Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 537,900.00
A.4.6.1.9 Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II 591,200.00
M A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.1 Pemasangan 1 buah kunci tanam antik 617,700.00
10 A.4.6.2.10 Pemasangan 1 buah door closer 900,700.00
11 A.4.6.2.11. Pemasangan 1 buah kunci slot 60,400.00
12 A.4.6.2.12 Pemasangan 1 buah door holder 91,100.00
A.4.6.2.13 Pemasangan 1 buah door stop 331,200.00
A.4.6.2.14 Pemasangan 1 buah rel pintu sorong 617,700.00
A.4.6.2.15 Pemasangan 1 buah kunci lemari 55,000.00
A.4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm 104,800.00
A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm 130,500.00
A.4.6.2.18 Pemasangan 1 m2 kaca tebal 8 mm 215,700.00
A.4.6.2.19 Pemasangan 1 m2 kaca tebal 12 mm 1,125,000.00
2 A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa 270,600.00
A.4.6.2.20 Pemasangan 1 m2 kaca cermin tebal 5 mm 194,600.00
A.4.6.2.21 Pemasangan 1 m2 kaca cermin tebal 8 mm 267,000.00
A.4.6.2.22 Pemasangan 1 m2 kaca wireglassed tebal 5 mm 289,900.00
A.4.6.2.23 Pemasangan 1 m2 kaca patri tebal 5 mm 2,690,200.00
A.4.6.2.24 Pemasangan 1 buah Casement Handle 78,300.00
A.4.6.2.25 Pemasangan 1 buah Looc Case 89,300.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.4.6.2.26 Pemasangan 1 buah engsel pintu koboi 59,000.00


A.4.6.2.28 Pemasangan 1 buah Floor Hinges 3,598,300.00
A.4.6.2.29 Pemasangan 1 buah Over panel 413,800.00
3 A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi 172,700.00
A.4.6.2.30 Pemasangan 1 buah Top patch Fitting 1,348,800.00
A.4.6.2.31 Pemasangan 1 buah Botom patch Fitting 1,475,300.00
A.4.6.2.32 Pemasangan 1 buah Bottom Fatch Lock + Cylinder 1,513,800.00
A.4.6.2.33 Pemasangan 1 buah Full Handle 1,403,800.00
4 A.4.6.2.4. Pemasangan 1 buah kunci silinder 206,500.00
5 A.4.6.2.5. Pemasangan 1 buah engsel pintu 50,000.00
6 A.4.6.2.6. Pemasangan 1 buah engsel jendela 58,600.00
7 A.4.6.2.7. Pemasangan 1 buah engsel angin 85,500.00
8 A.4.6.2.8. Pemasangan 1 buah spring knip 58,800.00
9 A.4.6.2.9. Pemasangan 1 buah hak angin kait 34,600.00
N A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama 18,500.00
A.4.7.1.10 Pengecatan 1 m2 bidang tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 22,300.00
A.4.7.1.10.a Pengecatan 1 m2 bidang tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) e 24,100.00
A.4.7.1.11. Pengecatan 1 m2 bidang tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 21,200.00
A.4.7.1.11.a Pengecatan 1 m2 bidang tembok lama (1 lapis cat dasar, 2 lapis cat penutup), exterior 21,200.00
A.4.7.1.12. Pelaburan 1 m2 tembok dengan kalkarium 8,800.00
A.4.7.1.13. Pelaburan 1 m2 tembok dengan kapur sirih 16,100.00
A.4.7.1.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan) 5,100.00
A.4.7.1.15. Pemasangan 1 m2 wallpaper 127,700.00
A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan meni besi 32,500.00
A.4.7.1.17. Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah 69,600.00
A.4.7.1.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis 59,500.00
A.4.7.1.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir 15,300.00
A.4.7.1.2. 1 m2 Pencucian bidang permukaan tembok yang pernah dicat 16,600.00
A.4.7.1.20. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis 150,700.00
A.4.7.1.21. Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir 137,300.00
A.4.7.1.22. Pengecetan 1 m2 dengan plitur melamic 288,200.00
A.4.7.1.23. Pengecatan 1 m2 bidang plafond (1 lapis cat dasar, 2 lapis cat penutup) 40,500.00
A.4.7.1.24. Pengecatan 1 m2 bidang tembok lapis aquaproof (2 lapis cat penutup) 20,900.00
A.4.7.1.25 Pengecatan 1 m2 bidang cat genteng 35,000.00
A.4.7.1.3. 1 m2 Pengerokan karat pada permukaan baja cara manual 17,200.00
A.4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 46,800.00
A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup) 63,500.00
1 A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil 40,500.00
2 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur 46,000.00
3 A.4.7.1.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter 16,900.00
A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis 51,700.00
O A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.1 Pemasangan 1 buah closet duduk/monoblock lengkap 2,669,400.00
A.5.1.1.10 Pemasangan 1 buah bak air fiberglass vol 1 m3 93,000.00
A.5.1.1.11 Pemasangan 1 buah bak beton volume 1 m3 918,400.00
A.5.1.1.12 Pemasangan 1 buah bak cuci piring stainlessteel 757,200.00
A.5.1.1.13 Pemasangan 1 buah bak cuci piring teraso 74,800.00
A.5.1.1.14 Pemasangan 1 buah floor drian 66,600.00
A.5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm 322,800.00
A.5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45cm x 45cm tinggi 50 cm 476,800.00
A.5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm 476,800.00
A.5.1.1.18 Pemasangan 1 m’ pipa galvanis diameter ½” 20,800.00
A.5.1.1.19 Pemasangan 1 buah kran diameter 1/2" atau 3/4" 75,900.00
A.5.1.1.19.A Pemasangan 1 buah kran Angsa diameter 1/2" atau 3/4" 146,700.00
A.5.1.1.19.B Pemasangan 1 buah jet washer 154,000.00
A.5.1.1.2 Pemasangan 1 buah closet jongkok porselen 718,500.00
A.5.1.1.20. Pemasangan 1 m’ pipa galvanis diameter ¾ ” 84,500.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

A.5.1.1.21 pemasangan 1 m’ pipa galvanis diameter 1” 93,500.00


A.5.1.1.22 Pemasangan 1 m’ pipa galvanis diameter 1 ½” 121,100.00
A.5.1.1.23. Pemasangan 1 m' pipa galvanis diameter 3" 251,000.00
A.5.1.1.24. Pemasangan 1 m' pipa galvanis diameter 4" 401,800.00
A.5.1.1.25 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2 ” 22,100.00
A.5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" 29,000.00
A.5.1.1.27 Pemasangan 1 m' pipa PVC tipe AW diameter 1" 32,000.00
A.5.1.1.27.A Pemasangan 1 m' pipa PVC tipe AW diameter 1 1/4" 48,600.00
A.5.1.1.28 Pemasangan 1 m' pipa PVC tipe AW diameter 1 1/2" 52,500.00
A.5.1.1.29 Pemasangan 1 m' pipa PVC tipe AW diameter 2" 51,700.00
A.5.1.1.3 Pemasangan 1 buah closet jongkok teraso 531,700.00
A.5.1.1.30 Pemasangan 1 m’ pipa PVC tipe AW diameter 2 1/2 ” 65,100.00
A.5.1.1.31 Pemasangan 1 m' pipa PVC tipe AW diameter 3" 117,700.00
A.5.1.1.32 Pemasangan 1 m' pipa PVC tipe AW diameter 4" 198,400.00
A.5.1.1.33 Pemasangan 1 unit Septik Tank 3,635,500.00
A.5.1.1.3A Pemasangan 1 buah closet jongkok Sistem Jet 3,713,200.00
A.5.1.1.4 Pemasangan 1 buah urinoir 3,554,100.00
A.5.1.1.5 Pemasangan 1 buah wastafel 1,288,400.00
A.5.1.1.5A Pemasangan 1 buah wastafel tanpa meja 2,062,500.00
A.5.1.1.6 Pemasangan 1 buah bathcuip porselen 108,000.00
A.5.1.1.7 Pemasangan 1 buah bak fiberglass vol 1 m3 972,900.00
A.5.1.1.8 Pemasangan 1 buah bak mandi batu bata vol 0.30 m3 1,029,900.00
A.5.1.1.9 Pemasangan 1 buah bak mandi teraso vol 0.30 m3 972,900.00
Dihit. B-01 Pengurugan 1 m3 dengan tanah 105,100.00
Dihit. F-01 Pemasangan 1 unit kusen dan daun pintu Tempered tipe PT 14,712,600.00
Dihit. F-02 Pemasangan 1 unit kusen dan daun pintu tipe P1 5,576,900.00
Dihit. F-03 Pemasangan 1 unit kusen dan daun pintu tipe P1 2,035,700.00
Dihit. F-04 Pemasangan 1 unit kusen dan daun pintu tipe P2 1,803,000.00
Dihit. F-05 Pemasangan 1 unit kusen dan daun pintu tipe P2' 2,032,800.00
Dihit. F-06 Pemasangan 1 unit kusen dan daun pintu Geser tipe PG 2,573,600.00
Dihit. F-07 Pemasangan 1 unit kusen dan daun pintu jendela tipe PJ 3,271,800.00
Dihit. F-08 Pemasangan 1 unit kusen dan daun jendela tipe J1 2,176,100.00
Dihit. F-08 Pemasangan 1 unit kusen alumunium J4 6,632,600.00
Dihit. F-08A Pemasangan 1 unit kusen LV 1,810,500.00
Dihit. F-09 Pemasangan 1 unit kusen dan daun jendela tipe J2 1,944,600.00
Dihit. F-10 Pemasangan 1 unit kusen dan daun jendela tipe J2' 1,605,700.00
Dihit. F-11 Pemasangan 1 unit kusen alumunium J3 1,094,700.00
Dihit. F-12 Pemasangan 1 unit kusen alumunium BV1 341,600.00
Dihit. F-13 Pemasangan 1 unit kusen alumunium BV2 2,451,300.00
Dihit. F-13A Pemasangan 1 m2 Alumunium Composite Panel 752,000.00
Dihit. I-01 Pemasangan 1 m2 lantai keramik ukuran 30 cm x 30 cm putih polos 206,300.00
Dihit. I-02 Pemasangan 1 m2 lantai keramik ukuran 40 cm x 40 cm putih polos 208,000.00
Dihit. I-03 Pemasangan 1 m2 lantai keramik ukuran 40 cm x 40 cm warna/corak/antislip 210,100.00
Dihit. I-04 Pemasangan 1 m2 lantai keramik ukuran 25 cm x 25 cm warna/corak/antislip 225,400.00
Dihit. I-05 Pemasangan 1 m2 dinding keramik 25 cm x 40 cm 289,100.00
Dihit. I-06 Pemasangan 1 m2 dinding keramik 60 cm x 60 cm 301,800.00
Dihit. J-01 Pemasangan 1 m2 langit-langit GRC board ukuran (120x240) cm, tebal 4 mm 49,300.00
Dihit. K-01 Pemasangan 1 m2 atap genteng morando glasuur 119,600.00
Dihit. K-02 Pemasangan 1 m’ bubung morando glasuur 114,500.00
Dihit. K-43 Pemasangan 1 m2 Bubble alumunium foil 39,500.00
Dihit. N-01 Pengecatan 1 m2 bidang plafond baru (1 lapis plamuur, 1 lapis cat dasar, 1 lapis cat penutup) 32,800.00
Dihit. O-01 Pemasangan 1 m' saluran gravel 144,900.00
Dihit. O-02 Pemasangan 1 unit septictank ukuran 1 x 2 m 5,424,500.00
Dihit. O-03 Pemasangan 1 unit resapan PVC 4" + lap. ijuk 281,000.00
Dihit. O-04 Pemasangan 1 unit septictank ukuran 1,5 x 2,5 m 9,017,100.00
Dihit. O-05 Pemasangan 1 unit resapan PVC 4" + batu belah + lap. Ijuk 4,486,300.00
Dihit. O-06 Sumur Bor + Pemipaan 32,963,000.00
Dihit. O-07 Rangka Tandon Air 410,625,900.00
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

Dihitung Pemasangan 1 unit pintu type PA. 1


Dihitung Pemasangan 1 m2 Dinding HPL 1,028,700.00
P-01 Memasang 1 buah instalasi titik Lampu 187,100.00
P-02 Memasang 1 buah instalasi titik Lampu Luar ( Taman ) 462,840.00
P-03 Memasang 1 buah Instalasi titik Stop Kontak 169,100.00
P-04 Memasang Kabel Tray ( W=200 mm ) #REF!
P-05 Memasang Tee Kabel Tray ( W=200 mm ) #REF!
P-06 Memasang Tee Kabel Tray ( W=300 mm ) #REF!
P-07 Memasang Tee Kabel Tray ( W=400 mm ) #REF!
P-08 Memasang Kabel Tray ( W=300 mm ) #REF!
P-09 Memasang Kabel Tray ( W=400 mm ) #REF!
P-10 Memasang Splitter TV #REF!
P-11 Memasang Penangkal Petir 1,120,700.00
P-12 Memasang Stop Kontak daya 93,670.00
P-13 Memasang Stop Kontak-TV 341,470.00
P-14 Memasang Stop Kontak-TELEPON #REF!
P-15 Memasang Saklar tunggal 95,710.00
P-16 Memasang Saklar ganda 99,180.00
P-17 Memasang 1 M Kabel Power ( NYY 4x2,5 mm ) 118,440.00
P-18 Memasang 1 M Kabel Power ( NYY 4x16 mm + NYA 10 mm ) 78,750.00
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
KODE HARGA
NO ITEM SATUAN PEKERJAAN
ANALISA SATUAN
1 2 3 4
Column1 Column2 Column3 Column4

#NAME? #NAME? #NAME?


#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
P PEKERJAAN ELEKTRIKAL

DIVISI 5. PERKERASAN BERBUTIR


#REF! Pek. Lapis Pondasi Bawah (LPB) Telford T= 20 cm #REF!
DIVISI 6. PERKERASAN ASPAL
#REF! Pek. Lapis Pondasi Atas Bersemen (CTB) T=15 cm #REF!
#REF! Pek. Laston Lapis Antara (AC-BC) L, T= 5 cm #REF!
#REF! Pek. Laston Lapis Aus (AC-WC) L, T= 5 cm #REF!
RINCIAN RENCANA ANGGARAN BIAYA

KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN ANGGARAN :

NO URAIAN PEKERJAAN KODE VOLUME


ANALISA SAT Area P L T B H Unit Berat
1 2 3 4

I PEKERJAAN PERSIAPAN
1 Pek. pembersihan lahan A.2.2.1.4 47 m2
2 Papan Nama Proyek ( 80 x 120 cm) U&B 1.00 bh
3 Pas. Direksi keet A.2.2.1.14 12.00 m2
4 Penyedian air kerja + listrik kerja U&B 1.00 ls
5 Pek. Pembongkaran Bangunan Lama 1.00 ls

II PEKERJAAN PELAKSANAAN
A BANGUNAN MESJID
A.I PEKERJAAN TANAH DAN PONDASI
Galian Tanah 3.70
Pondasi Foot Plat m3
FP1 0.50 m3 0.5 0.5 0.5 4.00
FB1 3.20 m3 12.8 0.5 0.5
Pasir Urug 2.37 m3 7.4 6.4 0.05
Urugan Tanah Kembali 1.23 m3
Pas. Aanstamping 1.15 m3 12.8 0.6 0.15
Pas. Batu Kali 1:5 2.56 m3
FB1 2.56 m3 12.8 0.4 0.5
Lantai Kerja 0.05 m3 0.05
Urugan Sirtu Peninggian Elevasi Lantai 4.74 m3
Utama 4.74 m3 7.4 6.4 0.1
A.II PEKERJAAN Beton K225
Foot Plate gabung
Beton K225 0.20 m3
Pembesian 35.51 kg
Bekisting 1.60
Foot Plate Fp1
Beton K225 0.20 m3 0.5 0.5 0.2 4.00
Pembesian 35.51 1.5 6.666667 0.89 4.00 12.00
Bekisting 1.60

Kolom Pedestal
Beton K225 0.10 m3
Pembesian 34.10 kg
Bekisting 1.92 m2
Kolom Pedestalk1
Beton K225 0.10 m3 0.6 0.2 0.20 4.00
Pembesian 16.00 kg 10 1 4 4.00 0.62
18.10 kg 6 0.78 5.8 4.00 0.22
Bekisting 1.92 m2 0.6 0.2 4.00
Sloof
Beton K225 0.48 12.8 0.15 0.25
Pembesian 51.20 kg 10 12.8 4 1.00 0.62
79.87 kg 6 0.78 102.4 1.00 0.22
Bekisting 6.40
Lantai 1
Kolom Lantai 1
Beton K225 0.52 m3
Pembesian 67.91 kg
Bekisting 11.42 m2
Kolom K1
Beton K225 0.45 m3 2.8 0.2 0.20 4.00
Pembesian 31.56 kg 10 3.2 4 4.00 0.62
16.20 kg 6 0.78 23.4 4.00 0.22
Bekisting 8.96 m2 2.8 0.2 4.00
Kolom Kp
Beton K225 0.07 m3 2.8 0.11 0.11 2.00
Pembesian 15.78 kg 10 3.2 4 2.00 0.62
4.36 kg 6 0.42 23.4 2.00 0.22
Bekisting 2.46 m2 2.8 0.11 2.00
Balok Lantai 1
Beton K225 0.19 m3
Pembesian 30.06 kg
Bekisting 2.58 m2
Balok Lt 1 (B1)
Beton K225 0.19 8.6 0.15 0.15
Pembesian 21.21 kg 10 8.6 4 1.00 0.62
8.86 kg 6 0.58 68.8 1.00 0.22
Bekisting 2.58
Pelat Lantai 1
Beton K225 1.47 m3 4.9 3 0.1
Pembesian 162.40 kg 8 4.9 21.00 0.39
Bekisting 14.70 4.9 3
NO URAIAN PEKERJAAN KODE VOLUME
ANALISA SAT Area P L T B H Unit Berat
1 2 3 4
A.III PEKERJAAN DINDING
Pek. Pasangan Dinding 3.90
Pek. Plesteran Dinding 7.80
Pek. acian 7.80
Pek. Dinding Granit -
Lantai 1
Pek. Pasangan Dinding 3.90 m2 8.6 0.6 1.26
Pek. Plesteran Dinding 7.80 m2
Pek. acian 7.80 m2
Pek. Dinding Batu Alam/Granit m2
A.IV PEKERJAAN KUSEN PINTU & JENDELA & KUBAH

Kusen KM 1.00
A.V PEKERJAAN PLAFON
Lantai 1
Pek. Rangka Plafond 14.70
Pek. Plafon PVC 14.70
Pek. Profil Plafon 5.6
A.VI PEKERJAAN LANTAI
Lantai 1
Pek. Urugan pasir bawah lantai 2.37 47.36 0.05
Pek. Lantai Granit 60x60 Antislip 47.36 47.36
A.VII PEKERJAAN PENGECATAN
Pek. Pengecatan dinding 7.80
Pek. Pengecatan Plafon 14.70
A.IX PEKERJAAN PLUMBING
Pek. Pipa 1/2 Inc 20.00 m
Pek. Pipa 2 " - m
Pek. Pipa 3" 8.00 m
Pek. Pipa 4" - m
Sefticktank Biofill - unit
Pek. Kran 1/2" 4.00 bh
Pek. Stop Kran 1.00 bh
Pek. Closet Jongkok - bh
Pek. Floor Drain 2.00 bh
A.IX PEKERJAAN ELEKTRIKAL
Pekerjaan instalasi titik lampu 2.00 Ttk
Pekerjaan pasangan BOX MCB 4 Group - Unt
Pekerjaan Pasangan lampu SL 18 Watt 2.00 Bh
Pekerjaan pasangan stop kontak 1.00 Bh
Pekerjaan pasangan saklar doble 2.00 Bh
Pekerjaan pasangan saklar Tunggal - Bh
Pek. Pasangan Batangan Arde + Kawat Arde - Bh
Pek. Kipas Angin 0 Unit
Pek. Sound System Indoor - Set
Pek. Sound System Outdoor - set
Pek. CCTV 8 Channel - Paket
Penyambungan Listrik PLN 900 Watt - Paket
NO URAIAN PEKERJAAN KODE VOLUME
ANALISA SAT Area P L T B H Unit Berat
1 2 3 4
NO URAIAN PEKERJAAN KODE VOLUME
ANALISA SAT Area P L T B H Unit Berat
1 2 3 4
NO URAIAN PEKERJAAN KODE VOLUME
ANALISA SAT Area P L T B H Unit Berat
1 2 3 4
DAFTAR HARGA UPAH
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2021

a Upah Tenaga Kerja Konstruksi Bangunan


HARGA
NO JENIS TENAGA KERJA SATUAN UPAH KET.
(Rp)

1 Pekerja Orang /Hari 95,000


2 Tukang Gali (Sumur) Orang /Hari 155,000
2 Tukang Batu Orang /Hari 110,000
3 Tukang Kayu Orang /Hari 110,000
4 Tukang Cat Tembok/Kayu Orang /Hari 110,000
5 Tukang Besi Orang /Hari 110,000
6 Kepala Tukang Batu Orang /Hari 110,000
7 Kepala Tukang Kayu Orang /Hari 110,000
8 Kepala Tukang Cat Tembok/Kayu Orang /Hari 110,000
9 Kepala Tukang Besi Orang /Hari 110,000
10 Kepala Tukang Baja Frofil Orang /Hari 110,000
10 Mandor Orang /Hari 110,000
11 Operator Alat Besar Orang /Hari 125,000
12 Pembantu Operator / Mekanik Orang /Hari 120,000
STANDAR HARGA BAHAN /MATERIAL BANGUNAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2021

NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA


Column1 Column2 Column3 Column4 Column5

A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA

2 Tanah Urug Pilihan m3 60,000


1 Sirtu Tersaring bergradasi m3 110,000
2 Pasir Urug m3 90,000
3 Pasir Pasang Kali m3 190,000
3 Pasir Pasang Gunung /Pilihan m3 190,000
4 Pasir Beton m3 220,000
8 Batu Pecah Mesin 2/3 m3 240,000
11 Batu Belah Pondasi m3 157,000
14 Batu Tempel Hitam Bt. Andesit m2 165,000
15 Batu Tempel Hitam Bt Candi m2 150,000
16 Batu Pinggir Beton 10 x 20 x 35 buah 25,000
17 Batu Pinggir Beton 15 x 35 x 50 K-225 buah 90,000
18 Batu Telor m3 135,000
19 Batako Kecil Ukuran 8 x 10 x 20 buah 3,500
20 Batako Besar Ukuran 8 x 20 x 30 buah 4,500
21 Con Block 8 x 20 x 40 buah 7,500
22 Bata Merah Bakar Kelas I Lokal Garut bh 100
23 Bata Merah Bakar Kelas II Lokal Urug bh 900
24 Bata Merah Oven (Klingker) buah 1,000
25 Bata Ringan buah 9,600
29 Rooster Motif 20 x 20 buah 13,000
30 Rooster Polos 10 x 20 bh 5,400
31 Rooster Silang 20 x 20 buah 4,600
32 Rooster Espana Ornamen buah 32,700
33 Rooster / Bata Kerawang buah 4,250
34 Rooster Keramik 30 x 30 buah 50,385
35 Rooster Keramik 20 x 20 buah 36,275
36 Rooster Keramik 18 x 18 buah 34,150
37 Grass Block 20 x 20 (Cisangkan) buah 22,500
38 Grass Block 20 x 20 (lokal/Setempat) buah 5,500
39 Grass Block 30 x 30 (Cisangkan) buah 25,950
40 Grass Block 30 x 30 (Lokal/Setempat) buah 12,375
41 Paving Blok Natural 8 cm (Cisangkan) m2 115,600
42 Paving Blok Warna 8 cm (Cisangkan) m2 135,375
43 Paving Blok Natural 8 cm (Lokal/Setempat) m2 85,000
44 Paving Blok Warna 8 cm (Lokal/Setempat) m2 115,000
45 Paving Blok Natural 6 cm (Cisangkan) m2 97,594
46 Paving Blok Warna 6 cm (Cisangkan) m2 112,175
47 Paving Blok Natural 6 cm (Lokal/Setempat) m2 75,000
48 Paving Blok Warna 6 cm (Lokal/Setempat) m2 90,000
49 Canstin Paving Blok (Cisangkan) m' 125,000
50 Semen PC/ 50 Kg Kualitas :Tiga Roda, Holcim, Gresik zak 60,000
51 Semen PC/ 50 Kg Kualitas : Garuda, Bima, Padang, MP zak 60,000
52 Semen PC/ 40 Kg zak 56,000
53 Semen Putih zak 125,000
54 Semen warna kg 13,250
55 Semen Mortar Utama (MU) Zak 96,000
56 Floor harderner kg 21,000
57 Kanstin Taman Ukuran Kecil 11x20 cm, p=0,20 m (Perssure) buah 9,500
58 Kanstin Taman Ukuran Besar 11x20 cm, p=0,40 m (Perssure) buah 18,000
59 Kanstin Jalan (Bina Marga /Kecil) 11x20 cm, p=0,50 m (Lokal/Cor) buah 25,000
60 Kanstin Jalan (Bina Marga /Besar) 11x40 cm, p=0,50 m (Lokal/Cor) buah 30,000
61 Panel Beton Polos Mutu K-225 240 x 40 x 5 cm lbr 126,500
62 Panel Beton Polos Mutu K-300 240 x 40 x 5 cm lbr 143,000
63 Tiang Beton Mutu K-225 Kolom 2,75 btg 259,050
64 Tiang Beton Mutu K-225 Kolom 3,25 btg 326,150
65 Tiang Beton Mutu K-300 Kolom 2,75 btg 324,500
66 Tiang Beton Mutu K-300 Kolom 3,25 btg 379,500
73 Readymix Beton K250, Tanpa Pompa (Selang) m3 935,000
74 Readymix Beton K225, Tanpa Pompa (Selang) m3 902,000
75 Readymix Beton K175, Tanpa Pompa (Selang) m3 858,000
76 Readymix Beton K125, Tanpa Pompa (Selang) m3 803,000
77 Pompa Readymix Beton (Sewa) Volume 0-50 m3 2,750,000
78 Pompa Readymix Beton (Sewa) Volume 50-100 m3 3,025,000
79 Pompa Readymix Beton (Sewa) Volume >100 m3, penambahan /m3 m3 33,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
80 Kapur Pasang/kapur Tembok (1 karung/zak=25 Kg) Zak 45,000
81 Kapur Sirih kg 4,500
82 Formite/spacer buah 28,250
83 Hollow /Con Blok 8 x 10 x 25, bentuk segi empat buah 7,500
84 Hollow /Con Blok 8 x 15 x 25, bentuk segi empat buah 9,000
85 Hollow /Con Blok 8 x 20 x 20, Bentuk : Mercy, Silang, buah 9,500
86 Kapur padam m3 70,000

B. LABURAN, PENGISI DAN ALATNYA

1 Plamir Tembok kg 27,500


2 Cat dasar ICI untuk Interior (2 lapis) 2,5 liter 138,275
3 Cat Tembok Dulux exterior 2,5 liter 225,000
4 Cat Tembok Mowilex exterior 2,5 liter 140,000
5 Cat Tembok Catylac exterior 5 kg 105,000
6 Cat Tembok Metrolite exterior 3 liter 87,000
7 Cat Tembok Dulux interior 2,5 liter 200,000
8 Cat Tembok Mowilex interior 2,5 ltr 126,000
9 Cat Tembok Catylac interior 5 kg 95,000
10 Cat Tembok Metrolite interior 3 liter 75,000
11 Cat Tembok Metrolite kg 23,000
12 Cat Tembok Vinilex Kg 40,000
13 Cat Tembok Sanlex kg 25,400
14 Cat dasar kg 55,300
15 Cat Tahan Asam liter 120,485
16 Cat Genteng Kualitas : Dulux, Jotun, Mowilex liter 67,540
17 Cat Genteng Kualitas : Sika Kg 55,850
18 Pelapis Alkali ICI (Cat Dasar Beton Eksterior) kg 120,485
19 Water Profing Emulsion kg 110,000
20 Water Profing Membrane m2 75,500
21 Kuas Roll Cat Temnok 4" Rollset Kecil buah 15,000
22 Kuas Roll Cat Tembok 9" Rollset Besar buah 25,000
23 Bak Roll Cat Tembok buah 20,000
24 Kape Tembok buah 12,800
25 Kape Kayu buah 10,500
26 Soligneum 5 liter 35,000
27 Flincote kg 38,500
28 Kwas 1" buah 4,000
29 Kwas 1,5" buah 6,000
30 Kwas 2" bh 8,000
31 Kwas 2,5" buah 10,000
32 Kwas 3" buah 12,000
33 Kwas 4" buah 20,000
34 Oker kg 37,500
35 Oten (Pewarna Plitur) kg 85,000
36 Spirtus kg 15,400
37 Bahan Pelitur Kripik (Sirlak India) kg 80,250
38 Dempul Lilin kg 49,900
39 Dempul Plitur kg 43,740
40 Wood Filler /IMPRA Dempul Halus kg 55,000
41 Melamine Lack /IMPRA Penutup /pelindung kg 65,000
42 Sanding Sealer /IMPRA Penutup pori-pori /serat kayu kg 65,000
43 Woodstain /IMPRA Pewarna kg 62,000
44 Politur liter 18,900
45 Politur Jadi liter 52,500
46 Terpentin liter 19,600
47 Tiner A Kualitas : Herin, Impala, Cobra liter 32,400
48 Tiner B Kualitas : Impas, ND, Lotus, ltr 24,000
49 Kumpon kg 6,000
50 Dempul kayu Kualitas : Cap Kucing kg 20,000
51 Dempul Plastik /Besi Kualitas : San Polac, Alfaglos kg 31,259
52 Dempul Duco Kualitas : Propan, Isamu kg 28,500
53 Ampelas lbr 3,500
54 Meni Kayu/Besi Kualitas : Cap Pedang, Belmas kg 31,000
55 Meni Kayu / Besi Kualitas : Cap Bintang,Oktan,Yoko, kg 23,600
56 Sincromat (Zink Cromate) Kualitas : Kansai, Kuda Terbang kg 44,800
57 Cat Kayu /Besi /Duco Kualitas : Mowilex, Dulux. Amco kg 72,000
58 Cat Kayu/Besi Kualitas : Seiv, Avian, Glotex, Al-tex kg 54,000
59 Cat Brom Kualitas : Seiv, Kuda Terb, Kanguru liter 130,000
60 Karet Lis m' 1,500
61 Minyak Cat kg 24,600
62 Residu liter 15,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
63 Vernis Kualitas : Avian, Samurai liter 72,000
64 Melamik pintu Ukuran 0,8 x 2.00 bh 495,000
65 Melamik kusen /jendela m 49,500
66 Minyak Bekisting liter 14,900
Catatan konversi cat : 1 liter stara dengan 1,2 s/d 1,25 kg
C. BAHAN KAYU BERIKUT BAHAN JADINYA

1 Bambu Ø 5 s/d 7 - 4 m btg 9,000


2 Bambu Ø 7 s/d 10 - 4 m btg 12,500
3 Bambu Gombong Ø 8 s/d 12 - 6 m btg 50,000
4 Bambu Gombong Ø 12 s/d 15 - 6 m btg 60,000
5 Dolken Ø 4 s/d 6 - 4 m btg 8,000
6 Dolken Ø 6 s/d 8 - 4 m btg 16,000
7 Kayu Jati Jatim Tua Lepas Mata dari Ø 80 cm ke atas m3 19,000,000
8 Kayu Jati Jateng Tua Lepas Mata dari Ø 80 cm ke atas m3 19,000,000
9 Kayu Jati Jabar Tua Lepas Mata dari Ø 80 cm ke atas m3 11,980,000
10 Kayu Jati Jabar Tua Lepas Mata dari Ø 80 cm ke bawah m3 10,380,000
11 Kayu Balok Kamper Medan (Kruing) Uk: 6/12, 8/12, 8/15 * m3 11,500,000
12 Kayu Papan Kamper Medan (Kruing) m3 12,200,000
13 Kayu Kamper Singkil / kapur Kayu Samarinda Kls II m3 12,000,000
14 Kayu Balok Kamper Samarinda Uk: 6/12, 8/12, 8/15 * m3 11,400,000
15 Kayu Papan Kamper Samarinda m3 12,000,000
16 Kayu Balok Borneo Super : Uk : 6/12, 8/12, 8/15 * m3 5,400,000
17 Kayu Papan Borneo Super m3 5,400,000
18 Kayu Balok Kamper Banjar Uk : 6/12, 8/12, 8/15 * m3 8,500,000
19 Kayu Papan Kamper Banjar m3 9,000,000
20 Kayu Balok Rasamala Uk: 6/12, 8/12, 8/15 * m3 4,800,000
21 Kayu Hutan Kelas I Segeng, Mahoni, Laban m3 3,527,000
22 Kayu Balok Albasia /Kayu Gunung III Uk: 6/12, 8/12, 8/15 * m3 2,000,000
23 Kayu Papan Albasia /Kayu Gunung III m3 2,125,000
24 List Profil Kamper 1 cm 1 cm m' 4,200
25 List Profil Kamper 2 cm 2 cm m' 7,280
26 List Profil Kamper 4 cm 4 cm m' 9,350
27 List Profil Kamper 5 cm 5 cm m' 10,750
28 List Profil Kamper 10 cm 10 cm m' 12,500
29 Pegangan Tangga Profil Jati m' 180,000
30 Pegangan Tangga Profil Kamper m' 65,000
31 Kayu Kaso 4/6 Borneo Uk : 4/6 - 4 m m3 5,400,000
32 Kayu Kaso 5/7 Borneo Uk : 5/7 - 4 m m3 5,400,000
33 Kayu Kaso 4/6 Albasia Uk : 4/6 - 4 m m3 2,100,000
34 Kayu Kaso 5/7 Albasia Uk : 5/7 - 4 m m3 2,000,000
35 Kayu Reng 2/3 Borneo Super Uk : 2/3 - 4 m m' 10,000
36 Kayu Reng 2/3 Borneo Super Uk : 3/4 - 4 m m' 15,000
37 Kayu Reng 2/3 Kamper Banjar Uk : 2/3 - 4 m m' 22,000
38 Kayu Reng 3/4 Kamper Banjar Uk : 3/4 - 4 m m' 35,000
39 Kayu Papan Terentang m3 2,337,500
40 Kayu Balok Terentang m3 2,200,000
41 Batang Kelapa Ø 30cm p=6 m btg 1,500,000
42 Tali Ijuk kg 12,000
43 Lapisan Ijuk tebal 10 cm m2 21,000

D. BAHAN PENUTUP RANGKA PLAFOND

1 Plafond Enternit (100 x 100) cm, t=4 mm m2 12,000


2 Plafond Hardpleks (120 x 240) cm, t=5 mm lbr 84,500
3 Plafond Asbes Semen 3,5 mm m2 24,250
4 Plafond Asbes Semen 4,0 mm m2 28,500
5 Gypsum Board (120 x 240) cm, t = 9 mm lbr 73,000
6 Gypsum Board (120 x 240) cm, t = 12 mm lbr 98,000
7 GRC /Versaboard (120 x 240) cm, t = 4 mm lbr 68,000
8 GRC /Versaboard (120 x 240) cm, t = 6 mm lbr 108,000
9 GRC /Versaboard (120 x 240) cm, t = 9 mm lbr 143,000
10 Wood plank setara Elephant (405 x 10) t=8 mm lbr 62,500
11 Wood plank setara Elephant (405 x 20) t=8 mm lbr 81,250
12 Wood plank setara Elephant (405 x 30) t=8 mm lbr 100,000
13 Talang air hujan 1/2 lingkaran (gutter) zincalum Ø15 cm setara galvanos btg/3mtr 105,325
14 Penyanga (bracket) talang zincalum Ø 15 cm bh 45,275
15 Penyanga (bracket) talang zincalum Ø 20 cm bh 65,250
16 Penyambung talang (gutter joint) zincalum Ø 15 cm bh 40,655
17 Penyambung talang (gutter joint) zincalum Ø 20 cm bh 57,650
18 Corong talang (nozzle) Ø 15 cm set 99,175
19 Corong talang (nozzle) Ø 20 cm set 137,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
20 Stopper talang zincalum Ø 15 cm psg 52,750
21 Stopper talang zincalum Ø 20 cm psg 70,000
22 Talang sudut dalam/luar (gutter angle) Ø 15 cm set 118,300
23 Rangka Baja Ringan C 75/75 setara taso btg/6 mtr 80,200
24 List Profil Gypsum terpasang, L=7 cm s/d 10 cm, m' 14,000
25 List Profil Gypsum terpasang, L=10 cm s/d 15 cm, m' 24,000
26 List Profil Gypsum terpasang, l=15 cm s/d 20 cm, m' 27,000
27 Tepung Gypsum kg 4,750
28 Acustik Amstrong 60 x 120 lbr 148,500
29 Cotton Plester buah 16,000
30 Textile tape rol 28,000
30 Cornice Coumpound kg 5,000

E. BAHAN KAYU LAPIS DAN PELAPIS DINDING

1 Triplek 3 mm 120 x 240 lbr 53,500


2 Triplek 4 mm 120 x 240 lbr 67,600
3 Triplek 4 mm motif ukuran pintu lbr 123,500
4 Multiplek 4 mm 120 x 240 lbr 87,900
5 Multiplek 9 mm 120 x 240 lbr 153,900
6 Multiplek 12 mm 120 x 240 lbr 152,300
7 Multiplek 18 mm 120 x 240 lbr 249,600
8 Blockboard 15 mm 120 x 240 lbr 154,000
9 Blockboard 18 mm 120 x 240 lbr 176,000
10 Blockboard 25 mm 120 x 240 lbr 209,000
11 Jabar Wood 4 mm lbr 131,250
12 Bilik Bambu (Tanpa Kulit) m2 12,500
13 Bilik Bambu (dengan Kulit) m2 17,500
14 Bilik Bambu Hitam Variasi m2 25,000
15 Wall Paper (kelas Biasa) m2 43,300
16 Wall Paper (kelas Menengah/sedang) m2 65,700
17 Wall Paper (kelas Baik) m2 90,900
18 Plywood 4 mm 120 x 240 lbr 64,800
19 Plywood 9 mm 120 x 240 lbr 140,700
20 Plywood 18 mm 120 x 240 lbr 212,200
21 TeakWood 3 mm 120 x 240 lbr 103,000
22 TeakWood 4 mm 120 x 240 lbr 150,600
23 TeakWood 3 mm 120 x 240 Uk. Pintu lbr 178,900
24 TeakWood 4 mm 120 x 240 Uk. Pintu lbr 223,800
25 Melamin 3 mm 120 x 240 Glossy /Doft lbr 105,000
26 Melamin 6 mm 120 x 240 Glossy /Doft lbr 129,200
27 Melamin 8 mm 120 x 240 Glossy /Doft lbr 151,200
28 HPL Wood Texture Kualitas : Taco m2 112,000
29 Formika Polos /Putih : Ukuran 120 x 240 lbr 210,000
30 Formika Motif Ukuran Pintu (3 x 80 x 200) lbr 172,500
31 Lem Kuning Setara AICA AIBON, FOX kg 61,600
32 Lem Putih /PVC Setara , FOX, RAJAWALI kg 22,000
33 Lem Pipa PVC setara : TANGOT, ISOPLAS kg 110,000
34 Lem Vynil setara : QUICKCURE kg 121,000

F. PENUTUP LANTAI DAN DINDING

1 Tegel PC 30 x 30 Warna : Natural /abu PC buah 5,300


2 Plin Tegel PC 15 x 30 Warna : Natural /abu PC buah 2,600
3 Tegel Warna 30 x 30 Warna : Warna Oker buah 5,850
4 Plin Tegel Warna 15 x 30 Warna : Warna Oker buah 2,900
5 Tegel Badak PC 30 x 30 Motif dan Warna : Natural /abu PC buah 5,600
6 Tegel Badak Warna 30 x 30 Motif dan Warna : Warna Oker buah 6,100
7 Keramik 20 x 20 dan 10 x 20 (stepnosing) KW 1 DN Putih /polos (Kualitas : KIA, Muli m2 40,825
8 Keramik 20 x 20 KW 1 DN Corak/Warna/ Anti slip (Kualitas : m2 44,275
9 Keramik 20 x 20; 20 x 25; 25 x 25 KW 1 DN Putih /polos (Kualitas : Roman, Mi m2 92,575
10 Keramik 20 x 20; 20 x 25; 25 x 25 KW 1 DN Corak/Warna/ Anti slip (Kualitas : m2 62,000
11 Keramik 25 x 40 KW 1 DN Corak/Warna/ Anti slip (Kualitas : m2 74,000
12 Keramik 30 x 30 KW 1 DN Putih /polos (Kualitas : KIA, Muli m2 45,425
13 Keramik 30 x 30 KW 1 DN Corak/Warna/ Anti slip (Kualitas : m2 44,000
14 Keramik 30 x 30 KW 1 DN Putih /polos (Kualitas : Roman, Mi m2 97,980
15 Keramik 30 x 30 KW 1 DN Corak/Warna/ Anti slip (Kualitas m2 103,500
16 Keramik 40 x 40 KW 1 DN Putih /polos (Kualitas : KIA, Muli m2 46,920
17 Keramik 40 x 40 KW 1 DN Corak/Warna/ Anti slip (Kualitas : m2 48,760
18 Keramik 40 x 40 KW 1 DN Putih /polos (Kualitas : Roman, Mi m2 98,325
19 Keramik 30 x 60 KW 1 DN Corak/Warna/ Anti slip (Kualitas m2 104,075
20 Keramik 60 x 60 KW 1 DN Putih /polos (Kualitas : Roman, Mi m2 98,325
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
21 Keramik 60 x 60 KW 1 DN Corak/Warna/ Anti slip (Kualitas m2 85,000
22 Keramik Granit 50 x 50 KW 1 DN Putih /polos (Kualitas : Granito, m2 138,000
23 Keramik Granit 50 x 50 KW 1 DN Corak/Warna/ Anti slip (Kualitas m2 141,450
24 Keramik Granit 60 x 60 KW 1 DN Putih /polos (Kualitas : Granito, m2 241,500
25 Keramik Granit 60 x 60 KW 1 DN Corak/Warna/ Anti slip (Kualitas m2 241,500
26 Granito Tile 60 x 60 KW 1 DN Polish (Kualitas : Essenza /setara m2 370,700
27 Granito Tile 60 x 60 KW 1 DN Unpolish (Kualitas : Essenza /set m2 540,100
28 Plin Lantai Granite 10 x 60 (berbagai ukuran) buah 6,000
29 Hospital plint uk . 10x 60 buah 75,000
30 Hospital plint sudut uk . 5 cm buah 50,000
29 Kramik Granite Stepnosing uk . 30x 60 buah 40,000
30 Karpet Kelas Standar Ex DN m2 192,500
31 Parquet Jati KW 1 Ukuran 1.2 cm x 5 cm x 20 cm m2 191,625
32 Parquet Jati KW 1 Ukuran 1.2 cm x 5 cm x 25 cm m2 215,250
33 Parquet Jati KW 1 Ukuran 1.2 cm x 5 cm x 30 cm m2 236,250
34 Parquet Jati KW 1 Ukuran 1.8 cm x 5 cm x 20 cm m2 299,250

G. BAHAN SALURAN AIR

1 Grafel U-20 cm' m' 42,750


2 Grafel U-30 cm' m' 57,000
3 Grafel U-40 cm' m' 71,250
4 Buis Beton Ø 20 cm (1 m') m' 58,500
5 Buis Beton Ø 30 cm (1 m') m' 81,000
6 Buis Beton Ø 40 cm (1 m') m' 97,750
7 Buis Beton Ø 50 cm (1 m') m' 144,000
8 Buis Beton Ø 60 cm (1 m') m' 188,000
9 Buis Beton Ø 70 cm (0.50 m') m' 190,000
10 Buis Beton Ø 80 cm (0.50 m') m' 192,000
11 Buis Beton Ø 100 cm (0.50 m') m' 228,000
12 Saluran Terbuka (U-Ditch) UD 50 Beton Dimensi : 50/60 - 120 m 718,750
13 Saluran Terbuka (U-Ditch) UD 70 Beton Dimensi : 50/70 - 120 m 891,250
14 Saluran Terbuka (U-Ditch) UD 80 Beton Dimensi : 50/80 - 120 m 1,029,250
15 Saluran Terbuka (U-Ditch) UD 100 Beton Dimensi : 50/100 - 120 m 2,084,375
16 Saluran Terbuka (U-Ditch) UD 120 Beton Dimensi : 50/120 - 120 m 2,443,750
17 Saluran Tertutup (Box Culvert) BC 50 Beton Dimensi : 50 x 50 - 100 m 1,239,700
18 Saluran Tertutup (Box Culvert) BC 60 Beton Dimensi : 60 x 60 - 100 m 1,603,100
19 Saluran Tertutup (Box Culvert) BC 80 Beton Dimensi : 80 x 80 - 100 m 2,868,100
20 Saluran Tertutup (Box Culvert) BC 100 Beton Dimensi : 100 x 100 - 100 m 3,630,000
21 Saluran Tertutup (Box Culvert) BC 120 Beton Dimensi : 120 x 120 - 100 m 4,840,000
22 Saluran Tertutup (Box Culvert) BC 150 Beton Dimensi : 150 x 150 - 100 m 9,035,400
23 Saluran Tertutup (Box Culvert) BC 200 Beton Dimensi : 200 x 200 - 100 m 12,705,000

H. BAHAN LOGAM DAN BAHAN JADINYA

1 Besi Beton U-24 (Bulat /Persegi Rata-rata) kg 12,000


2 Besi Beton U-32 /U-39 (Bulat /Persegi Rata-rata) kg 12,000
3 Besi Profil UNP /CNP (rata-rata) C 100.50.20/C 75. 45. 15 kg 14,000
4 Besi Plat (rata-rata) kg 15,000
5 Besi Siku (rata-rata) kg 18,200
6 Besi WF /H Beam (rata-rata) ex DN-SII kg 16,000
7 Besi WF /H Beam (rata-rata) ex LN kg 33,250
8 Besi Pipa (rata-rata) kg 22,750
9 Pagar BRC lengkap (tanpa Pondasi) BRC Ø 6, tiang Ø 2 inc m2 187,000
10 Pagar BRC lengkap (tanpa Pondasi) BRC Ø 8, tiang Ø 2 inc m2 270,000
11 Kawat Beton kg 17,500
12 Kawat Duri Barbwire/ Lokal kg 62,500
13 Kawat Bronjong Ø 3 mm kg 30,000
14 Kawat Bronjong Ø 4 mm kg 35,000
15 Kawat Bronjong Ø 3 mm Ukuran 1,00x0,5x2,00 Bh 450,000
16 Kawat Bronjong Ø 4 mm Ukuran 1,00x0,5x2,00 Bh 500,000
17 Kawat Tembaga kg 62,500
18 Ram Nyamuk Hijau m2 24,500
19 Ram Nyamuk Alluminium m2 28,250
20 Ram Kawat 1 x 1 (Putih) Ø1" x 1 m x 25 m (=12kg) m2 17,600
21 Ram Kawat Ayam Ø1/2" x 1 m x 18 m (=12kg) m2 17,600
22 Kawat Harmonika 3 cm Ø 3 mm, spasi kotak 50mm x 50mm m2 88,000
23 Kawat Harmonika 4 cm Ø 4 mm, spasi kotak 50mm x 50mm m2 115,500
24 Kawat Las Listrik kg 35,000
25 Wiremesh M6 Ø 6 mm 2,1m x 5,4m lbr 346,500
26 Wiremesh M8 Ø 8 mm 2,1m x 5,4m lbr 605,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
27 Chequer Plate uk. 120 x 240 t=4,5 mm lbr 1,384,250
28 Bondex 0,75 t=0,75 mm; L=1m, P=(disesuaikan) m 110,000
29 Bondex 1,00 t=1,00 mm; L=1m, P=(disesuaikan) m 137,500
30 Plat Alluminium 0.2 mm Tebal 0.2 mm m2 35,200
31 Plat Alluminium 0.3 mm Tebal 0.3 mm m2 49,700
32 Plat Alluminium 0.4 mm Tebal 0.4 mm m2 65,800
33 Plat Alluminium 0.5 mm Tebal 0.5 mm m2 81,750
34 Plat Alluminium 0.6 mm Tebal 0.6 mm m2 97,800
35 Plat Alluminium 0.1 mm Tebal 0.1 mm m2 162,600
36 Alumunium Composite Panel m2 360,000
37 Kusen Aluminium Natural 1.3 mm t = 1,3 mm (3") str : alexindo m' 75,000
38 Kusen Aluminium Warna 1.3 mm t = 1,3 mm (3") str : alexindo m' 95,000
39 Kusen Aluminium Natural/silver 1.3 mm t = 1,3 mm (4") str : alexindo m' 95,000
40 Kusen Aluminium Warna 1.3 mm t = 1,3 mm (4") str : alexindo m' 105,000
41 Profil Daun Pintu Aluminium Natural/Silver m' 62,500
42 Profil Daun Pintu Aluminium Warna m' 70,000
42 Profil Daun Jendela Aluminium Natural/Silver m' 42,000
43 Profil Daun Jendela Aluminium Warna m' 47,500
43 Spandrel Aluminium Natural/Silver 110 mm x 1 mm x 6 m lbr 117,500
44 Spandrel Aluminium 110 mm x 1 mm x 6 m lbr 130,000
45 Daun Jendela Aluminium Natural silver+accesories+kaca polos 5 mm m2 425,000
46 Daun Jendela Aluminium Warna Coklat /Hitam+accesories+kaca polos 5 m m2 475,000
47 Daun Pintu Swing Aluminium Natural silver + kaca polos 5 mm, floor hinge dor m2 1,125,000
48 Daun Pintu Swing Aluminium Warna coklat /hitam + kaca polos 5 mm, floor h m2 1,250,000
49 Daun Pintu Doble Teakwood buah 1,487,500
50 Pintu PVC Kamar Mandi Std Tinggi : ROYAL buah 550,000
51 Pintu PVC Kamar Mandi Std Sedang : Maspion, ETZA buah 475,000
52 Pintu PVC Kamar Mandi Std Biasa : Polos. CESSA buah 225,000
53 Pintu Folding Gate Besi Standar t=0,4mm m2 425,000
54 Pintu Folding Gate Galvalum Standar t=0,4mm m2 450,000
55 Pintu Roliing Door Besi t=0,4mm m2 400,000
56 Pintu Rolling Door Galvalum t=0,4mm m2 455,000
57 Rangka Jendela Nako + besi/tralis 3 klips (tanpa kaca) set 52,500
58 Rangka Jendela Nako + besi/tralis 4 klips (tanpa kaca) set 70,000
59 Rangka Jendela Nako + besi/tralis 5 klips (tanpa kaca) set 87,500
60 Rangka Jendela Nako + besi/tralis 6 klips (tanpa kaca) set 105,000
61 Jalusi Aluminium m' 59,700
62 Sunscreen Aluminium m2 521,500
63 Pintu Frameless (tempered 12 mm polos) floor hinge dorma BTS 84 m 3,000,000
64 Pintu fitting (tempered 12 mm polos) floor hinge dorma BTS 84 m 3,750,000
65 Seng Plat BJLS 0,4 mm 1219 x 2438 mm roll 298,540
66 Seng Plat BJLS 0,6 mm 1219 x 2438 mm roll 439,230
67 Seng Plat BJLS 0,4 mm 1219 x 25000 mm Roll 3,066,000
68 Seng Plat BJLS 0,6 mm 1219 x 25000 mm Roll 4,511,850
69 Profil Aluminium m' 25,500
70 Jendela Besi m2 493,800
71 Jendela Besi Tahan Api m2 663,500
72 Venetion Blind m2 250,000
73 Vertical Blind m2 359,000
74 Hollow 60 x 60 x 1.8 btg (6 m) 244,100
75 Hollow 60 x 60 x 1.6 btg (6 m) 217,000
76 Hollow 50 x 50 x 2.5 btg (6 m) 282,600
77 Hollow 50 x 50 x 1.0 btg (6 m) 113,000
78 Hollow 50 x 50 x 1.6 btg (6 m) 180,800
79 Hollow 50 x 50 x 1.3 btg (6 m) 146,900
80 Hollow 40 x 60 x 2.0 btg (6 m) 226,000
81 Hollow 40 x 60 x 1.6 btg (6 m) 180,800
82 Hollow 40 x 40 x 1.7 btg (6 m) 147,000
83 Hollow 40 x 40 x 1.6 btg (6 m) 144,600
84 Hollow 40 x 40 x 1.3 btg (6 m) 117,500
85 Hollow plafond 40 x 40 x 0,3 mm btg (4 m) 24,000
86 Hollow 30 x 60 x 1.8 btg (6 m) 183,100
87 Hollow 30 x 60 x 1.6 btg (6 m) 162,700
88 Hollow 30 x 30 x 2.0 btg (6 m) 135,600
89 Hollow 30 x 30 x 1.6 btg (6 m) 108,500
90 Hollow 30 x 30 x 1.3 btg (6 m) 88,100
91 Hollow 30 x 30 x 1.0 btg (6 m) 67,800
92 Hollow 20 x 40 x 1.8 btg (6 m) 122,000
93 Hollow 20 x 40 x 1.6 btg (6 m) 108,500
94 Hollow 20 x 40 x 1.3 btg (6 m) 88,100
95 Hollow 20 x 40 x 1.0 btg (6 m) 67,800
96 Hollow 50 x 25 x 2.0 btg (6 m) 169,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
97 Hollow 50 x 25 x 1.6 btg (6 m) 135,600
98 Hollow 50 x 25 x 1.3 btg (6 m) 110,200
99 Hollow 50 x 25 x 1.0 btg (6 m) 84,700
100 Hollow 20 x 20 x 2.0 btg (6 m) 90,400
101 Hollow 20 x 20 x 1.6 btg (6 m) 72,300
102 Hollow 20 x 20 x 1.3 btg (6 m) 58,700
103 Hollow 20 x 20 x 1.0 btg (6 m) 45,200
104 Pintu besi hollow m2 480,000
105 Huruf Stainless Steel cm 12,000
106 Tiang Pancang Segi Tiga 28x28x28 cm K-450 m' 225,000

I. BAHAN KACA

1 Kaca Polos 2 mm m2 58,275


2 Kaca Polos 3 mm m2 68,775
3 Kaca Polos 5 mm m2 90,000
4 Kaca Polos 8 mm m2 158,025
5 Kaca Reyband 5 mm m2 79,275
6 Kaca Reyband 6 mm m2 76,125
7 Kaca Reyband 8 mm m2 142,275
8 Kaca Reyband 10 mm m2 242,025
9 Kaca Clear Tempered 5 mm m2 221,025
10 Kaca Clear Tempered 6 mm m2 273,525
11 Kaca Clear Tempered 8 mm m2 404,775
12 Kaca Clear Tempered 10 mm m2 431,025
13 Kaca Clear Tempered 12 mm m2 483,525
14 Kaca Es / Susu 3 mm m2 99,750
15 Kaca Es / Susu 5 mm m2 141,750
16 Kaca Cermin 3 mm m2 100,275
17 Kaca Cermin 5 mm m2 142,275
18 Kaca Cermin 8 mm m2 202,125
19 Kaca Polos Sandblasting (Terpasang) Grafier 3mm /5mm /8mm m2 1,050,000
20 Kaca Polos Sandblasting (Terpasang) Grafier Airbrush 3mm /5mm /8mm m2 1,205,000
21 Kaca Patri Lokal Terpasang Polos m2 1,450,000
22 Kaca Patri Lokal Terpasang Airbrush m2 1,750,000
23 Kaca Patri Lokal Terpasang Kuningan m2 2,200,000
24 Glass Block DN 20 x 20 bh 27,000
25 Glass Block DN 20 x 20 ex LN buah 40,000
26 Lem Kaca /Sealant tube 41,000
27 Lem Kaca /Sealant m1 3,000
28 Sunblast m2 60,000
J. BAHAN PAKU DAN MUR BAUT

1 Paku 1 cm s/d 3 cm kg 21,000


2 Paku 4 cm s/d 7 cm kg 19,250
3 Paku 8 cm s/d 15 cm kg 18,500
4 Paku Beton 2 cm s/d 5 cm buah 650
5 Paku Kait Lengkap buah 500
6 Paku Cacing kg 69,500
7 Paku GRC kg 36,500
8 Paku Gypsum kg 35,270
9 Paku Skrup 5 cm kg 13,000
10 Paku Seng kg 18,000
11 Paku Hak Panjang 15 cm kg 13,500
12 Sekrup Fixer bh 1,500
13 Skrup Ukuran 1" dus 14,000
14 Paku Sekrup 3" buah 1,200
15 Skrup/suspention clip bh 1,300
16 Skrup/suspention road bh 800
17 Skrup Ukuran khusus 6x1 1/4" setara sunray dus/1500 121,000
18 Skrup Ukuran khusus 6x1 1/4" setara sunray bh 110
19 Skrup Ukuran khusus 6x1 1/2" setara sunray dus/1000 99,000
20 Skrup Ukuran khusus 6x1 1/2" setara sunray bh 165
21 Besi Beugeul Kuda-kuda kg 18,500
22 Duk Angker buah 6,500
23 Baut Anker kg 18,000
24 Baut Besar buah 11,250
25 Baut Kecil buah 1,500
26 Mur Baut Biasa Ø 19 s/d 16 (5 cm) buah 7,500
27 Mur Baut HTB Ø 19 s/d 16 (5 cm) buah 13,000
28 Mur Baut HTM 5/8x3" buah 7,350
29 Angker Mur Baut Ø 19 / Panjang 60 cm buah 27,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
30 Angker Mur Baut Ø 16 / Panjang 30 cm buah 19,000
31 Piser Ø 12 s/d 20 cm bh 650
32 Ramset / Dinabolt Ø 12 cm buah 8,000
33 Conection clip bh 2,500
34 Hangger/gantungan besi Ø 8 mm kg 20,000

K. BAHAN PERPIPAAN

1 Besi Pipa untuk Hydrant BSP Ø 1" btg (6 m) 179,200


2 Besi Pipa untuk Hydrant BSP Ø 1.15" btg (6 m) 204,800
3 Besi Pipa untuk Hydrant BSP Ø 1.5" btg (6 m) 243,200
4 Besi Pipa untuk Hydrant BSP Ø 2" btg (6 m) 328,000
5 Besi Pipa untuk Hydrant BSP Ø 2.5" btg (6 m) 560,800
6 Besi Pipa untuk Hydrant BSP Ø 3" btg (6 m) 647,200
7 Besi Pipa untuk Hydrant BSP Ø 4" btg (6 m) 861,600
8 Besi Pipa untuk Hydrant BSP Ø 6" btg (6 m) 1,780,000
9 Besi Pipa Hitam Ø 1" t = 2 mm btg (6 m) 110,400
10 Besi Pipa Hitam Ø 2" t = 2 mm btg (6 m) 216,000
11 Besi Pipa Hitam Ø 3" t = 2 mm btg (6 m) 372,000
12 Besi Pipa Hitam Ø 4" t = 2 mm btg (6 m) 452,000
13 Besi Pipa Hitam Ø 6" t = 2 mm btg (6 m) 824,000
14 Pipa GIP Medium A 1/2" btg (6 m) 168,800
15 Pipa GIP Medium A 3/4" btg (6 m) 214,400
16 Pipa GIP Medium A 1" btg (6 m) 244,800
17 Pipa GIP Medium A 1 1/4" btg (6 m) 304,000
18 Pipa GIP Medium A 1 1/2" btg (6 m) 287,200
19 Pipa GIP Medium A 1 3/4" btg (6 m) 388,800
20 Pipa GIP Medium A 2" btg (6 m) 547,200
21 Pipa GIP Medium A 2 1/2" btg (6 m) 676,800
22 Pipa GIP Medium A 3" btg (6 m) 936,800
23 Pipa GIP Medium A 4" btg (6 m) 1,201,600
24 Macam-macam Sambungan GIP 1/2" buah 7,200
25 Macam-macam Sambungan GIP 3/4" buah 8,800
26 Macam-macam Sambungan GIP 1" buah 13,600
27 Macam-macam Sambungan GIP 1 1/4" buah 18,400
28 Macam-macam Sambungan GIP1 1/2" buah 21,600
29 Macam-macam Sambungan GIP 1 3/4" buah 24,800
30 Macam-macam Sambungan GIP 2" buah 44,800
31 Macam-macam Sambungan GIP 2 1/2" buah 53,600
32 Macam-macam Sambungan GIP 3" buah 84,800
33 Macam-macam Sambungan GIP 4" buah 112,000
34 Pipa PVC type AW Ø 1/2" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 27,300
35 Pipa PVC type AW Ø 3/4" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 38,350
36 Pipa PVC type AW Ø 1" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 45,000
37 Pipa PVC type AW Ø 1 1/4" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 68,850
38 Pipa PVC type AW Ø 1 1/2" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 77,600
39 Pipa PVC type AW Ø 2" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 102,400
40 Pipa PVC type AW Ø 2 1/2" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 116,000
41 Pipa PVC type AW Ø 3" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 204,000
42 Pipa PVC type AW Ø 4" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 385,000
43 Pipa PVC type AW Ø 6" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 806,400
44 Pipa PVC type AW Ø 8" Kualitas RUCIKA, MASPION, Wavin btg (4 m) 1,242,000
45 Sambungan pipa PVC Ø 1/2" buah 5,400
46 Sambungan pipa PVC Ø 3/4" buah 7,300
47 Sambungan pipa PVC Ø 1" buah 8,100
48 Sambungan pipa PVC Ø 1 1/4" buah 10,800
49 Sambungan pipa PVC Ø 1 1/2" buah 14,700
50 Sambungan pipa PVC Ø 1 3/4" buah 14,700
51 Sambungan 2" buah 24,000
52 Sambungan pipa PVC Ø 2 1/2" buah 35,600
53 Sambungan pipa PVC Ø 3" buah 45,000
54 Sambungan pipa PVC Ø 4" buah 66,700
55 Pipa PVC 4" TY buah 135,800
56 Pipa PVC AW 4" (Jambang /berlobang) m' 88,800
57 Solatif Ledeng gl 6,200
58 PVC Waterstop Lebar 150 m' 77,000
59 PVC Waterstop Lebar 200 m' 76,200
60 PVC Waterstop Lebar 230 m' 88,300
61 PVC Waterstop Lebar 250 m' 99,300
62 PVC Waterstop Lebar 300 m' 112,100
63 PVC Waterstop Lebar 320 m' 120,500
64 Pipa HDPE Dia. 20 mm/ Ø 1/2" m' 7,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
65 Pipa HDPE Dia. 32 mm/ Ø 1" m' 10,500
66 Pipa HDPE Dia. 40 mm/ Ø 1 1/4" m' 16,400
67 Pipa HDPE Dia. 50 mm/ Ø 1 1/2" m' 25,500
68 Pipa HDPE Dia. 63 mm/ Ø 2" m' 40,700
69 Pipa HDPE Dia. 90 mm/ Ø 3" m' 82,700
70 Pipa PVC Dia. 20 mm/ Ø 1/2" m' 6,100
71 Pipa PVC Dia. 25 mm/ Ø 3/4" m' 8,500
72 Pipa PVC Dia. 32 mm/ Ø 1" m' 11,000
73 Pipa PVC Dia. 50 mm/ Ø 1 1/2" m' 26,500
74 Pipa PVC Dia. 63 mm/ Ø 2" m' 35,000
75 Pipa PVC Dia. 90 mm/ Ø 3" m' 71,000
76 Pipa PVC Dia. 110 mm/ Ø 4" m' 99,500
77 Pipa PVC Dia. 160 mm/ Ø 6" m' 211,000
78 Pipa PVC Dia. 225 mm/ Ø 8" m' 322,300
79 Seal Tape Set 5,500
80 Karet Paking Kg 20,000
81 Flange Socket RRJ Dia. 50 mm Bh 266,850
82 Flange Socket RRJ Dia. 63 mm Bh 367,500
83 Bend all flange Dia. 63 mm - 90 drj Bh 24,000
84 Bend all flange Dia. 75 mm - 45 drj Bh 280,500
85 Bend all flange Dia. 50 mm - 45 drj Bh 189,200
86 Bend all flange Dia. 50 mm - 90 drj Bh 200,500
87 Bend all flange Dia. 40 mm - 90 drj Bh 160,500
88 Tee flange Dia. 63 mm Bh 303,600
89 Flange Lass Pn 10 Dia. 63 mm Bh 115,800
90 Flange Lass Pn 10 Dia. 50 mm Bh 110,800
91 Flange Lass Pn 10 Dia. 40 mm Bh 105,800
92 Fudle Flange Kg 18,450
93 Lem PVC Tube 13,500
94 Box Street uk. 4" Bh 111,100
95 Gate Valve GI All Flange Dia. 75 mm Bh 1,700,000
96 Gate Valve GI All Flange Dia. 63 mm Bh 1,400,000
97 Bend PVC Socket Spigot Dia. 90 mm - 90 drj, ( Setara Vinillon) Bh 126,300
98 Bend PVC Socket Spigot Dia. 63 mm - 45 drj, Bh 74,400
99 Tiang Listrik, Pipa GI Bh 2,500,000
100 Pipa GI Dia. 90 mm SII m' 210,500
101 Pipa GI Dia. 63 mm SII m' 136,500
102 Pipa GI Dia. 50 mm SII m' 119,200
103 Pipa GI Dia. 40 mm SII m' 86,500
104 Pipa GI Dia. 20 mm SII m' 34,000
105 Repair Socket Dia. 63 mm buah 50,100
106 Repair Socket Dia. 90 mm buah 56,250
107 Sock Drat Luar PVC Dia. 20 mm buah 4,000
108 Sock Drat Luar PVC Dia. 25 mm buah 6,000
109 Knee GI Dia. 20 mm buah 7,350
110 Knee GI Dia. 25 mm buah 8,500
111 Knee GI Dia. 50 mm buah 39,000
112 Knee GI Dia. 63 mm buah 49,000
113 Knee PVC Dia. 63 mm buah 16,100
114 Knee PVC Dia. 50 mm buah 7,500
115 Knee PVC Dia. 32 mm buah 5,750
116 Knee PVC Dia. 25 mm buah 4,500
117 Knee PVC Dia. 20 mm buah 3,750
118 Knee drat PVC Dia. 20 mm buah 4,200
119 Double Naple Dia. 20 mm buah 8,400
120 Water Meter Dia. 20 mm buah 350,000
121 Floatin g Valve Dia. 20 mm buah 85,000
122 Stop Kran Dia. 20 mm buah 68,400
123 Flug Kran Dia. 20 mm buah 60,200
124 Kran Dia. 20 mm buah 25,100
125 Socket GI Dia. 20 mm buah 8,400
126 Plug PVC Dia. 20 mm buah 3,250
127 Dop PVC Dia. 20 mm buah 3,250
128 Tangki Fiber Glass 2 M3 buah 3,150,000
129 Tangki Air kapasitas 5000 LITER buah 9,500,000
130 Box Meter buah 80,000
131 Tee GI Dia. 20 mm buah 11,700
132 Tee PVC Dia. 20 mm buah 4,500
133 Tee PVC RRJ Dia. 63x63 mm, ( Setara Vinillon ) buah 262,200
134 Tee RRJ Dia. 63x32 mm buah 220,100
135 Tee PVC Dia. 25x25 mm buah 6,500
136 Tee PVC 63x63 mm buah 22,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
137 Tee PVC 63x50 mm buah 15,500
138 Tee PVC 63x32 mm buah 14,300
139 Tee PVC 32x32 mm buah 6,100
140 Tee PVC 32x20 mm buah 5,500
141 Tee Y 50x50 mm buah 185,000
142 Reducer PVC Dia. 90x63 mm buah 19,500
143 Reducer PVC Dia. 63x32 mm buah 9,500
144 Reducer PVC Dia. 63x50 mm buah 11,900
145 Reducer PVC Dia. 32x20 mm buah 3,750
146 Ball Valve 63mm buah 133,250
147 Ball Valve 32mm buah 58,500
148 Socket HDPE Dia. 63 mm buah 160,000
149 Socket HDPE Dia. 50 mm buah 103,350
150 Socket HDPE Dia. 40 mm buah 85,000
151 Socket HDPE Dia. 32 mm buah 45,000
152 Bend All Flange 45 derajat buah 215,000
153 Bend All Flange 90 derajat buah 250,000
154 Manometer dengan kran 1/2" + Valve buah 174,000
155 Cek Valve buah 450,000
156 Air Valve buah 150,000
157 Clamp Sadle OD buah 27,300
158 Penutup Well Heat buah 375,000
159 Kawat seling Baja m' 2,500
160 Tambang Plastik m' 9,000
161 Floating valve buah 546,800
162 Floating valve buah 1,406,800
163 Screen Unit 500,000
164 Vent GIP Unit 200,000
165 Manhole Unit 600,000
166 Water Stop m' 65,000
167 Water Stop m' 85,000

L. BAHAN SANITAIR

1 Stop Kran 3/4" KITZ Bahan : Kuningan buah 124,100


2 Stop Kran 1" KITZ Bahan : Kuningan buah 175,300
3 Stop Kran 1 1/2" KITZ Bahan : Kuningan buah 350,700
4 Stop Kran 2" KITZ Bahan : Kuningan buah 534,600
5 Stop Kran 2 1/2" KITZ Bahan : Kuningan buah 1,345,600
6 Stop Kran 3" KITZ Bahan : Kuningan buah 1,737,500
7 Check Valve 1/2" buah 103,900
8 Double Neple 1/2" buah 62,800
9 Water Mur 1/2" buah 55,000
10 Gate Walve 1/2" buah 81,400
11 Saringan Air Lt. KM Stainless Steel bh 47,000
12 Apooer Bath Tube buah 256,000
13 Kran Stainless Lokal Kait buah 62,000
14 Shower dinding lengkap set 235,000
15 Shower Tanpa Tiang buah 95,000
16 Kran Tembok Sun Eui dia. 1/2" buah 90,700
17 Kran Tembok dia. 1/2" Biasa buah 19,000
18 Kran Tembok dia. 3/4" Biasa buah 25,000
19 Kran Bebek Sun Eui 1/2" buah 158,700
20 Kran Bebek ITAP 1/2" buah 83,400
21 Kran Panas Dingin Sun Eui Standard buah 363,100
22 Jet Washer set 90,000
23 Bath Cape Washteren unit 3,676,900
24 Bak KM Fiber 60 x 60 buah 352,750
25 Tempat Sabun Poslin buah 84,500
26 Wastafel Lengkap TOTO LW 230 unit 1,462,000
27 Wastafel Lengkap INA unit 884,600
28 Closet Jongkok Standar Porselin Warna TOTO bh 350,000
29 Closet Jongkok Standar Porselin Putih TOTO unit 311,900
30 Closet Jongkok Lengkap Sistem Jet TOTO unit 3,084,000
31 Closet Duduk Lengkap Warna Standard TOTO C 240 unit 2,775,100
32 Closet Jongkok KIA buah 186,000
33 Closet Jongkok INA (Wanan gelap) buah 298,700
34 Closet Duduk KIA unit 940,100
35 Closet Dudduk Ina (Warna Gelap) buah 1,861,900
36 Wastafel Bulat Lengkap Warna Standard unit 1,578,400
37 Wastafel Type Amerika Standard buah 127,100
38 Wastafel bh 874,700
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
39 Closet Duduk Lengkap Warna Standar INA buah 2,080,500
40 Urinoir Lengkap Warna Standard TOTO unit 3,009,500
41 Penyekat Poslin Urinoir TOTO Setandar TOTO lbr 931,200
42 Kitchen Zink Stainless Standard Lokal ( 1 Lubang) bh 600,600
43 Kitchen Zink Stainless Non Standard Franke( 1 Lubang) buah 1,554,400
44 Kitchen Zink Stainless Non Standard Franke( 1 Lubang) buah 1,756,200
45 Talang PVC U-15 cm btg 69,800
46 Water Drain + Acsesoris set 1,375,500
47 Clean Out buah 973,900
48 Septictank Biofil (Type BF-03, BF-06-08, dst) unit 7,425,000
49 Septictank Ipal Biofil (Type R-05, R-10, dst) unit 14,960,000
50 Sealtape bh 5,500
M. BAHAN PENUTUP ATAP

1 Atap Plastik Gelombang 80 x 180 lbr 60,000


2 Atap Fiber Glass 80 x 180 (tipis) Gelombang lbr 63,750
3 Atap Fiber Glass 80 x 180 (tebal) Gelombang lbr 76,500
4 Atap Aluminium Natura USR 26 Setara JAINDO m2 164,500
5 Atap Aluminium Warna USR 26 Setara JAINDO m2 276,200
6 Atap Asbes Gelombang Kecil Ukuran 105 x 180 x 4 mm lbr 63,700
7 Atap Asbes Gelombang Besar Ukuran 102 x 180 x 4 mm lbr 87,500
8 Atap Seng Gelombang Ukuran 80 cm x 180 cm x 3 mm lbr 70,000
9 Atap Seng Gelombang Ukuran 240 cm x 105 cm x 4 mm lbr 98,000
10 Atap Seng Gelombang Ukuran 210 cm x 105 cm x 4 mm lbr 87,000
11 Atap Seng Gelombang Ukuran 150 cm x 105 cm x 4 mm lbr 63,000
12 Aluminium Foil Laminated Sigle Sided (Roll=1,2 x 50 m) Roll 404,250
13 Aluminium Foil Laminated Double Sided (Roll=1,2 x 50 m) Roll 514,500
14 Aluminium Foil Laminated Bubble (Roll=1,2 x 50 m) m2 703,500
15 Atap Genteng Plentong Pres Bakar KW 1 buah 2,900
16 Atap Genteng Plentong Pres Molen Oven KW 2 buah 2,900
17 Atap Genteng Flam Pres Molen Oven Jatiwangi buah 2,900
18 Bubung Genteng Pres Bulat ex Jatiwangi buah 7,700
19 Genteng Bubungan ex Jatiwangi Segitiga buah 4,600
20 Genteng Bubungan Beton buah 15,500
21 Genteng Metal Kualitas Rainbowroof, Multiroof m2 137,500
22 Nok Atas Metal (p=104 cm) Kualitas Rainbowroof, Multiroof lbr 55,000
23 Nok Pinggir Metal Kualitas Rainbowroof, Multiroof lbr 30,000
24 Wall Flasing Uk 6 cm x 10 cm x 91,4 cm (Rainbowroof, lbr 82,200
25 Genteng Beton Gelombang Std=14,5 bh/m2 (Monier, cisangkan) buah 7,700
26 Genteng Beton Flat Std=14,5 bh/m2 (Monier, cisangkan) buah 9,900
27 Genteng Keramik Gelombang Std=14 bh/m2 (KIA,M-class, Kanmuri) buah 11,000
28 Genteng Keramik Glasur Plat Std=14 bh/m2 (KIA,M-class, Kanmuri) buah 13,750
29 Genteng Kaca Std=14 bh/m2 (KIA,M-class, Kanmuri) buah 52,500
30 Genteng Murando Natural Std= 18 bh/m2 buah 3,500
31 Genteng Murando Glasur Coklat/Trans Std= 18 bh/m2 bh 4,700
32 Genteng Murando Glasur Warna Std= 18 bh/m2 buah 7,800
33 Bubung Murando Natural buah 5,400
34 Bubung Murando Glasur Coklat/Trans bh 6,500
35 Bubung Murando Glasur Warna buah 6,720
36 Bubungan Genteng Keramik buah 24,600
37 List plank Genteng Keramik buah 32,500
38 Genteng Kodok buah 3,900
39 Bubungan Genteng Kodok buah 7,700
40 Bubungan Genteng Plentong buah 7,700
41 Bubungan Stel Gelombang buah 14,600
42 Nok Genteng Metal lbr 83,300
43 Nok Atap Seng lbr 55,900
44 Nok Standar 40 cm 18, SWG 22 m2 81,800
45 Atap Zingkalum m2 150,000
46 Atap Spandek m2 160,000
47 Rangka Atap baja Ringan 0,75 m2 130,000
48 Bubungan Atap Zingkalum m' 110,600
49 Bubungan Atap Spandek m' 274,500
50 Lisplang Kalsiplang (3000 x 200 x 8.0 mm) lbr 55,400
51 Lisplang Kalsiplang (2400 x 200 x 8.0 mm) lbr 44,000
52 Lisplang Kalsiplang (3000 x 200 x 12.0 mm) lbr 83,100
53 Lisplang Kalsiplang (2400 x 200 x 12.0 mm) lbr 66,800
54 Lisplang Kalsiplang (2400 x 300 x 8.0 mm) lbr 66,000
55 Lisplang Kalsiplang (2400 x 300 x 12.0 mm) lbr 101,000
56 List Plafond Gypsum Polos Siku (Setara Jaya Board Panjang 2 m) btg 60,400
57 List Plafond Gypsum Polos Siku (Setara Jaya Board Panjang 5 m) btg 32,500
58 List Plafond Gypsum Polos (Setara Jaya Board Panjang 2 m) btg 17,900
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
59 List Plafond Gypsum Polos (Setara Jaya Board Panjang 5 m) btg 19,500
60 Atap Bitumen Monolayer 3 mm uk/ 95cm x 200cm lbr 180,285
61 Atap Bitumen Monolayer 3 mm uk/ 40cm x 106cm lbr 51,000
62 Atap Bitumen Monolayer 3 mm uk/ 96cm x 195cm lbr 166,650
63 Atap Transparat /clair gelombang uk/ 95cm x 200cm lbr 272,700
64 Atap Transparat /clair tile uk/ 400cm x 496cm lbr 212,100
65 Nok Atap Bitumen Monolayer 3 mm uk/ 50cm x 100cm lbr 88,880
66 Genteng onduline tile lbr 165,000
67 Nok genteng onduline lbr 85,000
68 Atap UPVC (White /Blue Doff, tebal 10mm) Setara : Alderon, Avantguard, Formax, Sun m2 165,000
69 Atap UPVC (Semi Transparan, tebal 10mm) Setara : Alderon, Avantguard, Formax, Sun m2 231,000
70 Wuwung atap UPVC (Top Ridge, tebal 10mm, p=
Setara : Alderon, Avantguard, Formax, Sun buah 99,000
71 Lock Seal Cap atap UPVC (Ø 32mm) Pack 27,500

N. BAHAN MEKANIKAL DAN PEMADAM KEBAKARAN

1 Electrical Pump kap. 750 gln/menit 120 ml (90 kW) unit 353,531,000
2 Diesel Pump kap. 750 gln/menit 120 ml (105 kW) unit 883,828,300
3 Presure Tank kap. 500 liter lengkap unit 51,681,000
4 Hydran Box dlm Gedung ( Lengkap ) unit 9,163,400
5 Fire House 1.5 x 30 m + nose unit 7,371,000
6 Fire Alarm Bell unit 183,425
7 Fire Strobo Light unit 70,035
8 Fire Control Panel 4 Zone unit 3,835,250
9 Fire Control Panel 8 Zone unit 4,585,625
10 Sirine and Strobo unit 566,950
11 Gas Detector unit 283,475
12 Smoke Detector 4 Wire unit 186,760
13 Heat Detector 4 wire unit 156,745
14 Smoke and Heat Detector 4 wire unit 196,765
Fire Extinguiser (APAR) 3 Kg + Bracket unit 1,350,000
kipas angin panasonic unit 975,000
Genset 12 KW unit 62,500,000
O. BAHAN ELEKTRIKAL

1 Kabel NYA 1 x 1.5 Setara : Eterna, Supreme Roll (50m) 202,125


2 Kabel NYA 1 x 2.5 Setara : Eterna, Supreme Roll (50m) 327,075
3 Kabel NYM 2 x 1.5 Setara : Eterna, Supreme Roll (50m) 313,950
4 Kabel NYA 2 x 2.5 Setara : Eterna, Supreme Roll (50m) 327,075
5 Kabel NYM 3 x 1.5 Setara : Eterna, Supreme Roll (50m) 399,685
6 Kabel NYM 3 x 2.5 Setara : Eterna, Supreme Roll (50m) 567,520
7 Kabel NYM 3 x 4 Setara : Eterna, Supreme Roll (100m) 1,835,400
8 Kabel NYY 2 x 1.5 Setara : Eterna, Supreme Roll (100m) 630,000
9 Kabel NYY 2 x 2.5 Setara : Eterna, Supreme Roll (100m) 987,000
10 Kabel NYY 3 x 1.5 Setara : Eterna, Supreme Roll (100m) 942,900
11 Kabel NYY 3 x 2.5 Setara : Eterna, Supreme Roll (100m) 1,344,000
12 Kabel NYY 4 x 1.5 Setara : Eterna, Supreme Roll (100m) 1,210,650
13 Kabel NYY 4 x 2.5 Setara : Eterna, Supreme Roll (100m) 1,879,500
14 Kabel NYY 4 x 10 Setara : Eterna, Supreme Roll (100m) 3,750,000
15 MCB 1 PAS 1P 6A C MCB Setara Schneider bh 91,355
16 MCB 1 PAS 1P 10A C MCB Setara Schneider bh 91,465
17 MCB 1 PAS 1P 16A C MCB Setara Schneider bh 91,960
18 MCB 1 PAS 1P 25A C MCB Setara Schneider bh 101,750
19 MCB 3 PAS 3P 6A C MCB Setara Schneider bh 419,265
20 MCB 3 PAS 3P 10A C MCB Setara Schneider bh 419,430
21 MCB 3 PAS 3P 16A C MCB Setara Schneider bh 420,090
22 MCB 3 PAS 3P 25A C MCB Setara Schneider bh 443,465
23 Saklar Tunggal/ Single Standard (1 Phase) Setara Brocco bh 15,950
24 Saklar Seri/double Standard (1 Phase) Setara Brocco bh 19,250
25 Stop Kontak Standard (1 Phase) Setara Brocco bh 29,210
26 Stop Kontak 3 Phase (Out Bow) Setara Brocco bh 121,134
27 Stop Kontak 3 Phase (In Bow) Setara Brocco bh 205,000
28 Stop Kontak AC Handle 3 Phase Setara Brocco bh 129,000
29 Lampu Bohlam 10/15/20/25/40/60 Watt Pijar Tipe Clear bh 27,500
30 Lampu Bohlam 25/40/60 Watt Pijar Tipe Softone bh 39,050
31 Lampu Bohlam 25/40/60 Watt Pijar Tipe Superlux bh 60,940
32 Lampu Neon 10 s/d 20 Watt setara Phillips bh 49,700
33 Lampu Neon 24 s/d 40 Watt setara Phillips bh 68,400
34 Rumah TL In Bow /Out Bow 2x20 W (kosongan Sonora) bh 195,900
35 Fitting + Lampu Down Light 24 Watt bh 454,600
36 Lampu Sirkel TL 20 W Lengkap bh 164,600
37 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 1,160,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
38 Jarum Penangkal Petir 16 bh 148,900
39 Kawat BC ( Tembaga ) kg 62,700
40 Pentanahan Penangkal Petir ttk 658,400
41 Arde /box schreeng Ls 150,000
42 Box Schreeng In-bouw C4 bh 52,500
43 Bongkar /Pasang Standard + Meteran PLN Ls 1,750,000
44 Instalasi Titik Lampu (Upah, Bahan dan Alat) ttk 150,000
45 Instalasi Titik Stop Kontak (Upah, Bahan dan Alat) ttk 150,000
46 Lampu Baret 30 cm + Neon Set 125,000
47 Lampu Dinding bh 400,000
48 Lampu Down Light sedang + lampu SL 10 watt bh 80,000
49 Lampu Down Light sedang + lampu SL 18 watt set 94,000
50 Lampu Gantung Uk. Besar Unit 2,800,000
51 Lampu Gantung uk. Sedang Unit 350,000
52 Lampu Gantung uk. Kecil Unit 2,650,000
53 Lampu SLE 15 Watt bh 44,000
54 Pemasangan pipa conduit titik 14,650
55 Lampu LED 5 Watt s/d 9 Watt Setara In Lite bh 30,250
56 Lampu LED 11 Watt s/d 14 Watt Setara In Lite bh 38,500
57 Lampu LED 16 Watt s/d 22 Watt Setara In Lite bh 49,500
58 Lampu SL 8 W Setara Phillips bh 29,700
59 Lampu SL 14 W Setara Phillips bh 38,500
60 Lampu SL 18 Watt Setara Phillips bh 36,000
61 Lampu SL 23 W Setara Phillips bh 42,900
62 Lampu Sorot Philips 40 Watt bh 70,600
63 Lampu spot light 120 Watt / 150 Watt bh 52,900
64 Lampu spot light 300 Wattt bh 760,000
65 Lampu Tanam bh 750,000
66 Lampu TL 1 x 20 Watt ( Lengkap ) bh 63,250
67 Lampu TL 1 x 40 Watt bh 26,500
68 Lampu TLD 2 x 36 Watt TKl + Accessories, Philips set 305,800
69 Lampu TL Type RMI 2x18 Watt 2x18W+lampu TL setara Phillips bh 269,000
70 Lampu TL Type RMI 2x24 Watt 2x24W+lampu TL setara Phillips bh 313,500
71 Lampu TL Type RMI 2x36 Watt 2x36W+lampu TL setara Phillips set 407,400
72 Lampu TL RM 4 x 20 Watt bh 705,000
73 Lampu LED Strip SMD352850 IP68 220 vac+steker hiled 5m' 212,500
74 MLL 160 Watt bh 200,000
75 Panel LP-A bh 380,000
76 Panel LP-B bh 560,000
77 Panel LP-C bh 365,200
78 Panel LP-D bh 360,000
79 Panel LP-E bh 360,000
80 Panel SDP bh 203,000
81 Pasang Telepon Ls 2,500,000
82 Saklar Ganda Setara BROCO bh 18,000
83 Saklar Tunggal Setara BROCO bh 13,500
84 Stop Kontak Setara BROCO bh 14,000
85 Saklar 4 gang Setara HAGER bh 53,750
86 Saklar 5 gang Setara HAGER bh 73,125
87 Saklar 6 gang Setara HAGER bh 165,625
88 Saklar 8 gang Setara HAGER bh 226,250
89 Ohm Saklar bh 203,000
89 Tiang Listrik bh 7,250,000
90 Trafo 80 Watt / 220 bh 580,000
91 Conduit 5/8" m' 4,200
92 Duradoos 9x9cm bh 18,000
93 Fuse 4 A set 16,940
94 inbow panasonics bh 4,200
95 Outlet Tv + Instalasi Set 250,000
96 Exhaust Fan 8 inch unit 280,000
AC 1 pk daikin Set 6,250,000
P. BAHAN ALAT PENGANTUNG DAN KUNCI

1 Kunci dan handle Pintu Digital Otomatis setara YALE Set 6,897,000
2 Kunci dan Handle Pintu Alumunium setara DEKSON, SOLID Set 630,000
3 Kunci silinder Pintu Alumunium setara DEKSON, SOLID bh 185,000
4 Kunci tanam 2 Slaag (kualitas biasa/kecil) setara ANCHOR, ROYAL, TOP, ISO bh 80,000
5 Kunci tanam 2 Slaag (kualitas sedang/besar, antsetara TESA, Set 184,000
6 Kunci Tanam 2 Slaag (kualitas tinggi/besar) setara YALE, SOLID, SEIS set 483,000
7 Kunci KM Bulat (kualitas biasa) bh 55,000
8 Kunci KM Bulat (kualitas sedang) setara BELOCA, BOSSINI, BELUCI bh 95,700
9 Kunci KM Bulat (kualitas tinggi) setara DEKSON, SOLID bh 126,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
10 Kunci Gembok Besar bh 97,750
11 Kunci Lemari setara HUBEN, 808 bh 17,250
12 Rel Pintu Geser /Pintu Marathon setara HENDERSON bh 483,000
13 Espangolet (kualitas biasa) silver /kuningan psg 82,000
14 Espangolet (kualitas sedang/tinggi) stainless steel bh 115,500
15 Casement handle bh 45,000
16 Grendel 2 " (5 cm) setara BELOCA bh 20,600
17 Grendel 4" (10 cm) setara BINOCHE bh 23,800
18 Grendel 6" (15 cm) setara BINOCHE bh 27,100
19 Grendel 10" (25 cm) setara BOLZANO bh 46,500
20 Hak Angin Kait Jendela Biasa Silver ps 11,000
21 Hak Angin Sendok Stainless / Kuningan bh 33,000
22 Hak Angin Jendela Antik ps 44,000
23 Kait angin Aluminium Psg 155,600
24 Sloot Pintu (model pengikat rantai) setara : DEKSON, SOLID bh 90,300
25 Sloot Pintu (model pengikat batang) setara : KENMASTER bh 37,600
26 Sloot Jendela Tunggal bh 28,750
27 Sloot Handle Jendela bh 37,950
28 Rambuncis Handle bh 12,000
29 Engsel Pintu Garasi Lipat Besi / Kayu setara HENDERSON bh 184,000
30 Engsel Pintu Stainless Steel 3" setara : DEKSON, SOLID, HINGE ps 40,250
31 Engsel Pintu Stainless Steel 4" setara : DEKSON, SOLID, HINGE bh 25,875
32 Engsel Pintu Jendela Silver /Gold 3" setara : HPP, ESSEN, ps 20,125
33 Engsel Pintu Jendela Silver /Gold 4" setara : HPP, ESSEN, ps 28,175
34 Engsel Jendela setara : HPP, ESSEN, ps 17,250
35 Engsel Harmonika psg 27,500
36 Engsel Lantai (Floor Hinge) setara : DEKSON Psg 2,172,500
37 Engsel Lantai (Floor Hinge) setara : DORMA Psg 3,245,000
38 Door Closer Standard (Biasa) setara : BELLUCI, SAFILO unt 172,500
39 Door Closer Standard (Sedang) setara : DEKKSON, DORMA unt 287,500
40 Door Closer Standard (Tinggi) setara : DEKKSON, DORMA unt 753,250
41 Door Holder unt 17,250
42 Door Stoper Minimalis, Stainless Steel unt 23,000
43 Tarikan Pintu (Standard /Biasa) Aluminium psg 75,000
44 Tarikan Pintu (Standard /Biasa) Stainless Steel psg 355,000
45 Tarikan Laci/Lemari Standard (Biasa) Antik, Kuning bh 3,450
46 Tarikan Laci/Lemari Standard (Sedang) Minimalis, Silver bh 20,125
47 Tarikan Laci/Lemari Standard (Tinggi) Minimalis, Stainless Steel bh 28,750
48 Karet Accesoris Kusen/Pintu Aluminium m' 30,600
49 Pas. Sticker Sandblast terpasang m2 150,000
50 Hand rails/grab bar KM/WC 40 cm Stainless Steel bh 145,000
Q. BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN

1 Aspal Bitumen kg 55,775


2 Asphal Concrete (ATB) AC-BC ton 1,766,032
3 Aspal Concrete / Laston (AC -WC) ton 1,798,282
4 Lataston / Hot Rolls Sheet ( HRS ) ton 1,888,807
5 Aspal Threated Base ( ATB ) ton 1,506,097
6 Asphal Concrete (ATB) AC Base ton 1,397,511
7 Lapis Resap Pengikat (Prime Coat) liter 16,675
8 Lapis Perekat (Tack Coat) liter 15,525

R. SEWA PERALATAN BERAT

a). SEWA ALAT


1 Asphalt Mixing Plant E01.a. (Kapasitas <30 Ton/Jam) Jam 5,220,000
E01.b. (Kapasitas >30 Ton/Jam) Jam 5,223,000
2 Asphalt Finisher E02 Jam 211,000
3 Asphal Sprayer E03 Jam 76,000
4 Bulldozer 100-150 HP E04 Jam 359,000
5 Compressor 4000-6500 L/M E05 Jam 225,000
6 Concrete Mixer 0.3-0.6 M3 E06 (Site Mix) Jam 70,000
7 Crane 10-15 Ton E07 Jam 411,000
8 Dump Truck 3.5 Ton E08 Jam 276,000
9 Dump Truck 4-6 Ton E09.a. (Kapasitas 4-6 Ton) Jam 343,000
10 Dump Truck 6-8 Ton E09.b. (Kapasitas 6-8 Ton) Jam 346,000
11 Dump Truck 8-10 Ton E09.c. (Kapasitas 8-10 Ton) Jam 347,000
12 Excavator 80-140 HP E10 Jam 413,000
13 Flat Bed Truck 3-4 M3 E11 Jam 554,850
14 Generator Set (Genset) E12.a. (Kapasitas <250 KVA) Jam 423,000
15 Generator Set (Genset) E12.b. (Kapasitas >250 KVA) Jam 464,000
16 Motor Grader > 100 HP E13 Jam 369,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
17 Track Loader 75-100 HP E14 Jam 330,017
18 Wheel Loader 1.0-1.6 M3 E15 Jam 316,000
19 Three Wheel Roller 6-8 T E16 Jam 193,000
20 Tandem Roller 6-8 T E17 Jam 251,000
21 Tire Roller 8-10 T E18 Jam 259,000
22 Vibratory Roller 5-8 T E19 Jam 241,000
23 Concrete Vibrator E20 Jam 49,000
24 Stone Crusher E21 (kapasiotas <60 Ton/Jam) Jam 681,000
25 Water Pump 70-100 mm E22 Jam 39,000
26 Water Tanker 3000 - 4500 L E23 Jam 273,000
27 Pedestrian Roller E24 Jam 55,000
28 Stamper E25 Jam 38,000
29 Jack Hammer E26 Jam 33,000
30 Concrete Pump E28 Jam 378,000
31 Crane 10-15 Ton E31 Jam 411,000
32 Mesin Las /Welding Set E32 Jam 407,000
33 Truck Concrete Mixer /Readymix E49 Jam 360,000
34 Pick Up E54 Jam 175,000
35 Alat Pancang + Hidrolik unit/hari 180,000
36 Alat Penyambung Tiang Pancang bh 200,000

S. BAHAN BAKAR DAN PELUMAS

1 Minyak Tanah liter 12,610


2 Kayu Bakar dari Kayu Karet m3 200,000
3 Bahan Bakar Residu lt 9,300
4 Minyak Solar lt #VALUE!
5 Bensin Premium lt #VALUE!
6 Plus Oil lt 62,000
7 Oil Mesran 40 SAE lt 62,000
8 Elpiji / botol 15 kg 190,900
9 Karbit kg 19,400
10 Soda Api kg 45,400
11 Sabun kg 11,100
12 Arang Kayu kg 12,000

T. BAHAN PENGISAP AIR SUMUR DALAM

1 Pompa Air Manual Tipe Kodok /Hijau, Stara DRAGON unit 299,500
2 Pompa Air Manual Tipe Kodok /Biru, Stara DRAGON unit 495,750
3 Mesin Pompa Air 100 W-125 W Kualitas : Sanyo, Wasser, Shimizu unit 618,200
4 Mesin Pompa Air 200 W-250 W Kualitas : Sanyo, Wasser, Shimizu unit 823,900
5 Pompa Jet Pump 200 W-250 W Kualitas : Sanyo, Wasser, Shimizu unit 2,374,675
6 Pompa Jet Pump 450 W-500 W Kualitas : Grundfos, Wasser, Shimizu unit 3,980,000
7 Pompa Submersible (Deep Well Pump) Kapasitas
Kualitas : Grundfos, Franklin, York unit 35,922,700
8 Pompa Celup (Dipping Pump) non-automatic Kualitas : Karcher, Pedrolo, Wasser, Shimi unit 1,236,250
9 Pompa Celup (Dipping Pump) aotomatic Kualitas : Karcher, Pedrolo, Wasser, Shimi unit 2,687,500
10 Gear Pump Kapasitas 60 liter / menit unit 26,875,600
11 Deep Well (Sumur Dalam) Kelengkapannya kapasitas 150 liter/ meni unit 415,250,000
12 Hand Oil Pump unit 7,778,500

U. BAHAN PENAMPUNG AIR

1 Tangki Air Plastik 250 lt (0,25m3) Bulat, (Excel, Penguin, Profil Tank) bh 700,000
2 Tangki Air Plastik 500 lt (0,5m3) Bulat, (Excel, Penguin, Profil Tank) bh 1,100,000
3 Tangki Air Plastik 1.000 lt (1m3) Bulat, (Excel, Penguin, Profil Tank) bh 1,762,500
4 Tangki Air Plastik 1.500 lt (1,5m3) Bulat, (Excel, Penguin, Profil Tank) bh 2,662,500
5 Tangki Air Plastik 2.000 lt (2m3) Bulat, (Excel, Penguin, Profil Tank) bh 3,437,500
6 Tangki Air Plastik 500 lt (0,5m3) Kubus, (Penguin, Profil Tank) bh 1,812,500
7 Tangki Air Plastik 1.000 lt (1m3) Kubus, (Penguin, Profil Tank) bh 3,312,500
8 Tangki Air Fiber Glass 0.5 m3 ( Excel ) Bulat/Kubus, (Excel, Penguin) bh 1,164,000
9 Tangki Air Fiber Glass 1 m3 ( Excel ) Bulat/Kubus, (Excel, Penguin) bh 1,862,500
10 Tangki Air Fiber Glass 2 m3 ( Excel ) Bulat/Kubus, (Excel, Penguin) bh 3,569,800
11 Tangki Stanless Steel 600 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 1,666,900
12 Tangki Stanless Steel 800 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 1,666,900
13 Tangki Stanless Steel 1000 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 1,927,700
14 Tangki Stanless Steel 1500 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 1,927,700
15 Tangki Stanless Steel 2100 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 3,911,200
16 Tangki Stanless Steel 5000 Liter (Tanpa Kaki) Bulat, (Excel, Penguin /setara) unit 22,740,400
17 Tangki Stanless Steel 660 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 3,167,000
18 Tangki Stanless Steel 800 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 3,848,200
19 Tangki Stanless Steel 1100 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 4,541,400
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
20 Tangki Stanless Steel 1500 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 6,190,700
21 Tangki Stanless Steel 2300 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 10,795,100
22 Tangki Stanless Steel 3200 Liter (Pakai Kaki) Bulat, (Excel, Penguin /setara) unit 15,254,000
23 Tangki Tanam 550 Liter (Dengan Pelindung BetBulat/Kubus, (Excel, Penguin/Setara) unit 2,132,500
24 Tangki Tanam 1100 Liter (Dengan Pelindung BeBulat/Kubus, (Excel, Penguin/Setara) unit 3,984,200
25 Tangki Tanam 2100 Liter (Dengan Pelindung BeBulat/Kubus, (Excel, Penguin/Setara) unit 7,689,100
26 Tangki Tanam 2500 Liter (Dengan Pelindung BeBulat/Kubus, (Excel, Penguin/Setara) unit 9,883,700
27 Tangki Tanam 550 Liter (Langsung Pendam) Bulat/Kubus, (Excel, Penguin/Setara) unit 2,132,500
28 Tangki Tanam 1100 Liter (Langsung Pendam) Bulat/Kubus, (Excel, Penguin/Setara) unit 3,984,200
29 Tangki Horisontal 1000 iter (Dengan kaki) Bulat, (Excel, Penguin/Setara) unit 4,068,000
30 Tangki Horisontal 5000 iter (Dengan kaki) Bulat, (Excel, Penguin/Setara) unit 16,680,000

V. ALAT TUKANG

1 Gergaji Gagang Karet Setara TEKIRO Bh 96,800


2 Ember Cor Beton Kecil Bahan Plastik Hitam Setara SINAR Bh 44,000
3 Ember Air Besar Bahan Plastik Warna Setara LIONS Bh 93,500
4 Linggis p=80cm-100 cm Bh 55,000
5 Palu Batu Kecil Gagang Kayu setara JASON Bh 99,000
6 Palu Batu Besar Gagang Kayu setara JASON Bh 154,000
7 Cangkul /Pacul Kecil Gagang Kayu Setara CAP BUAYA Bh 60,500
8 Cangkul /Pacul Besar Gagang Kayu Setara CAP BUAYA Bh 99,000
9 Sekop Gagang besi setaraTORA Bh 99,000
10 Singkup bh 90,304
11 Pengki bh 21,165
12 Garpu Bh 99,000
13 Gacok Bh 50,050
14 Parang Bh 95,700

W. BIDANG LAINNYA

1 Lampu Senter Re-Charger Bh 82,500


2 Rantai Kunci kg 38,225
3 Sabuk Pengaman Bh 91,245
4 Waterpass Level Bahan aluminium setara SELLERY Bh 73,700
5 Tambang Plastik kg 49,500
6 Takel ( Kapasitas 3 Ton ) Bh 1,925,000
7 Stempet (Grease) kg 55,000
8 Slang waterpass Bahan plastik bening Ø1/2 cm m' 5,500
9 Slang outlet pompa air irigasi Bahan terpal Ø 3" Setara KATO m' 19,250
10 Slang inlet pompa air irigasi Bahan PVC Ø 3" m' 104,500
11 Mesin Babad Rumput Gendong Kualitas : HONDA, TANAKA Bh 3,795,000
12 Mesin Babad Rumput Dorong Kualitas : HONDA, MAKITA Bh 10,945,000
13 Mesin rooling door otomatis unit 17,600,000
14 Mesin Sliding door otomatis unit 4,600,000
14 Papan Nama Bangunan / Nomenklatur bh 1,106,784
15 Papan Nama Saluran bh 1,165,500
16 Papan Oprasi Bendung bh 1,106,784
17 Papan Exploitasi bh 1,148,700
18 Kotak Baja Penyimpan Data bh 228,900
19 Plat Tanda Muka Air / Peil Schaal bh 256,100
20 Patok Hektometer ( Pengairan ) bh 180,700
21 Roll meter (Besar /panjang) Bahan plastik, P=50 m s/d 60 m bh 126,500
22 Roll meter (Kecil /pendek) Bahan logam, P=3 m s/d 5 m bh 27,500
23 Prasasti Marmer Bahan dan tulisan gravier m2 1,375,000
24 Prasasti Granit Hitam Bahan dan tulisan gravier m2 2,750,000
25 Pintu Angkat Type 1.B = 0.30 meter bh 1,604,010
26 Pintu Angkat Type 1.B = 0.40 meter bh 1,882,140
27 Pintu Angkat Type 1.B = 0.50 meter bh 2,640,330
28 Pintu Angkat Type II.B = 0.30 meter bh 1,604,010
29 Pintu Angkat Type II.B = 0.40 meter bh 2,467,610
30 Pintu Angkat Type II.B = 0.50 meter bh 2,786,380
31 Pintu Sorong baja type 1A Uk/ (B=0.30-0.60)&(H=0.30-0.60) m bh 4,610,100
32 Pintu Sorong baja type 2A Uk/ (B=0.60-0.80)&(H=0.30-1.00) m bh 9,220,200
33 Pintu Sorong baja type 3A Uk/ (B=0.30-1.20)&(H=0.40-1.50) m bh 11,986,260
34 Pintu Sorong baja type 4A Uk/ (B=1.00-1.00)&(H=0.50-2.00) m bh 14,137,640
35 Pintu Sorong baja type 5A Uk/ (B=1.00-1.50)&(H=0.70-0.90) m bh 15,858,490
36 Pintu Sorong baja type 6A Uk/ (B=1.60-2.00)&(H=0.90-1.35) m bh 16,582,390
37 Pintu Sorong baja type 7A Uk/ (B=2.10-2.50)&(H=1.35-1.70) m bh 18,196,560
38 Pintu sorong baja type 2 draadstang U'lir dengan 3 stel roda gigi b = 1.00 m; bh 58,533,750
39 Pintu sorong baja type 2 draadstang Ulir dengan 3 stel roda gigi b = 1.20 m;H bh 66,890,000
40 Pintu sorong baja type 2 draadstang Ulir dengan 3 stel roda gigi b = 1.50 m;H bh 87,447,500
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
41 Pintu sorong baja type 2 draadstang Ulir dengan 3 stel roda gigi b = 2.00 m;H bh 96,978,750
42 Mistar Ukuran Panjang (feil schal) Panjang 0.50 - 1.00 meter bh 64,530
43 Mistar Ukuran Panjang (feil schal) Panjang 1.00 - 1.50 meter bh 230,584
44 Mistar Ukuran Panjang (feil schal) Panjang 1.50 - 2.00 meter bh 421,788
45 Mistar Ukuran Panjang (feil schal) Panjang 2.00 - 3.00 meter bh 801,736
46 Mistar Ukuran Panjang (feil schal) Panjang 3.00 - 4.00 meter bh 994,172
47 Karet Penyekat /Rubber Water Stop Bahan Karet, Lebar 150 cm m 246,750
48 Karet Penyekat /Rubber Water Stop Bahan Karet, Lebar 225 cm m 338,100
49 Pintu Skot Balk Jati Jateng bh 46,352,460
50 Pintu Skot Balk Jati Jabar bh 31,348,680

X. TAMBAHAN DAFTAR HARGA BAHAN

a) Semen Instam /MU

1 Semen Instan /MU-100 Plester Premium 40 kg 69,000


2 Semen Instan /MU-200 Acian Plester & Beton 40 kg 182,275
3 Semen Instan /MU-260 Acian Profil 25 kg 219,075
4 Semen Instan /MU-270 Acian Putih 25 kg 179,400
5 Semen Instan /MU-300 Pasangan Bata 40 kg 58,075
6 Semen Instan /MU-301 Pas Bata & Plester 40 kg 66,125
7 Semen Instan /MU-380 Perekat Bata Ringan 40 kg 172,500
8 Semen Instan /MU-400 Perekat Keramik Dinding 5 kg 40,250
9 Semen Instan /MU-410 Self Leveling Floor 25 kg 293,250
10 Semen Instan /MU-440 Perata Lantai 40 kg 63,250
11 Semen Instan /MU-445 Perata Lantai Premium 40 kg 120,750
12 Semen Instan /MU-450 Perekat Keramik Lantai 40 kg 235,750
13 Semen Instan /MU-460 Perekat Keramik Daerah Basah 25 kg 504,275
14 Semen Instan /MU-470 White Tile Addesive 25 kg 442,750
15 Semen Instan /MU-480 Perekat Keramik diatas Keramik 5 kg 86,825
16 Semen Instan /MU-L500 Perekat Mortar & Beton 2 kg 236,325
17 Semen Instan /MU-600 Pelapis Kedap Air 30 kg 1,242,575
18 Semen Instan /MU-700 Floor Hardener 25 kg 161,575
19 Semen Instan /MU-800 Non-Shrink Grout 40 kg 180,550
20 Semen Instan /MU-830 Perbaikan Permukaan Beton 40 kg 302,450
21 Semen Instan /MU-840 Finish Coat Repair 25 kg 373,750

b) Bahan Acrylic

1 ACRYLIC 1,5 MM – 1 x 2 BENING LB 235,000


2 ACRYLIC 2 MM – 4 x 8 BENING LB 377,000
3 ACRYLIC 2 MM – 4 x 8 BIRU (327) LB 477,000
4 ACRYLIC 2 MM – 4 x 8 DOP LB 400,000
5 ACRYLIC 2 MM – 4 x 8 HIJAU (348), HITAM (502), KUNING (235) LB 485,000
6 ACRYLIC 2 MM – 4 x 8 SUSU LB 389,000
7 ACRYLIC 2 MM – 1 x 2 BENING LB 262,000
8 ACRYLIC 2 MM – 1 x 2 DOP LB 277,000
9 ACRYLIC 2 MM – 1 x 2 ORANGE (266) LB 325,000
10 ACRYLIC 2 MM – 1 x 2 SUSU LB 267,000
11 ACR. 2 MM -3×6 RYB BIRU 302, HIJAU 362, KUNING 212, MERA LB 280,000
12 ACR. 2 MM -3×6 SCOT HIJAU 993, SCOT ORANGE 994, SCO LB 300,000
13 ACRYLIC 2 MM – 3 x 6 BENING LB 222,000
14 ACRYLIC 2 MM – 3 x 6 BIRU (322) LB 280,000
15 ACRYLIC 2 MM – 3 x 6 BIRU (327) LB 270,000
16 ACRYLIC 2 MM – 3 x 6 DOP LB 225,000
17 ACRYLIC 2 MM – 3 x 6 HIJAU (348), HITAM (502), KUNING (235) LB 270,000
18 ACRYLIC 2 MM – 3 x 6 SUSU LB 217,000
19 ACRYLIC 3 MM JUMBO BENING, JUMBO SUSU LB 1,235,000
20 ACRYLIC 3 MM – 4 x 8 BENING LB 527,000
21 ACRYLIC 3 MM – 4 x 8 BIRU (327) LB 675,000
22 ACRYLIC 3 MM – 4 x 8 DOP LB 569,000
23 ACRYLIC 3 MM – 4 x 8 HIJAU (348), HITAM (502), KUNING (235) LB 675,000
24 ACRYLIC 3 MM – 4 x 8 SUSU LB 543,000
25 ACRYLIC 3 MM – 1 x 2 BENING LB 357,000
26 ACRYLIC 3 MM – 1 x 2 DOP LB 382,000
27 ACRYLIC 3 MM – 1 x 2 SUSU LB 369,000
28 ACRYLIC 3 MM – 3 x 6 BENING LB 303,000
29 ACRYLIC 3 MM – 3 x 6 BIRU (322), BIRU (324), BITU, (327) LB 385,000
30 ACRYLIC 3 MM – 3 x 6 DOP LB 322,000
31 ACRYLIC 3 MM – 3 x 6 HIJAU (367) HIJAU (367), hijau tua (348), HITAM (5 LB 385,000
32 ACRYLIC 3 MM – 3 x 6 SUSU LB 312,000
33 ACRYLIC 4 MM – JUMBO BENING, LB 1,605,000
NO BAHAN / MATERIAL SPESIFIKASI BAHAN/PENGGUNAAN SAT SATUAN HARGA
Column1 Column2 Column3 Column4 Column5
34 ACRYLIC 4 MM – 4 x 8 BENING LB 709,000
35 ACRYLIC 4 MM – 4 x 8 SUSU LB 732,000
36 ACRYLIC 4 MM – 1 x 2 BENING LB 477,000
37 ACRYLIC 4 MM – 3 x 6 BENING LB 403,000
38 ACRYLIC 4 MM – 3 x 6 SUSU LB 413,000
39 ACRYLIC 5 MM – 4 x 8 BENING LB 871,000
40 ACRYLIC 5 MM – 4 x 8 BIRU (327) LB 1,075,000
41 ACRYLIC 5 MM – 4 x 8 DOP LB 932,000
42 ACRYLIC 5 MM – 4 x 8 HITAM (502), MERAH (135) LB 1,075,000
43 ACRYLIC 5 MM – 4 x 8 SUSU LB 897,000
44 ACRYLIC 5 MM – 1 x 2 BENING LB 585,000
45 ACRYLIC 5 MM – 1 x 2 DOP LB 627,000
46 ACRYLIC 5 MM – 1 x 2 SUSU LB 602,000
47 ACRYLIC 5 MM – 3 x 6 BENING LB 492,000
48 ACRYLIC 5 MM – 3 x 6 BIRU (327) LB 625,000
49 ACRYLIC 5 MM – 3 x 6 DOP LB 527,000
50 ACRYLIC 5 MM – 3 x 6 HITAM (502), MERAH (135) LB 625,000
51 ACRYLIC 5 MM – 3 x 6 SUSU LB #VALUE!
52 ACRYLIC 6 MM – 4 x 8 BENING LB 1,045,000
53 ACRYLIC 6 MM – 4 x 8 SUSU LB 1,075,000
54 ACRYLIC 6 MM – 3 x 6 BENING LB 590,000
55 ACRYLIC 6 MM – 3 x 6 SUSU LB 609,000
56 ACRYLIC 8 MM – 4 x 8 BENING LB 1,393,000
57 ACRYLIC 8 MM – 4 x 8 SUSU LB 1,435,000
58 ACRYLIC 8 MM – 1 x 2 BENING LB 937,000
59 ACRYLIC 8 MM – 3 x 6 BENING LB 787,000
60 ACRYLIC 8 MM – 3 x 6 SUSU LB 811,000
61 ACRYLIC 10 MM – 4 x 8 BENING LB 1,725,000
62 ACRYLIC 10 MM – 4 x 8 SUSU LB 1,779,000
63 ACRYLIC 10 MM – 1 x 2 BENING LB 1,170,000
64 ACRYLIC 10 MM – 1 x 2 SUSU LB 1,205,000
65 ACRYLIC 10 MM – 3 x 6 BENING LB 985,000
66 ACRYLIC 10 MM – 3 x 6 SUSU LB 1,015,000
67 ACRYLIC GB 2 MM – 4 x 8 BENING LB 355,000
68 ACRYLIC GB 2 MM – 4 x 8 SUSU LB 365,000
69 ACRYLIC GB 3 MM – 4 x 8 BENING LB 515,000
70 ACRYLIC GB 3 MM – 4 x 8 SUSU LB 520,000
71 ACRYLIC GB 3 MM – 1 x 2 BENING LB 345,000
72 ACRYLIC GB 5 MM – 4 x 8 BENING LB 850,000
73 ACRYLIC GB 5 MM – 4 x 8 SUSU LB 870,000
74 NOZZEL KOMET BH 402,500
75 NOZZEL CEMARA BH 1,006,250
76 NOZZEL BEBEK BH 345,000
77 POMPA AIR SUMER SIBLE (3PK) BH 17,250,000
78 LAMPU DONAT LED BH 1,138,500
PERHITUNGAN BIAYA SMK3 KONSTRUKSI BANGUNAN

Asumsi - Asumsi
Nilai Pekerjaan : 5,419,963,845 Rupiah
Jumlah Pekerja : 50 Orang
Jangka Waktu : 150 Hari Kalender

HARGA
NO URAIAN SAT VOL TOTAL HARGA KET
SATUAN

1 Sosialisasi dan Promosi K3 terdiri atas:


b Pengarahan K3 (safety briefing) : Pertemuan Org 50.00 10,000 500,000
g Keselamatan (Safety
Papan Informasi K3. Talk dan/atau Tool Box Meeting) Bh 1.00 60,000 60,000

2 Alat Pelindung Diri terdiri atas:


a Topi Pelindung (Safety Helmet) ; Bh 50.00 65,000 3,250,000
b Pelindung Pernafasan Dan Mulut (Masker); Bh 50.00 4,500 225,000
c Sarung Tangan (Safety Gloves); Psg 50.00 7,500 375,000
d Rompi Keselamatan (Safety Vest); Bh 50.00 50,000 2,500,000
e Desinfektan ltr 5.00 280,000 1,400,000
f Handsanitizer ltr 5.00 40,000 200,000

3 Asuransi Dan Perijinan terdiri atas :


a BPJS Ketenagakerjaan Dan Kesehatan Kerja; Ls 1.00 6,465,500 6,465,500

4 Fasilitas sarana kesehatan :


a Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Ls 1.00 85,000 85,000

5 Rambu- Rambu terdiri atas :


a Rambu Peringatan; Bh 4.00 15,000 60,000
b Rambu Informasi; Bh 4.00 15,000 60,000

JUMLAH 15,180,500
2021

Column1 Column2
1.1.7.01.01.01.005.00016 Abu Batu
1.1.7.01.01.01.022.00168 Acustik Amstrong
1.1.7.01.01.02.001.00047 Ag2SO4
1.1.7.01.01.01.022.00538 Air Valve
1.1.7.01.01.02.001.00049 Alkalin Sitrat
1.1.7.01.01.02.002.00081 Alkaline Cyanide Reagent
1.1.7.01.01.02.002.00082 Alkohol
1.1.7.01.01.01.022.00605 Aluminium Foil Laminated
1.1.7.01.01.01.022.00606 Aluminium Foil Laminated
1.1.7.01.01.01.022.00607 Aluminium Foil Laminated
1.1.7.01.01.02.005.00038 Ammonium Heptamolybdate Tetrahydrate Ar 500 Gr, Prolabo
1.1.7.01.01.02.005.00039 Ammonium Molybdate Ar 1000 Gr, Smartlab
1.1.7.01.01.02.001.00052 Amonium Klorida
1.1.7.01.01.01.022.00121 Ampelas
1.1.7.01.01.01.022.00378 Angker Mur Baut Ø 19 / Panjang 60 cm
1.1.7.01.01.01.022.00561 Apooer Bath Tube
1.1.7.01.01.02.002.00071 Aquadest
1.1.7.01.01.01.022.00682 Arde /box schreeng
1.1.7.01.01.02.001.00032 Ascorbic Acid Powder Pillows pkg/100 (100 test)
1.1.7.01.01.01.001.00009 Aspal
1.1.7.01.01.01.001.00010 Aspal
1.1.7.01.01.01.001.00011 Aspal
1.1.7.01.01.01.001.00012 Aspal
1.1.7.01.01.01.022.00752 Aspal Bitumen
1.1.7.01.01.01.001.00013 Aspal Concrete / Laston (AC -WC)
1.1.7.01.01.01.001.00017 Aspal Curah
1.1.7.01.01.01.001.00020 Aspal Curah
1.1.7.01.01.01.001.00023 Aspal Curah
1.1.7.01.01.01.001.00026 Aspal Curah
1.1.7.01.01.01.001.00018 Aspal Drum 155 kg
1.1.7.01.01.01.001.00021 Aspal Drum 155 kg
1.1.7.01.01.01.001.00027 Aspal Drum 155 kg
1.1.7.01.01.01.001.00019 Aspal Minyak
1.1.7.01.01.01.001.00022 Aspal Minyak
1.1.7.01.01.01.001.00025 Aspal Minyak
1.1.7.01.01.01.001.00028 Aspal Minyak
1.1.7.01.01.01.001.00014 Aspal Threated Base ( ATB )
1.1.7.01.01.01.001.00015 Asphal Concrete (ATB) AC Base
1.1.7.01.01.01.022.00753 Asphal Concrete (ATB) AC-BC
1.1.7.01.01.01.022.00601 Atap Aluminium Natura USR 26
1.1.7.01.01.01.022.00602 Atap Aluminium Warna USR 26
1.1.7.01.01.01.022.00604 Atap Asbes Gelombang Besar
1.1.7.01.01.01.022.00603 Atap Asbes Gelombang Kecil
1.1.7.01.01.01.022.00633 Atap Bitumen Monolayer 3 mm
1.1.7.01.01.01.022.00634 Atap Bitumen Monolayer 3 mm
1.1.7.01.01.01.022.00635 Atap Bitumen Monolayer 3 mm
1.1.7.01.01.01.022.00600 Atap Fiber Glass 80 x 180 (tebal)
1.1.7.01.01.01.022.00599 Atap Fiber Glass 80 x 180 (tipis)
1.1.7.01.01.01.014.00021 Atap Genteng Flam
1.1.7.01.01.01.014.00019 Atap Genteng Plentong
1.1.7.01.01.01.014.00020 Atap Genteng Plentong
1.1.7.01.01.01.022.00598 Atap Plastik Gelombang 80 x 180
1.1.7.01.01.01.007.00014 Atap Seng Gelombang
1.1.7.01.01.01.007.00015 Atap Seng Gelombang
1.1.7.01.01.01.007.00016 Atap Seng Gelombang
1.1.7.01.01.01.007.00017 Atap Seng Gelombang
1.1.7.01.01.01.022.00620 Atap Spandek
1.1.7.01.01.01.022.00636 Atap Transparat /clair gelombang
1.1.7.01.01.01.022.00637
100 Atap Transparat /clair tile
1.1.7.01.01.01.022.00640 Atap UPVC (Semi Transparan, tebal 10mm)
1.1.7.01.01.01.022.00639 Atap UPVC (White /Blue Doff, tebal 10mm)
1.1.7.01.01.01.022.00619 Atap Zingkalum
1.1.12.01.03.0013.00020 Bahan Pelatihan Las Listrik
1.1.7.01.01.01.022.00107 Bahan Pelitur Kripik (Sirlak India)
1.1.7.01.01.01.022.00572 Bak KM Fiber 60 x 60
1.1.7.01.01.01.022.00529 Ball Valve 32mm
1.1.7.01.01.01.022.00528 Ball Valve 63mm
1.1.7.01.01.01.022.00130 Bambu
1.1.7.01.01.01.022.00131 Bambu
1.1.7.01.01.01.022.00132 Bambu Gombong
1.1.7.01.01.01.022.00133 Bambu Gombong
1.1.7.01.01.01.022.00052 Barang Lainnya
1.1.7.01.01.01.022.00825 Barang Lainnya
1.1.7.01.01.01.022.00059 Bata Merah Bakar Kelas I
1.1.7.01.01.01.022.00060 Bata Merah Bakar Kelas II
1.1.7.01.01.01.022.00061 Bata Merah Oven (Klingker)
1.1.7.01.01.01.022.00062 Bata Ringan
1.1.7.01.01.01.022.00057 Batako Besar
1.1.7.01.01.01.022.00056 Batako Kecil
1.1.7.01.01.01.022.00571 Bath Cape Washteren
1.1.7.01.01.01.005.00023 Batu Belah Pondasi
1.1.7.01.01.01.005.00024 Batu Bronjol (Untuk Bronjong)
1.1.7.01.01.02.005.00212 Batu Didih (Glass Beads) 2 Mm, 500 Gr
1.1.7.01.01.01.005.00017 Batu Gosok (Apung)
1.1.7.01.01.01.005.00025 Batu Koral Beton Kali
1.1.7.01.01.01.005.00018 Batu Pecah Mesin 0,5/1
1.1.7.01.01.01.005.00019 Batu Pecah Mesin 1/2
1.1.7.01.01.01.005.00020 Batu Pecah Mesin 2/3
1.1.7.01.01.01.005.00021 Batu Pecah Mesin 3/5
1.1.7.01.01.01.005.00022 Batu Pecah Mesin 5/7
1.1.7.01.01.01.005.00028 Batu Pinggir Beton
1.1.7.01.01.01.005.00029 Batu Pinggir Beton
1.1.7.01.01.01.005.00030 Batu Telor
1.1.7.01.01.01.005.00026 Batu Tempel Hitam
1.1.7.01.01.01.005.00027 Batu Tempel Hitam
1.1.7.01.01.01.022.00372 Baut Anker
1.1.7.01.01.01.022.00373 Baut Besar
1.1.7.01.01.01.022.00374 Baut Kecil
1.1.7.01.01.02.002.00105 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.02.002.00106 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.02.002.00107 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.02.002.00108 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.02.002.00109 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.02.002.00110 Belanja Bahan Kimia (Reagen)
1.1.7.01.01.01.022.00847 Belanja Modal Kanopi
1.1.7.01.01.01.022.00534 Bend All Flange 45 derajat
1.1.7.01.01.01.022.00535 Bend All Flange 90 derajat
1.1.7.01.01.01.022.00469 Bend all flange Dia. 40 mm - 90 drj
1.1.7.01.01.01.022.00467 Bend all flange Dia. 50 mm - 45 drj
1.1.7.01.01.01.022.00468 Bend all flange Dia. 50 mm - 90 drj
1.1.7.01.01.01.022.00465 Bend all flange Dia. 63 mm - 90 drj
1.1.7.01.01.01.022.00466 Bend all flange Dia. 75 mm - 45 drj
1.1.7.01.01.01.022.00480 Bend PVC Socket Spigot Dia. 63 mm - 45 drj,
1.1.7.01.01.01.022.00479 Bend PVC Socket Spigot Dia. 90 mm - 90 drj, ( Setara Vinillon)
1.1.7.01.01.01.022.00053 Besi
1.1.7.01.01.01.022.00054 Besi
1.1.7.01.01.01.012.00003 Besi Beton
1.1.7.01.01.01.012.00004 Besi Beton
1.1.7.01.01.01.022.00370 Besi Beugeul Kuda-kuda
1.1.7.01.01.01.022.00251 Besi Pipa
1.1.7.01.01.01.022.00391 Besi Pipa Hitam Ø 1" t = 2 mm
1.1.7.01.01.01.022.00392 Besi Pipa Hitam Ø 2" t = 2 mm
1.1.7.01.01.01.022.00393 Besi Pipa Hitam Ø 3" t = 2 mm
1.1.7.01.01.01.022.00394 Besi Pipa Hitam Ø 4" t = 2 mm
1.1.7.01.01.01.022.00395 Besi Pipa Hitam Ø 6" t = 2 mm
1.1.7.01.01.01.022.00383 Besi Pipa untuk Hydrant BSP Ø 1"
1.1.7.01.01.01.022.00384 Besi Pipa untuk Hydrant BSP Ø 1.15"
1.1.7.01.01.01.022.00385 Besi Pipa untuk Hydrant BSP Ø 1.5"
1.1.7.01.01.01.022.00386 Besi Pipa untuk Hydrant BSP Ø 2"
1.1.7.01.01.01.022.00387 Besi Pipa untuk Hydrant BSP Ø 2.5"
1.1.7.01.01.01.022.00388 Besi Pipa untuk Hydrant BSP Ø 3"
1.1.7.01.01.01.022.00389 Besi Pipa untuk Hydrant BSP Ø 4"
1.1.7.01.01.01.022.00390 Besi Pipa untuk Hydrant BSP Ø 6"
1.1.7.01.01.01.022.00247 Besi Plat
1.1.7.01.01.01.022.00246 Besi Profil UNP /CNP
1.1.7.01.01.01.022.00248 Besi Siku
1.1.7.01.01.01.022.00252 Besi Tempa
1.1.7.01.01.01.022.00249 Besi WF /H Beam
1.1.7.01.01.01.022.00250 Besi WF /H Beam
1.1.7.01.01.01.022.00845 Bilik
1.1.7.01.01.01.022.00182 Bilik Bambu (dengan Kulit)
1.1.7.01.01.01.022.00181 Bilik Bambu (Tanpa Kulit)
1.1.7.01.01.01.022.00183 Bilik Bambu Hitam Variasi
1.1.7.01.01.01.022.00178 Blockboard
1.1.7.01.01.01.022.00179 Blockboard
1.1.7.01.01.01.022.00180 Blockboard
1.1.7.01.01.02.001.00023
100 BOD Nutrien Buffer for sampel 300 mL
1.1.7.01.01.01.022.00264 Bondex 0,75
1.1.7.01.01.01.022.00265 Bondex 1,00
1.1.7.01.01.01.022.00684 Bongkar /Pasang Standard + Meteran PLN
1.1.7.01.01.01.022.00820 Box Culvert
1.1.7.01.01.01.022.00821 Box Culvert
1.1.7.01.01.01.022.00822 Box Culvert
1.1.7.01.01.01.022.00823 Box Culvert
1.1.12.01.03.0013.00014 Box Instrumen P3K
1.1.12.01.03.0007.00001 Box Intrumen P3K
1.1.7.01.01.01.022.00512 Box Meter
1.1.7.01.01.01.022.00683 Box Schreeng In-bouw C4
1.1.7.01.01.01.022.00476 Box Street uk. 4"
1.1.7.01.01.02.001.00042 Brilliant Green Lactose Broth
1.1.7.01.01.01.014.00022 Bubung Genteng
1.1.7.01.01.01.022.00613 Bubung Murando Glasur Coklat/Trans
1.1.7.01.01.01.022.00614 Bubung Murando Glasur Warna
1.1.7.01.01.01.022.00612 Bubung Murando Natural
1.1.7.01.01.01.022.00622 Bubungan Atap Spandek
1.1.7.01.01.01.022.00621 Bubungan Atap Zingkalum
1.1.7.01.01.01.022.00615 Bubungan Genteng Keramik
1.1.7.01.01.01.014.00035 Bubungan Genteng Kodok
1.1.7.01.01.01.014.00036 Bubungan Genteng Plentong
1.1.7.01.01.01.022.00616 Bubungan Stel Gelombang
1.1.7.01.01.01.015.00009 Buis Beton
1.1.7.01.01.01.015.00010 Buis Beton
1.1.7.01.01.01.015.00011 Buis Beton
1.1.7.01.01.01.015.00012 Buis Beton
1.1.7.01.01.01.015.00013 Buis Beton
1.1.7.01.01.01.015.00014 Buis Beton
1.1.7.01.01.01.015.00015 Buis Beton
1.1.7.01.01.01.015.00016 Buis Beton
1.1.7.01.01.02.005.00213 Bunsen Spirtus 150 Ml
1.1.7.01.01.02.005.00214 Cairan Pembersih Alat Gelas Ba 10
1.1.7.01.01.02.005.00215 Cairan Pembersih Alat Gelas Ch 53
1.1.7.01.01.01.022.00086 Canstin Paving Blok
1.1.7.01.01.01.022.00718 Casement handle
1.1.7.01.01.01.006.00049 Cat Brom
1.1.7.01.01.01.006.00039 Cat dasar
1.1.7.01.01.01.006.00027 Cat dasar ICI untuk Interior (2 lapis)
1.1.7.01.01.01.006.00041 Cat Genteng
1.1.7.01.01.01.006.00042 Cat Genteng
1.1.7.01.01.01.006.00048 Cat Kayu /Besi
1.1.7.01.01.01.006.00047 Cat Kayu /Besi /Duco
1.1.7.01.01.01.006.00040 Cat Tahan Asam
1.1.7.01.01.01.006.00030 Cat Tembok Catylac exterior
1.1.7.01.01.01.006.00034 Cat Tembok Catylac interior
1.1.7.01.01.01.006.00028 Cat Tembok Dulux exterior
1.1.7.01.01.01.006.00032 Cat Tembok Dulux interior
1.1.7.01.01.01.006.00054 cat tembok eksterior
1.1.7.01.01.01.006.00055 cat tembok eksterior
1.1.7.01.01.01.006.00056 cat tembok eksterior
1.1.7.01.01.01.006.00057 cat tembok eksterior
1.1.7.01.01.01.006.00036 Cat Tembok Metrolite
1.1.7.01.01.01.006.00031 Cat Tembok Metrolite exterior
1.1.7.01.01.01.006.00035 Cat Tembok Metrolite interior
1.1.7.01.01.01.006.00029 Cat Tembok Mowilex exterior
1.1.7.01.01.01.006.00033
100 Cat Tembok Mowilex interior
1.1.7.01.01.01.006.00038 Cat Tembok Sanlex
1.1.7.01.01.01.006.00037 Cat Tembok Vinilex
1.1.7.01.01.01.022.00537 Cek Valve
1.1.7.01.01.01.022.00556 Check Valve 1/2"
1.1.12.01.01.0002.00001 Chlorine / disinfektan 600 ML
1.1.7.01.01.02.001.00024 ChromaVer powder pillow
1.1.7.01.01.02.001.00033 ChromaVer powder pillow
1.1.7.01.01.02.001.00025 Chromocult Mikrobiologi , 100 pcs
1.1.7.01.01.02.001.00034 Chromocult Mikrobiologi , 100 pcs
1.1.7.01.01.01.022.00539 Clamp Sadle OD
1.1.7.01.01.01.022.00595 Clean Out
1.1.7.01.01.02.002.00103 Cleaner
1.1.7.01.01.01.022.00583 Closet Dudduk Ina (Warna Gelap)
1.1.7.01.01.01.022.00582 Closet Duduk KIA
1.1.7.01.01.01.022.00579 Closet Duduk Lengkap
1.1.7.01.01.01.022.00587 Closet Duduk Lengkap
1.1.7.01.01.01.022.00581 Closet Jongkok INA (Wanan gelap)
1.1.7.01.01.01.022.00580 Closet Jongkok KIA
1.1.7.01.01.01.022.00578 Closet Jongkok Lengkap
1.1.7.01.01.01.022.00576 Closet Jongkok Standar
1.1.7.01.01.01.022.00577 Closet Jongkok Standar
1.1.7.01.01.01.022.00058 Con Block 8 x 20 x 40
1.1.7.01.01.01.022.00699 Conduit 5/8"
1.1.7.01.01.01.022.00381 Conection clip
1.1.7.01.01.01.022.00170 Cornice Coumpound
1.1.7.01.01.01.022.00158 Corong talang (nozzle)
1.1.7.01.01.01.022.00159 Corong talang (nozzle)
1.1.7.01.01.01.022.00169 Cotton Plester
1.1.7.01.01.02.005.00086 Crm Cod Standard Solution 100 Mg/l In H2o, 100 Ml, Merck 1.25029.0100
1.1.7.01.01.02.005.00089 Crm Cod Standard Solution 1000 Mg/l In H2o, 100 Ml, Merck 1.25032.0100
1.1.7.01.01.02.005.00087
100 Crm Cod Standard Solution 200 Mg/l In H2o, 100 Ml, Merck 1.25030.0100
1.1.7.01.01.02.005.00090 Crm Cod Standard Solution 2000 Mg/l In H2o, 100 Ml, Merck 1.25033.0100
1.1.7.01.01.02.005.00088 Crm Cod Standard Solution 400 Mg/l In H2o, 100 Ml, Merck 1.25031.0100
1.1.7.01.01.02.005.00091 Crm Nitrate Standard Solution 0.50 Mg/l No3-n In H2o, 100 Ml, Merck 1.25
1.1.7.01.01.02.005.00093 Crm Nitrate Standard Solution 15,0 Mg/l No3-n In H2o, 100 Ml, Merck 1.25
1.1.7.01.01.02.005.00092 Crm Nitrate Standard Solution 2.50 Mg/l No3-n In H2o, 100 Ml Merck 1.250
1.1.7.01.01.02.005.00095 Crm Nitrate Standard Solution 200 Mg/l No3-n In H2o, 100 Ml, Merck 1.250
1.1.7.01.01.02.005.00094 Crm Nitrate Standard Solution 40,0 Mg/l No3-n In H2o, 100 Ml, Merck 1.25
1.1.7.01.01.02.005.00096 Crm Nitrite Standard Solution 0,200 Mg/l No2-n In H2o, 100 Ml, Merck 1.2
1.1.7.01.01.02.001.00026 Cuver 1 Cooper Reagent Powder Pillow For 20 ml
1.1.7.01.01.02.001.00035 Cuver 1 Cooper Reagent Powder Pillow For 20 ml
1.1.7.01.01.02.002.00072 Cycloheksanone 100 mL
1.1.7.01.01.02.002.00083 Cycloheksanone 100 mL
1.1.7.01.01.01.022.00270 Daun Jendela Aluminium Natural
1.1.7.01.01.01.022.00271 Daun Jendela Aluminium Warna
1.1.7.01.01.01.022.00272 Daun Pintu Swing Aluminium Natural
1.1.7.01.01.01.022.00273 Daun Pintu Swing Aluminium Warna
1.1.7.01.01.01.022.00758 Deep Well (Sumur Dalam)
1.1.7.01.01.01.022.00120 Dempul Duco
1.1.7.01.01.01.022.00118 Dempul kayu
1.1.7.01.01.01.022.00108 Dempul Lilin
1.1.7.01.01.01.022.00119 Dempul Plastik /Besi
1.1.7.01.01.01.022.00109 Dempul Plitur
1.1.12.01.01.0004.00001 Dexlite
1.1.7.01.01.01.022.00644 Diesel Pump kap. 750 gln/menit 120 ml (105 kW)
1.1.7.01.01.02.002.00102 Diluent
1.1.7.01.01.01.022.00741 Door Closer Standard (Biasa)
1.1.7.01.01.01.022.00742 Door Closer Standard (Sedang)
1.1.7.01.01.01.022.00743 Door Closer Standard (Tinggi)
1.1.7.01.01.01.022.00744 Door Holder
1.1.7.01.01.01.022.00745 Door Stoper
1.1.7.01.01.01.022.00509 Dop PVC Dia. 20 mm
1.1.7.01.01.01.022.00501 Double Naple Dia. 20 mm
1.1.7.01.01.01.022.00557 Double Neple 1/2"
1.1.7.01.01.02.002.00073 DPD Free Chlorine Reagent Powder Pillows for sa
1.1.7.01.01.01.022.00371 Duk Angker
1.1.7.01.01.01.022.00700 Duradoos 9x9cm
1.1.7.01.01.02.001.00027 EDTA Reagent Powder Pillow, 100/pkg,
1.1.7.01.01.02.001.00036 EDTA Reagent Powder Pillow, 100/pkg,
1.1.7.01.01.01.022.00643 Electrical Pump kap. 750 gln/menit 120 ml (90 kW)
1.1.7.01.01.01.022.00738 Engsel Harmonika
1.1.7.01.01.01.022.00737 Engsel Jendela
1.1.7.01.01.01.022.00739 Engsel Lantai (Floor Hinge)
1.1.7.01.01.01.022.00740 Engsel Lantai (Floor Hinge)
1.1.7.01.01.01.022.00732 Engsel Pintu Garasi Lipat Besi / Kayu
1.1.7.01.01.01.022.00735 Engsel Pintu Jendela Silver /Gold 3"
1.1.7.01.01.01.022.00736 Engsel Pintu Jendela Silver /Gold 4"
1.1.7.01.01.01.022.00733 Engsel Pintu Stainless Steel 3"
1.1.7.01.01.01.022.00734 Engsel Pintu Stainless Steel 4"
1.1.7.01.01.01.022.00716 Espangolet (kualitas biasa)
1.1.7.01.01.01.022.00717 Espangolet (kualitas sedang/tinggi)
1.1.7.01.01.01.022.00648 Fire Alarm Bell
1.1.7.01.01.01.022.00650 Fire Control Panel 4 Zone
1.1.7.01.01.01.022.00651 Fire Control Panel 8 Zone
1.1.7.01.01.01.022.00647 Fire House 1.5 x 30 m + nose
1.1.7.01.01.01.022.00649 Fire Strobo Light
1.1.7.01.01.01.022.00473 Flange Lass Pn 10 Dia. 40 mm
1.1.7.01.01.01.022.00472 Flange Lass Pn 10 Dia. 50 mm
1.1.7.01.01.01.022.00471 Flange Lass Pn 10 Dia. 63 mm
1.1.7.01.01.01.022.00463 Flange Socket RRJ Dia. 50 mm
1.1.7.01.01.01.022.00464 Flange Socket RRJ Dia. 63 mm
1.1.7.01.01.01.006.00046 Flincote
1.1.7.01.01.01.022.00503 Floatin g Valve Dia. 20 mm
1.1.7.01.01.01.022.00543 Floating valve
1.1.7.01.01.01.022.00544 Floating valve
1.1.7.01.01.01.022.00505 Flug Kran Dia. 20 mm
1.1.12.01.03.0003.00001 Format screening Vaksinasi Covid 19
1.1.7.01.01.01.022.00198 Formika
1.1.7.01.01.01.022.00199 Formika
1.1.7.01.01.01.022.00098 Formite/spacer
1.1.7.01.01.01.022.00474 Fudle Flange
1.1.7.01.01.01.022.00701 Fuse 4 A
1.1.7.01.01.01.022.00653 Gas Detector
1.1.7.01.01.01.022.00478 Gate Valve GI All Flange Dia. 63 mm
1.1.7.01.01.01.022.00477 Gate Valve GI All Flange Dia. 75 mm
1.1.7.01.01.01.022.00559 Gate Walve 1/2"
1.1.7.01.01.01.022.00757 Gear Pump
1.1.7.01.01.01.014.00026 Genteng Beton Flat
1.1.7.01.01.01.022.00611 Genteng Beton Gelombang
1.1.7.01.01.01.014.00023 Genteng Bubungan
1.1.7.01.01.01.014.00024 Genteng Bubungan Beton
1.1.7.01.01.01.014.00029 Genteng Kaca
1.1.7.01.01.01.014.00027 Genteng Keramik Gelombang
1.1.7.01.01.01.014.00028 Genteng Keramik Glasur Plat
1.1.7.01.01.01.014.00034 Genteng Kodok
1.1.7.01.01.01.014.00025 Genteng Metal
1.1.7.01.01.01.014.00038 Genteng Metal
1.1.7.01.01.01.014.00031 Genteng Murando Glasur Coklat/Trans
1.1.7.01.01.01.014.00032 Genteng Murando Glasur Warna
1.1.7.01.01.01.014.00030 Genteng Murando Natural
1.1.7.01.01.01.022.00347 Glass Block DN 20 x 20
1.1.7.01.01.01.022.00348 Glass Block DN 20 x 20 ex LN
1.1.7.01.01.01.022.00231 Grafel
1.1.7.01.01.01.022.00232 Grafel
1.1.7.01.01.01.022.00233 Grafel
1.1.7.01.01.01.022.00222 Granito Tile 60 x 60
1.1.7.01.01.01.022.00223 Granito Tile 60 x 60
1.1.7.01.01.01.022.00074 Grass Block
1.1.7.01.01.01.022.00075 Grass Block
1.1.7.01.01.01.022.00076 Grass Block
1.1.7.01.01.01.022.00077 Grass Block
1.1.7.01.01.01.022.00147 GRC /Versaboard
1.1.7.01.01.01.022.00148 GRC /Versaboard
1.1.7.01.01.01.022.00149 GRC /Versaboard
1.1.7.01.01.01.022.00722 Grendel 10" (25 cm)
1.1.7.01.01.01.022.00719 Grendel 2 " (5 cm)
1.1.7.01.01.01.022.00720 Grendel 4" (10 cm)
1.1.7.01.01.01.022.00721 Grendel 6" (15 cm)
1.1.7.01.01.01.022.00145 Gypsum Board
1.1.7.01.01.01.022.00146 Gypsum Board
1.1.7.01.01.02.002.00099 H2SO4
1.1.7.01.01.01.022.00725 Hak Angin Jendela Antik
1.1.7.01.01.01.022.00723 Hak Angin Kait Jendela Biasa
1.1.7.01.01.01.022.00724 Hak Angin Sendok
1.1.7.01.01.01.022.00759 Hand Oil Pump
1.1.12.01.03.0013.00013 Hand Sanitizer Dispenser
1.1.7.01.01.01.022.00382 Hangger/gantungan besi Ø 8 mm
1.1.7.01.01.01.022.00655 Heat Detector 4 wire
1.1.7.01.01.02.001.00046 HgSO4
1.1.7.01.01.01.022.00294 Hollow
1.1.7.01.01.01.022.00295 Hollow
1.1.7.01.01.01.022.00296 Hollow
1.1.7.01.01.01.022.00297
100 Hollow
1.1.7.01.01.01.022.00298 Hollow
1.1.7.01.01.01.022.00299 Hollow
1.1.7.01.01.01.022.00300 Hollow
1.1.7.01.01.01.022.00301 Hollow
1.1.7.01.01.01.022.00302 Hollow
1.1.7.01.01.01.022.00303 Hollow
1.1.7.01.01.01.022.00304 Hollow
1.1.7.01.01.01.022.00305 Hollow
1.1.7.01.01.01.022.00306 Hollow
1.1.7.01.01.01.022.00307 Hollow
1.1.7.01.01.01.022.00308 Hollow
1.1.7.01.01.01.022.00309 Hollow
1.1.7.01.01.01.022.00310 Hollow
1.1.7.01.01.01.022.00311 Hollow
1.1.7.01.01.01.022.00312 Hollow
1.1.7.01.01.01.022.00313 Hollow
1.1.7.01.01.01.022.00314 Hollow
1.1.7.01.01.01.022.00315 Hollow
1.1.7.01.01.01.022.00316 Hollow
1.1.7.01.01.01.022.00317 Hollow
1.1.7.01.01.01.022.00318 Hollow
1.1.7.01.01.01.022.00319 Hollow
1.1.7.01.01.01.022.00320 Hollow
1.1.7.01.01.01.022.00321 Hollow
1.1.7.01.01.01.022.00322 Hollow
1.1.7.01.01.01.022.00323 Hollow
1.1.7.01.01.01.022.00099 Hollow /Con Blok
1.1.7.01.01.01.022.00100 Hollow /Con Blok
1.1.7.01.01.01.022.00101 Hollow /Con Blok
1.1.7.01.01.01.022.00197 HPL Wood Texture
1.1.7.01.01.01.022.00646 Hydran Box dlm Gedung ( Lengkap )
1.1.7.01.01.01.022.00702 inbow panasonics
1.1.7.01.01.02.001.00028 Indicator PAN 0,1 % 100 ml,
1.1.7.01.01.01.006.00050 Inpra Clear Gloss
1.1.7.01.01.01.022.00685 Instalasi Titik Lampu
1.1.7.01.01.01.022.00686 Instalasi Titik Stop Kontak
1.1.12.01.03.0013.00009 Interior Back Board + Teralis
1.1.7.01.01.01.022.00859 IPAL INDIVIDUAL
1.1.7.01.01.01.022.00860 IPAL INDIVIDUAL
1.1.12.01.01.0010.00001 Isi ulang tabung gas
1.1.7.01.01.01.022.00285 Jalusi Aluminium
1.1.12.01.03.0013.00018 Jam Dinding
1.1.7.01.01.01.022.00679 Jarum Penangkal Petir 16
1.1.7.01.01.01.022.00290 Jendela Besi
1.1.7.01.01.01.022.00291 Jendela Besi Tahan Api
1.1.7.01.01.01.022.00657 Kabel NYA
1.1.7.01.01.01.022.00658 Kabel NYA
1.1.7.01.01.01.022.00660 Kabel NYA
1.1.7.01.01.01.022.00659 Kabel NYM
1.1.7.01.01.01.022.00661 Kabel NYM
1.1.7.01.01.01.022.00662 Kabel NYM
1.1.7.01.01.01.022.00663 Kabel NYM
1.1.7.01.01.01.022.00664 Kabel NYY
1.1.7.01.01.01.022.00665 Kabel NYY
1.1.7.01.01.01.022.00666 Kabel NYY
1.1.7.01.01.01.022.00667 Kabel NYY
1.1.7.01.01.01.022.00668 Kabel NYY
1.1.7.01.01.01.022.00669 Kabel NYY
1.1.7.01.01.01.022.00339 Kaca Cermin 3 mm
1.1.7.01.01.01.022.00340 Kaca Cermin 5 mm
1.1.7.01.01.01.022.00341 Kaca Cermin 8 mm
1.1.7.01.01.01.022.00335 Kaca Clear Tempered 10 mm
1.1.7.01.01.01.022.00336 Kaca Clear Tempered 12 mm
1.1.7.01.01.01.022.00332 Kaca Clear Tempered 5 mm
1.1.7.01.01.01.022.00333 Kaca Clear Tempered 6 mm
1.1.7.01.01.01.022.00334 Kaca Clear Tempered 8 mm
1.1.7.01.01.01.022.00337 Kaca Es / Susu 3 mm
1.1.7.01.01.01.022.00338 Kaca Es / Susu 5 mm
1.1.7.01.01.01.022.00344 Kaca Patri Lokal Terpasang
1.1.7.01.01.01.022.00345 Kaca Patri Lokal Terpasang
1.1.7.01.01.01.022.00346 Kaca Patri Lokal Terpasang
1.1.7.01.01.01.022.00324 Kaca Polos 2 mm
1.1.7.01.01.01.022.00325 Kaca Polos 3 mm
1.1.7.01.01.01.022.00326 Kaca Polos 5 mm
1.1.7.01.01.01.022.00327 Kaca Polos 8 mm
1.1.7.01.01.01.022.00342 Kaca Polos Sandblasting (Terpasang)
1.1.7.01.01.01.022.00343 Kaca Polos Sandblasting (Terpasang)
1.1.7.01.01.01.022.00331 Kaca Reyband 10 mm
1.1.7.01.01.01.022.00328 Kaca Reyband 5 mm
1.1.7.01.01.01.022.00329 Kaca Reyband 6 mm
1.1.7.01.01.01.022.00330 Kaca Reyband 8 mm
1.1.7.01.01.01.022.00726 Kait angin Aluminium
1.1.7.01.01.01.022.00857 Kandang Domba
1.1.7.01.01.01.022.00858 Kandang Domba Koloni
1.1.7.01.01.01.022.00848 KANOPI
1.1.7.01.01.01.022.00090 Kanstin Jalan (Bina Marga /Besar)
1.1.7.01.01.01.022.00089 Kanstin Jalan (Bina Marga /Kecil)
1.1.7.01.01.01.022.00088 Kanstin Taman Ukuran Besar
1.1.7.01.01.01.022.00087 Kanstin Taman Ukuran Kecil
1.1.7.01.01.01.022.00102 Kapur padam
1.1.7.01.01.01.022.00096 Kapur Pasang/kapur Tembok
1.1.7.01.01.01.022.00097 Kapur Sirih
1.1.7.01.01.01.022.00751 Karet Accesoris Kusen/Pintu Aluminium
1.1.7.01.01.01.022.00125 Karet Lis
1.1.7.01.01.01.022.00462 Karet Paking
1.1.7.01.01.01.022.00809 Karet Penyekat /Rubber Water Stop
1.1.7.01.01.01.022.00810 Karet Penyekat /Rubber Water Stop
1.1.7.01.01.01.022.00226 Karpet Kelas Standar
1.1.7.01.01.01.020.00001 Karung
1.1.7.01.01.01.022.00680 Kawat BC ( Tembaga )
1.1.7.01.01.01.022.00255 Kawat Beton
1.1.7.01.01.01.019.00005 Kawat Bronjong Ø 3 mm
1.1.7.01.01.01.019.00007 Kawat Bronjong Ø 3 mm
1.1.7.01.01.01.019.00006 Kawat Bronjong Ø 4 mm
1.1.7.01.01.01.019.00008 Kawat Bronjong Ø 4 mm
1.1.7.01.01.01.022.00256 Kawat Duri
1.1.7.01.01.01.022.00541 Kawat seling Baja
1.1.7.01.01.01.022.00257 Kawat Tembaga
1.1.7.01.01.01.022.00205 Keramik 20 x 20
1.1.7.01.01.01.022.00206 Keramik 20 x 20 20 x 25 25 x 25
1.1.7.01.01.01.022.00207 Keramik 20 x 20 20 x 25 25 x 25
1.1.7.01.01.01.022.00204 Keramik 20 x 20 dan 10 x 20 (stepnosing)
1.1.7.01.01.01.022.00208 Keramik 30 x 30
1.1.7.01.01.01.022.00209 Keramik 30 x 30
1.1.7.01.01.01.022.00210 Keramik 30 x 30
1.1.7.01.01.01.022.00211 Keramik 30 x 30
1.1.7.01.01.01.022.00212 Keramik 40 x 40
1.1.7.01.01.01.022.00213 Keramik 40 x 40
1.1.7.01.01.01.022.00214 Keramik 40 x 40
1.1.7.01.01.01.022.00215 Keramik 40 x 40
1.1.7.01.01.01.022.00216 Keramik 60 x 60
1.1.7.01.01.01.022.00217 Keramik 60 x 60
1.1.7.01.01.01.022.00218 Keramik Granit 50 x 50
1.1.7.01.01.01.022.00219 Keramik Granit 50 x 50
1.1.7.01.01.01.022.00220 Keramik Granit 60 x 60
1.1.7.01.01.01.022.00221 Keramik Granit 60 x 60
1.1.7.01.01.01.022.00861 Keran tembok
1.1.7.01.01.01.022.00590 Kitchen Zink Stainless
1.1.7.01.01.01.022.00591 Kitchen Zink Stainless
1.1.7.01.01.01.022.00592 Kitchen Zink Stainless
1.1.7.01.01.01.022.00500 Knee drat PVC Dia. 20 mm
1.1.7.01.01.01.022.00491 Knee GI Dia. 20 mm
1.1.7.01.01.01.022.00492 Knee GI Dia. 25 mm
1.1.7.01.01.01.022.00493 Knee GI Dia. 50 mm
1.1.7.01.01.01.022.00494 Knee GI Dia. 63 mm
1.1.7.01.01.01.022.00499 Knee PVC Dia. 20 mm
1.1.7.01.01.01.022.00498 Knee PVC Dia. 25 mm
1.1.7.01.01.01.022.00497 Knee PVC Dia. 32 mm
1.1.7.01.01.01.022.00496 Knee PVC Dia. 50 mm
1.1.7.01.01.01.022.00495 Knee PVC Dia. 63 mm
1.1.7.01.01.01.022.00788 Kotak Baja Penyimpan Data
1.1.7.01.01.01.022.00225 Kramik Granite Stepnosing
1.1.7.01.01.01.022.00569 Kran Bebek ITAP 1/2"
1.1.7.01.01.01.022.00568 Kran Bebek Sun Eui 1/2"
1.1.7.01.01.01.022.00506 Kran Dia. 20 mm
1.1.7.01.01.01.022.00570 Kran Panas Dingin Sun Eui Standard
1.1.7.01.01.01.022.00562 Kran Stainless Lokal Kait
1.1.7.01.01.01.022.00566 Kran Tembok dia. 1/2"
1.1.7.01.01.01.022.00567 Kran Tembok dia. 3/4"
1.1.7.01.01.01.022.00565 Kran Tembok Sun Eui dia. 1/2"
1.1.7.01.01.01.022.00117 Kumpon
1.1.7.01.01.01.022.00705 Kunci dan Handle Pintu Alumunium
1.1.7.01.01.01.022.00704 Kunci dan handle Pintu Digital Otomatis
1.1.7.01.01.01.022.00713 Kunci Gembok Besar
1.1.7.01.01.01.022.00710 Kunci KM Bulat (kualitas biasa)
1.1.7.01.01.01.022.00711 Kunci KM Bulat (kualitas sedang)
1.1.7.01.01.01.022.00712 Kunci KM Bulat (kualitas tinggi)
1.1.7.01.01.01.022.00714 Kunci Lemari
1.1.7.01.01.01.022.00706 Kunci silinder Pintu Alumunium
1.1.7.01.01.01.022.00707 Kunci tanam 2 Slaag (kualitas biasa/kecil)
1.1.7.01.01.01.022.00708 Kunci tanam 2 Slaag (kualitas sedang/besar, antik)
1.1.7.01.01.01.022.00709 Kunci Tanam 2 Slaag (kualitas tinggi/besar)
1.1.12.01.03.0013.00005 Kursi Guru
1.1.12.01.03.0013.00008 Kursi Siswa
1.1.7.01.01.01.022.00266 Kusen Aluminium Natural
1.1.7.01.01.01.022.00268 Kusen Aluminium Natural
1.1.7.01.01.01.022.00267 Kusen Aluminium Warna
1.1.7.01.01.01.022.00269 Kusen Aluminium Warna
1.1.7.01.01.01.022.00687 Lampu Baret 30 cm + Neon
1.1.7.01.01.01.022.00756 Lapis Perekat (Tack Coat)
1.1.7.01.01.01.022.00755 Lapis Resap Pengikat (Prime Coat)
1.1.7.01.01.01.022.00754 Lataston / Hot Rolls Sheet ( HRS )
1.1.7.01.01.02.001.00041 Lauryl Tryptose Broth
1.1.7.01.01.01.022.00816 Lem
1.1.7.01.01.01.022.00817 Lem
1.1.7.01.01.01.022.00349 Lem Kaca /Sealant
1.1.7.01.01.01.022.00200 Lem Kuning
1.1.7.01.01.01.022.00202 Lem Pipa PVC
1.1.7.01.01.01.022.00201 Lem Putih /PVC
1.1.7.01.01.01.022.00475 Lem PVC
1.1.7.01.01.01.022.00203 Lem Vynil
1.1.12.01.03.0013.00004 Lemari Kelas
1.1.7.01.01.02.001.00043 LES Endo Agar
1.1.7.01.01.01.022.00623 Lisplang Kalsiplang
1.1.7.01.01.01.022.00624 Lisplang Kalsiplang
1.1.7.01.01.01.022.00625 Lisplang Kalsiplang
1.1.7.01.01.01.022.00626 Lisplang Kalsiplang
1.1.7.01.01.01.022.00627 Lisplang Kalsiplang
1.1.7.01.01.01.022.00628 Lisplang Kalsiplang
1.1.7.01.01.01.022.00631 List Plafond Gypsum Polos
1.1.7.01.01.01.022.00632 List Plafond Gypsum Polos
1.1.7.01.01.01.022.00629 List Plafond Gypsum Polos Siku
1.1.7.01.01.01.022.00630 List Plafond Gypsum Polos Siku
1.1.7.01.01.01.014.00033 List plank Genteng Keramik
1.1.7.01.01.01.022.00164 List Profil Gypsum
1.1.7.01.01.01.022.00165 List Profil Gypsum
1.1.7.01.01.01.022.00166 List Profil Gypsum
1.1.7.01.01.01.022.00134 List Profil Kamper 1 cm
1.1.7.01.01.01.022.00138 List Profil Kamper 10 cm
1.1.7.01.01.01.022.00135 List Profil Kamper 2 cm
1.1.7.01.01.01.022.00136 List Profil Kamper 4 cm
1.1.7.01.01.01.022.00137 List Profil Kamper 5 cm
1.1.7.01.01.01.022.00642 Lock Seal Cap atap UPVC (Ø 32mm)
1.1.7.01.01.01.022.00844 Louding
1.1.7.01.01.02.002.00104 Lyse
1.1.7.01.01.01.022.00409 Macam-macam Sambungan GIP 1 1/4"
1.1.7.01.01.01.022.00411
100 Macam-macam Sambungan GIP 1 3/4"
1.1.7.01.01.01.022.00408 Macam-macam Sambungan GIP 1"
1.1.7.01.01.01.022.00406 Macam-macam Sambungan GIP 1/2"
1.1.7.01.01.01.022.00413 Macam-macam Sambungan GIP 2 1/2"
1.1.7.01.01.01.022.00412 Macam-macam Sambungan GIP 2"
1.1.7.01.01.01.022.00414 Macam-macam Sambungan GIP 3"
1.1.7.01.01.01.022.00407 Macam-macam Sambungan GIP 3/4"
1.1.7.01.01.01.022.00415 Macam-macam Sambungan GIP 4"
1.1.7.01.01.01.022.00410 Macam-macam Sambungan GIP1 1/2"
1.1.7.01.01.01.022.00547 Manhole
1.1.7.01.01.01.022.00536 Manometer dengan kran 1/2" + Valve
1.1.7.01.01.01.002.00030 Material
1.1.7.01.01.02.001.00044 Mc Conkey Agar
1.1.7.01.01.01.022.00670 MCB 1 PAS
1.1.7.01.01.01.022.00671 MCB 1 PAS
1.1.7.01.01.01.022.00672 MCB 1 PAS
1.1.7.01.01.01.022.00673 MCB 1 PAS
1.1.7.01.01.01.022.00674 MCB 3 PAS
1.1.7.01.01.01.022.00675 MCB 3 PAS
1.1.7.01.01.01.022.00676 MCB 3 PAS
1.1.7.01.01.01.022.00677 MCB 3 PAS
1.1.12.01.03.0013.00006 Meja Guru
1.1.12.01.03.0013.00007 Meja Siswa
1.1.7.01.01.01.022.00129 Melamik kusen /jendela
1.1.7.01.01.01.022.00128 Melamik pintu
1.1.7.01.01.01.022.00194 Melamin
1.1.7.01.01.01.022.00195 Melamin
1.1.7.01.01.01.022.00196 Melamin
1.1.7.01.01.01.022.00111 Melamine Lack /IMPRA
1.1.7.01.01.01.022.00122 Meni Kayu / Besi
1.1.7.01.01.01.022.00123 Meni Kayu / Besi
1.1.7.01.01.02.005.00151 Mercury Chloride (Hgcl2) P.a 50 Gr, Merck
1.1.7.01.01.02.005.00153 Mercury Sulfate (Hgso4) P.a 250 Gr, Merck
1.1.7.01.01.02.005.00152 Mercury Sulfate (Hgso4), P.a 50 Gr, Merck
1.1.7.01.01.02.005.00154 Mercury Tyosianat 250 Ml, Hach 22121-29
1.1.12.01.03.0013.00002 Mesin Absensi Contactless (Palm Face Card) - Sen
1.1.7.01.01.02.005.00150 Metanol 2,5 L, Merck
1.1.7.01.01.02.002.00074 Mineral Stabilizer 50 mL SCDB
1.1.7.01.01.02.002.00084 Mineral Stabilizer 50 mL SCDB
1.1.7.01.01.02.005.00155 Mineral Stabilizer 50 Ml Scdb Hach
1.1.7.01.01.01.021.00006 Minyak Cat
1.1.7.01.01.01.022.00689 MLL 160 Watt
1.1.12.01.03.0013.00001 Mobile Bracket 86"
1.1.7.01.01.01.022.00174 Multiplek
1.1.7.01.01.01.022.00175 Multiplek
1.1.7.01.01.01.022.00176 Multiplek
1.1.7.01.01.01.022.00177 Multiplek
1.1.7.01.01.01.022.00375 Mur Baut Biasa Ø 19 s/d 16 (5 cm)
1.1.7.01.01.01.022.00376 Mur Baut HTB Ø 19 s/d 16 (5 cm)
1.1.7.01.01.01.022.00377 Mur Baut HTM 5/8x3"
1.1.7.01.01.02.005.00167 N-(1-naphthyl) Ethylene Diamine Dihydrochloride (Neda) 5 Gr, Merck
1.1.7.01.01.02.002.00101 Na Hipoklorit
1.1.12.01.03.0013.00011 Nano Atomizer
1.1.7.01.01.02.005.00159 Natrium Acetat Anhidrat (Ch3coona) 250 Gr, Merck
1.1.7.01.01.02.005.00160 Natrium Hydrogen Phosphate (Na2hpo4) P.a 500 Gr, Merck
1.1.7.01.01.02.005.00161 Natrium Metabisulfit, P.a 250 Gr
1.1.7.01.01.02.005.00162 Natrium Nitrit (Nano2) P.a 250 Gr
1.1.7.01.01.02.001.00051 Natrium Nitroprusid
1.1.7.01.01.02.005.00164 Natrium Oxalate (Na2c2o4) P.a 1000 Gr, Merck 106557
1.1.7.01.01.02.005.00163 Natrium Oxalate (Na2c2o4) P.a 250 Gr, Merck 106557
1.1.7.01.01.02.005.00165 Natrium Phosphat (Na3po4) P.a 1000 Gr, Merck 106578
1.1.7.01.01.02.005.00166 Natrium Sulfida, P.a, 250 Gr
1.1.7.01.01.02.005.00169 Nessler Reagent 100 Ml, Hach 21194-32
1.1.7.01.01.02.005.00170 Nessler Reagent 500 Ml, Hach 21194-32
1.1.7.01.01.02.005.00168 Nessler, Extra Alkaline 500 Ml (250 Test)
1.1.7.01.01.02.002.00075 N-Hexane
1.1.7.01.01.02.002.00085 N-Hexane
1.1.7.01.01.02.005.00156 N-hexane Teknis 1 L
1.1.7.01.01.02.005.00157 N-hexane, P.a 1000 Ml, Merck
1.1.7.01.01.02.005.00158 N-hexane, P.a 2500 Ml, Merck
1.1.7.01.01.02.005.00173 Nitrate Nitrogen Std. Solution 1 Mg/l Sebagai No3-n 500 Ml, Hach 204649
1.1.7.01.01.02.005.00171 Nitraver 5 Nitrate Reagent Powder Pillows 10 Ml, 100/pkg, Hach 21061-69-4
1.1.7.01.01.02.005.00172 Nitraver 5 Nitrate Reagent Powder Pillows 25 Ml, 100/pkg, Hach 21061-69-4
1.1.7.01.01.02.001.00048 Nitraver 5 Reagent
1.1.7.01.01.02.005.00174 Nitrite Standard Solution 500 Ml, Merck 119899
1.1.7.01.01.02.005.00175 Nitrite Stock Solution 250 Μg/ml Sebagai N 500 Ml
1.1.7.01.01.02.005.00176 Nitriver 3 Nitrite Reagent 10 Ml, 100/pkg, Hach 21071-69
1.1.7.01.01.02.001.00029 Nitriver 3 Nitrite Reagent 25 Ml, 100/pkg,
1.1.7.01.01.02.001.00037 Nitriver 3 Nitrite Reagent 25 Ml, 100/pkg,
1.1.7.01.01.02.005.00177 Nitriver 3 Nitrite Reagent 25 Ml, 100/pkg, Hach 14065-99
1.1.7.01.01.02.005.00178 Nitrogrn Nitrate Reagent Set Lr, Hach 24298-00
1.1.7.01.01.01.022.00638 Nok Atap Bitumen Monolayer 3 mm
1.1.7.01.01.01.007.00018 Nok Atap Seng
1.1.7.01.01.01.022.00608 Nok Atas Metal (p=104 cm)
1.1.7.01.01.01.022.00617 Nok Genteng Metal
1.1.7.01.01.01.022.00609 Nok Pinggir Metal
1.1.7.01.01.01.022.00618 Nok Standar 40 cm 18, SWG 22
1.1.7.01.01.01.022.00815 NOZZEL BEBEK
1.1.7.01.01.01.022.00814 NOZZEL CEMARA
1.1.7.01.01.01.022.00813 NOZZEL KOMET
1.1.7.01.01.02.005.00179 Nutrien Agar 500 Gr, Merck
1.1.7.01.01.02.005.00180 Nutrien Agar 500 Gr, Oxoid
1.1.7.01.01.02.001.00045 Nutrient Agar
1.1.7.01.01.01.022.00104 Oker
1.1.7.01.01.01.022.00105 Oten (Pewarna Plitur)
1.1.7.01.01.01.022.00703 Outlet Tv + Instalasi
1.1.7.01.01.01.022.00253 Pagar BRC lengkap (tanpa Pondasi)
1.1.7.01.01.01.022.00254 Pagar BRC lengkap (tanpa Pondasi)
1.1.7.01.01.01.022.00350 Paku 1 cm s/d 3 cm
1.1.7.01.01.01.022.00351 Paku 4 cm s/d 7 cm
1.1.7.01.01.01.022.00352 Paku 8 cm s/d 15 cm
1.1.7.01.01.01.022.00353 Paku Beton 2 cm s/d 5 cm
1.1.7.01.01.01.022.00355 Paku Cacing
1.1.7.01.01.01.022.00356 Paku GRC
1.1.7.01.01.01.022.00357 Paku Gypsum
1.1.7.01.01.01.022.00360 Paku Hak Panjang
1.1.7.01.01.01.022.00354 Paku Kait Lengkap
1.1.7.01.01.01.022.00363 Paku Sekrup 3"
1.1.7.01.01.01.022.00359 Paku Seng
1.1.7.01.01.01.022.00358 Paku Skrup 5 cm
1.1.7.01.01.02.002.00100 PAN Indicator Solution 0.3%
1.1.7.01.01.01.022.00091 Panel Beton Polos Mutu K-225
1.1.7.01.01.01.022.00092 Panel Beton Polos Mutu K-300
1.1.7.01.01.01.022.00690 Panel LP-A
1.1.7.01.01.01.022.00691 Panel LP-B
1.1.7.01.01.01.022.00692 Panel LP-C
1.1.7.01.01.01.022.00693 Panel LP-D
1.1.7.01.01.01.022.00694 Panel LP-E
1.1.7.01.01.01.022.00695 Panel SDP
1.1.7.01.01.01.022.00787 Papan Exploitasi
1.1.7.01.01.01.022.00786 Papan Oprasi Bendung
1.1.12.01.03.0013.00003 Papan whiteboard
1.1.7.01.01.01.022.00227 Parquet Jati
1.1.7.01.01.01.022.00228 Parquet Jati
1.1.7.01.01.01.022.00229 Parquet Jati
1.1.7.01.01.01.022.00230 Parquet Jati
1.1.7.01.01.01.022.00696 Pasang Telepon
1.1.7.01.01.01.004.00010 Pasir Beton
1.1.7.01.01.01.004.00009 Pasir Pasang Gunung /Pilihan
1.1.7.01.01.01.004.00008 Pasir Pasang Kali
1.1.7.01.01.01.004.00007 Pasir Urug (bawah lantai)
1.1.7.01.01.01.022.00051 Patok Batas Tanah
1.1.7.01.01.01.022.00789 Patok Hektometer ( Pengairan )
1.1.7.01.01.01.022.00078 Paving Blok
1.1.7.01.01.01.022.00079 Paving Blok
1.1.7.01.01.01.022.00080 Paving Blok
1.1.7.01.01.01.022.00081 Paving Blok
1.1.7.01.01.01.022.00082 Paving Blok
1.1.7.01.01.01.022.00083 Paving Blok
1.1.7.01.01.01.022.00084 Paving Blok
1.1.7.01.01.01.022.00085 Paving Blok
1.1.7.01.01.01.022.00139 Pegangan Tangga Profil Jati
1.1.7.01.01.01.022.00140 Pegangan Tangga Profil Kamper
1.1.7.01.01.01.006.00043 Pelapis Alkali ICI
1.1.7.01.01.01.022.00688 Pemasangan pipa conduit
1.1.7.01.01.01.022.00854 Pembangunan MCK (DK)
1.1.7.01.01.01.022.00856 Pembangunan MCK (DK)
1.1.12.01.03.0007.00002 Pengukur Tinggi Badan
1.1.7.01.01.01.022.00681 Pentanahan Penangkal Petir
1.1.7.01.01.01.022.00540 Penutup Well Heat
1.1.7.01.01.01.022.00156 Penyambung talang (gutter joint)
1.1.7.01.01.01.022.00157 Penyambung talang (gutter joint)
1.1.7.01.01.01.022.00154 Penyanga (bracket) talang
1.1.7.01.01.01.022.00155 Penyanga (bracket) talang
1.1.7.01.01.01.022.00589 Penyekat Poslin Urinoir TOTO
1.1.7.01.01.01.022.00841 Peralatan
1.1.7.01.01.01.022.00842 Peralatan
1.1.7.01.01.01.008.00004 Peralatan Perhubungan
1.1.7.01.01.01.022.00818 Peralatan Perhubungan
1.1.7.01.01.01.022.00819 Peralatan Perhubungan
1.1.7.01.01.01.022.00824 Peralatan Perhubungan
1.1.7.01.01.02.002.00039 PERANGKAT LAINNYA
1.1.12.01.03.0013.00015 Perlengkapan dan Obat P3K
1.1.7.01.01.02.001.00050 Phenol
1.1.7.01.01.02.005.00181 Phenol P.a 250 Gr, Merck 100206
1.1.7.01.01.02.005.00182 Phosphate Standard Solution Traceable To Srm 500 Ml, Merck 119898
1.1.7.01.01.02.002.00076 PhosVer 3 Phospate Reagent Powder Pillows 10 m
1.1.7.01.01.02.005.00183 Phosver 3 Phospate Reagent Powder Pillows 10 Ml Pkg/100 (100 Test)
1.1.7.01.01.01.022.00792 Pintu Angkat Type 1.B = 0.30 meter
1.1.7.01.01.01.022.00793 Pintu Angkat Type 1.B = 0.40 meter
1.1.7.01.01.01.022.00794 Pintu Angkat Type 1.B = 0.50 meter
1.1.7.01.01.01.022.00795 Pintu Angkat Type II.B = 0.30 meter
1.1.7.01.01.01.022.00796 Pintu Angkat Type II.B = 0.40 meter
1.1.7.01.01.01.022.00797 Pintu Angkat Type II.B = 0.50 meter
1.1.7.01.01.01.022.00288 Pintu fitting (tempered 12 mm polos) floor hinge dorma BTS 84
1.1.7.01.01.01.022.00277 Pintu Folding Gate
1.1.7.01.01.01.022.00278 Pintu Folding Gate
1.1.7.01.01.01.022.00287 Pintu Frameless (tempered 12 mm polos) floor hinge dorma BTS 84
1.1.7.01.01.01.022.00274 Pintu PVC Kamar Mandi
1.1.7.01.01.01.022.00275 Pintu PVC Kamar Mandi
1.1.7.01.01.01.022.00276 Pintu PVC Kamar Mandi
1.1.7.01.01.01.022.00279 Pintu Roliing Door
1.1.7.01.01.01.022.00280 Pintu Rolling Door
1.1.7.01.01.01.022.00812 Pintu Skot Balk Jati Jabar
1.1.7.01.01.01.022.00811 Pintu Skot Balk Jati Jateng
1.1.7.01.01.01.022.00798 Pintu Sorong baja type 1A
1.1.7.01.01.01.022.00805 Pintu sorong baja type 2 draadstang
1.1.7.01.01.01.022.00806 Pintu sorong baja type 2 draadstang
1.1.7.01.01.01.022.00807 Pintu sorong baja type 2 draadstang
1.1.7.01.01.01.022.00808 Pintu sorong baja type 2 draadstang
1.1.7.01.01.01.022.00799 Pintu Sorong baja type 2A
1.1.7.01.01.01.022.00800 Pintu Sorong baja type 3A
1.1.7.01.01.01.022.00801 Pintu Sorong baja type 4A
1.1.7.01.01.01.022.00802 Pintu Sorong baja type 5A
1.1.7.01.01.01.022.00803 Pintu Sorong baja type 6A
1.1.7.01.01.01.022.00804 Pintu Sorong baja type 7A
1.1.7.01.01.01.022.00486 Pipa GI Dia. 20 mm SII
1.1.7.01.01.01.022.00485 Pipa GI Dia. 40 mm SII
1.1.7.01.01.01.022.00484 Pipa GI Dia. 50 mm SII
1.1.7.01.01.01.022.00483 Pipa GI Dia. 63 mm SII
1.1.7.01.01.01.022.00482 Pipa GI Dia. 90 mm SII
1.1.7.01.01.01.022.00400 Pipa GIP Medium A 1 1/2"
1.1.7.01.01.01.022.00399 Pipa GIP Medium A 1 1/4"
1.1.7.01.01.01.022.00401 Pipa GIP Medium A 1 3/4"
1.1.7.01.01.01.022.00398 Pipa GIP Medium A 1"
1.1.7.01.01.01.022.00396 Pipa GIP Medium A 1/2"
1.1.7.01.01.01.022.00403 Pipa GIP Medium A 2 1/2"
1.1.7.01.01.01.022.00402 Pipa GIP Medium A 2"
1.1.7.01.01.01.022.00404 Pipa GIP Medium A 3"
1.1.7.01.01.01.022.00397 Pipa GIP Medium A 3/4"
1.1.7.01.01.01.022.00405 Pipa GIP Medium A 4"
1.1.7.01.01.01.022.00446 Pipa HDPE Dia. 20 mm/ Ø 1/2"
1.1.7.01.01.01.022.00447 Pipa HDPE Dia. 32 mm/ Ø 1"
1.1.7.01.01.01.022.00448 Pipa HDPE Dia. 40 mm/ Ø 1 1/4"
1.1.7.01.01.01.022.00449 Pipa HDPE Dia. 50 mm/ Ø 1 1/2"
1.1.7.01.01.01.022.00450 Pipa HDPE Dia. 63 mm/ Ø 2"
1.1.7.01.01.01.022.00451 Pipa HDPE Dia. 90 mm/ Ø 3"
1.1.7.01.01.01.022.00437 Pipa PVC 4" TY
1.1.7.01.01.01.022.00438 Pipa PVC AW 4" (Jambang /berlobang)
1.1.7.01.01.01.022.00458 Pipa PVC Dia. 110 mm/ Ø 4"
1.1.7.01.01.01.022.00459 Pipa PVC Dia. 160 mm/ Ø 6"
1.1.7.01.01.01.022.00452 Pipa PVC Dia. 20 mm/ Ø 1/2"
1.1.7.01.01.01.022.00460 Pipa PVC Dia. 225 mm/ Ø 8"
1.1.7.01.01.01.022.00453 Pipa PVC Dia. 25 mm/ Ø 3/4"
1.1.7.01.01.01.022.00454 Pipa PVC Dia. 32 mm/ Ø 1"
1.1.7.01.01.01.022.00455 Pipa PVC Dia. 50 mm/ Ø 1 1/2"
1.1.7.01.01.01.022.00456 Pipa PVC Dia. 63 mm/ Ø 2"
1.1.7.01.01.01.022.00457 Pipa PVC Dia. 90 mm/ Ø 3"
1.1.7.01.01.01.022.00420 Pipa PVC type AW Ø 1 1/2"
1.1.7.01.01.01.022.00419 Pipa PVC type AW Ø 1 1/4"
1.1.7.01.01.01.022.00418 Pipa PVC type AW Ø 1"
1.1.7.01.01.01.022.00416 Pipa PVC type AW Ø 1/2"
1.1.7.01.01.01.022.00422 Pipa PVC type AW Ø 2 1/2"
1.1.7.01.01.01.022.00421 Pipa PVC type AW Ø 2"
1.1.7.01.01.01.022.00423 Pipa PVC type AW Ø 3"
1.1.7.01.01.01.022.00417 Pipa PVC type AW Ø 3/4"
1.1.7.01.01.01.022.00424 Pipa PVC type AW Ø 4"
1.1.7.01.01.01.022.00425 Pipa PVC type AW Ø 6"
1.1.7.01.01.01.022.00426 Pipa PVC type AW Ø 8"
1.1.7.01.01.01.022.00379 Piser Ø 12 s/d 20 cm
1.1.7.01.01.01.022.00143 Plafond Asbes Semen
1.1.7.01.01.01.022.00144 Plafond Asbes Semen
1.1.7.01.01.01.022.00141 Plafond Enternit
1.1.7.01.01.01.022.00142 Plafond Hardpleks
1.1.7.01.01.01.006.00026 Plamir Tembok
1.1.7.01.01.01.016.00010 Plat
1.1.7.01.01.01.016.00011 Plat
1.1.7.01.01.01.016.00017 Plat Alluminium 0.1 mm
1.1.7.01.01.01.016.00012 Plat Alluminium 0.2 mm
1.1.7.01.01.01.016.00013 Plat Alluminium 0.3 mm
1.1.7.01.01.01.016.00014 Plat Alluminium 0.4 mm
1.1.7.01.01.01.016.00015 Plat Alluminium 0.5 mm
1.1.7.01.01.01.016.00016 Plat Alluminium 0.6 mm
1.1.7.01.01.01.016.00018 Plat Tanda Muka Air / Peil Schaal
1.1.7.01.01.01.022.00224 Plin Lantai Granite 10 x 60
1.1.7.01.01.01.013.00008 Plin Tegel PC 15 x 30
1.1.7.01.01.01.013.00010 Plin Tegel Warna 15 x 30
1.1.7.01.01.01.022.00508 Plug PVC Dia. 20 mm
1.1.7.01.01.01.022.00187 Plywood
1.1.7.01.01.01.022.00188 Plywood
1.1.7.01.01.01.022.00189 Plywood
1.1.7.01.01.01.022.00114 Politur
1.1.7.01.01.01.022.00115 Politur Jadi
1.1.7.01.01.02.002.00077 Polyvinyl Alcohol Disp. Reagent 50 mL,
1.1.7.01.01.02.002.00086 Polyvinyl Alcohol Disp. Reagent 50 mL,
1.1.7.01.01.02.005.00184 Polyvinyl Alcohol Disp. Reagent 50 Ml, Hach 23765-26
1.1.7.01.01.01.022.00093 Pompa Readymix Beton (Sewa)
1.1.7.01.01.01.022.00094 Pompa Readymix Beton (Sewa)
1.1.7.01.01.01.022.00095 Pompa Readymix Beton (Sewa)
1.1.12.01.03.0013.00019 Poster Kesehatan
1.1.7.01.01.02.005.00192 Potasium Hydrogen Phthalat (Khp) P.a 250 G, Merck
1.1.7.01.01.02.005.00193 Potasium Hydroxide (Koh) P.a 500 Gr, Merck
1.1.7.01.01.02.005.00185 Potassium Antimony (Iii) Oxide Tartrate Trihydrate, P.a 250 Gr, Merck
1.1.7.01.01.02.005.00186 Potassium Chlorida (Kcl) P.a 1000 Gr, Merck
1.1.7.01.01.02.005.00187 Potassium Chromate (K2cro4) P.a 250 Gr, Merck
1.1.7.01.01.02.005.00189 Potassium Dichromat (K2cr2o7) P.a 1000 Gr, Merck
1.1.7.01.01.02.005.00188 Potassium Dichromat (K2cr2o7) P.a 500 Gr, Merck
1.1.7.01.01.02.005.00190 Potassium Dichromat (K2cr2o7) Teknis
1.1.7.01.01.02.005.00191 Potassium Dihydrogen Phosphate (Kh2po4) P.a 1000 Gr, Merck
1.1.7.01.01.02.005.00194 Potassium Nitrate, P.a 500 Gr, Merck
1.1.7.01.01.01.022.00791 Prasasti Granit Hitam
1.1.7.01.01.01.022.00790 Prasasti Marmer
1.1.7.01.01.01.022.00645 Presure Tank kap. 500 liter lengkap
1.1.7.01.01.01.022.00289 Profil Aluminium
1.1.7.01.01.02.001.00030 Pthalate Phosphate Reagent Powder Pilllow 100 Pc
1.1.7.01.01.02.001.00038 Pthalate Phosphate Reagent Powder Pilllow 100 Pc
1.1.7.01.01.02.005.00195 Pthalate Phosphate Reagent Powder Pilllow 100 Pcs, Hach 26151-99
1.1.7.01.01.01.022.00440 PVC Waterstop Lebar 150
1.1.7.01.01.01.022.00441 PVC Waterstop Lebar 200
1.1.7.01.01.01.022.00442 PVC Waterstop Lebar 230
1.1.7.01.01.01.022.00443 PVC Waterstop Lebar 250
1.1.7.01.01.01.022.00444 PVC Waterstop Lebar 300
1.1.7.01.01.01.022.00445 PVC Waterstop Lebar 320
1.1.7.01.01.01.022.00843 Ram
1.1.7.01.01.01.022.00260 Ram Kawat 1 x 1 (Putih)
1.1.7.01.01.01.022.00261 Ram Kawat Ayam
1.1.7.01.01.01.022.00259 Ram Nyamuk Alluminium
1.1.7.01.01.01.022.00258 Ram Nyamuk Hijau
1.1.7.01.01.01.022.00731 Rambuncis Handle
1.1.7.01.01.01.022.00380 Ramset / Dinabolt Ø 12 cm
1.1.7.01.01.01.008.00003 Rangka Atap baja Ringan 0,75
1.1.7.01.01.01.022.00163 Rangka Baja Ringan
1.1.7.01.01.01.022.00281 Rangka Jendela Nako + besi/tralis
1.1.7.01.01.01.022.00282 Rangka Jendela Nako + besi/tralis
1.1.7.01.01.01.022.00283 Rangka Jendela Nako + besi/tralis
1.1.7.01.01.01.022.00284 Rangka Jendela Nako + besi/tralis
1.1.7.01.01.01.022.00780 Rantai Kunci
1.1.7.01.01.01.022.00851 Rantai plastik
1.1.7.01.01.01.022.00852 Rantai plastik
1.1.7.01.01.01.022.00527 Reducer PVC Dia. 32x20 mm
1.1.7.01.01.01.022.00525 Reducer PVC Dia. 63x32 mm
1.1.7.01.01.01.022.00526 Reducer PVC Dia. 63x50 mm
1.1.7.01.01.01.022.00524
100 Reducer PVC Dia. 90x63 mm
1.1.7.01.01.01.022.00853 Rehabilitasi MCK (DK)
1.1.7.01.01.01.022.00855 Rehabilitasi MCK (DK)
1.1.7.01.01.01.022.00715 Rel Pintu Geser /Pintu Marathon
1.1.7.01.01.01.022.00487 Repair Socket Dia. 63 mm
1.1.7.01.01.01.022.00488 Repair Socket Dia. 90 mm
1.1.7.01.01.01.022.00126 Residu
1.1.7.01.01.01.022.00070
100 Rooster / Bata Kerawang
1.1.7.01.01.01.022.00063 Rooster Beton
1.1.7.01.01.01.022.00064 Rooster Beton
1.1.7.01.01.01.022.00069 Rooster Espana
1.1.7.01.01.01.022.00065 Rooster Jalusi
1.1.7.01.01.01.022.00071 Rooster Keramik
1.1.7.01.01.01.022.00072 Rooster Keramik
1.1.7.01.01.01.022.00073 Rooster Keramik
1.1.7.01.01.01.022.00066 Rooster Motif
1.1.7.01.01.01.022.00067 Rooster Polos
1.1.7.01.01.01.022.00068 Rooster Silang
1.1.7.01.01.01.022.00678 Rumah TL In Bow /Out Bow 2x20 W
1.1.7.01.01.01.022.00237 Saluran Terbuka (U-Ditch) UD 100
1.1.7.01.01.01.022.00238 Saluran Terbuka (U-Ditch) UD 120
1.1.7.01.01.01.022.00234 Saluran Terbuka (U-Ditch) UD 50
1.1.7.01.01.01.022.00235 Saluran Terbuka (U-Ditch) UD 70
1.1.7.01.01.01.022.00236 Saluran Terbuka (U-Ditch) UD 80
1.1.7.01.01.01.022.00242 Saluran Tertutup (Box Culvert) BC 100
1.1.7.01.01.01.022.00243 Saluran Tertutup (Box Culvert) BC 120
1.1.7.01.01.01.022.00244 Saluran Tertutup (Box Culvert) BC 150
1.1.7.01.01.01.022.00245 Saluran Tertutup (Box Culvert) BC 200
1.1.7.01.01.01.022.00239 Saluran Tertutup (Box Culvert) BC 50
1.1.7.01.01.01.022.00240 Saluran Tertutup (Box Culvert) BC 60
1.1.7.01.01.01.022.00241 Saluran Tertutup (Box Culvert) BC 80
1.1.7.01.01.01.022.00433 Sambungan 2"
1.1.7.01.01.01.022.00431 Sambungan pipa PVC Ø 1 1/2"
1.1.7.01.01.01.022.00430 Sambungan pipa PVC Ø 1 1/4"
1.1.7.01.01.01.022.00432 Sambungan pipa PVC Ø 1 3/4"
1.1.7.01.01.01.022.00429 Sambungan pipa PVC Ø 1"
1.1.7.01.01.01.022.00427 Sambungan pipa PVC Ø 1/2"
1.1.7.01.01.01.022.00434 Sambungan pipa PVC Ø 2 1/2"
1.1.7.01.01.01.022.00435 Sambungan pipa PVC Ø 3"
1.1.7.01.01.01.022.00428 Sambungan pipa PVC Ø 3/4"
1.1.7.01.01.01.022.00436 Sambungan pipa PVC Ø 4"
1.1.7.01.01.01.022.00112 Sanding Sealer /IMPRA
1.1.7.01.01.01.022.00560 Saringan Air Lt. KM Stainless Steel
1.1.7.01.01.01.022.00545 Screen
1.1.7.01.01.01.022.00461 Seal Tape
1.1.7.01.01.01.022.00361 Sekrup Fixer
1.1.7.01.01.02.001.00053 Selulose Nitrate Membran Filters
1.1.7.01.01.01.002.00058 Semen
1.1.7.01.01.01.002.00059 Semen
1.1.7.01.01.01.002.00037 Semen Instan /MU-100
1.1.7.01.01.01.002.00038 Semen Instan /MU-200
1.1.7.01.01.01.002.00039 Semen Instan /MU-260
1.1.7.01.01.01.002.00040 Semen Instan /MU-270
1.1.7.01.01.01.002.00041 Semen Instan /MU-300
1.1.7.01.01.01.002.00042 Semen Instan /MU-301
1.1.7.01.01.01.002.00043 Semen Instan /MU-380
1.1.7.01.01.01.002.00044 Semen Instan /MU-400
1.1.7.01.01.01.002.00045 Semen Instan /MU-410
1.1.7.01.01.01.002.00046 Semen Instan /MU-440
1.1.7.01.01.01.002.00047 Semen Instan /MU-445
1.1.7.01.01.01.002.00048 Semen Instan /MU-450
1.1.7.01.01.01.002.00049 Semen Instan /MU-460
1.1.7.01.01.01.002.00050 Semen Instan /MU-470
1.1.7.01.01.01.002.00051 Semen Instan /MU-480
1.1.7.01.01.01.002.00053 Semen Instan /MU-600
1.1.7.01.01.01.002.00054 Semen Instan /MU-700
1.1.7.01.01.01.002.00055 Semen Instan /MU-800
1.1.7.01.01.01.002.00056 Semen Instan /MU-830
1.1.7.01.01.01.002.00057 Semen Instan /MU-840
1.1.7.01.01.01.002.00052 Semen Instan /MU-L500
1.1.7.01.01.01.002.00036 Semen Mortar Utama (MU)
1.1.7.01.01.01.002.00033 Semen PC/ 40 Kg
1.1.7.01.01.01.002.00031 Semen PC/ 50 Kg
1.1.7.01.01.01.002.00032 Semen PC/ 50 Kg
1.1.7.01.01.01.002.00034 Semen Putih
1.1.7.01.01.01.002.00035 Semen warna
1.1.7.01.01.01.007.00010 Seng Plat BJLS 0,4 mm
1.1.7.01.01.01.007.00012 Seng Plat BJLS 0,4 mm
1.1.7.01.01.01.007.00011 Seng Plat BJLS 0,6 mm
1.1.7.01.01.01.007.00013 Seng Plat BJLS 0,6 mm
1.1.12.01.03.0007.00003 Senter
1.1.7.01.01.01.022.00596 Septictank Biofil
1.1.7.01.01.01.022.00597 Septictank Ipal Biofil
1.1.7.01.01.01.022.00563 Shower dengan Tiang
1.1.7.01.01.01.022.00564 Shower Tanpa Tiang
1.1.7.01.01.02.005.00197 Silver Nitrate (Agno3) P.a 25 Gr, Merck
1.1.7.01.01.02.005.00196 Silver Reagen Set (50 Test)
1.1.7.01.01.02.005.00198 Silver Solution 1000 Mg/l Sebagai Ag, 100 Ml
1.1.7.01.01.02.005.00199 Silver Sulfate (Agso4) P.a 25 Gr, Merck
1.1.7.01.01.01.022.00124 Sincromat (Zink Cromate)
1.1.7.01.01.01.022.00652 Sirine and Strobo
1.1.7.01.01.01.004.00006 Sirtu
1.1.7.01.01.01.022.00362 Skrup Ukuran 1"
1.1.7.01.01.01.022.00368 Skrup Ukuran khusus 6x1 1/2"
1.1.7.01.01.01.022.00369 Skrup Ukuran khusus 6x1 1/2"
1.1.7.01.01.01.022.00366 Skrup Ukuran khusus 6x1 1/4"
1.1.7.01.01.01.022.00367 Skrup Ukuran khusus 6x1 1/4"
1.1.7.01.01.01.022.00364 Skrup/suspention clip
1.1.7.01.01.01.022.00365 Skrup/suspention road
1.1.7.01.01.01.022.00785 Slang inlet pompa air irigasi
1.1.7.01.01.01.022.00784 Slang outlet pompa air irigasi
1.1.7.01.01.01.022.00730 Sloot Handle Jendela
1.1.7.01.01.01.022.00729 Sloot Jendela Tunggal
1.1.7.01.01.01.022.00728 Sloot Pintu (model pengikat batang)
1.1.7.01.01.01.022.00727 Sloot Pintu (model pengikat rantai)
1.1.7.01.01.01.022.00656 Smoke and Heat Detector 4 wire
1.1.7.01.01.01.022.00654 Smoke Detector 4 Wire
1.1.7.01.01.01.022.00489 Sock Drat Luar PVC Dia. 20 mm
1.1.7.01.01.01.022.00490 Sock Drat Luar PVC Dia. 25 mm
1.1.7.01.01.01.022.00507 Socket GI Dia. 20 mm
1.1.7.01.01.01.022.00533 Socket HDPE Dia. 32 mm
1.1.7.01.01.01.022.00532 Socket HDPE Dia. 40 mm
1.1.7.01.01.01.022.00531 Socket HDPE Dia. 50 mm
1.1.7.01.01.01.022.00530 Socket HDPE Dia. 63 mm
1.1.7.01.01.01.022.00439 Solatif Ledeng
1.1.7.01.01.01.022.00103 Soligneum
1.1.7.01.01.02.005.00200 Spands Reagent 500 Ml, Hach 44449
1.1.7.01.01.02.005.00201 Spands Reagent Solution 1000 Ml (500 Test)
1.1.12.01.03.0001.00001 Spidol drawing pen 0.2 / 0.5 (isi 12 buah)
1.1.7.01.01.01.022.00106 Spirtus
1.1.7.01.01.02.002.00040 Starter
1.1.7.01.01.01.022.00783 Stempet (Grease)
1.1.7.01.01.01.022.00552 Stop Kran 1 1/2" KITZ
1.1.7.01.01.01.022.00551 Stop Kran 1" KITZ
1.1.7.01.01.01.022.00554 Stop Kran 2 1/2" KITZ
1.1.7.01.01.01.022.00553 Stop Kran 2" KITZ
1.1.7.01.01.01.022.00555 Stop Kran 3" KITZ
1.1.7.01.01.01.022.00550 Stop Kran 3/4" KITZ
1.1.7.01.01.01.022.00504 Stop Kran Dia. 20 mm
1.1.7.01.01.01.022.00160 Stopper talang
1.1.7.01.01.01.022.00161 Stopper talang
1.1.7.01.01.02.005.00202 Sulfanilamide, P.a 100 Gr, Merck
1.1.7.01.01.02.005.00203 Sulfate Std. Solution Sebagai So4= 1000 Mg/l, 500 Ml
1.1.7.01.01.02.002.00080 SulfaVer 4 Sulfate
1.1.7.01.01.02.005.00204 Sulfaver 4 Sulfate Reagent 10 Ml, 100/pkg, Hach 21067-69
1.1.7.01.01.02.005.00205 Sulfide 1 Reagen Solution 500 Ml (500 Test)
1.1.7.01.01.02.002.00078 Sulfide 1 Reagent 100 mL,
1.1.7.01.01.02.002.00087 Sulfide 1 Reagent 100 mL,
1.1.7.01.01.02.005.00207 Sulfide 1 Reagent 100 Ml, Hach 1816-32
1.1.7.01.01.02.005.00206 Sulfide 2 Reagen Solution 500 Ml, (500 Test)
1.1.7.01.01.02.002.00079 Sulfide 2 reagent
1.1.7.01.01.02.002.00088 Sulfide 2 reagent
1.1.7.01.01.02.005.00208 Sulfide 2 Reagent 100 Ml, Hach 1817-32
1.1.7.01.01.01.022.00286 Sunscreen Aluminium
1.1.7.01.01.01.022.00782 Takel ( Kapasitas 3 Ton )
1.1.7.01.01.01.022.00153 Talang air hujan 1/2 lingkaran (gutter)
1.1.7.01.01.01.022.00593 Talang PVC U-15 cm
1.1.7.01.01.01.022.00162 Talang sudut dalam/luar (gutter angle)
1.1.7.01.01.01.022.00542 Tambang Plastik
1.1.7.01.01.01.022.00781 Tambang Plastik
1.1.7.01.01.01.022.00055 Tanah Urug Pilihan
1.1.7.01.01.01.022.00511 Tangki Air kapasitas 5000 LITER
1.1.7.01.01.01.022.00510 Tangki Fiber Glass 2 M3
1.1.7.01.01.01.022.00778 Tangki Horisontal 1000 iter (Dengan kaki)
1.1.7.01.01.01.022.00779 Tangki Horisontal 5000 iter (Dengan kaki)
1.1.7.01.01.01.022.00762 Tangki Stanless Steel 1000 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00768 Tangki Stanless Steel 1100 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00769 Tangki Stanless Steel 1500 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00763 Tangki Stanless Steel 1500 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00764 Tangki Stanless Steel 2100 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00770 Tangki Stanless Steel 2300 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00771 Tangki Stanless Steel 3200 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00765 Tangki Stanless Steel 5000 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00760 Tangki Stanless Steel 600 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00766 Tangki Stanless Steel 660 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00767 Tangki Stanless Steel 800 Liter (Pakai Kaki)
1.1.7.01.01.01.022.00761 Tangki Stanless Steel 800 Liter (Tanpa Kaki)
1.1.7.01.01.01.022.00773 Tangki Tanam 1100 Liter (Dengan Pelindung Beto
1.1.7.01.01.01.022.00777 Tangki Tanam 1100 Liter (Langsung Pendam)
1.1.7.01.01.01.022.00774 Tangki Tanam 2100 Liter (Dengan Pelindung Beto
1.1.7.01.01.01.022.00775 Tangki Tanam 2500 Liter (Dengan Pelindung Beto
1.1.7.01.01.01.022.00772 Tangki Tanam 550 Liter (Dengan Pelindung Beton
1.1.7.01.01.01.022.00776 Tangki Tanam 550 Liter (Langsung Pendam)
1.1.7.01.01.01.022.00748 Tarikan Laci/Lemari Standard (Biasa)
1.1.7.01.01.01.022.00749 Tarikan Laci/Lemari Standard (Sedang)
1.1.7.01.01.01.022.00750
100 Tarikan Laci/Lemari Standard (Tinggi)
1.1.7.01.01.01.022.00746 Tarikan Pintu (Standard /Biasa)
1.1.7.01.01.01.022.00747 Tarikan Pintu (Standard /Biasa)
1.1.7.01.01.01.022.00846 Tatapakan
1.1.7.01.01.01.022.00190 TeakWood
1.1.7.01.01.01.022.00191 TeakWood
1.1.7.01.01.01.022.00192 TeakWood
1.1.7.01.01.01.022.00193 TeakWood
1.1.7.01.01.01.022.00470 Tee flange Dia. 63 mm
1.1.7.01.01.01.022.00513 Tee GI Dia. 20 mm
1.1.7.01.01.01.022.00522 Tee PVC 32x20 mm
1.1.7.01.01.01.022.00521 Tee PVC 32x32 mm
1.1.7.01.01.01.022.00520 Tee PVC 63x32 mm
1.1.7.01.01.01.022.00519 Tee PVC 63x50 mm
1.1.7.01.01.01.022.00518 Tee PVC 63x63 mm
1.1.7.01.01.01.022.00514 Tee PVC Dia. 20 mm
1.1.7.01.01.01.022.00517 Tee PVC Dia. 25x25 mm
1.1.7.01.01.01.022.00515 Tee PVC RRJ Dia. 63x63 mm, ( Setara Vinillon )
1.1.7.01.01.01.022.00516 Tee RRJ Dia. 63x32 mm
1.1.7.01.01.01.022.00523 Tee Y 50x50 mm
1.1.7.01.01.01.013.00011 Tegel Badak PC 30 x 30
1.1.7.01.01.01.013.00012 Tegel Badak Warna 30 x 30
1.1.7.01.01.01.013.00007 Tegel PC 30 x 30
1.1.7.01.01.01.013.00009 Tegel Warna 30 x 30
1.1.7.01.01.01.022.00573 Tempat Sabun Poslin
1.1.12.01.03.0013.00010 Tempat Tidur Medis
1.1.12.01.03.0013.00016 Tensimeter Digital
1.1.7.01.01.01.022.00167 Tepung Gypsum
1.1.7.01.01.01.022.00116 Terpentin
1.1.7.01.01.01.011.00009 Tiang beton
1.1.7.01.01.01.011.00010 Tiang beton
1.1.7.01.01.01.011.00011 Tiang beton
1.1.7.01.01.01.011.00012 Tiang beton
1.1.7.01.01.01.011.00013 Tiang Beton Mutu K-225
1.1.7.01.01.01.011.00014 Tiang Beton Mutu K-225
1.1.7.01.01.01.011.00015 Tiang Beton Mutu K-300
1.1.7.01.01.01.011.00016 Tiang Beton Mutu K-300
1.1.7.01.01.01.022.00826 Tiang dan Rangka RPPJ
1.1.7.01.01.01.022.00827 Tiang dan Rangka RPPJ
1.1.7.01.01.01.022.00697 Tiang Listrik
1.1.7.01.01.01.022.00481 Tiang Listrik, Pipa GI
1.1.7.01.01.01.022.00828 Tiang Lurus
1.1.7.01.01.01.022.00829 Tiang Overhead
1.1.7.01.01.01.022.00830 Tiang Overhead
1.1.7.01.01.01.022.00831 Tiang penyangga
1.1.7.01.01.01.022.00832 Tiang penyangga
1.1.7.01.01.01.022.00833 Tiang penyangga
1.1.7.01.01.01.022.00834 Tiang PJU
1.1.7.01.01.01.022.00835 Tiang PJU
1.1.7.01.01.01.022.00836 Tiang PJU
1.1.7.01.01.01.022.00837 Tiang Rambu
1.1.7.01.01.01.022.00838 Tiang Rambu
1.1.7.01.01.01.022.00839 Tiang Siku
1.1.7.01.01.01.022.00840 Tiang Siku
1.1.12.01.03.0013.00017 Timbangan Badan Digital
1.1.7.01.01.01.021.00004 Tiner A
1.1.7.01.01.01.021.00005 Tiner B
1.1.7.01.01.01.022.00698 Trafo 80 Watt / 220
1.1.7.01.01.02.005.00209 Trinatrium Sitrat Anhidrat (Na3c6h5o7), P.a 500 Gr
1.1.7.01.01.01.022.00171 Triplek
1.1.7.01.01.01.022.00172 Triplek
1.1.7.01.01.01.022.00173 Triplek
1.1.7.01.01.01.022.00588 Urinoir Lengkap
1.1.7.01.01.01.022.00292 Venetion Blind
1.1.7.01.01.01.022.00546 Vent GIP
1.1.7.01.01.01.022.00127 Vernis
1.1.7.01.01.01.022.00293 Vertical Blind
1.1.7.01.01.01.022.00610 Wall Flasing
1.1.7.01.01.01.022.00184
100 Wall Paper
1.1.7.01.01.01.022.00185 Wall Paper
1.1.7.01.01.01.022.00186 Wall Paper
1.1.12.01.03.0013.00012 Wall Termometer
1.1.7.01.01.01.022.00584 Wastafel Bulat Lengkap
1.1.7.01.01.01.022.00575 Wastafel Lengkap INA
1.1.7.01.01.01.022.00574 Wastafel Lengkap TOTO LW 230
1.1.7.01.01.01.022.00586 Wastafel Meja
1.1.7.01.01.01.022.00585 Wastafel Type Amerika Standard
1.1.7.01.01.01.022.00594 Water Drain + Acsesoris
1.1.7.01.01.01.022.00850 Water Meter
1.1.7.01.01.01.022.00502 Water Meter Dia. 20 mm
1.1.7.01.01.01.022.00558 Water Mur 1/2"
1.1.7.01.01.02.002.00094 Water pollution CRM ERA Cat. #213
1.1.7.01.01.02.002.00089 Water pollution CRM ERA Cat. #499
1.1.7.01.01.02.002.00090 Water pollution CRM ERA Cat. #504
1.1.7.01.01.02.002.00091 Water pollution CRM ERA Cat. #506
1.1.7.01.01.02.002.00092 Water pollution CRM ERA Cat. #741
1.1.7.01.01.02.002.00093 Water pollution CRM ERA Cat. #743
1.1.7.01.01.01.006.00044 Water Profing Emulsion
1.1.7.01.01.01.006.00045 Water Profing Membrane
1.1.7.01.01.01.022.00548 Water Stop
1.1.7.01.01.01.022.00549 Water Stop
1.1.7.01.01.02.002.00095 Water Suplay CRM ERA Cat. #693
1.1.7.01.01.01.022.00262 Wiremesh M6
1.1.7.01.01.01.022.00263 Wiremesh M8
1.1.7.01.01.01.022.00110 Wood Filler /IMPRA
1.1.7.01.01.01.022.00150 Wood plank
1.1.7.01.01.01.022.00151 Wood plank
1.1.7.01.01.01.022.00152 Wood plank
1.1.7.01.01.01.022.00113 Woodstain /IMPRA
1.1.7.01.01.01.014.00037 Wuwung
1.1.7.01.01.01.022.00641 Wuwung atap UPVC (Top Ridge, tebal 10mm, p=+
1.1.7.01.01.02.001.00031 ZincoVer 5 Zink Reagent Powder Pillows 10 mL,
1.1.7.01.01.02.001.00039 ZincoVer 5 Zink Reagent Powder Pillows 10 mL,
1.1.7.01.01.02.005.00210 Zincover 5 Zink Reagent Powder Pillows 10 Ml, 100/pkg, Hach 21066-69
1.1.7.01.01.02.005.00211 Zn-acetat Dihidrat P.a 250 Gr, Merck
100
100
Column3 Column4 Column5
M3" 185,000.00
60 x 120 Lembar 148,500.00
25 gr Botol 5,993,000.00
Buah 602,000.00
500 gr Botol 2,260,000.00
Hach 21223-26, 50 mL Buah 1,534,500.00
Teknis 70% 1 L Botol 183,700.00
Sigle Sided (Roll=1,2 x 50 Roll 404,250.00
Double Sided (Roll=1,2 x Roll 514,500.00
Bubble (Roll=1,2 x 50 m) m2 703,500.00
rate Ar 500 Gr, Prolabo Botol 4,418,300.00
Botol 11,228,500.00
500 gr Botol 1,880,000.00
Lembar 4,000.00
buah 27,500.00
buah 256,000.00
20 liter Jerigen 255,000.00
Ls 150,000.00
HACH 14577-99 Pkg 3,276,900.00
Aspal Bitumen Kg 14,300.00
Aspal Cement Kilogram 11,900.00
Aspal AC-WC terhampar Ton 11,700.00
Asphalt liquid mixer 1000 Liter 9,200.00
Kg 13,605.00
Ton 1,200,833.00
TES UPLOAD KOMPON kg 13,840.00
TES UPLOAD KOMPON kg 13,840.00
TES UPLOAD KOMPON kg 13,840.00
TES UPLOAD KOMPON kg 13,840.00
TES UPLOAD KOMPON kg 2,545,200.00
TES UPLOAD KOMPON kg 2,545,200.00
TES UPLOAD KOMPON kg 2,545,200.00
TES UPLOAD KOMPON kg 18,613.00
TES UPLOAD KOMPON kg 18,613.00
TES UPLOAD KOMPON kg 18,613.00
TES UPLOAD KOMPON kg 18,613.00
Ton 1,506,090.00
Ton 1,149,000.00
Ton 1,162,500.00
Setara JAINDO m2 164,500.00
Setara JAINDO m2 276,200.00
Ukuran 102 x 180 x 4 mm lbr 87,500.00
Ukuran 105 x 180 x 4 mm lbr 63,700.00
uk/ 95cm x 200cm lbr 180,280.00
uk/ 40cm x 106cm lbr 51,000.00
uk/ 96cm x 195cm lbr 166,650.00
Gelombang lbr 76,500.00
Gelombang lbr 63,750.00
Pres Molen Oven Jatiwangibuah 2,900.00
Pres Bakar KW 1 buah 2,900.00
Pres Molen Oven KW 2 buah 2,900.00
lbr 60,000.00
Ukuran 80 cm x 180 cm x lbr 70,000.00
Ukuran 240 cm x 105 cm lbr 98,000.00
Ukuran 210 cm x 105 cm lbr 87,000.00
Ukuran 150 cm x 105 cm lbr 63,000.00
m2 160,000.00
uk/ 95cm x 200cm lbr 272,700.00
uk/ 400cm x 496cm lbr 212,100.00
Setara : Alderon, Avantguam2 231,000.00
Setara : Alderon, Avantguam2 165,000.00
m2 150,000.00
Las Listrik, Kawat Elektr Paket 2,200,000.00
Kg 80,250.00
buah 352,750.00
Buah 45,000.00
Buah 110,000.00
Ø 5 s/d 7 - 4 m btg 9,000.00
Ø 7 s/d 10 - 4 m btg 12,500.00
Ø 8 s/d 12 - 6 m Batang 52,500.00
Ø 12 s/d 15 - 6 m Batang 60,000.00
Iron Plate 5Kg Buah 362,600.00
Pemasangan tiang penyangBatang 539,700.00
Lokal Garut Buah 1,000.00
Lokal Urug Buah 900.00
Buah 1,000.00
Buah 10,500.00
Ukuran 8 x 20 x 30 Buah 4,500.00
Ukuran 8 x 10 x 20 Buah 3,500.00
unit 3,676,900.00
m3 157,000.00
M3" 210,000.00
Pkg 965,500.00
M3 60,000.00
Bentuk bulat /lonjong M3" 215,000.00
Screen M3" 287,231.00
M3" 292,481.00
m3 240,000.00
m3 225,000.00
m3 210,000.00
10 x 20 x 35 Buah -
15 x 35 x 50 K-225 Buah -
M3" -
Bt. Andesit M2 165,000.00
Bt Candi M2 150,000.00
kg 18,000.00
buah 11,250.00
buah 1,500.00
Cholesterol 4x100 mL/1x5Kit 1,650,000.00
Triglycerides 2x50 mL/1x Kit 1,210,000.00
Glucose-GOD PAP 4x100 Kit 1,196,250.00
Uric Acid 4x25 mL/1x5 m Kit 990,000.00
Widal Antigen Set Kit 1,072,500.00
Uric Acid 2x100 mL/1x5 Kit 1,375,000.00
M2 350,000.00
buah 215,000.00
buah 250,000.00
Bh 160,500.00
Bh 189,200.00
Bh 200,500.00
Buah 250,000.00
Bh 280,500.00
Buah 45,000.00
90 drj, ( Setara Vinillon) Buah 115,000.00
Besi Kilogram 19,000.00
Besi Kanal 8 Kilogram 25,000.00
U-24 (Bulat /Persegi Rata-rkg 13,500.00
U-32 /U-39 (Bulat /PersegiKg 15,800.00
kg 18,500.00
(rata-rata) kg 22,750.00
6 meter btg 110,400.00
6 meter btg 216,000.00
6 meter btg 372,000.00
6 meter btg 452,000.00
6 meter btg 824,000.00
6 meter btg 179,200.00
6 meter btg 204,800.00
6 meter btg 243,200.00
6 meter btg 328,000.00
6 meter btg 560,800.00
6 meter btg 647,200.00
6 meter btg 861,600.00
6 meter btg 1,780,000.00
(rata-rata) Kg 15,800.00
(rata-rata) C 100.50.20/C 7kg 24,000.00
(rata-rata) kg 18,200.00
(rata-rata) Kg 577,500.00
(rata-rata) ex DN-SII kg 19,000.00
(rata-rata) ex LN kg 33,250.00
M2 20,000.00
M2 18,400.00
M2 13,200.00
M2 26,300.00
15 mm 120 x 240 Lembar 230,000.00
18 mm 120 x 240 Lembar 185,000.00
25 mm 120 x 240 Lembar 209,000.00
50 pcs, HACH 14160-66 Pkg 1,028,000.00
t=0,75 mm L=1m, P=(disesm 110,000.00
t=1,00 mm L=1m, P=(disesm 137,500.00
Ls 1,750,000.00
Box culvert 1500 x 1500 x Buah 10,658,800.00
Box culvert 2000 x 2000 x Buah 22,205,500.00
Box culvert 500 x 500 x 12Buah 1,966,900.00
Box culvert 800 x 800 x 12Buah 4,377,900.00
Unit 290,000.00
Buah 290,000.00
Buah 55,000.00
bh 52,500.00
Bh 111,100.00
500 gr Botol 6,581,500.00
Pres Bulat ex Jatiwangi buah 7,700.00
Buah 5,000.00
Buah 8,500.00
Buah 5,000.00
m2 274,500.00
M2 110,600.00
buah 24,600.00
buah 7,700.00
buah 7,700.00
Buah 45,000.00
Ø 20 cm (1 m2) m2 58,500.00
Ø 30 cm (1 m2) m2 81,000.00
Ø 40 cm (1 m2) m2 97,750.00
Ø 50 cm (1 m2) m2 144,000.00
Ø 60 cm (1 m2) m2 188,000.00
Ø 70 cm (0.50 m2) m2 190,000.00
Ø 80 cm (0.50 m2) m2 192,000.00
Ø 100 cm (0.50 m2) m2 228,000.00
Buah 388,100.00
Liter 34,300.00
Liter 44,300.00
(Cisangkan) Meter 125,000.00
bh 49,500.00
Kualitas : Seiv, Kuda Terb Liter 130,000.00
Kg 75,000.00
2,5 liter Kaleng 138,270.00
Kualitas : Dulux, Jotun, M Liter 67,540.00
Kualitas : Sika Kg 125,000.00
Kualitas : Seiv, Avian, GloKg 58,000.00
Kualitas : Mowilex, Dulux Kg 72,000.00
Liter 120,480.00
5 kg Kg 22,000.00
5 kg Kg 231,000.00
2,5 liter Liter 225,000.00
2,5 liter Liter 307,000.00
cat tembok eksterior pail 690,000.00
5 kg sanlex hitam/putih Galon 180,000.00
5 kg sanlex hitam/putih Galon 180,000.00
5 kg avian Galon 252,000.00
Kg 30,000.00
3 liter Liter 105,000.00
3 liter Kaleng 75,000.00
2,5 liter Liter 200,000.00
2,5 liter Liter 210,000.00
Kg 30,000.00
Kg 91,000.00
Buah 351,000.00
buah 103,900.00
Botol 50,000.00
HACH 12710-99 Pkg 2,147,000.00
HACH 12710-102 Pkg 3,218,050.00
14087-047-N Pkg 5,337,000.00
14087-047-N Pkg 5,941,100.00
Buah 25,000.00
buah 973,900.00
Diatro Cleaner 1L Botol 506,000.00
buah 1,861,900.00
unit 940,100.00
Warna Standard TOTO C 2Unit 2,913,855.00
Warna Standar INA buah 2,080,500.00
Buah 185,000.00
buah 186,000.00
Sistem Jet TOTO unit 3,084,000.00
Porselin Warna TOTO unit 353,100.00
Porselin Putih TOTO unit 311,900.00
Buah 7,500.00
m2 4,200.00
bh 2,500.00
Kg 5,000.00
Ø 15 cm Set 99,170.00
Ø 20 cm Set 137,500.00
Buah 16,000.00
n H2o, 100 Ml, Merck 1.25029.0100 Botol 2,623,700.00
In H2o, 100 Ml, Merck 1.25032.0100 Botol 2,623,700.00
n H2o, 100 Ml, Merck 1.25030.0100 Botol 2,623,700.00
In H2o, 100 Ml, Merck 1.25033.0100 Botol 2,623,700.00
n H2o, 100 Ml, Merck 1.25031.0100 Botol 2,623,700.00
g/l No3-n In H2o, 100 Ml, Merck 1.25 Botol 2,623,700.00
g/l No3-n In H2o, 100 Ml, Merck 1.25 Botol 2,623,700.00
g/l No3-n In H2o, 100 Ml Merck 1.250 Botol 2,623,700.00
/l No3-n In H2o, 100 Ml, Merck 1.250 Botol 2,623,700.00
g/l No3-n In H2o, 100 Ml, Merck 1.25 Botol 2,623,700.00
Mg/l No2-n In H2o, 100 Ml, Merck 1.2 Botol 2,623,700.00
Hach 21058-69 Pkg 2,975,000.00
Hach 21058-69 Pkg 3,423,200.00
Hach 14033-32 Botol 1,535,000.00
Hach 14033-32 Botol 1,766,600.00
silver+accesories+kaca po m2 425,000.00
Coklat /Hitam+accesories+m2 475,000.00
silver + kaca polos 5 mm, m2 1,125,000.00
coklat /hitam + kaca polos m2 1,250,000.00
Kelengkapannya kapasitas U 1 nit 415,250,000.00
Kualitas : Propan, Isamu Kg 28,500.00
Kualitas : Cap Kucing Kg 25,000.00
Kg 49,900.00
Kualitas : San Polac, AlfagKg 40,000.00
Kg 43,740.00
Liter 13,500.00
unit 883,828,300.00
Diatro Dil 5 P 20L Box 2,057,000.00
setara : BELLUCI, SAFIL Unit 130,000.00
setara : DEKKSON, DOR unit 287,500.00
setara : DEKKSON, DOR Unit 753,250.00
Unit 17,250.00
Minimalis, Stainless Steel Unit 60,000.00
Buah 2,500.00
buah 8,400.00
buah 62,800.00
100/pkg, HACH 21055-69 Pak 1,980,440.00
buah 6,500.00
bh 18,000.00
HACH 7005-9 Pkg 1,790,000.00
HACH 7005-9 Pkg 2,055,900.00
0 ml (90 kW) unit 353,531,000.00
Pasang 27,500.00
setara : HPP, ESSEN, Pasang 10,000.00
setara : DEKSON Pasang 2,172,500.00
setara : DORMA Pasang 3,245,000.00
setara HENDERSON Buah 140,000.00
setara : HPP, ESSEN, Pasang 27,000.00
setara : HPP, ESSEN, Pasang 38,000.00
setara : DEKSON, SOLID Pasang 45,000.00
setara : DEKSON, SOLID Pasang 80,000.00
silver /kuningan bh 82,500.00
stainless steel bh 115,500.00
unit 183,420.00
unit 3,835,250.00
unit 4,585,620.00
unit 7,371,000.00
unit 70,030.00
Buah 65,000.00
Bh 110,800.00
Bh 115,800.00
Bh 266,850.00
Bh 367,500.00
Kg 38,500.00
Buah 130,000.00
buah 546,800.00
buah 1,406,800.00
Buah 55,000.00
Ukuran F4 70 gr Rim 140,000.00
Polos /Putih : Ukuran 120 M2 210,000.00
Motif Ukuran Pintu (3 x 80M2 172,500.00
Buah 28,250.00
Kg 18,450.00
set 16,940.00
unit 283,470.00
Buah 1,300,000.00
Bh 1,700,000.00
Buah 152,500.00
Kapasitas 60 liter / menit Unit 26,875,600.00
Std=14,5 bh/m2 (Monier, cBuah 11,800.00
Std=14,5 bh/m2 (Monier, cbuah 7,700.00
ex Jatiwangi Segitiga buah 4,600.00
buah 15,500.00
Std=14 bh/m2 (KIA,M-clasBuah 37,500.00
Std=14 bh/m2 (KIA,M-clasbuah 11,000.00
Std=14 bh/m2 (KIA,M-clasbuah 13,750.00
buah 3,900.00
Kualitas Rainbowroof, Mulm2 137,500.00
Sakura roof M2 77,000.00
Std= 18 bh/m2 Buah 3,500.00
Std= 18 bh/m2 Buah 5,000.00
Std= 18 bh/m2 buah 3,500.00
buah 27,000.00
buah 40,000.00
U-20 cm2 m2 42,750.00
U-30 cm2 m2 57,000.00
U-40 cm2 m2 71,250.00
KW 1 DN Polish (Kualitas m2: 370,700.00
KW 1 DN Unpolish (Kualitas m2 540,100.00
20 x 20 (Cisangkan) Buah 27,500.00
20 x 20 (lokal/Setempat) Buah 5,500.00
30 x 30 (Cisangkan) Buah 25,950.00
30 x 30 (Lokal/Setempat) Buah 12,370.00
(120 x 240) cm, t = 4 mm Lembar 68,000.00
(120 x 240) cm, t = 6 mm Lembar 108,000.00
(120 x 240) cm, t = 9 mm Lembar 143,000.00
setara BOLZANO Buah 80,000.00
setara BELOCA bh 20,600.00
setara BINOCHE Buah 30,000.00
setara BINOCHE Buah 40,000.00
(120 x 240) cm, t = 9 mm Lembar 76,700.00
(120 x 240) cm, t = 12 mmLembar 98,000.00
2.5 Liter Botol 3,988,700.00
Pasang 44,000.00
Silver Per Sampel 30,000.00
Stainless / Kuningan Buah 73,500.00
Buah 7,778,500.00
Unit 200,000.00
kg 20,000.00
unit 156,740.00
50 gr Botol 4,807,900.00
60 x 60 x 1.8 (6 m) btg 244,100.00
60 x 60 x 1.6 (6 m) btg 217,000.00
50 x 50 x 2.5 (6 m) btg 282,600.00
50 x 50 x 1.0 (6 m) btg 113,000.00
50 x 50 x 1.6 (6 m) btg 180,800.00
50 x 50 x 1.3 (6 m) btg 146,900.00
40 x 60 x 2.0 (6 m) btg 226,000.00
40 x 60 x 1.6 (6 m) btg 180,800.00
40 x 40 x 1.8 (6 m) btg 162,700.00
40 x 40 x 1.6 (6 m) btg 144,600.00
40 x 40 x 1.3 (6 m) btg 117,500.00
40 x 40 x 1.0 (6 m) btg 90,400.00
30 x 60 x 1.8 (6 m) btg 183,100.00
30 x 60 x 1.6 (6 m) btg 162,700.00
30 x 30 x 2.0 (6 m) btg 135,600.00
30 x 30 x 1.6 (6 m) btg 108,500.00
30 x 30 x 1.3 (6 m) btg 88,100.00
30 x 30 x 1.0 (6 m) btg 67,800.00
20 x 40 x 1.8 (6 m) btg 122,000.00
20 x 40 x 1.6 (6 m) btg 108,500.00
20 x 40 x 1.3 (6 m) btg 88,100.00
20 x 40 x 1.0 (6 m) btg 67,800.00
50 x 25 x 2.0 (6 m) btg 169,500.00
50 x 25 x 1.6 (6 m) btg 135,600.00
50 x 25 x 1.3 (6 m) btg 110,200.00
50 x 25 x 1.0 (6 m) btg 84,700.00
20 x 20 x 2.0 (6 m) btg 90,400.00
20 x 20 x 1.6 (6 m) btg 72,300.00
20 x 20 x 1.3 (6 m) btg 58,700.00
20 x 20 x 1.0 (6 m) btg 45,200.00
8 x 10 x 25, bentuk segi emBuah 7,500.00
8 x 15 x 25, bentuk segi emBuah 9,000.00
8 x 20 x 20, Bentuk : MercyBuah 9,500.00
Kualitas : Taco M2 112,000.00
unit 9,163,400.00
bh 4,200.00
HACH 21224-26 Botol 990,000.00
Impra AL 961 Clear Gloss Pc 2,133,400.00
(Upah, Bahan dan Alat) ttk 150,000.00
(Upah, Bahan dan Alat) ttk 150,000.00
Set 4,610,000.00
- Unit 8,842,822.00
- Unit 6,161,745.00
Tabung 100,000.00
m2 59,700.00
Unit 120,000.00
Buah 65,000.00
m2 493,800.00
m2 663,500.00
1 x 1.5 Setara : Eterna, Su Roll 130,000.00
1 x 2.5 Setara : Eterna, Su Roll 225,000.00
2 x 2.5 Setara : Eterna, Su Roll 570,000.00
2 x 1.5 Setara : Eterna, Su Roll 380,000.00
3 x 1.5 Setara : Eterna, Su Roll 550,000.00
3 x 2.5 Setara : Eterna, Su Roll 750,000.00
3 x 4 Setara : Eterna, Sup Roll 3,200,000.00
2 x 1.5 Setara : Eterna, S Roll 630,000.00
2 x 2.5 Setara : Eterna, S Roll 987,000.00
3 x 1.5 Setara : Eterna, S Roll 942,900.00
3 x 2.5 Setara : Eterna, S Roll 1,344,000.00
4 x 1.5 Setara : Eterna, S Roll 1,210,650.00
4 x 2.5 Setara : Eterna, S Roll 1,879,500.00
m2 100,270.00
m2 142,270.00
m2 202,120.00
m2 431,020.00
m2 483,520.00
m2 221,020.00
m2 273,520.00
m2 404,770.00
m2 99,750.00
m2 141,750.00
Polos m2 1,450,000.00
Airbrush m2 1,750,000.00
Kuningan m2 2,200,000.00
m2 58,270.00
M2 72,300.00
M2 94,300.00
M2 166,000.00
Grafier 3mm /5mm /8mm m2 1,050,000.00
Grafier Airbrush 3mm /5 m2 1,205,000.00
m2 242,020.00
m2 79,270.00
m2 76,120.00
m2 142,270.00
Pasang 155,600.00
Bahan Setara Kayu GunungUnit 8,000,000.00
Kafasitas 10-20 ekor Unit 25,000,000.00
Meter 500,000.00
11x40 cm, p=0,50 m (LokaBuah 30,000.00
11x20 cm, p=0,50 m (LokaBuah 25,000.00
11x20 cm, p=0,40 m (PerssBuah 18,000.00
11x20 cm, p=0,20 m (PerssBuah 9,500.00
M3" 70,000.00
(1 karung/zak=25 Kg) Zak 45,000.00
Kg 4,500.00
M2 30,600.00
Meter 6,500.00
Kg 90,000.00
Bahan Karet, Lebar 150 cmMeter 246,750.00
Bahan Karet, Lebar 225 cmMeter 338,100.00
Ex DN m2 192,500.00
Buah 8,500.00
Kg 27,500.00
Kg 26,300.00
kg 30,000.00
Ukuran 1,00x0,5x2,00 Bh 450,000.00
kg 35,000.00
Ukuran 1,00x0,5x2,00 Bh 500,000.00
Barbwire/ Lokal kg 62,500.00
m2 2,500.00
kg 62,500.00
KW 1 DN Corak/Warna/ AntiM2 57,500.00
KW 1 DN Putih /polos (Kual
m2 92,570.00
KW 1 DN Corak/Warna/ AntiM2 97,500.00
KW 1 DN Putih /polos (Kual
m2 40,820.00
KW 1 DN Putih /polos (Kual
M2 55,000.00
KW 1 DN Corak/Warna/ AntiM2 55,000.00
KW 1 DN Putih /polos (Kual
m2 97,980.00
KW 1 DN Corak/Warna/ Antim2 103,500.00
KW 1 DN Putih /polos (Kual
M2 68,000.00
KW 1 DN Corak/Warna/ AntiM2 65,000.00
KW 1 DN Putih /polos (Kual
m2 98,320.00
KW 1 DN Corak/Warna/ Antim2 104,070.00
KW 1 DN Putih /polos (Kual
m2 98,320.00
KW 1 DN Corak/Warna/ AntiM2 105,000.00
KW 1 DN Putih /polos (Kual m2 138,000.00
KW 1 DN Corak/Warna/ Anti m2 141,450.00
KW 1 DN Putih /polos (Kual m2 200,670.00
KW 1 DN Corak/Warna/ Anti m2 241,500.00
diameter 1/2" Buah 15,000.00
Standard Lokal ( 1 LubangBuah 393,000.00
Non Standard Franke( 1 Lubuah 1,554,400.00
Non Standard Franke( 1 Lubuah 1,756,200.00
Buah 5,000.00
Buah 9,000.00
Buah 8,900.00
Buah 31,500.00
buah 49,000.00
Buah 5,000.00
Buah 6,000.00
Buah 6,000.00
Buah 25,000.00
Buah 35,000.00
Buah 228,900.00
(berbagai ukuran) buah 6,500.00
Buah 104,000.00
buah 158,700.00
Buah 25,000.00
buah 363,100.00
buah 62,000.00
Biasa Buah 15,000.00
Biasa Buah 15,000.00
Buah 156,000.00
Kg 6,000.00
setara DEKSON, SOLID Set 630,000.00
setara YALE Set 6,897,000.00
Buah 75,000.00
bh 55,000.00
setara BELOCA, BOSSINIbh 95,700.00
setara DEKSON, SOLID Buah 130,000.00
setara HUBEN, 808 Buah 10,000.00
setara DEKSON, SOLID bh 484,000.00
setara ANCHOR, ROYAL,Buah 50,000.00
setara TESA, Set 184,000.00
setara YALE, SOLID, SEI set 483,000.00
Kursi guru model stacking,Unit 926,800.00
Ukuran P x L x T (cm) : 42Unit 998,500.00
1.3 mm t = 1,3 mm (3") str Meter 99,800.00
1.3 mm t = 1,3 mm (4") str Meter 126,413.00
1.3 mm t = 1,3 mm (3") str Meter 126,413.00
1.3 mm t = 1,3 mm (4") str Meter 139,720.00
Set 100,000.00
Liter 11,875.00
Liter 13,525.00
Ton 1,172,000.00
500 gr Botol 3,532,000.00
Lem Fox , putih Kilogram 39,900.00
Lem Karpet Fox Pack 49,100.00
kg 205,850.00
Setara AICA AIBON, FOXkg 61,600.00
setara : TANGOT, ISOPL kg 110,000.00
Setara , FOX, RAJAWALIkg 22,000.00
Tube 10,000.00
setara : QUICKCURE kg 121,000.00
Ukuran P x L x T (cm) : 80Unit 4,852,000.00
500 gr Botol 7,546,500.00
(3000 x 200 x 8.0 mm) lbr 55,400.00
(2400 x 200 x 8.0 mm) lbr 44,000.00
(3000 x 200 x 12.0 mm) lbr 83,100.00
(2400 x 200 x 12.0 mm) lbr 66,800.00
(2400 x 300 x 8.0 mm) lbr 66,000.00
(2400 x 300 x 12.0 mm) lbr 101,000.00
(Setara Jaya Board Panjangbtg 17,900.00
(Setara Jaya Board Panjangbtg 19,500.00
(Setara Jaya Board Panjangbtg 60,400.00
(Setara Jaya Board Panjangbtg 32,500.00
buah 32,500.00
terpasang, L=7 cm s/d 10 cm2 17,000.00
terpasang, L=10 cm s/d 15 m2 24,000.00
terpasang, l=15 cm s/d 20 m2 27,000.00
1 cm Meter 4,200.00
10 cm Meter 12,500.00
2 cm Meter 7,280.00
4 cm Meter 9,350.00
5 cm Meter 10,750.00
Pack 27,500.00
Louding Besi Unit 7,435,500.00
Diatro Lyse Diff + key 1L Botol 1,936,000.00
buah 18,400.00
buah 24,800.00
buah 13,600.00
buah 7,200.00
buah 53,600.00
buah 44,800.00
buah 84,800.00
buah 8,800.00
buah 112,000.00
buah 21,600.00
Unit 600,000.00
Buah 98,000.00
Tatapakan Semen, batu danBuah 196,200.00
500 gr Botol 4,957,900.00
1P 6A C MCB Setara SchneBuah 65,000.00
1P 10A C MCB Setara Schn Buah 65,000.00
1P 16A C MCB Setara Schn Buah 65,000.00
1P 25A C MCB Setara Schn Buah 62,000.00
3P 6A C MCB Setara SchneBuah 270,000.00
3P 10A C MCB Setara Schn Buah 270,000.00
3P 16A C MCB Setara Schn Buah 270,000.00
3P 25A C MCB Setara Schn Buah 270,000.00
Ukuran P x L x T (cm) : 12Unit 4,000,000.00
Ukuran P x L x T (cm) : 60Unit 1,446,900.00
m 49,500.00
Ukuran 0,8 x 2.00 Buah 495,000.00
3 mm 120 x 240 Glossy /DoLembar 110,000.00
6 mm 120 x 240 Glossy /DoLembar 129,200.00
8 mm 120 x 240 Glossy /DoLembar 151,200.00
Penutup /pelindung Kg 76,000.00
Kualitas : Cap Pedang, Be Kg 40,000.00
Kualitas : Cap Bintang,Ok Kg 23,600.00
Pkg 2,605,200.00
Pkg 6,527,100.00
Pkg 3,306,600.00
Botol 2,769,500.00
Display : 4.3-Inch Touch SUnit 6,530,000.00
Botol 1,438,400.00
HACH 2376626 Botol 985,000.00
HACH 2376626 Botol 1,108,800.00
Botol 827,700.00
Kg 27,500.00
bh 200,000.00
Screen Size : 65-100 inch Unit 9,990,000.00
4 mm 120 x 240 Lembar 87,900.00
9 mm 120 x 240 Lembar 161,600.00
12 mm 120 x 240 Lembar 185,000.00
18 mm 120 x 240 Lembar 249,600.00
buah 7,500.00
buah 13,000.00
buah 7,350.00
ydrochloride (Neda) 5 Gr, Merck Pkg 2,067,800.00
500 mL Botol 1,175,000.00
Unit 1,220,000.00
50 Gr, Merck Pkg 1,162,000.00
4) P.a 500 Gr, Merck Pkg 1,617,900.00
Pkg 1,227,500.00
Pkg 1,239,200.00
25 gr Botol 3,985,000.00
Gr, Merck 106557 Pkg 4,682,500.00
r, Merck 106557 Pkg 2,324,400.00
Gr, Merck 106578 Pkg 2,620,300.00
Pkg 3,491,400.00
Pkg 925,500.00
Pkg 4,138,500.00
Pkg 3,003,600.00
p.a 1000 mL, MERCK Botol 1,154,000.00
p.a 1000 mL, MERCK Botol 1,321,100.00
Botol 178,500.00
Botol 1,151,700.00
Botol 2,291,500.00
Sebagai No3-n 500 Ml, Hach 204649 Botol 1,400,000.00
ows 10 Ml, 100/pkg, Hach 21061-69-4Pkg 2,937,400.00
ows 25 Ml, 100/pkg, Hach 21061-69-4Pkg 3,231,200.00
Powder pillow 100/pkg, Pkg 2,555,700.00
Botol 1,152,100.00
gai N 500 Ml Pkg 2,125,200.00
pkg, Hach 21071-69 Pkg 1,906,100.00
Hach 14065-99 Pkg 2,450,000.00
Hach 14065-99 Pkg 2,820,400.00
pkg, Hach 14065-99 Pkg 2,193,600.00
Pkg 3,752,800.00
uk/ 50cm x 100cm lbr 88,880.00
lbr 55,900.00
Kualitas Rainbowroof, MulLembar 47,500.00
lbr 83,300.00
Kualitas Rainbowroof, Mullbr 30,000.00
m2 81,800.00
Buah 345,000.00
Buah 1,006,250.00
Buah 402,500.00
Pkg 2,776,700.00
Pkg 3,370,400.00
500 gr Botol 4,182,800.00
kg 37,500.00
Kg 85,000.00
Set 250,000.00
BRC Ø 6, tiang Ø 2 inc m2 187,000.00
BRC Ø 8, tiang Ø 2 inc m2 270,000.00
kg 21,000.00
kg 19,250.00
Kg 19,000.00
buah 650.00
kg 69,500.00
kg 36,500.00
kg 35,270.00
15 cm kg 13,500.00
buah 500.00
Dus 1,400.00
Kg 40,000.00
Kg 66,000.00
100 mL Botol 2,040,000.00
240 x 40 x 5 cm Lembar 126,500.00
240 x 40 x 5 cm Lembar 143,000.00
bh 380,000.00
bh 560,000.00
bh 365,200.00
bh 360,000.00
bh 360,000.00
bh 203,000.00
Buah 1,148,700.00
Buah 1,106,784.00
"Ukuran P x L (cm) : 240 xUnit 1,750,000.00
KW 1 Ukuran 1.2 cm x 5 cm2 191,620.00
KW 1 Ukuran 1.2 cm x 5 cm2 215,250.00
KW 1 Ukuran 1.2 cm x 5 cm2 236,250.00
KW 1 Ukuran 1.8 cm x 5 cm2 299,250.00
Ls 2,500,000.00
M3" 220,000.00
M3 136,500.00
m3 190,000.00
M3 94,500.00
Beton, P = 10 cm L= 10 c Buah 49,100.00
Buah 180,700.00
Natural 8 cm (Cisangkan) M2 115,600.00
Warna 8 cm (Cisangkan) M2 135,370.00
Natural 8 cm (Lokal/SetemM2 85,000.00
Warna 8 cm (Lokal/SetempM2 100,000.00
Natural 6 cm (Cisangkan) M2 90,000.00
Warna 6 cm (Cisangkan) M2 112,170.00
Natural 6 cm (Lokal/Setemm2 75,000.00
Warna 6 cm (Lokal/SetempM2 90,000.00
Meter 180,000.00
Meter 65,000.00
(Cat Dasar Beton EksteriorKg 120,480.00
titik 14,650.00
Paket (Termasuk Jasa Kons1 Paket 40,000,000.00
Paket (Termasuk Jasa Kons1 Paket 40,000,000.00
Unit 70,200.00
Titik 1,300,000.00
buah 375,000.00
zincalum Ø 15 cm Buah 40,650.00
zincalum Ø 20 cm Buah 57,650.00
zincalum Ø 15 cm Lembar 45,270.00
zincalum Ø 20 cm Lembar 65,250.00
Setandar TOTO lbr 931,200.00
Bilik Meter2 48,800.00
Paranet Meter2 55,200.00
Lempengan besi ( beam ) BaBatang 2,564,100.00
Tiang penyangga kabel FOSet 342,400.00
Wide Klem Buah 13,900.00
Paku Jalan Aluminium alloBuah 1,193,300.00
Mofte / Resin Pack 467,500.00
Paket 400,000.00
1 Kg Botol 5,125,000.00
Pkg 1,630,000.00
e To Srm 500 Ml, Merck 119898 Pkg 1,648,600.00
pkg/100 (100 Test) Pkg 1,880,000.00
illows 10 Ml Pkg/100 (100 Test) Pkg 2,208,200.00
Buah 1,604,010.00
Buah 1,882,140.00
Buah 2,640,330.00
Buah 1,604,010.00
Buah 2,467,610.00
Buah 2,786,380.00
loor hinge dorma BTS 84 m 3,750,000.00
Besi Standar t=0,4mm m2 425,000.00
Galvalum Standar t=0,4m m2 450,000.00
os) floor hinge dorma BTS 84 m 3,000,000.00
Std Tinggi : ROYAL buah 550,000.00
Std Sedang : Maspion, ET buah 475,000.00
Std Biasa : Polos. CESSA buah 225,000.00
Besi t=0,4mm m2 400,000.00
Galvalum t=0,4mm m2 455,000.00
Buah 31,348,680.00
Buah 46,352,460.00
Uk/ (B=0.30-0.60) dan (H=Buah 4,610,100.00
U2lir dengan 3 stel roda g Buah 58,533,750.00
Ulir dengan 3 stel roda gi Buah 66,890,000.00
Ulir dengan 3 stel roda gi Buah 87,447,500.00
Ulir dengan 3 stel roda gi Buah 96,978,750.00
Uk/ (B=0.60-0.80) dan (H=Buah 9,220,200.00
Uk/ (B=0.30-1.20) dan (H=Buah 11,986,260.00
Uk/ (B=1.00-1.00) dan (H=Buah 14,137,640.00
Uk/ (B=1.00-1.50) dan (H=Buah 15,858,490.00
Uk/ (B=1.60-2.00) dan (H=Buah 16,582,390.00
Uk/ (B=2.10-2.50) dan (H=Buah 18,196,560.00
m2 34,000.00
Meter 85,000.00
Meter 105,000.00
Meter 135,000.00
m2 210,500.00
6 meter btg 287,200.00
6 meter btg 304,000.00
6 meter btg 388,800.00
6 meter btg 244,800.00
6 meter btg 168,800.00
6 meter btg 676,800.00
6 meter btg 547,200.00
6 meter btg 936,800.00
6 meter btg 214,400.00
6 meter btg 1,201,600.00
Meter 9,100.00
Meter 13,650.00
Meter 21,350.00
Meter 33,150.00
Meter 52,900.00
Meter 107,500.00
buah 135,800.00
m2 88,800.00
m2 99,500.00
m2 211,000.00
Meter 6,800.00
m2 322,300.00
Meter 9,500.00
Meter 11,400.00
m2 26,500.00
m2 35,000.00
m2 71,000.00
Kualitas RUCIKA, MASPIO btg 77,600.00
Kualitas RUCIKA, MASPIO btg 68,850.00
Kualitas RUCIKA, MASPIO Batang 47,900.00
Kualitas RUCIKA, MASPIO Batang 28,700.00
Kualitas RUCIKA, MASPIO btg 140,400.00
Kualitas RUCIKA, MASPIO btg 102,400.00
Kualitas RUCIKA, MASPIO Batang 214,200.00
Kualitas RUCIKA, MASPIO Batang 40,300.00
Kualitas RUCIKA, MASPIO Batang 404,250.00
Kualitas RUCIKA, MASPIO btg 806,400.00
Kualitas RUCIKA, MASPIO btg 1,242,000.00
buah 6,500.00
3,5 mm M2 24,250.00
4,0 mm M2 28,500.00
(100 x 100) cm, t=4 mm M2 12,000.00
(120 x 240) cm, t=5 mm Lembar 84,500.00
kg 27,500.00
Plat Uji Set Lisensi Ditjen Set 6,200.00
Plat Nomor Beca Bahan PlaBuah 7,300.00
Tebal 0.1 mm m2 162,600.00
Tebal 0.2 mm m2 35,200.00
Tebal 0.3 mm m2 49,700.00
Tebal 0.4 mm m2 65,800.00
Tebal 0.5 mm m2 81,750.00
Tebal 0.6 mm m2 97,800.00
Buah 256,100.00
(berbagai ukuran) buah 6,000.00
Warna : Natural /abu PC buah 2,600.00
Warna : Warna Oker buah 2,900.00
Buah 2,000.00
4 mm 120 x 240 Lembar 68,100.00
9 mm 120 x 240 Lembar 147,800.00
18 mm 120 x 240 Lembar 222,900.00
Liter 18,900.00
Liter 75,000.00
HACH 23765-26 Pkg 850,000.00
HACH 23765-26 Pkg 957,000.00
l, Hach 23765-26 Botol 603,600.00
Volume 0-50 m3 --- 2,750,000.00
Volume 50-100 m3 --- 3,025,000.00
Volume lebih dari 100 m3 M3" 33,000.00
Unit 150,000.00
250 G, Merck Pkg 2,549,400.00
Pkg 1,276,500.00
te Trihydrate, P.a 250 Gr, Merck Pkg 1,538,400.00
Pkg 971,400.00
Pkg 3,788,700.00
000 Gr, Merck Pkg 5,740,000.00
00 Gr, Merck Pkg 4,720,900.00
Kg 483,300.00
2po4) P.a 1000 Gr, Merck Pkg 2,620,300.00
Pkg 1,237,000.00
Bahan dan tulisan gravier m2 2,750,000.00
Bahan dan tulisan gravier M2 1,375,000.00
unit 51,681,000.00
m2 25,500.00
Hach 26151-99 Pkg 2,317,000.00
Hach 26151-99 Pkg 2,665,300.00
lllow 100 Pcs, Hach 26151-99 Pkg 1,994,000.00
m2 77,000.00
Meter 90,000.00
Meter 102,500.00
Meter 110,000.00
Meter 125,000.00
Meter 140,000.00
Ram Kawat 1 x 1 cm Meter 52,700.00
Ø1" x 1 m x 25 m (=12kg)M2 25,000.00
Ø1/2" x 1 m x 18 m (=12kM2 25,000.00
m2 28,250.00
m2 24,500.00
Buah 15,000.00
buah 8,000.00
M2 173,300.00
C 75/75 setara taso 6 meterBatang 80,200.00
3 klips (tanpa kaca) set 52,500.00
4 klips (tanpa kaca) set 70,000.00
5 klips (tanpa kaca) set 87,500.00
6 klips (tanpa kaca) set 105,000.00
Kg 38,220.00
0.9 mm meter 33,600.00
0.6 mm meter 31,200.00
Buah 4,500.00
Buah 25,000.00
Buah 27,500.00
Buah 35,000.00
Paket (Termasuk Jasa Kons1 Paket 30,000,000.00
Paket (Termasuk Jasa Kons1 Paket 30,000,000.00
setara HENDERSON bh 483,000.00
Buah 35,000.00
Buah 70,000.00
liter 15,000.00
Buah 4,250.00
20 x 20 buah 15,260.00
30 x 30 Buah 6,800.00
Ornamen buah 32,700.00
39 x 18,5 x 9 Buah 7,900.00
30 x 30 Buah 50,380.00
20 x 20 buah 36,270.00
18 x 18 buah 34,150.00
20 x 20 Buah 6,000.00
20 x 20 Buah 4,800.00
20 x 20 Buah 6,000.00
(kosongan Sonora) Buah 250,000.00
Beton Dimensi : 50/100 - 1m 2,084,370.00
Beton Dimensi : 50/120 - 1m 2,443,750.00
Beton Dimensi : 50/60 - 12m 718,750.00
Beton Dimensi : 50/70 - 12m 891,250.00
Beton Dimensi : 50/80 - 12m 1,029,250.00
Beton Dimensi : 100 x 100 m 3,630,000.00
Beton Dimensi : 120 x 120 m 4,840,000.00
Beton Dimensi : 150 x 150 m 9,035,400.00
Beton Dimensi : 200 x 200 m 12,705,000.00
Beton Dimensi : 50 x 50 - m 1,239,700.00
Beton Dimensi : 60 x 60 - m 1,603,100.00
Beton Dimensi : 80 x 80 - m 2,868,100.00
buah 24,000.00
buah 14,700.00
buah 10,800.00
buah 14,700.00
buah 8,100.00
buah 5,400.00
buah 35,600.00
buah 45,000.00
buah 7,300.00
buah 66,700.00
Penutup pori-pori /serat ka Kg 76,000.00
Buah 65,000.00
Unit 500,000.00
Buah 7,000.00
buah 1,500.00
dia.47 mm, 0,45 µm, 100 pPkg 3,718,000.00
Zak 80,000.00
Zak 70,000.00
Plester Premium 40 Kg Buah 69,000.00
Acian Plester dan Beton 4 Buah 182,270.00
Acian Profil 25 Kg Buah 219,070.00
Acian Putih 25 Kg Buah 179,400.00
Pasangan Bata 40 Kg Buah 58,070.00
Pas Bata dan Plester 40 KgBuah 86,500.00
Perekat Bata Ringan 40 KgBuah 110,000.00
Perekat Keramik Dinding Buah 40,250.00
Self Leveling Floor 25 Kg Buah 293,250.00
Perata Lantai 40 Kg Buah 63,250.00
Perata Lantai Premium 40 Buah 120,750.00
Perekat Keramik Lantai 40Buah 235,750.00
Perekat Keramik Daerah BBuah 504,270.00
White Tile Addesive 25 KgBuah 442,750.00
Perekat Keramik diatas Ke Buah 86,820.00
Pelapis Kedap Air 30 Kg Buah 1,242,570.00
Floor Hardener 25 Kg Buah 161,570.00
Non-Shrink Grout 40 Kg Buah 180,550.00
Perbaikan Permukaan BetoBuah 302,450.00
Finish Coat Repair 25 Kg Buah 373,750.00
Perekat Mortar dan Beton Buah 236,320.00
Zak 110,000.00
zak 56,000.00
Kualitas :Tiga Roda, HolciZak 65,000.00
Kualitas : Garuda, Bima, Zak 55,000.00
Zak 125,000.00
Kg 13,250.00
1219 x 2438 mm roll 298,540.00
1219 x 25000 mm Roll 3,066,000.00
1219 x 2438 mm roll 439,230.00
1219 x 25000 mm Roll 4,511,850.00
Unit 100,000.00
(Type BF-03, BF-06-08, dsunit 7,425,000.00
(Type R-05, R-10, dst) unit 14,960,000.00
Buah 337,500.00
Buah 120,000.00
Pkg 1,661,800.00
Pkg 7,020,100.00
Pkg 2,663,800.00
Pkg 4,210,600.00
Kualitas : Kansai, Kuda TeKg 44,800.00
unit 566,950.00
Tersaring bergradasi m3 110,000.00
Dus 25,000.00
setara sunray (1000) dus 99,000.00
setara sunray Buah 165.00
setara sunray (1500) dus 121,000.00
setara sunray bh 110.00
bh 1,300.00
bh 800.00
Bahan PVC Ø 3" M2 104,500.00
Bahan terpal Ø 3" Setara M2 19,250.00
Buah 80,000.00
Buah 30,000.00
setara : KENMASTER Buah 50,000.00
setara : DEKSON, SOLID Buah 70,000.00
unit 196,760.00
unit 186,760.00
buah 4,000.00
buah 6,000.00
Buah 6,500.00
Buah 30,000.00
Buah 55,000.00
Buah 80,000.00
Buah 125,000.00
buah 6,200.00
5 liter Liter 35,000.00
Botol 1,421,300.00
Pkg 2,014,000.00
Dus 105,000.00
kg 15,400.00
Starter EM4 Pertanian- Ba Liter 91,400.00
Kg 55,000.00
Bahan : Kuningan buah 350,700.00
Bahan : Kuningan buah 175,300.00
Bahan : Kuningan buah 1,345,600.00
Bahan : Kuningan buah 534,600.00
Bahan : Kuningan buah 1,737,500.00
Bahan : Kuningan Buah 142,500.00
Buah 65,000.00
zincalum Ø 15 cm Pasang 52,750.00
zincalum Ø 20 cm Pasang 70,000.00
Pkg 5,201,800.00
00 Mg/l, 500 Ml Pkg 1,724,800.00
Reagent 10 mL, 100/pkg, Pkg 1,725,000.00
pkg, Hach 21067-69 Pkg 2,165,000.00
Pkg 3,444,700.00
HACH 1816-32 Pkg 1,255,000.00
HACH 1816-32 Pkg 1,531,200.00
Pkg 948,000.00
Pkg 3,444,700.00
HACH 1817-32 Pkg 1,235,000.00
HACH 1817-32 Buah 1,533,070.00
Pkg 948,000.00
m2 521,500.00
Buah 1,925,000.00
zincalum Ø15 cm setara gBatang 105,320.00
btg 69,800.00
Ø 15 cm Set 118,300.00
m2 9,000.00
Kg 49,500.00
m3 60,000.00
buah 9,500,000.00
buah 3,150,000.00
Bulat, (Excel, Penguin/SetaUnit 4,068,000.00
Bulat, (Excel, Penguin/SetaUnit 16,680,000.00
Bulat, (Excel, Penguin /set unit 1,927,700.00
Bulat, (Excel, Penguin /set Unit 4,541,400.00
Bulat, (Excel, Penguin /set Unit 6,190,700.00
Bulat, (Excel, Penguin /set Unit 1,927,700.00
Bulat, (Excel, Penguin /set Unit 3,911,200.00
Bulat, (Excel, Penguin /set Unit 10,795,100.00
Bulat, (Excel, Penguin /set Unit 15,254,000.00
Bulat, (Excel, Penguin /set Unit 22,740,400.00
Bulat, (Excel, Penguin /set unit 1,666,900.00
Bulat, (Excel, Penguin /set Unit 3,167,000.00
Bulat, (Excel, Penguin /set Unit 3,848,200.00
Bulat, (Excel, Penguin /set unit 1,666,900.00
Bulat/Kubus, (Excel, PenguUnit 3,984,200.00
Bulat/Kubus, (Excel, PenguUnit 3,984,200.00
Bulat/Kubus, (Excel, PenguUnit 7,689,100.00
Bulat/Kubus, (Excel, PenguUnit 9,883,700.00
Bulat/Kubus, (Excel, PenguUnit 2,132,500.00
Bulat/Kubus, (Excel, PenguUnit 2,132,500.00
Antik, Kuning Buah 3,450.00
Minimalis, Silver Buah 13,000.00
Minimalis, Stainless Steel Buah 16,000.00
Aluminium Buah 75,000.00
Stainless Steel Buah 300,000.00
Buah 135,000.00
3 mm 120 x 240 Lembar 108,200.00
4 mm 120 x 240 Lembar 158,200.00
3 mm 120 x 240 Uk. Pintu Lembar 187,900.00
4 mm 120 x 240 Uk. Pintu Lembar 235,000.00
Bh 303,600.00
Buah 10,000.00
Buah 7,500.00
Buah 7,500.00
Buah 37,500.00
Buah 40,000.00
Buah 45,000.00
Buah 6,000.00
buah 6,500.00
Buah 125,000.00
Buah 115,000.00
buah 185,000.00
Motif dan Warna : Natural buah 5,600.00
Motif dan Warna : Warna buah 6,100.00
Warna : Natural /abu PC buah 5,300.00
Warna : Warna Oker buah 5,850.00
Buah 103,500.00
Dimensi P x L x T (cm): 200Unit 2,750,000.00
Unit 650,000.00
Kg 5,000.00
liter 19,600.00
Tiang beton 11/200 daN Buah 91,000.00
Tiang beton 11/200 daN + Buah 332,400.00
Tiang Beton 9/200 daN Buah 92,000.00
Tiang Beton 9/200 daN + EBuah 309,100.00
Kolom 2,75 Batang 259,050.00
Kolom 3,25 Batang 326,150.00
Kolom 2,75 Batang 324,500.00
Kolom 3,25 Batang 379,500.00
Tiang dan Rangka RPPJ Bui Unit 377,800.00
Built Up (Uk. 180 cm x 24 Unit 206,100.00
bh 7,250,000.00
Bh 2,500,000.00
Tiang Lurus Buah 377,800.00
Tiang Overhead Buah 206,100.00
Penyangga Solar Tambah pBuah 13,696,000.00
Post besi ST 12 Galvanis Batang 785,000.00
Kabel FO Tinggi 7 meter Buah 3,066,300.00
Kabel FO Tinggi 9 meter Buah 901,500.00
Tiang PJU Oktagonal TungBuah 459,900.00
Tiang PJU Bulat Ganda 9 Buah 193,800.00
Tiang PJU Bulat Tunggal Buah 662,300.00
Tiang Rambu Built Up (DiSet 613,600.00
Built Up (Diameter 75 cm)Set 852,900.00
Lengan 4,5 meter Lengan 4Buah 23,540,000.00
Lengan 7,5 meter Lengan 7Buah 25,252,000.00
Unit 250,000.00
Kualitas : Herin, Impala, CLiter 36,000.00
Kualitas : Impas, ND, LotuLiter 35,000.00
bh 580,000.00
7), P.a 500 Gr Pkg 2,700,800.00
3 mm 120 x 240 lbr 53,500.00
4 mm 120 x 240 lbr 67,600.00
4 mm motif ukuran pintu Lembar 123,500.00
Warna Standard TOTO unit 3,009,500.00
m2 250,000.00
Unit 200,000.00
Kualitas : Avian, Samurai Liter 72,000.00
m2 359,000.00
Uk 6 cm x 10 cm x 91,4 cmlbr 82,200.00
(kelas Biasa) M2 45,500.00
(kelas Menengah/sedang) M2 69,000.00
(kelas Baik) M2 95,500.00
Unit 350,000.00
Warna Standard unit 1,578,400.00
Buah 66,000.00
unit 1,462,000.00
Buah 850,000.00
Buah 502,000.00
set 1,375,500.00
Ukuran 2 Inch Buah 3,500,000.00
buah 350,000.00
buah 55,000.00
DO Botol 3,494,700.00
pH, Total Solid, TDS, TSSBotol 4,767,400.00
Minyak dan lemak Botol 3,781,800.00
Total alkali, Cl, F, K, Na Botol 4,891,700.00
NH3, NO3, NO3 dan NO2,Botol 3,534,300.00
BOD, COD Botol 4,849,900.00
Kg 110,000.00
M2 75,500.00
m2 65,000.00
m2 85,000.00
Ca, Total as CaCO3, Ca a Botol 3,616,800.00
Ø 6 mm 2,1m x 5,4m lbr 346,500.00
Ø 8 mm 2,1m x 5,4m lbr 605,000.00
Dempul Halus Kg 45,000.00
setara Elephant (405 x 10) Lembar 62,500.00
setara Elephant (405 x 20) Lembar 81,250.00
setara Elephant (405 x 30) Lembar 100,000.00
Pewarna Kg 76,000.00
Buah 6,500.00
Setara : Alderon, Avantguabuah 99,000.00
HACH 21066-69 Pkg 3,195,000.00
HACH 21066-69 Pkg 3,677,300.00
ws 10 Ml, 100/pkg, Hach 21066-69 Pkg 3,108,100.00
Pkg 1,493,200.00
A.2.2.1.4 Pengukuran dan pemasangan 1 m' Bouwplank

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 22,150.00
B BAHAN
Kayu balok 5/7 m3 0.012 2,000,000.00 24,000.00
paku 2"-3" Kg 0.020 19,250.00 385.00
Kayu papan 3/20 m3 0.007 2,125,000.00 14,875.00
JUMLAH HARGA BAHAN 39,260.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 61,410.00


E Overhead & Profit 10% 6,141.00
F Harga Satuan Pekerjaan (D+E) 67,500.00

A.2.2.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 2.000 95,000.00 190,000.00
Tukang Kayu L.02 OH 2.000 110,000.00 220,000.00
Tukang batu L.02 OH 1.000 110,000.00 110,000.00
Kepala Tukang L.03 OH 0.300 110,000.00 33,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 558,500.00
B BAHAN
Dolken kayu d.8-10/400 cm Batang 1.250 -
Kayu m3 0.180 -
Paku Biasa kg 0.080 -
Besi strip kg 1.100 -
Sement portland kg 35.000 -
Pasir pasang m3 0.150 -
Pasir beton m3 0.100 -
Koral beton m3 0.150 -
Bata merah bh 30.000 -
Seng plat lbr 0.250 -
jendela naco bh 0.200 -
Kaca polos m2 0.080 -
Kunci Tanam bh 0.150 -
Plywood 4 mm lbr 0.060 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 558,500.00


E Overhead & Profit 10% 55,850.00
F Harga Satuan Pekerjaan (D+E) 614,300.00
A.2.2.1.9 Pembersihan 1 m2 lapangan dan perataan

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 15,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 15,000.00


E Overhead & Profit 10% 1,500.00
F Harga Satuan Pekerjaan (D+E) 16,500.00

A.2.2.1.13 Pembongkaran 1 m3 beton bertulang

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 13.334 95,000.00 1,266,730.00
Mandor L.04 OH 0.666 110,000.00 73,260.00
JUMLAH TENAGA KERJA 1,339,990.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,339,990.00


E Overhead & Profit 10% 133,999.00
F Harga Satuan Pekerjaan (D+E) 1,473,900.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1 Penggalian 1 m3 tanah sedalam 1 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.750 95,000.00 71,250.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 74,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 74,000.00


E Overhead & Profit 10% 7,400.00
F Harga Satuan Pekerjaan (D+E) 81,400.00

A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


pengurugan kembali 1 m3 galian dihitung dari 1/3 kali koefisien pekerjaan galian
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 95,000.00 47,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 53,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 53,000.00


E Overhead & Profit 10% 5,300.00
F Harga Satuan Pekerjaan (D+E) 58,300.00

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 29,600.00
B BAHAN
Pasir Urug m3 1.200 90,000.00 108,000.00
JUMLAH HARGA BAHAN 108,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 137,600.00


E Overhead & Profit 10% 13,760.00
F Harga Satuan Pekerjaan (D+E) 151,300.00

A.2.3.1.14 Pengurugan 1 m3 sirtu padat

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.250 95,000.00 23,750.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 26,500.00
B BAHAN
sirtu m3 1.200 110,000.00 132,000.00
JUMLAH HARGA BAHAN 132,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 158,500.00
E Overhead & Profit 10% 15,850.00
F Harga Satuan Pekerjaan (D+E) 174,300.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.500 95,000.00 142,500.00
Tukang batu L.02 OH 0.750 110,000.00 82,500.00
Kepala Tukang L.03 OH 0.075 110,000.00 8,250.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 241,500.00
B BAHAN
Batu belah m3 1.200 157,000.00 188,400.00
Semen portland Kg 136.000 1,200.00 163,200.00
Pasir Pasang m3 0.544 190,000.00 103,360.00
JUMLAH HARGA BAHAN 454,960.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 696,460.00


E Overhead & Profit 10% 69,646.00
F Harga Satuan Pekerjaan (D+E) 766,100.00

A.3.2.1.9 Pemasangan 1 m3 batu kosong (anstamping)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.780 95,000.00 74,100.00
Tukang batu L.02 OH 0.390 110,000.00 42,900.00
Kepala Tukang L.03 OH 0.039 110,000.00 4,290.00
Mandor L.04 OH 0.039 110,000.00 4,290.00
JUMLAH TENAGA KERJA 125,580.00
B BAHAN
Batu belah m3 1.200 157,000.00 188,400.00
Pasir urug m3 0.432 90,000.00 38,880.00
JUMLAH HARGA BAHAN 227,280.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 352,860.00


E Overhead & Profit 10% 35,286.00
F Harga Satuan Pekerjaan (D+E) 388,100.00
A.4.1.1 HARGA SATUAN PEKERJAAN BETON

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.200 95,000.00 114,000.00
Tukang batu L.02 OH 0.200 110,000.00 22,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.060 110,000.00 6,600.00
JUMLAH TENAGA KERJA 144,800.00
B BAHAN
Semen portland kg 230.000 1,200.00 276,000.00
Pasir beton m3 0.638 220,000.00 140,328.57
Kerikil (Maks 30mm) m3 0.761 240,000.00 182,577.78
JUMLAH HARGA BAHAN 598,906.35
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 743,706.35


E Overhead & Profit 10% 74,370.63
F Harga Satuan Pekerjaan (D+E) 818,000.00

A.4.1.1.7 Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 95,000.00 156,750.00
Tukang batu L.02 OH 0.275 110,000.00 30,250.00
Kepala Tukang L.03 OH 0.028 110,000.00 3,080.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 199,210.00
B BAHAN
Semen portland kg 371.000 1,200.00 445,200.00
Pasir beton m3 0.499 220,000.00 109,685.71
Kerikil (Maks 30mm) m3 0.770 240,000.00 184,711.11
Air Liter 0.000 - -
JUMLAH HARGA BAHAN 739,596.83
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 938,806.83


E Overhead & Profit 10% 93,880.68
F Harga Satuan Pekerjaan (D+E) 1,032,600.00

A.4.1.1.17 Pembesian 1 kg dengan besi polos atau besi ulir

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.0070 95,000.00 665.00
Tukang besi L.02 OH 0.0070 110,000.00 770.00
Kepala Tukang L.03 OH 0.0007 110,000.00 77.00
Mandor L.04 OH 0.0004 110,000.00 44.00
JUMLAH TENAGA KERJA 1,556.00
B BAHAN
besi beton (polos/ulir) kg 1.0500 12,000.00 12,600.00
kawat beton Kg 0.0150 17,500.00 262.50
JUMLAH HARGA BAHAN 12,862.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 14,418.50


E Overhead & Profit 10% 1,441.85
F Harga Satuan Pekerjaan (D+E) 15,800.00
A.4.1.1.19 Pemasangan 1 M2 Jaring Kawat Baja (wiremesh)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.0025 95,000.00 237.50
Tukang besi L.02 OH 0.0025 110,000.00 275.00
Kepala Tukang L.03 OH 0.0025 110,000.00 275.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 897.50
B BAHAN
Jaring kawat
M2 1.100 120,312.50 132,343.75
baja dilas
kawat beton Kg 0.005 17,500.00 87.50
JUMLAH HARGA BAHAN 132,431.25
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 133,328.75


E Overhead & Profit 10% 13,332.88
F Harga Satuan Pekerjaan (D+E) 146,600.00

A.4.1.20 Pemasangan 1 M' Penetrasi Mini Pile Beton 28 X 28 X 28 cm, Mutu K-450

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.052 95,000.00 4,940.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
Operator Crane OH 0.010 125,000.00 1,250.00
Pembantu Operator OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 9,040.00
B BAHAN
Tiang Pancang Segi Tiga 28x28x28 cm K-450 m' 1.030 225,000.00 231,750.00

JUMLAH HARGA BAHAN 231,750.00


C PERALATAN
Alat Pancang + Hidrolik sewa/hr 0.073 180,000.00 13,140.00
Alat Penyambung Tiang Pancang bh 0.250 200,000.00 50,000.00
JUMLAH HARGA ALAT 63,140.00

D Jumlah (A+B+C) 303,930.00


E Overhead & Profit 10% 30,393.00
F Harga Satuan Pekerjaan (D+E) 334,300.00
A.4.1.1 HARGA SATUAN PEKERJAAN BEKISTING

A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.520 95,000.00 49,400.00
Tukang Kayu L.02 OH 0.260 110,000.00 28,600.00
Kepala Tukang L.03 OH 0.026 110,000.00 2,860.00
Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 83,720.00
B BAHAN
kayu kelas III m3 0.040 2,125,000.00 85,000.00
Paku 5-10 cm Kg 0.300 19,250.00 5,775.00
Minyak bekisting Liter 0.100 14,900.00 1,490.00
JUMLAH HARGA BAHAN 92,265.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 175,985.00


E Overhead & Profit 10% 17,598.50
F Harga Satuan Pekerjaan (D+E) 193,500.00

A.4.1.1.21 Pemasangan 1 m2 bekisting untuk Sloof

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.520 95,000.00 49,400.00
Tukang Kayu L.02 OH 0.260 110,000.00 28,600.00
Kepala Tukang L.03 OH 0.026 110,000.00 2,860.00
Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 83,720.00
B BAHAN
kayu kelas III m3 0.045 2,125,000.00 95,625.00
Paku 5-10 cm Kg 0.300 19,250.00 5,775.00
Minyak bekisting Liter 0.100 14,900.00 1,490.00
JUMLAH HARGA BAHAN 102,890.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 186,610.00


E Overhead & Profit 10% 18,661.00
F Harga Satuan Pekerjaan (D+E) 205,200.00

A.4.1.1.22 Pemasangan 1 m2 bekisting untuk Kolom

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 95,000.00 62,700.00
Tukang Kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 106,260.00
B BAHAN
kayu kelas III m3 0.040 2,125,000.00 85,000.00
Paku 5-12 cm Kg 0.400 18,500.00 7,400.00
Minyak bekisting Liter 0.200 14,900.00 2,980.00
Balok kayu kelas III m3 0.015 2,000,000.00 30,000.00
Bambu dia.7-10 pj 4 mtr batang 2.000 12,500.00 25,000.00
JUMLAH HARGA BAHAN 150,380.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 256,640.00


E Overhead & Profit 10% 25,664.00
F Harga Satuan Pekerjaan (D+E) 282,300.00
A.4.1.1.23 Pemasangan 1 m2 bekisting untuk Balok

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 95,000.00 62,700.00
Tukang Kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 106,260.00
B BAHAN
kayu kelas III m3 0.040 2,125,000.00 85,000.00
Paku 5-12 cm Kg 0.400 18,500.00 7,400.00
Minyak bekisting Liter 0.200 14,900.00 2,980.00
Balok kayu kelas III m3 0.018 2,000,000.00 36,000.00
Plywood tebal 9 mm lbr 0.000 140,700.00 -
Bambu dia.7-10 pj 4 mtr batang 2.000 12,500.00 25,000.00
JUMLAH HARGA BAHAN 156,380.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 262,640.00


E Overhead & Profit 10% 26,264.00
F Harga Satuan Pekerjaan (D+E) 288,900.00

A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 95,000.00 62,700.00
Tukang Kayu L.02 OH 0.330 110,000.00 36,300.00
Kepala Tukang L.03 OH 0.033 110,000.00 3,630.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 106,260.00
B BAHAN
kayu kelas III m3 0.040 2,125,000.00 85,000.00
Paku 5-12 cm Kg 0.400 18,500.00 7,400.00
Minyak bekisting Liter 0.200 14,900.00 2,980.00
Balok kayu kelas III m3 0.015 2,000,000.00 30,000.00
Bambu dia.7-10 pj 4 mtr batang 6.000 12,500.00 75,000.00
JUMLAH HARGA BAHAN 200,380.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 306,640.00


E Overhead & Profit 10% 30,664.00
F Harga Satuan Pekerjaan (D+E) 337,300.00

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.180 95,000.00 17,100.00
Tukang batu L.02 OH 0.020 110,000.00 2,200.00
Tukang kayu L.02 OH 0.020 110,000.00 2,200.00
Tukang besi L.02 OH 0.020 110,000.00 2,200.00
Kepala tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.009 110,000.00 990.00
JUMLAH TENAGA KERJA 25,350.00
B BAHAN
Kayu kelas III m3 0.002 2,125,000.00 4,250.00
Paku 5 cm – 12 cm kg 0.010 18,500.00 185.00
Minyak bekisting Liter -
Besi beton polos kg 3.000 12,000.00 36,000.00
Kawat beton kg 0.450 17,500.00 7,875.00
Semen Portland kg 4.000 1,200.00 4,800.00
Pasir Beton m3 0.006 220,000.00 1,320.00
Kerikil m3 0.009 240,000.00 2,160.00
JUMLAH HARGA BAHAN 56,590.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 81,940.00
E Overhead & Profit 10% 8,194.00
F Harga Satuan Pekerjaan (D+E) 90,100.00
A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.297 95,000.00 28,215.00
Tukang batu L.02 OH 0.033 110,000.00 3,630.00
Tukang kayu L.02 OH 0.033 110,000.00 3,630.00
Tukang besi L.02 OH 0.033 110,000.00 3,630.00
Kepala tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 41,855.00
B BAHAN
Kayu kelas III m3 0.003 2,125,000.00 6,375.00
Paku 5 cm – 12 cm kg 0.020 18,500.00 370.00
Minyak bekisting Liter -
Besi beton polos kg 3.600 12,000.00 43,200.00
Kawat beton kg 0.050 17,500.00 875.00
Semen Portland kg 5.500 1,200.00 6,600.00
Pasir Beton m3 0.009 220,000.00 1,980.00
Kerikil m3 0.015 240,000.00 3,600.00
JUMLAH HARGA BAHAN 63,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 104,855.00


E Overhead & Profit 10% 10,485.50
F Harga Satuan Pekerjaan (D+E) 115,300.00
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.1 Pemasangan 1 kg besi profil

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 95,000.00 5,700.00
Tukang Las Konstruksi L.03 OH 0.060 110,000.00 6,600.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 13,290.00
B BAHAN
Besi profil kg 1.150 14,000.00 16,100.00
JUMLAH HARGA BAHAN 16,100.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,390.00


E Overhead & Profit 10% 2,939.00
F Harga Satuan Pekerjaan (D+E) 32,300.00

A.4.2.1.2 Pemasangan 1 kg besi Baja Iwf

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 95,000.00 5,700.00
Tukang Las Konstruksi L.03 OH 0.060 110,000.00 6,600.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 13,290.00
B BAHAN
Besi Baja IWF kg 1.150 16,000.00 18,400.00
JUMLAH HARGA BAHAN 18,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,690.00


E Overhead & Profit 10% 3,169.00
F Harga Satuan Pekerjaan (D+E) 34,800.00

A.4.2.1.2.b Pemasangan 1 kg besi CNP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 95,000.00 5,700.00
Tukang Las Konstruksi L.03 OH 0.060 110,000.00 6,600.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 13,290.00
B BAHAN
Besi CNP kg 1.150 14,000.00 16,100.00
JUMLAH HARGA BAHAN 16,100.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,390.00


E Overhead & Profit 10% 2,939.00
F Harga Satuan Pekerjaan (D+E) 32,300.00
A.4.2.1.4 Pemasangan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.050 95,000.00 99,750.00
Tukang Las Konstruksi L.03 OH 1.050 110,000.00 115,500.00
Kepala Tukang L.03 OH 0.105 110,000.00 11,550.00
Mandor L.04 OH 0.052 110,000.00 5,720.00
JUMLAH TENAGA KERJA 232,520.00
B BAHAN
Besi siku L 30.30.3 kg 15.000 18,200.00 273,000.00
Besi Plat Baja kg 32.800 15,000.00 492,000.00
kawat las kg 0.050 35,000.00 1,750.00
JUMLAH HARGA BAHAN 766,750.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 999,270.00


E Overhead & Profit 10% 99,927.00
F Harga Satuan Pekerjaan (D+E) 1,099,100.00

A.4.2.1.7 Pemasangan pintu rolling door besi

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.200 95,000.00 114,000.00
Tukang L.02 OH 1.200 110,000.00 132,000.00
Kepala Tukang L.03 OH 0.120 110,000.00 13,200.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 259,860.00
B BAHAN
Galvalum t=0,4mm m2 16.000 455,000.00 7,280,000.00
Mesin rooling door otomatis bh 1.000 17,600,000.00 17,600,000.00
Besi Siku kg 11.250 18,200.00 204,750.00
JUMLAH HARGA BAHAN 25,084,750.00

C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 25,344,610.00


E Overhead & Profit 10% 2,534,461.00
F Harga Satuan Pekerjaan (D+E) 27,879,000.00
Dihit. F-02 Pemasangan 1 unit kusen dan daun pintu tipe P1

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 4,224,990.10 844,998.02
JUMLAH TENAGA KERJA 844,998.02
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" warna m' 7.200 105,000.00 756,000.00
Fischer+Skrup set 8.000 2,150.00 17,200.00
Sealant tube 0.813 41,000.00 33,312.50
- Daun Pintu -
Daun Pintu Doble Teakwood bh 1.000 1,487,500.00 1,487,500.00
HPL Wood Texture m2 3.713 112,000.00 415,833.60
Kunci Tanam 2 Slaag (kualitas tinggi/besar) bh 1.000 483,000.00 483,000.00
Engsel Pintu Stainless Steel 4" bh 3.000 325,000.00 975,000.00
- BV atas Pintu -
Kaca Polos 5 mm m2 0.540 90,000.00 48,564.00
Karet Lis m' 5.720 1,500.00 8,580.00
JUMLAH HARGA BAHAN 4,224,990.10
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 5,069,988.12


E Overhead & Profit 10% 506,998.81
F Harga Satuan Pekerjaan (D+E) 5,576,900.00

Dihit. F-04 Pemasangan 1 unit kusen dan daun pintu tipe P2

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 1,365,964.50 273,192.90
JUMLAH TENAGA KERJA 273,192.90
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 5.700 95,000.00 541,500.00
Fischer+Skrup set 8.000 2,150.00 17,200.00
Sealant tube 0.713 41,000.00 29,212.50
- Daun Pintu -
Profil Daun Pintu Alumunium m' 5.800 62,500.00 362,500.00
Engsel Pintu Biasa bh 3.000 25,875.00 77,625.00
Handel Pintu Stainless psg 1.000 75,000.00 75,000.00
Slot Pintu bh 1.000 37,600.00 37,600.00
Spandrel 110x1mm m2 0.833 216,666.67 180,375.00
Karet m' 9.040 1,500.00 13,560.00
- BV atas Pintu -
Kaca Bening 5 mm m2 0.135 90,000.00 12,168.00
Karet m' 2.000 1,500.00 3,000.00
Sunblast m2 0.270 60,000.00 16,224.00
JUMLAH HARGA BAHAN 1,365,964.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,639,157.40


E Overhead & Profit 10% 163,915.74
F Harga Satuan Pekerjaan (D+E) 1,803,000.00
Dihit. F-07 Pemasangan 1 unit kusen dan daun pintu jendela tipe PJ

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 2,478,649.40 495,729.88
JUMLAH TENAGA KERJA 495,729.88
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 11.310 95,000.00 1,074,450.00
Fischer+Skrup set 9.000 2,150.00 19,350.00
Sealant tube 8.090 41,000.00 331,690.00
- Daun Pintu -
Profil Daun Pintu Alumunium m' 6.680 62,500.00 417,500.00
Engsel Pintu Biasa bh 3.000 25,875.00 77,625.00
Handel Pintu Stainless psg 1.000 75,000.00 75,000.00
Kunci Silinder set 1.000 185,000.00 185,000.00
Kaca Bening 5 mm m2 1.382 90,000.00 124,416.00
Karet m' 2.765 1,500.00 4,147.20
- Daun Jendela -
Profil Daun Jendela Alumunium m' 0.000 42,000.00 -
Engsel Casement bh 0.000 45,000.00 -
Ram Buncis bh 0.000 12,000.00 -
Kaca Bening 5 mm m2 0.738 90,000.00 66,456.00
Karet m' 1.477 1,500.00 2,215.20
Kayu Papan Kamper m3 0.008 12,000,000.00 100,800.00
JUMLAH HARGA BAHAN 2,478,649.40
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,974,379.28


E Overhead & Profit 10% 297,437.93
F Harga Satuan Pekerjaan (D+E) 3,271,800.00

Dihit. F-08 Pemasangan 1 unit kusen dan daun jendela tipe J1

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 1,648,595.50 329,719.10
JUMLAH TENAGA KERJA 329,719.10
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 10.800 95,000.00 1,026,000.00
Fischer+Skrup set 8.000 2,150.00 17,200.00
Sealant tube 0.788 41,000.00 32,287.50
- Daun Jendela -
Profil Daun Jendela Alumunium m' 3.880 42,000.00 162,960.00
Engsel Casement bh 4.000 45,000.00 180,000.00
Ram Buncis bh 2.000 12,000.00 24,000.00
Kaca Bening 5 mm m2 0.234 90,000.00 21,060.00
Karet m' 7.760 1,500.00 11,640.00
- BV atas Jendela -
Kaca Bening 5 mm m2 1.459 90,000.00 131,328.00
Karet m' 9.360 1,500.00 14,040.00
Sunblast m2 0.468 60,000.00 28,080.00
JUMLAH HARGA BAHAN 1,648,595.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,978,314.60


E Overhead & Profit 10% 197,831.46
F Harga Satuan Pekerjaan (D+E) 2,176,100.00
Dihit. F-08APemasangan 1 unit kusen LV

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 1,371,599.50 274,319.90
JUMLAH TENAGA KERJA 274,319.90
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 10.800 95,000.00 1,026,000.00
Fischer+Skrup set 8.000 2,150.00 17,200.00
Sealant tube 0.788 41,000.00 32,287.50
- Daun Jendela -

- BV atas Jendela -
Jalusi Aluminium m' 4.960 59,700.00 296,112.00
Karet m' 0.000 1,500.00 -
Sunblast m2 0.000 60,000.00 -
JUMLAH HARGA BAHAN 1,371,599.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,645,919.40


E Overhead & Profit 10% 164,591.94
F Harga Satuan Pekerjaan (D+E) 1,810,500.00

Dihit. F-12 Pemasangan 1 unit kusen alumunium BV1

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 258,858.20 51,771.64
JUMLAH TENAGA KERJA 51,771.64
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 2.200 95,000.00 209,000.00
Fischer+Skrup set 4.000 2,150.00 8,600.00
Sealant tube 0.275 41,000.00 11,275.00
Kaca Bening 5 mm m2 0.322 90,000.00 29,016.00
Karet m' 0.645 1,500.00 967.20
JUMLAH HARGA BAHAN 258,858.20
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 310,629.84


E Overhead & Profit 10% 31,062.98
F Harga Satuan Pekerjaan (D+E) 341,600.00

Dihit. F-13 Pemasangan 1 unit kusen alumunium BV2

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 1,857,060.40 371,412.08
JUMLAH TENAGA KERJA 371,412.08
B BAHAN
- Kusen -
Kusen Profil Alumunium 4" m' 16.800 95,000.00 1,596,000.00
Fischer+Skrup set 8.000 2,150.00 17,200.00
Sealant tube 1.575 41,000.00 64,575.00
Kaca Bening 5 mm m2 1.928 90,000.00 173,502.00
Karet m' 3.856 1,500.00 5,783.40
JUMLAH HARGA BAHAN 1,857,060.40
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,228,472.48


E Overhead & Profit 10% 222,847.25
F Harga Satuan Pekerjaan (D+E) 2,451,300.00
Dihit. F-13APemasangan 1 m2 Alumunium Composite Panel

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Upah Pembuatan dan Pemasangan (20% harga bahan) 0.200 546,962.50 109,392.50
JUMLAH TENAGA KERJA 109,392.50
B BAHAN
Rangka Hollow m' 4.100 24,500.00 100,450.00
Alumunium Composite Panel m2 1.100 360,000.00 396,000.00
Sealan tube 0.813 41,000.00 33,312.50
Paku Skrup bh 8.000 1,500.00 12,000.00
Pisher bh 8.000 650.00 5,200.00
JUMLAH HARGA BAHAN 546,962.50
C PERALATAN
Peralatan (5% harga bahan) 0.050 546,962.50 27,348.13
JUMLAH HARGA ALAT 27,348.13

D Jumlah (A+B+C) 683,703.13


E Overhead & Profit 10% 68,370.31
F Harga Satuan Pekerjaan (D+E) 752,000.00

A.4.2.1.18 Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang L.02 OH 0.200 110,000.00 22,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 43,310.00
B BAHAN
Seng pelat m 1.050 29,854.00 31,346.70
Paku 1 cm - 2.5 cm kg 0.015 21,000.00 315.00
Papan kayu kelas II atau III m3 0.019 2,125,000.00 40,375.00
JUMLAH HARGA BAHAN 72,036.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 115,346.70


E Overhead & Profit 10% 11,534.67
F Harga Satuan Pekerjaan (D+E) 126,800.00

A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.0,3 mm, modul 60 x 60 cm, untuk plafond

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.250 95,000.00 23,750.00
Tukang besi L.03 OH 0.250 110,000.00 27,500.00
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 55,430.00
B BAHAN
Rangka metal hollow 40.40.0,3 mm m' 3.500 6,000.00 21,000.00
Assesories (perkuatan, las dll) ls 100% x rangka 6,000.00 6,000.00
JUMLAH HARGA BAHAN 27,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 82,430.00


E Overhead & Profit 10% 8,243.00
F Harga Satuan Pekerjaan (D+E) 90,600.00

A.4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.734 67,000.00 49,178.00
Tukang besi L.03 OH 0.734 90,000.00 66,060.00
Kepala Tukang L.03 OH 0.073 95,000.00 6,935.00
Mandor L.04 OH 0.037 95,000.00 3,515.00
JUMLAH TENAGA KERJA 125,688.00
B BAHAN
Baja ringan canai dingin C75 kg 3.065 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 125,688.00


E Overhead & Profit 10% 12,568.80
F Harga Satuan Pekerjaan (D+E) 138,200.00

A.4.2.1.23 Pemasangan 1 m daun jendela alumunium 30/70

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.043 67,000.00 2,881.00
Tukang khusus alumunium L.03 OH 0.043 90,000.00 3,870.00
Kepala Tukang L.03 OH 0.004 95,000.00 408.50
Mandor L.04 OH 0.002 95,000.00 199.50
JUMLAH TENAGA KERJA 7,359.00
B BAHAN
profil alumunium m 1.100 73,500.00 80,850.00
skrup fixer buah 4.000 1,000.00 4,000.00
sealant tube 0.060 41,500.00 2,490.00
JUMLAH HARGA BAHAN 87,340.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 94,699.00


E Overhead & Profit 10% 9,469.90
F Harga Satuan Pekerjaan (D+E) 104,100.00

A.4.2.1.24 Pemasangan 1 m daun pintu alumunium 30/100

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.043 67,000.00 2,881.00
Tukang khusus alumunium L.03 OH 0.043 90,000.00 3,870.00
Kepala Tukang L.03 OH 0.004 95,000.00 408.50
Mandor L.04 OH 0.002 95,000.00 199.50
JUMLAH TENAGA KERJA 7,359.00
B BAHAN
profil alumunium 30/100 m 1.100 89,200.00 98,120.00
skrup fixer buah 8.000 1,000.00 8,000.00
sealant tube 0.060 41,500.00 2,490.00
JUMLAH HARGA BAHAN 108,610.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 115,969.00


E Overhead & Profit 10% 11,596.90
F Harga Satuan Pekerjaan (D+E) 127,500.00

A.4.2.1.25 Pemasangan 1 m daun pintu alumunium 30/120

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.043 67,000.00 2,881.00
Tukang khusus alumunium L.03 OH 0.043 90,000.00 3,870.00
Kepala Tukang L.03 OH 0.004 95,000.00 408.50
Mandor L.04 OH 0.002 95,000.00 199.50
JUMLAH TENAGA KERJA 7,359.00
B BAHAN
profil alumunium 30/120 m 1.100 - -
skrup fixer buah 8.000 1,000.00 8,000.00
sealant tube 0.060 41,500.00 2,490.00
JUMLAH HARGA BAHAN 10,490.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 17,849.00


E Overhead & Profit 10% 1,784.90
F Harga Satuan Pekerjaan (D+E) 19,600.00

Dihitung Pemasangan 1 unit pintu type PA. 1

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 9.2 124300 1143560
profil alumunium 30/100 A.4.2.1.24 m 11.44 127500 1458600
Lever Handle A.4.6.2.24 set 1 78300 78300
Looc Case A.4.6.2.25 bh 1 89300 89300
Engsel pintu A.4.6.2.5. bh 6 63800 382800
Kaca tebal 5 mm A.4.6.2.17 m2 3.088 138200 426761.6
JUMLAH HARGA BAHAN 3579321.6
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3579321.6


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 3579300

Dihitung Pemasangan 1 unit pintu type P. 1

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.043 - -
Tukang khusus alumunium L.03 OH 0.043 - -
Kepala Tukang L.03 OH 0.004 - -
Mandor L.04 OH 0.002 - -
JUMLAH TENAGA KERJA -
B BAHAN
profil alumunium A.4.2.1.11 m 4.900 143,500.00 703,150.00
profil alumunium 30/100 A.4.2.1.24 m 5.500 127,500.00 701,250.00
Lever Handle A.4.6.2.24 set 1.000 78,300.00 78,300.00
Looc Case A.4.6.2.25 bh 1 89,300.00
Engsel pintu A.4.6.2.5. bh 3 63800 191400
Kaca tebal 5 mm A.4.6.2.17 m2 1.2 138200 165,840.00
JUMLAH HARGA BAHAN 1,929,240.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,929,240.00


E Overhead & Profit 10% -
F Harga Satuan Pekerjaan (D+E) 1,929,200.00

Dihitung Pemasangan 1 unit pintu type P. 2

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 4.8 143500 688800
Spandrill UB m2 1 750000 750000
Lever Handle A.4.6.2.24 set 1 78300 78300
Looc Case A.4.6.2.25 bh 1 89300 89300
Engsel pintu A.4.6.2.5. bh 2 63800 127600
JUMLAH HARGA BAHAN 1734000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1734000


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 1734000

Dihitung Pemasangan 1 unit jendela type J1

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 5.2 143500 746200
profil alumunium 30/70 A.4.2.1.23 m 2.9 104100 301890
Engsel jendela A.4.6.2.6. bh 2 58400 116800
Hak Angin type geser A.4.6.2.9. bh 1 34600 34600
Casement Handle A.4.6.2.24 bh 1 78300 78300
Kaca tebal 5 mm A.4.6.2.17 m2 0.79 138200 109178
JUMLAH HARGA BAHAN 1386968
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1386968


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 1386900

Dihitung Pemasangan 1 unit jendela type J2

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 8.6 143500 1234100
profil alumunium 30/70 A.4.2.1.23 m 5.6 104100 582960
Engsel jendela A.4.6.2.6. bh 4 58400 233600
Hak Angin type geser A.4.6.2.9. bh 2 34600 69200
Casement Handle A.4.6.2.24 bh 2 78300 156600
Kaca tebal 5 mm A.4.6.2.17 m2 1.65 138200 228030
JUMLAH HARGA BAHAN 2504490
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2504490


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 2504400

Dihitung Pemasangan 1 unit jendela type J3

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 8.9 143500 1277150
profil alumunium 30/70 A.4.2.1.23 m 6 104100 624600
Engsel jendela A.4.6.2.6. bh 4 58400 233600
Hak Angin type geser A.4.6.2.9. bh 2 34600 69200
Casement Handle A.4.6.2.24 bh 2 78300 156600
Kaca tebal 5 mm A.4.6.2.17 m2 1.635 138200 225957
JUMLAH HARGA BAHAN 2587107
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2587107


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 2587100

Dihitung Pemasangan 1 unit Bovenlight type BV1

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 2.4 143500 344400
profil alumunium 30/70 A.4.2.1.23 m 2 104100 208200
Engsel jendela A.4.6.2.6. bh 2 58400 116800
Hak Angin type geser A.4.6.2.9. bh 1 34600 34600
Casement Handle A.4.6.2.24 bh 1 78300 78300
Kaca tebal 5 mm A.4.6.2.17 m2 0.12 138200 16584
JUMLAH HARGA BAHAN 798884
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 798884


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 798800

Dihitung Pemasangan 1 unit Bovenlight type BV2

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 2.6 143500 373100
Kaca tebal 5 mm A.4.6.2.17 m2 0.3 138200 41460
JUMLAH HARGA BAHAN 414560
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 414560


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 414500

Dihitung Pemasangan 1 unit dinding partisi type PR. 1


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 7.2 143500 1033200
profil alumunium 30/100 A.4.2.1.24 m 5.8 127500 739500
Lever Handle A.4.6.2.24 set 1 78300 78300
Looc Case A.4.6.2.25 bh 1 89300 89300
Engsel pintu A.4.6.2.5. bh 3 63800 191400
Kaca tebal 5 mm A.4.6.2.17 m2 1.6 138200 221120
Dinding Partisi A.4.4.1.27 m2 4.62 218900 1011318
Cat Dinding A.4.7.1.10. m2 9.24 68100 629244
JUMLAH HARGA BAHAN 3993382
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3993382


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 3993300

Dihitung Pemasangan 1 unit dinding partisi type PR. 2

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 7.2 143500 1033200
profil alumunium 30/100 A.4.2.1.24 m 5.8 127500 739500
Lever Handle A.4.6.2.24 set 1 78300 78300
Looc Case A.4.6.2.25 bh 1 89300 89300
Engsel pintu A.4.6.2.5. bh 3 63800 191400
Kaca tebal 5 mm A.4.6.2.17 m2 1.6 138200 221120
Dinding Partisi A.4.4.1.27 m2 3.12 218900 682968
Cat Dinding A.4.7.1.10. m2 6.24 68100 424944
JUMLAH HARGA BAHAN 3460732
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3460732


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 3460700

Dihitung Pemasangan 1 unit dinding partisi type PR. 3

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
Engsel pintu Koboi A.4.6.2.26 bh 4 59000 236000
Dinding Partisi A.4.4.1.27 m2 7.2 218900 1576080
Cat Dinding A.4.7.1.10. m2 14.4 68100 980640
Meja rangka kayu Lapis megatic Ls 1 9000000 9000000
JUMLAH HARGA BAHAN 11792720
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 11792720
E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 11792700

Dihitung Pemasangan 1 unit dinding partisi type PR. 4

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
Engsel pintu Koboi A.4.6.2.26 bh 4 59000 236000
Dinding Partisi A.4.4.1.27 m2 5.55 218900 1214895
Cat Dinding A.4.7.1.10. m2 11.1 68100 755910
Meja rangka kayu Lapis megatic Ls 1 9000000 9000000
JUMLAH HARGA BAHAN 11206805
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 11206805


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 11206800

Dihitung Pemasangan 1 unit dinding partisi type PR. 5

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
Dinding Partisi A.4.4.1.27 m2 6.15 218900 1346235
Cat Dinding A.4.7.1.10. m2 12.3 68100 837630
JUMLAH HARGA BAHAN 2183865
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2183865


E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 2183800

Dihitung Pemasangan 1 unit dinding partisi type PR. 6

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
Dinding Partisi A.4.4.1.27 m2 3.9 218900 853710
Cat Dinding A.4.7.1.10. m2 7.8 68100 531180
JUMLAH HARGA BAHAN 1384890
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1384890


E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 1384800

Dihitung Pemasangan 1 unit dinding partisi type PR. 7


No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
profil alumunium A.4.2.1.11 m 7.2 143500 1033200
profil alumunium 30/100 A.4.2.1.24 m 5.8 127500 739500
Lever Handle A.4.6.2.24 set 1 78300 78300
Looc Case A.4.6.2.25 bh 1 89300 89300
Engsel pintu A.4.6.2.5. bh 3 63800 191400
Kaca tebal 5 mm A.4.6.2.17 m2 1.6 138200 221120
Dinding Partisi A.4.4.1.27 m2 6.495 218900 1421755.5
Cat Dinding A.4.7.1.10. m2 12.99 68100 884619
JUMLAH HARGA BAHAN 4659194.5
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 4659194.5


E Overhead & Profit 10% 0
F Harga Satuan Pekerjaan (D+E) 4659100

Dihitung Pemasangan 1 unit dinding partisi type PR. 8

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.043 0 0
Tukang khusus alumunium L.03 OH 0.043 0 0
Kepala Tukang L.03 OH 0.0043 0 0
Mandor L.04 OH 0.0021 0 0
JUMLAH TENAGA KERJA 0
B BAHAN
Dinding Partisi A.4.4.1.27 m2 12.36 218900 2705604
Cat Dinding A.4.7.1.10. m2 24.72 68100 1683432
JUMLAH HARGA BAHAN 4389036
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 4389036


E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 4389000

A.4.2.1.20 Pemasangan 1 unit Pagar Pengaman Bahan Besi GIF 2 inchi Uk. Type A

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.35 67000 23450
Tukang besi L.03 OH 0.35 90000 31500
Kepala Tukang L.03 OH 0.035 95000 3325
Mandor L.04 OH 0.018 95000 1710
JUMLAH TENAGA KERJA 0
B BAHAN
Besi GIF 2 inchi m' 10.8 #NAME? #NAME?
Besi profil diameter 16 kg 9.4220928 #NAME? #NAME?
Cat Besi m2 1.729512 0 0
Upah kerja ls 0.2 #NAME? #NAME?
JUMLAH HARGA BAHAN #NAME?
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #NAME?


E Overhead & Profit 10% #NAME?
F Harga Satuan Pekerjaan (D+E) #NAME?
G PEKERJAAN KUSEN PINTU & JENDELA ALUMINIUM

G.1 1 Unit Memasang Kusen Pintu Jendela Aluminium Type P1 8,968,225.00


17.5 M' Gawang Kuseng Aluminium 105,000.00 1,837,500.00
3.08 M2 Kaca Bening 5 mm 90,000.00 277,200.00
3.08 M2 Kaca Bening 10 mm 850,000.00 2,618,000.00
11.6 M Bingkai aluminium 45,000.00 522,000.00
2 Psg Handle Pintu Tanam Biasa 550,000.00 1,100,000.00
1 Set Door Closer 350,000.00 350,000.00
1 Bh Kunci Tanam 220,000.00 220,000.00
2 Psg Engsel Pintu 40,200.00 80,400.00
6 Oh Pekerja 100,000.00 600,000.00
6 Oh Tukang Besi 120,000.00 720,000.00
Perlengkapan 35% 643,125.00

G.2 1 Unit memasang Kusen Aluminium Type P2 3,475,900.00


6.4 M' Gawang Kuseng Aluminium 105,000.00 672,000.00
1.41 M2 Kaca Bening 10 mm 850,000.00 1,198,500.00
6.2 M Bingkai aluminium 45,000.00 279,000.00
1 Psg Handle Pintu Tanam Biasa 250,000.00 250,000.00
1 Set Door Closer 350,000.00 350,000.00
1 Bh Kunci Tama Biasa 220,000.00 220,000.00
1 Psg Engsel Pintu 40,200.00 40,200.00
1.05 Oh Pekerja 100,000.00 105,000.00
1.05 Oh Tukang Besi 120,000.00 126,000.00
Perlengkapan 35% 235,200.00

G.3 1 Unit memasang Kusen Aluminium 802,455.00


4.98 M' Gawang Kuseng Aluminium 105,000.00 423,300.00
1.05 Oh Pekerja 100,000.00 105,000.00
1.05 Oh Tukang Besi 120,000.00 126,000.00

Perlengkapan 35% 148,155.00

G.4 1 Unit memasang Kusen Jendela Aluminium Type J1 3,839,845.00


17.5 M' Gawang Kuseng Aluminium 85,000.00 1,487,500.00
M' Bingkai aluminium 45,000.00 -
6.6 M2 Kaca Bening 5 mm 144,200.00 951,720.00
Ps Engsel jendela 26,600.00 -
Ps Hak angin lipat 15,500.00 -
Bh Grendel 10,300.00 -
4 Oh Pekerja 100,000.00 400,000.00
4 Oh Tukang Besi 120,000.00 480,000.00
Perlengkapan 35% 520,625.00

G.5 1 Unit memasang Kusen Aluminium Type JPU 3,478,188.78


22 M' Gawang Kuseng Aluminium 85,000.00 1,843,650.00
M' Bingkai aluminium 45,000.00 -
5.26 M2 Kaca Bening 5 mm 144,200.00 758,261.28
Ps Engsel jendela 26,600.00 -
Ps Hak angin lipat 15,500.00 -
1.05 Oh Pekerja 100,000.00 105,000.00
1.05 Oh Tukang Besi 120,000.00 126,000.00

Perlengkapan 35% 645,277.50

G.6 1 Unit memasang Kusen Jendela Aluminium Type J2 1,350,568.00


6 M' Gawang Kuseng Aluminium 85,000.00 510,000.00
M' Bingkai aluminium 45,000.00 -
1.54 M2 Kaca Bening 5 mm 144,200.00 222,068.00
Ps Engsel jendela 26,600.00 -
Ps Hak angin lipat 15,500.00 -
Bh Grendel 10,300.00 -
2 Oh Pekerja 100,000.00 200,000.00
2 Oh Tukang Besi 120,000.00 240,000.00
Perlengkapan 35% 178,500.00

G.7 1 Unit memasang Kusen Aluminium Type J3 2,205,736.00


9.6 M' Gawang Kuseng Aluminium 85,000.00 816,000.00
3.08 M2 Kaca Bening 5 mm 144,200.00 444,136.00
3 Oh Pekerja 100,000.00 300,000.00
3 Oh Tukang Besi 120,000.00 360,000.00
Perlengkapan 35% 285,600.00

G.8 1 Unit memasang Kusen Aluminium Type J5 2,212,699.34


7.95 M' Gawang Kuseng Aluminium 85,000.00 675,750.00
1.22 M2 Kaca Bening 5 mm 144,200.00 175,231.84
1.05 Oh Pekerja 100,000.00 105,000.00
1.05 Oh Tukang Besi 120,000.00 126,000.00

Perlengkapan 35% 236,512.50


G.8 1 Unit memasang Kusen Aluminium Type J4 894,205.00
4.1 M' Gawang Kuseng Aluminium 85,000.00 348,500.00
0.65 M2 Kaca Bening 5 mm 144,200.00 93,730.00
1.5 Oh Pekerja 100,000.00 150,000.00
1.5 Oh Tukang Besi 120,000.00 180,000.00
Perlengkapan 35% 121,975.00

G.9 1 Unit memasang Partisi Kaca Uk. 3,70 m x 3,60 m 6,551,344.00


32.8 M' Gawang Kuseng Aluminium 85,000.00 2,788,000.00
9.6 M' Bingkai Aluminium 45,000.00 432,000.00
13 M2 Kaca Bening 5 mm 144,200.00 1,920,744.00
2 Ps Grendel 10,300.00 20,600.00
2 Ps Engsel jendela 26,600.00 53,200.00
2 Bh Hak Angin Lipat 15,500.00 31,000.00
1.5 Oh Pekerja 100,000.00 150,000.00
1.5 Oh Tukang Besi 120,000.00 180,000.00

Perlengkapan 35% 975,800.00

G.10 Pekerjaan Pasangan Jalusi 623,090.00


0.06 M3 Kayu Kelas Kuat I-II Papan 5,500,000.00 330,000.00
0.15 Kg Paku Biasa 20,600.00 3,090.00
0.5 Oh Pekerja 100,000.00 50,000.00
2 Oh Tukang Kayu 120,000.00 240,000.00
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.10 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 5PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 9.680 1,200.00 11,616.00
pasir pasang m3 0.045 190,000.00 8,550.00
JUMLAH HARGA BAHAN 27,166.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 69,416.00


E Overhead & Profit 10% 6,941.60
F Harga Satuan Pekerjaan (D+E) 76,300.00

A.4.4.1.11 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 6PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 8.320 1,200.00 9,984.00
pasir pasang m3 0.049 190,000.00 9,310.00
JUMLAH HARGA BAHAN 26,294.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 68,544.00


E Overhead & Profit 10% 6,854.40
F Harga Satuan Pekerjaan (D+E) 75,300.00

A.4.4.1.12 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 8PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 6.500 1,200.00 7,800.00
pasir pasang m3 0.050 190,000.00 9,500.00
JUMLAH HARGA BAHAN 24,300.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 66,550.00
E Overhead & Profit 10% 6,655.00
F Harga Satuan Pekerjaan (D+E) 73,200.00

A.4.4.1.13 Pembuatan 1 m2 diding bata merah (5x11x22) cm tebal 1/2 batu camp 1SP : 10PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 4.500 1,200.00 5,400.00
Kapur padam m3 0.015 -
pasir pasang m3 0.050 190,000.00 9,500.00
JUMLAH HARGA BAHAN 21,900.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 64,150.00


E Overhead & Profit 10% 6,415.00
F Harga Satuan Pekerjaan (D+E) -

A.4.4.1.14 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :1PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 0.018 1,200.00 21.60
Kapur padam m3 0.018
pasir pasang m3 0.018 190,000.00 3,420.00
JUMLAH HARGA BAHAN 10,441.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 52,691.60


E Overhead & Profit 10% 5,269.16
F Harga Satuan Pekerjaan (D+E) -

A.4.4.1.15 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
bata merah m3 70.000 100.00 7,000.00
Semen portland Kg 0.014 1,200.00 16.80
Kapur padam m3 0.014 -
pasir pasang m3 0.028 190,000.00 5,320.00
JUMLAH HARGA BAHAN 12,336.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 54,586.80


E Overhead & Profit 10% 5,458.68
F Harga Satuan Pekerjaan (D+E) -

A.4.4.1.16 Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,000.00 33,250.00
Tukang batu L.02 OH 0.150 110,000.00 16,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 53,380.00
B BAHAN
HB-20 m3 12.500 9,500.00 118,750.00
Semen Portland Kg 30.320 1,200.00 36,384.00
Pasir pasang m3 0.728 190,000.00 138,320.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 296,814.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 350,194.00


E Overhead & Profit 10% 35,019.40
F Harga Satuan Pekerjaan (D+E) 385,200.00

A.4.4.1.17 Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 4PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,000.00 33,250.00
Tukang batu L.02 OH 0.150 110,000.00 16,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 53,380.00
B BAHAN
HB-20 m3 12.500 9,500.00 118,750.00
Semen Portland Kg 24.260 1,200.00 29,112.00
Pasir pasang m3 0.772 190,000.00 146,680.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 297,902.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 351,282.00


E Overhead & Profit 10% 35,128.20
F Harga Satuan Pekerjaan (D+E) 386,400.00

A.4.4.1.18 Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 3PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.320 95,000.00 30,400.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 46,680.00
B BAHAN
HB-15 m3 12.500 9,000.00 112,500.00
Semen Portland Kg 22.740 1,200.00 27,288.00
Pasir pasang m3 0.550 190,000.00 104,500.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 247,648.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 294,328.00


E Overhead & Profit 10% 29,432.80
F Harga Satuan Pekerjaan (D+E) 323,700.00

A.4.4.1.19 Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 4PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.320 95,000.00 30,400.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 46,680.00
B BAHAN
HB-15 m3 12.500 9,000.00 112,500.00
Semen Portland Kg 18.200 1,200.00 21,840.00
Pasir pasang m3 0.582 190,000.00 110,580.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 248,280.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 294,960.00


E Overhead & Profit 10% 29,496.00
F Harga Satuan Pekerjaan (D+E) 324,400.00

A.4.4.1.20 Pemasangan 1m2 dinding conblock HB10 campuran 1SP : 3PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
HB-15 m3 12.500 9,000.00 112,500.00
Semen Portland Kg 15.160 1,200.00 18,192.00
Pasir pasang m3 0.364 190,000.00 69,160.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 203,212.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 245,462.00


E Overhead & Profit 10% 24,546.20
F Harga Satuan Pekerjaan (D+E) 270,000.00

A.4.4.1.21 Pemasangan 1m2 dinding conblock HB10 campuran 1SP : 4PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
HB-10 m3 12.500 7,500.00 93,750.00
Semen Portland Kg 12.130 1,200.00 14,556.00
Pasir pasang m3 0.388 190,000.00 73,720.00
Besi angker diameter 8 Kg 0.280 12,000.00 3,360.00
JUMLAH HARGA BAHAN 185,386.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 227,636.00


E Overhead & Profit 10% 22,763.60
F Harga Satuan Pekerjaan (D+E) 250,300.00

A.4.4.1.22 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :3PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
Bata rooster m3 30.000 13,000.00 390,000.00
Semen Portland Kg 11.000 1,200.00 13,200.00
Pasir pasang m3 0.035 190,000.00 6,650.00
JUMLAH HARGA BAHAN 409,850.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 452,100.00


E Overhead & Profit 10% 45,210.00
F Harga Satuan Pekerjaan (D+E) -

A.4.4.1.23 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
Bata rooster m3 30.000 13,000.00 390,000.00
Semen Portland Kg 11.000 1,200.00 13,200.00
Pasir pasang m3 0.035 190,000.00 6,650.00
JUMLAH HARGA BAHAN 409,850.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 452,100.00


E Overhead & Profit 10% 45,210.00
F Harga Satuan Pekerjaan (D+E) 497,300.00
A.4.4.1.24 Pemasangan 1 cm2 dinding bata berongga ekspose 12x11x24 campuran 1SP :3PP

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.150 110,000.00 16,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 48,300.00
B BAHAN
Bata rooster m3 70.000 7,900.00 553,000.00
Semen Portland Kg 14.000 1,200.00 16,800.00
Pasir pasang m3 0.032 190,000.00 6,080.00
JUMLAH HARGA BAHAN 575,880.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 624,180.00


E Overhead & Profit 10% 62,418.00
F Harga Satuan Pekerjaan (D+E) -

A.4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
Bata ringan tebal 7,5cm bh 8.400 9,600.00 80,640.00
Prime Mortar (PM - 100) Kg 0.473 1,725.00 815.93
JUMLAH HARGA BAHAN 81,455.93
C PERALATAN
Peralatan % 10 8,145.59 8,145.59
JUMLAH HARGA ALAT 8,145.59

D Jumlah (A+B+C) 131,851.52


E Overhead & Profit 10% 13,185.15
F Harga Satuan Pekerjaan (D+E) 145,000.00

A.4.4.1.26 Pemasangan 1m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,250.00
B BAHAN
Bata ringan (hebel) 20x60x10 bh 8.400 10,900.00 91,560.00
Prime Mortar (PM - 100) Kg 0.063 1,725.00 108.68
JUMLAH HARGA BAHAN 91,668.68
C PERALATAN
Peralatan % 10 9,166.87 9,166.87
JUMLAH HARGA ALAT 9,166.87

D Jumlah (A+B+C) 143,085.54


E Overhead & Profit 10% 14,308.55
F Harga Satuan Pekerjaan (D+E) 157,300.00

A.4.4.1.27 1 m2 PARTISI GIFSUM, RANGKA BAJA RINGAN

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.370 95,000.00 35,150.00
Tukang batu L.02 OH 0.037 110,000.00 4,070.00
Kepala Tukang L.03 OH 0.240 110,000.00 26,400.00
Mandor L.04 OH 0.012 110,000.00 1,320.00
JUMLAH TENAGA KERJA 66,940.00
B BAHAN
Rangka Baja Ringan m' 4.500 14,500.00 65,250.00
Gypsum board 9 mm lbr 0.720 73,000.00 52,560.00
Kasa gypsum roll 0.050 11,000.00 550.00
Tepung gypsum kg 0.450 4,750.00 2,137.50
Alkasit kg 0.003 5,000.00 15.00
Paku skrup kg 0.150 35,270.00 5,290.50
JUMLAH HARGA BAHAN 125,803.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 192,743.00


E Overhead & Profit 10% 19,274.30
F Harga Satuan Pekerjaan (D+E) 212,000.00
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.5 Pemasangan 1 m2 pelesteran 1SP : 5PP tebal 15mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang batu L.02 OH 0.150 110,000.00 16,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 48,300.00
B BAHAN
Semen portland kg 5.184 1,200.00 6,220.80
pasir pasang M3 0.026 190,000.00 4,940.00
JUMLAH HARGA BAHAN 11,160.80
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 59,460.80


E Overhead & Profit 10% 5,946.08
F Harga Satuan Pekerjaan (D+E) 65,400.00

A.4.4.2.27 Pemasangan 1 m2 acian

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 32,200.00
B BAHAN
Semen portland kg 3.250 1,200.00 3,900.00
JUMLAH HARGA BAHAN 3,900.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 36,100.00


E Overhead & Profit 10% 3,610.00
F Harga Satuan Pekerjaan (D+E) 39,700.00
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.24 Pemasangan 1 m’ plint ubin granit ukuran 10 cm x 40 cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.090 95,000.00 8,550.00
Tukang batu L.02 OH 0.090 110,000.00 9,900.00
Kepala Tukang L.03 OH 0.009 110,000.00 990.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,990.00
B BAHAN
Plint ubin granit Bh 2.650 - -
Semen Portland kg 1.140 1,200.00 1,368.00
Semen warna Kg 0.100 13,250.00 1,325.00
Pasir pasang M3 0.003 190,000.00 570.00
JUMLAH HARGA BAHAN 3,263.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,253.00


E Overhead & Profit 10% 2,325.30
F Harga Satuan Pekerjaan (D+E) 25,500.00

Dihit. I-04 Pemasangan 1 m2 lantai keramik ukuran 25 cm x 25 cm warna/corak/antislip

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 95,000.00 66,500.00
Tukang batu L.02 OH 0.350 110,000.00 38,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 112,700.00
B BAHAN
Ubin keramik dus 1.050 62,000.00 65,100.00
Semen Portland Kg 10.000 1,200.00 12,000.00
Pasir pasang m3 0.045 190,000.00 8,550.00
Semen warna Kg 0.500 13,250.00 6,625.00
JUMLAH HARGA BAHAN 92,275.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 204,975.00


E Overhead & Profit 10% 20,497.50
F Harga Satuan Pekerjaan (D+E) 225,400.00

Dihit. I-05 Pemasangan 1 m2 dinding keramik 25 cm x 40 cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.900 95,000.00 85,500.00
Tukang batu L.02 OH 0.450 110,000.00 49,500.00
Kepala Tukang L.03 OH 0.045 110,000.00 4,950.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 144,900.00
B BAHAN
Keramik dus 1.050 74,000.00 77,700.00
Semen Portland Kg 9.300 1,200.00 11,160.00
Pasir pasang m3 0.018 190,000.00 3,420.00
Semen warna Kg 1.940 13,250.00 25,705.00
JUMLAH HARGA BAHAN 117,985.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 262,885.00
E Overhead & Profit 10% 26,288.50
F Harga Satuan Pekerjaan (D+E) 289,100.00
A.4.4.3.61 Pemasangan 1m2 floor harderner

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 26,580.00
B BAHAN
Floor harderner kg 5.000 21,000.00 105,000.00
JUMLAH HARGA BAHAN 105,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 131,580.00


E Overhead & Profit 10% 13,158.00
F Harga Satuan Pekerjaan (D+E) 144,700.00

A.4.4.3.62 Pemasangan 1 m’ plint vynil 15cm x 30cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.080 95,000.00 7,600.00
Tukang batu L.02 OH 0.080 110,000.00 8,800.00
Kepala Tukang L.03 OH 0.008 110,000.00 880.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 17,720.00
B BAHAN
Vynil buah 1.760 - -
Lem Kg 0.080 121,000.00 9,680.00
JUMLAH HARGA BAHAN 9,680.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,400.00


E Overhead & Profit 10% 2,740.00
F Harga Satuan Pekerjaan (D+E) 30,100.00

A.4.4.3.63 Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 26,580.00
B BAHAN
Papan kayu kelas 1 M3 0.003 3,527,000.00 10,581.00
Paku/skrup 5 cm Kg 0.050 13,000.00 650.00
JUMLAH HARGA BAHAN 11,231.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37,811.00


E Overhead & Profit 10% 3,781.10
F Harga Satuan Pekerjaan (D+E) 41,500.00

A.4.4.3.64 Pemasangan 1 m2 paving block natural tebal 6 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.250 95,000.00 23,750.00
Tukang batu L.02 OH 0.500 110,000.00 55,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 84,393.00
B BAHAN
Paving block 6 cm M2 1.010 75,000.00 75,750.00
Pasir beton M3 0.050 220,000.00 11,000.00
JUMLAH HARGA BAHAN 86,750.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 171,143.00


E Overhead & Profit 10% 17,114.30
F Harga Satuan Pekerjaan (D+E) 188,200.00

A.4.4.3.65 Pemasangan 1 m2 paving block natural tebal 8 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 95,000.00 47,500.00
Tukang batu L.02 OH 0.500 110,000.00 55,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 108,143.00
B BAHAN
Paving block 8 cm natural M2 1.010 85,000.00 85,850.00
Pasir beton M3 2.070 220,000.00 455,400.00
JUMLAH HARGA BAHAN 541,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 649,393.00


E Overhead & Profit 10% 64,939.30
F Harga Satuan Pekerjaan (D+E) 714,300.00

A.4.4.3.66 Pemasangan 1 m2 paving block berwarna tebal 6 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.250 95,000.00 23,750.00
Tukang batu L.02 OH 0.500 110,000.00 55,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 84,393.00
B BAHAN
Paving block 6cm berwarna M2 1.010 90,000.00 90,900.00
Pasir beton M3 0.050 220,000.00 11,000.00
JUMLAH HARGA BAHAN 101,900.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 186,293.00


E Overhead & Profit 10% 18,629.30
F Harga Satuan Pekerjaan (D+E) 204,900.00

A.4.4.3.67 Pemasangan 1 m2 paving block berwarna tebal 8 cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 95,000.00 47,500.00
Tukang batu L.02 OH 0.500 110,000.00 55,000.00
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 108,143.00
B BAHAN
Paving block 8cm berwarna M2 1.010 90,000.00 90,900.00
Pasir beton M3 0.259 220,000.00 56,925.00
JUMLAH HARGA BAHAN 147,825.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 255,968.00


E Overhead & Profit 10% 25,596.80
F Harga Satuan Pekerjaan (D+E) 281,500.00

A.4.4.3.68 Pemasangan 1 m2 keramik stepnozing

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.090 95,000.00 8,550.00
Tukang batu L.02 OH 0.090 110,000.00 9,900.00
Kepala Tukang L.03 OH 0.009 110,000.00 990.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,990.00
B BAHAN
Stepnosing bh 6.000 40,000.00 240,000.00
Semen portland Kg 1.140 1,200.00 1,368.00
Pasir Pasang m3 0.003 190,000.00 570.00
semen warna kg 0.100 13,250.00 1,325.00
JUMLAH HARGA BAHAN 243,263.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 263,253.00


E Overhead & Profit 10% 26,325.30
F Harga Satuan Pekerjaan (D+E) 289,500.00

A.4.4.3.69 Pemasangan 1 M2 Lantai Granit 60 x 60 Cm Warna / Corak Polised

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.240 95,000.00 22,800.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.012 110,000.00 1,320.00
JUMLAH TENAGA KERJA 38,640.00
B BAHAN
Granit 60 x 60 cm warna m2 1.100 241,500.00 265,650.00
Semen portland Kg 9.600 1,200.00 11,520.00
semen warna kg 1.500 13,250.00 19,875.00
Pasir Pasang m3 0.045 190,000.00 8,550.00
JUMLAH HARGA BAHAN 305,595.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 344,235.00


E Overhead & Profit 10% 34,423.50
F Harga Satuan Pekerjaan (D+E) 378,600.00

A.4.4.3.70 Pemasangan 1 M2 Lantai Granit 60 x 60 Cm Warna / Corak Unpolised

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.240 95,000.00 22,800.00
Tukang batu L.02 OH 0.120 110,000.00 13,200.00
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.00
Mandor L.04 OH 0.012 110,000.00 1,320.00
JUMLAH TENAGA KERJA 38,640.00
B BAHAN
Ubin keramik m2 1.100 241,500.00 265,650.00
Semen portland Kg 9.600 1,200.00 11,520.00
semen warna kg 1.500 13,250.00 19,875.00
Pasir Pasang m3 0.045 190,000.00 8,550.00
JUMLAH HARGA BAHAN 305,595.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 344,235.00


E Overhead & Profit 10% 34,423.50
F Harga Satuan Pekerjaan (D+E) 378,600.00
A.4.5.1 HARGA SATUAN PEKERJAAN PENUTUP PLAFOND

Dihitung Pemasangan 1 m2 ceilling concealed

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.323 67,000.00 21,641.000
Tukang Kayu L.02 OH 0.970 90,000.00 -
Kepala Tukang L.03 OH 0.005 95,000.00 -
Mandor L.04 OH 0.970 95,000.00 92,150.000
JUMLAH TENAGA KERJA 113,791.000
B BAHAN
Top Cros m' 0.000 #NAME? #NAME?
Furing Chanel
Wall Angel ( Lokal )
Kawat baja roll 0.550 55,000.00 30,250.000
Conector bh 1.300 4,000.00 5,200.000
Suspension Spring Clip 5mm -
Suspension Rod 100 cm, 5mm bh 0.620 6,000.00 3,720.000
Besi Angle Bracket -
Baut Ramset -
Paku Beton kg 0.110 #NAME? -
JUMLAH HARGA BAHAN #NAME?
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #NAME?


E Overhead & Profit 10% #NAME?
F Harga Satuan Pekerjaan (D+E) #NAME?
A.4.5.1.1 Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.030 95,000.00 2,850.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 11,760.000
B BAHAN
Asbes semen m2 1.100 28,500.00 31,350.000
Paku tripleks kg 0.110 19,250.00 2,117.500
JUMLAH HARGA BAHAN 33,467.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,227.50


E Overhead & Profit 10% 4,522.75
F Harga Satuan Pekerjaan (D+E) 49,700.00

A.4.5.1.2 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.000
Tukang Kayu L.02 OH 0.120 110,000.00 13,200.000
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.000
Mandor L.04 OH 0.006 110,000.00 660.000
JUMLAH TENAGA KERJA 26,580.000
B BAHAN
Akustik Lembar 12.000 - -
Paku tripleks kg 0.050 19,250.00 962.500
JUMLAH HARGA BAHAN 962.500
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,542.50


E Overhead & Profit 10% 2,754.25
F Harga Satuan Pekerjaan (D+E) 30,200.00

A.4.5.1.3 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.000
Tukang Kayu L.02 OH 0.120 110,000.00 13,200.000
Kepala Tukang L.03 OH 0.012 110,000.00 1,320.000
Mandor L.04 OH 0.006 110,000.00 660.000
JUMLAH TENAGA KERJA 26,580.000
B BAHAN
Akustik Lembar 5.800 - -
Paku tripleks kg 0.050 19,250.00 962.500
JUMLAH HARGA BAHAN 962.500
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,542.50


E Overhead & Profit 10% 2,754.25
F Harga Satuan Pekerjaan (D+E) 30,200.00

A.4.5.1.4 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.000
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.000
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.000
Mandor L.04 OH 0.005 110,000.00 550.000
JUMLAH TENAGA KERJA 22,150.000
B BAHAN
Akustik Lembar 1.500 - -
Paku tripleks kg 0.050 19,250.00 962.500
JUMLAH HARGA BAHAN 962.500
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,112.50


E Overhead & Profit 10% 2,311.25
F Harga Satuan Pekerjaan (D+E) 25,400.00

A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.000
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.000
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.000
Mandor L.04 OH 0.005 110,000.00 550.000
JUMLAH TENAGA KERJA 22,150.000
B BAHAN
Tripleks Lembar 0.375 67,600.00 25,350.000
Paku tripleks kg 0.030 19,250.00 577.500
JUMLAH HARGA BAHAN 25,927.500
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 48,077.50


E Overhead & Profit 10% 4,807.75
F Harga Satuan Pekerjaan (D+E) 52,800.00

A.4.5.1.6 Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 95,000.00 76,000.000
Tukang Kayu L.02 OH 0.800 110,000.00 88,000.000
Kepala Tukang L.03 OH 0.080 110,000.00 8,800.000
Mandor L.04 OH 0.040 110,000.00 4,400.000
JUMLAH TENAGA KERJA 177,200.000
B BAHAN
Kayu papan m3 0.015 3,527,000.00 52,905.000
Paku tripleks kg 0.010 19,250.00 192.500
JUMLAH HARGA BAHAN 53,097.500
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 230,297.50


E Overhead & Profit 10% 23,029.75
F Harga Satuan Pekerjaan (D+E) 253,300.00

A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240) cm, tebal 9 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 16,100.00
B BAHAN
Gypsum board lbr 0.364 73,000.00 26,572.00
Paku skrup kg 0.110 35,270.00 3,879.70
JUMLAH HARGA BAHAN 30,451.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 46,551.70


E Overhead & Profit 10% 4,655.17
F Harga Satuan Pekerjaan (D+E) 51,200.00

Dihit. J-01 Pemasangan 1 m2 langit-langit GRC board ukuran (120x240) cm, tebal 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 16,100.00
B BAHAN
GRC board Lembar 0.364 68,000.00 24,752.00
Paku skrup kg 0.110 36,500.00 4,015.00
JUMLAH HARGA BAHAN 28,767.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 44,867.00


E Overhead & Profit 10% 4,486.70
F Harga Satuan Pekerjaan (D+E) 49,300.00

A.4.5.1.8 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 95,000.00 47,500.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.025 110,000.00 2,750.000
JUMLAH TENAGA KERJA 110,750.000
B BAHAN
Profil Allum "T" m 3.600 - -
Kawat Ø 4 mm kg 0.150 22,900.00 3,435.000
Ramset Buah 1.050 30,400.00 31,920.000
Akustik 60 x 120 Lembar 1.500 - -
JUMLAH HARGA BAHAN 35,355.000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 146,105.00


E Overhead & Profit 10% 14,610.50
F Harga Satuan Pekerjaan (D+E) 160,700.00

A.4.5.1.9 Pemasangan 1 m’ list langit-langit kayu profil

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 95,000.00 4,750.000
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.000
Kepala Tukang L.03 OH 0.005 110,000.00 550.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 11,130.000
B BAHAN
List kayu profil m 1.050 9,350.00 9,817.500
Paku kg 0.010 19,250.00 192.500
JUMLAH HARGA BAHAN 10,010.000
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 21,140.00


E Overhead & Profit 10% 2,114.00
F Harga Satuan Pekerjaan (D+E) 23,200.00

A.4.5.1.10 Pemasangan 1 m2 rangka besi hollow 1x40.40.1,3 mm, modul 60 x 60 cm, plafond

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,000.00 33,250.00
Tukang besi L.03 OH 0.350 110,000.00 38,500.00
Kepala Tukang L.03 OH 0.035 110,000.00 3,850.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 77,580.00
B BAHAN
Hollow 4 x 4 m' 4.000 24,100.00 96,400.000
Assesories (perkuatan, las dll) Ls 100%xrangka 24,100.00 24,100.000
JUMLAH HARGA BAHAN 120,500.000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 198,080.00


E Overhead & Profit 10% 19,808.00
F Harga Satuan Pekerjaan (D+E) 217,800.00

A.4.5.1.11 Pemasangan 1 m' list langit-langit gypsum

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 95,000.00 4,750.00
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,130.00
B BAHAN
List Gypsum m 1.050 14,000.00 14,700.00
Paku kg 0.010 35,270.00 352.70
JUMLAH HARGA BAHAN 15,052.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 26,182.70


E Overhead & Profit 10% 2,618.27
F Harga Satuan Pekerjaan (D+E) 28,800.00

A.4.5.1.12 Pemasangan 1 m' plafond up ceilling gypsum board lebar 15 cm, tebal 9 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA 1.75
Pekerja L.01 OH 0.175 95,000.00 16,625.000
Tukang Kayu L.02 OH 0.088 110,000.00 9,625.000
Kepala Tukang L.03 OH 0.009 110,000.00 962.500
Mandor L.04 OH 0.009 110,000.00 962.500
JUMLAH TENAGA KERJA 28,175.000
B BAHAN
Gypsum board Lembar 0.050 73,000.00 3,678.447
Rangka Hollow m' 2.700 19,808.00 53,481.600
Plester roll 0.020 16,000.00 320.000
Paku skrup gross 0.110 35,270.00 3,879.700
Cornis Compound kg 0.110 5,000.00 550.000
JUMLAH HARGA BAHAN 61,909.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 90,084.75


E Overhead & Profit 10% 9,008.47
F Harga Satuan Pekerjaan (D+E) 99,000.00

Dihitung Pemasangan 1 m2 Dinding HPL

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.850 95,000.00 80,750.000
Tukang Kayu L.02 OH 2.550 110,000.00 280,500.000
Kepala Tukang L.03 OH 0.255 110,000.00 28,050.000
Mandor L.04 OH 0.043 110,000.00 4,730.000
JUMLAH TENAGA KERJA 394,030.000
B BAHAN
Rangka Hollow m 8.100 19,808.00 160,444.800
HPL lbr 0.382 112,000.00 42,777.778
Plywood tebal 9 mm lbr 0.382 140,700.00 53,739.583
Plat stainless steel m' 1.100 55,000.00 60,500.000
Paku, Sekrup & Fisher gross 0.500 55,000.00 27,500.000
Lem kuning kg 0.300 61,600.00 18,480.000
Lem Kayu kg 0.300 22,000.00 6,600.000
Acessories % 0.125 370,042.16 46,255.270
JUMLAH HARGA BAHAN 416,297.43
C PERALATAN
Alat Bantu % 30 416,297.43 124,889.229
JUMLAH HARGA ALAT 124,889.229

D Jumlah (A+B+C) 935,216.66


E Overhead & Profit 10% 93,521.67
F Harga Satuan Pekerjaan (D+E) 1,028,700.00
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.1 Pemasangan 1 m2 atap genteng palentong kecil

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.000
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.000
Kepala Tukang L.03 OH 0.008 110,000.00 825.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 24,205.000
B BAHAN
genteng palentong bh 25.000 2,900.00 72,500.000
JUMLAH HARGA BAHAN 72,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 96,705.00


E Overhead & Profit 10% 9,670.50
F Harga Satuan Pekerjaan (D+E) 106,300.00

Dihit. K-01 Pemasangan 1 m2 atap genteng morando glasuur

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.00
Kepala Tukang L.03 OH 0.008 110,000.00 825.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 24,205.00
B BAHAN
genteng morando glassur bh 18.000 4,700.00 84,600.00
JUMLAH HARGA BAHAN 84,600.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 108,805.00


E Overhead & Profit 10% 10,880.50
F Harga Satuan Pekerjaan (D+E) 119,600.00

A.4.5.2.2 Pemasangan 1 m2 atap genteng kodok

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.000
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.000
Kepala Tukang L.03 OH 0.008 110,000.00 880.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 24,260.000
B BAHAN
Genteng kodok bh 25.000 3,900.00 97,500.000
JUMLAH HARGA BAHAN 97,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 121,760.00


E Overhead & Profit 10% 12,176.00
F Harga Satuan Pekerjaan (D+E) 133,900.00

A.4.5.2.3 Pemasangan 1 m2 atap genteng palentong besar/super


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.000
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.000
Kepala Tukang L.03 OH 0.008 110,000.00 880.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 24,260.000
B BAHAN
genteng palentong bh 12.000 3,100.00 37,200.000
JUMLAH HARGA BAHAN 37,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 61,460.00


E Overhead & Profit 10% 6,146.00
F Harga Satuan Pekerjaan (D+E) 67,600.00

A.4.5.2.4 Pemasangan 1 m' bubung genteng palentong

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.002 110,000.00 220.000
JUMLAH TENAGA KERJA 62,420.000
B BAHAN
genteng bubung bh 5.000 7,700.00 38,500.000
semen portland kg 8.000 1,200.00 9,600.000
pasir pasang m3 0.032 190,000.00 6,080.000
JUMLAH HARGA BAHAN 54,180.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 116,600.00


E Overhead & Profit 10% 11,660.00
F Harga Satuan Pekerjaan (D+E) 128,200.00

A.4.5.2.5 Pemasangan 1 m’ bubung genteng kodok glazuur

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.002 110,000.00 220.000
JUMLAH TENAGA KERJA 62,420.000
B BAHAN
genteng bubung bh 5.000 - -
semen portland kg 8.000 1,200.00 9,600.000
pasir pasang m3 0.032 190,000.00 6,080.000
JUMLAH HARGA BAHAN 15,680.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 78,100.00


E Overhead & Profit 10% 7,810.00
F Harga Satuan Pekerjaan (D+E) 85,900.00

A.4.5.2.6 Pemasangan 1 m’ bubung genteng palentong besar


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.002 110,000.00 220.000
JUMLAH TENAGA KERJA 62,420.000
B BAHAN
genteng bubung bh 4.000 - -
semen portland kg 8.000 1,200.00 9,600.000
pasir pasang m3 0.032 190,000.00 6,080.000
JUMLAH HARGA BAHAN 15,680.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 78,100.00


E Overhead & Profit 10% 7,810.00
F Harga Satuan Pekerjaan (D+E) 85,900.00

Dihit. K-02 Pemasangan 1 m’ bubung morando glasuur

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.00
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 62,420.00
B BAHAN
genteng bubung bh 4.000 6,500.00 26,000.00
semen portland kg 8.000 1,200.00 9,600.00
pasir pasang m3 0.032 190,000.00 6,080.00
JUMLAH HARGA BAHAN 41,680.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 104,100.00


E Overhead & Profit 10% 10,410.00
F Harga Satuan Pekerjaan (D+E) 114,500.00

A.4.5.2.7 Pemasangan 1 m2 roof light fibreglass 90 x 180

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.067 110,000.00 7,370.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,210.000
B BAHAN
Rooflight 90 x 180 Lbr 0.600 - -
Paku biasa ½”-1” Kg 0.050 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,210.00


E Overhead & Profit 10% 2,221.00
F Harga Satuan Pekerjaan (D+E) 24,400.00
A.4.5.2.8 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.000
Kepala Tukang L.03 OH 0.008 110,000.00 880.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 23,310.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.500 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,310.00


E Overhead & Profit 10% 2,331.00
F Harga Satuan Pekerjaan (D+E) 25,600.00

A.4.5.2.9 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.075 110,000.00 8,250.000
Kepala Tukang L.03 OH 0.008 110,000.00 880.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 23,310.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.600 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,310.00


E Overhead & Profit 10% 2,331.00
F Harga Satuan Pekerjaan (D+E) 25,600.00

A.4.5.2.10 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 2 ,5 m x 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.600 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00
A.4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 1.80 m x 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.750 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.12 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 3.00 m x 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.350 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.13 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.70 m x 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.420 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00
A.4.5.2.14 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.40 m x 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.440 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.15 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 2.10 m x 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.510 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.16 Pemasangan 1 m2 atap asbes gelombang 1.05 m x 1.50 m x 4 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.800 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00
A.4.5.2.17 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 3.00 m x 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.370 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.18 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.70 m x 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.380 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.19 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.40 m x 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.460 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00
A.4.5.2.20 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 2.10 m x 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.490 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.21 Pemasangan 1 m2 atap asbes gelombang 1.08 m x 1.80 m x 6 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.000
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.000
Kepala Tukang L.03 OH 0.007 110,000.00 770.000
Mandor L.04 OH 0.007 110,000.00 770.000
JUMLAH TENAGA KERJA 22,540.000
B BAHAN
Asbes gel 92 x 250 Lbr 0.570 - -
Paku pancing 6 x 23 Kg 0.120 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,540.00


E Overhead & Profit 10% 2,254.00
F Harga Satuan Pekerjaan (D+E) 24,700.00

A.4.5.2.22 Pemasangan 1 m’ bubung stel gelombang 0.92 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Bubung stel gel. Lbr 2.400 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00
A.4.5.2.23 Pemasangan 1 m’ bubung stel gelombang 1.05 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Bubung stel gel. Lbr 2.100 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00

A.4.5.2.24 Pemasangan 1 m’ bubung stel gelombang 1.08 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Bubung stel gel. Lbr 2.050 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00

A.4.5.2.25 Pemasangan 1 m’ nok paten 0.92 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Nok paten 92 cm Lbr 1.200 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00
A.4.5.2.26 Pemasangan 1 m’ nok paten 1.05 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Nok paten 92 cm Lbr 1.200 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00

A.4.5.2.27 Pemasangan 1 m’ nok paten 1.08 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Nok paten 92 cm Lbr 1.200 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00

A.4.5.2.28 Pemasangan 1 m’ nok stel 0.92 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 27,870.000
B BAHAN
Nok stel 92 cm Lbr 1.100 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,870.00


E Overhead & Profit 10% 2,787.00
F Harga Satuan Pekerjaan (D+E) 30,600.00
A.4.5.2.29 Pemasangan 1 m’ nok stel 1.05 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.000
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.000
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 23,600.000
B BAHAN
Nok stel 92 cm Lbr 1.100 - -
Paku skrup 3.5” buah 6.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 23,600.00


E Overhead & Profit 10% 2,360.00
F Harga Satuan Pekerjaan (D+E) 25,900.00

A.4.5.2.30 Pemasangan 1 m2 genteng beton

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.000
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.000
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.000
Mandor L.04 OH 0.010 110,000.00 1,100.000
JUMLAH TENAGA KERJA 32,200.000
B BAHAN
Genteng beton buah 11.000 7,700.00 84,700.000
Paku biasa 2”-5” Kg 0.030 21,000.00 630.000
JUMLAH HARGA BAHAN 85,330.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 117,530.00


E Overhead & Profit 10% 11,753.00
F Harga Satuan Pekerjaan (D+E) 129,200.00

A.4.5.2.31 Pemasangan 1 m2 genteng bitument

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.140 95,000.00 13,300.00
Tukang Kayu L.02 OH 0.070 110,000.00 8,050.00
Kepala Tukang L.03 OH 0.007 110,000.00 822.50
Mandor L.04 OH 0.007 110,000.00 840.00
JUMLAH TENAGA KERJA 23,012.50
B BAHAN
Genteng onduline tile lbr 0.732 165,000.00 120,780.00
Sekrup bh 12.000 1,200.00 14,400.00
JUMLAH HARGA BAHAN 135,180.00
C PERALATAN
0.100 135,180.00 13,518.00
JUMLAH HARGA ALAT 13,518.00

D Jumlah (A+B+C) 171,710.50


E Overhead & Profit 10% 17,171.05
F Harga Satuan Pekerjaan (D+E) 188,881.55
A.4.5.2.32 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 31,210.00
B BAHAN
Genteng metal Buah 1.300 137,500.00 178,750.00
Paku biasa ½”-1” Kg 0.200 21,000.00 4,200.00
JUMLAH HARGA BAHAN 182,950.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 214,160.00


E Overhead & Profit 10% 21,416.00
F Harga Satuan Pekerjaan (D+E) 235,500.00

A.4.5.2.33 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.00
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 31,210.00
B BAHAN
Genteng metal Buah 2.000 137,500.00 275,000.00
Paku biasa ½”-1” Kg 0.200 21,000.00 4,200.00
JUMLAH HARGA BAHAN 279,200.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 310,410.00


E Overhead & Profit 10% 31,041.00
F Harga Satuan Pekerjaan (D+E) 341,400.00

A.4.5.2.34 Pemasangan 1 m2 atap sirap kayu

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.166 95,000.00 15,770.00
Tukang Kayu L.02 OH 0.250 110,000.00 27,500.00
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 46,900.00
B BAHAN
Sirap kayu buah 30.000 - -
Paku biasa ½”-1” Kg 0.200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 46,900.00


E Overhead & Profit 10% 4,690.00
F Harga Satuan Pekerjaan (D+E) 51,500.00
A.4.5.2.35 Pemasangan 1 m’ nok genteng beton

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.00
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 64,400.00
B BAHAN
Nok genteng beton buah 3.500 15,500.00 54,250.00
Paku biasa ½”-1” Kg 0.050 21,000.00 1,050.00
Semen PC Kg 10.800 1,200.00 12,960.00
Pasir pasang M3 0.032 190,000.00 6,080.00
Semen warna Kg 1.000 13,250.00 13,250.00
JUMLAH HARGA BAHAN 87,590.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 151,990.00


E Overhead & Profit 10% 15,199.00
F Harga Satuan Pekerjaan (D+E) 167,100.00

A.4.5.2.36 Pemasangan 1 m’ nok genteng aspal

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.084 95,000.00 7,980.00
Tukang Kayu L.02 OH 0.125 110,000.00 13,750.00
Kepala Tukang L.03 OH 0.013 110,000.00 1,430.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 23,600.00
B BAHAN
Nok genteng onduline lbr 1.474 85,000.00 125,290.00
Sekrup bh 10.000 1,200.00 12,000.00
JUMLAH HARGA BAHAN 137,290.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 160,890.00


E Overhead & Profit 10% 16,089.00
F Harga Satuan Pekerjaan (D+E) 176,900.00

A.4.5.2.37 Pemasangan 1 m’ nok genteng metal

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.250 95,000.00 23,750.00
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.00
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 43,330.00
B BAHAN
Nok genteng metal lmbr 1.100 83,300.00 91,630.00
Paku biasa ½”-1” Kg 0.050 21,000.00 1,050.00
JUMLAH HARGA BAHAN 92,680.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 136,010.00


E Overhead & Profit 10% 13,601.00
F Harga Satuan Pekerjaan (D+E) 149,600.00

A.4.5.2.38 Pemasangan 1 m’ nok sirap

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.125 95,000.00 11,875.00
Tukang Kayu L.02 OH 0.250 110,000.00 27,500.00
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 42,785.00
B BAHAN
Seng pelat 3" x 6” Lbr 0.400 - -
Paku biasa ½”-1” Kg 0.050
Paku biasa 2”-5” Kg 0.050 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,785.00


E Overhead & Profit 10% 4,278.50
F Harga Satuan Pekerjaan (D+E) 47,000.00

A.4.5.2.39 Pemasangan 1 m2 atap seng gelombang

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.00
Tukang Kayu L.02 OH 0.060 110,000.00 6,600.00
Kepala Tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 19,320.00
B BAHAN
Seng pelat 3" x 6” Lbr 0.700 - -
Paku biasa ½”-1” Kg 0.020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 19,320.00


E Overhead & Profit 10% 1,932.00
F Harga Satuan Pekerjaan (D+E) 21,200.00

A.4.5.2.40 Pemasangan 1 m’nok atap seng

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.070 110,000.00 7,700.00
Kepala Tukang L.03 OH 0.007 110,000.00 770.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,380.00
B BAHAN
Seng pelat 3”x6” bjls 28 Lbr 0.300 - -
Paku biasa ½”-1” Kg 0.040 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 23,380.00
E Overhead & Profit 10% 2,338.00
F Harga Satuan Pekerjaan (D+E) 25,700.00

A.4.5.2.41 Pemasangan 1 m2 atap alumunium

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.750 110,000.00 82,500.00
Kepala Tukang L.03 OH 0.080 110,000.00 8,800.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 106,210.00
B BAHAN
Aluminium gel tebal 0.55 Lbr 1.050 160,000.00 168,000.00
Paku hak Panjang 15 cm Kg 0.020 13,500.00 270.00
JUMLAH HARGA BAHAN 168,270.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 274,480.00


E Overhead & Profit 10% 27,448.00
F Harga Satuan Pekerjaan (D+E) 301,900.00

A.4.5.2.43 Pemasangan 1 m2 alumunium foil/sisalation

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,180.00
B BAHAN
Alumunium foil - m2 1.050 8,085.00 8,489.25
JUMLAH HARGA BAHAN 8,489.25
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,669.25


E Overhead & Profit 10% 2,966.93
F Harga Satuan Pekerjaan (D+E) 32,600.00

Dihit. K-43 Pemasangan 1 m2 Bubble alumunium foil

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.050 110,000.00 5,500.00
Kepala Tukang L.03 OH 0.005 110,000.00 550.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,180.00
B BAHAN
Alumunium foil - m2 1.050 14,070.00 14,773.50
JUMLAH HARGA BAHAN 14,773.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,953.50


E Overhead & Profit 10% 3,595.35
F Harga Satuan Pekerjaan (D+E) 39,500.00

A.4.5.2.44 Pemasangan 1 m’ nok alumunium

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang Kayu L.02 OH 1.000 110,000.00 110,000.00
Kepala Tukang L.03 OH 0.100 110,000.00 11,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 136,000.00
B BAHAN
Nok standar 40 x 18 buah 1.200 - -
Paku hak Panjang 15 cm Kg 0.040 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 136,000.00


E Overhead & Profit 10% 13,600.00
F Harga Satuan Pekerjaan (D+E) 149,600.00
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 7.000 95,000.00 665,000.000
Tukang Kayu L.02 OH 21.000 110,000.00 2,310,000.000
Kepala Tukang L.03 OH 2.100 110,000.00 231,000.000
Mandor L.04 OH 0.350 110,000.00 38,500.000
JUMLAH TENAGA KERJA 3,244,500.000
B BAHAN
Balok kayu Kamper m3 1.100 12,200,000.00 13,420,000.000
Paku 10 cm Kg 1.250 18,500.00 23,125.000
Lem kayu Kg 1.000 22,000.00 22,000.000
JUMLAH HARGA BAHAN 13,465,125.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 16,709,625.00


E Overhead & Profit 10% 1,670,962.50
F Harga Satuan Pekerjaan (D+E) 18,380,500.00

A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II dan III

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 6.000 95,000.00 570,000.000
Tukang Kayu L.02 OH 18.000 110,000.00 1,980,000.000
Kepala Tukang L.03 OH 1.800 110,000.00 198,000.000
Mandor L.04 OH 0.300 110,000.00 33,000.000
JUMLAH TENAGA KERJA 2,781,000.000
B BAHAN
Balok kayu m3 1.200 3,527,000.00 4,232,400.000
Paku 10 cm Kg 1.250 18,500.00 23,125.000
Lem kayu Kg 1.000 22,000.00 22,000.000
JUMLAH HARGA BAHAN 4,277,525.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 7,058,525.00


E Overhead & Profit 10% 705,852.50
F Harga Satuan Pekerjaan (D+E) 7,764,300.00

A.4.6.1.3 Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,000.00 33,250.000
Tukang Kayu L.02 OH 1.050 110,000.00 115,500.000
Kepala Tukang L.03 OH 0.105 110,000.00 11,550.000
Mandor L.04 OH 0.018 110,000.00 1,980.000
JUMLAH TENAGA KERJA 162,280.000
B BAHAN
Papan kayu m3 0.040 2,337,500.00 93,500.000
Paku 10 cm Kg 0.050 18,500.00 925.000
JUMLAH HARGA BAHAN 94,425.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 256,705.00


E Overhead & Profit 10% 25,670.50
F Harga Satuan Pekerjaan (D+E) 282,300.00

A.4.6.1.4 Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,000.00 33,250.000
Tukang Kayu L.02 OH 1.050 110,000.00 115,500.000
Kepala Tukang L.03 OH 0.105 110,000.00 11,550.000
Mandor L.04 OH 0.018 110,000.00 1,980.000
JUMLAH TENAGA KERJA 162,280.000
B BAHAN
Papan kayu m3 0.040 2,337,500.00 93,500.000
Paku 10 cm Kg 0.050 18,500.00 925.000
JUMLAH HARGA BAHAN 94,425.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 256,705.00


E Overhead & Profit 10% 25,670.50
F Harga Satuan Pekerjaan (D+E) 282,300.00

A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 95,000.00 95,000.000
Tukang Kayu L.02 OH 3.000 110,000.00 330,000.000
Kepala Tukang L.03 OH 0.300 110,000.00 33,000.000
Mandor L.04 OH 0.050 110,000.00 5,500.000
JUMLAH TENAGA KERJA 463,500.000
B BAHAN
Papan kayu m3 0.040 19,000,000.00 760,000.000
Lem kayu Kg 0.500 22,000.00 11,000.000
JUMLAH HARGA BAHAN 771,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,234,500.00


E Overhead & Profit 10% 123,450.00
F Harga Satuan Pekerjaan (D+E) 1,357,900.00

A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela, kayu kelas I dan II

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 95,000.00 76,000.000
Tukang Kayu L.02 OH 2.400 110,000.00 264,000.000
Kepala Tukang L.03 OH 0.240 110,000.00 26,400.000
Mandor L.04 OH 0.040 110,000.00 4,400.000
JUMLAH TENAGA KERJA 370,800.000
B BAHAN
Papan kayu m3 0.024 12,000,000.00 288,000.000
Lem kayu Kg 0.300 22,000.00 6,600.000
JUMLAH HARGA BAHAN 294,600.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 665,400.00


E Overhead & Profit 10% 66,540.00
F Harga Satuan Pekerjaan (D+E) 731,900.00

A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi, kayu kelas I dan II

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 95,000.00 95,000.000
Tukang Kayu L.02 OH 3.000 110,000.00 330,000.000
Kepala Tukang L.03 OH 0.300 110,000.00 33,000.000
Mandor L.04 OH 0.050 110,000.00 5,500.000
JUMLAH TENAGA KERJA 463,500.000
B BAHAN
Papan kayu m3 0.064 3,527,000.00 225,728.000
Lem kayu Kg 0.500 22,000.00 11,000.000
JUMLAH HARGA BAHAN 236,728.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 700,228.00


E Overhead & Profit 10% 70,022.80
F Harga Satuan Pekerjaan (D+E) 770,200.00

A.4.6.1.8 Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 95,000.00 66,500.000
Tukang Kayu L.02 OH 2.100 110,000.00 231,000.000
Kepala Tukang L.03 OH 0.210 110,000.00 23,100.000
Mandor L.04 OH 0.035 110,000.00 3,850.000
JUMLAH TENAGA KERJA 324,450.000
B BAHAN
Papan kayu m3 0.025 3,527,000.00 88,175.000
Paku 1 cm – 2.5 cm kg 0.030 21,000.00 630.000
Lem kayu kg 0.500 22,000.00 11,000.000
Plywood tebal 4 mm
Lembar 1.000 64,800.00 64,800.000
Ukuran (90 x 220) cm
JUMLAH HARGA BAHAN 164,605.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 489,055.00


E Overhead & Profit 10% 48,905.50
F Harga Satuan Pekerjaan (D+E) 537,900.00

A.4.6.1.9 Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 95,000.00 76,000.000
Tukang Kayu L.02 OH 2.400 110,000.00 264,000.000
Kepala Tukang L.03 OH 0.240 110,000.00 26,400.000
Mandor L.04 OH 0.040 110,000.00 4,400.000
JUMLAH TENAGA KERJA 370,800.000
B BAHAN
Papan kayu m3 0.026 3,527,000.00 90,291.200
Paku 1 cm – 2.5 cm kg 0.030 21,000.00 630.000
Lem kayu kg 0.500 22,000.00 11,000.000
Plywood tebal 4 mm
Lembar 1.000 64,800.00 64,800.000
Ukuran (90 x 220) cm
JUMLAH HARGA BAHAN 166,721.20
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 537,521.20


E Overhead & Profit 10% 53,752.12
F Harga Satuan Pekerjaan (D+E) 591,200.00

A.4.6.1.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I dan II

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.670 95,000.00 63,650.000
Tukang Kayu L.02 OH 2.000 110,000.00 220,000.000
Kepala Tukang L.03 OH 0.200 110,000.00 22,000.000
Mandor L.04 OH 0.335 110,000.00 36,850.000
JUMLAH TENAGA KERJA 342,500.000
B BAHAN
Papan kayu m3 0.060 3,527,000.00 211,620.000
Lem kayu Kg 0.150 22,000.00 3,300.000
JUMLAH HARGA BAHAN 214,920.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 557,420.00


E Overhead & Profit 10% 55,742.00
F Harga Satuan Pekerjaan (D+E) 613,100.00

A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.800 95,000.00 76,000.000
Tukang Kayu L.02 OH 2.400 110,000.00 264,000.000
Kepala Tukang L.03 OH 0.240 110,000.00 26,400.000
Mandor L.04 OH 0.040 110,000.00 4,400.000
JUMLAH TENAGA KERJA 370,800.000
B BAHAN
Papan kayu m3 0.025 3,527,000.00 88,175.000
Paku 1 - 2,5 cm Kg 0.030 21,000.00 630.000
Lem kayu Kg 0.300 22,000.00 6,600.000
Teakwood 4 mm 90 x 220 cm Lembar 1.000 64,800.00 64,800.000
JUMLAH HARGA BAHAN 160,205.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 531,005.00


E Overhead & Profit 10% 53,100.50
F Harga Satuan Pekerjaan (D+E) 584,100.00

A.4.6.1.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.85 67000 56950
Tukang Kayu L.02 OH 2.55 90000 229500
Kepala Tukang L.03 OH 0.255 95000 24225
Mandor L.04 OH 0.043 95000 4085
JUMLAH TENAGA KERJA 314760
B BAHAN
Papan kayu m3 0.025 4042500 101062.5
Paku 1 - 2,5 cm Kg 0.03 19400 582
Lem kayu Kg 0.8 16800 13440
Teakwood 4 mm 90 x 220 cm Lembar 1 73500 73500
Formika Lembar 0.5
JUMLAH HARGA BAHAN 101644.5
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 416404.5


E Overhead & Profit 10% 41640.45
F Harga Satuan Pekerjaan (D+E) 458,000.00

A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 4 67000 268000
Tukang Kayu L.02 OH 12 90000 1080000
Kepala Tukang L.03 OH 1.2 95000 114000
Mandor L.04 OH 0.2 95000 19000
JUMLAH TENAGA KERJA 1481000
B BAHAN
Balok kayu m3 1.1 4042500 4446750
Besi strip tebal 5 mm kg 15 11200 168000
Paku 12 cm kg 5.6 14100 78960
JUMLAH HARGA BAHAN 4614750
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 6095750


E Overhead & Profit 10% 609575
F Harga Satuan Pekerjaan (D+E) 6,705,300.00

A.4.6.1.14 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 6.7 67000 448900
Tukang Kayu L.02 OH 20.1 90000 1809000
Kepala Tukang L.03 OH 2.01 95000 190950
Mandor L.04 OH 0.335 95000 31825
JUMLAH TENAGA KERJA 2480675
B BAHAN
Balok kayu m3 1.2 13860000 16632000
Besi strip tebal 5 mm kg 15 11200 168000
Paku 12 cm kg 5.6 14100 78960
JUMLAH HARGA BAHAN 16800000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 19280675


E Overhead & Profit 10% 1928067.5
F Harga Satuan Pekerjaan (D+E) 21,208,700.00

A.4.6.1.15 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 6.7 67000 448900
Tukang Kayu L.02 OH 20.1 90000 1809000
Kepala Tukang L.03 OH 2.01 95000 190950
Mandor L.04 OH 0.335 95000 31825
JUMLAH TENAGA KERJA 2480675
B BAHAN
Balok kayu m3 1.1 4042500 4446750
Besi strip tebal 5 mm kg 15 11200 168000
Paku 12 cm kg 3 14100 42300
JUMLAH HARGA BAHAN 4614750
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 7095425


E Overhead & Profit 10% 709542.5
F Harga Satuan Pekerjaan (D+E) 7,804,900.00

A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.1 67000 6700
Tukang Kayu L.02 OH 0.1 90000 9000
Kepala Tukang L.03 OH 0.01 95000 950
Mandor L.04 OH 0.005 95000 475
JUMLAH TENAGA KERJA 17125
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.014 2310000 32340
Reng 2 x 3 cm m3 0.036 3999600 143985.6
Paku 5 dan 10 cm Kg 0.25 13600 3400
JUMLAH HARGA BAHAN 179725.6
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 196850.6


E Overhead & Profit 10% 19685.06
F Harga Satuan Pekerjaan (D+E) 216,500.00

A.4.6.1.17 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.1 67000 6700
Tukang Kayu L.02 OH 0.1 90000 9000
Kepala Tukang L.03 OH 0.01 95000 950
Mandor L.04 OH 0.005 95000 475
JUMLAH TENAGA KERJA 17125
B BAHAN
Kaso-kaso 5 x 7cm m3 0.014 2310000 32340
Reng (3 x 4) cm m3 0.057 3334000 190038
Paku 5 dan 10 cm Kg 0.25 13600 3400
JUMLAH HARGA BAHAN 225778
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 242903


E Overhead & Profit 10% 24290.3
F Harga Satuan Pekerjaan (D+E) 267,100.00

A.4.6.1.18 Pemasangan 1 m2 rangka atap sirap, kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.12 67000 8040
Tukang Kayu L.02 OH 0.12 90000 10800
Kepala Tukang L.03 OH 0.012 95000 1140
Mandor L.04 OH 0.006 95000 570
JUMLAH TENAGA KERJA 20550
B BAHAN
Kayu kelas II m3 0.014 4042500 56595
Paku 5 dan 10 cm Kg 0.057 13600 775.2
JUMLAH HARGA BAHAN 57370.2
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77920.2


E Overhead & Profit 10% 7792.02
F Harga Satuan Pekerjaan (D+E) 85,700.00

A.4.6.1.19 Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.15 67000 10050
Tukang Kayu L.02 OH 0.3 90000 27000
Kepala Tukang L.03 OH 0.03 95000 2850
Mandor L.04 OH 0.075 95000 7125
JUMLAH TENAGA KERJA 47025
B BAHAN
Kaso-kaso 5 x 7cm m3 0.0154 2310000 35574
Paku 5 dan 10 cm Kg 0.2 13600 2720
JUMLAH HARGA BAHAN 38294
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 85319


E Overhead & Profit 10% 8531.9
F Harga Satuan Pekerjaan (D+E) 93,800.00

A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang Kayu L.02 OH 0.300 110,000.00 33,000.00
Kepala Tukang L.03 OH 0.030 110,000.00 3,300.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 56,400.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.016 2,000,000.00 32,600.00
Paku 5 dan 10 cm Kg 0.250 19,250.00 4,812.50
JUMLAH HARGA BAHAN 37,412.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 93,812.50


E Overhead & Profit 10% 9,381.25
F Harga Satuan Pekerjaan (D+E) 103,100.00

A.4.6.1.21 Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.1 67000 6700
Tukang Kayu L.02 OH 0.2 90000 18000
Kepala Tukang L.03 OH 0.02 95000 1900
Mandor L.04 OH 0.005 95000 475
JUMLAH TENAGA KERJA 27075
B BAHAN
Papan kayu m3 0.0108 4042500 43659
Paku 5 dan 7 cm Kg 0.1 13600 1360
JUMLAH HARGA BAHAN 45019
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 72094


E Overhead & Profit 10% 7209.4
F Harga Satuan Pekerjaan (D+E) 79,300.00

A.4.6.1.22 Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.1 67000 6700
Tukang Kayu L.02 OH 0.2 90000 18000
Kepala Tukang L.03 OH 0.02 95000 1900
Mandor L.04 OH 0.005 95000 475
JUMLAH TENAGA KERJA 27075
B BAHAN
Papan kayu m3 0.0108 4042500 43659
Paku 5 dan 7 cm Kg 0.05 13600 680
JUMLAH HARGA BAHAN 44339
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 71414


E Overhead & Profit 10% 7141.4
F Harga Satuan Pekerjaan (D+E) 78,500.00

A.4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 95,000.00 14,250.00
Tukang Kayu L.02 OH 0.450 110,000.00 49,500.00
Kepala Tukang L.03 OH 0.045 110,000.00 4,950.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 69,580.00
B BAHAN
Balok kayu m3 0.028 2,000,000.00 56,000.00
Paku 5 dan 7 cm Kg 0.150 19,250.00 2,887.50
JUMLAH HARGA BAHAN 58,887.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 128,467.50


E Overhead & Profit 10% 12,846.75
F Harga Satuan Pekerjaan (D+E) 141,300.00

A.4.6.1.25 Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.2 67000 13400
Tukang Kayu L.02 OH 0.6 90000 54000
Kepala Tukang L.03 OH 0.06 95000 5700
Mandor L.04 OH 0.01 95000 950
JUMLAH TENAGA KERJA 74050
B BAHAN
Balok kayu, 6 x 12 m3 0.028 4042500 113190
Paku 5 dan 10 kg 0.15 13600 2040
Plywood 4 mm, 120 x 240 Lembar 0.86 69300 59598
Lem kayu kg 0.56 16800 9408
JUMLAH HARGA BAHAN 184236
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 258286


E Overhead & Profit 10% 25828.6
F Harga Satuan Pekerjaan (D+E) 284,100.00

A.4.6.1.26 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.6 67000 40200
Tukang Kayu L.02 OH 1.8 90000 162000
Kepala Tukang L.03 OH 0.18 95000 17100
Mandor L.04 OH 0.03 95000 2850
JUMLAH TENAGA KERJA 222150
B BAHAN
Papan kayu m3 0.007 4042500 28297.5
Paku 5 dan 10 kg 0.1 13600 1360
Paku skrup 10 cm kg 0.15 14100 2115
JUMLAH HARGA BAHAN 31772.5
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 253922.5


E Overhead & Profit 10% 25392.25
F Harga Satuan Pekerjaan (D+E) 279,300.00

A.4.6.1.27 Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.025 67000 1675
Tukang Kayu L.02 OH 0.075 90000 6750
Kepala Tukang L.03 OH 0.008 95000 760
Mandor L.04 OH 0.001 95000 95
JUMLAH TENAGA KERJA 9280
B BAHAN
Plywood 4 mm m3 0.4 69300 27720
Paku 1 dan 2.5 kg 0.05 19400 970
JUMLAH HARGA BAHAN 28690
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37970


E Overhead & Profit 10% 3797
F Harga Satuan Pekerjaan (D+E) 41,700.00

A.4.6.1.28 Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A TENAGA
Pekerja L.01 OH 0.1 67000 6700
Tukang Kayu L.02 OH 0.05 90000 4500
Kepala Tukang L.03 OH 0.005 95000 475
Mandor L.04 OH 0.005 95000 475
JUMLAH TENAGA KERJA 12150
B BAHAN
Bilik bambu m2 1.5 0
Kaso-kaso 5 x 7 m3 0.014 0
Paku kg 0.012 0
List kayu 2/4 m3 0.003 0
JUMLAH HARGA BAHAN 0
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 12150


E Overhead & Profit 10% 1215
F Harga Satuan Pekerjaan (D+E) 13,300.00

A.4.6.1.29 Pemasangan 1 m' talang datar/jurai seng bjls

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.2 67000 13400
Tukang Kayu L.02 OH 0.4 90000 36000
Kepala Tukang L.03 OH 0.025 95000 2375
Mandor L.04 OH 0.01 95000 950
JUMLAH TENAGA KERJA 52725
B BAHAN
Seng galvanis m' 1.05 0
Paku Kg 0.015 0
Kayu Papan Kls III m3 0.019 0
JUMLAH HARGA BAHAN 0
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 52725


E Overhead & Profit 10% 5272.5
F Harga Satuan Pekerjaan (D+E) 57,900.00

A.4.6.1.30 Pemasangan 1 m2 listplank ukuran (100 x 20) cm, woodplank motif kayu

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.00
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 34,250.00
B BAHAN
Woodplank m' 1.050 20,312.50 21,328.13
Paku 1 - 2,5 cm Kg 0.100 21,000.00 2,100.00
JUMLAH HARGA BAHAN 23,428.13
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 57,678.13


E Overhead & Profit 10% 5,767.81
F Harga Satuan Pekerjaan (D+E) 63,400.00
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.1 Pemasangan 1 buah kunci tanam antik

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 95,000.00 5,700.000
Tukang Kayu L.02 OH 0.600 110,000.00 66,000.000
Kepala Tukang L.03 OH 0.060 110,000.00 6,600.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 78,630.000
B BAHAN
Kunci tanam antik Bh 1.000 483,000.00 483,000.000
JUMLAH HARGA BAHAN 483,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 561,630.00


E Overhead & Profit 10% 56,163.00
F Harga Satuan Pekerjaan (D+E) 617,700.00

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 95,000.00 950.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.005 110,000.00 550.000
JUMLAH TENAGA KERJA 62,000.000
B BAHAN
Kunci tanam biasa Bh 1.000 184,000.00 184,000.000
JUMLAH HARGA BAHAN 184,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 246,000.00


E Overhead & Profit 10% 24,600.00
F Harga Satuan Pekerjaan (D+E) 270,600.00

A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.005 95,000.00 475.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 61,305.000
B BAHAN
Kunci tanam KM Bh 1.000 95,700.00 95,700.000
JUMLAH HARGA BAHAN 95,700.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 157,005.00


E Overhead & Profit 10% 15,700.50
F Harga Satuan Pekerjaan (D+E) 172,700.00

A.4.6.2.4. Pemasangan 1 buah kunci silinder

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.005 95,000.00 475.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 61,305.000
B BAHAN
Kunci silinder Bh 1.000 126,500.00 126,500.000
JUMLAH HARGA BAHAN 126,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 187,805.00


E Overhead & Profit 10% 18,780.50
F Harga Satuan Pekerjaan (D+E) 206,500.00

A.4.6.2.5. Pemasangan 1 buah engsel pintu

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.001 110,000.00 88.000
JUMLAH TENAGA KERJA 19,663.000
B BAHAN
Engsel pintu Bh 1.000 25,875.00 25,875.000
JUMLAH HARGA BAHAN 25,875.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,538.00


E Overhead & Profit 10% 4,553.80
F Harga Satuan Pekerjaan (D+E) 50,000.00

A.4.6.2.6. Pemasangan 1 buah engsel jendela

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 95,000.00 950.000
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.000
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.000
Mandor L.04 OH 0.001 110,000.00 55.000
JUMLAH TENAGA KERJA 13,105.000
B BAHAN
Engsel jendela Bh 1.000 40,250.00 40,250.000
JUMLAH HARGA BAHAN 40,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 53,355.00


E Overhead & Profit 10% 5,335.50
F Harga Satuan Pekerjaan (D+E) 58,600.00

A.4.6.2.7. Pemasangan 1 buah engsel angin

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 55.000
JUMLAH TENAGA KERJA 33,755.000
B BAHAN
Engsel angin Bh 1.000 44,000.00 44,000.000
JUMLAH HARGA BAHAN 44,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,755.00


E Overhead & Profit 10% 7,775.50
F Harga Satuan Pekerjaan (D+E) 85,500.00

A.4.6.2.8. Pemasangan 1 buah spring knip

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 20,455.000
B BAHAN
Engsel spring knip Bh 1.000 33,000.00 33,000.000
JUMLAH HARGA BAHAN 33,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 53,455.00


E Overhead & Profit 10% 5,345.50
F Harga Satuan Pekerjaan (D+E) 58,800.00

A.4.6.2.9. Pemasangan 1 buah hak angin kait

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 20,455.000
B BAHAN
hak angin kait Bh 1.000 11,000.00 11,000.000
JUMLAH HARGA BAHAN 11,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,455.00


E Overhead & Profit 10% 3,145.50
F Harga Satuan Pekerjaan (D+E) 34,600.00

A.4.6.2.10 Pemasangan 1 buah door closer

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 95,000.00 4,750.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 65,580.000
B BAHAN
door closer Bh 1.000 753,250.00 753,250.000
JUMLAH HARGA BAHAN 753,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 818,830.00


E Overhead & Profit 10% 81,883.00
F Harga Satuan Pekerjaan (D+E) 900,700.00

A.4.6.2.11. Pemasangan 1 buah kunci slot

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.000
B BAHAN
Kunci slot Bh 1.000 28,750.00 28,750.000
JUMLAH HARGA BAHAN 28,750.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 54,960.00


E Overhead & Profit 10% 5,496.00
F Harga Satuan Pekerjaan (D+E) 60,400.00

A.4.6.2.12 Pemasangan 1 buah door holder

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 95,000.00 4,750.000
Tukang Kayu L.02 OH 0.500 110,000.00 55,000.000
Kepala Tukang L.03 OH 0.050 110,000.00 5,500.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 65,580.000
B BAHAN
door holder Bh 1.000 17,250.00 17,250.000
JUMLAH HARGA BAHAN 17,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 82,830.00


E Overhead & Profit 10% 8,283.00
F Harga Satuan Pekerjaan (D+E) 91,100.00

A.4.6.2.13 Pemasangan 1 buah door stop

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 95,000.00 950.000
Tukang Kayu L.02 OH 0.100 110,000.00 11,000.000
Kepala Tukang L.03 OH 0.010 110,000.00 1,100.000
Mandor L.04 OH 0.005 110,000.00 550.000
JUMLAH TENAGA KERJA 13,600.000
B BAHAN
door stop Bh 1.000 287,500.00 287,500.000
JUMLAH HARGA BAHAN 287,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 301,100.00


E Overhead & Profit 10% 30,110.00
F Harga Satuan Pekerjaan (D+E) 331,200.00

A.4.6.2.14 Pemasangan 1 buah rel pintu sorong

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.060 95,000.00 5,700.000
Tukang Kayu L.02 OH 0.600 110,000.00 66,000.000
Kepala Tukang L.03 OH 0.060 110,000.00 6,600.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 78,630.000
B BAHAN
rel pintu sorong Bh 1.000 483,000.00 483,000.000
JUMLAH HARGA BAHAN 483,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 561,630.00


E Overhead & Profit 10% 56,163.00
F Harga Satuan Pekerjaan (D+E) 617,700.00

A.4.6.2.15 Pemasangan 1 buah kunci lemari

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.025 95,000.00 2,375.000
Tukang Kayu L.02 OH 0.250 110,000.00 27,500.000
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.000
Mandor L.04 OH 0.001 110,000.00 143.000
JUMLAH TENAGA KERJA 32,768.000
B BAHAN
kunci lemari Bh 1.000 17,250.00 17,250.000
JUMLAH HARGA BAHAN 17,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 50,018.00


E Overhead & Profit 10% 5,001.80
F Harga Satuan Pekerjaan (D+E) 55,000.00

A.4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.001 110,000.00 88.000
JUMLAH TENAGA KERJA 19,663.000
B BAHAN
Kaca tebal 3 mm Bh 1.100 68,775.00 75,652.500
JUMLAH HARGA BAHAN 75,652.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 95,315.50


E Overhead & Profit 10% 9,531.55
F Harga Satuan Pekerjaan (D+E) 104,800.00

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.001 110,000.00 88.000
JUMLAH TENAGA KERJA 19,663.000
B BAHAN
Kaca tebal 5 mm Bh 1.100 90,000.00 99,000.000
JUMLAH HARGA BAHAN 99,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 118,663.00


E Overhead & Profit 10% 11,866.30
F Harga Satuan Pekerjaan (D+E) 130,500.00

A.4.6.2.18 Pemasangan 1 m2 kaca tebal 8 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.017 95,000.00 1,615.000
Tukang Kayu L.02 OH 0.170 110,000.00 18,700.000
Kepala Tukang L.03 OH 0.017 110,000.00 1,870.000
Mandor L.04 OH 0.001 110,000.00 99.000
JUMLAH TENAGA KERJA 22,284.000
B BAHAN
Kaca tebal 8 mm Bh 1.100 158,025.00 173,827.500
JUMLAH HARGA BAHAN 173,827.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 196,111.50


E Overhead & Profit 10% 19,611.15
F Harga Satuan Pekerjaan (D+E) 215,700.00

A.4.6.2.19 Pemasangan 1 m2 kaca tebal 12 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.025 95,000.00 2,375.000
Tukang Kayu L.02 OH 0.250 110,000.00 27,500.000
Kepala Tukang L.03 OH 0.025 110,000.00 2,750.000
Mandor L.04 OH 0.001 110,000.00 143.000
JUMLAH TENAGA KERJA 32,768.000
B BAHAN
Kaca tebal 12 mm Bh 1.100 900,000.00 990,000.000
JUMLAH HARGA BAHAN 990,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,022,768.00
E Overhead & Profit 10% 102,276.80
F Harga Satuan Pekerjaan (D+E) 1,125,000.00

A.4.6.2.20 Pemasangan 1 m2 kaca cermin tebal 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 20,455.000
B BAHAN
Kaca cermin 5 mm Bh 1.100 142,275.00 156,502.500
JUMLAH HARGA BAHAN 156,502.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 176,957.50


E Overhead & Profit 10% 17,695.75
F Harga Satuan Pekerjaan (D+E) 194,600.00

A.4.6.2.21 Pemasangan 1 m2 kaca cermin tebal 8 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 20,455.000
B BAHAN
Kaca cermin 8 mm Bh 1.100 202,125.00 222,337.500
JUMLAH HARGA BAHAN 222,337.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 242,792.50


E Overhead & Profit 10% 24,279.25
F Harga Satuan Pekerjaan (D+E) 267,000.00

A.4.6.2.22 Pemasangan 1 m2 kaca wireglassed tebal 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.015 95,000.00 1,425.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.008 110,000.00 880.000
JUMLAH TENAGA KERJA 20,455.000
B BAHAN
Kaca wireglassed 5
Bh 1.100 221,025.00 243,127.500
mm
JUMLAH HARGA BAHAN 243,127.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 263,582.50


E Overhead & Profit 10% 26,358.25
F Harga Satuan Pekerjaan (D+E) 289,900.00
A.4.6.2.23 Pemasangan 1 m2 kaca patri tebal 5 mm

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.075 95,000.00 7,125.000
Tukang Kayu L.02 OH 0.150 110,000.00 16,500.000
Kepala Tukang L.03 OH 0.015 110,000.00 1,650.000
Mandor L.04 OH 0.004 110,000.00 440.000
JUMLAH TENAGA KERJA 25,715.000
B BAHAN
Kaca patri 5mm Bh 1.100 2,200,000.00 2,420,000.000
JUMLAH HARGA BAHAN 2,420,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,445,715.00


E Overhead & Profit 10% 244,571.50
F Harga Satuan Pekerjaan (D+E) 2,690,200.00

A.4.6.2.24 Pemasangan 1 buah Casement Handle

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.000
B BAHAN
Casement Handle Bh 1.000 45,000.00 45,000.000
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 71,210.00


E Overhead & Profit 10% 7,121.00
F Harga Satuan Pekerjaan (D+E) 78,300.00

A.4.6.2.25 Pemasangan 1 buah Looc Case

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.000
B BAHAN
Looc Case Bh 1.000 55,000.00 55,000.000
JUMLAH HARGA BAHAN 55,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 81,210.00


E Overhead & Profit 10% 8,121.00
F Harga Satuan Pekerjaan (D+E) 89,300.00

A.4.6.2.26 Pemasangan 1 buah engsel pintu koboi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Engsel pintu koboi Bh 1.000 27,500.00 27,500.000
JUMLAH HARGA BAHAN 27,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 53,710.00


E Overhead & Profit 10% 5,371.00
F Harga Satuan Pekerjaan (D+E) 59,000.00

A.4.6.2.28 Pemasangan 1 buah Floor Hinges

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Floor Hinges Bh 1.000 3,245,000.00 3,245,000.000
JUMLAH HARGA BAHAN 3,245,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,271,210.00


E Overhead & Profit 10% 327,121.00
F Harga Satuan Pekerjaan (D+E) 3,598,300.00

A.4.6.2.29 Pemasangan 1 buah Over panel

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Over panel Bh 1.000 350,000.00 350,000.000
JUMLAH HARGA BAHAN 350,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 376,210.00


E Overhead & Profit 10% 37,621.00
F Harga Satuan Pekerjaan (D+E) 413,800.00

A.4.6.2.30 Pemasangan 1 buah Top patch Fitting

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Top patch Fitting Bh 1.000 1,200,000.00 1,200,000.000
JUMLAH HARGA BAHAN 1,200,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,226,210.00


E Overhead & Profit 10% 122,621.00
F Harga Satuan Pekerjaan (D+E) 1,348,800.00

A.4.6.2.31 Pemasangan 1 buah Botom patch Fitting

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Botom patch Fitting Bh 1.000 1,315,000.00 1,315,000.000
JUMLAH HARGA BAHAN 1,315,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,341,210.00


E Overhead & Profit 10% 134,121.00
F Harga Satuan Pekerjaan (D+E) 1,475,300.00

A.4.6.2.32 Pemasangan 1 buah Bottom Fatch Lock + Cylinder

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Bottom Fatch Lock + Cylinder Bh 1.000 1,350,000.00 1,350,000.000
JUMLAH HARGA BAHAN 1,350,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,376,210.00


E Overhead & Profit 10% 137,621.00
F Harga Satuan Pekerjaan (D+E) 1,513,800.00

A.4.6.2.33 Pemasangan 1 buah Full Handle

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.000
Tukang Kayu L.02 OH 0.200 110,000.00 22,000.000
Kepala Tukang L.03 OH 0.020 110,000.00 2,200.000
Mandor L.04 OH 0.001 110,000.00 110.000
JUMLAH TENAGA KERJA 26,210.00
B BAHAN
Full Handle Bh 1.000 1,250,000.00 1,250,000.000
JUMLAH HARGA BAHAN 1,250,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,276,210.00


E Overhead & Profit 10% 127,621.00
F Harga Satuan Pekerjaan (D+E) 1,403,800.00
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.10 Pengecatan 1 m2 bidang tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.00
Tukang cat L.02 OH 0.063 110,000.00 6,930.00
Kepala Tukang L.03 OH 0.006 110,000.00 693.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 9,853.00
B BAHAN
Plamir Tembok Kg 0.100 27,500.00 2,750.00
Cat dasar Kg 0.100 11,060.00 1,106.00
Cat penutup Kg 0.260 25,400.00 6,604.00
JUMLAH HARGA BAHAN 10,460.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 20,313.00


E Overhead & Profit 10% 2,031.30
F Harga Satuan Pekerjaan (D+E) 22,300.00

Dihit. N-01 Pengecatan 1 m2 bidang plafond baru (1 lapis plamuur, 1 lapis cat dasar, 1 lapis cat penutup)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 95,000.00 1,900.00
Tukang cat L.02 OH 0.063 110,000.00 6,930.00
Kepala Tukang L.03 OH 0.006 110,000.00 693.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 9,853.00
B BAHAN
Plamir Tembok Kg 0.100 27,500.00 2,750.00
Cat dasar Kg 0.100 55,300.00 5,530.00
Cat penutup Kg 0.130 90,000.00 11,700.00
JUMLAH HARGA BAHAN 19,980.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,833.00


E Overhead & Profit 10% 2,983.30
F Harga Satuan Pekerjaan (D+E) 32,800.00

A.4.7.1.24. Pengecatan 1 m2 bidang tembok lapis aquaproof (2 lapis cat penutup)

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.028 95,000.00 2,660.000
Tukang cat L.02 OH 0.042 110,000.00 4,620.000
Kepala Tukang L.03 OH 0.004 110,000.00 462.000
Mandor L.04 OH 0.003 110,000.00 330.000
JUMLAH TENAGA KERJA 8,072.00
B BAHAN
Aquaproof Kg 0.100 110,000.00 11,000.000
JUMLAH HARGA BAHAN 11,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 19,072.00


E Overhead & Profit 10% 1,907.20
F Harga Satuan Pekerjaan (D+E) 20,900.00
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.3A Pemasangan 1 buah closet jongkok Sistem Jet

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.000 95,000.00 95,000.000
Tukang batu L.02 OH 1.500 110,000.00 165,000.000
Kepala tukang L.03 OH 0.150 110,000.00 16,500.000
Mandor L.04 OH 0.050 110,000.00 5,500.000
JUMLAH TENAGA KERJA 282,000.00
B BAHAN
Closet Jongkok Lengkap Unit 1.000 3,084,000.00 3,084,000.000
Semen Portland Kg 6.000 1,200.00 7,200.000
Pasir pasang M3 0.010 190,000.00 1,900.000
Bata Merah Bakar Kelas I buah 6.000 100.00 600.000
JUMLAH HARGA BAHAN 3,093,700.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,375,700.00


E Overhead & Profit 10% 337,570.00
F Harga Satuan Pekerjaan (D+E) 3,713,200.00

A.5.1.1.5 Pemasangan 1 buah wastafel

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.200 95,000.00 114,000.00
Tukang batu L.02 OH 1.450 110,000.00 159,500.00
Kepala tukang L.03 OH 0.150 110,000.00 16,500.00
Mandor L.04 OH 0.060 110,000.00 6,600.00
JUMLAH TENAGA KERJA 296,600.00
B BAHAN
Wastafel Unit 1.000 874,700.00 874,700.00
JUMLAH HARGA BAHAN 874,700.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,171,300.00


E Overhead & Profit 10% 117,130.00
F Harga Satuan Pekerjaan (D+E) 1,288,400.00

A.5.1.1.14 Pemasangan 1 buah floor drian

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 95,000.00 950.00
Tukang batu L.02 OH 0.100 110,000.00 11,000.00
Kepala tukang L.03 OH 0.010 110,000.00 1,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 13,600.00
B BAHAN
floor drain bh 1.000 47,000.00 47,000.00
JUMLAH HARGA BAHAN 47,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 60,600.00


E Overhead & Profit 10% 6,060.00
F Harga Satuan Pekerjaan (D+E) 66,600.00
A.5.1.1.19 Pemasangan 1 buah kran diameter 1/2" atau 3/4"

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.010 95,000.00 950.000
Tukang batu L.02 OH 0.400 110,000.00 44,000.000
Kepala tukang L.03 OH 0.040 110,000.00 4,400.000
Mandor L.04 OH 0.005 110,000.00 550.000
JUMLAH TENAGA KERJA 49,900.00
B BAHAN
Kran air bh 1.000 19,000.00 19,000.000
Sealtape bh 0.025 5,500.00 137.500
JUMLAH HARGA BAHAN 19,137.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 69,037.50


E Overhead & Profit 10% 6,903.75
F Harga Satuan Pekerjaan (D+E) 75,900.00

A.5.1.1.25 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2 ”

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.036 95,000.00 3,420.000
Tukang batu L.02 OH 0.060 110,000.00 6,600.000
Kepala tukang L.03 OH 0.006 110,000.00 660.000
Mandor L.04 OH 0.002 110,000.00 220.000
JUMLAH TENAGA KERJA 10,900.00
B BAHAN
Pipa PVC 1/2" m' 1.200 6,825.00 6,825.000
Perlengkapan % 35.000 6,825.00 2,388.750
JUMLAH HARGA BAHAN 9,213.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 20,113.75


E Overhead & Profit 10% 2,011.38
F Harga Satuan Pekerjaan (D+E) 22,100.00

A.5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.036 95,000.00 3,420.00
Tukang batu L.02 OH 0.060 110,000.00 6,600.00
Kepala tukang L.03 OH 0.006 110,000.00 660.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 10,900.00
B BAHAN
Pipa PVC 3/4" m' 1.200 9,587.50 11,505.00
Perlengkapan % 35.000 11,505.00 4,026.75
JUMLAH HARGA BAHAN 15,531.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 26,431.75


E Overhead & Profit 10% 2,643.18
F Harga Satuan Pekerjaan (D+E) 29,000.00
Dihit. O-01 Pemasangan 1 m' saluran gravel

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
Galian Tanah A.2.3.1.2 M3 0.090 90,450.00 8,140.50
Urugan Pasir A.2.3.1.11 M3 0.015 137,600.00 2,064.00
Pas. Bata A.4.4.1.10 M2 0.600 69,416.00 41,649.60
Pek. Plesteran A.4.4.2.5 M2 0.180 59,460.80 10,702.94
Pek. Acian A.4.4.2.27 M2 0.180 36,100.00 6,498.00
Grefel Beton 30 Cm X 1/2 U&B M' 1.100 57,000.00 62,700.00
JUMLAH 131,755.04

D Jumlah (A+B+C) 131,755.04


E Overhead & Profit 10% 13,175.50
F Harga Satuan Pekerjaan (D+E) 144,900.00

Dihit. O-02 Pemasangan 1 unit septictank ukuran 1 x 2 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20% Harga Bahan) ls 0.200 90,600.00 18,120.00
JUMLAH TENAGA KERJA 18,120.00
B BAHAN
Pasir Urug m3 0.100 90,000.00 9,000.00
Pipa galvanis 1" m' 2.000 40,800.00 81,600.00
JUMLAH HARGA BAHAN 90,600.00
C PEKERJAAN
Galian Tanah A.2.3.1.2 m3 4.000 90,450.00 361,800.00
Lantai Kerja A.4.1.1.4 m3 0.140 743,706.35 104,118.89
Pasangan bata A.4.4.1.10 m2 10.800 69,416.00 749,692.80
Plesteran A.4.4.2.5 m2 10.800 59,460.80 642,176.64
Acian A.4.4.2.27 m2 10.800 36,100.00 389,880.00
Plat Beton Penutup
- Cor beton A.4.1.1.5 m3 0.200 892,771.90 178,554.38
- Pembesian A.4.1.1.17 kg 120.000 14,418.50 1,730,220.00
- Bekisting A.4.1.1.24 m2 2.000 306,640.00 613,280.00
Urugan kembali bekas galian (1/4 dari galian) A.2.3.1.9 m3 1.000 53,000.00 53,000.00
JUMLAH HARGA PEKERJAAN 4,822,722.71

D Jumlah (A+B+C) 4,931,442.71


E Overhead & Profit 10% 493,144.27
F Harga Satuan Pekerjaan (D+E) 5,424,500.00

Dihit. O-03 Pemasangan 1 unit resapan PVC 4" + lap. ijuk

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20% Harga Bahan) ls 0.200 211,400.00 42,280.00
JUMLAH TENAGA KERJA 42,280.00
B BAHAN
PVC 4" m' 2.000 96,250.00 192,500.00
Ijuk m2 0.900 21,000.00 18,900.00
JUMLAH HARGA BAHAN 211,400.00
C PEKERJAAN
Galian Tanah A.2.3.1.2 m3 0.020 90,450.00 1,809.00
JUMLAH HARGA PEKERJAAN 1,809.00

D Jumlah (A+B+C) 255,489.00


E Overhead & Profit 10% 25,548.90
F Harga Satuan Pekerjaan (D+E) 281,000.00
Dihit. O-04 Pemasangan 1 unit septictank ukuran 1,5 x 2,5 m

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20% ) ls 0.200 6,763,140.43 1,352,628.09
JUMLAH TENAGA KERJA 1,352,628.09
B BAHAN
Pipa galvanis 1" m' 2.000 40,800.00 81,600.00
JUMLAH HARGA BAHAN 81,600.00
C PEKERJAAN
Galian Tanah A.2.3.1.2 m3 7.500 90,450.00 678,375.00
Pasir Urug m3 0.375 90,000.00 33,750.00
Lantai Kerja A.4.1.1.4 m3 0.188 743,706.35 139,444.94
- Cor beton A.4.1.1.5 m3 0.375 892,771.90 334,789.46
Pasangan bata A.4.4.1.10 m2 14.400 69,416.00 999,590.40
Plesteran A.4.4.2.5 m2 14.400 59,460.80 856,235.52
Acian A.4.4.2.27 m2 14.400 36,100.00 519,840.00
Plat Beton Penutup
- Cor beton A.4.1.1.5 m3 0.975 892,771.90 870,452.61
- Pembesian A.4.1.1.17 kg 75.000 14,418.50 1,081,387.50
- Bekisting A.4.1.1.24 m2 3.750 306,640.00 1,149,900.00
Urugan kembali bekas galian (1/4 dari galian) A.2.3.1.9 m3 1.875 53,000.00 99,375.00
JUMLAH HARGA PEKERJAAN 6,763,140.43

D Jumlah (A+B+C) 8,197,368.52


E Overhead & Profit 10% 819,736.85
F Harga Satuan Pekerjaan (D+E) 9,017,100.00

Dihit. O-05 Pemasangan 1 unit resapan PVC 4" + batu belah + lap. Ijuk

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20%) ls 0.200 3,222,595.62 644,519.12
JUMLAH TENAGA KERJA 644,519.12
B BAHAN
PVC 4" m' 2.000 96,250.00 192,500.00
Ijuk m2 0.900 21,000.00 18,900.00
JUMLAH HARGA BAHAN 211,400.00
C PEKERJAAN
Galian Tanah A.2.3.1.2 m3 3.000 90,450.00 271,350.00
Pasangan bata A.4.4.1.10 m2 10.400 69,416.00 721,926.40
Plesteran A.4.4.2.5 m2 7.600 59,460.80 451,902.08
Acian A.4.4.2.27 m2 7.600 36,100.00 274,360.00
Plat Beton Penutup
- Cor beton A.4.1.1.5 m3 0.600 892,771.90 535,663.14
- Pembesian A.4.1.1.17 kg 20.000 14,418.50 288,370.00
- Bekisting A.4.1.1.24 m2 1.600 306,640.00 490,624.00
Batu belah m3 1.200 157,000.00 188,400.00
JUMLAH HARGA PEKERJAAN 3,222,595.62

D Jumlah (A+B+C) 4,078,514.75


E Overhead & Profit 10% 407,851.47
F Harga Satuan Pekerjaan (D+E) 4,486,300.00
Dihit. O-06 Sumur Bor + Pemipaan

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20%) ls 0.200 18,000,000.00 3,600,000.00
JUMLAH TENAGA KERJA 3,600,000.00
B BAHAN
Pompa Jet Pump 450 W-500 W bh 1.000 3,980,000.00 3,980,000.00
Mesin Pompa Air 200 W-250 W bh 1.000 823,900.00 823,900.00
Pipa PVC type AW Ø 4" m' 30.000 96,250.00 2,887,500.00
Pipa PVC type AW Ø 1" m' 60.000 11,250.00 675,000.00
JUMLAH HARGA BAHAN 8,366,400.00
C PEKERJAAN
Pek. Bor sumur m' 30.000 600,000.00 18,000,000.00
JUMLAH HARGA PEKERJAAN 18,000,000.00

D Jumlah (A+B+C) 29,966,400.00


E Overhead & Profit 10% 2,996,640.00
F Harga Satuan Pekerjaan (D+E) 32,963,000.00

Dihit. O-07 Rangka Tandon Air

Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp.)
(Rp.)
A TENAGA
Tambahan Upah Kerja (20%) ls 0.200 309,499,008.86 61,899,801.77
JUMLAH TENAGA KERJA 61,899,801.77
B BAHAN
Pipa PVC type AW Ø 1" bh 3.000 45,000.00 135,000.00
Tangki Air Plastik 1.000 lt (1m3) bh 1.000 1,762,500.00 1,762,500.00
JUMLAH HARGA BAHAN 1,897,500.00
C PEKERJAAN
- Pek. Galian tanah A.2.3.1.10 m3 2.176 58,300.00 126,860.80
- Pek. Urugan kembali A.2.3.1.5 m3 0.544 164,000.00 89,216.00
- Pek. Pilecap
- Pek. Urugan pasir bawah pondasi A.2.3.1.7 m3 0.128 5,800.00 742.40
- Cor beton A.4.1.1.18 m3 0.461 15,200.00 7,004.16
- Pembesian A.4.1.1.27 kg 117.358 104,000.00 12,205,224.35
- Bekisting A.4.1.1.6 m2 0.922 1,011,700.00 932,382.72
- Pek. Kolom Pedestal
- Cor beton A.4.1.1.18 m3 0.107 15,200.00 1,629.44
- Pembesian A.4.1.1.27 kg 21.524 104,000.00 2,238,469.08
- Bekisting A.4.1.1.8 m2 0.858 1,048,800.00 899,450.88
- Rangka Tandon Air A.4.2.1.15 kg 254.627 1,150,100.00 292,846,029.03
- Angkur Ø16 L300 bh 8.000 19,000.00 152,000.00
JUMLAH HARGA PEKERJAAN 309,499,008.86

D Jumlah (A+B+C) 373,296,310.63


E Overhead & Profit 10% 37,329,631.06
F Harga Satuan Pekerjaan (D+E) 410,625,900.00
P PEKERJAAN ELEKTRIKAL

P-01 Memasang 1 buah instalasi titik Lampu

Jumlah
Harga Satuan
No Uraian Kode Koefisien Satuan Harga
(Rp.)
(Rp.)
A TENAGA
Pembantuk tukang listrik 0.166 OH 95,000.00 15,770.00
Tukang listrik 0.166 OH 110,000.00 18,260.00
Kepala tukang Listrik 0.033 OH 110,000.00 3,630.00
Mandor 0.017 OH 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
Kabel NYM 3x2,5 mm2 8.000 m 11,350.40 90,803.20
Conduit 5/8" 8.000 m 4,200.00 33,600.00
Perlengkapan instalasi 5.000 % 124,403.20 6,220.16
JUMLAH HARGA BAHAN 130,623.36
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 170,109.36


E Overhead & Profit 10% 17,010.94
F Harga Satuan Pekerjaan (D+E) 187,100.00

P-03 Memasang 1 buah Instalasi titik Stop Kontak

Jumlah
Harga Satuan
No Uraian Kode Koefisien Satuan Harga
(Rp.)
(Rp.)
A TENAGA
Pembantuk tukang listrik 0.166 OH 95,000.00 15,770.00
Tukang listrik 0.166 OH 110,000.00 18,260.00
Kepala tukang Listrik 0.033 OH 110,000.00 3,630.00
Mandor 0.017 OH 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
Kabel NYM 3x2,5 mm2 7.000 m 11,350.40 79,452.80
Conduit 5/8" 7.000 m 4,200.00 29,400.00
Perlengkapan instalasi 5.000 % 108,852.80 5,442.64
JUMLAH HARGA BAHAN 114,295.44
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 153,781.44


E Overhead & Profit 10% 15,378.14
F Harga Satuan Pekerjaan (D+E) 169,100.00

P-11 Memasang Penangkal Petir

Jumlah
Harga Satuan
No Uraian Kode Koefisien Satuan Harga
(Rp.)
(Rp.)
A TENAGA
Pembantuk tukang listrik 0.166 OH 95,000.00 15,770.00
Tukang listrik 0.166 OH 110,000.00 18,260.00
Kepala tukang Listrik 0.033 OH 110,000.00 3,630.00
Mandor 0.017 OH 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
Pentanahan Penangkal Petir 1.000 titik 658,400.00 658,400.00
Kawat BC ( Tembaga ) 12.000 m' 10,450.00 125,400.00
Jarum Penangkal Petir 1.000 bh 148,900.00 148,900.00
Perlengkapan instalasi 5.000 % 932,700.00 46,635.00
JUMLAH HARGA BAHAN 979,335.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,018,821.00


E Overhead & Profit 10% 101,882.10
F Harga Satuan Pekerjaan (D+E) 1,120,700.00
P-12 Memasang Stop Kontak daya

NO URAIAN KODE KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A TENAGA
Pembantuk tukang listrik 0.1660 Oh 95,000.00 15,770.00
Tukang listrik 0.1660 Oh 110,000.00 18,260.00
Kepala tukang Listrik 0.0330 Oh 110,000.00 3,630.00
Mandor 0.0166 Oh 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
Stop kontak 13 A 1.0000 bh 14,000.00 14,000.00
Perlengkapan instalasi 5.0000 % 14,000.00 700.00
JUMLAH HARGA BAHAN 14,700.00
C PERALATAN

JUMLAH HARGA ALAT -


Jumlah Harga Tenaga, Bahan dan Peralatan 93,672.00
Overhead + Profit 0.0000 % -
Harga Satuan Pekerjaan 93,672.00
Dibulatkan 93,670.00

P-15 Memasang Saklar tunggal

NO URAIAN KODE KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A TENAGA
Pembantuk tukang listrik 0.1660 Oh 95,000.00 15,770.00
Tukang listrik 0.1660 Oh 110,000.00 18,260.00
Kepala tukang Listrik 0.0330 Oh 110,000.00 3,630.00
Mandor 0.0166 Oh 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
skalar tunggal 1.0000 bh 15,950.00 15,950.00
Perlengkapan instalasi 5.0000 % 15,950.00 797.50
JUMLAH HARGA BAHAN 16,747.50
C PERALATAN

JUMLAH HARGA ALAT -


Jumlah Harga Tenaga, Bahan dan Peralatan 95,719.50
Overhead + Profit 0.0000 % -
Harga Satuan Pekerjaan 95,719.50
Dibulatkan 95,710.00

P-16 Memasang Saklar ganda

NO URAIAN KODE KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A TENAGA
Pembantuk tukang listrik 0.1660 Oh 95,000.00 15,770.00
Tukang listrik 0.1660 Oh 110,000.00 18,260.00
Kepala tukang Listrik 0.0330 Oh 110,000.00 3,630.00
Mandor 0.0166 Oh 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
skalar ganda 1.0000 bh 19,250.00 19,250.00
Perlengkapan instalasi 5.0000 % 19,250.00 962.50
JUMLAH HARGA BAHAN 20,212.50
C PERALATAN

JUMLAH HARGA ALAT -


Jumlah Harga Tenaga, Bahan dan Peralatan 99,184.50
Overhead + Profit 0.0000 % -
Harga Satuan Pekerjaan 99,184.50
Dibulatkan 99,180.00
P-18 Memasang 1 M Kabel Power ( NYY 4x16 mm + NYA 10 mm )

NO URAIAN KODE KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A TENAGA
Pembantuk tukang listrik 0.1660 Oh 95,000.00 15,770.00
Tukang listrik 0.1660 Oh 110,000.00 18,260.00
Kepala tukang Listrik 0.0330 Oh 110,000.00 3,630.00
Mandor 0.0166 Oh 110,000.00 1,826.00
JUMLAH TENAGA KERJA 39,486.00
B BAHAN
NYY 4x16 mm 1.0000 m1 0.00 -
NYA 10 mm 1.0000 m1 37,500.00 37,500.00
Perlengkapan instalasi 5.0000 % 37,500.00 1,875.00
JUMLAH HARGA BAHAN 39,375.00
C PERALATAN

JUMLAH HARGA ALAT -


Jumlah Harga Tenaga, Bahan dan Peralatan 78,750.00
Overhead + Profit 0.0000 % -
Harga Satuan Pekerjaan 78,750.00
Dibulatkan 78,750.00
JENIS PEKERJAAN : KESELAMATAN DAN KESEHATAN KERJA KODE
SATUAN PEMBAYARAN : Lump Sum

PERKIRAA
HARGA SATUAN JUMLAH HARGA
No URAIAN SATUAN N
KUANTITAS (Rp) (Rp)
A. DATA DAN ASUMSI
1 Jangka Waktu Pelaksanaan Pekerjaan Bulan 5
2 Jumlah Pekerja Asumsi Orang 50

B. Keselamatan dan Kesehatan Kerja


1 Penyiapan RKK :
a Pembuatan Dokumen Rencana Keselamatan Kerja Konstruksi, Prosedur, Instruksi Kerja, Set 1 250,000.00 250,000.00
Ijin Kerja dan Formulir
b Pembuatan Kartu Identitas Pekerja (KIP) Lbr 6 5,000.00 30,000.00

2 Sosialisasi dan Promosi Dan Pelatihan :


a Pengarahan K3 (Safety briefing) : Pertemuan keselamatan (Safety Talk dan atau Org 6 100,000.00 600,000.00
Tool Box Meeting)
b Spanduk (Banner) K3 Lbr 1 50,000.00 50,000.00

3 Alat Pelindung Diri (APD) terdiri dari :


a Helm pelindung (Safety Helmet); Buah 6 30,000.00 180,000.00
b Pelindung pernafasan dan mulut (Masker) Buah 12 4,000.00 48,000.00
c Sarung Tangan (Safety gloves) Psg 6 10,000.00 60,000.00
d Sepatu keselamatan (Safety shoes) Psg 6 120,000.00 720,000.00
e Rompi keselamatan (Safety vest) Buah 6 25,000.00 150,000.00

4 Asuransi dan Perijinan


a BPJS Ketenagakerjaan dan Kesehatan Kerja Ls 1 12,760,000.00 12,760,000.00

5 Personil K3 Konstruksi
a Petugas K3 0rg 1 Tidak ada Tidak ada

6 Fasilitas dan Sarana Kesehatan


a Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban, Termo meter, Hand sanitizer, dll) Ls 1 800,000.00 800,000.00

7 Rambu-Rambu terdiri atas


a Rambu Peringatan Buah 1 200,000.00 200,000.00

8 Konsultasi dengan Ahli terkait keselamtan kontruksi : - - - -

9 Lain-lain terkait pengendalian resiko K3


a Bendera K3 Buah 1 50,000.00 50,000.00

C TOTAL BIAYA KESELAMATAN DAN KESEHATAN KERJA Rp 15,898,000.00


E JUMLAH DIBULATKAN Rp 15,898,000.00
1 I
2 1
3 2
4 3
5 4
9A
10 A.I
19 A.II
68 A.III
74 A.IV
122 A.IX
135 A.IX
86 A.V
90 A.VI
105 A.VII
108 A.VIII
148 A.X
159 A.XI
164 A.XII
168 B
201 C.
219 D
286 E
338 F
8 II
6
7
11
12
13
14
15
16
17
18
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
69
70
71
72
73
75
76
77
78
79
80
81
82
83
84
85
87
88
89
91
92
93
94
95
96
97
98
99
100
101
102
103
104
106
107
109
110
111
112
113
114
115
116
117
118
119
120
121
123
124
125
126
127
128
129
130
131
132
133
134
136
137
138
139
140
141
142
143
144
145
146
147
149
150
151
152
153
154
155
156
157
158
160
161
162
163
165
166
167
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337

You might also like